Metering Section Extention - Final
-
Upload
caare-felix -
Category
Documents
-
view
15 -
download
6
description
Transcript of Metering Section Extention - Final
Project : PROPOSED METERING SECTION OFFICE EXTENSIONLocation : Motorpool, Pasonanca, Zamboanga City
Scope of Work :
A. NON - ENGINEERING BASIC ITEMS
I. FEE'S
II. SUPERVISION
B. ENGINEERING BASIC ITEMS
I. CLEARING WORKS
II. SUPERVISION
III. MASONRY WORKS
IV. PLUMBING WORKS
V. CARPENTRY WORKS
VI. ROOFING WORKS
VII. PAINTING WORKS
VIII. ELECTRICAL WORKS
IX. DEMOBILIZATION
Cost of Project :
Qty. Unit Unit Cost Amount Total
A. NON - ENGINEERING BASIC ITEMS
I. FEE'S
Building Permit 88 sq.m. 4.80 424.37 424.37
Direct Cost 424.37
OCM 42.44
Total Cost of Item A.I. 466.80
II. SUPERVISION
1 - Engineering Assistant 54 days 524.00 28,296.00 28,296.00
Direct Cost 28,296.00
OCM 2,829.60
Total Cost of Item A.II. 31,125.60
B. ENGINEERING BASIC ITEMS
I. CLEARING WORKS
Quantity = 81.35 sq.m.
Clearing & Grubbing 81.35 sq.m. 46.00 3,742.10 3,742.10
Direct Cost 3,742.10
OCM 374.21
Total Cost of Item B.I. 4,116.31
II. REMOVAL & DEMOLITION WORKS
Quantity = 17.43 sq.m.A. Labor:
2 - Carpenters 2 days 366.00 1,464.00
1 - Laborer 2 days 317.00 634.00 2,098.00
Direct Cost 2,098.00
OCM 209.80
Total Cost of Item B.II. 2,307.80
III. MASONRY WORKS
1. Setting of CHB
Quantity = 23.07 sq.m.
402,943.16Php
Item Description
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
BILL OF MATERIALS & COST ESTIMATES
1/5Pricelist Database as of May, 2013
Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 2012)
A. Materials:100mm x 200mm x 400mm CHB (NLB) 289 pcs. 15.00 4,335.00
Portland Cement 13 bags 329.00 4,277.00
Washed Sand 1.50 cu.m. 1,220.00 1,830.00
Hacksaw Blade 2 pcs. 92.00 184.00
10mm.Ø x 6.00m Def. Reinforcing Steel Bars 15 pcs. 203.00 3,045.00
#100 Nylon Chord 1 roll 92.00 92.00
#16 G.I. Tie-wire 1 kg. 92.00 92.00 13,855.00
B. Labor:1 - Mason 3 days 366.00 1,098.00
2 - Laborers 3 days 317.00 1,902.00 3,000.00
Direct Cost 16,855.00
OCM 1,685.50
Total Cost of Item B.III.1 18,540.50
2/5Pricelist Database as of May, 2013
Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 2012)
2. Plastering Works (16mm thick on each side)
Quantity = 168.76 sq.m.
A. Materials:Portland Cement 34 bags 329.00 11,186.00
Fine Sand (for Plastering) 3 cu.m. 1,952.00 5,856.00 17,042.00
B. Labor:2 - Masons 15 days 366.00 10,980.00
2 - Laborers 15 days 317.00 9,510.00 20,490.00
Direct Cost 37,532.00
OCM 3,753.20
Total Cost of Item B.III.2 41,285.20
3. Tile Works
Quantity = 34.33 sq.m.
A. Materials:200mm x 200mm Ceramic Floor Tiles 296 pcs. 16.00 4,736.00
200mm x 200mm Ceramic Wall Tiles 992 pcs. 12.00 11,904.00
Tile Grout/Cement joint Filler (2kg./pack) 9 packs 54.00 486.00
Portland Cement 4 bags 329.00 1,316.00
Fine Sand (for Plastering) 1 cu.m. 1,952.00 1,952.00
6mm x 2.40 PVC Tile Trim 12 pcs. 49.00 588.00
100mmØ Grinding Disc 2 pcs. 123.00 246.00 21,228.00
B. Labor:1 - Mason 13 days 366.00 4,758.00
1 - Laborer 13 days 317.00 4,121.00 8,879.00
C. Equipment Rental:1 - Unit Angle Grinder 13 days 300.00 3,900.00 3,900.00
Direct Cost 34,007.00
OCM 3,400.70
Total Cost of Item B.III.3 37,407.70
IV. PLUMBING WORKS
Quantity = 1 lot
A. Materials:Sanitary Pipes & Fittings
100mm.Ø x 3.00m PVC Sanitary Pipe, S-1,000 4 pcs. 952.00 3,808.00
50mm.Ø x 3.00m PVC Sanitary Pipe, S-1,000 3 pcs. 336.00 1,008.00
100mm.Ø x 50mm.Ø PVC Sanitary Wye, S-1,000 2 pcs. 198.00 396.00
100mm.Ø x 50mm.Ø PVC Sanitary Tee, S-1,000 3 pcs. 198.00 594.00
100mm.Ø x 900 PVC Sanitary Bend, S-1,000 2 pcs. 110.00 220.00
100mm.Ø x 100mmØ PVC Sanitary Wye, S-1,000 2 pcs. 177.00 354.00
100mm.Ø x 450 PVC Sanitary Bend, S-1,000 4 pcs. 85.00 340.00
100mmØ PVC Sanitary Clean Out Adaptor & Plug, 2 pcs. 87.00 174.00
S-1,000
50mm.Ø x 900 PVC Sanitary Bend, S-1,000 6 pcs. 37.00 222.00
50mm.Ø PVC Sanitary P-Trap, S-1,000 2 pcs. 113.00 226.00
50mm.Ø x 450 PVC Sanitary Bend, S-1,000 4 pcs. 29.00 116.00
50mm.Ø x 50mm.Ø PVC Sanitary Tee, S-1,000 2 pcs. 51.00 102.00
PVC Pipe Cement Solvent, 400cc 4 cans 228.00 912.00 8,472.00
Water Supply Pipes & Fittings
12mm.Ø x 6.00m G.I. Pipe, Sch. 40 3 pcs. 2,040.00 6,120.00
12mm.Ø x 90o G.I. Bend, Sch. 40 12 pcs. 20.00 240.00
12mm.Ø x 12mm.Ø G.I. Tee, Sch. 40 6 pcs. 17.00 102.00
12mm.Ø G.I. Coupling, Sch. 40 7 pcs. 10.00 70.00
12mm.Ø Brass Faucet Hose Bibb 2 pcs. 464.00 928.00
19mm Teflon Tape 4 rolls 34.00 136.00 7,596.00
Fixtures & Others
Flush Type Water Closet w/ Complete Fittings & Accs. 2 sets 3,428.00 6,856.00
Wall Mounted Urinal w/ Complete Fittings & Accs. 2 sets 2,196.00 4,392.00
3/5Pricelist Database as of May, 2013
Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 2012)
Wall Mounted Lavatory w/ Complete Fittings & Accs. 2 sets 1,226.00 2,452.00
Ceramic Tissue Holder 2 sets 275.00 550.00
#5 Plastic Floor Drain side Centered Hinge Type 2 sets 62.00 124.00
Round Perforated cover w/ Sediment Bucket
Hacksaw Blade 1 pc. 92.00 92.00
330mm. x 435mm. Frame Mirror 2 sets 244.00 488.00 14,954.00
B. Labor:1 - Plumber 6 days 366.00 2,196.00
2 - Laborers 6 days 317.00 3,804.00 6,000.00
Direct Cost 37,022.00
OCM 3,702.20
Total Cost of Item B.IV. 40,724.20
4/5Pricelist Database as of May, 2013
Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 2012)
V. CARPENTRY WORKS
1. Ceiling Works
Quantity = 94.64 sq.m.
A. Materials:6mm thk x 1.20m x 2.40m Marine Plywood 33 shts. 510.00 16,830.00
155pcs. -2" x 2" x 10' Hard Wood 517 bd.ft. 43.00 22,231.00
2" C.W.N. 9 kgs. 73.00 657.00
4" C.W.N. 8 kgs. 72.00 576.00 40,294.00
B. Labor:2 - Carpenters 7 days 366.00 5,124.00 5,124.00
Direct Cost 45,418.00
OCM 4,541.80
Total Cost of Item B.V.1 49,959.80
2. Wall Enclosure
Quantity = 3.39 sq.m.
A. Materials:6mm thk x 1.20m x 2.40m Marine Plywood 2 shts. 510.00 1,020.00
6pcs. -2" x 2" x 10' Hard Wood 20 bd.ft. 43.00 860.00
2" C.W.N. 0.50 kg. 73.00 36.50
4" C.W.N. 0.5 kg. 72.00 36.00 1,952.50
B. Labor:
2 - Carpenters 1 day 366.00 732.00 732.00
Direct Cost 2,684.50
OCM 268.45
Total Cost of Item B.V.2 2,952.95
3. Doors
A. Materials:
0.60m x 2.10m PVC Flush Type Door w/ PVC Jambs, 2 sets 2,196.00 4,392.00 4,392.00
w/ Complete Accessories
B. Labor:2 - Carpenters 1 day 366.00 732.00
2 - Laborers 1 day 317.00 634.00 1,366.00
Direct Cost 5,758.00
OCM 575.80
Total Cost of Item B.V.3 6,333.80
4. Wooden Columns & Girder
A. Materials:3pcs. -2" x 4" x 8' Hard Wood 16 bd.ft. 43.00 688.00
6pcs. -4" x 4" x 10' Hard Wood 80 bd.ft. 43.00 3,440.00
4" C.W.N. 2 kgs. 72.00 144.00 4,272.00
B. Labor:2 - Carpenters 1 day 366.00 732.00
2 - Laborers 1 day 317.00 634.00 1,366.00
Direct Cost 5,638.00
OCM 563.80
Total Cost of Item B.V.4 6,201.80
VI. ROOFING WORKS
Quantity = 37.44 sq.m.
A. Materials:1. Roofing Sheets, Gutter, & Polycarbonate Sheet
6mm thk x 2.10m x 4.88m Polycarbonate Sheet (Blue) 2 shts. 7,320.00 14,640.00
0.40mm thk x 810mm x 3.80 Spandek 915, 13 shts. 2,374.00 30,862.00
Galvalume Coated Steel (Pacific Blue)
0.40mm thk x 3.65m Galvalume Coated Steel, 3 pcs. 2,562.00 7,686.00
5/5Pricelist Database as of May, 2013
Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 2012)
Spanish Gutter4mmØ x 38mm Teks Screw 338 pcs. 4.00 1,352.00
1/8" x 1/4" Alum. Blind Rivets 1 box 372.00 372.00
75mmØ x 90o Sanitary PVC Bend, S-1,000 6 pcs. 66.00 396.00
75mmØ x 3.00m Sanitary PVC Pipe, S-1,000 3 pcs. 720.00 2,160.00 57,468.00
2. Purlins, Rafters & Fascia Board
8pcs. -2" x 4" x 10' Hard Wood 40 bd.ft. 43.00 1,720.00
20pcs. -2" x 3" x 10' Hard Wood 100 bd.ft. 43.00 4,300.00
19mm thk x 1.20m x 2.40m Marine Plywood 3 shts. 1,545.00 4,635.00
2" C.W.N. 1 kg. 73.00 73.00
4" C.W.N. 3 kgs. 72.00 216.00 10,944.00
6/5Pricelist Database as of May, 2013
Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 2012)
B. Labor:2 - Carpenters 3 days 366.00 2,196.00
1 - Laborer 3 days 317.00 951.00 3,147.00
Direct Cost 71,559.00
OCM 7,155.90
Total Cost of Item B.VI. 78,714.90
VII. PAINTING WORKS
Quantity = 199.41 sq.m.
A. Materials:Concrete Neautralizer 3 gals. 563.00 1,689.00
Liquid Tile Primer 10 gals. 805.00 8,050.00
Liquid Tile Cast 6 gals. 529.00 3,174.00
Liquid Tile Top Coat (White Gloss) 10 gals. 960.00 9,600.00
Liquid Tile Reducer 5 gals. 450.00 2,250.00
Body Filler w/ Hardener 1 gal. 739.00 739.00
Lacquer Thinner 1 gal. 564.00 564.00
2" Paint Brush 2 pcs. 68.00 136.00
4" Paint Brush 2 pcs. 93.00 186.00
7" Baby Roller w/ tray 2 pcs. 146.00 292.00
# 150 Sand Paper 1 doz. 146.00 146.00
# 120 Sand Paper 1 doz. 146.00 146.00
Lamp Black Tinting Color 1 pint 131.00 131.00
Raw Sienna Tinting Color 1 pint 131.00 131.00
Thalo Blue Tinting Color 1 pint 131.00 131.00 27,365.00
B. Labor:2 - Painter 3 days 366.00 2,196.00
1 - Laborer 3 days 317.00 951.00 3,147.00
Direct Cost 30,512.00
OCM 3,051.20
Total Cost of Item B.VII. 33,563.20
VIII. ELECTRICAL WORKS
Quantity = 1 lot
A. Materials:60 Amperes Main Circuit Breaker, 2 Pole, 250 Volts, Panel Board
enclosed in Powder Coated Finished Panel Box 1 set 4,770.00 4,770.00
with 5 Single Phase Branches of:
2 sets - 15 Amps. Branch
3 sets - 20 Amps. Branch
8.0mm2 THW Stranded Wire 40 mtrs. 84.00 3,360.00
3.5mm2 TW Stranded Wire 100 mtrs. 31.00 3,100.00
2.0mm2 TW Stranded Wire 100 mtrs. 17.00 1,700.00
20mmØ x 3m PVC Conduit Pipe 26 pcs. 102.00 2,652.00
20mmØ x 90o PVC Long Sweep Elbow 5 pcs. 14.00 70.00
20mmØ PVC Male Adaptor 5 pcs. 6.00 30.00
20mmØ PVC Coupling 13 pcs. 6.00 78.00
20mmØ PVC Locknut 5 pcs. 5.00 25.00
2-40 Watts Fluorescent luminaire, Industrial Type 2 pcs. 1,270.00 2,540.00
1-40 Watts Fluorescent luminaire, Industrial Type 1 pc. 910.00 910.00
18 Watts 3U CFL with Capsule 7 pcs. 150.00 1,050.00
42" Ceiling Fan, Industrial Type 1 pc. 975.00 975.00
Switch 1-Gang w/ plate (flush type), w/ Led Set, 10A, 250V 3 pcs. 130.00 390.00
Switch 3-Gang w/ plate (flush type), w/ Led Set, 10A, 250V 3 pcs. 272.00 816.00
Ceiling Socket with screw 3 pcs. 50.00 150.00
Duplex Convenience Outlet w/ plate (flush type) 9 pcs. 100.00 900.00
2" x 4" x 2" PVC Utility Box ( H.D.) 15 pcs. 22.00 330.00
4" x 4" PVC Junction Box ( H.D.) w/ Cover 16 pcs. 26.00 416.00
#16 G.I. Tie Wire 3 kgs. 75.00 225.00
PVC Solvent Cement 1 qrt. 370.00 370.00
1/4" Camridge / Mica Tube 2 mtrs. 11.00 22.00
0.8mm x 19mm x 8m Polytype Electrical Tape 5 pcs. 25.00 125.00
0.8mm x 19mm x 8m Rubber Tape 2 pcs. 100.00 200.00 25,204.00
7/5Pricelist Database as of May, 2013
Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 2012)
B. Labor:2 - Skilled Worker 7 days 366.00 5,124.00
2 - Laborers 7 days 317.00 4,438.00 9,562.00
Direct Cost 34,766.00
OCM 3,476.60
Total Cost of Item B.VIII. 38,242.60
IX. DEMOBILIZATION 1 lot 10,000.00 10,000.00 10,000.00
Direct Cost 10,000.00
OCM 1,000.00
Total Cost of Item B.IX. 11,000.00
8/5Pricelist Database as of May, 2013
Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 2012)
A. NON - ENGINEERING BASIC ITEMS
I. FEE'S
II. SUPERVISION
B. ENGINEERING BASIC ITEMS
I. CLEARING WORKS
II. REMOVAL & DEMOLITION WORKS
III. MASONRY WORKS
IV. PLUMBING WORKS
V. CARPENTRY WORKS
VI. ROOFING WORKS
VII. PAINTING WORKS
VIII. ELECTRICAL WORKS
IX. DEMOBILIZATION
TOTAL PROJECT COST
Prepared by: Reviewed & Checked by: Approved by:
FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO EFREN C. SALVACION
Researcher/Analyst A, (J.O.) Principal Engineer C Division Manager C
Planning & Development Section Planning & Development Section Planning & Design Division
ARIANN D. GODINEZ
Senior Engineer A, EE (J.O.)
Planning & Development Section
Recommending Project Implementation: Approved for Project Implementation:
ARNULFO A. ALFONSO LEONARDO REY D. VASQUEZ
Department Manager C General Manager
Maintenance Department
65,448.35Php
78,714.90Php
33,563.20Php
38,242.60Php
97,233.40Php
40,724.20Php
402,943.16Php
11,000.00Php
S U M M A R Y
466.80Php
31,125.60Php
4,116.31Php
2,307.80Php
9/5Pricelist Database as of May, 2013
Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 2012)
PROJECT : PROPOSED METERING SECTION OFFICE EXTENSIONLocation :
Project Cost :
Project Duration : FIFTY-FOUR (54) CALENDAR DAYS
Manpower Requirements : 12 MANPOWER (1- Engineering Assistant, 2- Carpenters, 1- Plumber, 1- Electrician, 2- Masons, 1- Painter, & 4- Laborers)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
A. NON-ENGINEERING BASIC ITEMS
I. FEE'S 0.12%
II. SUPERVISION 7.72% # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #
B. ENGINEERING BASIC ITEMS
I. CLEARING WORKS 1.02%
II. REMOVAL & DEMOLITION WORKS 0.57%
III. MASONRY WORKS
1. SETTING OF CHB 4.60%
2. PLASTERING WORKS 10.25% # # # # # # # # # # # # # # #
3. TILE WORKS 9.28%
IV. PLUMBING WORKS 10.11%
V. CARPENTRY WORKS
1. CEILING WORKS 12.40%
2. WALL ENCLOSURE 0.73% #
3. DOORS 1.57% #
4. WOODEN COLUMNS & GIRDER 1.54% #
VI. ROOFING WORKS 19.53% # # #
VII. PAINTING WORKS 8.33% # # #
VIII. ELECTRICAL WORKS 9.49% # # # # # # #
IX. DEMOBILIZATION 2.73%
TOTAL PROJECT COST 100%
CASH OUTLAY REQUIREMENT 0%
TARGETED COMPLETION THIS PERIOD 0.00% 0%
COMMULATIVE COMPLETION TO DATE 26%
Prepared by: Reviewed & Checked by: Approved by: Recommending Project Implementation: Approved for Project Implementation:
FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO EFREN C. SALVACION ARNULFO A. ALFONSO LEONARDO REY D. VASQUEZ
Researcher/Analyst A, (J.O.) Principal Engineer C Division Manager C Department Manager C General Manager
Planning & Development Section Planning & Development Section Planning & Design Division Maintenance Department
6,333.80Php
6,201.80Php
78,714.90Php
33,563.20Php
38,242.60Php
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICTPilar St., Zamboanga City
C A L E N D A R D A Y S
Php102,774.82
25.51%
Php300,168.34
41,285.20Php
37,407.70Php
25.51%
11,000.00Php
402,943.16Php
74.49%
40,724.20Php
49,959.80Php
2,952.95Php
4,116.31Php
2,307.80Php
18,540.50Php
466.80Php
31,125.60Php
100.00%
GANTT CHART
Php402,943.16
Work Item Amounts % Perfected
PROJECT : PROPOSED METERING SECTION OFFICE EXTENSION
Location : Motorpool, Pasonanca, Zamboanga City
Project Cost :
Project Duration : FIFTY-FOUR (54) CALENDAR DAYS
Manpower Requirements : 12 MANPOWER (1- Engineering Assistant, 2- Carpenters, 1- Plumber, 1- Electrician, 2- Masons, 1- Painter, & 4- Laborers)
1 DAY 3 DAYS 4 DAYS 1 DAY 1 DAY
3 DAYS
2 DAYS 1 DAY 2 DAYS 3 DAYS 15 DAYS 3 DAYS 13 DAYS 3 DAYS 2 DAYS
2 DAYS
c f&c r
A - Securing Permit
B - Partial Clearing Works 7 DAYS 3 DAYS 2 DAYS
C - Removal & Demolition Works
D - Setting of 4" CHB
E - Plastering Works A. NON-ENGINEERING BASIC ITEMS
F - Tile Works I. FEE'S
G - Installation of Sanitary and Water Supply Pipes 3 II. SUPERVISION
H - Installation of Plumbing Fixtures B. ENGINEERING BASIC ITEMS
I - Ceiling works at Laboratory/ Meter Repair/ Calibration Area 3 I. CLEARING WORKS
J - Wall Enclosure 1 II. REMOVAL & DEMOLITION WORKS
K - Final Clearing Works III. MASONRY WORKS
L - Installation of Doors 1 1. SETTING OF CHB
M - Installation/ Erection of Wooden Columns & Girder 1 2. PLASTERING WORKS
N - Installation of Roofing Sheets, Gutter, Polycarbonate Sheet, 3 3. TILE WORKS
Purlins, Rafters, & Fascia Board IV. PLUMBING WORKS
O - Ceiling works at Prop. Meter Repair/ Calibration Area V. CARPENTRY WORKS
P - Painting Works 1. CEILING WORKS
Q - Electrical Works 2. WALL ENCLOSURE
R - Demobilization 2 3. DOORS
0 4. WOODEN COLUMNS & GIRDER
0 VI. ROOFING WORKS
0 VII. PAINTING WORKS
0 VIII. ELECTRICAL WORKS
C R I T I C A L P A T H : 0 IX. DEMOBILIZATION
0
1. A-B-C-D-E-G-F-I-Q-P-R DAYS
2. A-B-C-D-E-G-F-H-M-N-O-J-L-R DAYS 0
0
0
Prepared by: Checked and Reviewed by: Approved by: Recommending Approval for Project Implementation: Approved for Project Implemention:
4 3 7
FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO EFREN C. SALVACION ARNULFO A. ALFONSO LEONARDO REY D. VASQUEZ
Researcher/ Analyst A (J.O.) Principal Engineer C Division Manager C Department Manager C General Manager
N
ACTIVITIES
B, K
2
54
3 M, K
3
7
Q
I
4
G, H
1
LENGTH PROJECT DURATION
54
SCOPE OF WORKS ACTIVITY UNDER
A
1 J
L, P
C
D
E
F
E
3 F
H
3
2
F
I
1 O
C
J
L
15 D
13 G
I, O
3
Q
2
1 A
M
N
2 B
3
R
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar St., Zamboanga City
PERT CPM
402,943.16PhP
ACTIVITY COMPLETED DURATION (DAYS) PRECEDENCE
P
ST
AR
T
A B C D E G F
H
I
M
K
N O J L
Q P R
EN
D
Planning and Development Section Planning and Development Section Planning and Design Division Maintenance Department