Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers

Transcript of Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1...

Page 1: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Melissa HollisEngineering Systems Support

State Specifications and Estimates OfficeMay 2011

1

Basis of Estimatesfor Designers, Estimators, and Reviewers

Page 2: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates

Welcome to the Basis of Estimates training. This presentation is designed in three parts:

Part 1 introduces users to the Basis of Estimates, including how to navigate the online manual.

Part 2 helps Designers select the appropriate item(s) for the work required.

Part 3 assists with reviews by FDOT and Consultants, highlighting recent changes, common errors, and related issues.

2

Part 1: Introduction to the Basis of Estimates

Part 2: Selecting Pay Items

Part 3: Estimating and Review

Page 3: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates

If you need additional information on a pay item or project specific conditions, please contact your District Estimates Office, or the Basis of Estimates Coordinator.

Contact information is available on the Specifications and Estimates Office web page at:

http://www.dot.state.fl.us/ specificationsoffice/

This training is under development. Suggestions for future enhancement are welcome. Please contact [email protected]

3

Part 1: Introduction to the Basis of Estimates

Part 2: Selecting Pay Items

Part 3: Estimating and Review

Page 4: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates

The general Information section includes a brief overview of the various estimating systems.

The BOE Online section shows how to access and use the BOE files.

The first 10 Chapters of the BOE provide additional details that are applicable to all items.

Note: Chapters 11-20 are pay item specific. They are detailed in Part 2 of the Basis of Estimates training.

4

Part 1: Introduction to the Basis of Estimates

General InformationBOE OnlineChapters

Chapter 1: Updates & RegistrationChapter 2: Units of MeasureChapter 5: Contact ListsChapter 6: Pay Item RequestsChapter 7: Plan NotesChapter 8: FormsChapter 9: Trnsport & WebgateChapter 10: Formatting Items

I

Page 5: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Within the General Information section, we will review Terminology and Timelines that are important throughout the Design Process.

Within our Department, we tend to use acronyms or abbreviations for commonly used terminology. Here are a few of the terms used throughout this presentation.

5

General InformationTerminology

DOT or FDOT: Florida Department of TransportationBOE: Basis of EstimatesSpecs: Specifications, including the Standard Specifications (bound book), Supplemental Specifications (FHWA approved), Special Provisions, Developmental Specifications, and Technical Special ProvisionsEstimates: Pay Item, Quantity, Price

I

Page 6: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

DOT or FDOT: The Florida Department of Transportation.

6

General InformationTerminology

DOT or FDOT: Florida Department of TransportationBOE: Basis of EstimatesSpecs: Specifications, including the Standard Specifications (bound book), Supplemental Specifications (FHWA approved), Special Provisions, Developmental Specifications, and Technical Special ProvisionsEstimates: Pay Item, Quantity, Price

I

Page 7: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

BOE: Basis of Estimates

An online document which provides guidance on the use of pay items for use on Construction and Maintenance contracts.

Note that this manual is NOT a contract document. All measurement and payment information must be included in the contract package.

7

General InformationTerminology

DOT or FDOT: Florida Department of TransportationBOE: Basis of EstimatesSpecs: Specifications, including the Standard Specifications (bound book), Supplemental Specifications (FHWA approved), Special Provisions, Developmental Specifications, and Technical Special ProvisionsEstimates: Pay Item, Quantity, Price

I

Page 8: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Specs: Specifications, including the Standard Specifications (bound book), Supplemental Specifications (FHWA approved), Special Provisions, Developmental Specifications, and Technical Special Provisions

Complete specifications normally include:

description

material requirements

construction or installation requirements

method of measurement

basis of payment

8

General InformationTerminology

DOT or FDOT: Florida Department of TransportationBOE: Basis of EstimatesSpecs: Specifications, including the Standard Specifications (bound book), Supplemental Specifications (FHWA approved), Special Provisions, Developmental Specifications, and Technical Special ProvisionsEstimates: Pay Item, Quantity, Price

I

Page 9: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

While the plan details often include a visual “description” of the work to be completed, the specifications are normally used to complete the materials, construction, and compensation details.

Note: Plan details should never be used to repeat, modify, or “override” specifications.

Conflicts between plans and specifications should be avoided. (More details in Chapter 6.)

9

General InformationTerminology

DOT or FDOT: Florida Department of TransportationBOE: Basis of EstimatesSpecs: Specifications, including the Standard Specifications (bound book), Supplemental Specifications (FHWA approved), Special Provisions, Developmental Specifications, and Technical Special ProvisionsEstimates: Pay Item, Quantity, Price

I

Page 10: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Estimates part of the contract package includes pay items, quantities, and prices.

The pay items are selected to correspond with the specifications. Pay Item selection information is available in Part 2.

Quantities are estimated according to the plans and specifications.

10

General InformationTerminology

DOT or FDOT: Florida Department of TransportationBOE: Basis of EstimatesSpecs: Specifications, including the Standard Specifications (bound book), Supplemental Specifications (FHWA approved), Special Provisions, Developmental Specifications, and Technical Special ProvisionsEstimates: Pay Item, Quantity, Price

I

Page 11: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Quantities may be tabulated the plans, or calculated in the computation book (COMP book). More on forms and documentation in Chapter 8.

Note that most prices are based on “furnish and install” operations, as indicated in the contract documents (plans and/or specs).

11

General InformationTerminology

DOT or FDOT: Florida Department of TransportationBOE: Basis of EstimatesSpecs: Specifications, including the Standard Specifications (bound book), Supplemental Specifications (FHWA approved), Special Provisions, Developmental Specifications, and Technical Special ProvisionsEstimates: Pay Item, Quantity, Price

I

Page 12: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Together, the Plans, Specifications, and Estimates create the PSE package.

12

General InformationTerminology

PSE PackageProposalBidderContract

ProjectCategory / Design Group

Roadway, Structures, Signing & Pavement Markings, Lighting, Signals, Landscaping, Utilities, Architectural, Mass Transit

I

Page 13: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The completed PSE package, also known as the proposal, is used by various bidders. The successful bidder is awarded the contract and becomes the Contractor.

Proposals are identified by a 5 digit alpha/numeric value such as T12345, where the T indicates a Tallahassee let proposal. Other letters would indicate a District Let proposal. The number following the letter indicates the primary district.

13

General InformationTerminology

PSE PackageProposalBidderContract / Contractor

ProjectCategory / Design Group

Roadway, Structures, Signing & Pavement Markings, Lighting, Signals, Landscaping, Utilities, Architectural, Mass Transit

I

Page 14: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Within a proposal (or later, the contract), one or more projects are included.

Projects are identified by a 11 digit number, normally in the following format:

123456-1-52-01

This may also be known as the Financial Management (FM) number.

14

General InformationTerminology

PSE PackageProposalBidderContract

ProjectCategory / Design Group

Roadway, Structures, Signing & Pavement Markings, Lighting, Signals, Landscaping, Utilities, Architectural, Mass Transit

I

Page 15: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Within a project, work is divided into various categories or design groups. Each category normally has a corresponding component set of plans.

Note: Each bridge is entered as a separate category, but the plans may be developed together, especially for parallel bridges. A separate category is required for each bridge, to capture the length and width, as well as the corresponding items, quantities, and costs for the bridge.

15

General InformationTerminology

PSE PackageProposalBidderContract

ProjectCategory / Design Group

Roadway, Structures, Signing & Pavement Markings, Lighting, Signals, Landscaping, Utilities, Architectural, Mass Transit

I

Page 16: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Note: Exceptions exist for incidental landscaping that may be included on Roadway plans; refer to the Plans Preparation Manual (PPM) for details.

Items for each category should correspond to the work shown in the component plans. For example, lighting items loaded in the lighting category should correspond with the work shown in the lighting plans.

16

General InformationTerminology

PSE PackageProposalBidderContract

ProjectCategory / Design Group

Roadway, Structures, Signing & Pavement Markings, Lighting, Signals, Landscaping, Utilities, Architectural, Mass Transit

I

Page 17: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Continuing with System terminology…

LRE is the Long Range Estimates System. This system produces a budget cost estimate before plans/quantities are available.

Expected items and quantities are determined from the typical section(s) and length. Items, quantities, and prices are updated as the scope is refined and updated.

Prices are based on the previous 12 months’ historical bid prices, and/or updated based on project conditions.

17

General InformationTerminology

LRE: Long Range EstimatesTrnsportPES, CES, LAS, SiteManager, DSSWebgate, Designer InterfaceWebTrnsport

PPM: Plans Preparation ManualCPAM: Construction Project Administration ManualStandards: Design Standards, Interim Standards, Indexes

I

Page 18: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Trnsport is a suite of programs designed to meet the needs of state transportation departments.

Trnsport is an AASHTO product. (pronounced “ash-toe”)

AASHTO = American Association of State Highway Transportation Officials.

18

General InformationTerminology

LRE: Long Range EstimatesTrnsportPES, CES, LAS, SiteManager, DSSWebgate, Designer InterfaceWebTrnsport

PPM: Plans Preparation ManualCPAM: Construction Project Administration ManualStandards: Design Standards, Interim Standards, Indexes

I

Page 19: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Within the Trnsport suite, separate programs are used by Designers, Estimators, Contracts Administration, and Construction. The modules include:

PES: Proposal and Estimating System

Items and quantities are loaded into PES. (Consultant Designers use the Designer Interface to complete this task.)

19

General InformationTerminology

LRE: Long Range EstimatesTrnsportPES, CES, LAS, SiteManager, DSSWebgate, Designer InterfaceWebTrnsport

PPM: Plans Preparation ManualCPAM: Construction Project Administration ManualStandards: Design Standards, Interim Standards, Indexes

I

Page 20: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

CES: Cost Estimating System

FDOT Estimators use CES to compare item history for similar quantities and similar project types.

Item prices normally include materials, labor, and equipment costs.

The unit price for small quantities is generally higher than the unit price for a large quantity, due to equipment set-up and related labor costs.

20

General InformationTerminology

LRE: Long Range EstimatesTrnsportPES, CES, LAS, SiteManager, DSSWebgate, Designer InterfaceWebTrnsport

PPM: Plans Preparation ManualCPAM: Construction Project Administration ManualStandards: Design Standards, Interim Standards, Indexes

I

Page 21: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

LAS: Letting and Award System

The Contracts Administration Office uses LAS to distribute bid packages to potential bidders. Once bids are received, the successful bid is awarded.

(Details on the letting and award process are included in the Specifications, Section 3.)

21

General InformationTerminology

LRE: Long Range EstimatesTrnsportPES, CES, LAS, SiteManager, DSSWebgate, Designer InterfaceWebTrnsport

PPM: Plans Preparation ManualCPAM: Construction Project Administration ManualStandards: Design Standards, Interim Standards, Indexes

I

Page 22: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

After award, Proposal information, including items, quantities, and awarded bid prices are transferred to SiteManager.

SiteManager is the database used to track daily construction activities. Monthly payments are made to the contractor, based on the progress of the construction activities.

Historical bid information is stored in DSS: Decision Support System

22

General InformationTerminology

LRE: Long Range EstimatesTrnsportPES, CES, LAS, SiteManager, DSSWebgate, Designer InterfaceWebTrnsport

PPM: Plans Preparation ManualCPAM: Construction Project Administration ManualStandards: Design Standards, Interim Standards, Indexes

I

Page 23: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Webgate and the Designer Interface were designed by DOT staff to simplify access to various Trnsport modules and databases.

Webgate includes various reports:

Project Edit Report

Proposal Summary

Master Pay Item List

Item Average Unit Cost

We’ll demonstrate these reports at the end of the presentation.

23

General InformationTerminology

LRE: Long Range EstimatesTrnsportPES, CES, LAS, SiteManager, DSSWebgate, Designer InterfaceWebTrnsport

PPM: Plans Preparation ManualCPAM: Construction Project Administration ManualStandards: Design Standards, Interim Standards, Indexes

I

Page 24: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

WebTrnsport is the next generation Trnsport product.

We have recently received a test version. An implementation schedule will be determined as more details are available.

24

General InformationTerminology

LRE: Long Range EstimatesTrnsportPES, CES, LAS, SiteManager, DSSWebgate, Designer InterfaceWebTrnsport

PPM: Plans Preparation ManualCPAM: Construction Project Administration ManualStandards: Design Standards, Interim Standards, Indexes

I

Page 25: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Plans Preparation Manual is maintained by the State Roadway Design Office. It includes guidance on when specific items of work should or shouldn’t be included on a project.

This manual is directed towards designers working on FDOT projects.

While the PPM is a part of the Design firm’s contract with the Department, it is not a contract document between the construction contractor and the Department.

25

General InformationTerminology

LRE: Long Range EstimatesTrnsportPES, CES, LAS, SiteManager, DSSWebgate, Designer InterfaceWebTrnsport

PPM: Plans Preparation ManualCPAM: Construction Project Administration ManualStandards: Design Standards, Interim Standards, Indexes

I

Page 26: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Construction Project Administration Manual is maintained by the State Construction Office.

This manual is directed towards FDOT Engineers and other representatives, acting on behalf of the Department.

26

General InformationTerminology

LRE: Long Range EstimatesTrnsportPES, CES, LAS, SiteManager, DSSWebgate, Designer InterfaceWebTrnsport

PPM: Plans Preparation ManualCPAM: Construction Project Administration ManualStandards: Design Standards, Interim Standards, Indexes

I

Page 27: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Standards are also known as the Design Standards, Interim Standards, or Indexes.

The standards become a part of the contract documents, by reference in the plans or specifications.

They are used by both designers and contractors.

The standards, including any interims or updates, are available on the Roadway Design web pages. Be sure to use the Instructions for Design Standards (IDS), when available; they will provide pay item guidance.

27

General InformationTerminology

LRE: Long Range EstimatesTrnsportPES, CES, LAS, SiteManager, DSSWebgate, Designer InterfaceWebTrnsport

PPM: Plans Preparation ManualCPAM: Construction Project Administration ManualStandards: Design Standards, Interim Standards, Indexes, Instructions for Design Standardshttp://www.dot.state.fl.us/rddesign/ DesignStandards/Standards.shtm

I

Page 28: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

With a typical project, there are several common stages of development.

In the Pre-Design stage, the project scope is loosely defined. Project limits and type of work are identified.

Using LRE, a Scope Estimate is produced. The project and scope estimate are entered into the 5 year work program- a system to schedule proposed work with expected funding.

28

General InformationTimeline

Pre-DesignDesignLetting & Bid ReviewAwardConstruction

I

Page 29: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Following the selection of a designer, the initial design and creation of plans begins.

Reviews are conducted at various phases, throughout the development of the PSE package.

During phase 1, basic plan and profile information is created.

Complete requirements for each phase are shown in the PPM.

29

General InformationTimeline

Pre-DesignDesignLetting & Bid ReviewAwardConstruction

I

Page 30: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

During phase II, additional details are defined- lighting, landscape, etc. Pay Items are identified at this time.

During phase III, most of the design work is completed. Quantities for all pay items are loaded into the Trnsport system. Specifications are under review, as needed.

Note: The LRE continues to be the primary source for project costs, until items, quantities, and prices are complete in Trnsport. It is important to maintain the LRE scope and details.

30

General InformationTimeline

Pre-DesignDesignLetting & Bid ReviewAwardConstruction

I

Page 31: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Sometime between phases III and IV, when the items and quantities are finalized, the LRE is archived, and the Trnsport estimate is used.

Where LRE contains expected values based on typical section and length, Trnsport contains known values based on calculation of quantities shown in the plans.

Hint: If the LRE is maintained with scope changes, we are able to give you an earlier “heads up” when pay item changes are expected.

31

General InformationTimeline

Pre-DesignDesignLetting & Bid ReviewAwardConstruction

I

Page 32: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

During Phase IV, designers should be resolving any comments from the phase III reviews, as well as updating the traffic control plans. Specifications and estimates are completed.

With the phase IV submittal, the PSE package should be complete- ready for the letting process.

32

General InformationTimeline

Pre-DesignDesignLetting & Bid ReviewAwardConstruction

I

Page 33: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

During Phase IV, designers should be resolving any comments from the phase III reviews, as well as updating the traffic control plans. Specifications and estimates are completed.

With the phase IV submittal, the PSE package should be complete- ready for the letting process.

ALL design work should be COMPLETE before the PHASE IV “Final Plans” submittal.

33

General InformationTimeline

Pre-DesignDesignLetting & Bid ReviewAwardConstruction

I

Page 34: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Within the Letting and Bid Review process, the project(s) is/are attached to a proposal number, authorized for funding, and advertized to potential bidders.

After the letting (when bids are received), the bids are reviewed and awarded.

Details of the letting and award process are included in the specifications.

Upon award, the proposal is transferred to SiteManager, for use by Construction.

34

General InformationTimeline

Pre-DesignDesignLetting & Bid ReviewAwardConstruction

I

Page 35: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Timeline review:

Just as with plans, there are early estimates (LRE), phase estimates (including the annual Work Program reviews), authorization estimate, and the final bid package or “official” estimate.

The authorization estimate can be considered a good “ball park” estimate for authorization and advertisement. The more refined official estimate is used for review and award purposes.

35

General InformationTimeline

Pre-DesignDesignLetting & Bid ReviewAwardConstruction

I

Page 36: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Once the contract is awarded, the construction activities begin.

Note that the terms “Monthly Estimate” and “Final Estimate” are used by the Construction Office, for monthly and final payment of the construction operations.

36

General InformationTimeline

Pre-DesignDesignLetting & Bid ReviewAwardConstruction

I

Page 37: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates

This completes the General Information section of Part 1.

Continuing on with the online BOE…

37

Part 1: Introduction to the Basis of Estimates

General InformationBOE OnlineChapters

Chapter 1: Updates & RegistrationChapter 2: Units of MeasureChapter 5: Contact ListsChapter 6: Pay Item RequestsChapter 7: Plan NotesChapter 8: FormsChapter 9: Trnsport & WebgateChapter 10: Formatting Items

I

Page 38: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

All BOE online files are provided in .pdf format, searchable with Acrobat Reader® or other similar programs. The reader is available from Adobe® at www.adobe.com

The files are located on the FDOT Specifications and Estimates web page. Select the BOE link from the top ribbon, or use the Basis of Estimates link within the blue bar on the left side of the page.

38

BOE Onlinesearchable .pdf filesReader is available from http://www.adobe.com

Files are located on the Specifications and Estimates web page at http://www.dot.state.fl.us/ specificationsoffice/

Basis of Estimates

I

Page 39: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Note that this manual is NOT a contract document. All measurement and payment information must be included in the contract package.

39

BOE OnlineNOT a contract documentRefer to Chapter 10 for coordinating BOE content with the plans and specifications

I

Page 40: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Do not print the entire BOE.

The BOE files add up to more than 500 pages, and many change on a monthly basis.

Print only the pages or groups you need- signals, lighting, etc.

40

BOE OnlineComplete file is large!

I

Page 41: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Chapter 1 provides update and registration information, as well as critical dates for proposed changes.

The Monthly Updates generally involve minor detail changes or clarifications. The list of valid “open” Pay Items is also updated monthly.

41

Chapter 1Updated MonthlyEstimates BulletinsRegistration through Contact Database http://www.dot.state.fl.us/ projectmanagementoffice/ contactdatabase.shtm

I

Page 42: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Major changes, such as new/replacement pay items, are normally included in an Estimates Bulletin.

Bulletins will detail history, usage conditions, and implementation dates.

When possible, major changes are scheduled for January or July letting implementation. Applicable specifications and/or standards are coordinated for implementation with the same letting date.

42

Chapter 1Updated MonthlyEstimates BulletinsRegistration through Contact Database http://www.dot.state.fl.us/ projectmanagementoffice/ contactdatabase.shtm

I

Page 43: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Contact Database is supported by the Production Support Office, previously known as the Project Management Office. It is used to contact customers of FDOT Design and Construction Offices, when major announcements are needed.

BOE, PPM, CPAM, and other design manual/handbook users are encouraged to register for these announcements.

BOE announcements are normally sent 2-5 times annually. (It is not used for frequent “junk mail”.)

43

Chapter 1Updated MonthlyEstimates BulletinsRegistration through Contact Database http://www.dot.state.fl.us/ projectmanagementoffice/ contactdatabase.shtm

I

Page 44: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Chapter 2 includes a list of abbreviation used by FDOT, within our estimating systems.

Common conversion factors are provided for general reference.

44

Chapter 2: Units of MeasureAbbreviationsConversion Factors

I

Page 45: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Chapter 3 has been requested by several users, although many prefer to use the .pdf text search.

Chapter 4 is currently blank.

45

Chapter 3: Alphabetical ListChapter 4: Blank for future use

I

Page 46: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Chapter 5 includes several contact lists.

For most of your pay item needs, the Project Manger, District Estimates (or Final Plans) Office should be your primary contact.

If you are considering a new product, method, or non-standard design, the pay item coordinators are available to help with specs, standards, and pay items.

When technical expertise is needed, the responsible offices are contacted.

46

Chapter 5: Contact ListsDirectory of Coordinators

Central Office Pay Item coordinatorsResponsible Offices

Listing, by pay item range, of the responsible office and contact person(s)

I

Page 47: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

While the District Coordinators and technical experts are quite helpful, Designers are asked to please follow district processes by working through Project Managers and/or District coordinators, before contacting the responsible office representatives, especially for project specific issues.

47

Chapter 5: Contact ListsProject Specific Issues

Designer coordinates with Project Manager.Project Manger works with District or Responsible Office, as needed

E-mail, with Designer and Project Manager’s contact information, works well to expedite responses. Carefully select the “cc: group”Project Number, Letting & Production Dates

I

Page 48: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

E-mail works well when the appropriate persons are included. Forward the e-mail history when requesting assistance from the responsible office; the technical expert may need to request additional details from the designer.

48

Chapter 5: Contact ListsProject Specific Issues

Designer coordinates with Project Manager.Project Manger works with District or Responsible Office, as needed

E-mail, with Designer and Project Manager’s contact information, works well to expedite responses. Carefully select the “cc: group”Project Number, Letting & Production Dates

I

Page 49: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Ensure that all correspondence includes a project number. A letting and/or production date is helpful.

For best service, submit questions and requests in a timely manner, in accordance with the PPM submittal schedule. Allow others sufficient response time, before submittal dates.

More on requesting pay items in a few moments…

49

Chapter 5: Contact ListsProject Specific Issues

Designer coordinates with Project Manager.Project Manger works with District or Responsible Office, as needed

E-mail, with Designer and Project Manager’s contact information, works well to expedite responses. Carefully select the “cc: group”Project Number, Letting & Production Dates

I

Page 50: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Chapter 6 details processes for Requesting Pay Items. Please refer to the online file for complete information.

Over the past year, we have simplified the process for requesting pay items; please review the text or ask for assistance when considering a new pay item.

Looking at Opening Pay Items and Creating New Pay Items…

50

Chapter 6: Requesting Pay ItemsOpening pay itemsCreating new pay itemsPay Item request instructionsInactive ItemsPay Item reviewsCoordination TeamManagement TeamDevelopmental, Trial, and/or Special Pay ItemsGeneric Pay Items

I

Page 51: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Items shown in the Basis of Estimates may be opened, subject to implementation dates or other notes shown.

Most of the valid combinations are currently open.

When existing pay items do not meet the needs for a project, several options are available.

New items may included additional sizes, shapes, or other material properties.

The project may call for “adjust”, rather than “Furnish & Install”. Items may be furnished by a local agency, to be installed by the contractor.

51

Chapter 6: Requesting Pay ItemsOpening pay itemsCreating new pay items

Additional Size, shape, etc.Other operations?General use, new specs?Project Specific/Limited use?Developmental/Experimental?

I

Page 52: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

New items are also created when new specifications are developed. These new items may be an expansion of an existing pay item structure, or they may completely replace pay item groups.

Old Specs: old pay items;

New specs: new pay items.

Finally, “special” pay items are created when project specific needs are unique, developmental, or experimental. Talk with your District Estimates Office if you have “special” considerations.

More info in a few moments…

52

Chapter 6: Requesting Pay ItemsOpening pay itemsCreating new pay items

Additional Size, shape, etc.Other operations?General use, new specs?Project Specific/Limited use?Developmental/Experimental?

I

Page 53: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Frequent questions: “Is it close enough?” or “Should I use an existing pay item, with a plan note?”

NO, don’t abuse a pay item because it…

•Skews Cost History

• Avoids development of a new item/ product/ specification

• Introduces potential claims due to non-standard use (or incomplete specs/details)

Do not use a plan note to change the intent of an existing item or spec.

53

Chapter 6: Requesting Pay ItemsOpening pay itemsCreating new pay items

Additional Size, shape, etc.Other operations?General use, new specs?Project Specific/Limited use?Developmental/Experimental?

I

Page 54: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Pay Item Request Form is not required.

When requesting a new item, either by form or e-mail, please include the proposed pay item description, unit of measure, and pay item structure (size, shape, or other needed variables).

For new items, it is also helpful to include BOE details, specs, or plan details, as needed to complete the BOE information. (Don’t copy the online BOE; I have a copy…)

54

Chapter 6: Requesting Pay ItemsOpening pay itemsCreating new pay itemsPay Item request instructionsInactive ItemsPay Item reviewsCoordination TeamManagement TeamDevelopmental, Trial, and/or Special Pay ItemsGeneric Pay Items

I

Page 55: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Remember to Include your contact information- name, phone, and e-mail address.

Hint: Furnish only and Install only are questioned. Please explain when these items are requested.

District Estimators will forward your request. A response will be sent “reply to all” as soon as the item is available.

Most requests are completed within 30 minutes. (If I am at my desk, items can be opened in +/- 3 minutes. Afternoon requests are normally processed the following morning.)

55

Chapter 6: Requesting Pay ItemsOpening pay itemsCreating new pay itemsPay Item request instructionsInactive ItemsPay Item reviewsCoordination TeamManagement TeamDevelopmental, Trial, and/or Special Pay ItemsGeneric Pay Items

I

Page 56: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Notes concerning pay item structure (variables):

Variables should be used when needed to distinguish operation, size, shape, or any other characteristic that significantly affects the installed cost. Characteristics that do not affect cost may be detailed in the plans or specs, or left as an option to the Contractor.

More details on the pay item structure are available in Chapter 10.

56

Chapter 6: Requesting Pay ItemsOpening pay itemsCreating new pay itemsPay Item request instructionsInactive ItemsPay Item reviewsCoordination TeamManagement TeamDevelopmental, Trial, and/or Special Pay ItemsGeneric Pay Items

I

Page 57: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

As specifications and/or standards are updated, the Responsible Office(s) are asked to review the list of valid pay items.

Items are considered to be inactive when they are not used for a 2 year period. If no future use is proposed, the Responsible Office may recommend removing the item(s) from the BOE.

If items are deemed obsolete, due to specification or design standard changes, they are blocked, as needed.

57

Chapter 6: Requesting Pay ItemsOpening pay itemsCreating new pay itemsPay Item request instructionsInactive ItemsPay Item reviewsCoordination TeamManagement TeamDevelopmental, Trial, and/or Special Pay ItemsGeneric Pay Items

I

Page 58: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Continuing on with the Coordination Team “C-Team” and Management Team “M-Team”…

58

Chapter 6: Requesting Pay ItemsOpening pay itemsCreating new pay itemsPay Item request instructionsInactive ItemsPay Item reviewsCoordination TeamManagement TeamDevelopmental, Trial, and/or Special Pay ItemsGeneric Pay Items

I

Page 59: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Both Teams are composed of members from Design, Construction, Traffic Ops, and Maintenance.

The C-Team works to coordinate the implementation of Pay Items, Specifications, Standards, and other issues.

The M-Team works to resolve issues between offices, whether resulting from project, specification, policy, legislation, or other administrative issues.

59

Chapter 6: Requesting Pay ItemsCoordination Team

Representatives from Design, Construction, Maintenance, and other officesCoordinate the implementation of Pay Items, Specifications, Standards, and other issues

Management TeamManagers from same officesWork to resolve issues between offices, policy issues, etc.

I

Page 60: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Depending on the issue, either the responsible office, C-Team, or M-Team will coordinate with the District Office(s) prior to implementing major changes.

Following direction from the M-Team, the specifications, standards, pay items, manuals, and/or handbooks are updated. The C-Team coordinates the implementation, preparing Bulletin(s) as necessary.

60

Chapter 6: Requesting Pay ItemsCoordination Team

Representatives from Design, Construction, Maintenance, and other officesCoordinate the implementation of Pay Items, Specifications, Standards, and other issues

Management TeamManagers from same officesWork to resolve issues between offices, policy issues, etc.

I

Page 61: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Developmental, Trial, and/or “Special” pay items are considered for various limited use situations:

Specifications are subject to change, often due to new or experimental conditions

Unique or uncommon project conditions

New product evaluation

All of these situations should be monitored by the Responsible Office, so that results can be carefully recorded and evaluated.

61

Chapter 6: Requesting Pay ItemsOpening pay itemsCreating new pay itemsPay Item request instructionsInactive ItemsPay Item reviewsCoordination TeamManagement TeamDevelopmental, Trial, and/or Special Pay ItemsGeneric Pay Items

I

Page 62: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Generic Pay Items are new. “They are intended to support one-time usage pay items or specialty situations where a standard pay item is not available, and for which it is not practical to create a new pay item.”

While they are a wonderful new tool, there are rules that apply, to avoid abuse.

62

Chapter 6: Requesting Pay ItemsOpening pay itemsCreating new pay itemsPay Item request instructionsInactive ItemsPay Item reviewsCoordination TeamManagement TeamDevelopmental, Trial, and/or Special Pay ItemsGeneric Pay Items

I

Page 63: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The following rules apply in the usage of all generic pay items, including duplicate Lump sum projects.

63

Chapter 6: Requesting Pay ItemsGeneric Pay Items- Rules

do not use if there is an existing itemdo not use to avoid an itemdo not use to circumvent a review or approval processdo not use as a “work around” for something that has been rejected or denied.do not use to “sole source” a productdo not use to avoid requesting an item

Must be supported by Tech spec and/or plan detailMust be loaded in the appropriate category

I

Page 64: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Chapter 7 addresses Plan Notes.

While this chapter previously contained a list of commonly used plan notes, these notes are no longer duplicated from the PPM.

This chapter is now used to address when some plan notes are needed, and how to ensure that the note compliments the standards, specs, and or pay items.

64

Chapter 7: Plan NotesGeneral InformationCoordination between plans, specs, and pay items“T” Flag for Tech Specs and/or Plan Details

I

Page 65: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Plan Notes should NOT be used to change, duplicate, or override the specifications or standards.

When changes to the specifications or standards are needed, coordinate with the responsible office for instructions on how to complete the change. Approvals may be needed for “non-standard” design or construction requirements.

65

Chapter 7: Plan NotesGeneral InformationCoordination between plans, specs, and pay items“T” Flag for Tech Specs and/or Plan Details

I

Page 66: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Specifications generally include:

Description

Materials

Construction or Installation requirements

Method of Measurement

Basis of Payment

When all or part of a specification is not available, a plan note or detail may be used to complete the information.

66

Chapter 7: Plan NotesGeneral InformationCoordination between plans, specs, and pay items“T” Flag for Tech Specs and/or Plan Details

I

Page 67: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

It is the Designer’s responsibility to ensure that the plans, specifications, and pay items are complete for each item of work included in the plans.

67

Chapter 7: Plan NotesGeneral InformationCoordination between plans, specs, and pay items“T” Flag for Tech Specs and/or Plan Details

I

Page 68: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

When specifications are known to be incomplete for a given pay item, a “T” flag is included on some reports to remind the designer that additional information (specs and/or details) is needed in the contract documents.

Remember: to be complete, the description, material requirements, construction or installation instructions, method of measurement, and basis of payment is needed.

68

Chapter 7: Plan NotesGeneral InformationCoordination between plans, specs, and pay items“T” Flag for Tech Specs and/or Plan Details

I

Page 69: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Plan notes or detail drawings are often helpful to “describe” the work to be completed.

Does the plan note include material requirements?

Does the plan note include installation methods or performance requirements?

Does the plan note include measurement instructions? Is it field measured or plan quantity?

Does the plan note require a complete installation?

If not complete, a Tech Spec may be required.

69

Chapter 7: Plan NotesGeneral InformationCoordination between plans, specs, and pay items“T” Flag for Tech Specs and/or Plan Details

I

Page 70: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

In other terms, a plan note is used with the Tech Spec to provide complete information for an item of work.

Other flags include

D Plan Details required

P Permit required

M Monitored item

G Generic Item

A Approvals needed

70

Chapter 7: Plan NotesGeneral InformationCoordination between plans, specs, and pay items“T” Flag for Tech Specs and/or Plan Details

I

Page 71: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

There are two types of forms used to calculate and document pay items and quantities.

71

Chapter 8: FormsCADD (Tabulation forms included in the plans)

COMP (Computation Book forms)

I

Page 72: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The CADD forms are included in the plans. Most items are tabulated by location, with quantity totals by pay item for the entire category of work.

The CADD forms are maintained by the State CADD Office.

72

Chapter 8: FormsCADD (Tabulation forms included in the plans)

COMP (Computation Book forms)

I

Page 73: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The COMP forms are included in the Computation Book. Most items are calculated by location, with quantity totals by pay item for the entire category of work.

COMP forms are maintained by the State Construction Office.

73

Chapter 8: FormsCADD (Tabulation forms included in the plans)

COMP (Computation Book forms)

I

Page 74: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Chapter 9 provides an overview of the Webgate and Designer Interface. These FDOT programs were designed to work with the AASHTO Trnsport software.

74

Chapter 9: Webgate and Designer Interface

RACF Password requiredDesigner InterfaceTrnsport Reports

Internet Reports

I

Page 75: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Webgate and Designer Interface web application require a RACF or “FDOT mainframe” userID and password. These accounts are only available to consultants whose firms have current contracts with the Department.

UserIDs and passwords should be requested through your FDOT Project Manager.

75

Chapter 9: Webgate and Designer Interface

RACF Password requiredDesigner InterfaceTrnsport Reports

Internet Reports

I

Page 76: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Designer Interface is a FDOT web interface to the Trnsport PES module. This interface allows the Designer to enter pay items and quantities, by category, for projects assigned to their consulting firm.

76

Chapter 9: Webgate and Designer Interface

RACF Password requiredDesigner InterfaceTrnsport Reports

Internet Reports

I

Page 77: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Several reports are available for Designers. The two most commonly used reports are the Project Edit Report and Proposal Summary of Quantities.

The Project Edit Report should be used after any changes are made to the pay items or quantities, or after any “idle” or “shelved” period.

The Project Edit Report will help to identify missing structures category information, obsolete items, and possible “T” flag items.

77

Chapter 9: Webgate and Designer Interface

RACF Password requiredDesigner InterfaceTrnsport Reports

Internet Reports

I

Page 78: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Proposal Summary of Quantities report is used to include the items and quantities in the plans. Note that the proposal is normally created during the later project phases.

The Project Edit Report should always be run & verified, for each project within the proposal, prior to running the Proposal Summary of Quantities. This will help to avoid many pay item and Trnsport errors.

78

Chapter 9: Webgate and Designer Interface

RACF Password requiredDesigner InterfaceTrnsport Reports

Internet Reports

I

Page 79: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Project Edit Report is also used to verify structures header information for each structure. Critical information includes:

•Bridge Number

•Length

•Width

•Superstructure Type

•Substructure Type

This information is used for FHWA reporting. Refer to Chapter 9 for additional information.

79

Chapter 9: Webgate and Designer Interface

RACF Password requiredDesigner InterfaceTrnsport Reports

Internet Reports

I

Page 80: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

For users who do not have a RACF password, several common reports are available on the Specifications and Estimates web page.

http://www.dot.state.fl.us/ specificationsoffice/Estimates/ HistoricalCostInformation/ HistoricalCost.shtm

If additional pay item information is needed, please contact the District Estimates staff, or the State Specifications and Estimates Office- Estimates System Support section.

80

Chapter 9: Webgate and Designer Interface

RACF Password requiredDesigner InterfaceTrnsport Reports

Internet Reports

I

Page 81: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Chapter 10 details the how the BOE information is organized for each pay item group.

There are 10 digits available for a pay item number, including the leading zero for most items:

0123-456-789

The first group of digits corresponds to the applicable specification section.

81

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 82: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The remaining digits are used to describe the operation and other variables needed to distinguish the pay item.

Maintenance Items, valid only on maintenance contracts, are shown in some editions of the BOE. They are easily identified with a leading “E” in the first group of digits. The remaining pay item structure and formatting guidelines are the same for all pay items.

82

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 83: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Pay Item Description should be clear and concise.

When entered into the Trnsport system, the pay item description, along with all variable characteristics, will be entered. Some text may be abbreviated to fit within the available fields.

83

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 84: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

A sample pay item is shown.

Note that the top area has the pay item details, while the bottom area has the pay item structure.

84 I

Page 85: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

A sample pay item is shown.

Note that the top area has the pay item details, while the bottom area has the pay item structure.

85 I

Structure

Details

Page 86: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The pay item description shown at the top of each item group.

While some pay item groups will list the primary word first, as in “Pipe, Optional”, more descriptions are now shown as we commonly speak them, as in “Optional Pipe”.

Either description may be used in the specs and plans.

Variables, as shown in the pay item structure, should be included with the pay item description whenever necessary to clearly identify a specific pay item: PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 12” SD

86

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 87: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The unit, accuracy, and plan quantity information must agree with the available specifications and/or standards.

When creating a new item, the unit of measure should consider the application or installation methods, as well as possible quantity adjustments in the field.

Accuracy requirements should consider both the product and field conditions.

87

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 88: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The response to “Plan Quantity?” is either a “yes” or “no”.

The available specifications or standards must indicate a “Plan Quantity” measurement for this field to be “yes”.

For new items, the responsible office will consider field measurement and possible adjustments before recommending whether to use Plan Quantity.

88

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 89: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

For Designers, ensure that the plan quantity is accurately shown in the plans.

Subject to 9-3 of the specifications, adjustments to plan quantity will be made if the difference between actual and plan quantity exceeds 5% or an amount of $5000.

89

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 90: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Important Dates field is used to inform users of implementation (or obsolete) dates.

When available, replacement items will be referenced in this field.

Notes for obsolete items will normally remain in the BOE for 1 year after implementation, to assist designers with replacement items.

90

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 91: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Detail section of each pay item is intended to provide a brief summary of the correct usage, as well as measurement details. As necessary, a “do not use when…” statement will be included to clarify correct usage.

The details are obtained from the responsible office, valid specifications, and helpful designers. Comments and suggestions are welcome through e-mail or online BOE web page.

91

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 92: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

When related pay items are recommended or required, they are shown in this field. Carefully consider each pay item and the product or work included for payment.

92

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 93: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Items are documented in either the plans: CADD tabulation sheets; or computation book: COMP forms.

In general, pay items with complex geometries are calculated and documented in the computation book, and identified by location. Pay items with easily defined geometries or locations are shown in the plans on a tabulation sheet.

When a CADD form is available, tabulation in the plans is generally preferred. See the PPM and Design Standards Instructions for more information.

93

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 94: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

References may include PPM guidelines, standards, or specifications. When available, these references should be considered before choosing the pay item(s).

If the specification or standard does not apply, do not use the pay item without further guidance. Depending on project conditions, either a modified spec or standard is needed, or a “special” pay item may be recommended. Contact the District Estimates staff for assistance.

94

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, Stand.Plan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 95: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Plan Detail and/or Tech Spec Required: Refer to Chapter 7 for additional information.

When is a Plan Note/Detail sufficient? Only when the remaining specification information is complete: description, materials, construction, measurement, and payment.

Then is a Tech Spec required? Whenever the above information is incomplete in the contract documents.

95

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 96: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Most specifications are written for “furnish and install” operations. When other operations are called for, ensure that the appropriate instructions are available.

Furnish only: Due to FHWA funding rules, the Department does not normally require additional items to be furnished without installation. Exceptions might include special items, to be funded by a local maintaining agency. Contact the District Estimates staff prior to using this operation.

96

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 97: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Install only: Some “specialty items” are available on a state contract, purchased by the Department, and then installed by the Contractor. In this case, an Install only item may be used. When this occurs, the plans or specs must detail the item, pick-up/delivery instructions, as well as any incidentals that may need to be furnished by the Contractor.

Another example: For some signals or utility items, a local agency may furnish the product to be installed by the contractor. This ensures that installed products remain compatible with existing systems.

97

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 98: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Relocate: Ensure that the existing item is in good condition. Evaluate whether it is cost effective to relocated an old or obsolete item. Plans or specs should clearly identify the initial and final locations, as well as any incidental items that may need to be furnished by the Contractor for a complete installation.

98

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 99: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Adjust / Modify: Detail minor work to be completed by the Contractor.

Remove: Plans or specs should identify whether the contractor is to take ownership, stockpile, or deliver the item(s) to a FDOT maintenance yard.

99

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 100: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Special or Custom Items: When available, the special or custom description should only be used when there is a significant deviation from the specifications or standards. Complete specs, details, or design calculations may be required.

Minor changes to the spec or standard requirements may often be noted in the plans, using the standard pay item(s).

100

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 101: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Is an item standard or special?

If the proposed change does not significantly affect the design calculations, cost, or lifespan of the item, it is likely a minor change; use the standard pay item.

If the proposed change significantly affects the design calculations, cost or lifespan, it is likely that a special or custom pay item should be used.

101

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 102: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Mast Arm Example

Slightly shorter arm required: load calculations are not negatively impacted, may be field cut; use standard pay item.

Additional sign or signal required: wind loads need to be evaluated by designer; extra length or diameter arms may increase material requirements, additional cost. Use the custom pay item.

102

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 103: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

The Pay Item Structure shows the available pay item combinations, including operation, size, shape, etc.

Variables are only used when they significantly affect the installed cost of an item.

Ranges are used to group items with a similar installed cost.

103

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 104: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Too few items: Specs or plan details are used to distinguish between many items; this provides a mixed cost history on each item.

Too Many items: detailed pay items, but limited cost history on each item. Details are needed in the specs or standards.

104

Too Many items

Too Few Items

I

Page 105: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Grouped by similar cost history (ranges): common features are shown in the standards; specific sizes or special details are shown in the specs or plans.

Grouping by similar cost provides a balance between too many items (limited history on each item) and too few items (mixed history for varied characteristics).

105

Too Many items

Too Few Items

Grouped by similar cost

history

I

Page 106: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

Items to remember:

Installed cost=Materials + Equipment+ Labor

Unit price on small quantities is normally higher, due to equipment set-up or labor costs.

Additional pricing information is available in Part 3 of the CBT.

106

Price vs. Quantity

District XDistrict YDistrict Z

Quantity

$

I

Page 107: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 1

A “Where to find it” table is included at the end of Chapter 10. Remember that the first group of pay item digits corresponds to the applicable specification section.

100s General, Earthwork

200s Base Courses

300s Pavement

400s Structures

500s Incidental Construction

600s Traffic Control Devices

700s Signing, Lighting, and Pavement Markings

900s Special Items

107

Chapter 10: Formatting Pay Items

Pay Item DescriptionUnit, Accuracy, Plan QuantityImportant DatesDetailRelated ItemsDocumentationReferences, Specs, StandardsPlan Detail and/or Tech SpecPay Item StructureWhere to Find It

I

Page 108: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates

This concludes this part.

Part 2 is designed to help Designers select the appropriate item(s) for the work required.

108

Part 1: Introduction to the Basis of Estimates

Part 2: Selecting Pay Items

Part 3: Estimating and Review

I

Page 109: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Each section will review BOE details about specific items, to assist with item selection:

Spec highlights

Standards

References

Additional guidance

This guidance highlights commonly used items.

For complete details, refer to the Basis of Estimates, Specifications, and/or other references for each item.

109

Selecting Pay Items100s200s300s400s500s600s700s800s900sUtilitiesGeneric Items

I

Page 110: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The 100s deal with General Construction Operations, Clearing the Construction site, and Earthwork.

As you can see, from the section titles, they begin with set-up of the construction site…

110

Selecting Pay Items100s

101 Mobilization102 Maintenance of Traffic103 Temporary Work Struct.104 Erosion/Sediment Control109 Engineer’s Field Office110 Clearing and Grubbing120 Excavation and Embankment

I

Page 111: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

…continues with basic ground preparation,…

111

Selecting Pay Items100s

121 Flowable Fill 125 Excavation for Structures and Pipe141 Settlement Plate Assembly144 Geotechnical145 Geotechnical Fabrics

I

Page 112: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

and includes some related operations.

We’ll now take a look at each section, along with selected pay items. Remember that the first 3 digits of a pay item correspond to the associated specification section number.

112

Selecting Pay Items100s

160 Stabilizing161 Predesigned Subbase162 Prepared Soil Layer173 Pressure Grouting175 Cracking and Reseating Existing Concrete Pavement

I

Page 113: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The Mobilization pay item is used on each project, loaded in the Roadway category. When no roadway plans are present, the item is loaded in the primary category, i.e. Signals category for a “signals only” project, or Landscape category for a “landscape only” project.

This Lump Sum item is intended to cover the contractor’s expenses for “movement of personnel, equipment, supplies, and incidentals to the project site…”

113

Selecting Pay Items100s

101 Mobilization102 Maintenance of Traffic103 Temporary Work Struct.104 Erosion/Sediment Control109 Engineer’s Field Office110 Clearing and Grubbing120 Excavation and Embankment

I

Page 114: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The Maintenance of Traffic items are only intended for use while the contract is under construction. Most MOT items (cones, barricades, signs, etc.) should be removed at the end of the construction period.

Designers should carefully consider the item, unit of measure, MOT phase, and contract duration when selecting and estimating MOT items.

If the contract duration is changed MOT quantities (per day) may need to be recalculated.

114

Selecting Pay Items100s

101 Mobilization102 Maintenance of Traffic103 Temporary Work Struct.104 Erosion/Sediment Control109 Engineer’s Field Office110 Clearing and Grubbing120 Excavation and Embankment

I

Page 115: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Separate payment for Temporary Work Structures is only permitted when the structure is required to support construction equipment, or to comply with permits. (Falsework and scaffording are not included.)

Think of this item as “building a work bridge before building the bridge”

Coordinate with the State Structures Design Office, prior to using this item.

115

Selecting Pay Items100s

101 Mobilization102 Maintenance of Traffic103 Temporary Work Struct.104 Erosion/Sediment Control109 Engineer’s Field Office110 Clearing and Grubbing120 Excavation and Embankment

I

Page 116: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Erosion and Sediment Control specifications are transitioning from prescribed materials and methods to contractor selected operations. Refer to the latest specifications for guidance on the correct pay item(s).

Note that the Contractor will be required to install erosion control devices in accordance with the State of Florida Erosion and Sediment Control manual. It is located online at http://www.dot.state.fl.us/Specificationsoffice/Implemented/urlinspecs/files/flerosionsedimentmanual.pdf

116

Selecting Pay Items100s

101 Mobilization102 Maintenance of Traffic103 Temporary Work Struct.104 Erosion/Sediment Control109 Engineer’s Field Office110 Clearing and Grubbing120 Excavation and Embankment

I

Page 117: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

We’ll now take a look at a few of the items within Section 104.

104-10-3 Sediment Barriers, LF

This item includes synthetic bales, staked silt fence, and other similar materials.

Use caution when updating old plans that calculated the number of synthetic bales. The linear feet of barriers will need to be recalculated, as necessary.

Keep in mind that 104-18 Inlet Protection, per each, may replace some of the bales or barriers.

117

Selecting Pay Items100s

101 Mobilization102 Maintenance of Traffic103 Temporary Work Struct.104 Erosion/Sediment Control109 Engineer’s Field Office110 Clearing and Grubbing120 Excavation and Embankment

I

Page 118: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

104-11 Floating Turbidity Barrier, LF

104-12 Staked Turbidity Barrier, LF

Note that the staked turbidity barrier differs from the staked silt fence. While the silt fence is an open weave fabric, allowing water to flow through, the turbidity barrier is made of nylon reinforced PVC

118

Selecting Pay Items100s

101 Mobilization102 Maintenance of Traffic103 Temporary Work Struct.104 Erosion/Sediment Control109 Engineer’s Field Office110 Clearing and Grubbing120 Excavation and Embankment

I

Page 119: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The field office is included on a project only when required by the Construction Office. Note that this is a field office, provided by the Contractor, but used by the FDOT Engineer and staff. Refer to the CPAM for additional guidelines.

The size of the office should be shown in the plans and pay item number. The specifications detail the office requirements, as well as calculation of days.

119

Selecting Pay Items100s

101 Mobilization102 Maintenance of Traffic103 Temporary Work Struct.104 Erosion/Sediment Control109 Engineer’s Field Office110 Clearing and Grubbing120 Excavation and Embankment

I

Page 120: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Most projects will include the lump sum Clearing and Grubbing pay item. The secondary units, per acre, are used for estimating purposes.

Additional minor pavement removal, debris removal, and incidental work may be included under this item, according to the specifications.

While the limits and scope of work are shown in the plans, do not tabulate the number of acres in the plans.

Removal of Existing Structure, item 110-3-, is used when widening or replacing bridges. This is also a lump sum item, with secondary area units.

120

Selecting Pay Items100s

101 Mobilization102 Maintenance of Traffic103 Temporary Work Struct.104 Erosion/Sediment Control109 Engineer’s Field Office110 Clearing and Grubbing120 Excavation and Embankment

I

Page 121: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Chapter 3 of the PPM addresses earthwork:

•when to use excavation and embankment items

•when to use each item

•how to calculate the volume (ground measure or truck measure)

•and when no additional payment is provided.

Note that payment for some items is based on the volume of the material added or removed, while other items use a truck measurement, with adjustments based on the fill material. Refer to the specifications for detailed calculations.

121

Selecting Pay Items100s

101 Mobilization102 Maintenance of Traffic103 Temporary Work Struct.104 Erosion/Sediment Control109 Engineer’s Field Office110 Clearing and Grubbing120 Excavation and Embankment121 Flowable Fill 125 Excavation for Structures and Pipe

I

Page 122: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Flowable fill is used for “beddings, encasements, closure for tanks, pipes, and general backfill for trenches.”

The material is placed using concrete construction equipment- chute, pumping, or other methods approved by the engineer.

For most items of work, flowable fill is incidental to other items of work: pipe bedding, backfill, and other encasements.

122

Selecting Pay Items100s

101 Mobilization102 Maintenance of Traffic103 Temporary Work Struct.104 Erosion/Sediment Control109 Engineer’s Field Office110 Clearing and Grubbing120 Excavation and Embankment121 Flowable Fill 125 Excavation for Structures and Pipe

I

Page 123: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

For many items of work, payment for excavation is included in the item being installed. No direct payment is provided; payment is included in the contract price for concrete or the applicable structure.

123

Selecting Pay Items100s

101 Mobilization102 Maintenance of Traffic103 Temporary Work Struct.104 Erosion/Sediment Control109 Engineer’s Field Office110 Clearing and Grubbing120 Excavation and Embankment121 Flowable Fill 125 Excavation for Structures and Pipe

I

Page 124: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The 100s deal with General Construction Operations, Clearing the Construction site, and Earthwork.

When unusual geotechnical situations are present, coordinate with the District or State Geotechnical Engineer. They will be able to assist with recommended design solutions, specifications, and pay items.

Selected items are described in the Structure Design Guidelines (SDG), as identified in the Instructions for Design Standards.

124

Selecting Pay Items100s

141 Settlement Plate Assembly144 Geotechnical145 Geotechnical Fabrics

I

Page 125: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Settlement Plate Assembly is used when directed by the District or State Geotechnical Engineer. Complete technical specifications will be required, based on project conditions.

125

Selecting Pay Items100s

141 Settlement Plate Assembly144 Geotechnical145 Geotechnical Fabrics

I

Page 126: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The 144 pay items and specifications should only be used with guidance from the District or State Geotechnical Engineer. Complete Technical Specifications will be necessary.

126

Selecting Pay Items100s

141 Settlement Plate Assembly144 Geotechnical145 Geotechnical Fabrics

I

Page 127: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Selected geotechnical fabrics are shown on index 501. All other applications should be used as directed by the District or State Geotechnical Engineer.

Note: No separate payment is made for fabrics used to wrap pipes or line trenches, such as French drain. Refer to the applicable drainage specifications for these applications.

127

Selecting Pay Items100s

141 Settlement Plate Assembly144 Geotechnical145 Geotechnical Fabrics

I

Page 128: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Looking at the last group of 100s…

Stabilization, subbase, and reseating existing concrete pavement are used in accordance with the pavement design manuals.

128

Selecting Pay Items100s

160 Stabilizing161 Predesigned Subbase162 Prepared Soil Layer173 Pressure Grouting175 Cracking and Reseating Existing Concrete Pavement

I

Page 129: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Type B Stabilization “serves as a working platform to permit the efficient construction of the base material” – per the Flexible Pavement Design Manual. Consult this manual for appropriate use of the pay item.

129

Selecting Pay Items100s

160 Stabilizing161 Predesigned Subbase162 Prepared Soil Layer173 Pressure Grouting175 Cracking and Reseating Existing Concrete Pavement

I

Page 130: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 161- Predesigned Subbase is used only for shoulder and non-traffic areas.

130

Selecting Pay Items100s

160 Stabilizing161 Predesigned Subbase162 Prepared Soil Layer173 Pressure Grouting175 Cracking and Reseating Existing Concrete Pavement

I

Page 131: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

There are three commonly used applications for a prepared soil layer:

The finish soil layer is used for areas to be seeded, mulched, and/or planted: i.e. grass or sod.

An organic soil layer or blanket material is used only when required by a permit.

These items are generally NOT used for Landscape Operations; landscape bed preparation is included in the lump sum payment for installing plants. Detail all soil requirements in the landscape plans and/or specifications.

131

Selecting Pay Items100s

160 Stabilizing161 Predesigned Subbase162 Prepared Soil Layer173 Pressure Grouting175 Cracking and Reseating Existing Concrete Pavement

I

Page 132: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 173 is to be used for subsurface applications only. Due to the technical nature of this work, coordinate the use of this item with the State Geotechnical Engineer in the Structures Design Office.

132

Selecting Pay Items100s

160 Stabilizing161 Predesigned Subbase162 Prepared Soil Layer173 Pressure Grouting175 Cracking and Reseating Existing Concrete Pavement

I

Page 133: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The use of the 175 pay items should be coordinated with the District or State Pavement Design Engineer. In the past, these items were used to reseat concrete pavement before placing asphalt surface. A review of the subsurface conditions may be recommended before selecting this item of work.

133

Selecting Pay Items100s

160 Stabilizing161 Predesigned Subbase162 Prepared Soil Layer173 Pressure Grouting175 Cracking and Reseating Existing Concrete Pavement

I

Page 134: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The 200s deal with Base Courses.

Most base course designs use Optional Base.

When needed, reworked limerock, asphalt treated permeable base, or Cement treated permeable base may be used. Refer to the specifications and/or Pavement Design Handbook for additional information.

134

Selecting Pay Items200s

204 Graded Aggregate Base210 Reworking Limerock Base285 Optional Base286 Turnout Construction287 Asphalt Treated Permeable Base288 Cement Treated Permeable Base

I

Page 135: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

While Section 204 exists in the specifications, payment for work under this section is included under Optional Base.

135

Selecting Pay Items200s

204 Graded Aggregate Base210 Reworking Limerock Base285 Optional Base286 Turnout Construction287 Asphalt Treated Permeable Base288 Cement Treated Permeable Base

I

Page 136: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Reworking limerock base is included only when directed by the District Construction or Pavement Design Engineer.

Note that two pay items work together: the first is for the work/labor described by the specifications; the second pay item is for the new material provided by the contractor.

136

Selecting Pay Items200s

204 Graded Aggregate Base210 Reworking Limerock Base285 Optional Base286 Turnout Construction287 Asphalt Treated Permeable Base288 Cement Treated Permeable Base

I

Page 137: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Optional Base is a plan quantity item, paid per square yard.

Note that the thickness required varies with the base material selected by the Contractor. The required thickness is shown on Index 514 of the Design Standards.

Base options may be limited, according to guidance in the Plans Preparation Manual.

137

Selecting Pay Items200s

204 Graded Aggregate Base210 Reworking Limerock Base285 Optional Base286 Turnout Construction287 Asphalt Treated Permeable Base288 Cement Treated Permeable Base

I

Page 138: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The Turnout construction items are for constructing the base portion of the turnout area on widening or resurfacing projects, as shown on index 516.

The asphalt pavement and friction course are paid separately.

138

Selecting Pay Items200s

204 Graded Aggregate Base210 Reworking Limerock Base285 Optional Base286 Turnout Construction287 Asphalt Treated Permeable Base288 Cement Treated Permeable Base

I

Page 139: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Asphalt and Cement Treated Permeable Base are constructed in accordance with Index 287. Note that payment for new construction may be different for rehabilitation work. Additional subdrainage items may be necessary, based on project conditions.

139

Selecting Pay Items200s

204 Graded Aggregate Base210 Reworking Limerock Base285 Optional Base286 Turnout Construction287 Asphalt Treated Permeable Base288 Cement Treated Permeable Base

I

Page 140: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The first part of the 300s deal with Bituminous Treatment Surface Courses (Asphalt).

The specifications include several sections with no pay items; these sections include material and construction requirements. Payment for these items is included in the asphalt material quantities.

140

Selecting Pay Items300s

315 Stress Absorbing Membrane327 Milling334 Superpave Asphalt Concrete337 Friction Course339 Miscellaneous Asphalt Pavement341 Asphalt Rubber Membrane Interlayer

I

Page 141: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The remaining sections within the 300s are for concrete pavement and approach slabs.

141

Selecting Pay Items300s

346, 347 Concrete Requirements350 Cement Concrete Pavement352 Grinding Concrete Pavement353 Concrete Pavement Slab Replacement370 Bridge Approach Expansion Joints (for concrete pavement)

I

Page 142: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Looking at the individual sections within the 300s:

Section 315 is infrequently used; designers should contact the State Pavement Design Office when considering this item.

Basis of Estimates- Part 2

142

Selecting Pay Items300s

315 Stress Absorbing Membrane327 Milling334 Superpave Asphalt Concrete337 Friction Course339 Miscellaneous Asphalt Pavement341 Asphalt Rubber Membrane Interlayer

I

Page 143: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Milling is frequently used to remove existing asphalt pavement. Milling can also be used to improve ridability and cross slope of the finished pavement. The amount of material milled- the depth, must be shown in the plans.

The contractor takes ownership of the milled material, and may transport it to the asphalt plant for future recycling.

143

Selecting Pay Items300s

315 Stress Absorbing Membrane327 Milling334 Superpave Asphalt Concrete337 Friction Course339 Miscellaneous Asphalt Pavement341 Asphalt Rubber Membrane Interlayer

I

Page 144: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Superpave is the primary material used for most asphalt roadways.

The superpave pay items are selected based on the traffic level. These levels vary from A (low traffic level- quiet rural roads) to E (high traffic level- busy interstate). Levels C and D are used most frequently.

While the quantity measurement of the superpave is made per ton, a pay adjustment will be applied, based on the quality of the asphalt. Details for measurement and payment are included in the specification.

144

Selecting Pay Items300s

315 Stress Absorbing Membrane327 Milling334 Superpave Asphalt Concrete337 Friction Course339 Miscellaneous Asphalt Pavement341 Asphalt Rubber Membrane Interlayer

I

Page 145: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The friction course items are measured and paid similar to the superpave. Quantity measurement is made per ton and a pay adjustment will be applied, based on the quality of the friction courses.

145

Selecting Pay Items300s

315 Stress Absorbing Membrane327 Milling334 Superpave Asphalt Concrete337 Friction Course339 Miscellaneous Asphalt Pavement341 Asphalt Rubber Membrane Interlayer

I

Page 146: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Two items of note for Asphalt:

First: several binder options are available for both the Superpave and Friction Course options. Selection of the binder should be in accordance with the flexible pavement manual, or as directed by the District Pavement Design Office.

Second, “Warranty” options are available for some asphalt/ resurfacing contracts. These options balance material and performance requirements over extended periods of time. Refer to the various types of innovative contracts for additional details. These options should only be included when directed by the District Design or Construction Office.

146

Selecting Pay Items300s

315 Stress Absorbing Membrane327 Milling334 Superpave Asphalt Concrete337 Friction Course339 Miscellaneous Asphalt Pavement341 Asphalt Rubber Membrane Interlayer

I

Page 147: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Miscellaneous Asphalt is used “where vehicular traffic does not travel, such as under guardrail, bicycle paths, median pavement, sidewalks, etc.”

Estimated quantities, per the specification, are based on 100 lbs/square yard, per inch of thickness.

147

Selecting Pay Items300s

315 Stress Absorbing Membrane327 Milling334 Superpave Asphalt Concrete337 Friction Course339 Miscellaneous Asphalt Pavement341 Asphalt Rubber Membrane Interlayer

I

Page 148: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

According to the Flexible Pavement Design Manual, an asphalt rubber membrane interlayer, ARMI, “should normally be used over cracked and reseated concrete pavement. An ARMI may also be useful as a moisture barrier if subgrade moisture is entering the pavement system through capillary action and causing a rippling of the asphalt surface.”

148

Selecting Pay Items300s

315 Stress Absorbing Membrane327 Milling334 Superpave Asphalt Concrete337 Friction Course339 Miscellaneous Asphalt Pavement341 Asphalt Rubber Membrane Interlayer

I

Page 149: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Sections 346 and 347 detail the concrete requirements for various classes of structural and non-structural concrete. No direct payment is made under these sections. The concrete material is paid according to the application: bridge structures, sidewalk, inlets, etc.

149

Selecting Pay Items300s

346, 347 Concrete Requirements350 Cement Concrete Pavement352 Grinding Concrete Pavement353 Concrete Pavement Slab Replacement370 Bridge Approach Expansion Joints (for concrete pavement)

I

Page 150: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 350 is for cement concrete pavement only. The pay items associated with this section should not be used for concrete structures, approach slabs, or other miscellaneous work.

150

Selecting Pay Items300s

346, 347 Concrete Requirements350 Cement Concrete Pavement352 Grinding Concrete Pavement353 Concrete Pavement Slab Replacement370 Bridge Approach Expansion Joints (for concrete pavement)

I

Page 151: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 352 is applicable only for grinding concrete pavement. It is not applicable for bridge decks or approach slabs.

Grinding is now required for all new concrete pavement, in addition to specified existing concrete pavement. Payment will be made for all areas to be ground.

151

Selecting Pay Items300s

346, 347 Concrete Requirements350 Cement Concrete Pavement352 Grinding Concrete Pavement353 Concrete Pavement Slab Replacement370 Bridge Approach Expansion Joints (for concrete pavement)

I

Page 152: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 353 is used to replace complete slabs of concrete pavement. Joint construction is included in the payment for the slab.

These items are not applicable for non-pavement areas such as bus pads, approach slabs, etc.

152

Selecting Pay Items300s

346, 347 Concrete Requirements350 Cement Concrete Pavement352 Grinding Concrete Pavement353 Concrete Pavement Slab Replacement370 Bridge Approach Expansion Joints (for concrete pavement)

I

Page 153: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 370 is applicable only where concrete pavement meets a bridge approach slab.

For expansion joints on a bridge, refer to the applicable items in Section 458.

153

Selecting Pay Items300s

346, 347 Concrete Requirements350 Cement Concrete Pavement352 Grinding Concrete Pavement353 Concrete Pavement Slab Replacement370 Bridge Approach Expansion Joints (for concrete pavement)

I

Page 154: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

There are a number of sections associated with the Structures group.

The sections address concrete placement, reinforcement, …

154

Selecting Pay Items400s

400 Concrete Structures407 Three Sided Precast Culvert410 Precast Concrete Box Culvert411-413 Cracks in Structures415 Reinforcing Steel416 Anchors and Dowels

I

Page 155: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

drainage structures, …

155

Selecting Pay Items400s

425 Inlets, Manholes, and Junction Boxes430 Pipe Culvers and Storm Sewers431 Pipe Liner435 Plate Pipe & Arch Culverts436 Trench Drains440 Underdrains443 French Drains444 Deep Drainage Wells449 Precast Concrete Drainage Products

I

Page 156: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

precast and prestressed construction, …

156

Selecting Pay Items400s

450 Precast Prestressed Concrete Construction451 Prestressed Soil Anchors452 Precast Segmental Bridge Construction

I

Page 157: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

foundations, …

157

Selecting Pay Items400s

453 Epoxy Joints- Precast Segment455 Structures Foundations457 Integral Pile Jackets458 Bridge Deck Joints459 Bitumen Coating and Polyethylene Sheeting on Concrete Piles

I

Page 158: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

movable bridges, and timber.

158

Selecting Pay Items400s

460 Str Steel & Misc Metals461 Multirotational Bearings462 Post-Tensioning465 Movable Bridge470 Timber Structures471 Fender System

I

Page 159: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Looking at the individual sections…

Section 400 addresses the construction of concrete structures.

Culverts, endwalls, superstructures, substructures, and approach slabs are paid per cubic yard of concrete, according to the class of concrete specified in the plans, design standards, or specifications.

For other concrete items, the designer should verify pay items and units of measure with the specifications or design standards.

159

Selecting Pay Items400s

400 Concrete Structures407 Three Sided Precast Culvert410 Precast Concrete Box Culvert411-413 Cracks in Structures415 Reinforcing Steel416 Anchors and Dowels

I

Page 160: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Sections 407 and 410 address 3 and 4 sided precast culverts.

The 3-sided precast culvert is paid per length. Variables included with the pay item account for the span and height. (Do not adjust the length to account for multiple barrels.)

The 4 sided precast box culvert is paid by concrete and steel quantities. The precast box culvert may be used in lieu of cast-in-place culverts, subject to the specification requirements.

160

Selecting Pay Items400s

400 Concrete Structures407 Three Sided Precast Culvert410 Precast Concrete Box Culvert411-413 Cracks in Structures415 Reinforcing Steel416 Anchors and Dowels

I

Page 161: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Sections 411 through 413 address the methods and materials for repairing various cracks in existing structures.

For precast, prestressed items, payment for sealer is included in the precast item.

For cast-in-place surfaces to be sealed, payment is made per gallon of sealer. Note that Class 5 coatings are paid under section 400 items.

161

Selecting Pay Items400s

400 Concrete Structures407 Three Sided Precast Culvert410 Precast Concrete Box Culvert411-413 Cracks in Structures415 Reinforcing Steel416 Anchors and Dowels

I

Page 162: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Reinforcing steel is paid per pound for most structures.

Example: superstructure, substructure, bulkhead, approach slabs, box culverts

When reinforcement is included, per standard or specification, no separate payment is made.

Example: endwalls, traffic separators,slabs around pull boxes, light pole foundations

Read the applicable specs and standards.

162

Selecting Pay Items400s

400 Concrete Structures407 Three Sided Precast Culvert410 Precast Concrete Box Culvert411-413 Cracks in Structures415 Reinforcing Steel416 Anchors and Dowels

I

Page 163: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 416 addresses anchors and dowels used for structural applications, including traffic railing barrier applications.

There is no separate payment for the work described in this section. All work is incidental to the applicable structural item(s).

163

Selecting Pay Items400s

400 Concrete Structures407 Three Sided Precast Culvert410 Precast Concrete Box Culvert411-413 Cracks in Structures415 Reinforcing Steel416 Anchors and Dowels

I

Page 164: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

There are many types of inlets, manholes, and junction boxes. Refer to the Design Standards for the correct type for each location.

When minor changes to a standard are needed, detail the change in the plans and use the pay item that corresponds to the standard.

The “Special” pay item should only be used when the design standards are not applicable. Complete designs, including reinforcement details, are required in the plans.

164

Selecting Pay Items400s

425 Inlets, Manholes, and Junction Boxes430 Pipe Culvers and Storm Sewers431 Pipe Liner435 Plate Pipe & Arch Culverts436 Trench Drains440 Underdrains443 French Drains444 Deep Drainage Wells449 Precast Concrete Drainage Products

I

Page 165: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 430 details the materials and installation requirements for drainage pipe and end sections.

Drainage pipe is paid according to plan quantity.

For JPA utility applications, refer to the utility items in the 1000s group.

165

Selecting Pay Items400s

425 Inlets, Manholes, and Junction Boxes430 Pipe Culvers and Storm Sewers431 Pipe Liner435 Plate Pipe & Arch Culverts436 Trench Drains440 Underdrains443 French Drains444 Deep Drainage Wells449 Precast Concrete Drainage Products

I

Page 166: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Pipe liner is used to rehabilitate an existing pipe. Normally, pipe liner is installed from one drainage structure to another, along an entire length of pipe.

Designers should coordinate with the State Drainage Office prior to using any partial length or sectional liners, as a full length liner or pipe replacement may be more cost effective.

In addition to showing the pipe length and location in the plans, the contract documents must include the allowable materials and/or material requirements.

166

Selecting Pay Items400s

425 Inlets, Manholes, and Junction Boxes430 Pipe Culvers and Storm Sewers431 Pipe Liner435 Plate Pipe & Arch Culverts436 Trench Drains440 Underdrains443 French Drains444 Deep Drainage Wells449 Precast Concrete Drainage Products

I

Page 167: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Plate pipe and pipe arch culverts are installed similarly to optional pipe of Section 430.

Measurement and payment are also by plan quantity.

If coatings are required, a note should be included in the plans. Bituminous coating materials are specified in Section 944. Other coating materials may require a tech spec. Payment for coatings are included in the culvert.

167

Selecting Pay Items400s

425 Inlets, Manholes, and Junction Boxes430 Pipe Culvers and Storm Sewers431 Pipe Liner435 Plate Pipe & Arch Culverts436 Trench Drains440 Underdrains443 French Drains444 Deep Drainage Wells449 Precast Concrete Drainage Products

I

Page 168: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Trench drain is installed in accordance with Index 206, for use in gutters and driveways.

Payment is made per plan quantity, and includes pipe, concrete backfilling, outlet pipe, and grate.

168

Selecting Pay Items400s

425 Inlets, Manholes, and Junction Boxes430 Pipe Culvers and Storm Sewers431 Pipe Liner435 Plate Pipe & Arch Culverts436 Trench Drains440 Underdrains443 French Drains444 Deep Drainage Wells449 Precast Concrete Drainage Products

I

Page 169: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Unlike many other drainage items, Underdrain is measured in place for payment.

The pipe, fittings, aggregate, filter fabric, and incidentals are included in the linear foot payment. Additional details are included in the design standards, index 286.

169

Selecting Pay Items400s

425 Inlets, Manholes, and Junction Boxes430 Pipe Culvers and Storm Sewers431 Pipe Liner435 Plate Pipe & Arch Culverts436 Trench Drains440 Underdrains443 French Drains444 Deep Drainage Wells449 Precast Concrete Drainage Products

I

Page 170: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

French drain is installed in accordance with the Drainage Manual. Note that all French drain should be paid with the 443 pay items, rather than the component materials for pipe, filter fabric, and rock.

170

Selecting Pay Items400s

425 Inlets, Manholes, and Junction Boxes430 Pipe Culvers and Storm Sewers431 Pipe Liner435 Plate Pipe & Arch Culverts436 Trench Drains440 Underdrains443 French Drains444 Deep Drainage Wells449 Precast Concrete Drainage Products

I

Page 171: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Drainage wells for roadway drainage applications are used infrequently; project specific technical specifications will be required.

For Roadway or Landscaping- irrigation operations, refer to the 730 items.

171

Selecting Pay Items400s

425 Inlets, Manholes, and Junction Boxes430 Pipe Culvers and Storm Sewers431 Pipe Liner435 Plate Pipe & Arch Culverts436 Trench Drains440 Underdrains443 French Drains444 Deep Drainage Wells449 Precast Concrete Drainage Products

I

Page 172: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 449 details requirements for precast concrete drainage products. Payment is incidental to the various items of work, under other sections.

172

Selecting Pay Items400s

425 Inlets, Manholes, and Junction Boxes430 Pipe Culvers and Storm Sewers431 Pipe Liner435 Plate Pipe & Arch Culverts436 Trench Drains440 Underdrains443 French Drains444 Deep Drainage Wells449 Precast Concrete Drainage Products

I

Page 173: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Precast items described in sections 450, 451, and 451 should be coordinated with the design standards. Note that pay item guidance is provided in the instructions for design standards, according to the applicable index.

173

Selecting Pay Items400s

450 Precast Prestressed Concrete Construction451 Prestressed Soil Anchors452 Precast Segmental Bridge Construction

I

Page 174: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Separate payment for soil anchors is only for permanent applications.

Payment for anchors used with temporary walls is included in the price of the temporary wall.

174

Selecting Pay Items400s

450 Precast Prestressed Concrete Construction451 Prestressed Soil Anchors452 Precast Segmental Bridge Construction

I

Page 175: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The 452 pay item is intended to cover the set-up costs for a segmental casting yard. It is required for all Segmental Bridge projects. Coordinate with the District Structures Design Office, as needed, with this item.

175

Selecting Pay Items400s

450 Precast Prestressed Concrete Construction451 Prestressed Soil Anchors452 Precast Segmental Bridge Construction

I

Page 176: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Per the specification, “this Section applies to precast segmental structures with multiple shear joints in webs and joints with suitable shear keys in precast substructure segments.”

There is no separate payment for the work completed under this section; it is included under the precast item(s).

176

Selecting Pay Items400s

453 Epoxy Joints- Precast Segment455 Structures Foundations457 Integral Pile Jackets458 Bridge Deck Joints459 Bitumen Coating and Polyethylene Sheeting on Concrete Piles

I

Page 177: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 455 is an extensive section dealing with piling, drilled shafts, spread footings, and auger cast piles.

Note that foundations for some lighting and mast arm structures are required to meet the foundation requirements of Section 455. However, no separate payment is made for the foundation; payment is incidental to the item being installed.

177

Selecting Pay Items400s

453 Epoxy Joints- Precast Segment455 Structures Foundations457 Integral Pile Jackets458 Bridge Deck Joints459 Bitumen Coating and Polyethylene Sheeting on Concrete Piles

I

Page 178: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

CSL tubes: While Crosshole Song Logging tubes are placed in all drilled shafts, the CLS testing pay item is only used for non-redundant bridges structures, for drilled shafts identified in the plans. The CSL testing pay item is NOT used for miscellaneous structures such as mast arms or high mast lighting.

Refer to the BOE or specification for details on additional testing, when defects are suspected.

178

Selecting Pay Items400s

453 Epoxy Joints- Precast Segment455 Structures Foundations457 Integral Pile Jackets458 Bridge Deck Joints459 Bitumen Coating and Polyethylene Sheeting on Concrete Piles

I

Page 179: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Integral pile jackets are used to protect piles in extreme environments. Due to the variable conditions, coordination with the State Materials Office is recommended during early plans development.

The pay items are normally used for rehabilitation projects. Corrosion experts in the State Materials Office will assist with the appropriate pay item number(s).

179

Selecting Pay Items400s

453 Epoxy Joints- Precast Segment455 Structures Foundations457 Integral Pile Jackets458 Bridge Deck Joints459 Bitumen Coating and Polyethylene Sheeting on Concrete Piles

I

Page 180: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

There are several types of bridge joints described in the 458 specification, including poured- with and without backer rod, and strip seals.

Additional types of products are available, but will require Technical Special Provisions for both the material and installation requirements.

All items should be used in accordance with the design standards.

180

Selecting Pay Items400s

453 Epoxy Joints- Precast Segment455 Structures Foundations457 Integral Pile Jackets458 Bridge Deck Joints459 Bitumen Coating and Polyethylene Sheeting on Concrete Piles

I

Page 181: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Guidance on the use of this item is included in the Soils and Foundations Handbook.

Note that the area for payment of polyethylene sheeting is based on the area of the pile wrapped, not the quantity of material applied (area x layers).

181

Selecting Pay Items400s

453 Epoxy Joints- Precast Segment455 Structures Foundations457 Integral Pile Jackets458 Bridge Deck Joints459 Bitumen Coating and Polyethylene Sheeting on Concrete Piles

I

Page 182: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The 500s include a wide range of incidental construction.

Sections include filter fabric, …

182

Selecting Pay Items500s

502 Shear Connectors504 Steel Grid Floors506 Bridge Drainage System510 Navigation Lights- Fixed bridges514 Plastic Filter Fabric

I

Page 183: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

barriers, sidewalk, curbs, …

183

Selecting Pay Items500s

520 Gutter, Curb, Traffic Separator521 Barriers, Railing, Parapets522 Sidewalk523 Patterned/Textured Pavement524 Ditch & Slope Pavement525 Asphalt Curb526 Architectural Pavers527 Detectable Warnings

I

Page 184: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

sound barriers, guardrail, retaining walls, fencing, …

184

Selecting Pay Items500s

530 Riprap534 Sound Barriers536 Guardrail538 Resetting Guardrail540 High Tension Cable Barrier544 Crash Cushions546 Rumble Strips548 Retaining Wall Systems550 Fencing

I

Page 185: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

conduit installation, painting, coatings,…

185

Selecting Pay Items500s

555 Directional Bore556 Jack & Bore557 Vibratory Plowing560 Painting Structural Steel561 Painting Structural Steel- Rehab562 Galvanized Surfaces563 Anti-Graffiti Coating Systems

I

Page 186: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

turf, and landscape.

186

Selecting Pay Items500s

570 Performance Turf571 Plastic Erosion Mat580 Landscape Installation

I

Page 187: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Looking now at the individual sections within the 500s…

Section 502 details the requirements for shear connectors.

No separate payment is made for the 502 work; payment is incidental to Section 460 structural steel.

187

Selecting Pay Items500s

502 Shear Connectors504 Steel Grid Floors506 Bridge Drainage System510 Navigation Lights- Fixed bridges514 Plastic Filter Fabric

I

Page 188: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Steel grid floors are used for roadway and sidewalk floors on the movable spans of bridges.

Payment for the steel grid floors is made per square foot of the plan quantity area, and includes paint, filling (as called for in the plans), and welding.

188

Selecting Pay Items500s

502 Shear Connectors504 Steel Grid Floors506 Bridge Drainage System510 Navigation Lights- Fixed bridges514 Plastic Filter Fabric

I

Page 189: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Bridge drainage systems are paid per length of pipes and number of drains. All material requirements must be included in the plans or specifications.

The bridge drainage system is currently paid per drain, as well as the length of drainage piping.

As necessary, coordinate with the District or State Drainage Office for drainage requirements.

189

Selecting Pay Items500s

502 Shear Connectors504 Steel Grid Floors506 Bridge Drainage System510 Navigation Lights- Fixed bridges514 Plastic Filter Fabric

I

Page 190: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Note that Section 510 is applicable only to fixed bridges. Movable bridges should refer to Section 465.

The Navigation Light system must be completely detailed in the plans. Remember to include material requirements, as well as installation and/or performance requirements. Payment is by lump sum.

190

Selecting Pay Items500s

502 Shear Connectors504 Steel Grid Floors506 Bridge Drainage System510 Navigation Lights- Fixed bridges514 Plastic Filter Fabric

I

Page 191: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Plastic filter fabric has several different applications: drainage, stabilization, and riprap. Refer to the applicable standards and specifications to determine if separate payment is made for this item.

191

Selecting Pay Items500s

502 Shear Connectors504 Steel Grid Floors506 Bridge Drainage System510 Navigation Lights- Fixed bridges514 Plastic Filter Fabric

I

Page 192: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

All payment quantities in this section are based on the plan quantity, and include the concrete, reinforcing steel, joints, and finishing.

Refer to the Design Standards for valid types of each item.

192

Selecting Pay Items500s

520 Gutter, Curb, Traffic Separator521 Barriers, Railing, Parapets522 Sidewalk523 Patterned/Textured Pavement524 Ditch & Slope Pavement525 Asphalt Curb526 Architectural Pavers527 Detectable Warnings

I

Page 193: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Barrier walls described in Section 521 and the Design Standards are paid according to the plan quantity measurement.

Removal of barrier walls from bridges should be included in the Removal of Existing Structures pay item.

Removal of barrier walls from the roadway may be included under clearing and grubbing, or paid separately for removal, per length.

193

Selecting Pay Items500s

520 Gutter, Curb, Traffic Separator521 Barriers, Railing, Parapets522 Sidewalk523 Patterned/Textured Pavement524 Ditch & Slope Pavement525 Asphalt Curb526 Architectural Pavers527 Detectable Warnings

I

Page 194: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Sidewalks are normally installed with 4” or 6” thickness, according to the standards. The 6” sidewalk is used where driveways cross the sidewalk path.

Payment for new sidewalk includes the installation of detectable warnings at curb ramps, in accordance with Section 527.

194

Selecting Pay Items500s

520 Gutter, Curb, Traffic Separator521 Barriers, Railing, Parapets522 Sidewalk523 Patterned/Textured Pavement524 Ditch & Slope Pavement525 Asphalt Curb526 Architectural Pavers527 Detectable Warnings

I

Page 195: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Pay Items for Bus Bay/Boarding Pad and Bus Shelter Pad are also available within the Sidewalk section. Note that the Bus Bay pay item is only used for the roadway portion of a bus pad.

The Bus Shelter Pad pay item is only used when a shelter area is to be included. (Graphic request: bay, pad, and shelter, with or without bus)

For both items, remember to include concrete requirements, reinforcement, joint, and other details in the contract documents.

195

Selecting Pay Items500s

520 Gutter, Curb, Traffic Separator521 Barriers, Railing, Parapets522 Sidewalk523 Patterned/Textured Pavement524 Ditch & Slope Pavement525 Asphalt Curb526 Architectural Pavers527 Detectable Warnings

I

Page 196: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 523 details patterned / textured pavement for both concrete and asphalt applications.

Designers should refer to the latest PPM guidance prior to including this item of work on a project.

196

Selecting Pay Items500s

520 Gutter, Curb, Traffic Separator521 Barriers, Railing, Parapets522 Sidewalk523 Patterned/Textured Pavement524 Ditch & Slope Pavement525 Asphalt Curb526 Architectural Pavers527 Detectable Warnings

I

Page 197: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Ditch and slope pavement are detailed in Section 524. The work includes payment for earthwork, filter fabric, and skimmers, according to the specs and standards.

Per the specification, “The square yard quantity includes any ditch blocks with ditch or slope pavement on top.”

When concrete core ditch blocks are used without ditch or slope pavement, separate payment is made for the concrete. “The cubic yard pay item includes any ditch block within a grass or earth ditch, without other pavement on top.”

197

Selecting Pay Items500s

520 Gutter, Curb, Traffic Separator521 Barriers, Railing, Parapets522 Sidewalk523 Patterned/Textured Pavement524 Ditch & Slope Pavement525 Asphalt Curb526 Architectural Pavers527 Detectable Warnings

I

Page 198: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 525 details Asphalt Curb. Not that payment for this section is for permanent asphalt curb applications only.

Payment for temporary asphalt separator is included under Maintenance of Traffic.

198

Selecting Pay Items500s

520 Gutter, Curb, Traffic Separator521 Barriers, Railing, Parapets522 Sidewalk523 Patterned/Textured Pavement524 Ditch & Slope Pavement525 Asphalt Curb526 Architectural Pavers527 Detectable Warnings

I

Page 199: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Architectural pavers are used for both roadway and sidewalk applications. Refer to the PPM for guidance on acceptable applications for pavers.

Payment is made per area, with no deduction for manholes or utility structures within the normal area.

199

Selecting Pay Items500s

520 Gutter, Curb, Traffic Separator521 Barriers, Railing, Parapets522 Sidewalk523 Patterned/Textured Pavement524 Ditch & Slope Pavement525 Asphalt Curb526 Architectural Pavers527 Detectable Warnings

I

Page 200: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Detectable warnings are the “bumps” used to warn persons of the curb ahead. They must meet ADA requirements.

When installed on new concrete or asphalt surfaces, the detectable warning is included in the cost of the sidewalk or pedestrian walkway.

Separate payment for the detectable warnings is made only when installed on existing surfaces. Note: existing is defined as in-place prior to the contract.

200

Selecting Pay Items500s

520 Gutter, Curb, Traffic Separator521 Barriers, Railing, Parapets522 Sidewalk523 Patterned/Textured Pavement524 Ditch & Slope Pavement525 Asphalt Curb526 Architectural Pavers527 Detectable Warnings

I

Page 201: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Riprap materials are used to protect slopes from erosion. The Drainage Manual provides guidance on material selection, based on location and water flow velocity.

Measurement and payment of riprap materials varies from cubic yard measurement for sand-cement, to Ton measurement for rubble or stone. Per the specifications, the weight may be determined by railroad weight, truck weight, or barge displacement.

201

Selecting Pay Items500s

530 Riprap534 Sound Barriers536 Guardrail538 Resetting Guardrail540 High Tension Cable Barrier544 Crash Cushions546 Rumble Strips548 Retaining Wall Systems550 Fencing

I

Page 202: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 534 sound barriers are paid by plan quantity, per square foot. Measurement, per the specification, is from the top to bottom of the panel, along the length shown in the plans. The cost of the foundation is included in the payment.

Anti-graffiti or other coatings are paid separately.

202

Selecting Pay Items500s

530 Riprap534 Sound Barriers536 Guardrail538 Resetting Guardrail540 High Tension Cable Barrier544 Crash Cushions546 Rumble Strips548 Retaining Wall Systems550 Fencing

I

Page 203: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Guardrail is normally paid as a length or “run”, with separate payment for the end anchorage assembly. Refer to the design standards for limits of payment.

Posts, blocks, rubrail, nested panels, and pipe rail are included in the payment length.

Do not double the length for double face guardrail. Payment is based on the centerline length.

203

Selecting Pay Items500s

530 Riprap534 Sound Barriers536 Guardrail538 Resetting Guardrail540 High Tension Cable Barrier544 Crash Cushions546 Rumble Strips548 Retaining Wall Systems550 Fencing

I

Page 204: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

When the guardrail removal pay item is used, detail whether the materials should be stockpiled, delivered to a maintenance yard, or disposed of by the contractor.

Do not use the removal item for guardrail that is to be reset within the same project or contract. Refer to Section 538 for resetting.

204

Selecting Pay Items500s

530 Riprap534 Sound Barriers536 Guardrail538 Resetting Guardrail540 High Tension Cable Barrier544 Crash Cushions546 Rumble Strips548 Retaining Wall Systems550 Fencing

I

Page 205: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Resetting guardrail includes the removal and placement of guardrail. The contractor will provide new offset blocks and hardware.

Panels or posts damaged by the contractor will be replaced at no additional cost.

Non-salvagable or additional new panels needed will be paid per length, according to the specification.

205

Selecting Pay Items500s

530 Riprap534 Sound Barriers536 Guardrail538 Resetting Guardrail540 High Tension Cable Barrier544 Crash Cushions546 Rumble Strips548 Retaining Wall Systems550 Fencing

I

Page 206: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The specifications and standards for High Tension Cable Barrier are currently under development. Contact the monitor in the State Roadway Design Office for the latest guidance.

206

Selecting Pay Items500s

530 Riprap534 Sound Barriers536 Guardrail538 Resetting Guardrail540 High Tension Cable Barrier544 Crash Cushions546 Rumble Strips548 Retaining Wall Systems550 Fencing

I

Page 207: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Formerly called Impact Attenuators, Crash Cushions are commonly used at the approach of guardrail or concrete barrier walls. Index 430 of the Design standards provides guidance on the products available for various applications

An Optional pay item is available, subject to the limits shown on Index 430. While the designer may select a specific brand, “the reasons for restricting to a specific brand must be documented in the project design file.”

207

Selecting Pay Items500s

530 Riprap534 Sound Barriers536 Guardrail538 Resetting Guardrail540 High Tension Cable Barrier544 Crash Cushions546 Rumble Strips548 Retaining Wall Systems550 Fencing

I

Page 208: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Refer to the PPM, Vol 1, Chapter 4, for complete information on the selection of crash cushions.

208

Selecting Pay Items500s

530 Riprap534 Sound Barriers536 Guardrail538 Resetting Guardrail540 High Tension Cable Barrier544 Crash Cushions546 Rumble Strips548 Retaining Wall Systems550 Fencing

I

Page 209: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The Rumble Strips section includes both raised and ground-in types.

Raised strip sets may be either thermoplastic or asphalt, installed on the roadway or paved shoulder. Payment is made per set.

Ground-in strips are installed along the shoulder. Plan quantity payment is made per mile, excluding any bridge lengths.

209

Selecting Pay Items500s

530 Riprap534 Sound Barriers536 Guardrail538 Resetting Guardrail540 High Tension Cable Barrier544 Crash Cushions546 Rumble Strips548 Retaining Wall Systems550 Fencing

I

Page 210: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Retaining wall systems include a variety of proprietary products listed on the Qualified Products List (QPL).

Payment for these wall systems is based on the plan quantity of the wall, as described in the specifications.

Retaining wall systems are often detailed with separate component plans. The pay items should be loaded with the roadway pay items, even when attached to a structure.

210

Selecting Pay Items500s

530 Riprap534 Sound Barriers536 Guardrail538 Resetting Guardrail540 High Tension Cable Barrier544 Crash Cushions546 Rumble Strips548 Retaining Wall Systems550 Fencing

I

Page 211: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Most fencing is either Type A “wire fabric farm fence”, Type B “chain link”, or Type R “bridge fencing”.

Special Type fencing should only be used for wood or plastic “decorative” fencing. Detail material requirements in the plans or specs.

Feature options include barbed wire, full or partial enclosure, or vinyl coating. Special features need to be detailed in the specifications or plans. Material requirements may be needed in the plans or specifications.

211

Selecting Pay Items500s

530 Riprap534 Sound Barriers536 Guardrail538 Resetting Guardrail540 High Tension Cable Barrier544 Crash Cushions546 Rumble Strips548 Retaining Wall Systems550 Fencing

I

Page 212: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Directional Bore, Jack & Bore, and Vibratory Plowing are methods used to install cable and/or conduit.

Payment for Installation includes the outer conduit materials or “sleeve”, as detailed in the plans. The inner “content” is paid separately, under the appropriate items for cable and/or conduit.

212

Selecting Pay Items500s

555 Directional Bore556 Jack & Bore557 Vibratory Plowing560 Painting Structural Steel561 Painting Structural Steel- Rehab562 Galvanized Surfaces563 Anti-Graffiti Coating Systems

I

Page 213: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Sections 560 and 561 detail painting and coating requirements for structural steel.

Section 560 addresses new steel. Payment for this work is included in the price per pound for the structural steel item.

Section 561 addresses rehabilitation painting or coating of existing structural steel. Lump Sum payment includes all work detailed in the plans and specifications.

213

Selecting Pay Items500s

555 Directional Bore556 Jack & Bore557 Vibratory Plowing560 Painting Structural Steel561 Painting Structural Steel- Rehab562 Galvanized Surfaces563 Anti-Graffiti Coating Systems

I

Page 214: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 562 addresses the repair of galvanized surfaces. Payment is included in the item being treated or repaired.

214

Selecting Pay Items500s

555 Directional Bore556 Jack & Bore557 Vibratory Plowing560 Painting Structural Steel561 Painting Structural Steel- Rehab562 Galvanized Surfaces563 Anti-Graffiti Coating Systems

I

Page 215: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Anti-graffiti coating systems include both sacrificial and non-sacrificial materials. These items should be coordinated with the District Maintenance Office.

Measurement is made per square foot, based on the plan quantity of the projected area; no allowance is made for surface texture.

215

Selecting Pay Items500s

555 Directional Bore556 Jack & Bore557 Vibratory Plowing560 Painting Structural Steel561 Painting Structural Steel- Rehab562 Galvanized Surfaces563 Anti-Graffiti Coating Systems

I

Page 216: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Performance Turf includes both grassing and sodding. All mowing, watering, and other incidentals are included in the payment for turf.

While the designer may call for sod in selected locations, the contractor should be given the turf option (seed, sod, or other methods) whenever possible.

216

Selecting Pay Items500s

570 Performance Turf571 Plastic Erosion Mat580 Landscape Installation

I

Page 217: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 571 details requirements for plastic erosion mats (turf reinforcement mat), as shown in the standards, and used with Performance Turf.

Payment is made per area, with no allowance for overlaps.

Do not use this pay item for other materials or special erosion “mats”. Refer to the specs or BOE for drainage & erosion transition mats.

217

Selecting Pay Items500s

570 Performance Turf571 Plastic Erosion Mat580 Landscape Installation

I

Page 218: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Landscape work is paid as two lump sum pay items: large plants and small plants. Large plants includes trees in 7 gallon containers, or larger, and most palms. Small plants includes all other plants, as well as incidental work.

All work should be detailed in the plans, in accordance with the PPM.

218

Selecting Pay Items500s

570 Performance Turf571 Plastic Erosion Mat580 Landscape Installation

I

Page 219: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The 600s are for Traffic Control Devices.

Sections within the 600s include grounding, conduit, pull boxes,…

219

Selecting Pay Items600s

603 General Requirements608 Guaranties611 Acceptance620 Signal Installation Grounding630 Conduit632 Signal And Interconnect Cable634 Span Wire Assembly635 Pull and Junction Boxes639 Electrical Power

I

Page 220: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

… poles, signals, …

220

Selecting Pay Items600s

641 Prestressed Conc Poles649 Steel Strain Poles, Mast Arms, Monotube Assemblies650 Vehicular Signal Assemblies653 Pedestrian Signal Assemblies659 Signal Head Retrofit Auxiliaries660 Inductive Loop Detectors665 Pedestrian Detector Assembly

I

Page 221: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

… and controllers.

Note that all of the Signals specifications, min specs, standards, and pay items are currently under review. Refer to the applicable office web pages for the latest updates and implementation schedules.

221

Selecting Pay Items600s

670 Traffic Controller Assembly671 Traffic Controllers676 Controller Cabinets678 Controller Accessories690 Removal of Existing Traffic Signal Equipment699 Internally Illuminated Signs

I

Page 222: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Looking at the individual sections…

When working with Traffic Control Devices, two important sources of information become applicable:

The Minimum Specifications for Traffic Control Signal Devices (MTSCSD), otherwise known as “min specs”, provide performance and acceptance criteria.

The Approved Product List (APL) lists products that are approved for use on Florida’s roadways. Note that inclusion on the APL does not imply that FDOT has developed construction specifications, or will use the product on state roads.

222

Selecting Pay Items600s

603 General Requirements608 Guaranties611 Acceptance620 Signal Installation Grounding630 Conduit632 Signal And Interconnect Cable634 Span Wire Assembly635 Pull and Junction Boxes639 Electrical Power

I

Page 223: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

APL items are approved for use local agencies. They have met MUTCD requirements, and are acceptable for use in Florida.

Note: MUTCD is the Manual for Uniform Traffic Control Devices.

(Pronounced M-U-T-C-D)

Section 603 brings the min specs and APL into construction contracts.

223

Selecting Pay Items600s

603 General Requirements608 Guaranties611 Acceptance620 Signal Installation Grounding630 Conduit632 Signal And Interconnect Cable634 Span Wire Assembly635 Pull and Junction Boxes639 Electrical Power

I

Page 224: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Sections 608 and 611 provide basic guidance for Guaranties and Acceptance. There is no separate payment for these requirements.

224

Selecting Pay Items600s

603 General Requirements608 Guaranties611 Acceptance620 Signal Installation Grounding630 Conduit632 Signal And Interconnect Cable634 Span Wire Assembly635 Pull and Junction Boxes639 Electrical Power

I

Page 225: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The grounding section includes general requirements for protection against faults, surge currents, and lightning transients.

There is no separate payment; work is included in the item being grounded.

Note that the requirements of this specification may be referenced by lighting, signing, or other non-signals applications.

225

Selecting Pay Items600s

603 General Requirements608 Guaranties611 Acceptance620 Signal Installation Grounding630 Conduit632 Signal And Interconnect Cable634 Span Wire Assembly635 Pull and Junction Boxes639 Electrical Power

I

Page 226: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 630 provides the requirements for conduit. Note that a locate wire may be required for fiber optic installations.

For estimating quantities, if you have a 100’ trench with 4 conduits, the total length of conduit installed would be 400’. The contractor will adjust the unit bid price according to the length of trench and number of conduits.

Similarly for underpavement and jacked conduit, the total length of all conduits is recorded; the contractor will adjust bid prices when multiple conduits are run together.

226

Selecting Pay Items600s

603 General Requirements608 Guaranties611 Acceptance620 Signal Installation Grounding630 Conduit632 Signal And Interconnect Cable634 Span Wire Assembly635 Pull and Junction Boxes639 Electrical Power

I

Page 227: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Signal cable within an intersection is paid on a “per intersection” basis. While no allowance is made for large or small intersections, the contractor will bid according to the size of the intersections shown in the plans.

When signal cable is necessary outside of an intersection, such as for beacons or signs, the cable is paid per foot.

When using fiber optic cable, carefully review the available specifications. Plan Details and/or Technical Specs may be necessary.

227

Selecting Pay Items600s

603 General Requirements608 Guaranties611 Acceptance620 Signal Installation Grounding630 Conduit632 Signal And Interconnect Cable634 Span Wire Assembly635 Pull and Junction Boxes639 Electrical Power

I

Page 228: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Span Wires with concrete poles are the standard for most of the state. Coastal areas, within limits defined in the PPM, generally use mast arms.

The standard span wire assembly was updated with the 2009 PPM. Projects should be updated according to current guidance. Payment for the span wire assembly is made per intersection.

228

Selecting Pay Items600s

603 General Requirements608 Guaranties611 Acceptance620 Signal Installation Grounding630 Conduit632 Signal And Interconnect Cable634 Span Wire Assembly635 Pull and Junction Boxes639 Electrical Power

I

Page 229: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Pull and Junction boxes are paid per each. The installation requirements are shown in the Design Standards. Note that the items installed must be included on the APL.

229

Selecting Pay Items600s

603 General Requirements608 Guaranties611 Acceptance620 Signal Installation Grounding630 Conduit632 Signal And Interconnect Cable634 Span Wire Assembly635 Pull and Junction Boxes639 Electrical Power

I

Page 230: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Electrical Power Service Assemblies are used in accordance with Design Standard 17736.

Items may include conduit, wore, meter, disconnect, and other items shown in the design standards.

230

Selecting Pay Items600s

603 General Requirements608 Guaranties611 Acceptance620 Signal Installation Grounding630 Conduit632 Signal And Interconnect Cable634 Span Wire Assembly635 Pull and Junction Boxes639 Electrical Power

I

Page 231: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Prestressed Concrete Poles for signals applications are shown on index 17725. The poles installed must be listed on the QPL.

Note that the type of pole is included in the pay item description, but plan details are necessary to indicate the pole length and mounting height.

231

Selecting Pay Items600s

641 Prestressed Conc Poles649 Steel Strain Poles, Mast Arms, Monotube Assemblies650 Vehicular Signal Assemblies653 Pedestrian Signal Assemblies659 Signal Head Retrofit Auxiliaries660 Inductive Loop Detectors663 Vehicle Detector Assemblies665 Pedestrian Detector Assembly

I

Page 232: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Refer to the current PPM for guidance on mast arm installations. Generally, these will only be used in coastal areas.

The pay item structure details the design wind speed and arm length.

When using steel strain poles, plan details are needed for pole type and height.

Monotube Assemblies are not included in the design standards; complete design details are required in the plans.

232

Selecting Pay Items600s

641 Prestressed Conc Poles649 Steel Strain Poles, Mast Arms, Monotube Assemblies650 Vehicular Signal Assemblies653 Pedestrian Signal Assemblies659 Signal Head Retrofit Auxiliaries660 Inductive Loop Detectors663 Vehicle Detector Assemblies665 Pedestrian Detector Assembly

I

Page 233: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Traffic Signal assemblies include the signal with LED indicators, backplates, visors, and all incidentals to complete the signal assembly.

Note that these assemblies are to be used for permanent installations only; temporary installations should use the appropriate Maintenance of Traffic items in Section 102.

233

Selecting Pay Items600s

641 Prestressed Conc Poles649 Steel Strain Poles, Mast Arms, Monotube Assemblies650 Vehicular Signal Assemblies653 Pedestrian Signal Assemblies659 Signal Head Retrofit Auxiliaries660 Inductive Loop Detectors663 Vehicle Detector Assemblies665 Pedestrian Detector Assembly

I

Page 234: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Pedestrian Signal Assemblies allow for various types. Note that the LED Countdown is the current standard.

234

Selecting Pay Items600s

641 Prestressed Conc Poles649 Steel Strain Poles, Mast Arms, Monotube Assemblies650 Vehicular Signal Assemblies653 Pedestrian Signal Assemblies659 Signal Head Retrofit Auxiliaries660 Inductive Loop Detectors663 Vehicle Detector Assemblies665 Pedestrian Detector Assembly

I

Page 235: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The 659 pay items are used only for retrofit applications. On new installations, all backplates, visors, and attachment hardware is included in the signal head assembly.

235

Selecting Pay Items600s

641 Prestressed Conc Poles649 Steel Strain Poles, Mast Arms, Monotube Assemblies650 Vehicular Signal Assemblies653 Pedestrian Signal Assemblies659 Signal Head Retrofit Auxiliaries660 Inductive Loop Detectors663 Vehicle Detector Assemblies665 Pedestrian Detector Assembly

I

Page 236: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 660 currently describes various types of loop detectors. As additional types of vehicle detection are approved, the contents of this section may be incorporated with Section 663 for Vehicle Detector Assemblies.

Refer to the latest specifications and design standards for detector requirements.

236

Selecting Pay Items600s

641 Prestressed Conc Poles649 Steel Strain Poles, Mast Arms, Monotube Assemblies650 Vehicular Signal Assemblies653 Pedestrian Signal Assemblies659 Signal Head Retrofit Auxiliaries660 Inductive Loop Detectors663 Vehicle Detector Assemblies665 Pedestrian Detector Assembly

I

Page 237: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Pedestrian Detectors include both standard and accessible types. Refer to the Traffic Engineering Manual for assistance with determining the appropriate type for project conditions.

237

Selecting Pay Items600s

641 Prestressed Conc Poles649 Steel Strain Poles, Mast Arms, Monotube Assemblies650 Vehicular Signal Assemblies653 Pedestrian Signal Assemblies659 Signal Head Retrofit Auxiliaries660 Inductive Loop Detectors663 Vehicle Detector Assemblies665 Pedestrian Detector Assembly

I

Page 238: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The 670 group of items includes controllers and cabinets. Coordinate with the District Traffic Engineering & Operations office to ensure that the proposed equipment is compatible with the local agency.

238

Selecting Pay Items600s

670 Traffic Controller Assembly671 Traffic Controllers676 Controller Cabinets678 Controller Accessories

I

Page 239: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Section 690, Removal of Existing Traffic Signal Equipment: Per the specifications, “The Department retains ownership of the equipment removed unless otherwise state in the Contract Documents.

As necessary, the plans should indicate the location for delivery of removed signal equipment.

239

Selecting Pay Items600s

690 Removal of Existing Traffic Signal Equipment699 Internally Illuminated Signs

I

Page 240: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

While the 699 Internally Illuminated Signs are “signs”, they are normally included with the signals category, due to their connections with the signalized intersections.

These signs should be tabulated and detailed in the Signalization plans and category.

240

Selecting Pay Items600s

690 Removal of Existing Traffic Signal Equipment699 Internally Illuminated Signs

I

Page 241: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The 700s are for Traffic Control: Signing & Pavement Markings, …

241

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 242: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The 700s are for Traffic Control: Signing & Pavement Markings, Lighting, Monitoring, and ITS.

242

Selecting Pay Items700s

714 Motorist Aid Call Boxes715 Highway Lighting741-747 Traffic Monitoring Site750-751 Architectural Work780-786 Intelligent Transportation System (ITS)

I

Page 243: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Highway Signing covers both roadside and overhead signs.

For single and multi-post sign assemblies, refer to the standards for the appropriate sizes.

Payment includes the sign(s) and post(s), furnished and installed.

For lighted signs, payment includes electrical work.

243

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 244: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

For overhead signs, the pay items separate the operation, span length, and sign size.

As for all signs, foundations and electrical work are included in the sign assembly payment.

Monotube assemblies require complete specifications, drawings, and details. Coordinate with the maintaining agency, as standard sign structures may be preferred.

244

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 245: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Measurement and Payment of Stripes and Pavement Markings:

•Longitudinal Stripe (along direction of traffic) is paid per net mile (solid) or gross mile (skip).

•Transverse Stripe (across the direction of traffic) is paid per foot.

•Dotted, Guidelines, and 6-10 Gap Extension lines are paid per foot.

Refer to the BOE for complete measurement and payment details.

245

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 246: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Refer to the PPM, vol 1, 7.2.8 for guidance on selecting pavement marking materials.

Did you know- the arrows, symbols and messages are paid separately?

show pavement arrows? Arrows are paid as a complete marking, regardless of the number of “points” or directions on the marking.

246

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 247: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Show bike lane arrow and “bicycle person” symbol.

The cyclist is available as a preformed thermoplastic material, and should be 6’ tall, to meet current standards.

Show bicycle with chevron message The new “bicycle with chevron” is one message.

Show sun pass lane/message Each word is paid as a separate message- “SUN PASS ONLY” would be paid as 3 messages.

Other symbols and messages are shown on the design standards.

247

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 248: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Audible and Vibratory marking have specific applications, as directed “for rural construction projects, excluding limited access facilities.”

Refer to the BOE or PPM for additional guidance.

248

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 249: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Object Markers are used to mark obstructions within or adjacent to the roadway; delineators are used to indicate the alignment of the roadway. Both are to be used in accordance with the design standards and the MUTCD.

No separate payment is made for object markers mounted on vehicular impact attenuators, according to Section 544.

249

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 250: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Raised Retro-Reflective Pavement Markers (RPMs) are used to supplement pavement markings. Refer to the standards for correct usage.

250

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 251: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Two Reactive component pavement marking is used on concrete surfaces, as described in the PPM, vol 1, 7.2.8.

251

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 252: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Painted traffic marking materials are used in both MOT and final surface applications.

252

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 253: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Thermoplastic markings are used as “the Department’s primary material to be used for permanent markings on asphalt surfaces.”

– PPM, vol 1, 7.2.8

Some Districts will apply thermoplastic during construction operations, in lieu of a final surface paint. The remaining Districts will apply thermoplastic under a maintenance contract, following the completion of construction contract. Coordinate with your District Design Office for current district policy.

253

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 254: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Permanent Tape is an option for use on concrete surfaces.

High performance tapes are required for longitudinal markings; standard tapes are limited to transverse lines, arrows, and messages.

254

Selecting Pay Items700s

700 Highway Signing701 Audible and Vibratory Markings705 Object Markers & Delineators706 Reflective Pavement Markers709 Traffic Stripes- Two Reactive Components710 Painted Traffic Markings711 Thermoplastic Traffic Stripes and Markings713 Permanent Tape Stripes and Markings

I

Page 255: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Motorist aid call boxes are still used along the Turnpike and selected major roadways.

Note that the call box pad is included in the payment for the complete call box installation.

When replacing/upgrading the pad, “modify”, don’t forget to detail the removal, storage, and reinstallation of the call box assembly. Damaged boxes must be replaced by the contractor, at no additional cost.

255

Selecting Pay Items700s

714 Motorist Aid Call Boxes715 Highway Lighting741-747 Traffic Monitoring Site750-751 Architectural Work780-786 Intelligent Transportation System (ITS)

I

Page 256: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Most lighting installations are “furnish and install” for a complete installation. The foundation is included in the cost of the pole, even for high mast pole installations that require more extensive foundations.

Conduit is paid as the length from point A to B, with no additional quantity for sweeps or vertical distances. Note- when multiple conduits are included in a trench, payment is based on the total length of conduit, not the length of the trench.

For example: 4 conduits in a 100 foot trench = 400 total feet of conduit.

256

Selecting Pay Items700s

714 Motorist Aid Call Boxes715 Highway Lighting741-747 Traffic Monitoring Site750-751 Architectural Work780-786 Intelligent Transportation System (ITS)

I

Page 257: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Coordinate the use of the Traffic Monitoring Site specifications and pay items with the responsible office. Technical specifications may be required.

257

Selecting Pay Items700s

714 Motorist Aid Call Boxes715 Highway Lighting741-747 Traffic Monitoring Site750-751 Architectural Work780-786 Intelligent Transportation System (ITS)

I

Page 258: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Architectural pay item should only be used with “significant” architectural work. Coordinate the use of these items with the State Architect.

New or Rehab work on a complete building is paid under Section 750. Component work only, i.e. water, HVAC, communications, or electrical, may be paid under the appropriate 751 items. Do not use the 751 items when complete work is paid under the 750 item.

258

Selecting Pay Items700s

714 Motorist Aid Call Boxes715 Highway Lighting741-747 Traffic Monitoring Site750-751 Architectural Work780-786 Intelligent Transportation System (ITS)

I

Page 259: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

When asbestos is known to exist, contact the Architectural Section for specific guidance. Special contracts exist for asbestos removal.

Refer to Section 465 for Bridge Tender House. Coordinate with the Moveable Bridge Section of the State Structures Design Office.

259

Selecting Pay Items700s

714 Motorist Aid Call Boxes715 Highway Lighting741-747 Traffic Monitoring Site750-751 Architectural Work780-786 Intelligent Transportation System (ITS)

I

Page 260: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

ITS, or Intelligent Transportation Systems incorporate several types of vehicle detection to help traffic move efficiently.

Some ITS systems are incorporated into local signalization systems, and may be designed into the signalization plans.

Design guidance is provided in the PPM, Vol. 1, Chapter 7.

Revisions are currently underway to “merge” ITS and signalization specifications and pay items. Refer to the specifications and BOE for the latest information.

260

Selecting Pay Items700s

714 Motorist Aid Call Boxes715 Highway Lighting741-747 Traffic Monitoring Site750-751 Architectural Work780-786 Intelligent Transportation System (ITS)

I

Page 261: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

When possible, pay items for ITS components were specified for “complete assemblies”. For example, the Dynamic Message Sign (DMS) includes the sign, structure, foundation, electronics, and testing for a fully operational sign.

Refer to the specifications for work and materials included with each pay item.

261

Selecting Pay Items700s

714 Motorist Aid Call Boxes715 Highway Lighting741-747 Traffic Monitoring Site750-751 Architectural Work780-786 Intelligent Transportation System (ITS)

I

Page 262: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The mass transit items currently have very limited use. If your project involves mass transit, please coordinate with your District Estimates Office to further develop this group of items.

262

Selecting Pay Items800s

I

Page 263: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The 900s are a special group of items. They may involve new or different contracting rules, specifications, or other situations.

263

Selecting Pay Items900s

Developmental, Monitored, Limited use, or other Special Pay Items999- 2 Lump Sum Contract999- 16 Partnering999- 20 Disputes Review Board999- 25 Initial Contingency Amt999-102 Speed and Law Enforcement Officer

I

Page 264: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

When a specification is under development, a pay item may be assigned using a 9xx-SSS-### format, where xx is the year, SSS is the proposed specification section number, and ### is a sequential number to define any additional description. It is not necessary to completely define an “abc-def” pay item structure while the specification is under development.

For developmental, monitored or limited use items, a monitor from the responsible office (structures, drainage, etc.) will

264

Selecting Pay Items900s

Developmental, Monitored, Limited use, or other Special Pay Items999- 2 Lump Sum Contract999- 16 Partnering999- 20 Disputes Review Board999- 25 Initial Contingency Amt999-102 Speed and Law Enforcement Officer

I

Page 265: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Lump Sum contracts are frequently used for small contracts with known quantities, where minimal adjustments are anticipated. A “duplicate” project is maintained with pay items and quantities for estimating and reporting purposes.

265

Selecting Pay Items900s

Developmental, Monitored, Limited use, or other Special Pay Items999- 2 Lump Sum Contract999- 16 Partnering999- 20 Disputes Review Board999- 25 Initial Contingency Amt999-102 Speed and Law Enforcement Officer

I

Page 266: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

When partnering is recommended by the construction office, a lump sum amount is included with the contract to provide for meeting rooms, facilitator fees, and travel expenses of the facilitator.

When this item is used, District Specifications Office should coordinate with the Contracts Administration Office.

266

Selecting Pay Items900s

Developmental, Monitored, Limited use, or other Special Pay Items999- 2 Lump Sum Contract999- 16 Partnering999- 20 Disputes Review Board999- 25 Initial Contingency Amt999-102 Speed and Law Enforcement Officer

I

Page 267: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

There are several specifications available for a Disputes Review Board, depending on project conditions. The construction office should determine whether a Regional or Statewide Disputes Review Board is recommended.

The goal of the Disputes Review Board is to resolve project issues, before costly legal action becomes necessary.

267

Selecting Pay Items900s

Developmental, Monitored, Limited use, or other Special Pay Items999- 2 Lump Sum Contract999- 16 Partnering999- 20 Disputes Review Board999- 25 Initial Contingency Amt999-102 Speed and Law Enforcement Officer

I

Page 268: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The initial contingency amount is determined by construction, in accordance with the CPAM.

While this is a non-bid item, it allows the construction office to encumber funds for unforeseen work and supplemental agreements.

268

Selecting Pay Items900s

Developmental, Monitored, Limited use, or other Special Pay Items999- 2 Lump Sum Contract999- 16 Partnering999- 20 Disputes Review Board999- 25 Initial Contingency Amt999-102 Speed and Law Enforcement Officer

I

Page 269: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

The Speed and Law Enforcement Officer is a non-bid pay item used where active law enforcement is necessary. The funds included with this pay item are used for contracts between the department and state or local law enforcement. This pay item is used at the discretion of the Engineer, and not for the Contractor’s operations.

Refer to the Maintenance of Traffic pay item when a Traffic Control Officer is needed for controlling signalized intersections, traffic pacing, or other actions detailed in the design standards.

269

Selecting Pay Items900s

Developmental, Monitored, Limited use, or other Special Pay Items999- 2 Lump Sum Contract999- 16 Partnering999- 20 Disputes Review Board999- 25 Initial Contingency Amt999-102 Speed and Law Enforcement Officer

I

Page 270: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Pay Items within the 1000-1999 range are for use on Utility JPA projects only.

Common use utility items, such as pipe and fittings, are included in sections 1000-1099.

Other utility applications are:

1500s Sanitary Sewer

1600s Water Main

1700s Power Transmission

1800s Communications

1900s Fuel Transmission

270

Selecting Pay Items1000s

1000 Utility Work, LS1050 Utility Pipe1055 Utility Fittings1060 Utility Structures1080 Utility Fixtures1135 Guys and Anchors1501 Lift Station- Sanitary Sewer1644 Fire Hydrant1720 Transformer1820 Telephone/Communications

I

Page 271: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

All of the utility items will require Technical Special Provisions and/or plan details to cover the description, materials, installation, measurement, and payment information.

Note that historical costs for utility items vary widely, due to project-by-project requirements and specifications.

271

Selecting Pay Items1000s

1000 Utility Work, LS1050 Utility Pipe1055 Utility Fittings1060 Utility Structures1080 Utility Fixtures1135 Guys and Anchors1501 Lift Station- Sanitary Sewer1644 Fire Hydrant1720 Transformer1820 Telephone/Communications

I

Page 272: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Generic Items are “intended to support one-time usage pay items or specialty situations where a standard pay item is not available, and for which it is not practical to create a new pay item.”

While these pay items are readily available, there are no specifications, plan details, or cost history available.

Complete rules for these items are included in Chapter 6. Here is a brief summary of the rules: Must not be used if there is an existing pay item. Must not be used to violate or circumvent standard pay items.

272

Selecting Pay ItemsGeneric Items

000-AAA-BBB

000-100-BBB Structures000-200-BBB Roadway000-300-BBB Signing/Pavement Marking000-400-BBB Lighting000-500-BBB Signals/ITS000-600-BBB Landscaping

I

Page 273: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Must not be used to circumvent the approval process on developmental items. Must not be used as a work-around for a pay item that has been rejected for statewide usage by Central Office. Must not to be used for sole-sourcing of materials/ methods for items of work.

Coordination with the responsible office (Roadway, Structures, Traffic Ops, etc.) is recommended, as similar requests from multiple districts may encourage development of specs, standards, and/or pay items.

273

Selecting Pay ItemsGeneric Items

000-AAA-BBB

000-100-BBB Structures000-200-BBB Roadway000-300-BBB Signing/Pavement Marking000-400-BBB Lighting000-500-BBB Signals/ITS000-600-BBB Landscaping

I

Page 274: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

Generic Pay Items are formatted as 000-AAA-BBB, where

AAA is the Design Group/Trns•port Category (100 for Structures, 200 for Roadway, etc.), and

BBB is the Sequential Number that can be re-used.

For all generic pay items, the unit of measure is shown as “ZZ”. Within the supplemental description, the Estimator provides a brief description of the work and unit of measure.

274

Selecting Pay ItemsGeneric Items

000-AAA-BBB

000-100-BBB Structures000-200-BBB Roadway000-300-BBB Signing/Pavement Marking000-400-BBB Lighting000-500-BBB Signals/ITS000-600-BBB Landscaping

I

Page 275: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 2

As an example, a Roadway “Widget” using a Generic Pay Item might be shown as:

000-200- 1 Roadway Design Group- Generic Pay Item 1 (Widget, each)

Complete specs and/or details are required for each item. Load the generic pay item into the corresponding Trnsport category.

275

Selecting Pay ItemsGeneric Items

000-AAA-BBB

000-100-BBB Structures000-200-BBB Roadway000-300-BBB Signing/Pavement Marking000-400-BBB Lighting000-500-BBB Signals/ITS000-600-BBB Landscaping

I

Page 276: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates

This concludes this part.

If you would like to view additional material, please select the Part you would like to view.

276

Part 1: Introduction to the Basis of Estimates

Part 2: Selecting Pay Items

Part 3: Estimating and Review

I

Page 277: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates

Please select the Part you would like to view.

277

Part 1: Introduction to the Basis of Estimates

Part 2: Selecting Pay Items

Part 3: Estimating and Review

I

Page 278: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates

This concludes this part.

If you would like to view additional material, please select the Part you would like to view.

278

Part 1: Introduction to the Basis of Estimates

Part 2: Selecting Pay Items

Part 3: Estimating and Review

I

Page 279: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates

Please select the Part you would like to view.

279

Part 1: Introduction to the Basis of Estimates

Part 2: Selecting Pay Items

Part 3: Estimating and Review

I

Page 280: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Part 3 of this CBT is intended for reviewers- both consultant and FDOT.

It is organized into 3 sections- Updates, General Conditions, and Categories & Pay Items.

This Part of the CBT is dependent upon users sharing experiences with others. Please send your comments to [email protected]

Thank you for your help.

280

Part 3- Estimating and ReviewUpdatesGeneral ConditionsCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 281: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Updates: Includes major changes to the specifications, standards, pay items, and related handbooks or manuals.

General Conditions: Includes general information for estimates reviews.

Categories & Pay Items: Estimating and Review issues, by category

Please select a section to proceed.

281

Part 3- Estimating and ReviewUpdatesGeneral ConditionsCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 282: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Updates are normally implemented for either the January or July letting. Specifications, standards, and/or pay items will be coordinated for these letting dates.

Do not implement changes before/after these scheduled dates, without approval of the responsible office, as some “pieces” of an issue may be tied to implementation dates. For example, an “old” specification may refer to an “old” standard and valid QPL items. The “new” specification and standard will be implemented together, with “new” qualified products to meet the new requirements.

282

Part 3- Estimating and ReviewUpdates

Basis of EstimatesSpecificationsDesign Standards and InstructionsPlans Preparation ManualStructures Manual

Florida GreenbookPavement Design Manual

I

Page 283: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

When beginning reviews for January or July letting projects, ensure that you have the latest updates.

All estimators and reviewers should be registered for the Contact Database to receive updates from the Estimates, Roadway, and Structures Design offices. Several other offices also use the Contact Database to keep users informed of bulletins, revisions, and other important information.

283

Part 3- Estimating and ReviewUpdates

Basis of EstimatesSpecificationsDesign Standards and InstructionsPlans Preparation ManualStructures Manual

Florida GreenbookPavement Design Manual

I

Page 284: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

If a project letting date is changed, the plans, specifications, and pay items should be completely reviewed for compliance with the appropriate updates.

284

Part 3- Estimating and ReviewUpdates

Basis of EstimatesSpecificationsDesign Standards and InstructionsPlans Preparation ManualStructures Manual

Florida GreenbookPavement Design Manual

I

Page 285: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

General Conditions

Estimating and review varies by project, depending on many factors. This section will help to address these factors, providing some guidance for consultant and FDOT estimators.

285

Part 3- Estimating and ReviewUpdatesGeneral ConditionsCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 286: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

The general conditions or factors affecting an estimate include Historical Cost, Project Conditions, Incidentals, Quantity, Operation, and Specifications.

These factors are not in order of significance. They may vary from project-to-project, or even item-to-item.

286

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 287: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Frequently used items have historical costs available. The estimator should consider the number of contracts, as well as the “normal” use of the pay item.

Historical costs should not be used for “special” or unusual situations, or those with limited cost history.

The Item Average Unit Cost report or the LRE Reference Price are good sources for historical costs.

287

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 288: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Project Conditions affect prices in many ways.

Location- Haul distances, near or far, may affect the price of asphalt and concrete products.

Rural/Urban- Traffic conditions may affect production rates, as well as MOT and incidental costs.

Night Work or Limited lane closures- Restrictions may affect the time or locations available for work, increasing labor costs.

Seasons- While Florida does not experience significant snow or frozen ground, spring break and athletic events may impact some projects with increased MOT costs.

288

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 289: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

The Trnsport CES module, available only to FDOT Estimators, uses various project conditions within the regression models. These include county, season, work type, and rural/urban location.

Engineering experience and knowledge of local traffic conditions may be the best tool for considering project conditions.

289

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 290: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Most items of work call for the contractor to “furnish and install”, for a complete and accepted item of work.

Normal incidentals, i.e. hardware or coatings, are detailed in the standards or specifications.

When the designer calls for additional items of work to be included in an item of work, these incidentals generally increase bid prices. Significant changes should be addressed with separate or “special” payment.

290

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 291: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Price decreases with increased quantity?

In general, larger quantities yield better unit prices, as the equipment and set-up costs associated with an item are distributed over a larger quantity. Unit prices stabilize when materials and labor become the significant factors.

291

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 292: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Installed cost=Materials + Equipment+ Labor

Unit price on small quantities is normally higher, due to equipment set-up or labor costs.

292

Price vs. Quantity

District XDistrict YDistrict Z

Quantity

$

I

Page 293: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

The Trnsport CES module is an excellent tool for pricing items based on quantity. Regression models will provide price vs quantity graphs, as needed. These graphs are also helpful for identifying when price varies by district or market area.

Unfortunately, the regression models only work when historical data is available. For infrequently used items with minimal history, other estimating tools must be used.

293

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 294: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

While the normal operation of work is to “furnish and Install”, it is possible to have other operations:

Install, relocate, Adjust, Modify, Remove, Dispose, Stockpile, or Place Out of Service.

The contract documents should be carefully reviewed to ensure that these operations are clearly defined. Most of these operations will require a plan detail and/or Tech Spec.

Don’t “break out” payment for separate operations or incidental work. For example, do not separate foundation work for lighting, signing, signals or ITS poles.

294

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 295: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

EXAMPLE: bubble or other stand-out graphic?

Items should be stockpiled only when the District Maintenance or maintaining agency requests the item.

For example, electrical conductor has a salvage value. The contractor will factor this amount into the bid for removal of the conductor.

FDOT is not in the “scrap metals business”. Do not stockpile conductor, unless specifically requested.

295

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 296: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

The Designer should ensure that EVERY ITEM OF WORK has complete information:

Description, either in words or plan detail drawing

Material Requirements, including maintenance or replacement requirements during construction

Construction or Installation requirements

Method of Measurement

Basis of Payment

296

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 297: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Ensure that the plans (sheets, standards), specs (special provisions, supplemental specifications, Tech Specs), and pay items agree.

Any conflicts could result in supplemental agreements.

297

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 298: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Most design should be completed in accordance with the existing standards and specifications. Minor changes can be completed with approved modifications.

If the existing specification does not apply, coordinate with the District Specifications staff.

If the spec does not apply, then the pay item likely does not apply; coordinate with the District Estimates staff.

298

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 299: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Why did they do that?

Standard or Special?

Incidental or Separate?

LF or Each?

There are many ways to design. While FDOT provides many standards, there are situations were non-standard is chosen.

Understanding “why” a non-standard choice was made will improve the estimate or review process. It is the responsibility of the estimator & reviewer to determine which items will affect the contractor’s work and price.

299

Part 3- Estimating and ReviewGeneral Conditions

•Historical Cost•Project Conditions•Incidentals•Quantity•Operations•Specs, Notes, details

I

Page 300: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Categories & Pay Items

This section is set-up to review estimate and pay item issues, by category.

Additional information may be available, by pay item section, in part 2 of the CBT.

With each category or component plans, the reviewer should ensure that the items shown on the plans correspond with the tabulation sheets and summary of quantities.

300

Part 3- Estimating and ReviewUpdatesGeneral ConditionsCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 301: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Select a Category, or enter to continue.

301

Part 3- Estimating and ReviewUpdatesGeneral ConditionsCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 302: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

The structures category header is of significant importance to the estimator, as this information is used for FHWA and FDOT reporting.

At a minimum, the estimator should verify that the Project Edit Report structures header information is correct. Run this report with EVERY review submittal.

If any of the Work Program fields are incorrect, notify the Project Manager and/or District Work Program Office to make corrections.

302

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 303: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Verify that the length, width, and other category information is correct. For bridge widening, only the widened width is entered; do not include the existing or new total width.

Bridge Graphic?:

New/Replacement bridges- use the total length and outside-to-outside width

Widened bridges- use the total length and only the widened width (usually 1 or 2 lanes added to outside)

Bridge Repairs- use the total length and out-to-out width

For variable width bridges, enter the average width, so that the length*width total will equal the total bridge area.

303

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 304: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Graphic: Parallel (northbound/southbound) side-by-side bridges

While parallel bridges are often designed together, it is important to load each bridge in a separate category, so that the bridge number, dimensions, quantities, and payments can be made correctly.

Retaining Wall pay items are loaded in the roadway category, even when they are located at the bridge abutment.

304

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 305: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

If there is minimal roadway or other work, it is possible to have only structures plans. When this occurs, Mobilization, MOT, initial contingency, and other incidental items may appear in the structures category.

The bridge report will separate the “true bridge costs” from the miscellaneous or “incidental” bridge costs.

305

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 306: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Roadway

The roadway plans cover a wide range of activities. Some of the most common

306

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 307: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Miscellaneous Concrete, Items 400-1-15, 400-2-15, etc.

Prior to July 2009, 5 CY of Misc Concrete was included on most projects, for use as directed by the Engineer. It was used primarily around pull & junction boxes, light poles, etc.

After July 1, 2009, no separate payment is made for miscellaneous concrete. The work and materials are incidental to the item being installed- box, pole, etc.

Watch for old plan notes referencing these pay items; they should be removed.

307

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 308: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

524 Ditch and Slope Pavement

Ditch Blocks: included in SY price for ditch pavement. Paid separately (CY) only when there is no ditch or slope pavement

308

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 309: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Signing & Pavement Marking

Specifications for pavement markings continue to change as new materials become available. Some materials, such as Audible and Vibratory Pavement Markings, are intended only for outside longitudinal stripes. Other products may be limited to undivided rural roads. The Designer should follow PPM guidance for selection of pavement markings.

309

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 310: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Signing & Pavement Marking

Directional Arrows: Several years ago, separate pay items existed for single, double, and triple point arrows. When pay items were restructured, payment was changed to “arrows”, per each. The intent was for each arrow, regardless of the number of points.

310

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 311: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Lighting

Light Poles complete: Both standard highway and high mast lighting include everything from the luminaire to the foundation; they are complete. No separate payment is made for drilled shafts, excavation, or other incidentals.

Light Poles, Special Design should only be used when the design standards do not apply. Decorative, historical, and unique designs are common uses for Special Design light poles.

311

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 312: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Conduit: Conduit is paid as the length from point A to B, with no additional quantity for sweeps or vertical distances. Note- when multiple conduits are included in a trench, payment is based on the total length of conduit, not the length of the trench.

For example: 4 conduits in a 100 foot trench = 400 total feet of conduit.

312

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 313: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Signals

Mast Arms: According to the PPM, Mast Arms are called for within 10 miles of the coastline. All other locations should have span wire assemblies. Refer to the PPM for details.

Conduit: Conduit is paid as the length from point A to B, with no additional quantity for sweeps or vertical distances. Note- when multiple conduits are included in a trench, payment is based on the total length of conduit, not the length of the trench.

For example: 4 conduits in a 100 foot trench = 400 total feet of conduit.

313

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 314: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

ITS component requirements are changing.

ITS and other local signalization systems are frequently merging, especially in urban areas. Watch for updates to the specifications, standards, and pay items. As necessary, signals and/or ITS pay items may be used in either component plans.

314

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 315: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Most ITS Items are “all inclusive” for complete installations. Read the available specifications to verify which incidentals are included.

315

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 316: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Landscaping design varies considerably between districts, as well as between projects.

All landscape work should be detailed in the landscape plans, according to the PPM.

There are two pay items for landscaping: small plants and incidentals, and large plants. Both items are lump sum, although individual plants and incidental items must be tabulated in the plans.

316

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 317: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

No Landscape plans?

The PPM allows some minor landscape work to be detailed in the roadway plans. See PPM vol 2, ch 26.

When there are no landscape pay items, tree protection and other incidental work is included in the related roadway pay item(s). Ensure that the work is detailed completely.

317

Part 3- Estimating and ReviewCategories & Pay Items

No Landscaping

I

Page 318: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Irrigation work may be included with either Landscape or Roadway plans. Ensure that the component plans and specifications provide complete details, including material requirements.

318

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 319: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Part 3

Utility work varies by project and utility company. Details and/or Technical Specs are required for every item of work. Ensure that material and installation requirements are included.

Due to the technical nature of these items, historical information is of limited value. “Ballpark” price ranges may assist the estimator, but project requirements should be the primary consideration.

319

Part 3- Estimating and ReviewCategories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 320: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Demonstrate webgate reports.

320

Page 321: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates

This concludes this part.

If you would like to view additional material, please select the Part you would like to view.

321

Part 1: Introduction to the Basis of Estimates

Part 2: Selecting Pay Items

Part 3: Estimating and Review

I

Page 322: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

322 I

Page 323: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Basis of Estimates- Index

323

Part 1: Introduction to the Basis of Estimates General Information BOE Online Chapters

Chapter 1: Updates & Registration

Chapter 2: Units of Measure Chapter 5: Contact Lists Chapter 6: Pay Item

Requests Chapter 7: Plan Notes Chapter 8: Forms Chapter 9: Trnsport &

Webgate Chapter 10: Formatting Items

Part 2- Selecting Pay Items 100s 200s 300s 400s 500s 600s 700s 800s 900s Utilities

Part 3- Estimating and Review Updates

January, this year July, this year January, next year July, next year

General Conditions Categories & Pay Items

Structures, Roadway, Signing & Pavement Marking, Lighting, Signals, ITS, Landscaping, Utilities

I

Page 324: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Updates to this CBT

History of revisions

324

June 2009: created 1st draft of CBT, with parts 1 and 2 based on previous BOE training. Part 3 in early development.

I

Page 325: Melissa Hollis Engineering Systems Support State Specifications and Estimates Office May 2011 1 Basis of Estimates for Designers, Estimators, and Reviewers.

Updates to the CBT

Pending questions

325

Should the presentation be separated into 3 files?

How do we ask Districts for help with maintaining the presentation, especially part 3?

Link to specs throughout, if more info is available.

BOE Certification? Include in QC? Project Manager & Designer requirement

I