Melbourne University - Year 2 Construction Analysis

26
Construction Analysis of Cave House by McBride Charles Ryan - Index 1. Site Preparation Demolishing the previous building Excavation of basement at 3 stages 2. Basement Footings Ground floor vertical supports In-ground services 3. Ground Floor (Horizontal Frames) and Boundaries Band beams Horizontal Slabs for ground floor Pouring concrete Fencing 4. Ground Floor (Vertical Frames) Bracing Timber Studs 5. First Floor (Horizontal Frames) Horizontal Frames 6. First Floor (Vertical Frames) Timber Stud Walls 7. Roof Structure Roof Fames Roof beams and rafters Lintels where there are doors or entrances 8. Roof Cover and Facade Insulation in roof ceilings Roof water proofing Façade is being constructed 9. Window Frames and Insulation Insulation in ceiling and façade 10. Suspended Ceiling Suspended ceiling is enclosed 11. Internal Partition and Services Timber stud wall (noggings) are covered up with plasterboard to form internal walls Works on joinery, sink/toilet drains 12. Finishing Painting of walls Carpet finishing on ground floor Pouring of concrete slab over basement floor

description

 

Transcript of Melbourne University - Year 2 Construction Analysis

Page 1: Melbourne University - Year 2 Construction Analysis

Construction Analysis of Cave House by McBride Charles Ryan - Index

1. Site Preparation

• Demolishing the previous building

• Excavation of basement at 3 stages

2. Basement Footings

• Ground floor vertical supports

• In-ground services

3. Ground Floor (Horizontal Frames) and Boundaries

• Band beams

• Horizontal Slabs for ground floor

• Pouring concrete

• Fencing

4. Ground Floor (Vertical Frames)

• Bracing

• Timber Studs

5. First Floor (Horizontal Frames)

• Horizontal Frames

6. First Floor (Vertical Frames)

• Timber Stud Walls

7. Roof Structure

• Roof Fames – Roof beams and rafters

• Lintels where there are doors or

entrances

8. Roof Cover and Facade

• Insulation in roof ceilings

• Roof water proofing

• Façade is being constructed

9. Window Frames and Insulation

• Insulation in ceiling and façade

10. Suspended Ceiling

• Suspended ceiling is enclosed

11. Internal Partition and Services

• Timber stud wall (noggings) are

covered up with plasterboard to form

internal walls

• Works on joinery, sink/toilet drains

12. Finishing

• Painting of walls

• Carpet finishing on ground floor

• Pouring of concrete slab over

basement floor

Page 2: Melbourne University - Year 2 Construction Analysis
Page 3: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Section Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 01

SITE PREPERATION

Page 4: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Section Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 02

BASEMENT FOOTINGS

BAND BEAM

RETAINING WALL

BUTTRESS FOOTING BEHIND CUT SECTION

Page 5: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Section Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 03

GROUND FLOOR &

BOUNDARIES

CONCRETE SLAB POURED OVER BAND BEAMS

Page 6: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Section Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 04

GROUND FLOOR

(VERTICAL FRAMES)

TIMBER STUDS

JOINT

Page 7: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Section Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 05

FIRST FLOOR

(HORIZONTAL FRAMES)

SCAFFOLDING SEEN BEHIND CUT SECTION

Page 8: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Section Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 06

FIRST FLOOR

(VERTICAL FRAMES)

TIMBER STUD WALLS (NOGGING)

Page 9: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Section Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 07

ROOF STRUCTURE

ROOF LINEJOISTS

Page 10: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Section Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 08

ROOF COVER AND

FAÇADE

DOWNPIPE AND WASTE PIPES

ROOF WATER COLLECTION POINT

FAÇADE LANDING

ROOF INSULATION

FAÇADE LINE

Page 11: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Section Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 09

WINDOW FRAMES &

INSULATION

INSULATION AROUND THE PIPES

Page 12: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Section Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 10

SUSPENDED CEILING

PLACING THE CEILING BOARDS TO COVER UP WIRING/INSULATION

FINISHED COVERING SUSPENDED CEILING

WIRING CONNECTED TO SERVICES

Page 13: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Section Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 11

INTERNAL PARTITIONS &

SERVICES

BEHIND CUT SECTION (OUTDOOR AREA)

TIMBER STUD WALLS ARE COVERED UP

Page 14: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Section Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 12

FINISHING

Page 15: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Plan Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 01

SITE PREPERATION

(BASEMENT)

Page 16: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Plan Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 02

BASEMENT FOOTINGS

(BASEMENT)

VERTICAL SUPPORTS FOR BAND BEAM ANDD GROUND FLOOR CONCRETE SLAB

Page 17: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Plan Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 03

HORIZONTAL FRAMES &

BOUNDARIES

(GROUND FLOOR)

Page 18: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Plan Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 04

VERTICAL FRAMES &

BRACING

(GROUND FLOOR)

GROUND FLOOR BRACING

BRACING OUTLINE (ONLY STUDS AT CURRENT STAGE)

Page 19: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Plan Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 05

HORIZONTAL FRAMES –

BEAMS & JOISTS

(FIRST FLOOR)

FLOOR JOISTS

FLOOR BEAMS

Page 20: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Plan Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 06

VERTICAL FRAMES –

TIMBER STUD WALLS

(FIRST FLOOR)

VERTICAL TIMBER STUDS

BOUNDARY LINE

CEILING LINE

Page 21: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Plan Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 07

ROOF STRUCTRE

(ROOF)

ROOF RAFTERS

VERTICAL FRAMES OF FIRST FLOOR

Page 22: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Plan Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 08

FAÇADE & INTERNAL

WIRINGS (NOT

CONNECTED YET)

(GROUND FLOOR)

FAÇADE STRUCTURE

FIREPLACE CONSTRUCTION AT EARLY STAGES

Page 23: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Plan Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 09

WINDOW FRAMES &

INSULATION

(GROUND FLOOR)

BRACING STUDS COVERED UP

Page 24: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Plan Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 10

SUSPENDED CEILING –

REFLECTED CEILING VIEW

(GROUND FLOOR)

FIREPLACE FURTHER CONSTRUCTED

Page 25: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Plan Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 11

SERVICES & JOINERIES

(GROUND FLOOR)

FIREPLACE AND BUILT IN SHELVES

Page 26: Melbourne University - Year 2 Construction Analysis

Naomi Wirianata 616224

ABPL20033 Construction

Analysis

Flipbook Assignment Part 4

- Final Submission

Plan Drawing – G3

Cave House by McBride Charles

Ryan

Scale 1:50

Stage 12

FINISHING

(GROUND FLOOR)