Construction Analysis of Cave House by McBride Charles Ryan - Index
1. Site Preparation
• Demolishing the previous building
• Excavation of basement at 3 stages
2. Basement Footings
• Ground floor vertical supports
• In-ground services
3. Ground Floor (Horizontal Frames) and Boundaries
• Band beams
• Horizontal Slabs for ground floor
• Pouring concrete
• Fencing
4. Ground Floor (Vertical Frames)
• Bracing
• Timber Studs
5. First Floor (Horizontal Frames)
• Horizontal Frames
6. First Floor (Vertical Frames)
• Timber Stud Walls
7. Roof Structure
• Roof Fames – Roof beams and rafters
• Lintels where there are doors or
entrances
8. Roof Cover and Facade
• Insulation in roof ceilings
• Roof water proofing
• Façade is being constructed
9. Window Frames and Insulation
• Insulation in ceiling and façade
10. Suspended Ceiling
• Suspended ceiling is enclosed
11. Internal Partition and Services
• Timber stud wall (noggings) are
covered up with plasterboard to form
internal walls
• Works on joinery, sink/toilet drains
12. Finishing
• Painting of walls
• Carpet finishing on ground floor
• Pouring of concrete slab over
basement floor
![Page 2: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/2.jpg)
![Page 3: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/3.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Section Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 01
SITE PREPERATION
![Page 4: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/4.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Section Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 02
BASEMENT FOOTINGS
BAND BEAM
RETAINING WALL
BUTTRESS FOOTING BEHIND CUT SECTION
![Page 5: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/5.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Section Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 03
GROUND FLOOR &
BOUNDARIES
CONCRETE SLAB POURED OVER BAND BEAMS
![Page 6: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/6.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Section Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 04
GROUND FLOOR
(VERTICAL FRAMES)
TIMBER STUDS
JOINT
![Page 7: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/7.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Section Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 05
FIRST FLOOR
(HORIZONTAL FRAMES)
SCAFFOLDING SEEN BEHIND CUT SECTION
![Page 8: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/8.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Section Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 06
FIRST FLOOR
(VERTICAL FRAMES)
TIMBER STUD WALLS (NOGGING)
![Page 9: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/9.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Section Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 07
ROOF STRUCTURE
ROOF LINEJOISTS
![Page 10: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/10.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Section Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 08
ROOF COVER AND
FAÇADE
DOWNPIPE AND WASTE PIPES
ROOF WATER COLLECTION POINT
FAÇADE LANDING
ROOF INSULATION
FAÇADE LINE
![Page 11: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/11.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Section Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 09
WINDOW FRAMES &
INSULATION
INSULATION AROUND THE PIPES
![Page 12: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/12.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Section Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 10
SUSPENDED CEILING
PLACING THE CEILING BOARDS TO COVER UP WIRING/INSULATION
FINISHED COVERING SUSPENDED CEILING
WIRING CONNECTED TO SERVICES
![Page 13: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/13.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Section Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 11
INTERNAL PARTITIONS &
SERVICES
BEHIND CUT SECTION (OUTDOOR AREA)
TIMBER STUD WALLS ARE COVERED UP
![Page 14: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/14.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Section Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 12
FINISHING
![Page 15: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/15.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Plan Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 01
SITE PREPERATION
(BASEMENT)
![Page 16: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/16.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Plan Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 02
BASEMENT FOOTINGS
(BASEMENT)
VERTICAL SUPPORTS FOR BAND BEAM ANDD GROUND FLOOR CONCRETE SLAB
![Page 17: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/17.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Plan Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 03
HORIZONTAL FRAMES &
BOUNDARIES
(GROUND FLOOR)
![Page 18: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/18.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Plan Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 04
VERTICAL FRAMES &
BRACING
(GROUND FLOOR)
GROUND FLOOR BRACING
BRACING OUTLINE (ONLY STUDS AT CURRENT STAGE)
![Page 19: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/19.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Plan Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 05
HORIZONTAL FRAMES –
BEAMS & JOISTS
(FIRST FLOOR)
FLOOR JOISTS
FLOOR BEAMS
![Page 20: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/20.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Plan Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 06
VERTICAL FRAMES –
TIMBER STUD WALLS
(FIRST FLOOR)
VERTICAL TIMBER STUDS
BOUNDARY LINE
CEILING LINE
![Page 21: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/21.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Plan Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 07
ROOF STRUCTRE
(ROOF)
ROOF RAFTERS
VERTICAL FRAMES OF FIRST FLOOR
![Page 22: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/22.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Plan Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 08
FAÇADE & INTERNAL
WIRINGS (NOT
CONNECTED YET)
(GROUND FLOOR)
FAÇADE STRUCTURE
FIREPLACE CONSTRUCTION AT EARLY STAGES
![Page 23: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/23.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Plan Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 09
WINDOW FRAMES &
INSULATION
(GROUND FLOOR)
BRACING STUDS COVERED UP
![Page 24: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/24.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Plan Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 10
SUSPENDED CEILING –
REFLECTED CEILING VIEW
(GROUND FLOOR)
FIREPLACE FURTHER CONSTRUCTED
![Page 25: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/25.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Plan Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 11
SERVICES & JOINERIES
(GROUND FLOOR)
FIREPLACE AND BUILT IN SHELVES
![Page 26: Melbourne University - Year 2 Construction Analysis](https://reader034.fdocuments.us/reader034/viewer/2022052514/579071031a28ab6874a01dde/html5/thumbnails/26.jpg)
Naomi Wirianata 616224
ABPL20033 Construction
Analysis
Flipbook Assignment Part 4
- Final Submission
Plan Drawing – G3
Cave House by McBride Charles
Ryan
Scale 1:50
Stage 12
FINISHING
(GROUND FLOOR)