Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
Sixth Framework Programme
MANAGING FP6 CONTRACTS
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
Core contractstandard text (completed with project data)
Annex Ithe “project” (technical tasks - work to be carried out)
Annex IIgeneral conditions (standard, applicable to every instrument)
Annex IIIinstrument specific provisions (variable per instrument)
Contract Structure
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
Supplemented by supplementary information and guidance notes when necessary
Financial (including auditing, cost methodologies) Negotiation (including technical annex) Consortium agreement (including IPR) Project management (including reporting)
plus guidelines imposed by Rules for Participation Guidelines on Evaluation and Selection
procedures
Guidelines
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
Regulates internal organisation and management of consortium (Commission is not a party)
New - Compulsory unless exempted by the call for proposals
Non binding guidelines provided by the Commission (consortium agreement checklist)
After or (preferably) before signing the contract - some decisions must be made by the participants before signature of contract (e.g. exclusion of pre-existing know-how)
Consortium Agreement
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
Signature and entry into force:
Contractual link of all contractors with the Commission (equal status)New - Contract enters into force upon signature of coordinator and Commission
Coordinator must ensure other contractors sign within delays (established in contract)
Distribution of advance to other contractors possible after minimum requirements met
Project begins on date established in the contract Reporting periods
Special clauses
Core contract
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
Technical Responsibility (applicable to all instruments)
Financial Responsibility - New
Used as a last resort
Limited in proportion to the participant’s share to the project, up to the total amount they are entitled to receive
Exceptions: International Organisations, public bodies or entities guaranteed by MS/AS: solely responsible for their own debts specific actions for SME’s and fellowships and, when duly justified, specific support actions
Collective Responsibility of Contractors
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
New - Cost categories not requiredCosts must be :
actual, economic and necessary for the project
incurred during the duration of the projectrecorded in the accounts (or third parties)follow contractors own accounting rules
and must exclude indirect taxes, duties, interests, costs reimbursed in respect of another Community project, and not give rise to profit
Audit certificates by external auditor for each partner, each year for IP/NoE
for public bodies - competent public officer
Costs
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
Cost reporting models Full Cost with actual indirect costs (FC)- eligible direct and indirect costs are charged
All legal entities can use the FC model except physical persons(physical persons participating as individuals use the AC model (some SMEs are technically physical persons but can use the FCF or FC model depending on their accounting capacity)
Full Cost with flat rate for indirect costs (FCF)- eligible direct costs plus a flat rate of 20% of eligible direct costs (minus costs of sub-contracts) to cover indirect costs are chargedAvailable to non-commercial or non-profit organisations, international organisations and SMEs
Additional Cost with indirect flat rate costs (AC)- eligible direct additional costs plus flat rate of 20% of direct additional costs (minus costs of sub-contracts) Available to non-commercial or non-profit organisations and international organisations that cannot distinguish the share of direct and indirect costs of the project
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
Periodic advances (pre-financing) yearly for IP and NoE (specified in the contract for other
instruments)
up to 85% of EC financial contribution for first
period plus first 6 months of subsequent period
settled when associated with an audit certificate
EC contribution depends on :
contractor’s cost model (AC, FC, FCF) type of activity (research, demonstration,
management, training, etc) allowed by instrument submission of audit certificate (settled payment) receipts
Distribution depends on consortium’s decisions
Payments
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
INTEGRATED PROJECTS Reimbursement Rates
Maximum Reimbursement rates of Costs
Research & technological development /
Innovation
Demonstration TrainingManagement
of the consortium
FC / FCFCONTRACTORS
50% 35% 100%100%
up to 7% of the contribution
ACCONTRACTORS
100% 100% 100%
100%up to 7% of the contribution
(1)
(1) Contractors working on the additional cost model may also charge the cost of permanent personel to their contractors, to the extent that they can be identified
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
Maximum Reimbursement Rates
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
Controls
Reports Periodic activity reports (including plan for
dissemination and use) Periodic financial reports Supplementary reports if foreseen (in Annex I
or III)
Audits Scientific, technological, and financial audits New - monitoring by Commission with
external experts (annual for IP and NoE) Ethical or other reviews Contractors right to refuse particular expert
Audits and Controls
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
Financial irregularity is grounds for exclusion from evaluation or selection procedure
Violation of fundamental ethical principles is grounds for exclusion from evaluation or selection procedure
Recovery decisions (Article 256 EC Treaty)
Other sanctions in contract (liquidated damages for overclaims)
Sanctions
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
AmendmentsAmendments
Art.10 Art.10 of of Core Contract Core Contract && Art.8 Art.8 of of Annex IIAnnex II
Request in writingRequest in writing
NewNew at the request of the coordinator, deemed to act on at the request of the coordinator, deemed to act on behalf of the consortiumbehalf of the consortium
NewNew Tacit amendmentsTacit amendments with implicit agreement of the with implicit agreement of the Commission within 6 weeksCommission within 6 weeks onlyonly for modification and for modification and evolution of the consortium and for technical reportsevolution of the consortium and for technical reports
NewNew in IP/NoE, enlargement of the consortium to new in IP/NoE, enlargement of the consortium to new contractors and new activities may be foreseen. This contractors and new activities may be foreseen. This enlargement follows a competitive call launched by the enlargement follows a competitive call launched by the consortium with evaluation of proposals by external expertsconsortium with evaluation of proposals by external experts
Megan Richards RTD FP6 Kick Off Meeting Priority 7 and 8 11 November 2004
Contracts and translations
Guide to Amendments of contracts
Special clauses and Guide to special clauses
Guide to Financial issues
Frequently Asked Questions
IPR Guide and Guide to Article II.35.1.b
Consortium agreement checklist
Negotiation documents (CPF/guidance notes)
http://europa.eu.int/comm/research/fp6/working -groups/model-contract/index_en.html
Model Contract Web site