Meet The Team
Uday Durg, PE
Program Executive for Lower Manhattan Projects, MTACC
Hsin Wu, PE
Program Manager
Bharat Kothari, PE
Program Manager
Naresh Patel, PE
Construction Manager
Judy Duffy
Assistant Director, Government and Community Relations, MTA
Contact Number: 646‐252‐2652
Since We Last Saw You…
All contracts are now in construction and fully funded
Transit Center foundation –Completed August 16th 2010
Work progressing rapidly on A/C Mezzanine
Corbin Building restoration underway
Broadway sidewalk work ongoing
Transit Center foundation in July 2010
All Contracts Underway
Transit Center Foundation – Completed August 16th, 2010
Contract completed on time and within budget
Included underpinning of historic Corbin Building
Allows for restoration of the building for future use by the public
Will allow for a more accessible transfer between the A/C and 4/5 Stations
FSTC 03/2009
FSTC 05/2009
FSTC 07/2009
FSTC 09/18/2009
FSTC 09/25/2009
FSTC 10/06/2009
FSTC 10/28/2009
FSTC 11/16/2009
FSTC 12/11/2009
FSTC 01/19/2010
FSTC 03/01/2010
FSTC 04/02/2010
FSTC 05/03/2010
FSTC 06/04/2010
FSTC 06/25/2010
FSTC 07/14/2010
FSTC 08/03/2010
A/C Mezzanine Rehabilitation
New Structural Framing
New Steel Columns
A/C Mezzanine Rehabilitation
Elevator Pit Work
New Dey Street Entrance at Broadway
Erection of Dey Street Entrance Steel
Historic Corbin Building Restoration
Façade Demolition and Utility Work
Street and Sidewalk Work
Sidewalk work on west side of Broadway ongoing and scheduled to be completed early 2011
Work to put in new elevator at 129 Fulton and new entrance at 150 William to begin this quarter
135 William Street work ongoing and new entrance and elevator scheduled to open late spring 2011
Broadway between Dey and Cortlandt StreetsCurrent to October 14, 2010
13’-0”
8’-0”
11’-0”11 ’-0”
11 ’-0”
LANE
LANE
12 ’-0”15 ’-6”
LANE
LANE
12 ’- 0”15 ’-6”
LANE
TAPEREDBARRIER
ARROW BOARD
2’-0”JERSEY
BARRIER (TYP)
CO
RT
LA
ND
T ST
RE
ET
DE
Y ST
RE
ET
Work HoursWork Hours7:00 AM 7:00 AM –– 12:00 AM12:00 AM
3’ CONCRETE BARRIERS TOPPED WITH 5’ HIGH MESH FENCE TO ALLOW SIGHT LINES TO BUSINESSES ALONG BROADWAY
Notes:WDF to work two shifts per day to complete work.Work on-going – work areas to shift as required.
LEGENDLEGEND
PEDESTRIAN WALKWAY
PROPOSED MPT WORK ZONE
CONCRETE BARRIERSTIMBER BARRIERS
DOT APPROVED MPT AREA
FSTC WORK SITE
CONSTRUCTION BARRICADES4’ HIGH FENCE
RAMP
WORK BY OTHERS
BROADWAY
LANE
11 ’-0”
11’-0”
”
AT LEAST 8’ OF PEDESTRIAN WALKWAY
PLYWOOD & MESH FENCE
60’ CLEARANCE FROM SOUTH CURB OF DEY STREET
11
WOODEN BARRIERS
Broadway between Fulton and Dey Streets – Phase 1September 20 – October 14, 2010
CORTLANDT ST.
JOHN ST.
MAIDEN LANE
DEY ST.
FULTON ST.
MAINTAIN TWO (2) 11’WIDE TRAVEL LANES AT ALL TIMES
PEDESTRIAN WALKWAY
CONTRACTOR MAY ONLY WORK ONE SIDE OF DEY STREET AT A TIME
DEY STREET HEAD HOUSE
Note: Since both roads (Fulton Street and Broadway) cannot be closed at the same time, the work will be done in phases. Details of proposed MPT to be developed by Contractor .
CORBIN BLDG.
TRANSIT CENTER BUILDING
MPT REQUIREMENTS TO BE ADJUSTED TO MAINTAIN PEDESTRIAN AND TRAFFIC FLOW AS REQUIRED
Work HoursWork Hours7:00 AM 7:00 AM –– 12:00 AM12:00 AM
LEGENDLEGEND
PEDESTRIAN WALKWAY
PROPOSED MPT WORK ZONE
CONCRETE BARRIERSTIMBER BARRIERS
DOT APPROVED MPT AREA
FSTC WORK SITE
CONSTRUCTION BARRICADES4’ HIGH FENCE
CROSSWALKS
WORK BY OTHERS
CONTRACTOR TO KEEP HALF OF SIDEWALK OPEN FOR PEDESTRIAN TRAFFIC AT ALL TIMES
PLYWOOD & MESH FENCE 12
Fulton Street between Broadway and Nassau Street
Nas
sau
St.
To Broadway
.
Phase Activities: 1. Install sewer along south curbline of Fulton Street by 4B Contractor expected in
2011 or in 2012 (not shown).
2. After completion of work, replace roadway, sidewalk and curb in 2012 or later according to standard NYCT roadway new 3” thick asphaltic concrete wearing course. Concrete base to match existing thickness.
RESTORE DISTURBED PAVEMENT TO MATCH EXISTING CONDITIONS
8’ PEDESTRIAN WALKWAY
11’ TRAVEL LANE CONCRETE BARRIER
TIMBER BARRIER
TRANSIT CENTER
BUILDING
EXISTING MPT 4A
144 FULTON STREET
FULTON STREET6’ PEDESTRIAN WALKWAY
25’
Work HoursWork Hours7:00 AM 7:00 AM –– 10:00 PM10:00 PM
ACCESS GATEMOVEABLE BARRIEREXIT GATE
10’
LEGENDLEGEND
PEDESTRIAN WALKWAY
PROPOSED MPT WORK ZONE
CONCRETE BARRIERSTIMBER BARRIERS
DOT APPROVED MPT AREA
FSTC WORK SITE
CONSTRUCTION BARRICADES4’ HIGH FENCE
CROSSWALKS
ACCESS HOLE
WORK BY OTHERS
PLYWOOD & MESH FENCE 13
Pending Agreement with 129 Fulton Street
FULTON STREET
11’ TRAVEL LANE
129 FULTON STREET
PEDESTRIAN WALKWAY
SUBWAY STAIR ENTRANCE
NA
SSA
U S
TR
EE
T
8’PEDESTRIAN WALKWAY
127 FULTON STREET
CURBLINE
Work HoursWork Hours7:00 AM 7:00 AM –– 10:00 PM10:00 PM
DU
TC
H S
TR
EE
T
’
8’
LEGENDLEGEND
PEDESTRIAN WALKWAY
PROPOSED MPT WORK ZONE
CONCRETE BARRIERSTIMBER BARRIERS
DOT APPROVED MPT AREA
FSTC WORK SITE
CONSTRUCTION BARRICADES4’ HIGH FENCE
CROSSWALKS
WORK BY OTHERS
Notes:
1. Asbestos removal at 129 Fulton Street completed.
2. Coordination with the owner of 129 Fulton Street to relocate the building utilities required prior to Skanska’s start.
3. Elevator installation to take one year.
4. Crossroads project façade work at 127 Fulton Street to take four months from start date.
5. After installation of elevator, restore roadway, sidewalk and curb. MPT to be adjusted as required in 2012.
PLYWOOD BARRICADE BY OTHERS – SCHEDULE UNKNOWN
CROSSROADS PROJECT –EXPECTED TO USE / MAINTAIN SCAFFOLD
PLYWOOD & MESH FENCE
SKANSKA TO INSTALL ELEVATOR AT 129 FULTON STREET – WORK EXPECTED TO LAST ONE YEAR
125 FULTON STREET
125 FULTON STREET VAULT WORK TO BE COMPLETED
14
Intersection of Fulton and William Streets
WIL
LIA
M S
TR
EE
T
135 WILLIAM STREET
NEW ASPHALT STREET CURRENTLY CONTROLLED BY OTHERS. MPT PLANS TO BE FINALIZED IN 2012.
6’ PEDESTRIAN WALKWAY
DECKING
Phase Activities:
1. Decking along sidewalk of William completed.
2. Current work being coordinated with DDC (Trocom) work at Fulton/William Intersection
3. Installation of new roof structure connection into 135 William Street started March 2010 and will continue through 2012.
4. Restore roadway, sidewalk and curb in 2012. MPT to be adjusted as required’
Note: DOT approved MPT shown in red. Remaining MPT pending approval.
TIMBER BARRIER
15
150 WILLIAM STREET
FULTON STREET
WIL
LIA
M S
TR
EE
T
11’ TRAVEL LANE
Work HoursWork Hours7:00 AM 7:00 AM –– 10:00 PM10:00 PM
CROSSWALKS SERVICED BY EXISTING TRAFFIC SIGNAL
CROSSWALKS
LEGENDLEGEND
PEDESTRIAN WALKWAY
PROPOSED MPT WORK ZONE
CONCRETE BARRIERSTIMBER BARRIERS
DOT APPROVED MPT AREA
FSTC WORK SITE
CONSTRUCTION BARRICADES4’ HIGH FENCE
CROSSWALKS
WORK BY OTHERS
PLYWOOD & MESH FENCE
AREA EXTENDED FOR CON ED & ECS UTILITY RELOCATION WORK ON-GOING
CONCRETE BARRIER
SIDEWALK WORK EXPECTED TO START NOVEMBER 26, 2010 THROUGH MAY 2011
125’±
6 FT. GAS MAIN CONNECTING TO 135 WILLIAM ST. WILL TAKE 2 WEEKENDS AND FULL CLOSURE OF STREET- TBD.
John Street between Broadway and Nassau St. – June 2010 Through Nov. 2012
Trailer and Loading Area
ACCESS GATEMOVEABLE BARRIER
WorkWork HoursHours7:00 AM 7:00 AM –– 5:00 PM5:00 PM
Open SidewalkOpen SidewalkFall 2010Fall 2010
PEDESTRIANWALKWAY
HYDRANT
ACCESS GATEMOVEABLE BARRIER
BR
OA
DW
AY
NA
SS
AU
ST
RE
ET
JOHN STREET
SIDEWALK CLOSEDSIDEWALK
CLOSED
EGRESSMOVEABLE BARRIER
CHAIN LINK AND MESH FENCE
11’ TRAVEL LANE
161’-11
17’-6
CHAIN LINK AND MESH FENCE
Schedule: 34 Months Schedule: 34 Months 2/2010 2/2010 –– 11/201211/2012
Note: To be coordinated with work to be performed at 24 John Street
LEGENDLEGEND
PEDESTRIAN WALKWAY
PROPOSED MPT WORK ZONE
CONCRETE BARRIERSTIMBER BARRIERS
DOT APPROVED MPT AREA
FSTC WORK SITE
CONSTRUCTION BARRICADES4’ HIGH FENCE
CROSSWALKS
WORK BY OTHERS
PLYWOOD & MESH FENCE
8FT. HIGH PLYWOOD BRRIERR
PROPERTY LINE BOX TO BE COMPLETED WHEN SKANSKA FINISHES THE ROOF STRUCTURE
16
Broadway between Vesey and Fulton Streets – Phase 2
CORTLANDT ST.
JOHN ST.
MAIDEN LANE
DEY ST.
FULTON ST.
MAINTAIN TWO (2) 11’WIDE TRAVEL LANES
PEDESTRIAN WALKWAY
CONTRACTOR MAY ONLY WORK ONE SIDE OF FULTON STREET AT A TIME
DEY STREET HEAD HOUSE
17
CORBIN BLDG.
TRANSIT CENTER BUILDING
MPT REQUIREMENTS TO BE ADJUSTED TO MAINTAIN PEDESTRIAN AND TRAFFIC FLOW AS REQUIRED Work HoursWork Hours
7:00 AM 7:00 AM –– 10:00 PM10:00 PM
Note: Since both roads (Fulton Street and Broadway) cannot be closed at the same time, the work will be done in phases. Details of proposed MPT to be developed by Contractor .
LEGENDLEGEND
PEDESTRIAN WALKWAY
PROPOSED MPT WORK ZONE
CONCRETE BARRIERSTIMBER BARRIERS
DOT APPROVED MPT AREA
FSTC WORK SITE
CONSTRUCTION BARRICADES4’ HIGH FENCE
CROSSWALKS
WORK BY OTHERS
PLYWOOD & MESH FENCE
Community Outreach
Local business banners up on Fulton, John and William Streets
Large Broadway banner featuring project renderings
New Downtown Alliance wayfindingbanner up at corner of Dey and Broadway
Be on the lookout for new signage around the holidays!
Community Outreach
Post local business information on MTA’s website and local organizations’websites similar to 2nd Ave Subway’s “Shop 2AVE” program
Community Outreach
Regular meetings with the Downtown Alliance, Community Board 1 and NYC Department of Transportation
Daily site walkthroughs with checklist
Coming in 2011…New Dey Street Entrance and Retail
Coming in 2011…Rehabilitated Cortlandt Street Station!
Coming in 2011…New Dey Street Concourse & 4/5 Connection
Coming in 2011…2012…2013…2014
Customer Benefit 2009 2011 2012 2013 2014
Cortlandt Street R Station NB Platform (COMPLETED) Nov
Mar
New 135 William Street Entrance May
New Fulton St A/C to 4/5 Connection Aug
Cortlandt Street R Station SB Platform Sept
4/5 Fulton Street Station Rehab July
New Dey Street Entrance July
Opening of Dey Street Concourse Nov
New Escalator to John Street Nov
Corbin Building Restoration & First Fl Retail Dec
Opening of A/C Mezzanine
Opening of Transit Center Building June