MEDACTHU PROGRAM
28 September 2007
EPA ThessaliaEmergency and Readiness Procedures
EPA THESSALIA
GAS DISTRIBUTION SYSTEM
GAS DISTRIBUTION SYSTEM DATA
EPA MANAGES THE MEDIUM AND LOW
PRESSURE GAS DISTRIBUTION NETWORK
(MPDS, LPDS) IN THE URBAN AREA OF LARISSA
AND GHIANULI MUNICIPALITIES AND IN THE
AREA OF VOLOS
EPA MANAGES THE MEDIUM AND LOW PRESSURE GAS DISTRIBUTION NETWORK IN THE INDUSTRIAL AREAS (VIPE) OF LARISSA AND VOLOS
DESIGN PRESSURE: 19 BAR
SERVICE PRESSURE: 16 BAR
TYPE OF DISTRIBUTION: PIPELINES
PIPELINE MATERIAL: STEEL
PIPE INSTALLATION: BURIED PIPES
LENGTH: ~86 KM
DIAMETER: VARIES FROM 14’’ TO 2’’
MEDIUM PRESSURE DATA
GAS SUPPLIER: DESFA
GAS DELIVERY STATIONS (CITYGATES): 2
NORTH LARISSA CITYGATE LOCATION: NEW NATIONAL
ROAD, SYKOYRIO JOINT
SOUTH LARISSA CITYGATE LOCATION: BY NEW
NATIONAL ROAD, NEAR PLATYKAMPOS JOINT
OPERATIONS AT CITYGATES PROVIDED BY DESFA
PRESSURE REDUCTION AND REGULATION SERVICES
OVERALL QUANTITY AND ENERGY METERING
ODORIZATION
MEDIUM PRESSURE DATA inLARISSA
GAS SUPPLIER: DESFA
GAS DELIVERY STATIONS (CITYGATES): 2
VOLOS A’ INDUSTRIAL ESTATE (A VIPE) CITYGATE
LOCATION: A VIPE VOLOS, 3RD ROAD
KOKKINA VILLAGE DESFA LINE VALVE CITYGATE FROM
WHICH STARTS A 28 KM 8“ BRANCH TO SOVEL
OPERATIONS AT CITYGATES PROVIDED BY DESFA
SERVICE PRESSURE REDUCTION AND REGULATION
OVERALL QUANTITY AND ENERGY METERING
ODORIZATION
MEDIUM PRESSURE DATA VOLOS & SOVEL (ALMYROS)
PRESSURE REDUCTION: 19/4 BAR
NOMINAL CAPACITY: 5000 Nm3/h
TYPE: 2 LINES
INSTALLATION: ABOVE GROUND FENCED IN
PUBLIC AREAS
NUMBER OF IRI: 4 (SERVING LARISSA-
GHIANULI), 2 (SERVING INDUSTRIAL AREA)
IRI STATIONS LARISSA AREA
PRESSURE REDUCTION: 19/4 BAR
NOMINAL CAPACITY: 5000 Nm3/h
TYPE: 2 LINES
INSTALLATION: ABOVE GROUND FENCED IN PUBLIC
AREAS
NUMBER OF IRI: 4 (SERVING VOLOS-NEA IONIA
COUNCILS), 1 (SERVING A’ INDUSTRIAL ESTATE – A’
VIPE), 1 (SERVING B’ INDUSTRIAL ESTATE – VIPE
VELESTINO), 1 (SERVING AGRIA COUNCIL)
IRI STATIONS VOLOS AREA
DESIGN PRESSURE: 4 BAR
SERVICE PRESSURE: 3 BAR
PIPELINE MATERIAL: HIGH DENSITY POLYETHYLENE
PIPE INSTALLATION: BURIED PIPES
LENGTH: ~490 KM
DIAMETER: VARIES FROM Φ160 TO Φ63
NETWORK TOPOLOGY: LOOPED (Φ125) WITH OPEN BRANCH EXTENSIONS (Φ125/Φ63) DERIVED FROM LOOP FOR SATURATION
LPDS DEVELOPMENT
URBAN AREA OF LARISSA DIVIDED INTO THREE OPERATING SECTOR (OS) EACH ONE COVERED BY A MAJOR LOOP AND SATURATED BY OPEN BRANCHES
EACH OS SUPPLIED BY ONE OR MORE IRI
LP DISTRIBUTION SYSTEM
THE LOW PRESSURE DISTRIBUTION NETWORK SERVES:
~ 20300 CLIENTS IN GAS IN LARISSA AND VOLOS
AREAS
20 INDUSTRIAL CLIENTS
CLIENTS ARE SERVED VIA 5.500 SERVICE LINES DERIVED
FROM THE LOW PRESSURE DISTRIBUTION NETWORK
26 EPA INDUSTRIAL CLIENTS ARE SERVED FROM THE
MEDIUM PRESSURE DISTRIBUTION NETWORK (4 IN LARISSA
AREA)
CLIENTS IN GAS
ΘΕΣ ΣΑΛΙΑΣ
MEDIUM PRESSURE P&IDLARISSA
MEDIUM PRESSURE P&ID VOLOS/NEA IONIA
EPA THESSALIA
OPERATING PROCEDURES
PROCEDURES
EPA Procedures N° 011 and 012
According to the Natural Gas Distribution Licence EPA Thessalia has to guarantee:
Operation and Maintenance of the whole
network
Readiness Management
Crisis Management
Safety of the population
Safety of the involved employees
Secure operation of the gas distribution system
Continuity of gas distribution service
Compliance to regulations:
- Gas Distribution License
- National Technical Regulation: Operation
and Maintenance Manual
PROCEDURESREQUIREMENTS TO BE FULFILLED
READINESS PROCEDURE
PRO 011 and operational instruction 013Applied in case of anomaly or accident in the gas network or in the internal installation of the Client
CALL CENTER
SCADA
THIRDS
Head of ReadinessOperating Technical Head
(2º )Squad Head (1º)Technician (1º)External Contractor
Intervention by 2 h for 90% of calls and 4h for 10%
EPA RUNS A READINESS SERVICE DURING WORKING AND NON WORKING HOURS (24 H A DAY, 365 D A YEAR) ACCORDING TO INTERNAL PROCEDURES 011 AND 013
DURING WORKING HOURS THE OPERATING READINESS IS GUARANTEED BY THE HEAD OF READINESS, THE OPERATING TECHNICAL HEAD, THE SQUAD HEAD AND TECHNICIAN. ALL PEOPLE ARE ON OPERATING READINESS WHILE CARRYING OUT NORMAL MAINTENANCE DUTIES ACCORDING TO THE SCHEDULE
AFTER THE WORKING HOURS THERE ARE TWO LEVELS OF AVAILABILITY:
- 1° LEVEL: Squad Head and Technician
- 2° LEVEL: Operating technical head
READINESS PROCEDURE CONT’D
READINESS MANAGEMENTTHE READINESS SQUAD HEAD IS CONTACTED BY THE CALL CENTER ABOUT GAS INCIDENTS OCCURING AT THE EPA RESPONSIBILITY ZONE
THE SQUAD HEAD MANAGES THE READINESS SQUAD DECIDING THE RESOURCES TO UTILISE FOR RESOLVING THE SITUATION
AN EXTERNAL CONTRACTOR WITH ADEQUATE PERSONNEL AND EQUIPMENT IS ALSO ON READINESS WITH DUTIES REGULATED BY A CONTRACT WITH EPA
CONTRACTOR IS ORDERED BY THE SQUAD HEAD, AFTER JUDGEMENT OF THE INCIDENT, TO INTERVENE IN MAXIMUM TWO HOURS TIME FROM THE ANNOUNCEMENT
THE OPERATING TECHNICAL HEAD IS CALLED BY THE SQUAD HEAD IN CASE OF DIFFICULT INTERVENTION OR PRESENCE OF PUBLIC AUTHORITIES
THE OPERATING TECHNICAL HEAD INFORMS THE COMPANY’S UPPER LEVEL MANAGEMENT IF THE INCIDENT IS JUDGED TO HAVE CHARACTERISTICS OF AN EMERGENCY OR CRISIS
EPA THESSALIA
EMERGENCY PROCEDURE
The results on gas distribution system may be:
Unscheduled out of operation of City Gates or IRS
Unscheduled out of operation of Medium Pressure and Low Pressure network with gas supply interruption for one or more final clients
Gas supply interruption to one or more final clients following a gas leakage
Pressure excess or shortage in the network
Gas supply interruption to at least 250 final Clients and for which the gas is not supplied for more than 24 hours.
Pro. 012: CRISIS MANAGEMENT FOR THE GAS DISTRIBUTION SYSTEM
EMERGENCY: EVENT ABLE TO PRODUCE SERIOUS AND/OR LARGE SCALE EFFECTS ON GAS DISTRIBUTION SYSTEM
ATTACHED:
I. TERRITORIAL EMERGENCY PLAN for
EPA THESSALONIKIS
EPA THESSALIAS
II. GENERAL EMERGENCY PLAN
III. JOURNAL OF EMERGENCY MANAGEMENT
ACTIVITIES
Pro. 012: CRISIS MANAGEMENT FOR THE GAS DISTRIBUTION SYSTEM
EMERGENCY MANAGEMENT
NOTIFICATION OF ANOMALIES IN THE DISTRIBUTION NETWORK
EVALUATION OF THE ANOMALIES or INNEFICIENCIES
EMERGENCY MANAGEMENT
FINAL ANALYSIS
CONTROL AND MONITORING
REPORTING
NOTICE OF ANOMALIES
CALL CENTER MAY BE INFORMED ABOUT AN
ANOMALY BY:
THIRDS
SAFETY BOARDS SUCH AS FIRE FIGHTING
BRIGADE, POLICE ETC.
ALARMS FROM REMOTE CONTROL SYSTEM
EPA PERSONNEL
THE CALL CENTER OPERATES ACCORDING TO THE
PROCEDURE 011 READINESS MANAGEMENT
EVALUATION OF ANOMALIES
THE READINESS HEAD OR THE OPERATING TECHNICAL HEAD
INFORM THE HEAD OF TECHNICAL DEPARTMENT ABOUT A
LARGE SCALE OR OUTSTANDING ANOMALY
THE HEAD OF TECHNICAL DEPARTMENT EVALUATES THE
EVENTS AND ANNOUNCES THE EMERGENCY TAKING CHARGE
OF THE OPERATIONS
IN CASE OF GENERAL EMERGENCY (PUBLIC AUTHORITIES AND
BOARD INVOLVED, MEDIA ETC.) EPA GENERAL MANAGER
ANNOUNCES AND TAKE CHARGE OF GENERAL EMERGENCY
EMERGENCY MANAGEMENT
COORDINATES THE EMERGENCY STRUCTURE (INCLUDING MAINLY
ALL TECHNICAL PERSONNEL)
IN CASE OF GENERAL EMERGENCY IS ACTIVATED ALSO THE
EMERGENCY STEERING COMMITTEE (INCLUDING ALL UPPER LEVEL
MANAGEMENT OF EPA)
INFORMS AND GET INVOLVED AUTHORITIES AND SAFETY BOARDS IF
REQUIRED. IN THIS CASE IS SUPPORTED BY “COIME” AND “LEGAL”
DEPARTMENT
INFORMS COMMERCIAL DEPARTMENT IF IT’S NECESSARY TO
INTERRUPT THE GAS SUPPLY TO SOME CUSTOMERS
ACTIONS PROVIDED BY THE HEAD OF EMERGENCY
EMERGENCY MANAGEMENT CONT’D
KEEP THE CALL CENTER UPDATED ABOUT THE EMERGENCY
PROGRESS IN ORDER TO GUARANTEE A CONSTANT AND CORRECT
INFORMATION TO PEOPLE CALLING
ONCE RESTATED THE SAFETY CONDITIONS AND THE GAS SUPPLY TO
ALL FINAL CLIENTS, THE HEAD ANNOUNCES THE END OF THE
EMERGENCY
INFORMS ALL PERSONNEL, DEPARTMENTS AND AUTHORITIES
INVOLVED DURING THE EMERGENCY
AN EMERGENCY JOURNAL IS FILLED IN TO RECORD ALL ACTIONS
ADOPTED.
ACTIONS PROVIDED BY THE HEAD OF EMERGENCY
FINAL ANALYSIS
BY TWO MONTHS FROM THE END “INAU” DEPARTMENT
PROVIDES AN ANALYSIS OF THE EMRGENCY CASE
HOW THE INTERNAL STRUCTURE HAS WORKED
HOW THE EXTERNAL CONTRACTORS HAVE WORKED
AVAILABILITY OF DATA AND INFORMATION
AVAILABILITY OF TOOLS AND MATERIALS
COMMUNICATION
RELATIONSHIP WITH AUTHORITIES, MEDIA ETC
EVENTUAL NEEDS FOR IMPROVING THE EMERGENCY PLAN
MONITORING AND REPORTING
THE HEAD OF EMERGENCY SENDS TO THE GREEK ENERGY
AUTHORITY (RAE) A REPORT FOR EACH EMERGENCY AS
REQUIRED BY THE GAS LICENCE
“INAU” MONITORS ALL EMERGENCY ACTIVITIES AND ISSUES
EVERY SIX MONTHS A REPORT
AFTER EACH EMERGENCY “INAU” ISSUES A REPORT TO BE
PRESENTED TO THE GENERAL MANAGER
ALL TERRITORIAL AND GENERAL EMERGENCY PLANS ARE
FILED AND UPDATED BY TECHNICAL DEPARTMENT