Measure K 2015-2016 Annual Report

27

Transcript of Measure K 2015-2016 Annual Report

Page 1: Measure K 2015-2016 Annual Report
Page 2: Measure K 2015-2016 Annual Report

Since 1990, the voter approved half-cent sales tax provides dedicated funding for transportation projects in San Joaquin County.

The Measure K Promise

Page 3: Measure K 2015-2016 Annual Report

• Completed Projects• Improved Transit

Access• Continuing Projects

2015-2016Year in Review

Page 4: Measure K 2015-2016 Annual Report

State Route 99

South Stockton Widening

Page 5: Measure K 2015-2016 Annual Report

Did you know?Caltrans and local partners have

now widened 14 miles of SR-99 from SR-4 to Austin Road.

Page 6: Measure K 2015-2016 Annual Report

Widened to six lanes

Overcrossings at MLK Blvd and Main St

New interchange at Golden Gate Ave

Reconstructed the Mariposa Rd interchange

New Park & Ride facility

Page 7: Measure K 2015-2016 Annual Report

TOTAL PROJECT COST

MEASURE K INVESTMENT

$214 M

$47.5 M

Page 8: Measure K 2015-2016 Annual Report

State Route 4 /

Crosstown Freeway

Extension

Page 9: Measure K 2015-2016 Annual Report

Did you know?These are the longest pre-cast

girders in the country (known as “super girders”) and they were built

right here in Lathrop.

Page 10: Measure K 2015-2016 Annual Report

Four-lane elevated roadway extends freeway from Fresno Ave to Navy Dr

Grade separation removing 6,500 vehicles a day from Boggs Tract neighborhood

Navy Dr interchange

Page 11: Measure K 2015-2016 Annual Report

MEASURE K INVESTMENT$70 M

TOTAL PROJECT COST$138 M

Page 12: Measure K 2015-2016 Annual Report

Interstate 5North

Stockton Widening &

Rehab Projects

Page 13: Measure K 2015-2016 Annual Report

Did you know?The I-5 North Stockton Widening and Rehab Projects added San

Joaquin County’s first High Occupancy Vehicle lanes.

Page 14: Measure K 2015-2016 Annual Report

Added new auxiliary lanes and soundwalls

Reconstructed existing freeway with Long lasting reinforced concrete (40-year life) between MLK and Hammer Ln

Page 15: Measure K 2015-2016 Annual Report

MEASURE K INVESTMENT$47 M

TOTAL PROJECT COST$194.5 M

Page 16: Measure K 2015-2016 Annual Report

Freeway Service Patrol

Page 17: Measure K 2015-2016 Annual Report

Improved TransitAccess

Page 18: Measure K 2015-2016 Annual Report

Escalon eTrans 3 daily round trips Local and

regional connections

986 passengers in 2015-2016

Page 19: Measure K 2015-2016 Annual Report

San Joaquin Regional Transit District

Intercity, interregional, and rural transit services

4.08 M passenger trips throughout the county in 2015-2016

Page 20: Measure K 2015-2016 Annual Report

Altamont Corridor Express Service from

Stockton, Lathrop, Manteca, Tracy to several Bay Area destinations

1.3 M passengers in 2015-2016

Page 21: Measure K 2015-2016 Annual Report

Ripon Blossom Express Local and

regional connections to San Joaquin RTD and Modesto Area Express

1,109 passengers in 2015-2016

Page 22: Measure K 2015-2016 Annual Report

Continuing Projects

Page 23: Measure K 2015-2016 Annual Report

Lower Sacramento Road Improvement

Page 24: Measure K 2015-2016 Annual Report

Harney Lane Grade Separation

Page 25: Measure K 2015-2016 Annual Report

Hammer Lane Widening Phase 3B

N

Page 26: Measure K 2015-2016 Annual Report

Thornton Road Widening

Page 27: Measure K 2015-2016 Annual Report

Download full report:www.sjcog.org/measureK