Measure E - Major Project Timeline
Commencment of Construction
Completion of Construction
Open
Science Center Nov 2001 Apr 2004 Sep 2004Parking Structure Dec 2003 Sep 2004 Sep 2004Student Community Services Dec 2003 Apr 2005 May 2005Kirsch Center Jan 2004 Feb 2005 May 2005
Science Center
The site of the Science Center looking toward the CDC on
10/28/02
The Science Center one year later
Science Center
The exterior showing the metal siding and the support
structure.
The Old OTI trailers were located here. This is the
walkway between two of the buildings.
Science Center
Crane lifting the air handling units on to the roof. Units are for the heating
and air-conditioning.
This is the roof showing the exhaust vents used for extracting air from the
fume hoods & restrooms, etc. Also shows the support poles for the
piping.
Interior of Science Center
One of the labs showing the acid waste pipes.
The interior of the lecture hall showing the floor
vents.
Parking Structure
The parking structure will be located in lot C.
Lot C will be closed from 1 Dec 2003.
Student Community Services
The SCS building is located behind the ATC,
on the present site of staff lot A. Staff lot A will be closed from 24 Nov
2003.
Kirsch Environmental Center
The Kirsch Center will be located in the South West Corner of campus, on the present site of the tennis courts. The courts will be closed at the end of Dec.
Parking OptionsVallco ‘No Fuss Bus’ drop off and pick up
Location of Vallco
parking lot
Staff carpool parking
Open Lots:A BCompact CPerimeter RdD
Open Lots:Flint
JKIFE