ME1105 - 1 - Staff Personal Pagesra600/ME2105/Lectures/ME2104-03.pdf · Managing Design (Academic...

16
Ahmed Kovacevic, City University London 1 Project management Prof Ahmed Kovacevic Lecture 3 Department of Mechanical Engineering and Aeronautics Room CG25, Phone: 8780, E-Mail: [email protected] www.staff.city.ac.uk /~ra600/intro.htm Mechanical Analysis and Design ME 2104

Transcript of ME1105 - 1 - Staff Personal Pagesra600/ME2105/Lectures/ME2104-03.pdf · Managing Design (Academic...

  • Ahmed Kovacevic, City University London1

    Project management

    Prof Ahmed Kovacevic

    Lecture 3

    Department of Mechanical Engineering and AeronauticsRoom CG25, Phone: 8780, E-Mail: [email protected]

    www.staff.city.ac.uk/~ra600/intro.htm

    Mechanical Analysis and Design ME 2104

  • Ahmed Kovacevic, City University London2

    Plan for this lecture

    Project management overview Project management tools

    » Work breakdown structures» Team calendars» Gantt charts» Budgets

  • Ahmed Kovacevic, City University London3

    Managing Design (Academic Project Management)

    Design is an activity that can consume significant time and resources

    This lecture outlines various techniques that allow a team to manage and control a design project

    The 3Ss of project management:» Scope

    – To know the goals and to accomplish them» Spending

    – To complete the project within the specified budget» Scheduling

    – To finish the project “on time”

  • Ahmed Kovacevic, City University London4

    Project Management Approach Managing the design process consists of four functions:

    » Planning– Define scope, schedule and spending (the 3Ss)

    » Organizing– Determine who is responsible for each project task

    » Leading - Motivate team by showing that 1) tasks are fair2) division of work is fair and 3) level of work produces satisfactory progress toward goals

    » Controlling– Relies on a sound plan to measure progress and take

    corrective actionsTools that can be applied in these phases are explained

  • Ahmed Kovacevic, City University London5

    Project Management Tools

    Work breakdown structures (planning, organizing)» Determines scope of activities» Hierarchical representation (like a family tree) of all tasks» Work is “broken down” into pieces small enough to estimate

    resources (£, number of persons) and time required Team calendar (planning)

    » Shows time available to the team» Highlights deadlines

    Gantt chart (planning, organizing)» Horizontal bar graph mapping design activities (and their

    duration) against a timeline» Shows parties responsible for activities

  • Ahmed Kovacevic, City University London6

    Work Breakdown Structures (WBS) WBS is considered the most important management

    tool for design projects. It decomposes overall task into smaller, more

    manageable subtasks.As a simple example, consider a spacecraft design:

    PM Tools: What must be done to FINISH the job

    Extraterrestrial Rover

    Propulsion Guidance Power generationScience

    toolsCommuni-

    cations Control

    Robotic arm Abrasion tool

    MicroscopicimagerSpectrometer

    Mars Exploration Rover (MER)

  • Ahmed Kovacevic, City University London7

    Work Breakdown Structures (1)

    Observation 1: Each item that you take to a lower level should be alwaysbroken into two or more subtasks

    PM Tools: What must be done to FINISH the job

    DESIGN

    TASK

  • Ahmed Kovacevic, City University London8

    Work Breakdown Structures (2)

    Observation 2: Break down an activity until you can determine > how long it will take and > who will do it

    PM Tools: What must be done to FINISH the job

    DESIGN

    TASK

  • Ahmed Kovacevic, City University London9

    Work Breakdown Structures (3)

    Observation 3: WBS should be complete in the sense that any activity that consumes resources or time is included

    Observation 4: Any part of the hierarchy of tasks should add up

    PM Tools: What must be done to FINISH the job

    DESIGN

    TASK

  • Ahmed Kovacevic, City University London10

    PM Tools: Keeping track of TIME

    A mapping of deadlines (given to you) onto a traditional calendar

    Also include team -generated deadlines for tasks in the WBS» Becomes an extension of

    the team working agreement

    » Include recurring or routine activities such as team meetings

    Team Calendars

  • Ahmed Kovacevic, City University London11

    Points to keep in mind:» Team calendar should be

    reviewed at each meeting» Times on calendar should

    be consistent with WBS

    Team Calendars

    PM Tools: Keeping track of TIME

  • Ahmed Kovacevic, City University London12

    Gantt Charts The Gantt chart is named after a well known industrial

    engineer, Henry Laurence Gantt During World War I (1910s), he studied manufacturing

    processes and labor utilization to improve the productivity of munitions factories

    A Gantt chart is an easy-to-use, valuable Project Management tool

    It shows, in one table:» Tasks to be completed» Persons responsible» Start, duration, and end times/dates» Activity precedence (what has to be done first, in what order)

    PM Tools: Keeping track of TIME

  • Ahmed Kovacevic, City University London13

    Gantt Chart Example

    For scheduling, it is critical to understand the precedence relationships between tasks» Sequential tasks - Task 1 must be finished before Task 3

    can begin» Parallel tasks - Tasks 3 and 4 can be undertaken

    simultaneously (or in parallel)

    PM Tools: Keeping track of TIME

    A c t i v i t ie s R e s p o n s ib le p a r t yA S O N D J F M A M y J J y A S O N D J F M A M y J J y A S O N DP r o je c t s t a r t d a y < 1 >

    L i t . R e v ie w - P r o d u c t p l a t f o r m & I n f o . m o d e l i n gT e a m

    1 . R e v ie w p r o d u c t c a s e s M a r y , J o h n

    2 .a C h a r a c t e r i z e i n f o r m a t i o n t y p e sJ a n e2 .b I d e n t i f y p r o d u c t c o m m o n a l i t i e sB i l l2 . c E s t a b l i s h p l a t f o r m c a t e g o r ie s M a r y

    3 . D e v e lo p g e n e r a l i z e d f l o w m o d e l T e a m

    4 . A p p ly f lo w m o d e l t o c a s e s t u d ie sB i l l , J o h n

    5 . D e v e lo p c a p t u r e / s t o r a g e / r e t r ie v a l a g e n t sM a r y , J a n e

    6 . D e v e lo p p r o d u c t f a m i l y / p l a t f o r m a g e n t sJ o h n , M a r y

    7 . I m p le m e n t p r o t o t y p ic a l s y s t e m B i l l

    F a c e - t o - f a c e m e e t in g s T e a m < D E T C > < N S F > < > < D E T C > < N S F > < > < D E T C >

    R e s e a r c h t r a n s f e r < > < > < > < > < > < > < >

    2 0 0 42 0 0 3 2 0 0 5

    Sheet1

    200320042005

    ActivitiesResponsible partyASONDJFMAMyJJyASONDJFMAMyJJyASOND

    Project start day

    Lit. Review-Product platform & Info. modelingTeam

    1. Review product casesMary, John

    2.a Characterize information typesJane

    2.b Identify product commonalitiesBill

    2.c Establish platform categoriesMary

    3. Develop generalized flow modelTeam

    4. Apply flow model to case studiesBill, John

    5. Develop capture/storage/retrieval agentsMary, Jane

    6. Develop product family/platform agentsJohn, Mary

    7. Implement prototypical systemBill

    Face-to-face meetingsTeam

    Research transfer

    Sheet2

    Sheet3

  • Ahmed Kovacevic, City University London14

    Budget: Show Me the Money Design project budgets consist of:

    » Research expenses» Materials for prototypes» Materials for your “final” product (really, it is still a prototype)» Value of design team time

    For the upcoming project, you will be allowed only £30» This £30 covers the first three categories of the budget» For this project, you will be judged (to a certain degree) on the

    cost of your “final” product - not to exceed £30» The total cost of the project will exceed that amount if you

    include the value of your time

  • Ahmed Kovacevic, City University London15

    Value of Design Team Time

    A simple algorithm to estimate value of design team time» Costteam = Moverhead * Costdirect» Moverhead is a multiplier that covers fringe benefits, supervision,

    profit and facilities costs to the organization» Costdirect is the money/pay that you, the designer, would see in a

    paycheck» Typical values: Moverhead = 2 – 4

    Costdirect = £15 – 50 /hr

    Even at a minimal wage (£5/hr) for a design team of five for ten hours a week for ten weeks, the cost is £5000-10,000

    PM Tools: Show me the MONEY

  • Ahmed Kovacevic, City University London16

    Conclusion on Budgets Make initial estimates of your

    budget for» Research expenses» Materials for prototypes» Materials for your “final” product

    For value of team time, keep records of hours spent on the project throughout the semester» The bottom line on the value of design

    team time:

    Time is Money!

    PM Tools: Show me the MONEY

    Project managementPlan for this lectureManaging Design �(Academic Project Management)Project Management ApproachProject Management ToolsWork Breakdown Structures (WBS)Work Breakdown Structures (1)Work Breakdown Structures (2)Work Breakdown Structures (3)Team CalendarsTeam CalendarsGantt ChartsGantt Chart ExampleBudget: Show Me the MoneyValue of Design Team TimeConclusion on Budgets