Withdrawable switchgear SF6 circuit-breaker Medium Voltage Distribution MCset 4 - 24 kV Installation instruction November 2012

Transcript of MCset 4 - 24 kV - Schneider...

Page 1: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

Withdrawable switchgear SF6 circuit-breaker

Medium Voltage Distribution

MCset 4 - 24 kVInstallation instructionNovember 2012

Page 2: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing
Page 3: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 1

Content

General 3Glossary 3Symbols 3Recommendations 4Standard tightening torques 5List of bags and accessories 5

Approximatedimensionsandweights 6NIA version 6NIA version with IPX1 protection 7Internal arc version with protection on 3 sides 8Internal arc version with protection on 3 sides, with a ceiling height between 2.8 and 4 m 9Internal arc version with protection on 3 sides with IPX1 protection 10Internal arc version with protection on 4 sides, height under ceiling lower than 4 m 11Internal arc version with protection on 4 sides, in substations with a ceiling height between 2.8 and 4 m 12Internal arc version with protection on 4 sides in a substation with a ceiling height of 2.8 to 4 m with IPX1 protection 13AD4 cubicle (for cubicle entry from above) 14CL4-GL4 cubicles (with upstream CT) 14

Handlinginstructions 15Packaging 15Handling 16Storing 17

Installationandoperationrecommendations 18The switchgear’s resistance to ageing in an MV substation 18Operation and maintenance 18

Unpacking 19

Floorfinishingandcubiclefastening 20Surface condition 20Floor quality 20Description of the fixing rails and accessories 20Placing and adjusting on standard civil engineering works 20Placing and adjusting on earthquake resistant civil engineering works 22

Proceduretodraw-out/draw-inthemobilepart 24Safety rules for use 24Extraction and lowering tool 24Without lowering (extraction table) 24Procedure to draw-out the mobile part 25Procedure to draw-in the mobile part 28Procedure to extract the VTs and opening the MV cable compartment 31Procedure to insert the VT’s and closing the MV cable compartment 35

Accesstotheinteriorofthecubicles 40AD4 - RD4 cubicle 40CL4 cubicle (bus-section) 41CL4 cubicle (bus-section) with upstream CT’s 42GL4 cubicle (bus-riser) 43TT4 cubicle 44DI4 cubicle 45AD4 RHC cubicle (for cubicle entry from above) 46

Page 4: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

2 07897542ENversion 02

Content

Installationinstructions 47Preparation of the cubicle to the positioning 47Adjusting cubicles on standard civil engineering works 48Fastening to the floor on standard civil engineering works 48Fastening to the floor on earthquake resistant civil engineering works 49Verify correct positioning 49Assembly tunnel 50Cubicle coupling 54Installation extension busbar 61Connection of earthing busbar 63End panels assembling 64Fitting the main busbars 691250 A main busbars 702000 / 2500 A main busbars 71Fitting joint covers 72Positioning the joint covers 74

ConnectionoftheLVcables 75LV cables routing 75LV cables connections 76Closing the top entry LV cable steel sheet 76

EarthingcircuitequipotentialconnectionandMVcableearthing 77Starting conditions 77Equipotential connection of the switchboard’s earth to the substation earth 77Connection of MV cables 78One single core or three-core cable per phase 78One to four single core cables per phase 79Three-core cable per phase 79Anchoring supports for MV cables 80Earthing of MV cable shields 81Earthing of MV cable shields (DI4) 81Final operations 82

FittingfusesinDI4cubicle 83

Testsonsite 84Voltage test on the main circuits 84How to prepare the cubicles 84Operations to be carried out on the cubicle to be connected to the testing equipment 85Withdraw the VT fuses 85Close the earthing switch 86Prevent the insertion of the circuit-breaker 87Open the earthing switch 88Restore the possibility of circuit-breaker insertion 89After performing the test 89

Index 90

Page 5: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 3

General

Symbols

SMALToperation

Operation position.

Open earthing switch mechanicalindicator.

Close earthing switch mechanical.

Mobilepart

SF Withdrawable circuit-breaker with SF6 breaking which is used in AD4 and CL4 cubicles

ERT Rack-in or rack-out and removal tool of the mobile parts on the ground

Extractiontable Extraction or insertion table without the removal tool of the mobile parts on the ground

Glossary UF Functionnal Unit (cubicle + mobile part + Sepam)

NIA Basic version, without internal arc withstand

AD4 Incomming / outgoing cubicle

RD4 Incomming / outgoing cubicle (without circuit-breaker)

CL4-GL4 Withdrawable line coupling cubicle

TT4 Mesurement and busbar earthing cubicle

AD4RHB-RHC Cubicle with busbar connection from the top

DI4 Fuse switch outgoing cubicle

TT Voltage transformer

TC Current transformer or current sensor

VPIS Voltage Presence Indicating System

LV Low voltage

MV Voltage class 24 kV

SMALT Earthing switch

BB Busbar

Page 6: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

4 07897542ENversion 02

General

Mobilepartoperation

Operating position.

Racked-in position.

Racked-out position.

Insertion / extraction position.

Recommendations

Height(H)ofceilingfortunnelinstallation

ItisnecessarytohaveaheightofceilingHu2.80mtoinstallatunnel.

Installationabovetheswitchboard All type of equipment installation such as lamp or light are forbidden.

Marking It is compulsory forbidden to walk on the parts bearing this marking.

It is compulsory forbidden to remove the parts bearing this marking when the equipment is energised.

Page 7: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 5

General

Standardtighteningtorques

(nongreasedscrewsandbolts) Screw TorqueinNmØ 6 13

Ø 8 28

Ø 10 50

Ø 12 75

Ø 14 120

Applicationmethods:

The elastic washers placed on the external sides of the pads and busbars ensure better distribution of stress regarding bolts tightened to the recommended torques.

Listofbagsandaccessories Package ContentSwitchboardendandfixingparts

- switchboard end sheets **- tunnels- cubicle fixing rails (lengh: 2m) - bag of screws and expansion pins

Cubiclecomponent*(baglocatedinsideofeachcubicle)

- busbar- bag of screws

Standardsaccessories(baglocatedinsideofthe1stcubicleoftheswitchboard)

- operating crank- identification front plates- civil engineering guide- installation instruction- using instruction

Mobileparttools - ERT or extraction table

Package(maybesupplied)

Content

Spareparts(baglocatedinsideofthe1stcubicleoftheswitchboard)

- fuses, cranks, etc.

Optionalaccessories - earthing truck (independant box)

- phase balance testing device

- mobile part tools: ERT or extraction table (independant box)

* The VT’s fuses are already fitted inside their compartment in the cubicle.** With internal arc version, the switchboard end sheets may be mounted on the cubicles.

Page 8: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

6 07897542ENversion 02

Dimensions AD4 CL4+GL4 TT4 RD4 DI4Width(mm) 900 900 + 900 900

Height(mm) 2325

Depth(mm) 1750 + 40 = 1790

Approximateweights(withoutLVcablesoraccessories) AD4* CL4+GL4 TT4 RD4 DI4Weight(kg) 1300 900 + 500 650 750 550

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

Approximatedimensionsandweights

NAIversion

Page 9: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 7

Approximatedimensionsandweights

NIAversionwithIPX1protection

Dimensions AD4 CL4+GL4 TT4 RD4 DI4Width(mm) 900 900 + 900 900

Height(mm) 2732

Depth(mm) 1750 + 91 = 1841

Approximateweights(withoutLVcablesoraccessories) AD4* CL4+GL4 TT4 RD4 DI4Weight(kg) 1350 950 + 550 700 800 600

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

Page 10: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

8 07897542ENversion 02

Internalarcversionwithprotectionon3sides(wallinstallation)

Approximatedimensionsandweights

Dimensions AD4 CL4+GL4 TT4 RD4 DI4

Width(mm) 900 900 + 900 900

Height(mm) 2325

Depth(mm) 150 + 1750 + 40 = 1940

Approximateweights(withoutLVcablesoraccessories) AD4* CL4+GL4 TT4 RD4 DI4Weight(kg) 1300 900 + 500 650 750 550

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

Page 11: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 9

Dimensions AD4 CL4+GL4 TT4 RD4 DI4Width(mm) 900 900 + 900 900

Height(mm) 2732

Depth(mm) 150 + 1750 + 40 = 1940

Approximateweights(withoutLVcablesoraccessories) AD4* CL4+GL4 TT4 RD4 DI4Weight(kg) 1350 1025 + 625 800 950 700

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

Internalarcversionwithprotectionon3sides,withaceilingheightbetween2.8and4m

Approximatedimensionsandweights

Page 12: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

10 07897542ENversion 02

Approximatedimensionsandweights

Internalarcversionwithprotectionon3sideswithIPX1protection

Dimensions AD4 CL4+GL4 TT4 RD4 DI4Width(mm) 900 900 + 900 900

Height(mm) 2732

Depth(mm) 150 + 1750 + 91 = 1991

Approximateweights(withoutLVcablesoraccessories) AD4* CL4+GL4 TT4 RD4 DI4Weight(kg) 1350 1025 + 625 800 950 700

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

Page 13: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 11

Approximatedimensionsandweights

Dimensions AD4 CL4+GL4 TT4 RD4 DI4Width(mm) 900 900 + 900 900

Height(mm) 2325

Depth(mm) 1900 + 40 = 1940

Approximateweights(withoutLVcablesoraccessories) AD4* CL4+GL4 TT4 RD4 DI4Weight(kg) 1350 1025 + 625 800 950 700

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

Internalarcversionwithprotectionon4sides,heightunderceilinglowerthan4meters

Page 14: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

12 07897542ENversion 02

Dimensions AD4 CL4+GL4 TT4 RD4 DI4Width(mm) 900 900 + 900 900

Height(mm) 2732

Depth(mm) 1900 + 40 = 1940

Approximateweights(withoutLVcablesoraccessories) AD4* CL4+GL4 TT4 RD4 DI4Weight(kg) 1350 1025 + 625 800 950 700

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

Internalarcversionwithprotectionon4sides,insubstationswithaceilingheightbetween2.8and4m

Approximatedimensionsandweights

Page 15: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 13

Approximatedimensionsandweights

Internalarcversionwithprotectionon4sidesinasubstationwithaceilingheightof2.8to4mwithIPX1protection

Dimensions AD4 CL4+GL4 TT4 RD4 DI4Width(mm) 900 900 + 900 900

Height(mm) 2732

Depth(mm) 1900 + 91 = 1991

Approximateweights(withoutLVcablesoraccessories) AD4* CL4+GL4 TT4 RD4 DI4Weight(kg) 1350 1025 + 625 800 950 700

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

Page 16: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

14 07897542ENversion 02

Approximatedimensionsandweights

Dimensions AD4 CL4-GL4Width(mm) 900 900 + 900

Height(mm) 2325 2325

Depth(mm) 2250 + 40 = 2290 2250 + 40 = 2290

Approximateweights(withoutLVcablesoraccessories) AD4* CL4-GL4Weight(kg) 1400 1100 + 500

* with 2 CT’s per phase, circuit breaker and withdrawable VT compartment.

AD4cubicle(forcubicleentryfromabove)

CL4-GL4cubicles(withupstreamCT)

Accessfromtherearisimperativeforthisversion.Recommendeddistance:800mmbetweentherearofthecubicleandthewall.

Accessfromtherearisimperativeforthisversion.Recommendeddistance:800mmbetweentherearofthecubicleandthewall.AccesstoMVcables.

Page 17: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 15

Donotwalkonthetopofpackagedcubicles

Handlinginstructions

Packaging

Standardpackaging

The cubicles are shipped simply placed on a pallet and wrapped in a polyethylene bag.

The cubicles may include or not their circuit-breaker.

Marinepackaging

The cubicles are shipped on a pallet, in a closed crate.

The cubicles may include or not the circuit-breaker.

Page 18: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

16 07897542ENversion 02

Handling

Handlingusingasling

Use a 900 mm minimum width crosspiece between rings.

Attach the four slings to the relevant lifting devices.

As soon as the cubicle is lifted, the pallet can be removed.

CubicleAD4(forcubicleentryfromabove)

CubicleCL4withupstreamCTs

Handlinginstructions

Page 19: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 17

Handlingonrollers

Storing

Store the devices in their original packaging, placed on dry ground or on a material insulating it from moisture.

Prolongedstorage After prolonged storage, thoroughly clean insulating parts before operation.

Handlinginstructions

Beforeputtingthecubicleontherollers,removethepallet.

Page 20: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

18 07897542ENversion 02

Installationandoperationrecommendations

Theswitchgear’sresistancetoageinginanMVsubstationdependson3mainfactors

ThenecessityofcorrectimplementationofconnectionsNew cold retractable or slip-on technology offers ease of installation that favours resistance over time.Their design allows them to used in polluted environments with harsh climatic conditions.

ImpactoftherelativehumidityfactorInstalling a heating device is essential in climates with high relative humidity levels and major temperature differences.Ensure that draughts and / or thermal shocks are avoided in all cubicle compartments in order to avoid the creation of dew points (sources of partial discharges).The equipment must be installed in conformity with the relevant IEC standard. Outside of these normal usage conditions, we recommend contacting Schneider Electric to determine the operations to be carried out as well as their frequency according to the actual service conditions.

Ventilationcontrol:Grid size must be suited to the power dissipated in the substation. These grids must be placed exclusively in the vicinity of the transformer, in order to avoid air circulation on the MV switchboard.

Operationandmaintenance After 6 to 12 month operations, we recommend you to check the busbars and MV cable connection tightening.It should be done with a calibrated torque spanner, adjust to lower torque compare to values indicated in page 6.If no problems are detected and if the busbars and cable connections haven’t been modified, it will not necessary to do again this check. In case of dismantling, the elastic washers must be change and replace by new ones supplied by Schneider Electric.

It is strongly advised to periodically carry out (minimum every 2 years approximately) a few operation cycles on operating devices.Outside normal conditions of use (between -5°C and 40°C , absence of dust, corrosive gas, etc.), it is recommended to examine with our Schneider Electric services centre the steps to be taken, in order to ensure correct functioning of the installation.

Our service centre is at your disposal at any time: - to undergo an installation diagnostic,- to offer you, if need be, suitable maintenance operations,- to offer you maintenance contracts,- to offer you adaptations.

Page 21: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 19

Unpacking

Unpacking

Tools- Fork or ring spanner n.18 (A1 ou A2).

Cubiclesshallbeunpackedincloseproximitytotheerectionsite.

Remove the plastic wrapping and lifting the cubicle by the four anchoring devices. Remove the pallet and lay the cubicle on the floor (see chapter “Handlinginstructions”).

Then remove the four anchoring devices

Remove the screws and the relevant cage nuts except in the case of cubicles provided with end panels where to put the spacer and the screw without removing the nut cage side of the end panel.

Remove packings placed inside the cell.

The circuit breakers are delivered in cubicles in a withdrawn position.

Standardcubicle

AD4,RHC–RHBcubicles,CL4cubiclewithupstreamCT’s

Don’tdismantleanypartsfromthecubicle.

Page 22: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

20 07897542ENversion 02

Floorfinishingandcubiclefastening

Surfacecondition The floor surface must be level (no bumps) and such that a 2 meters rule placed on all surfaces and in every direction shows a clearance of no more than 5 mm.

Floorquality For the rolling of mobile part extraction tools without degrading the floor, it must have a compression withstand u 33 Mpa.

Descriptionofthefixingrailsandaccessories

Cubiclefixing

Standardcivilengineering:- 1 fixing railA (length 2 m),- 4 expansion pins B, - 2 fastening shims C.

Earthquakeresistantcivilengineering:- 2 fixing rails A (length 2 m), - 8 expansion pins B, - 4 fastening shims C.

Placingandadjustingonstandardcivilengineeringworks

Preparation

Drill holes in the floor and the fixing rails.

Tools

Drill. Socket spanner n.13.

Placingthefixingrails

Place and fix the rails to the floor using the supplied expansion pins, screws and washers.Cut the last rail to the required length.

Taketheequipmentfromthecivilengineeringpackageoftheswitchboardpackaging.

Page 23: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 21

Tighteningthefixingrails

LongitudinaladjustmentUsing a water level and using shims before tightening the screws.

Floorfinishingandcubiclefastening

Forthecorrectinstallationofcubicles,itisadvisedtocomplywithatoleranceof±0.1cm/mandamaxgapof±0.3cmonthelengthoftheswitchboard.

Page 24: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

22 07897542ENversion 02

PlacingandadjustingonearthquakeresistantcivilengineeringworksPreparationDrill holes in the floor and the fixing rails.

Tools

Drill.

Placingthefixingrails

Place and fix the rails to the floor using the supplied expansion pins, screws and washers.Cut the last rail the required length.

Tools

Socket spanners n.13.

Floorfinishingandcubiclefastening

Page 25: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 23

LongitudinaladjustmentUsing a water level and using shims before tightening the screws.

Transversaladjustment.Using a spirit level and using shims before tightening the screws.

Floorfinishingandcubiclefastening

Therailsmustbeverysmooth,becauseadjustment-usingactuatorsisnotpossible.

Forthecorrectinstallationofcubicles,itisadvisedtocomplywithatoleranceof±0.1cm/mandamaxgapof±0.3cmonthelengthoftheswitchboard.

Page 26: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

24 07897542ENversion 02

Safetyrulesforuse These tools allow to extract the mobile parts (circuit-breaker, contactor, sectionning truck). The ERT allow to leave the mobile part on the floor.These tools are intended to be used only as an accessory of MCset switchboards.They shall be used when the cubicles have been laid on the floor.They shall not be modified.

Extractionandloweringtool

Overalldimensionsandweights

Weight86 kg

A: crankB: connecting device to the cubiclesC: circuit-breaker supporting railD: locating pins for matching to the cubiclesE: wheel brake

The support C rails might be adjusted independently by an action the leverA one side only.

Withoutlowering(extractiontable)

Overalldimensionsandweights

Weight60 kg

A: connecting device to the cubiclesB: circuit-breaker supporting railC: locating pins for matching to the cubiclesD: wheel brakeE: crank for width adjustmentF: screw for height fixingG: screws for compensation of floor unevenness

Formoredetails:refertothedeviceattachedmanual.

Proceduretodraw-out/draw-inthemobilepart

Page 27: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 25

Proceduretodraw-outthemobilepart

Startingcondition

Cubicle with circuit-breaker in disconnected / test position.

Open the access door to the circuit-breaker compartment.

At the 1st extraction:- Remove the strap part (1). - Remove the block which hold the rod in upper position (2).

Unplug the connector of LV circuits.

Extractionofthemobilepart(procedureisthesamewithanERToranextractiontable)

Move the extraction tool into position in front of the cubicle (take care that the locating pins engage with the holes provided on the cubicle).

Lock the trolley in position by pushing and turning the two latching handles in the indicated way.

After the operation, make sure that the trolley is locked.

Lock the wheels by pressing the brake.

Turn the selector 2 to the position

marked with .Then remove the circuit-

breaker.

Pull it out until it comes against the stops of trolley.

Proceduretodraw-out/draw-inthemobilepart

Duringthisoperationthecircuit-breakerspringscanbetrippedautomatically.

Themobilepartshallbemovewiththeextractiontoolsonly.Donoteapplyeffortontheconnectionarms.Theextractionofthemobilepartshallbedonewhenthecubicleshavebeenlaidonthefloor.

Page 28: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

26 07897542ENversion 02

Return selector to the position .

Unlock the trolley from the cubicle by turning the two handles in the indicated way.

Release the brakes on the trolley wheels.

Take away the trolley (1).

ClosingtheMVdoor

Lower the shutter. To close the door without the circuit-breaker inside: - push the hook A to the top, - push the locking part B in the indicated position, then let A free.

The locking system will reset automatically when the circuit-breaker is inserted.

Proceduretodraw-out/draw-inthemobilepart

Page 29: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 27

Leavingthemobilepartonthefloor(onlywithERT)

Put the circuit-breaker on the ground by turning the crank (2). Set the selector 2 to position .

Take away the trolley.

Proceduretodraw-out/draw-inthemobilepart

Page 30: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

28 07897542ENversion 02

Proceduretodraw-inthemobilepart

Startingconditions

Cubicle: the circuit-breaker compartment door is open.

ERT: the rails of trolley are in the lowered position.

Circuit-breaker: it is on the floor with the selector 2

in the position marked .

ERTMove the trolley under the circuit-breaker until it comes against the stop.

Set selector 2 to position . By turning the crank (1), lift the circuit-breaker up to the insertion level.

InsertionwiththeERTorwithextractiontable

Approach the trolley with the circuit-breaker in front of the cubicle.

Move the trolley into position in front of the cubicle; take care that the locating pins engage with the holes provided on the cubicle.

Proceduretodraw-out/draw-inthemobilepart

Page 31: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 29

Lock the trolley in position by pushing and turning the two latching handles (after the operation, make sure that the trolley is locked).

Lock the wheels by pressing the brakes.

Set the selector 2 to position . Push the circuit-breaker into the circuit-breaker compartment until it stops.

Set selector 2 to position . Unlock the trolley from the cubicle by turning the two handles and then pulling them out.

Release the brakes on the trolley wheels.

Remove the trolley.

Proceduretodraw-out/draw-inthemobilepart

Page 32: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

30 07897542ENversion 02

Push and hold the locking device (A - B).

Plugging-in the connector of LV circuits. (C). If the connector is not properly inserted, the locking device will prevent the door from being closed.

Lift the black shutter located on the back of the door before closing the door.

Proceduretodraw-out/draw-inthemobilepart

Page 33: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 31

Proceduretodraw-out/draw-inthemobilepart

ProceduretoextracttheVTsandopeningtheMVcablecompartment

ForcubiclesequippedwithwithdrawableVTs

Remove the circuit-breaker, see chapter “Proceduretodraw-outthemobilepart”.

Draw-out the VT fuses as per procedures (see chapter “WithdrawtheVTfuses”).

Open the disconnector protecting the VT secondaries placed in the LV compartment.

ToolsCrank supplied.

Tools - flat wrench 10 (A).- flat wrench 13 (B).- ratchet wrench 10 (C1).

Close the earthing switch (see chapter“Closetheearthingswitch”).

We recommend that you lock it in this position.

Loosen the 2 screws using the operating crank handle.

Open the door leading to the MV cable connection compartment.

Page 34: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

32 07897542ENversion 02

Proceduretodraw-out/draw-inthemobilepart

Unbolt the 5 nuts.Disconnect the VT secondaries LV connection connector.

Remove the 2 screws.

Withdraw the closing cross-bar. Extract the VT compartment.

Page 35: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 33

Proceduretodraw-out/draw-inthemobilepart

ToolsCrank supplied.

Open the disconnector protecting the VT secondaries placed in the LV compartment.

Tools - flat wrench 10 (A).- flat wrench 13 (B).- ratchet wrench 10 (D).

CubiclesequippedwithfixedVTs

Close the earthing switch (see chapter“Closetheearthingswitch”).

Loosen the 2 screws using the operating crank.

Open the door leading to the MV cable connection compartment.

Disconnect the VT secondaries LV connection connector.

Close the earthing switch (see chapter“Closetheearthingswitch”).

We recommend that you lock it in this position.

Page 36: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

34 07897542ENversion 02

Proceduretodraw-out/draw-inthemobilepart

Disconnect the connection bar of each VT by unscrewing the nut.

Remove the 5 nuts.

Tohaveaneasieraccessinsidethecubicle,removethebottomsheetofthecircuit-breakercompartmentandthebarriersbetweenphases.

Open the circuit-breaker compartment door.

Remove the bottom plate of the circuit-breaker compartment by unscrewing the 4 fixing bolts.

Remove the barriers between phases following the sequence indicated in the figure.

Close again the circuit-breaker’s and VTs’ compartment doors.

Remove the VT assembly, by running it on its wheels.

Remove the crosspiece.

Page 37: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 35

Proceduretodraw-out/draw-inthemobilepart

Close the door and secure it by means of the 2 bolts, to be tightened with the operating crank.

Remount the bottom plate of the circuit-breaker compartment and fasten it by means of the 4 bolts provided.

Put the circuit-breaker back into its compartment (see chapter “Proceduretodraw-inthemobilepart”).

Put in place the barriers between phases following the sequence indicated in the figure.

CubiclewithoutVTs

ProceduretoinserttheVT’sandclosingtheMVcablecompartment

Open the earthing switch (see chapter “Openearthingswitch”).

ToolsCrank supplied.

Tools - flat wrench 10 (A).- flat wrench 13 (B).- ratchet wrench 10 (D).

Page 38: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

36 07897542ENversion 02

Proceduretodraw-out/draw-inthemobilepart

Replace the VT truck into position.

Remount the bottom plate of the circuit-breaker compartment and fasten it by means of the 4 bolts provided.

Put the circuit-breaker back into its compartment (see chapter “Proceduretodraw-inthemobilepart”).

Put in place the barriers between phases following the sequence indicated in the figure.

CubicleequippedwithwithdrawableVTs

ToolsCrank supplied.

Tools - flat wrench 10 (A).- flat wrench 13 (B).- ratchet wrench 10 (D).

Remount the crosspiece across.

Page 39: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 37

Proceduretodraw-out/draw-inthemobilepart

Fit the 2 screws.

Racked-in the connector of the VT secondaries.

Close the MCCB of the VT secondaries.

Put the VT fuses in the inserted position by following the proper operating sequence (see chapter “ProceduretoinserttheVT’sandclosingtheMVcablecompartment”).

Close the door and secure it by means of the 2 bolts, to be tightened with the operating crank.

Fit the 5 nuts.

Open the earthing switch (see chapter “Openingtheearthingswitch”).

Page 40: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

38 07897542ENversion 02

Proceduretodraw-out/draw-inthemobilepart

Replace the VTs.

Connect the connection bar of each TV by screwing the nut.

Put in place the barriers between phases following the sequence indicated in the figure.

CubicleequippedwithfixedVTs

ToolsCrank supplied.

Tools - flat wrench 10 (A).- flat wrench 13 (B).- ratchet wrench 10 (D).

Remount the bottom plate of the circuit-breaker compartment and fasten it by means of the 4 bolts provided.

Put the circuit-breaker back into its compartment (see chapter “Proceduretodraw-inthemobilepart”).

Remount the crosspiece across.

Page 41: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 39

Proceduretodraw-out/draw-inthemobilepart

Close the MCCB of the VT secondaries.

Fit the 2 screws.

Racked-in the connector of the VT secondaries.

Close the door and secure it by means of the 2 bolts, to be tightened with the operating crank.

Fit the 5 nuts.

Open the earthing switch (see chapter “Openingtheearthingswitch”).

Page 42: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

40 07897542ENversion 02

AD4-RD4cubicle

Access to the rear adjustment bolts through the cable basement or trench.

Access to the main busbar.

Additional cable access from the front.

Access to MV cables, VTs, earthing switch, CT secondaries or toroidal CT, access to the rear adjustment bolts.

Access to the circuit-breaker (AD4).

Access to LV compartment.

Access to the LV terminal boards.

Noaccessfromtherear

Accesstotheinteriorofthecubicles

Page 43: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 41

CL4cubicle(bus-section)

Accesstotheinteriorofthecubicles

Additional access to lower main busbar from the front.

Access to the main busbar.

Access to VTs, access to lower main busbar, access to the rear adjustment bolts.

Access to the circuit-breaker.

Access to the LV compartment.

Noaccessfromtherear

Access to the LV terminal boards.

Page 44: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

42 07897542ENversion 02

CL4cubicle(bus-section)withupstreamCT’s

Accessfromtherearisimperativeforthisversion

Accesstotheinteriorofthecubicles

Additional access to the lower main busbar from the front.

Access to the main bubars.

Access to VT’s and lower main busbar. Access to the rear adjustment bolts.

Access to the circuit-breaker.

Access to the LV compartment.

Access to the LV terminal boards.

Access to the CT’s and to the voltage cable measurment.

Page 45: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 43

GL4cubicle(bus-riser)

Accesstotheinteriorofthecubicles

Additional access to lower main busbar from the front.

Access to the main busbar.

Access to the CT secondaries, access to the lower main busbar, access to the rear adjustment bolts.

Access to the LV compartment.

Access to the LV terminal boards.

Noaccessfromtherear

Page 46: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

44 07897542ENversion 02

TT4cubicle

Accesstotheinteriorofthecubicles

Noaccessfromtherear

Additional access to the lower main busbar from the front.

Access to the main busbar.

Access to the VTs, earthing switch, access to the lower connections, access to the rear adjustment bolts.

Access to the LV compartment.

Access to the LV terminal boards.

Page 47: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 45

DI4cubicle

Accesstotheinteriorofthecubicles

Access to the rear adjustment bolts through the cable basement or trench.

Access to the main busbar (if a single DI4 cubicle is placed side by side to other cubicles, it is easier to get access from the busbar compartments of the adjacent cubicles).

Access to MV cables, earthing switch, access to the rear adjustment bolts.

Access to the LV compartment.

Access to the LV terminal boards.

Noaccessfromtherear

Page 48: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

46 07897542ENversion 02

AD4RHCcubicle(forcubicleentryfromabove)

Accesstotheinteriorofthecubicles

Access to MV cables.

Accessfromtherearisimperativeforthisversion.

AccesstoMVcables.

Access to the rear adjustment bolts through the cable basement or trench.

Additional cables access from the front.

Access to the main busbars.

Access to VT’s, earthing switch and CT’s secondaries. Access to the rear adjustment bolts.

Access to the circuit-breaker.

Access to the LV compartment.

Access to the LV terminal boards.

Page 49: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 47

Installationinstructions

Preparationofthecubicletothepositioning

Cubicle shall be prepared in the erection site. Operations Cubicle PageRacking-out of the mobile part AD4, CL4-GL4 23

Racking-out of the VT’s AD4, CL4-GL4, RD4, TT4 29

Removal of the bottom plate of the MV compartment

AD4, CL4-GL4, RD4, TT4 30

Removal of the barriers between phases AD4, CL4-GL4, RD4, TT4 30

Positioningonthecablebasement

Note: the positioning can be done by rolling or lifting.

Insert the roller (A) under the cubicle by using a lever.

Place the crossing tools across the cable basement.

If the cable basement consists of one uninterrupted opening on the floor, the use of special crossing tools is required.

Place the crossing tools across the cable basement, in the location where the cubicle is to be placed.

Move the cubicle by means of rollers and position it in front of the crossing tools.

Then push the cubicle in position.A:rollersB: crossing tools.

Forcubiclesequippedwithatunnel,itmustbeinstalledbeforeplacingthecubicleinposition(seechapter“Assemblytunnel”).

Page 50: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

48 07897542ENversion 02

Adjustingcubiclesonstandardcivilengineeringworks

Theoperationsdescribedhereaftermustonlybecarriedoutoncethecubicleispositionedoncivilengineeringworks.

Tool2 open end spanners n. 18.

Position the support plate E at the rear of the cubicle by gaining access through the maintenance space.

Place the 2 quick cage nuts B at the rear of the cubicle, by gaining access underneath the cubicle.

Screw the lock nut A on each actuator D, place washer C, then screw the actuators in the quick cage nuts.

Lift the rear of the cubicle by screwing the 2 actuators to level the cubicle.

Fasteningtotheflooronstandardcivilengineeringworks

Note:Remove the front panel (if the cubicle is fitted with VT, it is first necessary to remove them, see the chapter “Accesstotheinteriorofthecubicles”).

To be retrieved from the bag of screws and bolts.

Place the fastening screws at the front of the cubicle and tighten them.

Installationinstructions

Page 51: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 49

Fasteningtotheflooronearthquakeresistantcivilengineeringworks

Note:Remove the front panel (if the cubicle is fitted with VT, it is first necessary to remove them, see the chapter “Accesstotheinteriorofthecubicles”).

To be retrieved from the bag of screws and bolts.

Place the fastening screws at the rear of the cubicle and tighten them.

To be retrieved from the bag of screws and bolts.

Place the fastening screws at the front of the cubicle and tighten them.

Verifycorrectpositioning

Startingsituation

Circuit breaker and VT truck removed from the cubicle. Bottom plate of the circuit-breaker compartment removed from the cubicle.

Tools

- Fork or ring spanner n.10 (A). - Ratchet spanner n.10 (B1).- Spirit level.

Remount the sheet steel bottom plate of the circuit-breaker compartment.

Fasten the 4 fixing bolts.

Check that the cubicle is level by means of a spirit level.

Check that the doors could open and close correctly.

Insert the circuit breaker (see chapter “Proceduretodraw-inthemobilepart”).

Installationinstructions

Page 52: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

50 07897542ENversion 02

Assemblytunnel

Cubicleconfiguration:-internalarcversionon4sides

See drawing ref. S1A6488002 for this version:- internal arc version on 4 sides, incoming from the top,

See drawing ref. S1A6487002 for this version:- internal arc version on 4 sides, incoming from the bottom.

See guide “Installationdrawingfiles-AAA13028EN”.

Take out from bolts and screws bag: - nuts F,- bolts G,- washers E.

Tools- Ratchet spanner n.10 (A).- Fork or ring spanner n.10 (B).

Take out from the wood crate the panels and the roof.Fix the panels at the rear, then at the front of the cubicle.Fix the roof.Respect the assembly as shown on the diagram.Tighten the tunnels only at the end of the complete assembly of tunnels.

Installationinstructions

Internalarcversionon4sides,incomingfromthetop.

Internalarcversionon4sides,incomingfromthebottom.

Page 53: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 51

Cubicleconfiguration:-internalarcversionon4sides,-IPX1protectiondegree.

Take out from bolts and screws bag:- nuts F,- bolts G,- washers E.

Tools- Ratchet spanner n.10 (A).- Fork or ring spanner n.10 (B).

Installationinstructions

Take out from the wood crate the panels and the roof.Fix the panels at the rear, then at the front of the cubicle.Fix the roof.Respect the assembly as shown on the diagram.Tighten the tunnels only at the end of the complete assembly of tunnels.

The assembly is identical to the page 50 with the addition a sheet IPX1, see drawing ref. S1A6488102.

See guide “Installationdrawingfiles-AAA13028EN”.

Page 54: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

52 07897542ENversion 02

Cubicleconfiguration:-internalarcversiononawall

Take out from bolts and screws bag: - nuts F,- bolts G,- washers E.

Tools- Ratchet spanner n.10 (A).- Fork or ring spanner n.10 (B).

Installationinstructions

Take out from the wood crate the panels and the roof.Fix the panel at the front and the plate at the rear of the cubicle.Fix the roof on the front panel and on the wall.Respect the assembly as shown on the diagram.Tighten the tunnels only at the end of the complete assembly of tunnels.

See drawing ref. S1A6488202 for this version:- internal arc version on 3 sides.

See guide “Installationdrawingfiles-AAA13028EN”.

Page 55: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 53

Cubicleconfiguration:-NIA,-IPX1protectiondegree.

Take out from bolts and screws bag:- bolts G,- washers E.

Tools- Ratchet spanner n.10 (A).- Fork or ring spanner n.10 (B).

Installationinstructions

See drawing ref. S1A6581502 for this version:

- NIA, IPX1, incoming from the top.

See guide “Installationdrawingfiles-AAA13028EN”.

Take out from the wood crate the panels and the roof.Fix the panels at the rear, then at the front of the cubicle.Fix the roof.Respect the assembly as shown on the diagram.Tighten the tunnels only at the end of the complete assembly of tunnels.

Page 56: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

54 07897542ENversion 02

Cubiclecoupling

Cubicleconfiguration:-NIA,-AD4,CL4-GL4,TT4,DI4,RD4.

For more details, see drawing ref. 03833104N0.

Take out from bolts and screws bag:- nuts F and I,- bolts G and H,- washers L.

Tools- 2 ratchet spanners n.13 (A) with the relevant extension.

In order to put in place the 2nd cubicle, operate as for the 1st cubicle.Fasten the two cubicles together (9 fixing points).For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.

Installationinstructions

Page 57: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 55

Cubicleconfiguration:-NIA,-incomingfromthetop,-AD4.

For more details, see drawing ref. 03833104N0.

Take out from bolts and screws bag:- nuts F and I,- bolts G and H,

Tools- 2 ratchet spanners n.13 (A) with the relevant extension.- 2 ratchet spanners n.10 (B).

In order to put in place the 2nd cubicle, operate as for the 1st cubicle.Fasten the two cubicles together (12 fixing points).For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.

Installationinstructions

Page 58: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

56 07897542ENversion 02

Cubicleconfiguration:-NIA,-IPX1,-AD4,CL4-GL4,TT4,DI4,RD4.

For more details, see drawing ref. 03833104N0.

For the tunnels assembly, see page 53.

See guide “Installationdrawingfiles-AAA13028EN”.

Take out from bolts and screws bag:- nuts F and I,- bolts G and H,- washers L.

Tools- 2 ratchet spanners n.13 (A) with the relevant extension.- 2 ratchet spanners n.10 (B).

Installationinstructions

In order to put in place the 2nd cubicle, operate as for the 1st cubicle.Fasten the two cubicles together (12 fixing points).For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.Tighten the tunnels only at the end of the complete assembly of tunnels.

Page 59: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 57

Cubicleconfiguration:-internalarcprotectionon3sides,-AD4,CL4-GL4,TT4,DI4,RD4.

For more details, see drawing ref. 03833105N0.

Take out from bolts and screws bag:- nuts F ,- bolts G .

Tools- 2 ratchet spanners n.13 (A) with the relevant extension.

In order to put in place the 2nd cubicle, operate as for the 1st cubicle.Fasten the two cubicles together (9 fixing points).For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.

Installationinstructions

Page 60: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

58 07897542ENversion 02

Cubicleconfiguration:-internalarcprotectionon4sides,-AD4,CL4-GL4,TT4,DI4,RD4,-tunnel.

For more details, see drawing ref. 03833105N0.

For the tunnels assembly, see page 50.

See guide “Installationdrawingfiles-AAA13028EN”.

Take out from bolts and screws bag:- nuts F and I,- bolts G and H,- washers L.

Tools- 2 ratchet spanners n.13 (A) with the relevant extension.- 2 ratchet spanners n.10 (B).

In order to put in place the 2nd cubicle, operate as for the 1st cubicle.Fasten the two cubicles together (27 fixing points).For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.Tighten the tunnels only at the end of the complete assembly of tunnels.

Installationinstructions

Internalarcversionon4sides,incomingfromthetop.

Internalarcversionon4sides,incomingfromthebottom.

Page 61: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 59

Cubicleconfiguration:-internalarcprotectionon4sides,-incomingfromthetop,-AD4.

For more details, see drawing ref. 03833105N0.

Take out from bolts and screws bag:- nuts F and I,- bolts G and H.

Tools- 2 ratchet spanners n.13 (A) with the relevant extension.- 2 ratchet spanners n.10 (B). In order to put in place the 2nd cubicle, operate as for the 1st cubicle.

Fasten the two cubicles together (12 fixing points).For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.

Installationinstructions

Page 62: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

60 07897542ENversion 02

Cubicleconfiguration:-internalarcprotectionon4sides,-IPX1protectiondegree,-AD4,CL4-GL4,TT4,DI4,RD4.

For more details and for the following version, see drawing ref. 03833105N0:- internal arc protection 3 sides, tunnel,- internal arc protection 4 sides,- internal arc protection 4 sides, tunnel, incoming from the top.

Take out from bolts and screws bag:- nuts F and I,- bolts G and H,- washers L.

Tools- 2 ratchet spanners n.13 (A) with the relevant extension.- 2 ratchet spanners n.10 (B).

In order to put in place the 2nd cubicle, operate as for the 1st cubicle.Fasten the two cubicles together (30 fixing points).For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.Tighten the tunnels only at the end of the complete assembly of tunnels.

Installationinstructions

Tunnelcoupling:

Page 63: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 61

Installationinstructions

Cubicleconfiguration:-1250AAD4andRD4,-Entrybusbarfromthetop.

Installationextensionbusbar

Takeoutfromboltsandscrewsbag:- 3 washers Ø12 HUA12584(C),- 3 screws M12x35 21528282(D),- 36 plastic rivets 03829823N0.

Tools:- Allen wrench.

Operatinginstructions:- Assemble the extension bars,- Add the protection covers.

A: 3 insulator supports 03829853N0B: 3 sheated connection bars HRB82349C: 3 washers Ø12 HUA12584D: 3 screws M12x35 21528282E: 3 sheated bars HRB82345F: 36 plastic rivets 03829823N0G: 3 covers junction 03833387N0.

Torque:- Screws M12x35 21528282 (D): 7.5 daNm.

Page 64: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

62 07897542ENversion 02

Installationinstructions

Cubicleconfiguration:-2500AAD4andRD4,-Entrybusbarfromthetop.

Takeoutfromboltsandscrewsbag:- 3 washers Ø12 HUA12584(C),- 3 screws M12x70 V1181270 (D),- 24 plastic rivets 03829823N0.

Tools:- Allen wrench.

Operatinginstructions:- Assemble the extension bars,- Add the protection covers.

A: 3 insulator supports 03829853N0B: 6 sheated connection bars HRB82349C: 3 washers Ø12 HUA12584D: 3 screws M12x70 V1181270E: 3 sheated bars HRB82345F: 3 sheated bars HRB82347G: 24 plastic rivets 03829823N0H: 3 covers junction 03833387N0.

Torque:- Screws M12x70 V1181270 (D): 7.5 daNm.

Page 65: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 63

Connectionofearthingbusbar

Take out from bolts and screws bag:- nuts I,- bolts H,- washers E.

Tools- 2 ratchet spanners n.16 (A) with the relevant extension.- Ring spanner n.16 (B).- Torque spanner (C).

For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.

Tightening torques 30 Nm.

Installationinstructions

Page 66: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

64 07897542ENversion 02

Endpanelsassembling

Cubicleconfiguration:-NIA.

For more details, see drawing ref. 03835598N0.

Take out from bolts and screws bag:- bolts F-G-H,- nuts I,- washers L-M-N.

: G + I + L

: H + I + L

: F + I + L

: G + L

: H + L

: H + I + M + N

Tools- 2 ratchet spanners n.10 (A) with the relevant extension.

Operatinginstructions:- Position the profile C and fix them as show.- Position the panel D and fix them in the upper locations.- Position the panel E and fix them in the upper locations.- Finish the fixing of the 2 panels as show.- Apply the adhesive plate B on panel D.

- Repeat the operation for the right side.

For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.

Installationinstructions

Page 67: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 65

Cubicleconfiguration:-NIA,-incomingfromthetop,-AD4.

For more details, see drawing ref. 03837100N0.

Take out from bolts and screws bag:- bolts F-G-H,- nuts I,- washers L-M-N.

: G + I + L

: H + I + L

: F + I + L

: G + L

: H + L

: H + I + M + N

Tools- 2 ratchet spanners n.10 (A) with the relevant extension.

Operatinginstructions:- Position the profile C and fix them as show.- Position the panel D and fix them in the upper locations.- Position the panel E and fix them in the upper locations.- Finish the fixing of the 2 panels as show.- Position the panel O and fix them as show.- Apply the adhesive plate B on panel D.

- Repeat the operation for the right side.

For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.

Installationinstructions

Page 68: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

66 07897542ENversion 02

Installationinstructions

Cubicleconfiguration:-Internalarcprotectionon3sides.

For more details, see drawings: - S1B5688102 : left end plates assembly- S1B5688202 : right end plates assembly

See guide “Installationdrawingfiles-AAA13028EN”.

Tools- 2 ratchet spanners n.10 (B) with the relevant extension.

Take out from bolts and screws bag:

A:screw HM6x16B:screw HM6x16C:screw HM6x16

D:nut HM6

E:washer Ø 6F:washer Ø 12

G:rivet TR 6.5x14.1H:rivet TR 6.5x20.3

I:cage nut M8J:cage nut M6x9.5

Operatinginstructions:- Position the 3 profiles L/M/N and fix them,- Position the cover plate of the busbar O and fix,- Position the end plate P and fix,- Position the end plate Q and fix,- Position the vents holes R and S and fix them.

- Repeat the operation for the right side.

For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.

Page 69: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 67

Tools- 2 ratchet spanners n.10 (B) with the relevant extension.

Installationinstructions

Cubicleconfiguration:-Internalarcprotectionon4sides.

For more details, see drawings: - S1B5688102 : left end plates assembly- S1B5688202 : right end plates assembly- S1A6487502 : left end panels assembly- S1A6487702 : right end panels assembly

See guide “Installationdrawingfiles-AAA13028EN”.

Take out from bolts and screws bag:

Operatinginstructions:- Position the 3 profiles L/M/N and fix them,- Position the cover plate of the busbar O and fix,- Position the end plate P and fix,- Position the end plate Q and fix,- Position the vents holes R and S and fix them.- Position the cover plate of the tunnel T and fix.

- Repeat the operation for the right side.

For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.

A:screw HM6x16B:screw HM6x16C:screw HM6x16

D:nut HM6

E:washer Ø 6F:washer Ø 12

G:rivet TR 6.5x14.1H:rivet TR 6.5x20.3

I:cage nut M8J:cage nut M6x9.5

Page 70: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

68 07897542ENversion 02

Installationinstructions

Cubicleconfiguration:-internalarcprotectionon4sides-incomingfromthetop.

For more details, see drawings: - S1B5688102 : left end plates assembly- S1B5688202 : right end plates assembly- S1A6487802 : assembly of the finition rear panels incoming from the top.

See guide “Installationdrawingfiles-AAA13028EN”.

Tools- 2 ratchet spanners n.10 (B) with the relevant extension for one.

Take out from bolts and screws bag:

A:screw HM6x16B:screw HM6x16C:screw HM6x16K:screw HM6x20

D:nut HM6

E:washer Ø 6F:washer Ø 12

G:rivet TR 6.5x14.1H:rivet TR 6.5x20.3

I:cage nut M8J:cage nut M6x9.5

Operatinginstructions:- Position the 3 profiles L/M/N and fix them,- Position the cover plate of the busbar O and fix,- Position the end plate P and fix,- Position the end plate Q and fix,- Position the vents holes R and S and fix them.- Position the cover plate of the tunnel U and fix.

- Repeat the operation for the right side.

For access to the fixing points, see the chapter “Accesstotheinteriorofthecubicles”.

Page 71: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 69

Fittingthemainbusbars

For more details, see drawing ref. 03835661N0.

For access to busbars, see the chapter “Accesstotheinteriorofthecubicles”.

Tools- Fork or ring spanner n. 18 (A). - 2 ring spanners n.18 (B1) or ratchet spanners n.18 (B2). - torque spanner (C).

Cubicle type AD4-CL4-GL4-TT4-RD4 and DI4.

Cubicle type CL4 and GL4

Fit the main busbars between the 2 cubicles.

Insert the bolts and tighten them (to be recommended tightening value).

This procedure shall be repeated for any cubicle added to the switchboard.

1:self-locking nut2:nut3:washer4: screw

Installationinstructions

Page 72: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

70 07897542ENversion 02

1250Amainbusbars

630and1250Atee-connections

Mainbusbars–topview

Lowermainbusbars–topview(CL4-GL4)

Installationinstructions

Page 73: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 71

2000/2500Amainbusbars

2000/2500Atee-connections

2000/2500Atee-connections

630/1250Atee-connections Mainbusbars–topview

Lowermainbusbars–topview

Lowermainbusbars–topview(CL4-GL4)

Installationinstructions

Page 74: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

72 07897542ENversion 02

Fittingjointcovers

For more details, see drawing ref. 03835661N0.

Choosingproperjointcovers

Choose the proper joint cover type according to the needs of each cubicle of the switchboard as shown in the following drawing.Tools

Tool- Stanley knife.

right

sid

e en

dor cu

bicl

e A

D4

right

sid

e en

d ou

tgoi

ng y

630

A

orcu

bicl

e D

I4

right

sid

e en

d ou

tgoi

ng y

630

A

or

cubi

cle

TT4

right

sid

e en

d y

630A

cubi

cle

TT4

in a

ny m

iddl

e po

sitio

n y

630A

cubi

cle

AD

4 in

any

mid

dle

posi

tion

cubi

cle

CL4

cubi

cle

AD

4 in

any

mid

dle

posi

tion

outg

oing

y 6

30A

cubi

cle

DI4

in

any

mid

dle

posi

tion

outg

oing

y6

30A

cubi

cle

TT4

left

end

pane

l y

630A

or

cubi

cle

DI4

le

ft si

de e

nd

outg

oing

y 6

30A

or

cubi

cle

AD

4 le

ft si

de e

nd

outg

oing

y 6

30A

or

cubi

cle

AD

4 le

ft si

de e

nd

right side end panel left side end panel

Cuttingjointcovers

Cut the joint covers as shown in the drawings in this page and in the following one.

03833376N0

4th cut

3rd cut 2nd cut

1st cut1st cut

right end

2nd cut

right end

3rd cut

left end

4th cut

right end

1st + 4th cut

intermediate

2nd + 3rd cut

intermediate

Installationinstructions

Page 75: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 73

4th cut 1st cut

3rd cut 2nd cut

5th cut

1st cut

right end

2nd cut

right end

3rd cut

left end

4th cut

right end

1st + 4th cut

intermediate

2nd + 3rd cut

intermediate

2nd + 5th cut

right end left end

2nd + 3rd + 5th cut

intermediate

1st cut 2nd cut

1st cut

right end

2nd cut

right end

1st + 2nd cut

intermediate

without cut 1st + 3rd cut 2nd + 4th cut

1st cut 2nd cut

3rd cut 4th cut

Installationinstructions

Page 76: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

74 07897542ENversion 02

Clip

Positioningthejointcovers

Open the joint cover and put it into position on the busbar joint (for the joint covers of the 2500 A busbars, to put screws + washers + nuts nylon to close them).

Close it and fix by using the proper pins.

Closing the MV cable compartment.

Replace the VT truck into position (see the chapter “ProceduretoinserttheVT’sandclosingtheMVcablecompartment”).

Installationinstructions

Page 77: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 75

ConnectionoftheLVcables

LVcablesrouting

Entryfromthebottom.

Entry from the bottom in every single cubicle.

LV cables shall be run to the LV compartment inside the vertical duct on the right end side provided for every single cubicle.

To install the LV cables in the vertical duct, you should extract the circuit breaker and the VT’s (see the chapters “Proceduretodraw-outthemobilepart” and “ProceduretoextracttheVTsandopeningtheMVcablecompartment”).

Maximum entry section available for LV cables.

Entryfromthetop.

Tools

- Socket spanners n.10.

- Drill.

Remove the 2 fixing bolts (1) of the LV entry steel sheet.

Make a hole in the sheet according to the number and type of cables.

Install the grommets (not supply) on the sheet and insert the cables.

Remount the metal sheet for LV cables.

Page 78: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

76 07897542ENversion 02

LVcablesconnections

Tools- Socket spanners n.10.

To reach the terminal blocks of the LV cables, take off the top front sheet metal (remove the 6 fixing bolts).

Connect the cables to the terminal blocks according to the schematic diagrams.

ClosingthetopentryLVcablesteelsheet

To keep the panel protection degree between 2 cubicles, the top entry LV cable sheet must be install:- on the right for all cubicles,- on the left on the cubicle positioned at the right side end of the switchboard.

To make an easier installation, the fixing holes are oblong.

ConnectionoftheLVcables

Page 79: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 77

EarthingcircuitequipotentialconnectionandMVcableearthing

Startingconditions If the MV cables have not been connected at the erection of the switchboard, in order to get access to the connecting terminals, it is necessary to carry out the following operations:- Remove circuit-breakers and VTs (both fixed and withdrawable versions)(see the chapter “Proceduretodraw-outthemobilepart”).- Remove barriers between phases and the bottom plates of the circuit-breaker compartment (see the chapter “ProceduretoextracttheVTsandopeningtheMVcablecompartment”).

Equipotentialconnectionoftheswitchboard’searthtothesubstationearth

After connecting the earth links between cubicles, the earth circuit shall be bonded to the substation earth. To that purpose, the earth conductor is provided with holes suitable for M10 bolted connections. The link to the substation earth can be ran through an unused cable grommet.

Tools- Ratchet spanner n.16 (A1).- Fork or ring spanner n.16 (B).

Page 80: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

78 07897542ENversion 02

ConnectionofMVcables

General

Remove the bottom metal plates in the cable compartment.

Cut the cable grommets according to the number and diameter of cables.

In order to terminate the MV cables, see the relevant manufacturer’s instructions.

Fit them to the cables.

Onesinglecoreorthree-corecableperphase

The instructions refer to one phase; repeat the procedure for the other two.

Tools- 2 fork or ring spanners n.18 (A).- Torque spanner (B).

Bolt the cable lugs to the proper connecting terminal, using the grommets the closest to the rear (tighteningtorque50Nm).

EarthingcircuitequipotentialconnectionandMVcableearthing

Page 81: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 79

Onetofoursinglecorecablesperphase

The instructions refer to one phase; repeat the procedure for the others.

Tools- Fork or ring spanner n.13 (A).- 2 fork or ring spanners n.18 (B).- Torque spanner (C).

Bolt the cable lug to the proper connecting terminal.

Insert the cable one by one starting from the one closest to the rear.

Tightento50Nm.

Example of terminals (suggested by Schneider Electric) compatible for cable 630 mm²: -Raychem - type TMPP, -Pirelli - type STI-GT, -F&G - type Typ AV 20 E. Cable-terminals: -Cembre - series A-M.

Three-corecableperphase

In order to terminate the cables, see the relevant manufacturer’s instructions.

Cut the cable grommets according to the number and diameter of cables.

Run the three-core cable through the toroidal CT (if requested).

EarthingcircuitequipotentialconnectionandMVcableearthing

Page 82: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

80 07897542ENversion 02

AnchoringsupportsforMVcables

The operation is the same for all types of cables.

Takeofffromthecubiclecomponentspackage: the metal bottom plates, the cable anchoring supports, the crosspiece to fix the anchoring supports, the screws bag.

Tools- Fork or ring spanner n.13.

For access to the cable compartment (see the chapter “Accesstotheinteriorofthecubicles”).

Take care to not hurt the cable isolating when you clamp the anchoring support.

Fit the metal bottom plates.

Unused holes shall be closed with cable grommets (not cut).

1: fixing point for the crosspiece.

Fit the crosspiece on the bottom plate (1 bolt – nuts assembling).

Fit the anchoring supports on the cable according the picture above for 3 single core cables.

Fit the anchoring supports on the cable according the picture above for 1 three-core cables.

EarthingcircuitequipotentialconnectionandMVcableearthing

Page 83: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 81

Rear Rear

Front Front

EarthingofMVcableshields

The earth braids or wires shall be connected to the principal earth conductor to the back provided in each cable compartment.

In the presence of toroidal CTs, take care to run the earthing connection through the CT before fixing it.Example: one cable per phase, 3 braids or wires to connect.

Example: one cable per phase, 3 braids or wires to connect.

Two cables per phase, 6 braids or wires to connect.

EarthingofMVcableshields(DI4)

The earth braid shall be connected to the earth bar on the rear of the switchboard.

EarthingcircuitequipotentialconnectionandMVcableearthing

Page 84: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

82 07897542ENversion 02

Finaloperations

VTtruckreplacing For a description of VT truck replacing, see the chapter “ProceduretoinserttheVT’sandtoclosetheMVcablecompartment”.

Insertionofcircuit-breaker For a description of insertion of circuit-breaker, see the chapter “Proceduretodraw-inthemobilepart”.

EarthingcircuitequipotentialconnectionandMVcableearthing

Page 85: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 83

FittingfusesinDI4cubicle

The striker end of the fuse is marked. The fuse characteristics and direction of mounting are printed on the fuse.

Turn the fuse so that the label is in front (striker at the top end).

Insert the bottom of the fuse all the way into the lower annular contact.

Fit the upper part of the fuse do not forget to draw by hand the upper field repartitor (A).

Verify the correct mounting of the upper field repartitor (A).

Turn the fuse so that the label appears (B) in front.

To select fuses, consult the catalog reserved for them.

For different types of fuse, please contact SchneiderElectric.

InstallFUSARCtypefuseswithmediumtypestrikesaccordingtoIEC32-3IEC282-1andDIN43-625.

Startstatus

Open the MV compartment.

Insert in first the fuse of the farthest phase.

Checkingtheconditionofthefusesbeforeassemblingthem.

Whenchangingafuse,changeall3fuses.

Donotre-usedfusesthathavealreadybeenused.

Page 86: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

84 07897542ENversion 02

Testsonsite

Voltagetestonthemaincircuits After erection, the equipment shall be tested in order to check the correct installation. The power-frequency test voltage shall be 80% of the rated test value (40kV rms), because the cubicles have already been tested in Schneider Electric factory at 100% of the voltage rated value) and shall be applied to each phase conductor of the main circuit for 1 minute earthing the other two phase conductors.

CTs secondaries shall be short-circuited at the LV terminal boards (if the auxiliary circuits are open).The leads from the testing equipment shall be connected to the MV cable lugs of a cubicle. This requires the opening of a lower door during the test for passing the above-mentioned leads.During the voltage tests, all the cubicle shall be fitted with the relevant circuit-breakers. The circuit-breakers shall be plugged in service position and closed. Since hand closing is not permitted with closed doors, a special procedure is required (see below) when auxiliary power supply is not available.Obviously, the MV cables shall be disconnected and the earthing switch shall be opened.

Howtopreparethecubicles

Operationstobecarriedoutoncubiclesnotdirectlyconnectedtothetestingequipment

For a complete description of the following operations, please consult the SF circuit-breaker instruction for use handbook. - Circuit-breaker in disconnected position and the compartment door open. - Lift the locking rod A located on the top of the circuit-breaker mechanism.- Insert spacer U to keep the rod in raised position.- Push the circuit-breaker to the service position and remove spacer U.- Charge the closing spring of the circuit-breaker and close it by pressing pushbutton “ I ”.

Thetestconfigurationrequiressomelockstodefraud.Theseoperationsshouldbeperformedonlybyspecialists.Itisimperativetofollowtheproceduresdescribedbelow.Voltagetransformersshouldbedisconnected.Inthepresenceoflightning,thelattermustbedisconnectedduringthetestvoltagefrequency,toavoidseriousdamage.

NB: In cubicles equipped with VTs withdrawable fuse version, disconnect the fuses. In cubicles equipped with fixed VTs, disconnect the VTs power supply primary circuit.

Page 87: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 85

Operationstobecarriedoutonthecubicletobeconnectedtothetestingequipment

StartingconditionsThe circuit-breaker is in disconnected position, or in test / disconnected position or removed from the cubicle.

Remove the possible keys or padlocks preventing the operation of the earthing switch.

Verifythatthevoltageindicatinglampsareoff.

WithdrawtheVTfuses

StartingconditionsSelector 6 in position

Set selector 6 to . This operation requires first to pull outward the selector and then to turn it.

ThisoperationturnsofftheCT’ssecondaries.

Insert the crank into hole 7 and turn counter clockwise until further rotation becomes impossible.

Set selector 6 to withdrawn position .

The symbols marked on the blue front cover of the circuit-breaker summarise the above-mentioned procedure.

Testsonsite

Page 88: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

86 07897542ENversion 02

Closetheearthingswitch

Push the pushbutton of the earthing switch electromechanical lock. If the cubicle is not equipped with this option, go directly to the following sequence.

Set selector 4 to .

This operation requires first to pull outward the selector and then to turn it.

Insert the crank into hole 5 and turn it clockwise until the earthing switch position indicator reads “on”.

Turn selector 4 clockwise to position I.

The earthing switch is in closed position. The MV cables are short-circuited and earthed. The selector in this position prevents the insertion of the circuit-breaker.

The symbols marked on the yellow front cover summarise the above-mentioned procedure. For more protection, it is possible to prevent the insertion of the circuit-breaker by setting the selector P as shown in the following drawing.

Testsonsite

Page 89: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 87

Preventtheinsertionofthecircuit-breaker

OpentheVTcompartmentdoor

Set selector P to .

Remove the 2 screws indicated in the figure and open the lower door.

Make ineffective the interlock preventing the opening of the earthing switch with open door by entering the slot indicated with a screwdriver and pushing it downwards. This allows to introduce the operating handle into the hole 5 and the earthing switch open.

Testsonsite

Push the pushbutton of the earthing switch electromechanical lock. If the cubicle is not equipped with this option, go directly to the following sequence.

Theoperationdescribedisallowedonlyfortestingconfiguration.Thisoperation,performedwhentheswitchboardisinservice,isextremelydangerousbecauseitmakestheoperatorreachtheliveparts.

Page 90: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

88 07897542ENversion 02

Opentheearthingswitch

Set selector 4 to . This operation requires first to pull outward the selector and then to turn it.

Insert the crank into hole 5 and turn its counter clockwise until the earthing switch position indicator reads “off”.

Set selector 4 to position “O”.

The earthing switch is in open position. The symbols marked on the yellow front cover summarise the above-mentioned procedure.

Testsonsite

Push the pushbutton of the earthing switch electromechanical lock. If the cubicle is not equipped with this option, go directly to the following sequence.

Page 91: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 89

Push the pushbutton of the earthing switch electromechanical lock. If the cubicle is not equipped with this option, go directly to the following sequence.

Restorethepossibilityofcircuit-breakerinsertion

Set selector P in horizontal position

With the circuit-breaker in disconnected position and the compartment door open, lift the locking rod A located on the top of the circuit-breaker mechanism.Insert spacer U to keep the rod in raised position.

Push the circuit-breaker to the service position and remove spacer U.

Charge the closing spring of the circuit-breaker and close it by pressing pushbutton “I”.

Connect the leads from the testing equipment to the MV cable lugs.

Afterperformingthetest Move the circuit-breaker to the disconnected position.Close the earthing switch.Disconnect the test equipment.

In the presence of a VT truck, reinstall him:

- Remount the panel and fixing it by tightening the two screws.- Open the earthing switch.- Plug-in the VT fuses.

Testsonsite

Page 92: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

90 07897542ENversion 02

AAD4 cubicle (for cubicle entry from above) 14AD4 - RD4 cubicle 40AD4 RHC cubicle (for cubicle entry from above) 46Adjusting cubicles on standard civil engineering works 48 After performing the test 89 Anchoring supports for MV cables 80 Assembly tunnel 50

B1250 A main busbars 702000 / 2500 A main busbars 71

CCL4 cubicle (bus-section) 41CL4 cubicle (bus-section) with upstream CT’s 42 CL4-GL4 cubicles (with upstream CT) 14Close the earthing switch 86 Closing the top entry LV cable steel sheet 76Connection of earthing busbar 63 Connection of MV cables 78 Cubicle coupling 54

DDescription of the fixing rails and accessories 20DI4 cubicle 45

EEarthing of MV cable shields 81Earthing of MV cable shields (DI4) 91 End panels assembling 64 Equipotential connection of the switchboard’s earth to the substation earth 77 Extraction and lowering tool 24

FFastening to the floor on standard civil engineering works 48Fastening to the floor on earthquake resistant civil engineering works 49 Final operations 82 Fitting joint covers 72 Fitting the main busbars 69 Floor quality 20

GGlossary 3GL4 cubicle (bus-riser) 43CL4-GL4 cubicles (with upstream CT) 14

HHandling 16How to prepare the cubicles 84

IInstallation extension busbar 61 Internal arc version with protection on 3 sides 8Internal arc version with protection on 3 sides, with a ceiling height between 2.8 and 4 m 9Internal arc version with protection on 3 sides with IPX1 protection cubicle 10Internal arc version with protection on 4 sides, height under ceiling lower than 4 m 11

Index

Page 93: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

version 0207897542EN 91

Index

IInternal arc version with protection on 4 sides, in substations with a ceiling height between 2.8 and 4 m 12Internal arc version with protection on 4 sides in a substation with a ceiling height of 2.8 to 4 m with IPX1 protection cubicle 13

LList of bags and accessories 5LV cables connections 76 LV cables routing 75

NNIA version 6NIA version with IPX1 protection cubicle 7

OOne single core or three-core cable per phase 78One to four single core cables per phase 79 Open the earthing switch 88Operation and maintenance 18 Operations to be carried out on the cubicle to be connected to the testing equipment 85

PPackaging 15 Placing and adjusting on standard civil engineering works 20Placing and adjusting on earthquake resistant civil engineering works 22 Positioning the joint covers 74 Preparation of the cubicle to the positioning 47Prevent the insertion of the circuit-breaker 87Procedure to draw-out the mobile part 25Procedure to draw-in the mobile part 28Procedure to extract the VTs and opening the MV cable compartment 31Procedure to insert the VT’s and closing the MV cable compartment 35

RRecommendations 4 Restore the possibility of circuit-breaker insertion 89

SSafety rules for use 24 Standard tightening torques 5 Starting conditions 77Storing 17 Surface condition 20Symbols 3

TThe switchgear’s resistance to ageing in an MV substation 18 Three-core cable per phase 79TT4 cubicle 44

VVerify correct positioning 49 Voltage test on the main circuits 84

WWithdraw the VT fuses 85Without lowering (extraction table) 24

Page 94: MCset 4 - 24 kV - Schneider Electricmt.schneider-electric.be/Main/MCset_Fluair400/instructions/... · MCset 4 - 24 kV Installation instruction ... MV Voltage class 24 kV SMALT Earthing

07897542EN - REV. 02

SchneiderElectricIndustriesS.A.SHead Office35 rue Joseph MonierCS 30323 92506 Rueil-Malmaisonwww.schneider-electric.com

11/2012

0789

7542

EN

- R

EV.

02

a S

chne

ider

Ele

ctric

Indu

strie

s S

AS

– A

ll rig

hts

rese

rved

.

As standards, specifications and designs change from time to time, please ask for confirmation of the information given in this publication. This document has been printed on ecological paper.

Publishing: Schneider Electric Industries SAS.Design: Profil.Printing:

SchneiderElectricgroupservicecentersaretheretoprovide:- engineering and technical assistance,- commissioning,- training,- preventive and corrective maintenance,- adaptation work,- spare parts.

CallyoursalesrepresentativewhowillputyouintouchwithyournearestSchneiderElectricgroupservicecenterordirectlycallthefollowingtelephonenumber:+33(0)476576060GrenobleFrance.