McKinsey & Company report on CU construction

download McKinsey & Company report on CU construction

of 94

description

McKinsey & Company report on CU construction

Transcript of McKinsey & Company report on CU construction

  • Pre-Decisional - Proprietary and Confidential

    Developing Capital Excellence

    Full report January 2016

  • 1 Pre-Decisional - Proprietary and Confidential |

    Executive summary (1/2)

    1 Budget performance based on initial Vice-chancellor approval limit for projects, not legislative approval 2 Compared to original estimated completion date in program planning

    Diagnostic CU Boulder makes significant investments in capital projects and is exploring ideas and opportunities to improve efficiency and effectiveness in the execution of these projects

    Completed 1900+ Minor and Outlay projects over the past five years routinely fall under budget similar to other public organizations, accounting for about 18% of total budget value

    Completed 30 Major projects (those above $2M), which account for 80%+ of the total spend. Approximately 8 projects requiring additional spending limit were typically those impacted by accelerated timeline, scope changes, or decision delays

    Interviews with over 40 personnel across all stakeholder groups, review of selected projects, and analysis of available documentation on processes surfaced opportunities for increased excellence: a) Capital planning: Right-time commitment of funds in the project planning stage to align with available information

    on scope and schedule b) Contracting methodology: Provide clear guidelines for the project delivery method or contracting terms to

    manage owner risk c) Communication: Proactively manage risks through increased project tracking and clarity in communicating

    progress with appropriate stakeholders d) Project Manager workforce: Enhance PM workforce execution through structured training and onboarding

    processes Recommendations four themes have emerged as opportunities for increasing capital excellence based on the

    above diagnostic: Develop a clear, well-documented, and scalable stage gate process to drive capital investment success Adopt clear guidelines in contracting strategy to address project risk based on project scope, target cost, expected

    delivery schedule, market conditions, and internal capability Deploy project controls to drive transparency of cost, schedule, and milestones during project execution thus

    increasing consistency Train and retain the Project Manager workforce to ensure best practices adoption and execution in project delivery

  • 2 Pre-Decisional - Proprietary and Confidential |

    Executive summary (2/2)

    Implementation CU Boulder has the opportunity to transform its capital program and potentially capture up to 15% in planned capital spend

    In addition to the efficiencies captured, the implementation of the recommendations would bring other performance and health benefits to CU Boulder including: Performance: improve pipeline management; ability to attract best contractors; ability to anticipate and

    resolve performance issues Health: improve relationships across stakeholders; increase in morale, accountability and ownership;

    heighten value proposition to current and potential workforce

    Though current recommendations focus primarily on streamlining project delivery, CU Boulder can engage in a broader set of available strategies for capital excellence which could potentially result in even higher savings

    Athletics Complex project review reveals that the Athletics Complex faced several challenges in scope and schedule management due to complex, often unclear, multi-party interactions at an accelerated pace

    Scope misalignment between Athletics, designer, and PD&C resulted in ongoing changes and cost escalations throughout the project lifecycle

    High staff turnover both internal and external to PD&C created coordination and communication challenges given lack of continuity in an already fast-tracked project

    In order to prevent future costs, project closeout and quality assurance is an important final step and may require additional support to supplement capacity of existing team structure

  • 3 Pre-Decisional - Proprietary and Confidential |

    Over the past 5 years, CU Boulders capital spend has been concentrated on Major projects with a valued budget of ~$870M

    302

    980

    957

    Total budget on projects1 Number of projects

    Projects over $2M Athletics Complex Systems biotechnology

    building Recreation facilities

    improvements

    Projects between $25k-$2M Food service renovation Replace boilers, roof Lab renovation

    Projects under $25k Sound proofing Temporary cooling Fire alarm upgrade

    Examples

    PRELIMINARY

    Project size range Total value

    1,967 Total $1,046M

    Outlays $8M

    $867M

    Range $25k-$500K Total value $91M

    Range $1-$2M Total value $39M

    $171M

    Category I Range $2-$50

    Total value $318M Major

    Minor

    Range $500K-$1M Total value $42M

    Category II Range $50-$100

    Total value $240M

    Category III Range $100+

    Total value $308M

    Source: PD&C, Team analysis

    1 Representative project scale but not exhaustive. Current budget for projects from March 2010 after the implementations of the CP module to September 2015 across all stages of development from planning (~$30 M) to closed. Budget defined as most recently approved budget in FAMIS as of mid-September 2015

    2 Two grants listed as separate projects were merged with their associated projects. Three projects out of the 30 are ESCO with combined project value of USD ~21 M

  • 4 Pre-Decisional - Proprietary and Confidential |

    Projects requiring additional spending limit were typically impacted by accelerated timeline, scope changes, or decision delays

    Source: Team Analysis, PD&C

    SB Academic Wing1

    Campus Utility1

    SPSC - Data room

    Ekeley Middle Wing

    13

    22

    12

    Ketchum1

    JILA 60 SEEC1

    12

    28

    75

    System Biotech 113

    Athletics Complex1 142

    % Change in legislative spending limit

    Initial legislative spending limit2

    1 Ongoing project | 2 Initial legislative approval | 3 Current legislative approval

    PRELIMINARY

    18

    14

    Stad - Video Board

    5 GIPF Bldg (Athletics) 1

    Bball/ Vball Practice 11

    IBS

    Wilderness1 EUCLID1 (CASE)

    7 Wilderness - Recom

    4

    4

    Hallett Renovation

    Atmospheric Lab

    Glenn Miller Ballroom

    7

    3

    Rec Facilities 64 43

    USD Change in legislative spending limit

    N/A

    16

    56

    18

    2

    10

    6

    10

    53

    0

    0

    0

    0

    0

    0

    2

    0

    0

    3

    0

    17%

    35%

    21%

    75%

    28%

    88%

    12%

    50%

    N/A

    0%

    10%

    0%

    2%

    0%

    0%

    0%

    13%

    14%

    0%

    0%

    Current legislative spending limit3

    N/A

    169

    23

    28

    37

    91

    160

    14

    112

    4

    43

    64

    4

    20

    5

    7

    11

    16

    3

    7

    USD Million

    Projects impacted by significant scope or timeline fluctu-ations

    Normal projects

    Observed difference in performance between projects which are pursued as expected and those impacted by: Accelerated

    scheduling Significant or

    constant scope changes

    Delayed timing in decision-making

    NON-EXHAUSTIVE Detailed next

  • 5 Pre-Decisional - Proprietary and Confidential |

    Based on 40+ interviews, select project reviews, data analysis, and focus groups we identified a set of opportunities

    Opportunities to increase efficiency and effectiveness

    Cap

    ital

    Plan

    ning

    More consistent Program Planning efforts, aligned with paced project schedule to decrease owner risk

    Address backlog in maintenance through improved capital allocation Enhance integrated portfolio view with clear project prioritization Rethink approval process to match the release of funds to the maturity level of the project

    Des

    ign Augment alignment between PD&C and administration in regards to project budget estimates

    and timelines Continue with recently launched effort for early engagement of Project Manager in project

    lifecycle

    Con

    trac

    t- in

    g

    Refine choice in contracting strategy (choice of delivery model, contract type, award process) to align to scope, project schedule, market conditions, and owner execution capability

    Consistently enforce contract terms in the field leading to lower owner risk

    Proj

    ect

    exec

    utio

    n Standardize project execution processes Adopt and enforce tools and as a standardization method Increase ownership of project controls (i.e., cost and schedule tracking)

    Enhance communication on project progress Celebrate success Leverage performance monitoring (e.g., lessons learned at project completion) as source of

    insight Provide training for onboarding new employees and continuous development

    Cro

    ss-c

    uttin

    g

    Emerging themes for developing excellence

    Develop a clear, well-documented, and scalable stage gate process to drive capital investment success

    Adopt clear guidelines in contracting strategy to address project risk based on project scope, target cost, expected delivery schedule, market conditions, and internal capability

    Deploy project controls to drive transparency of cost, schedule, and milestones during project execution thus increasing consistency

    Train and retain the Project Manager workforce to ensure best practices adoption and execution in project management

    Source: Interviews

  • 6 Pre-Decisional - Proprietary and Confidential |

    CU Boulder can adapt best practices in capital management across the four themes to continue to pursue excellence

    Emerging theme Description Best practice

    Stage-Gate process: how do projects move through multiple fund and scope approval gates through the lifecycle?

    Stage-gate process matches the release of required funds to the maturity level of project definition; specifically, it ensures projects do not progress without an adequate evaluation of the underlying business case, completion of key deliverables, and mitigation of critical risks

    Single and comprehensive capital investment framework

    Transparency: how do project controls allow for right information at the right time?

    Project controls dashboards enable PMs and Project Coordinators to: Proactively identify issues Ensure relevant information is at hand to

    contribute to the decision making process in a timely manner

    Tracking information on cost, schedule and milestones for each project

    Contracting: how project delivery and contracting methods are selected

    Selecting contracting strategy (delivery model, contract terms, award process) based on project specifications (size, cost, delivery schedule, complexity), market conditions, and internal capability

    Clear guidelines on contracting strategy to best manage owner risk McKinsey & Company

    VGI-AAA123-20090508-

    Working D

    raft -Last Modified 9/7/2011 3:32:09 A

    MP

    rinted 4/6/2011 4:32:15 PM

    | 3

    Contracting strategy entails defining 3 linked elements of a project

    Delivery model (How do I determine optimal contracting scope?) Should I own the asset or are other ownership structures more

    suitable, e.g., lease?

    Which project value chain steps should be done internally and which ones by contractor(s)?

    Into how many contracts should the project scope be split? What is the optimal split of scope between the contractors?

    Contract terms (How do I ensure most optimal contracting terms?) What are the key project cost, performance, and schedule risks? Who is the natural owner of the risks? What mechanisms exist to transfer or share risk? How can objectives be aligned between owner and contractor to

    ensure an efficient execution through compensation elements such as incentives, penalties, warranties, etc.?

    Key dimensions of contracting strategy Key questions to be considered

    Award process (How do I select my contractors?) How can the effectiveness of existing award process be enhanced ? How many and which suppliers/contractors should be invited? How do we get the suppliers interested? What is the criteria for evaluation various suppliers?

    Deliverymodel

    Awardprocess

    Contract terms

    2

    1

    3

    Project Managers: how well is project management best practice followed?

    Establishing standardized methods, training for PM staff on consistent approaches, and support from key decision makers which allow PM team to increase success in delivery of projects

    Standardized processes with capability building training to ensure consistent execution

    McKinsey & Company

    Working D

    raft -Last Modified 07-S

    ep-11 6:35:55 PM

    Printed

    |

    SJO-AAA123-20110525-

    5

    4 Planning and scheduling process

    Planning team

    Create WBS Identify critical

    milestones Create/ update

    plan Publish plan

    Monitor & report project progress

    Recommend focus actions/ area

    Publish report

    Recommend & perform required analyses

    Publish analysis report

    Process step

    Users

    Create/ update plan

    Provide timely, accurate inputs

    Help in identifying critical milestones

    Progress measurement

    Provide timely, accurate inputs

    Execute recom-mended focus actions

    Customized analysis

    Identify required analyses

    Provide timely, accurate inputs

    Roles

    A

    B

    C

    D

  • 7 Pre-Decisional - Proprietary and Confidential |

    Adding stage gates to existing Capital Project Process will focus University resources and increase control for Major projects

    # Funding gate # Review-only gate

    STAGE GATE PROCESS A

    to

    Operations From...

    Project Initiation/ Concept

    Development

    Project Obtains Board Approval and is Funded

    Schematic Design

    Construction Documents

    Bidding and Negotiation

    Program Planning

    Consultant and

    Contractor Selection

    Design Development Construction Close Out

    PD&C Planning Led Process PD&C Project Manager Led Process

    Cabinet Review and Authorization

    2 1

    Consultant and

    Contractor Selection

    Project Initiation/ Concept

    Development

    Develop feasible options. Release seed money.

    Design Development

    Start-up/ Commission-

    ing Close Out

    Program Planning/

    Scope Selection

    Schematic Design Construction

    Is this needed? Is it a priority?

    PD&C Planning Led Process PD&C Project Manager Led Process

    Is the best option still viable after scoping? Freeze Scope. Release full budget. Is the project ready to begin operation?

    Is option still viable given the refined estimate?

    Any outstanding accounts or issues? Is the project ready to be turned over?

    6

    Construction Documents

    Bidding and Negotiation

    2b 1 2a 3 4 5

    Source: PD&C process, Expert interviews, Team Analysis

  • 8 Pre-Decisional - Proprietary and Confidential |

    Proposed contracting process establishes a consistent risk based approach to enhance project outcomes

    CONTRACTING PROCESS

    Steps Select a Delivery Model

    Goals

    Integrate Contractor selection process into Contracting Strategy Playbook to best utilize process to meet cost, schedule or quality based outcomes

    Establish a Contracting Strategy Playbook for optimizing cost/schedule/quality aligned with State regulations and CU Boulder past experience

    Understand how alternative models (bundling, PPP, IPC) could be utilized to better spread risks

    Understand CU Boulder desired role (skill building)

    Transfer project risks to align objectives between owner and contractors, not to outsource them

    Ensure the terms of the performance contract are pragmatic, clear, and measurable

    Who to involve

    PD&C Legal Procurement Vice Chancellor Contractor Rep Design Team Rep

    PD&C Legal Procurement Vice Chancellor Contractor Rep Design Team Rep

    PD&C Legal Procurement Vice Chancellor

    Select a Contractor Determine Contract Terms and Sign

    Actions

    Develop Contracting Strategy Playbook working group to explore best delivery options of CU Boulder projects

    Integrate contractor selection methods into Contracting Strategy Playbook Formalize Contractor Score

    Card

    Develop standard language added to State contracts to provide a fair and equitable balance of risk on large Capital Projects

    B

  • 9 Pre-Decisional - Proprietary and Confidential |

    CU Boulder requires a systematic approach to building transparency among stakeholders in project delivery

    TRANSPARENCY

    Description

    Define key data and clear KPIs for project delivery

    CU Boulder should define Key Performance Indicators (KPIs) at a project level based on project categories defined (i.e. Major, Minor, and Outlays) with clear targets across each

    An individual should also be identified as a responsible party for reporting and meeting the KPI target (may be different individuals)

    Clear direction and training should be provided on how to calculate and report the KPI

    C1

    Create an accessible KPI dashboard

    KPI dashboard should be accessible at multiple levels (e.g. project level and portfolio level) to the relevant stakeholders

    The accessible dashboard can be communicated widely to build transparency among all stakeholders (e.g. users, administration, PD&C) and increase project accountability

    C2

    Provide a forum for decision making

    KPI dashboards can be used as a tool in a regular forum of stakeholders (e.g. a Project Review Board) to discuss project progress

    Project Review Boards will also help resolve issues proactively as it will: Enable decision makers to have the right information Allow PMs to raise concerns at right time

    C3

    KPI dashboard is designed at both project and portfolio level

    Source: Expert interviews, Team Analysis

    C

  • 10 Pre-Decisional - Proprietary and Confidential |

    Project manager performance is the single most influential driver of construction project profitability

    We have found that project performance is highly correlated with project manager capabilities Project performance is not correlated with: Geography Asset class Complexity Customer Project manager age or tenure

    (grey hair)

    D

    High performing PMs excel at these skills

    Org

    ca

    pabi

    litie

    s

    I

    Fina

    ncia

    l as

    tute

    ness

    C

    omm

    erci

    al

    orie

    ntat

    ion

    Mgm

    t ca

    pabi

    litie

    s

    II

    III

    IV 1. Managing client needs (e.g. change orders)

    1. Optimizing schedule, scope, and cost dimensions

    1. Leveraging organization resources

    1. Understanding financial statements

    1. Mitigating project risk

    1. Maintaining project lifecycle view

    1. Overseeing contractors effectively

    1. Mastering contract details

    1. Planning & tracking project performance

    1. Managing internal and external teams

    10

    9

    4

    3

    6

    5

    8

    7

    1

    2

    We have run an analysis of 10,000 projects, checking the correlation of project performance with different factors

    Source: Interviews, Team analysis

    Highest priority

    Sustain Train Skills

    PROJECT MANAGER PERFORMANCE D

  • 11 Pre-Decisional - Proprietary and Confidential |

    A field and forum format ensures appropriate balance between effort, effectiveness, and reach

    Source: Team analysis

    2015 2016

    Q2 Q3 Q4 Q4 Q1

    Forum Classroom

    setting where skills are taught by

    experienced PMs and standard setters

    Field Practice

    application of lessons and

    coaching sessions to help PMs

    operate with excellence

    Field work (~12 weeks) Field work

    (~12 weeks)

    #1 (1 day) #4 (1 day) #3 (1 day) #2 (1 day)

    Field work (~12 weeks) Field work

    (~12 weeks)

    Preparation for forums Select

    partici-pants

    Plan curricu-lum and field work

    Set expectations through program overview

    Deliver first series of workshops combining activities and pure lecture modules

    Outline field work assignments

    Celebrate stories of success from field work

    Establish forum for PMs to discuss what worked and what was challenging

    Deliver next set of lectures and field work

    Repeat defined forum format ILLUSTRATIVE

    Provide workshops for clients on PD&Cs processes

    Perform project kick-off with client

    Use transparency tools throughout project

    Fill out KPIs and use to have discussions with management, clients, and contracts on the progress and performance of projects

    Leverage contracting playbook during contracting

    Create risk assessments before project on critical areas and develop mitigation plans

    Coach new PMs in process

    Engage with internal/ external teams to develop improved working processes

    Session sequence Forum 1 Overseeing contractors

    effectively and Mitigating project risk Forum 2 Planning & tracking project

    performance Forum 3 Managing client needs Forum 4 Managing internal & external

    teams

    Sustain Train Skills

    Partnering with training provider can help reduce timeframe required for field work

    PROJECT MANAGER PERFORMANCE D

  • 12 Pre-Decisional - Proprietary and Confidential |

    Applying capital productivity levers can increase CU Boulders effectiveness and improve its organizational health in the project delivery functions

    Source: Expert interviews, Team Analysis

    Applying capital productivity levers can achieve substantial efficiency in capital deployment.

    in addition to multiple other benefits to University of Colorado, Boulder

    Estimated savings of 15% of the overall capital spend based on select levers of streamlining project delivery: Stage-Gate process: move through multiple

    fund and scope approval gates across lifecycle allocating full funding when with a higher degree of cost certainty

    Contracting: select the project delivery method and contract terms to match the project goals and share risks

    Transparency: add project controls and tracking to provide right information at the right time

    Project Managers: spread project management best practice to create consistent approach

    Estimated savings of 30% based on all capital levers across project prioritization, streamlining delivery, and making the most of existing facilities

    Grow a transparent and trust-based relationship across all stakeholders (Board of Regents, Administration, Planning, Design & Construction, and Users) involved in project delivery

    Increase morale, accountability, and ownership of projects in project delivery functions

    Better able to attract and retain top talent in the project delivery functions at CU Boulder

    Better able to manage the pipeline of upcoming projects from an internal resource perspective

    Attract best contractors to engage in project delivery of complex and base projects

    Better able to anticipate and resolve project performance related issues

    Maintain and enhance the beauty of the unique campus architecture in a cost effective manner

  • 13 Pre-Decisional - Proprietary and Confidential |

    CU Boulder has started initiatives that address aspects of the four recommendation focus areas

    Source: CU Boulder Master Plan and Interviews

    Initiative

    Creating Key Performance Indicators dashboard

    Developing preliminary set of project KPIs dashboards with Office of Performance Improvement

    Detailing project plans through Project Charter

    Providing an executive summary of Program Plan covering agreed budget, schedule, and scope, signed by PD&C and Administration

    Simplifying campus design formats

    Redeveloping campus design standards to more concise format

    Description Involving PM earlier in the process

    Involving PM earlier at project conceptualization instead of Design Development phase

    Investing in software tools and solutions

    Undergoing an evaluation of software options to be used across Facilities Management (e.g. developing database for smaller projects to provide better cost estimates)

    Stag

    e ga

    te

    Con

    tr-

    actin

    g Tr

    ansp

    aren

    cy

    PM

    Tool

    s

    Leverage technology for permitting and inspections

    Implementing electronic permitting technology to ensure tracking of permitting and inspection

    Engaging contractors with performance specifications

    Investigating use of performance-based specifications to transfer risk to contractor and design team

  • 14 Pre-Decisional - Proprietary and Confidential |

    Overall implementation plan

    2015 2016 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    E. PMO for implementation

    Launch field and forum trainings Define & implement policy to ensure sustainment (e.g. training refreshers, assessments, etc.)

    Activity

    Complex Minor and Outlays

    Define stage-gate process for CU (roles, deliverables, etc @ each gate)

    B. Contracting strategy

    Launch: pilot, adjust, scale to all complex projects

    Create contracting strategy playbook

    Share plan and create SG working group

    Identify CS working group

    Syndicate with key stakeholders

    Workshop(s) to share recommendations and future plan

    Assess results and define next steps (e.g. extend to base Minor and Outlays projects)

    Major projects

    A. Stage gate process

    Assess results of PMs and define next steps

    Scale v2.0 to all projects

    Map needed PM skills (and current state)

    C. Transparency

    Design, pilot, and adjust PRB & dashboard v2.0

    Assess results and define next steps

    Assess results and define next steps

    Launch: pilot, adjust, scale to all projects Syndicate with key stakeholders

    Implement version 1.0 for all Major projects

    Identify mode for PM trainings (internal/external)

    Syndicate version 1.0 of transparency measures (dashboard and PRB)

    D. Project Managers

    Implementation of 1.0 continues until v2.0 is scaled to all

    Design program (curriculum and format)

    PRELIMINARY

    Phase 3: sustaining excellence Phase 2: building excellence Phase 1: quick wins & critical actions Phase 4: future considerations

    Source: Team analysis

  • 15 Pre-Decisional - Proprietary and Confidential |

    Appendix

  • 16 Pre-Decisional - Proprietary and Confidential |

    Organization context Athletics project review Overall diagnostic Recommendations Value at stake Implementation plan

    Contents

  • 17 Pre-Decisional - Proprietary and Confidential |

    Planning Design & Construction is a ~65 FTE organization within Facilities Management that manages project delivery for CU Boulder Department of Facilities Management Planning, Design and Construction

    Facilities Management

    PD&C

    Facilities Engineering (12)

    Reviews designs for compliance with codes, UCB standards, good engineering practices

    Provides engineering support to the facilities maintenance and operations staff, design guidance to UCB project managers, and design-oversight of consultants.

    Develops and maintains university standards, design guidelines, and construction-requirements lists in cooperation with maintenance staff.

    Ensures code compliance

    Facilities Planning (7)

    Manages and directs the planning and design of campus facilities and grounds

    Maintains the space database

    Processes official requests for space

    Performs space utilization/needs analyses

    CAD/Document Management/ CASP (6)

    Maintains library of campus site and building engineering drawings

    Catalogs and archives campus project documents and related materials

    Updates achieve drawings accurately reflect the campus and its structures.

    Develops and maintains campus GIS and maps database

    Design & Construction (37)

    Provides administrative, management and professional services required to facilitate and accomplish projects on the campus

    Coordinates the bidding process procuring consulting services

    Administers and maintains contracts, budgets, and schedules

    Office Administration (3)

    Supports PD&C

    Source: CU Boulder organizational chart and PD&C website

  • 18 Pre-Decisional - Proprietary and Confidential |

    PD&C uses the following capital construction process for Major projects (1/2) BCPC = Boulder Campus Planning Commission CCHE = Colorado Commission on Higher Ed.

    FM = Facilities Management

    Defines the basic scope and likely cost of the project

    Informs the administration about the project

    Secures campus administration approval to proceed with development of a program plan

    Project Initiation and Feasibility

    Outcome: Approval to prepare a Program Plan

    Program Planning

    Defines the programmatic requirements for the designer

    Defines limits of work, including site and infrastructure requirements

    Builds consensus as to scope, cost and time line of the project

    Defines the financial plan and sources of funds

    Outcome: Campus agreement on scope of project and a funding plan identifying sources of revenue

    Approvals

    Secures Approval from Board of Regents and CCHE

    Incorporates project into larger capital financial planning of university and state

    Develops support for the project at all levels of state government

    Secures funding for State-funded project

    Outcome: Authorization to begin expending money on a capital construction project

    Architect Selection

    Selects the most-qualified architect and engineering firms to do the project

    Encumbers money to begin the project

    Contractors are selected for some delivery methods

    Outcome: A design team is contracted to design the entire project

    Concept and Schematic Design

    Confirms and enhances program plan requirements

    Generates concept for final building

    Provides room by room layout of spaces

    Secures approval of DRB and review by BCPC of schematic plans

    Outcome: Schematic design is approved and project budget is confirmed

    Source: Colorado.edu

  • 19 Pre-Decisional - Proprietary and Confidential |

    PD&C uses the following capital construction process for Major projects (2/2)

    Develops detailed room requirements

    Integrates infrastructure systems into the building design

    Provides pricing documents for contractor

    Secures final DRB approval and other entitlements

    Design Development

    Outcome: Design Develop-ment is approved within the contract budget.

    Construction Documents

    Translates the design intent into documents from which a builder can construct the project

    Describes the quantity and quality of the materials to be provided by the contractor

    Provides final estimates of the project prior to bidding

    Outcome: A complete set of plans and specifications is produced that describes the design fully.

    Bidding & Negotiation

    Initiates procurement processes for all trades

    Produces a final construc-tion price

    Contracts with builders to construct the project

    Outcome: Final contract for construction

    Construction

    Contractor constructs the project

    FM ensures that the building is built per plans and specs and meets building codes

    Outcome: The project is realized

    Occupancy and Warranty Period

    The building is occupied by the users for which it has been designed

    FM monitors the project to identify and correct any construction defects

    Outcome: The building is accepted and available to move in

    Source: Colorado.edu

    BCPC = Boulder Campus Planning Commission CCHE = Colorado Commission on Higher Ed. FM = Facilities Management

  • 20 Pre-Decisional - Proprietary and Confidential |

    Organization context Athletics project review Overall diagnostic Recommendations Value at stake Implementation plan

    Contents

  • 21 Pre-Decisional - Proprietary and Confidential |

    Athletics Complex has been a challenging program and continues to be a source of concern for CU Boulder

    Source: PD&C, Team analysis

    Original Program Plan called for a phased approach and was envisioned to be completed August 2016/17 Accelerated timeline and performing all phases concurrently has created additional

    stress on delivery model

    Internal misunderstanding in early phases between Athletics and PD&C resulted in ongoing project changes and cost escalations

    Lack of team continuity, both internal and external, created hand-off challenges and eventually coordination and communication challenges

    GMP was not executed, despite constant assurance provided by Mortenson and an agreed upon scope and budget that led to an agreement in GMP GMP agreement of USD 141 M achieved in April 2015 In May 2015 Mortenson refused to sign

    Quality assurance during project closeout is an important final step in Athletics Complex project in order to prevent future costs and may require additional support to supplement capacity of existing team structure Current closeout process is mainly safety focus and user has already discovered

    some closeout issues

  • 22 Pre-Decisional - Proprietary and Confidential |

    Introduction to the Folsom Field Athletic Complex upgrade plan

    1 Includes Space for Olympic Sports teams and their support spaces, training table, and renovated and expanded academic support center

    Last major construction effort in 1991 with addition of Dal Ward Upgrade to the facilities was an effort to increase recruitment

    success of top-performing student athletes which were being drawn to nearby schools with more advance facilities

    Original Program Plan (and original cost) called for a phased approach with the following phase split: Phase 1: 4th Floor Build-Out to serve as Olympics Sports

    Offices (USD 6.1 M) Phase 2: Indoor facility, practice fields, site development, and

    above ground parking lot (USD 117.9 M) Phase 3: Dal Ward renovation1 (USD 15.8 M)

    Original occupancy date was estimated August 2016/17

    Contract was drafted as a Design/Build with a Guaranteed Maximum Price (GMP) but clause was not executed

    Under design/build contract, lead contractor is tasked with developing designs for the end building and executing on that design

    GMP clause is a clause which sets an upper budgetary limit which project is expected not to surpass. Costs which exceed that limit are not to be paid by the client and is an effective risk mitigation tool GMP clause was never formally executed by Mortenson

    Contract form is ideal for fixed and known project scope, situations similar Folsom Field Athletic Complex with evolving scope is not best suited

    Athletic Complex project was intended to modernize and advance CUs facilities among growing talent competition

    Phases were intended to help reduce cost and inconvenience of a full blown construction site but would have taken longer

    Winners of contract were contractor Mortenson and architectural engineering firm Populous

    Phase 1: 4th Floor Buildout

    1

    Phase 2: Indoor facility, practice field, and parking

    2

    Phase 3: Dal Ward

    3

    1 2

    3

    Team Governance

    Final decision-maker for build team

    Made recommenda-tions which needed Mortensons approval

    Site presence

    Multiple staff flying in as needed

    Select staff moved to Boulder, others

    Winning contractor, led contractor relationship with CU

    Design part of bid team, essentially worked for Mortenson

    Role on project

    Source: Interviews, Athletic Complex Program Plan

  • 23 Pre-Decisional - Proprietary and Confidential |

    Athletics Complex has been impacted by high rates of personnel turnover both at CU and Mortenson

    Source: Interviews

    Lack of continuity has significantly impacted progress of the project

    2013 2015 2014

    Group Position Active period

    Present

    Athletics Department

    Planning, Design, & Const-ruction

    Mortenson

    Populous

    AD 1 AD Athletic Director

    Assistant AD AAD 1 AAD 2

    Adminis-tration User Rep UR 1 No replacement

    CA 1 CA 2 Campus Architect, Director of PDC

    Project Manager PM 1 PM 2

    Lead estimator LE 1 and CDL 2

    C&D Liaison CDL 1

    PM 1 Project Manager

    Lead Designer LD 1

    VP, Gen Manager VP 1

    Dir 2 Dir 1 Dir of Project Dev

    SR Proj Manager PM 1 Multiple PMs

  • 24 Pre-Decisional - Proprietary and Confidential |

    Changes represented a significant upward budgetary push, which were offset by cost cutting initiatives in other areas of the project

    Source: Interviews

    PRELIMINARY

    Increases driven by twelve significant scope evolutions, but those increases were controlled by three reductions

    701

    3

    012

    11

    Total Apr Jan

    -2

    Dec Sep Jul Jun May Mar Feb

    1

    8

    Dal Ward -6

    IPF2 Height Reduct

    -1

    IPF2 Track

    Total

    24Indoor Parking1

    1 Separate project but had schedule and cost implications on Athletics Complex 2 IPF = Indoor Practice Field

    2014 2015

    USD millions

    1

    3

    2

    4

    2

    1

    1

    Total

    Grounds Temp

    Foot- print

    1

    1

    Total

    Kitchen

    Total 0.2

    Brand 0.2

    3

    1

    Total

    IPF2 Sprink- lers

    -0

    Aud/ Vis 2

    Rooftop Design

    1

    1

    Total

    Tenant Finish

    0

    0

    Total

    DAS Systems

    0.7

    0.4

    0.3

    Total

    Rooftop bridge

    5th Floor Add-on

    -2

    -2

    Total

    Value Eng

    5

    6

    7

    8 9 10 13

    11

    12

    14 15 16

    Focus of changes only on significant changes to scope

    Does not include required changes to schedule, manpower, and other changes required to support scope change

  • 25 Pre-Decisional - Proprietary and Confidential |

    Going forward, there are three important considerations for the Athletics Complex project

    1

    2

    3 Throughout the project, Mortenson provided constant assurance to CU personnel that project was on track with agreed upon budget and timeframe

    Current closeout process has strong administrative and safety focus, no identifiable quality assurance closeout plan is in place and may require additional support capacity

    As of December 2015, the project is 93% of budget (USD 140 M) has been released to Mortenson

    Source: Interviews, Press Search, Mortenson

  • 26 Pre-Decisional - Proprietary and Confidential |

    Organization context Athletics project review Overall diagnostic Recommendations Value at stake Implementation plan

    Contents

  • 27 Pre-Decisional - Proprietary and Confidential |

    Overall capital program diagnostic

    Quantitative performance on CU Boulders capital portfolio over the past 5 years shows overruns and delays for a set of Major projects as well as underruns for Minor and Outlay projects

    Major projects (projects above $2M) comprise of 80% of the spend. Approximately 8 projects requiring additional spending limit were typically those impacted by accelerated timeline, scope changes, or decision delays

    Significant portion of the spend, ~$250M, is still outstanding and provides an opportunity to improve project delivery in on-going projects

    Though market conditions impacted the overall cost of projects since 2009, there is no immediate impact on attractiveness of CU projects based on bid analyses

    More than half (>1000 projects) of all Minor and Outlay projects are completed at 5% or more under the original target cost, similar to other public agencies

    Qualitative analyses and review of select Major projects show that CU Boulders capital program faces challenges in both strategy and project delivery with the following key opportunities: Capital planning: Meet target costs by rethinking approval process to match the release of funds to

    the maturity level of the project Contracting methodology: Manage owner risk through clear guidelines on selection project delivery

    method or contracting terms Communication: Manage risks proactively by increasing project tracking and clarity in

    communicating progress with appropriate stakeholders Project Manager workforce: Increase consistency in PM workforce through structured training and

    onboarding processes and a decrease in turnover

  • 28 Pre-Decisional - Proprietary and Confidential |

    Over the past 5 years, CU Boulders capital spend has been concentrated on Major projects with a valued budget of ~$870M

    302

    980

    957

    Total budget on projects1 Number of projects

    Projects over $2M Athletics Complex Systems biotechnology

    building Recreation facilities

    improvements

    Projects between $25k-$2M Food service renovation Replace boilers, roof Lab renovation

    Projects under $25k Sound proofing Temporary cooling Fire alarm upgrade

    Examples

    PRELIMINARY

    Project size range Total value

    1,967 Total $1,046M

    Outlays $8M

    $867M

    Range $25k-$500K Total value $91M

    Range $1-$2M Total value $39M

    $171M

    Category I Range $2-$50

    Total value $318M Major

    Minor

    Range $500K-$1M Total value $42M

    Category II Range $50-$100

    Total value $240M

    Category III Range $100+

    Total value $308M

    Source: PD&C, Team analysis

    1 Representative project scale but not exhaustive. Current budget for projects from March 2010 after the implementations of the CP module to September 2015 across all stages of development from planning (~$30 M) to closed. Budget defined as most recently approved budget in FAMIS as of mid-September 2015

    2 Two grants listed as separate projects were merged with their associated projects. Three projects out of the 30 are ESCO with combined project value of USD ~21 M

  • 29 Pre-Decisional - Proprietary and Confidential |

    Projects requiring additional spending limit were typically impacted by accelerated timeline, scope changes, or decision delays

    Source: Team Analysis, PD&C

    SB Academic Wing1

    Campus Utility1

    SPSC - Data room

    Ekeley Middle Wing

    13

    22

    12

    Ketchum1

    JILA 60 SEEC1

    12

    28

    75

    System Biotech 113

    Athletics Complex1 142

    % Change in legislative spending limit

    Initial legislative spending limit2

    1 Ongoing project | 2 Initial legislative approval | 3 Current legislative approval

    PRELIMINARY

    18

    14

    Stad - Video Board

    5 GIPF Bldg (Athletics) 1

    Bball/ Vball Practice 11

    IBS

    Wilderness1 EUCLID1 (CASE)

    7 Wilderness - Recom

    4

    4

    Hallett Renovation

    Atmospheric Lab

    Glenn Miller Ballroom

    7

    3

    Rec Facilities 64 43

    USD Change in legislative spending limit

    N/A

    16

    56

    18

    2

    10

    6

    10

    53

    0

    0

    0

    0

    0

    0

    2

    0

    0

    3

    0

    17%

    35%

    21%

    75%

    28%

    88%

    12%

    50%

    N/A

    0%

    10%

    0%

    2%

    0%

    0%

    0%

    13%

    14%

    0%

    0%

    Current legislative spending limit3

    N/A

    169

    23

    28

    37

    91

    160

    14

    112

    4

    43

    64

    4

    20

    5

    7

    11

    16

    3

    7

    USD Million

    Projects impacted by significant scope or timeline fluctu-ations

    Normal projects

    Observed difference in performance between projects which are pursued as expected and those impacted by: Accelerated

    scheduling Significant or

    constant scope changes

    Delayed timing in decision-making

    NON-EXHAUSTIVE Detailed next

  • 30 Pre-Decisional - Proprietary and Confidential |

    Specific context of building projects reveal important details about on the dynamic process of design and construction (1/3)

    Source: Team Analysis, PD&C

    Athletics Complex

    Driver for cost change: Accelerated project timeline, insufficient time for program planning complex project

    Additional context Accelerated timeline provided limited time for

    planning efforts to which external consultant was hired to supplement

    Inadequate familiarity/attention to capital process and requirements by new campus staff

    Important changes and decisions were being made as late as construction

    System Biotech

    Driver for cost change: Unforeseen construction escalation in laboratories and need to master plan the building site for East Campus

    Additional context Efforts were required to master plan the site for

    East Campus impacting the budget and schedule Laboratory facilities required more advanced

    features than expected Additional design fees for LEED certification

    Campus Utility

    Driver for cost change: Delayed approval and new environmental requirements

    Additional context Original program plan developed in 2007 which

    set budget in dollars for that market Original plan called for $134 M project but

    program was only approved for $75 M plan was reworked

    Approved 2011 plan operated in a more expensive market; student support for continued CoGen

    SEEC

    Driver for cost change: Delayed funding, changed site and program fluctuation

    Additional context Program planning efforts began in 2002 and were

    paused, restarted and finalized in 2008 Series of approval delays and program plan

    amendments led to the escalation of cost compared to original budget request

    Nature of the building and the market costs changed significantly from 2008 to 2015

  • 31 Pre-Decisional - Proprietary and Confidential |

    Specific context of building projects reveal important details about on the dynamic process of design and construction (2/3)

    Source: Team Analysis, PD&C

    JILA

    Driver for cost change: Delayed federal funding and unforeseen construction needs

    Additional context Original project cost estimated in 2007 but federal

    funding was not available until 2009 Unforeseen existing conditions around hazardous

    materials were discovered underground (e.g. aged plant fuel storage tanks)

    High sensitivity of research equipment required advanced vibration-prevention features

    Systems Biotechnology Academic Wing

    Driver for cost change: Delayed funding availability Additional context

    Educational wing of this facility delayed from 2006 to 2015-16 due to the demand for state capital construction funding and economic hardship

    Original cost was completed before the construction upswing in the Denver area

    Increase of cost driven by higher market demand and inflationary cost which occurred between 2008 and present day

    Ketchum

    Driver for cost change: Scope significantly evolved from original capital renewal scope

    Additional context First state funding request was in 1998 which was

    only for capital renewal of the building; Circa 1938 building

    Appropriated design funds rescinded along with construction phase funding in 2007-08

    2014 funding was granted for a complete overhaul with an expanded program plan

    Ekeley

    Driver for cost change: Delayed funding and inflationary impact of costs

    Additional context Project plan originally scoped in late 1990s Appropriated design funds rescinded along with

    construction funding in 2007-08 Inflationary cost pressures from the original

    funding approval impacted the budgetary needs of the project

  • 32 Pre-Decisional - Proprietary and Confidential |

    Specific context of building projects reveal important details about on the dynamic process of design and construction (3/3)

    Source: Team Analysis, PD&C

    SPSC Data Room

    Driver for cost change: Cost decreased significantly due to dramatic technological innovation in market

    Additional context Original plan was to develop a facility to hold data servers

    to back-up crucial university information Popularization of online cloud memory capabilities

    significantly drove down the need to purchase devices to support data needs of university

    Project costs were dramatically reduced

  • 33 Pre-Decisional - Proprietary and Confidential |

    Denver market conditions impact project performance (both positively and negatively) and need to be accounted for in planning

    4,450

    4,3424,317

    4,178

    7,0787,0106,9856,890

    6,341

    3,900

    3,950

    4,000

    4,050

    4,100

    4,150

    4,200

    4,250

    4,300

    4,350

    4,400

    4,450

    4,500

    0

    500

    1,000

    1,500

    2,000

    2,500

    3,000

    3,500

    4,000

    4,500

    5,000

    5,500

    6,000

    6,500

    7,000

    7,500

    3,975

    6,384

    4,092

    Observations: Denver area market

    experienced growth increase in prices over the past five years

    From June 2009 to July 2010 the compound aggregated growth rate was 1.91% for BCI and 3.04% for CCI

    Further pricing pressure may existing due to scarcity of labor at subcontracting levels and increasing project demands coming online

    CCI

    BCI

    2010 2011 2012 2013 2014 2015

    Recession recovery

    Growth period

    NOTE: The ENR indexes measure how much it costs to purchase the following hypothetical package of goods compared to what it was in the base year. The CCI uses 200 hours of common labor, multiplied by the 20-city average rate for wages and fringe benefits. The BCI uses 68.38 hours of skilled labor, multiplied by the 20-city wage- fringe average for three tradesbricklayers, carpenters and structural ironworkers. For their materials component, both indexes use 25 cwt of fabricated standard structural steel at the 20-city average price, 1.128 tons of bulk portland cement priced locally and 1,088 board ft of 2x4 lumber priced locally.

    Source: Engineering New Record, Team analysis

  • 34 Pre-Decisional - Proprietary and Confidential |

    Analysis of bids reveal CU projects are attractive to general market

    Source: PD&C, Team Analysis

    Total interested bidders

    Second Lowest Lowest Spread (%) Project

    Construction start

    Highest Lowest Spread (%)

    Total qualified bidders

    Project budget (USD M)

    32

    43

    211

    22

    7

    4

    91

    3

    4

    1386

    64

    7

    432

    4

    7

    11

    13

    148

    143 IBS Jun 09

    6

    5

    210

    8

    3

    1410

    9

    4

    4

    148

    10

    4

    613

    6

    7

    89

    6

    8

    3

    5

    24

    3

    64

    4

    35

    5

    5

    4

    6

    24%

    32%

    41%

    12%

    12%

    17%

    23%

    32%

    23%

    23%

    14%

    40%

    40%

    13%

    6%

    13%

    35%

    18%

    10%

    11%

    23

    46%

    15%

    3%

    1%

    17%

    6%

    8

    4%

    4%

    3%

    5%

    6%

    0%

    0%

    5%

    3%

    1%

    40%

    25%

    2%

    3%

    6%

    22%

    Sys biotech Sep 09

    B/V Ball Apr 10

    WLRD Rec May 10

    E-wing Jan 161

    Euclid Oct 15

    Ecme Hvac Sep 15

    Wilderness Mar 15

    Ketchum Jan 15

    GIPF Blg Sep 14

    GM Ballrm May 14

    Athletics Apr 14

    MAC Dec 13

    Atmos lab Aug 13

    Comp data Aug 13

    EKLC Apr 12

    Utility syst Aug 12

    Rec facility Jun 12

    Video board Apr 12

    East Elect May 11

    Jila May 10

    HLET May 10

    1 Expected construction start

    No discernable trend can be identified when reviewing past history of Major bids, while total number of interested bidders is trending lower in 2nd half of 2015

  • 35 Pre-Decisional - Proprietary and Confidential |

    Minor and Outlay projects are routinely under budget

    Source: PD&C, Team Analysis

    106

    214

    342

    105

    20-50 50+

    1092

    -5-5 -20- -5 5-20 >-20

    1 Includes Substantial Completion, Post Construction, and Closed Representative from March 2010 after the implementations of the CP module to September 2015

    2 Excludes projects with USD 0 spend, Minor = 11 and Outlay = 12 3 Excludes 215 closed projects with a budget of USD 0 but representing USD 890 K of actual spend

    99122

    176186

    1524

    50+ 20-50 >-20 5-20 -5-5 -20- -5

    Percentage over/under budget Percentage over/under budget

    Minor projects1 N = 7862

    Outlay projects1 N = 6102,3

    -0.1 0 0 0.2 0.5 0.8 -0.2 0 0.6 3.1 3.1 14.7

    # Total budget over/underrun USD Millions

    55% of projects USD 20.2 M

    underrun

    64% of projects USD 1.5 M

    underrun

    Majority of projects were under budget by more than 5% (55% of Minor and 64% of Outlay)

    Underruns in Minor and Outlay projects amount to ~$22M, less than 2% of overall capital budget over five years

    Underruns are expected given low project values and lack of knowledge on existing field conditions

    PRELIMINARY

  • 36 Pre-Decisional - Proprietary and Confidential |

    Potential to unlock limited value by tightening budget estimation processes or employing staged release of funds during project execution Lower underruns may allow greater budget to

    perform more projects Performance metrics need to capture user

    satisfaction, delivery schedule, and execution cost

    Among other public organizations, regular underruns for Minor and Outlays are not uncommon but may constrain user access to capital

    Source: PD&C, Team Analysis, Press search

    PRELIMINARY

    Underrun represents approximately 18% of total budgeted amount for Outlay and Minor projects1

    120

    21 1078

    Underrun

    0 0 1

    Overrun

    -22 2

    Budgeted

    129

    Spend

    Minor

    Outlay

    which is in line with other public organizations setting budgets for similar projects

    Public org 1

    18%

    14-18%

    CU

    Public org 2 Up to 30%+

    USD Millions Average % budget underrun

    1 Includes Substantial Completion, Post Construction, and Closed Representative from March 2010 after the implementations of the CP module to September 2015

  • 37 Pre-Decisional - Proprietary and Confidential |

    Rapid diagnostic evaluates the effectiveness of CU Boulders Capital program across the following dimensions

    Organization Mindsets and capabilities Processes and tools

    Strategy translation Risk/return appetite estimation Capital headroom calculation

    Portfolio review Portfolio allocation Ongoing returns tracking

    Opportunity Origination Business case optimization and concept selection Design, procurement, & contracting Construction & Execution Comm. & Ramp-up Project control

    Best practice area Description

    Organization structures and standards applied to capital Personnel attitudes and skill sets devoted to capital Enabling systems applied to capital budgeting and delivery

    Formal mechanisms for ensuring corporate strategy implementation Establishing corporate/group level risk and return expectations Calculation/simulation of cash generation and investment ability Top down review of project portfolios, including improvement

    potential

    Selecting projects for execution, understanding interactions, risk Evaluating how results match to risk/return appetite Initial scoping of opportunities and preparation for project success Development and testing of concepts against a reference case for

    most effective selection

    Detailed project design, planning, and procurement

    Tactical project execution including scope changes Startup and handoff to ongoing operating team Assessing project outcomes, establishing feedback loops

    Enablers

    Capital Strategy

    Portfolio Strategy

    Project Delivery

    Source: McKinsey Capital Productivity Practice

  • 38 Pre-Decisional - Proprietary and Confidential |

    Rapid diagnostic based on interviews and select project reviews reveals that strategy as well as project delivery are below industry average at CU Boulder

    0.0

    1.0

    2.0

    3.0

    4.0 Organization

    Processes and tools

    Mindsets and capabilities

    Strategy translation to asset base

    Risk/Return appetite

    Capital headroom calculation

    Portfolio review

    Portfolio allocation Ongoing returns tracking

    Opportunity origination

    Business case definition and concept

    Design. procurement. and contracting

    Construction and Execution

    Commissioning and ramp-up

    Project control Opportunity origination Concept selectionProject definition and approval

    Project ramp-up

    Project execution

    Opportunity origination

    Concept selection

    Project definition and approval

    Project ramp-up

    Project execution

    Portfolio Strategy

    Capital Strategy

    Project delivery

    Source: Based on 40+ interviews with PD&C

    PRELIMINARY

    Enablers

    Industry average = 2-3

  • 39 Pre-Decisional - Proprietary and Confidential |

    Based on 40+ interviews, select project reviews, data analysis, and focus groups we identified a set of opportunities

    Opportunities to increase efficiency and effectiveness

    Cap

    ital

    Plan

    ning

    More consistent Program Planning efforts, aligned with paced project schedule to decrease owner risk

    Address backlog in maintenance through improved capital allocation Enhance integrated portfolio view with clear project prioritization Rethink approval process to match the release of funds to the maturity level of the project

    Des

    ign Augment alignment between PD&C and administration in regards to project budget estimates

    and timelines Continue with recently launched effort for early engagement of Project Manager in project

    lifecycle

    Con

    trac

    t- in

    g

    Refine choice in contracting strategy (choice of delivery model, contract type, award process) to align to scope, project schedule, market conditions, and owner execution capability

    Consistently enforce contract terms in the field leading to lower owner risk

    Proj

    ect

    exec

    utio

    n Standardize project execution processes Adopt and enforce tools and as a standardization method Increase ownership of project controls (i.e., cost and schedule tracking)

    Enhance communication on project progress Celebrate success Leverage performance monitoring (e.g., lessons learned at project completion) as source of

    insight Provide training for onboarding new employees and continuous development

    Cro

    ss-c

    uttin

    g

    Emerging themes for developing excellence

    Develop a clear, well-documented, and scalable stage gate process to drive capital investment success

    Adopt clear guidelines in contracting strategy to address project risk based on project scope, target cost, expected delivery schedule, market conditions, and internal capability

    Deploy project controls to drive transparency of cost, schedule, and milestones during project execution thus increasing consistency

    Train and retain the Project Manager workforce to ensure best practices adoption and execution in project management

    Source: Interviews

  • 40 Pre-Decisional - Proprietary and Confidential |

    Organization context Athletics project review Overall diagnostic Recommendations Value at stake Implementation plan

    Contents

  • 41 Pre-Decisional - Proprietary and Confidential |

    CU Boulder can adapt best practices in capital management across the four themes to begin developing excellence

    Emerging theme Description Best practice

    Stage-Gate process: how do projects move through multiple fund and scope approval gates through the lifecycle?

    Stage-gate process matches the release of required funds to the maturity level of project definition; specifically, it ensures projects do not progress without an adequate evaluation of the underlying business case, completion of key deliverables, and mitigation of critical risks

    Single and comprehensive capital investment framework

    Transparency: how do project controls allow for right information at the right time?

    Project controls dashboards enable PMs and Project Coordinators to: Proactively identify issues Ensure relevant information is at hand to

    contribute to the decision making process in a timely manner

    Tracking information on cost, schedule and milestones for each project

    Contracting: how project delivery and contracting methods are selected

    Selecting contracting strategy (delivery model, contract terms, award process) based on project specifications (size, cost, delivery schedule, complexity), market conditions, and internal capability

    Clear guidelines on contracting strategy to best manage owner risk McKinsey & Company

    VGI-AAA123-20090508-

    Working D

    raft -Last Modified 9/7/2011 3:32:09 A

    MP

    rinted 4/6/2011 4:32:15 PM

    | 3

    Contracting strategy entails defining 3 linked elements of a project

    Delivery model (How do I determine optimal contracting scope?) Should I own the asset or are other ownership structures more

    suitable, e.g., lease?

    Which project value chain steps should be done internally and which ones by contractor(s)?

    Into how many contracts should the project scope be split? What is the optimal split of scope between the contractors?

    Contract terms (How do I ensure most optimal contracting terms?) What are the key project cost, performance, and schedule risks? Who is the natural owner of the risks? What mechanisms exist to transfer or share risk? How can objectives be aligned between owner and contractor to

    ensure an efficient execution through compensation elements such as incentives, penalties, warranties, etc.?

    Key dimensions of contracting strategy Key questions to be considered

    Award process (How do I select my contractors?) How can the effectiveness of existing award process be enhanced ? How many and which suppliers/contractors should be invited? How do we get the suppliers interested? What is the criteria for evaluation various suppliers?

    Deliverymodel

    Awardprocess

    Contract terms

    2

    1

    3

    Project Managers: how well is project management best practice followed?

    Establishing standardized methods, training for PM staff on consistent approaches, and support from key decision makers which allow PM team to increase success in delivery of projects

    Standardized processes with capability building training to ensure consistent execution

    McKinsey & Company

    Working D

    raft -Last Modified 07-S

    ep-11 6:35:55 PM

    Printed

    |

    SJO-AAA123-20110525-

    5

    4 Planning and scheduling process

    Planning team

    Create WBS Identify critical

    milestones Create/ update

    plan Publish plan

    Monitor & report project progress

    Recommend focus actions/ area

    Publish report

    Recommend & perform required analyses

    Publish analysis report

    Process step

    Users

    Create/ update plan

    Provide timely, accurate inputs

    Help in identifying critical milestones

    Progress measurement

    Provide timely, accurate inputs

    Execute recom-mended focus actions

    Customized analysis

    Identify required analyses

    Provide timely, accurate inputs

    Roles

    A

    B

    C

    D

    Source: Interviews, Expert interviews, Team analysis

  • 42 Pre-Decisional - Proprietary and Confidential |

    Existing CU Boulder approval process for Major projects does not match project maturity with funding commitments

    x

    Current Process

    Observations

    Unclear project pipeline prioritization process leads to suboptimal use of resources in developing Program Plans Consensus must be built across many campus departments to develop a Program Plan which requires considerable investment

    of time and effort from the PD&C planning staff

    100% of project target cost is established and committed before design is adequately developed Length of time from project approval at funding gate 2 to project bidding exposes CU Boulder to market conditions as project

    estimates no longer reflect the current market conditions

    Project Managers enter the process after critical project decisions regarding scope and schedule are made Continued scope development occurs in the schematic design and design development stage through user input

    Program Planning

    Close Out and Warranty Period

    PD&C Planning Led Process PD&C Project Manager Led Process

    Schematic Design

    Construc-tion Docu-ments

    Bidding and Nego-tiation

    Con-sultant and Contractor Selection

    Design Develop-ment

    Construc-tion

    Project Initiation/ Concept Develop-ment

    Cabinet review and authorization

    Project obtains board approval and is funded

    2 1

    Source: CU Boulder PD&C website and interviews

    STAGE GATE PROCESS A

    # Funding gate # Review-only gate

  • 43 Pre-Decisional - Proprietary and Confidential |

    Operations

    Adding stage gates to existing Capital Project Process will focus University resources and increase control for Major projects

    Consultant and

    Contractor Selection

    to

    From...

    Project Initiation/ Concept

    Development

    Project Obtains Board Approval and is Funded

    Schematic Design

    Construction Documents

    Bidding and Negotiation

    Program Planning

    Consultant and

    Contractor Selection

    Design Development Construction Close Out

    PD&C Planning Led Process PD&C Project Manager Led Process

    Cabinet Review and Authorization

    2 1

    Project Initiation/ Concept

    Development

    Develop feasible options. Release seed money.

    Design Development

    Start-up/ Commission-

    ing Close Out

    Program Planning/

    Scope Selection

    Schematic Design Construction

    Is this needed? Is it a priority?

    PD&C Planning Led Process PD&C Project Manager Led Process

    Is the best option still viable after scoping? Freeze Scope. Release full budget. Is the project ready to begin operation?

    Is option still viable given the refined estimate?

    Any outstanding accounts or issues? Is the project ready to be turned over?

    6

    Construction Documents

    Bidding and Negotiation

    2b 1 2a 3 4 5

    Source: Expert interviews, Team analysis

    STAGE GATE PROCESS A

    # Funding gate # Review-only gate

  • 44 Pre-Decisional - Proprietary and Confidential |

    Proposed process splits the funding gate and provides an opportunity to develop the design prior to committing total funds

    Project Initiation and Concept Development

    Program Planning Schematic Design

    Design Development

    0

    5

    10

    15

    20

    25

    30>50

    50

    40

    30

    20

    10

    0

    -10

    -20

    -30

    -40

    -50

    Share of total Percent

    30%

    10% 5-15%

    2%

    5%

    0.5%

    Estimate Accuracy1 Percent

    Estimate accuracy Engineering complete Funding required (percent of total investment cost)

    Consultant and Contractor Selection

    Cabinet Review and Authorization pre-design

    Release full project funds with stronger confidence

    100% of funding committed

    Select best option or set of alternatives to further develop

    2a 1 2b

    0.5 10% of funding

    committed

    Source: Expert interviews, Team analysis

    STAGE GATE PROCESS A

    # Funding gate # Review-only gate

    1- Cost estimate accuracy increases (narrows) as design progresses, even as the cost estimate mid-point fluctuates as design progresses.

  • 45 Pre-Decisional - Proprietary and Confidential |

    Stage-Gate Process for complex projects at CU Boulder will help manage resources and provide more financial control (1/2)

    Stag

    es

    Act

    iviti

    es

    Someone identifies a project Options are generated

    with order of magnitude estimates

    Design Team and/or Contractor Selected either in a temporary (Paid competition/initial design phase contract) or permanent basis depending on project and delivery method selected Basic engineering is conducted to create a

    decision-worthy estimate

    Project Initiation and Concept Development

    Program Planning Schematic Design

    A/E and/or Contractor Selection

    2a 1 2b

    Review gate 1

    Gate questions: Is the project need legitimate? Is it a priority?

    Funding gate 2a

    Gate questions: Do feasible options exist that

    match the intended purpose?

    Funding gate 2b

    Stakeholders: User PD&C (Planning) Vice Chancellor, Administration Board of Regents (Informed)

    Stakeholders: User PD&C (Planning and PM) Vice Chancellor, Administration CFO Finance BCPC (Informed)

    Stakeholders: User PD&C (PM, Eng., Shops) Design Team & Contractor Vice Chancellor, Administration BCPC Board of Regents

    Gate questions: Is the best option still viable after

    scoping?

    Final approval authority: Vice Chancellor

    Final approval authority: CFO

    Final approval authority: Board of Regents

    The best option is selected and funds are allocated to complete preliminary engineering

    Source: Expert interviews, Team analysis

    # Funding gate # Review-only gate

    STAGE GATE PROCESS A

  • 46 Pre-Decisional - Proprietary and Confidential |

    Stage-Gate Process comparison for the Wildlife Place project Ex

    istin

    g Pr

    oces

    s Pr

    opos

    ed P

    roce

    ss

    Program Planning 2 1

    Contractor Selection/Sche-

    matic Design Design

    Development Construction Documents

    2b Program Planning 2a 1 Contractor

    Selection/Sche-matic Design

    Design Development

    Construction Documents

    Funding Required

    Program Plan Funding

    Board of Regents

    Project Estimate

    % Design Complete

    Funding Required

    Board of Regents

    Project Estimate

    % Design Complete

    --

    0%

    --

    Program Plan Funding

    --

    0%

    --

    After Funding: Increase to $22.4M at 100% DD estimate VE and ESCO engaged, schedule slips Board of Regents approves additional $2.5M (Total $20.4M) Additional funding required to achieve project scope

    100% of project estimate

    $17.9M

    5%

    Board approves full capital spend

    $20.2M (mid-point of estimate less $2.2M from Stage 2a funding gate)

    Project estimate tightens through SD ($19M - $25.8M ) VE to reduce cost, based on need and function, retain quality

    30-50%

    Board of Regents approves capital spend for remaining unfunded portion of project (~80-90%)

    $2.2M (12.5% of Estimate)

    $9M - $26.9M ($17.9M)

    5%

    Board informed of design start

    Source: Expert interviews, Team analysis

    # Funding gate # Review-only gate

    STAGE GATE PROCESS A

  • 47 Pre-Decisional - Proprietary and Confidential |

    An internal stage gate working group of stakeholders can design processes and develop necessary documentation

    Stage Gate documentation: suggested table of contents

    Gate 2b

    Gates 3-6

    Appendix

    Objectives for Gate Key Deliverables for Gate

    By Function Timeline

    Critical Functions of Team Summary Process Map for Gate Project Managers Roles in completing Gate How to ensure success at Gate 2b

    Alternative Gates for Special Projects CU Boulder Standard forms

    Objectives for Gate Key Deliverables for Gate

    By Function Timeline

    Critical Functions of Team Summary Process Map for Gate Project Managers Roles in completing Gate How to ensure success at Gate 2b

    Gate 1

    Stage Gates

    Gate 2a Objectives for Gate Key Deliverables for Gate

    By Function Critical Functions of Team Summary Process Map for Gate Project Managers Roles in completing

    Gate How to ensure success at Gate 2a

    Objectives for Gate Key Deliverables for Gate

    By Function Timeline

    Critical Functions of Team Summary Process Map for Gate Project Managers Roles in completing

    Gate How to ensure success at Gate 1

    Decision and funding gates for: Base Projects Complex Projects

    Stage Gate Playbook creation process

    Activities: Conduct a series of

    workshops to address each section of the stage gate playbook

    Review playbook with key stakeholders to validate approach

    Suggested working group: PD&C (3)

    Planning Representative

    Project Manager Engineering

    Vice Chancellor Potential Participants (at

    key intervals): Users Legal

    Source: Expert interviews, Team analysis

    Detailed next (sample)

    STAGE GATE PROCESS A

  • 48 Pre-Decisional - Proprietary and Confidential |

    Stage 1 Project Initiation and Concept Development Objectives, key deliverables, and critical functions

    Select best scope alternative that meets the CU Boulders needs and objectives

    Define all scope elements to a level enabling sound decision making

    Define project execution plan to meet targets as required

    Explicit reconciliation of variances against project requirements

    Complete scope identification and selection of a single option for all scope elements

    Complete draft of a project execution plan

    Initial risk assessment Cost estimate with an accuracy of

    50%; and a first estimate at an operations expenditure budget

    Develop an initial schedule through completion, including resources for next phase

    Objectives Critical functions Key deliverables

    Planner - lead Users Engineering Operations / Shop support Outside support:

    Estimating Scheduling

    Support functions

    Finance Vice Chancellor

    STAGE GATE PROCESS

    ILLUSTRATIVE

    Source: Expert interviews, Team analysis

    A

  • 49 Pre-Decisional - Proprietary and Confidential |

    Function Deliverable

    Stage 1 Project Initiation and Concept Development (1/2) Deliverables by function

    PD&C (Planning and Project Manager)

    Project charter Issue record of decision for alternative selection Provide detailed scope Conduct analysis to facilitate key decision points(e.g., site, execution

    strategy) Develop initial project execution plan (scope / change management plan;

    project team and resources; contracting strategy; risk management; project controls (KPIs); estimate (50%), quality, procurement, testing and close out, schedule; communication plan; contractor management

    Engineering lead

    Evaluate technical alternatives analysis and provide recommendation Complete basic engineering data requirements (e.g., load requirements,

    equipment sizing, energy use, etc.) Implement optional value improving practices (VIPs):

    Types of plant and equipment Concept optimization Constructability reviews

    Regulatory Assign code representative, if applicable Assign environmental representative, if applicable

    STAGE GATE PROCESS

    ILLUSTRATIVE

    Source: Expert interviews, Team analysis

    A

  • 50 Pre-Decisional - Proprietary and Confidential |

    Stage 1 Project Initiation and Concept Development (2/2) Deliverables by function

    STAGE GATE PROCESS

    ILLUSTRATIVE

    Function

    Contracting Strategy

    Define delivery method, contract award method, and contract terms

    Operations and Maintenance

    Provide OPEX cost estimate, if applicable Assign operations representative for next phase, if applicable Define maintenance requirements, if applicable

    Quality assurance

    Define quality oversight

    Finance Review estimate, validate financial view calculation Input project into the budget

    Legal Provide support, as required

    Deliverable

    Source: Expert interviews, Team analysis

    A

  • 51 Pre-Decisional - Proprietary and Confidential |

    Stage 1 Project Initiation and Concept Development (1/2) Summary process map

    STAGE GATE PROCESS

    ILLUSTRATIVE

    Form core project team Review

    business case Clarify roles and

    responsibilities Identify targets

    as per CU Boulder needs

    Review project charter

    Identify additional resources required

    Project manager assigned

    Initiate conceptual engineering User

    requirements Preliminary

    massing Assess

    infrastructure requirements

    Narrow down potential sites (if applicable)

    Narrow down building concept and potential MEP systems

    Update conceptual engineering Include massing Process control

    strategies

    Identify financial and logistical issues

    Apply value improvement practices Finalize

    programmed areas

    Agree on standards and specifications

    Conduct process simplification and/or value engineering

    Conduct early constructability analysis

    Scope and document the best option: Conduct formal

    evaluation of alternatives including fatal flaws analysis, and select best available option for application

    Document record of decision

    Source: Expert interviews, Team analysis

    A

  • 52 Pre-Decisional - Proprietary and Confidential |

    Stage 1 Project Initiation and Concept Development (2/2) Summary process map

    Confirm basic engineering requirements Develop renderings

    Review engineering requirements for permits

    Decision Gate

    Confirm business objectives, risks and uncertainties and confirm compliance with both CU Boulder and user requirements and strategies

    Confirm scope to be developed and compliance with University objectives

    Present cost and schedule

    Confirm project objectives, priorities, trade-offs

    Summarize project execution strategy and plans

    Identify resource requirements for next phase and through project completion

    Issue record of decision

    STAGE GATE PROCESS

    ILLUSTRATIVE

    Develop schedule to reach Stage 2a and detailed milestone schedule for execution phase

    Prepare factored estimate (50%)

    Develop Plans for Completing: Basic

    engineering Detailed

    engineering Procurement Construction Contracting Project controls

    Develop detailed risk matrix

    Conduct preliminary equipment sizing

    Reconcile project objectives

    Develop resource requirements for Stage 2a

    Update Campus project budget

    Finalize and review scope of work

    Estimate OPEX

    Develop operations and maintenance strategies Recycle

    Proceed to Stage 2a Cancel/postpone

    Source: Expert interviews, Team analysis

    A

  • 53 Pre-Decisional - Proprietary and Confidential |

    Though the proposed stage-gate process is currently defined for Major projects, CU Boulder can extend the process to complex and eventually all Minor and Outlay projects (1/2)

    STAGE GATE PROCESS

    Rough cost of project

    150,000

    500,000

    Low Med/High

    Complexity

    Base projects

    Complex projects

    2,000,000

    Major Project Threshold

    Source: Team analysis

    A

    Base Projects can continue to utilize existing stage gate process, potentially adding key QA/QC steps

    Complex and Major Projects should use proposed stage gate process

    Definition of thresholds should be agreed through Stage-Gate working group

  • 54 Pre-Decisional - Proprietary and Confidential |

    Though the proposed stage-gate process is currently defined for Major projects, CU Boulder can extend the process to complex and eventually all Minor and Outlay projects (2/2)

    Source: Team analysis

    STAGE GATE PROCESS

    Phase 3 (2 months)

    All Minor/Outlay Projects: Applicable processes from

    Phases 1 and 2 New processes, etc. with a

    focus for streamlining

    Phase 2 (3 months)

    Develop and Implement Process for Complex Minor Projects ($0.5M-2M): Applicable processes from Phase 1 New processes, templates, agendas,

    reviews required for Phase 2

    Phase 1 (4.5 months)

    Develop and Implement Stage Gate Process for Major Projects ($2M and over) including: Pre-work required for each gate Templates Agenda for stage gate meetings Reviews required

    Expansion of stage gate process

    Time line of stage gate rollout

    A

  • 55 Pre-Decisional - Proprietary and Confidential |

    University capital project funding thresholds vary widely but are typically higher than CU Boulders

    Source: Press Search

    Initial project approvals thresholds

    Change approval thresholds

    CU Boulder has low approval thresholds even after accounting for expected regional cost variations (e.g. UC expected $/sqft costs are 1.6-1.8x CU expected costs, but UC initial approval thresholds are 10x CU thresholds)

    Delegated approval systems require up-front Board approval of Long Range Development Plans and thereafter allow Campuses to act autonomously up to a larger cap

    Percentage of budget expansion varies widely, with common aim to keep projects moving in uncertain circumstances

    Smaller campuses networks

    have smaller thresholds

    20101052

    40

    60

    15 5

    25% 30%

    5% 10% 10%

    USD Millions

    Percent of initial cost

    # of academic campuses

    Expected $/sqft1

    4 1 8 10

    185-305 185-305 265-395 340-490

    1

    1 Hard construction costs $/GSF for University buildings in select US cities, Rider Levett Bucknall Quarterly Construction Report, 2nd Quarter 2015

    NA

    Delgated budget threshold

    Observations

    A STAGE GATE PROCESS

  • 56 Pre-Decisional - Proprietary and Confidential |

    CU Boulder can adapt best practices in capital management across the four themes to begin developing excellence

    Emerging theme Description Best practice

    Stage-Gate process: how do projects move through multiple fund and scope approval gates through the lifecycle?

    Stage-gate process matches the release of required funds to the maturity level of project definition; specifically, it ensures projects do not progress without an adequate evaluation of the underlying business case, completion of key deliverables, and mitigation of critical risks

    Single and comprehensive capital investment framework

    Transparency: how do project controls allow for right information at the right time?

    Project controls dashboards enable PMs and Project Coordinators to: Proactively identify issues Ensure relevant information is at hand to

    contribute to the decision making process in a timely manner

    Tracking information on cost, schedule and milestones for each project

    Contracting: how project delivery and contracting methods are selected

    Selecting contracting strategy (delivery model, contract terms, award process) based on project specifications (size, cost, delivery schedule, complexity), market conditions, and internal capability

    Clear guidelines on contracting strategy to best manage owner risk McKinsey & Company

    VGI-AAA123-20090508-

    Working D

    raft -Last Modified 9/7/2011 3:32:09 A

    MP

    rinted 4/6/2011 4:32:15 PM

    | 3

    Contracting strategy entails defining 3 linked elements of a project

    Delivery model (How do I determine optimal contracting scope?) Should I own the asset or are other ownership structures more

    suitable, e.g., lease?

    Which project value chain steps should be done internally and which ones by contractor(s)?

    Into how many contracts should the project scope be split? What is the optimal split of scope between the contractors?

    Contract terms (How do I ensure most optimal contracting terms?) What are the key project cost, performance, and schedule risks? Who is the natural owner of the risks? What mechanisms exist to transfer or share risk? How can objectives be aligned between owner and contractor to

    ensure an efficient execution through compensation elements such as incentives, penalties, warranties, etc.?

    Key dimensions of contracting strategy Key questions to be considered

    Award process (How do I select my contractors?) How can the effectiveness of existing award process be enhanced ? How many and which suppliers/contractors should be invited? How do we get the suppliers interested? What is the criteria for evaluation various suppliers?

    Deliverymodel

    Awardprocess