McCord Road Underpass Project
McCord Road Underpass
Thursday, August 14, 2014
John
![Page 2: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/2.jpg)
Welcome
ODOT Construction
• Theresa Pollick, Public Information Officer
• Douglas Raby, P.E. Area Engineer
• Daniel Kelsey, P.E. Project Engineer
ODOT – Administrative
Lucas County Engineers Office
• Keith Early, P.E. Lucas County Engineer
• Jeff Lohse, P.E. Chief Deputy Engineer
![Page 3: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/3.jpg)
Project History
1994: TMACOG & the Lucas County Engineers
Office identified the rail crossing at McCord
Road as a safety and congestion concern.
Estimated 100 trains per day
Both Train and vehicle traffic are projected to
increase.
State Railroad Grade Separation Funding
became available: Lucas County Engineers
office and TMACOG applied.
![Page 4: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/4.jpg)
Project Basics
A project to construct an underpass at McCord
Road and the Norfolk-Southern railroad track
Build a roundabout at North Mall Drive/Hall
Street.
Prime Contractor: Beaver Excavating
Company
Project Cost: $24.3 Million
Start: August 4, 2014
Complete: November 2016
![Page 5: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/5.jpg)
McCord Road Today
![Page 6: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/6.jpg)
McCord Rd Winter 2016
![Page 7: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/7.jpg)
Construction Timeline
2014
Now through December
• Intermittent lane restrictions on McCord Road
from Airport Highway to Angola Road
• Lane restrictions possible on N. Mall Drive
• Crews build temporary railroad track foundation
& temporary roadway (S. Holland Park
Boulevard)
• Restrictions will be for moving equipment
![Page 8: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/8.jpg)
ODOT Project McCord Rd
Stage 1
![Page 9: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/9.jpg)
Construction Timeline
2015 McCord
• Spring 2015 – McCord Road/Hall/Mall Drive
75 DAY CLOSURE
McCord Road at North Mall Drive & Hall
Street will be closed to construct
roundabout
• Accommodate Springfield Local Schools
• Detour: Airport Highway; Holland-Sylvania
Road; Angola Road
![Page 10: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/10.jpg)
Construction Timeline
2015
• 75 Day Closure
North Mall Drive at the west entrance to
Wal*mart
Summer 2015
![Page 11: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/11.jpg)
Construction Timeline
2015 – Early Spring-Fall 2015
• Stage 2: Preliminary construction of stage 2
will start in March 2015
• Stage 2 has 4 phases including:
The closures of McCord Road -North Mall
Drive – Hall Street from May through August.
• The pump station construction will begin
early 2015 as well.
![Page 12: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/12.jpg)
ODOT Project McCord Rd
Stage 2
![Page 13: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/13.jpg)
ODOT Project McCord Rd
Stage 2: Pedestrian Plan
![Page 14: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/14.jpg)
Construction Timeline
• Stage 3: Fall 2015-Spring 2016
• Roundabout at McCord Road and Mall
Drive/Hall opens
• Temporary road (Holland Park Roadway) will
be open
• McCord will remain closed through August
2016
![Page 15: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/15.jpg)
ODOT Project 140236 McCord Rd
Stage 3
![Page 16: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/16.jpg)
Construction Timeline
Stage 4
Remaining portion of McCord Road, north of
the roundabout, will be completed by end of
September 2016
Remove temporary road, temporary railroad
tracks and resurface the project.
![Page 17: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/17.jpg)
ODOT Project 140236 McCord Rd
Stage 4
![Page 18: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/18.jpg)
![Page 20: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/20.jpg)
Nearby ODOT Projects
• I-475 Bridge Widening Projects
• TWO CLOSURES OF ANGOLA ROAD
SEPTEMBER 2014 - 90 day Closure of Angola at
I-475.
• SPRING 2015 - 90 day Closure of Angola at
I-475.
Detour: McCord; Airport Hwy; Holland-Sylvania
![Page 21: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/21.jpg)
Nearby ODOT Projects
• I-475 Bridge Widening Projects
• Possibility of Angola Road and McCord Road
begin closed at the same time
• GOAL is to minimize this possibility
![Page 22: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/22.jpg)
Public Information
![Page 23: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/23.jpg)
OHGO
![Page 24: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from](https://reader031.fdocuments.us/reader031/viewer/2022030504/5ab16d9c7f8b9a284c8c7273/html5/thumbnails/24.jpg)