McCombs Middle School Final Plans · 2017-12-05 · corridor 1003 vestibule storage 1707 e fire ran...
8
McCombs Middle School Final Plans Classrooms and expanded entrance Board Meeting December 12, 2017
Transcript of McCombs Middle School Final Plans · 2017-12-05 · corridor 1003 vestibule storage 1707 e fire ran...
McCombs Middle School Final Plans Classrooms and expanded entrance
Board Meeting
December 12, 2017
Site Plan
Floor Plan
Eleva,on
Highlights of project
• Additional three classrooms.
• Additional student restrooms.
• Expanded Boys & Girls Club opportunities.
• Expanded cafeteria.
• Improved administrative office/school access. Consolidated support functions.
Timeline
• December 12, 2017– Board review and approval of final plans
• Early spring 2018 – Construction start • August 15, 2018 – Completion Project budget – Estimated $1,050,000 (District)
$577,250 (Club contribution)
Total: $1,627,250 Funding – Year 3 of SWP plan