MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

37
MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Transcript of MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Page 1: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

MBTA

Groundwater Action Plan

Dr. Steve J. Poulos, P.E.

Page 2: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Topics to Cover

• Groundwater System in Back Bay

• MBTA’s Short Term Solution

• Toward MBTA’s Long Term Solution

Page 3: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Groundwater System in Back Bay

Page 4: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Groundwater in Back Bay/South End Fill

The groundwater in the Back Bay fill is, for the most part, contained within certain low-permeability boundaries that form the Back Bay. Addition or removal of groundwater in one location will affect wide areas within the fill.

Page 5: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

From Gaining Ground (2003), Figure 7.9 (Courtesy of Kane Maps)

1992 Bird’s Eye View with 1630 Shoreline of Back Bay

Study Area

Page 6: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Groundwater in Back Bay/South End Fill

Current sources of inflow to groundwater:– Leakage from Charles River and Fens– Infiltration from rainfall– Leaky water mains– Leaky sewer pipes above El. 5 BCB– Existing recharge systems

Page 7: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Groundwater in Back Bay/South End Fill

Current causes of low groundwater levels:– Loss of infiltration due to surface cover– Leakage into sewers below groundwater– Construction dewatering– Sump pumping from deep basements– Pumping for transportation corridors– Sump pumping from residences– Flow into lower sand layer

Page 8: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Groundwater in Back Bay/South End Fill

• But the groundwater levels are below El. 5 BCB in some zones, and nearby untreated timber piles are exposed to decay.

• At each zone of low groundwater levels the balance between inflow and outflow is changed due to local groundwater removal.

• At each location of low groundwater the causes, and therefore the methods used to solve the problem, both vary.

Page 9: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

MBTA’s Short Term Solution

Page 10: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Purposes of Short Term Solution

• To raise groundwater levels in an area where they have been low for several years.

• To make an in-situ test of a short term recharge system.

• To make measurements needed to design and estimate cost of possible permanent groundwater mitigation systems.

• To help identify nearby causes of groundwater lowering.

Page 11: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

View of Short Term Recharge System near Back Bay Station

Page 12: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Monitoring Well Locations

Page 13: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Details of Short Term Solution (1 of 3)

• Monitor up to 30 existing observation wells including the newly installed monitoring well on Chandler Street weekly prior to starting new recharge.

• Install two new recharge wells, one at the north end of Cazenove St. and one on Berkeley St.

Page 14: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Closer View of Short Term Recharge System

Page 15: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.
Page 16: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.
Page 17: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Details of Short Term Soltion(2 of 3)

• Recharge well on Cazenove St. at ~5 gpm using City water. Monitor effect on groundwater levels.

• Estimate how much the flow rate can be increased without affecting low basements.

• Increase recharge rate accordingly.• Measure effect of increased recharge rate on

groundwater levels.• Follow the same steps for the well on Berkeley St.

Page 18: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.
Page 19: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.
Page 20: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.
Page 21: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.
Page 22: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.
Page 23: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.
Page 24: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Construction Information for Short Term Solution

• Construction information to be distributed to adjacent residents prior to start of construction.

• Construction duration will be about one week at each location.

• No parking in vicinity of construction during work shift hours.

• About one parking space at each location will be used to store equipment between work shifts.

• Road plates and cold patch asphalt will be placed after each work shift.

Page 25: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Details of Short Term Solution(3 of 3)

• After testing is complete for the short term solution, set the flow rates appropriately for continued recharging in the two new and two existing recharge wells.

• Continue groundwater level measurements and make adjustments as needed to keep the wells operational until a permanent solution is installed and operating – perhaps in three years.

Page 26: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

ScheduleShort Term Solution

July to November 2006 Permitting for Recharge Wells

November 2006 Install Recharge Wells

October 2006 to December 2006

Weekly Groundwater Measurements

December 2006 to December 2009

Monthly Groundwater Measurements

Page 27: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Herald Street Pump Station

• Reviewed available plans. • Interviewed MBTA operations and maintenance

personnel.• Pump station observations made on:

– August 25, 2006 and October 3, 2006.

• Water is not pumped automatically.• Evaluating whether flow is occurring through

pump station without pumping.

Page 28: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Suggested Solutions that may be Implemented now by Others

• Direct roof drains into pervious fill.

• Reduce pumping as much as practicable.

• Repair leaks in deep sewers.

• Repair specific leaks if practicable.

• Develop city-wide regulations for controlling groundwater levels.

Page 29: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Short Term Solution____________________

Questions?

Page 30: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Selection of MBTA’s Long Term Solution

Page 31: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Steps to Select a Long Term Solution

• Establish Action Plan Team.• Eliminate infeasible options.• Obtain data needed to evaluate remaining options.• For the remaining options, prepare preliminary

designs and reasonable cost estimates for construction and maintenance of each option.

• Make detailed evaluations of selected options.• Select recommended solution(s) based on

evaluation of advantages and disadvantages.

Page 32: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Steps to Select a Long Term Solution

• Review MBTA plans to understand where leakage may occur.

• Measure water flow in manholes within track drainage system.

• Measure water quality in manholes and at selected pumping stations.

• Use results of Short Term Solution to obtain good estimate of permeability of fill and check against direct in-situ measurement in the new observation well.

• Use the results the Short Term Solution to help locate causes and rates of nearby groundwater removal.

Page 33: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Possible Long Term Solutions for the MBTA

• Reduce pumping as much as practicable.

• Recharge pumped groundwater into fill.

• Build buried walls or do local grouting.

• Recharge roof drains directly into fill.

• Baffles in manholes.

• Line drain pipes.

• Combinations of above.

Page 34: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Steps to Select a Long Term Solution

• Evaluate practicable solutions to mitigate or eliminate effect of groundwater pumping.

• Select a solution that is effective, environmentally appropriate, and has acceptable initial and long-term costs.

Page 35: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Draft ScheduleLong Term Solution Recommendation

July 2006 –

December 2007Data Acquisition and Public Involvement

January 2007 –

February 2007Data Evaluation and Analysis, and Public Involvement

March 2007Recommend Long Term Solution and Public Involvement

Page 36: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

Draft ScheduleLong Term Solution

Fall 2006 – Winter 2006Evaluate, Recommend, Public Involvement

Winter 2006 – Spring 2007 Plan, Design, Public Involvement

Spring 2007 – Winter 2007 Bid, Permit, Public Involvement

Winter 2007 – Winter 2008 Construct, Public Involvement

Winter 2008 – Spring 2009Observe, Monitor, Public Involvement

Spring 2009 – Winter 2009Phase Out Short Term Solution, Public Involvement

Page 37: MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.

EndThank you!