Materials Degradation/Aging Action Plan Committee (MAPC). · – See following slides for an update...
Transcript of Materials Degradation/Aging Action Plan Committee (MAPC). · – See following slides for an update...
Bill Pitesa (Duke), MAPC Executive Chair Scot Greenlee (Exelon), MAPC Technical Chair Kurt Edsinger (EPRI), MAPC Program Manager
Robin Dyle (EPRI), Technical Executive
Industry/NRC Executive Meeting on Materials Program June 25, 2014
Materials Degradation / Aging Action Plan Committee (MAPC)
2 © 2013 Electric Power Research Institute, Inc. All rights reserved.
Outline
• Program Organization • Research Update for other EPRI Programs
– Primary Systems Corrosion Research (PSCR) – No Chemistry or WRTC this meeting
• Technical Issues Update – CASS – BTP 5-3
• Proposal for Prioritizing Research • Contact Information
3 © 2013 Electric Power Research Institute, Inc. All rights reserved.
Programs to Manage Materials Issues
• EPRI Materials Programs – BWR Materials (BWRVIP) – PWR Materials (MRP) – Steam Generator (SGMP) – Primary Systems Corrosion Research (PSCR) – Welding & Repair Technology Center (WRTC)
• Other Coordinated EPRI Programs – NDE – Water Chemistry Control
• PWR Owners Group – Materials Subcommittee (MSC)
4 © 2013 Electric Power Research Institute, Inc. All rights reserved.
Materials Action Plan Committee (MAPC)
Source: EPRI Operations Protocol
“Beginning January 1, 2010, the EPRI Materials Degradation and Aging Action Plan Committee has the principal role for overseeing industry activities related to primary system materials and the continuing commitment to the Industry Materials Initiative (NEI 03-08).
5 © 2013 Electric Power Research Institute, Inc. All rights reserved.
Materials Organizational Structure
PMMP Executive Committee (EC)
Nuclear Power Council
Materials & Aging Action Plan Committee
(MAPC)
Executive Chair: Bill Pitesa, Duke
Technical Chair: Scot Greenlee, Exelon
BWR Vessel Internals Program (BWRVIP)
Materials Reliability Program (MRP)
Steam Generator Mgmt Project (SGMP)
Primary System Corrosion Research
(PSCR)
BWRVIP Executive Committee
NDE Action Plan Committee*
Other APCs not shown
PWR Owners Group Materials Subcommittee (PWROG MSC)**
PMMP (EOC)
Welding & Repair Technology Center
(WRTC)
BWRVIP EOC
Water Chemistry Action Plan Committee
Long Term Operations
*NDE APC coordinates with Materials APC and PWR Owners Group **Materials Subcommittee has a representative on Materials APC
6 © 2013 Electric Power Research Institute, Inc. All rights reserved.
EPRI IASCC Crack Growth Report–Status • Database includes over 1600 test segments (cyclic data excluded)
ranked by expert panel • Fluence range 0.21– 43.5 dpa • Draft report on the IASCC database and low ECP (PWR and BWR-
HWC) and high ECP (BWR-NWC) IASCC models is complete • Next draft for industry review to be issued in August for PSCR, MRP
and BWRVIP committees review • Resolve industry comments, revise report and publish by end of 2014 • The report will provide the technical basis for crack growth disposition
curves for irradiated BWR and PWR stainless steel internals for renewal term and subsequent license renewal
• Expect to provide report to NRC for review in 2015
7 © 2013 Electric Power Research Institute, Inc. All rights reserved.
CASS in Reactor Internals • Issue affects BWRs (BWRVIP-234) and PWRs (MRP-227-A) • MRP and BWRVIP met with NRC staff 2/18/2014 to understand issues
related to thermal and irradiation embrittlement of CASS – NRC concerns were use of perceived non-conservative values for
CASS chemical compositions (FN), and fluences for onset of irradiation embrittlement (e.g., Grimes letter versus MRP-175)
• NRC has issued RAIs to PWRs with a proposed new position – NRC tech basis shared with Industry early June
• MRP / BWRVIP CASS joint working group established technical position for screening CASS reactor internals – Unified industry position for CASS internals – Applicable to BWRs and PWRs – Provided to NRC May 23
• Next Steps: – Industry meeting with staff 7/15/2014 – Quick resolution of technical issues needed
8 © 2013 Electric Power Research Institute, Inc. All rights reserved.
BTP 5-3 Summary and Background of Issue • In 1972/73 ASME Code adopted RTNDT-based evaluation of RPV integrity • NRC revised 10 CFR 50 Appendix G to require all plants to comply • Because RPVs ordered before August 15, 1973 may not have those
tests, NRC provided methods to convert pre-1973 test data into parameters needed (then MTEB 5-2, now BTP 5-3) – Technical basis for NRC guidance in BTP 5-3 is unknown – Older plants used BTP 5-3, which NRC reviewed and approved
• Many older PWRs and BWRs have used these licensed values for 40 years to show compliance with RPV integrity regulations
• 2013 research by AREVA suggested potential non-conservatism of one of the BTP 5-3 methods
• In an evaluation of the AREVA results, it was found that NRC had contracted with EG&G Idaho (INEL) in 1983 to review and evaluate BTP 5-3 (MTEB 5-2) – INEL report noted 3 of 5 methods found to be potentially non-
conservative – No record of NRC disposition of report found – BTP 5-3 was not revised
9 © 2013 Electric Power Research Institute, Inc. All rights reserved.
Outline of MRP/BWRVIP BTP 5-3 Project Plan • Industry decided to perform its own data review and evaluation • Identify possible, viable alternatives to the guidance in BTP 5-3
paragraphs B.1.1(3), B.1.1(4), or B.1.2 if they are found to be potentially non-conservative
• Assess extent of condition – To verify the scope of materials potentially affected, a survey was
sent to all BWRS and PWRs; responses by July 25, 2014 • Assemble enhanced materials database of USE and TNDT measurements
and evaluate the BTP 5-3 procedures (independent of current on-going NRC evaluation)
• Where necessary, recommend revised procedures • Draft report due mid-November • Industry suggests a public meeting to discuss BTP 5-3 (and other RPV
issues) in the Fall – e.g., late October 2014
10 © 2013 Electric Power Research Institute, Inc. All rights reserved.
Prioritizing Materials Work and Research
Background • A number of research projects have been driven by a regulatory need,
whether perceived or communicated, rather than a defined issue or a safety challenge
• Examples: – SG divider plate cracking – Plant specific RAIs on use of MRP-227 – P-T limits (small flaws vs. operational constraints) – BWR steam dryer evaluation methodology – RAIs for previously approved BWRVIP guidance
• In many cases, the initial look was appropriate, but we are not good at stopping when we know enough to stop
11 © 2013 Electric Power Research Institute, Inc. All rights reserved.
Proposal for Prioritizing Research (cont’d) Approach • Develop a template to discuss and compare research priorities • Focused on upfront discussion (i.e., as issue begins to emerge), but
also need the ability to check and adjust • Start with NEI cumulative impact assessment • Potential filters might include:
– Impact on safety – Breadth of impact – Reopening approved issues absent OE or new data – Support for ongoing review – Realistic versus hypothetical issue – Public Perception
12 © 2013 Electric Power Research Institute, Inc. All rights reserved.
MAPC Key Contact Information • MAPC Executive Chairman Bill Pitesa, Duke, Senior Vice President and Chief Nuclear Officer
– Phone: 704-382-7258 – E-Mail: [email protected]
• MAPC Technical Chairman Scot Greenlee, Exelon, Senior Vice President, Engineering & Technical Services
– Phone: 630-657-3723 – Email: [email protected]
• MAPC Program Manager Kurt Edsinger, EPRI, Director of Materials
– Phone: 650-855-2271 – Email: [email protected]
• Robin Dyle, EPRI, Technical Executive – Phone: 205-426-5371 – Email: [email protected]
13 © 2013 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity
14 © 2013 Electric Power Research Institute, Inc. All rights reserved.
Materials Roadmaps
1. BWR and PWR Irradiated Materials Testing and Degradation Models 2. Steam Generator Foreign Object Management 3. Steam Generator Degradation Prediction and Mitigation 4. Management of Jet Pump Flow-Induced Vibration 5. Ensuring Reactor Pressure Vessel Integrity Through Eighty Years of
Operation 6. PWR reactor internals aging management 7. Welding of Irradiated Materials for PWR and BWR Internals 8. Alloy 52 Nickel-Base Filler Metal Weldability Solution 9. High Chromium Weld Metal Development and Cracking Mechanisms
15 © 2013 Electric Power Research Institute, Inc. All rights reserved.
Materials Roadmaps (cont’d)
10. Aging Management of Alloy 600 and Alloy 82/182 in the Steam Generator Channel Head Assembly
11. Mitigation of Boiling Water Reactor Materials Degradation 12. Fatigue Management in Boiling and Pressurized Water Reactor
Coolant Systems 13. Pipe Rupture Probability Re-Assessment (XLPR) 14. Primary Water Stress Corrosion Cracking Characterization of Alloy
690 and Weld Metals 15. Advance Welding Process development in the Nuclear Power
Industry 16. Incorporation of Fabrication, Repair and Joining Technologies in
Nuclear Codes and Standards 17. Steam Generator Tube Integrity Assessment 18. Understanding of Environmental Effects on Fracture Properties
BWR Vessel & Internals Project (BWRVIP)
Tim Hanley, Exelon BWRVIP Executive Committee Chairman
Drew Odell, Exelon BWRVIP Integration Committee Chairman
Andy McGehee BWRVIP Program Manager
Robin Dyle EPRI Technical Executive
Industry/NRC Executive Meeting on Materials Program June 25, 2014
2 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Overview Outline
• Current Members and Organization
• 2014 BWRVIP Major Tasks
• Status of Key Topics with NRC
• Contact Information
3 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Current Members and Organization
4 © 2014 Electric Power Research Institute, Inc. All rights reserved.
2014 BWRVIP Member Utilities
U. S. • Constellation • DTE Energy • Duke Energy
• Energy Northwest • Entergy • Exelon
• FirstEnergy • NextEra Energy
• NPPD • PPL
• PSEG Nuclear • Southern Nuclear Company • Tennessee Valley Authority
• Xcel Energy
Non-US • BKW FMB Energie AG – Switzerland
• Chubu Electric Power Company – Japan • Chugoku Electric Power Company – Japan • Comision Federal de Electricidad – Mexico
• Forsmarks Kraftgrupp AB – Sweden • Iberdrola Generation – Spain
• Kernkraftwerk Leibstadt – Switzerland • Nuclenor – Spain
• OKG Aktiebolag – Sweden • Ringhals AB – Sweden
• Taiwan Power Company – Taiwan • Tokyo Electric Power Company – Japan
5 © 2014 Electric Power Research Institute, Inc. All rights reserved.
2014 BWRVIP Organization
Assessment Committee Ron DiSabatino, Exelon (Technical Chairman)
Steve Richter, Energy Northwest (Technical Vice Chair)
Bob Carter, EPRI (Task Manager)
Mitigation Committee Dan Miller, PPL (Technical Chairman)
David Willer, DTE (Technical Vice Chair)
Raj Pathania, (EPRI Task Manager)
Integration Committee Drew Odell, Exelon Vacant
Chairman Vice Chairman
Andy McGehee
EPRI Program Manager
Repair Focus Group Denver Atwood, Southern Nuclear (Chairman)
Wynter McGruder, Xcel (Vice Chairman)
Ken Wolfe, EPRI (Task Manager)
Inspection Focus Group Dave Potter, Xcel (Chairman)
Christian McKean, Exelon (Vice Chairman)
Jeff Landrum, EPRI (Task Manager)
Executive Committee Tim Hanley, Exelon Vacant
Chairman Vice-Chairman
Andy McGehee
EPRI Program Manager Executive Oversight Committee Ken Knaide, PSEG (AC Exec Sponsor),
Joe Frisco, Duke (Mitigation Exec Sponsor),
Dennis Madison, Southern (BWROG Chair),
Dave Czufin, TVA (EOC at large)
Mitigation Monitoring FG Steve Williams, Duke (Chairman)
Larry Loomis, Entergy (Vice Chair)
Susan Garcia, (EPRI Task Manager)
Red = gap
Green = new
6 © 2014 Electric Power Research Institute, Inc. All rights reserved.
2014 BWRVIP Major Tasks
7 © 2014 Electric Power Research Institute, Inc. All rights reserved.
2014 BWRVIP Major Tasks • 2014 Water Chemistry Guidelines Revision
– Revision to the current BWR Water Chemistry Guidelines, BWRVIP-190 has been released to VIP members for implementation
• Evaluation of Shroud Cracking (NDE & Boat Sample Analysis at Hatch Unit 1) – See following slides for an update
• Inspection and Evaluation Guidelines Optimization – Core Spray, Jet Pump Guidelines and Core Shroud – Currently Core Spray has been submitted to NRC and Jet
Pump is in-progress • Address Jet Pump Flow-Induced Vibration Issues
– See following slides for an update on the BWRVIP’s Full Scale Jet Pump Test Facility
Core Shroud Inspection and Boat Sample Testing
9 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Background
• Atypical cracking found during 2008 ID visual inspections of core shroud at Hatch Unit 1 – Similar but less extensive cracking observed at several other
BWRs – Cracking did not have characteristics typical of IGSCC – Cracking might be the result of IASCC
• BWRVIP Focus Group formed in 2010 to investigate cause of cracking – Focus Group recommended evaluation of Hatch cracking to
determine cause and recommend further actions – BWRVIP report issued in 2011 recommended UT inspection
to further characterize length, depth and orientation of flaws, and removal of boat sample
– UT and boat sample removal performed in Spring 2014
10 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Boat Sample Location Selection
• Locations for boat sample were pre-selected based on 2008 visual inspection results
• Sample depth sizing and removal was a critical path activity, thus decision tree developed and used to select between locations based on UT results
• Sample taken at a location of high fluence where flaw was ~0.8” deep
• Boat sample: – Approximately 2”x3”x1” – Contains weld and base metal – Crack extends from weld into base
metal (perpendicular to H4)
11 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Boat Sample Evaluation
• BWRVIP is funding testing and analysis of the boat sample to determine cause of cracking
• Boat sample schedule: – Shipment of boat sample is expected in September 2014 – Final report to be published in November 2015
• However, schedule is contingent upon timely NRC approval of Class B shipping container
12 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Ongoing BWRVIP Activities
• BWRVIP Focus Group evaluating required actions – What near term actions are required?
• Interim inspections, prior inspection data review, etc. • Is adequate guidance available for evaluating indications (structural and leakage)
– Longer term • Monitoring of fleet inspection results • Review boat sample results • Revise shroud inspection guidance as necessary
13 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Jet Pump Testing for BWR 4 Configuration
14 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Full Scale Jet Pump Test Facility
Accumulator for pressure control
Heat exchanger
Recirculation pump and motor
Flow meter
Water storage tank
Test vessel
Concrete enclosure
15 © 2014 Electric Power Research Institute, Inc. All rights reserved.
View from Top of Pressure Vessel
Filled with water
16 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Status of Full Scale Jet Pump Testing
• Testing of the facility in the BWR/5 jet pump configuration was completed in Fall of 2012 and demonstrated that the test facility met all flow, temperature and pressure requirements, and was able to replicate the flow-induced vibration (FIV) phenomena. The testing provided a significant amount of knowledge regarding the causes of jet pump FIV.
• Vendor demonstrations for FIV repair hardware have been performed.
• Vendors and utilities have used the facility for hardware developmental testing.
• Currently reconfiguration of the test facility for BWR/4 testing is underway.
17 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Status of Key NRC Topics
18 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Status of Key Topics with NRC
• GE Safety Communications impact on BWRVIP Guidance • Remote VT Round Robin • BWRVIP-62, Rev 1 - Inspection Relief with OLNC & HWC • Integrated Surveillance Program (ISP) for BWRs
19 © 2014 Electric Power Research Institute, Inc. All rights reserved.
GE Safety Communications impact on BWRVIP Guidelines • GEH issued (June 2013) three Safety Communications
(SCs) that deal with RLB loads – 09-03, Rev 1: Core Shroud Screening Reports
(consideration of RLB acoustic loads in the reports) – 11-07, Rev 0: Impact of Inertial Loading and Potential
New Load Combination from Recirculation Suction Line Break Acoustic Loads
– 12-20, Rev 0: Error in Method of Characteristics Boundary Conditions Affecting Acoustic Loads Analyses
• SCs are an output of GEH’s 10 CFR Part 21 evaluation program and all three of these SCs conclude that the issues do not present substantial safety concerns and are not reportable under Part 21
20 © 2014 Electric Power Research Institute, Inc. All rights reserved.
GE Safety Communications impact on BWRVIP Guidelines • Focus Group meeting held 9-19-13 at Exelon offices. • Goal to identify reports that were directly impacted or could
benefit from augmented guidance. • Reviewed the BWRVIP Guidelines for components addressed
by the BWRVIP. • Focused on those sections that discuss loads , load
combinations and example flaw evaluations. • Meeting minutes were published to BWRVIP members. • 4 reports were identified as likely having “technical bases
impact” • BWRVIP-25, Core Plate / BWRVIP-26-A, Top Guide /
BWRVIP-38, Shroud Support / BWRVIP-136, Shroud Support Gussets
21 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Future and Ongoing Actions GE Safety Communications & BWRVIP reports • Develop augmented guidance for loads and load combinations • Evaluate reports for impact BWRVIP-25 I&E Guideline (Core Plate) underway Remaining reports will follow based upon scope and
budget. • Based on current knowledge and conservatisms, the BWRVIP
believes there are no near-term concerns with use of BWRVIP guidelines.
• When evaluations are complete, BWRVIP will advise the NRC and revise documents as warranted.
22 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Remote VT Round Robin - Involvement in Industry Wide Projects • Remote VT Round Robin
– Joint Memorandum of Understanding (MOU) project between EPRI and the NRC Research
– BWRVIP co-funds the project – The BWRVIP Inspection Focus Group Chairman also Chairs
the utility Ad hoc committee overseeing the project – There is extensive use of remote VT by the BWRVIP
Inspection & Evaluation Guidelines (I&EGs) so the BWRVIP is a major stakeholder in the project
– Objective and planning meeting (Phase 3) is scheduled for August 5 & 6, 2014 in Charlotte. NRC Research and their contractor for the Remote VT MOU, Pacific Northwest National Laboratories (PNNL), are participating.
23 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Topical Report Reviews
• BWRVIP-62, Rev. 1 (Inspection Relief with OLNC & HWC) – Submitted to the NRC March 7, 2012 – NRC requested review of many of the reference documents
for BWRVIP-62, Rev. 1 – NRC has questioned aspects of the already approved
technology for classic Noble Metals Chemical Addition (NMCA) and Hydrogen Water Chemistry (HWC)
– Good communications between Industry and Staff via several teleconferences and a face-to-face meeting (March 28, 2013) held to outline the issues and work toward resolution
– RAIs received from the staff in March 2014 – The BWRVIP is working on RAI responses with a pre-RAI
submittal meeting with the staff scheduled for July 18, 2014
24 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Integrated Surveillance Program (ISP) for BWRs
• Due to the BWRVIP’s capsule testing process, including BWRVIP Committee review and approval of the capsule reports, the capsule reports cannot be completed within one-year and thus extensions to 18 months are necessary.
• Historically, the BWRVIP provided notification letters for the delays, but in recent years submitted formal extension requests for the last three ISP capsule withdrawals (Susquehanna 1, Duane Arnold and Perry).
• A conversation was held with the NRC in November 2013 and the NRC noted that the SE for the ISP acknowledges the BWRVIP as being responsible for submittal of ISP capsule reports and, if needed, extension requests.
25 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Integrated Surveillance Program (ISP) for BWRs
• The NRC asked that extension requests include the current Effective Full Power Years (EFPY) for the plants affected by the capsule results and the EFPY for the approved P-T curves at those plants. The BWRVIP agreed to include that information in future requests and provided that information to the NRC for Duane Arnold and Perry via letter 2013-211, dated 11/20/13.
• Several communications with the staff have followed to ensure all technical information was available for the staff to complete their review.
• It is expected that the staff will provide responses to the extension requests shortly.
26 © 2014 Electric Power Research Institute, Inc. All rights reserved.
BWRVIP Key Contact Information
• BWRVIP Executive Chairman Tim Hanley, Exelon
– Phone: 630-657-3724 – E-Mail: [email protected]
• Utility Technical Chairman Drew Odell, Exelon – Phone: 610-212-1155 – Email: [email protected]
• EPRI Program Manager Andy McGehee – Phone: 704-502-6440 – Email: [email protected]
27 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity
David Czufin, TVA, PMMP Executive Chairman Randy Stark, EPRI, SGMP Program Manager Anne Demma, EPRI, MRP Program Manager
June 25, 2014
PWR Materials – MRP and SGMP
2 © 2014 Electric Power Research Institute, Inc. All rights reserved.
BWRVIP BWR Vessel &
Internals Program
Exec Chair Dennis Madison
SNC
IC Chair Drew Odell
Exelon
Andy McGehee EPRI PM
Advisory Structure Action Plan Committee
Executive Chair: Bill Pitesa, Duke Technical Chair: Scot Greenlee, Exelon
Kurt Edsinger, Director
MRP PWR Materials
Reliability Program
Exec Chair David Czufin
TVA
IC Chair Bernie Rudell
Exelon
Anne Demma EPRI PM
WRTC Welding & Repair
Technology Center
Exec Chair Bill Pitesa
Duke
IC Chair Dan Patten
FENOC
Greg Frederick EPRI PM
SGMP Steam Generator Mgmt Program
Exec Chair David Czufin
TVA
IC Chair Jim Stevens
Luminant
Randy Stark EPRI PM
PSCR Primary Systems
Corrosion Research
Exec Chair Bill Pitesa
Duke
IC Chair Ian Armson Rolls
Royce
TG Lian EPRI PM
Exec Sponsor Elliott Flick, Exelon
Exec Sponsor Eric Larson, FENOC
Exec Sponsor Ben Mays, Luminant
3 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Materials Reliability Program
4 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Outline
• MRP Organization • NEI 03-08 Guidelines • Technical Areas Examples
5 © 2014 Electric Power Research Institute, Inc. All rights reserved.
2014 MRP Organization
Materials Reliability Program (IC)
Rudell, Constellation IC Vice Chairman-TBD
Demma, EPRI
Regulatory Interface Richter, NEI Dyle, EPRI
Technical Support TAC Hoehn, Ameren
Childress, Duke Energy McDevitt, EPRI
Inspection TAC Fernandez, APS
Cordes, Southern Nuclear Swain, EPRI
Mitigation/Testing TAC
Gobell, Entergy Efsing, Ringhals
Smith, EPRI
Assessment TAC Sims, Entergy DeBoo, Exelon Amberge, EPRI
Harrington, EPRI
Technical Advisory Group
IC Vice Chairman-TBD Demma, EPRI Materials Review Visits
Crane, INPO
6 © 2014 Electric Power Research Institute, Inc. All rights reserved.
MRP Documents with Mandatory & Needed Elements Governed by the Materials Initiative
Doc Number (EPRI PID)
Rev Document Title Date Implementation
Level Comments
MRP-126 (1009561)
0 Generic Guidance for an Alloy 600 Management Plan
Nov 2004 Mandatory
MRP-146 (1022564)
1 Management of Thermal Fatigue in Normally Stagnant Non-Isolable Reactor Coolant System Branch Lines
Jun 2011 Needed
MRP-146S (1018330)
0 Management of Thermal Fatigue in Normally Stagnant Non-Isolable Reactor Coolant System Branch Lines – Supplemental Guidance
Jan 2009 Needed
MRP-227-A (1022863)
A MRP 227-A, Pressurized Water Reactors Internals Inspection and Evaluation Guidelines
Dec 2011 Mandatory
MRP 2014-006
0 MRP-227-A Interim Guidance Modification to inspection requirements of tables 4-3 and 5-3 for Westinghouse Control Rod Guide Tube Assemblies
Feb 2014 Needed MRP Letter
Documents Incorporated Within (i.e., issued prior to the initiative) or Under the Materials Initiative (i.e., issued since the initiative)
7 © 2014 Electric Power Research Institute, Inc. All rights reserved.
MRP Documents with Mandatory & Needed Elements Governed by the Materials Initiative
Doc Number (EPRI PID)
Rev Document Title Date Implementatio
n Level Comments
MRP-228 (1025147)
1 MRP-228 Inspection Standard for PWR Internals
Dec 2012 Needed
MRP 2013-023
0 MRP-228 Interim Guidance Reactor Internal Baffle-Former Bolting Ultrasonic Examinations
Oct 2013 Needed Letter
MRP-139 (1015009)
MRP 2010-046
1 MRP-139, Primary System Piping Butt Welds Inspection and Evaluation Guideline, and Interim Guidance Letter MRP 2010-046
Dec 2008 N/A Superseded by requirements of Code Case N-770 as amended by 50.55a Listed for historical purposes only. MRP maintains the technical basis.
MRP-326 (1022871)
MRP 2012-031
0 MRP-326, Coordinated PWR Vessel Surveillance Program (CRVSP) Guidelines, and Interim Guidance Letter MRP 2012-031
Dec 2011 N/A All required member actions have been completed. Listed for historical purposes only.
Documents Incorporated Within (i.e., issued prior to the initiative) or Under the Materials Initiative (i.e., issued since the initiative)
8 © 2014 Electric Power Research Institute, Inc. All rights reserved.
MRP Technical Area: Irradiated Material Testing
Zorita Internals Research Project (ZIRP)
Current Participants • EPRI • U.S. NRC • CSN (Spanish regulator) • SSM (Swedish regulator) • Tractebel • AXPO • Additional in-kind contribution
from Japanese utilities/MHI
Objective: Characterize the effects of neutron irradiation on the mechanical and microscopic properties of stainless steel materials irradiated under service conditions to increase the understanding of fluence effects at end of service life (40, 60 years and beyond)
Jose Cabrera NPP “Zorita” Westinghouse design
1968 – 2006 (~26 EFPY)
9 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Zorita Internals Research Project Zorita Baffle Plate Materials
• Baffle plate material from between 3rd and 4th formers
• Type 304 Stainless Steel • Doses ranging from a few
dpa to ~50 dpa • Thickness 28.6 mm • Piece B1 contains eight
Type 347 SS bolts
Piece B3 ~10 dpa max
Piece B1 ~50 dpa max Piece B2
~30 dpa max
10 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Zorita Internals Research Project Current Status
• Tensile Testing complete – 10, 30, and 50 dpa specimens at
RT and 320°C • Crack Growth Rate Testing
– 30 and 50 dpa specimens currently underway
– 10 dpa specimen and duplicates of all doses to follow
• Crack Initiation Testing – High dpa material tests to begin
4Q2014 • Fracture Toughness Testing
– Begin with 10 dpa specimens in air and primary water in 3Q2014
– 30 and 30 dpa specimens to follow • Microstructural Testing
– Shipment of material to MHI in Japan for TEM, gas analysis
Piece B1 Piece B2 Piece B3
11 © 2014 Electric Power Research Institute, Inc. All rights reserved.
MRP Projects Using Additional Zorita Materials
• Determine combined effects of irradiation & elevated temperature on embrittlement of stainless steel welds and characterize environmental effect on fracture toughness in irradiated stainless steel welds
• Currently in contracting process with vendor • Project uses Zorita core barrel weld material
Thermal and Irradiation Embrittlement and
Environmental Effects Testing of Stainless Steel
Welds
• Develop IASCC CGR data in irradiated stainless steel weld and HAZ materials for comparison to existing data for base materials
• Currently in contracting process with vendor • Project uses Zorita core barrel weld material
CGR Testing of Irradiated SS Weld and HAZ Materials
• Evaluate IASCC crack initiation and crack growth rates and degree of void swelling in highly-irradiated (near end-of-life conditions) stainless steel base metal and welds
• Currently evaluating responses to RFP • Project uses Zorita baffle plate & core barrel weld
material
Determination of IASCC CGR, Initiation Rate, and Void Swelling in Zorita
Material after Post-Reactor Irradiation
12 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Peening for PWSCC Mitigation - Components of Interest
13 © 2014 Electric Power Research Institute, Inc. All rights reserved.
• Peening prevents PWSCC initiation and eliminates growth of shallow flaws within the surface compressive residual stress zone
• In mid-2012, EPRI completed the MRP-335 topical report supporting inspection optimization for peening mitigation of Alloy 82/182 piping dissimilar metal butt welds and Alloy 600 RV top head nozzles
• ASME Section XI is addressing peening
• Code Case N-770-4 addressing the Alloy 82/182 piping butt welds was approved on May 7, 2014
• A revision to Code Case N-729 is now being developed to address Alloy 600 top head nozzles, and is expected to be approved in 2015
• U.S. industry is eager for U.S. NRC to complete its SE review of the topical report formally submitted in February 2013
MRP Technical Area: PWSCC Mitigation by Peening
Laser Peening
Bubbles collapse
Water Jet Peening
Bubble cloud
Plans for peening two US PWRs in 2016 have been announced
14 © 2014 Electric Power Research Institute, Inc. All rights reserved.
MRP Technical Area: Alloy 690 • Testing and field experience
confirm high PWSCC resistance of Alloys 690/52/152
• More extensive work explored or underway to further understand – Vulnerability to abnormal
microstructure and to welding residual stresses and strains
– Role of weld imperfections in initiation and growth of PWSCC
• Work substantiates technical basis for optimized inspection of A690 replacement components such as the reactor pressure vessel head
Repair Weld 1
15 © 2014 Electric Power Research Institute, Inc. All rights reserved.
MRP-375 Technical Basis for Reexamination Interval for RV Heads with Alloy 690 Nozzles • Lab and plant data support a technically based longer volumetric/surface
examination interval using appropriate analytical tools
• Currently, more than 100 replacement and new heads with Alloy 690 nozzles and Alloy 52/152 attachment welds are in service worldwide
• A detailed technical basis document supporting extension of the current 10-year interval of N-729-1 was published by EPRI in February 2014 – MRP-375 (EPRI 3002002441), freely downloadable at www.epri.com – Recommends a 20-year interval, and includes options for sample inspection
programs – Proposes that the existing visual exam (VE) interval for evidence of leakage of no
more than 5 calendar years be maintained
• ASME Section XI is now considering a revision to Code Case N-729 that includes a revised interval for volumetric/surface exams
• Licensees are now developing relief requests based on MRP-375
• Request technical dialogue on efficient regulator review approach for multiple relief requests or other alternatives
16 © 2014 Electric Power Research Institute, Inc. All rights reserved.
MRP Technical Area: PWR Internals
• PWR Internals Inspection and Evaluation Guidelines MRP-227-A (Report 1022863) issued in Jan. 2012
• Revising the guidelines • Publish in 2015
Experience to date shows limited degradation
• Inspection guidance and flaw evaluation methodologies
17 © 2014 Electric Power Research Institute, Inc. All rights reserved.
PWR Internals Inspection Results to Date and Reporting • Initial full inspections at W and B&W and partial CE NSSS
designs have not identified any major issues of concern • Issues of greatest concern not seen
– SCC of austenitic welded components not observed • Cracking currently limited to high strength bolting
– IASCC of welds not observed, indications limited to bolts – Macroscopic effect of void swelling not observed
• EPRI MRP provided internals inspection results to NRC
staff in EPRI letter MRP-2014-009, consistent with MRP-227-A ‘Needed’ requirement for reporting results – Submitted to NRC on May 12, 2014 (ML14135A383, 84, 85)
18 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Industry Near Term Inspection Plans
Anticipated near term schedule of U.S. inspections
Fall 2014 – 1 Westinghouse Design
Spring 2015 – 1 CE Design
Fall 2015 – 3 Westinghouse Designs
Several more in 2016-2018 time frame
19 © 2014 Electric Power Research Institute, Inc. All rights reserved.
PWR Internals Topic of Interest
Cold Work of Stainless Steels (Licensee Action Item 1) • NRC staff reviewers provided plant-specific RAIs related to
>20% cold work (CW) of stainless steel • MRP and OEM prepared RAI response template provided
to licensees via MRP-2013-025 – Criteria defined by MRP – Resource intensive effort with no cases of CW found yet
20 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Steam Generator Management Program
21 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Outline
• SGMP Organization • NEI 03-08 Guidelines • Current Key Technical Areas
22 © 2014 Electric Power Research Institute, Inc. All rights reserved.
EPRI SGMP Organization
SGMP Integration Committee (IC) J. Stevens, Luminant (Chair)
J. Arhar, PG&E (V.C.) R. Stark, EPRI
Technical Advisory Group J. Arhar, PG&E
J. Benson, EPRI NEI M. Richter
Technical Support TAC L. Miller, Dominion (Chair) K. Johnson, Duke (V.C.)
R. Wolfe, EPRI
Engineering & Regulatory TAC P. Fabian, PSEG(Chair)
W. Leaverton, APS (V.C.) H. Cothron, EPRI
NDE TAC D. Folsom, TVA (Chair) S. Redner, Xcel (V.C.)
R. Guill, EPRI
INPO C. Lane
23 © 2014 Electric Power Research Institute, Inc. All rights reserved.
SGMP Guidelines Status (Page 1 of 2)
Guideline Title Current Rev #
Report #
Last Pub
Implementation
Interim Guidance
Review Date Comments
Steam Generator Integrity
Assessment Guidelines
3 1019038 Nov 2009 9/1/2010
SGMP-IG-10-01
SGMP-IG-12-01
Rev 4 in progress
EPRI Steam Generator In Situ Pressure
Test Guidelines
4 1025132 Oct 2012 10/10/2013 none 2015
PWR Steam Generator
Examination Guidelines
7 1013706 Oct 2007 9/1/2008
SGMP-IG-08-04
SGMP-IG-12-01
Rev 8 in progress
PWR Steam Generator Primary-to-Secondary
Leak Guidelines
4 1022832 Sep 2011
4/11/20127/11/2012 none 2014
24 © 2014 Electric Power Research Institute, Inc. All rights reserved.
SGMP Guidelines Status (Page 2 of 2)
Guideline Title Current Rev # Report # Last Pub
DateImplementation
Date(s)Interim
GuidanceReview
Date Comments
PWR Primary Water Chemistry Guidelines 7 3002000505 April
2014 1/28/2015
PWR Secondary Water Chemistry Guidelines 7 1016555 Feb 2009 8/20/2009
11/20/2009
SGMP-IG-13-01
SGMP-IG-14-02
2014
Steam Generator Management Program
Administrative Procedures
3 1022343 Dec 2010 9/1/201112/31/2011 none n/a Rev 4 in
progress
Steam Generator Degradation Specific
Flaw Handbook1 1019037 Dec 2009 n/a none n/a Rev 2 in
progress
25 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Steam Generator Management Program Current Issues for the SGMP
• Channel Head divider plate to stub runner weld cracking • Cracking of Alloy 600TT steam generator tubing
– PWSCC & ODSCC – Cracking at tube end and indications at tube end welds (both
hot and cold legs) • Mechanical wear of tubes due to contact with support structures
and foreign objects • Improved thermal-hydraulics code (Triton) • Improved inspection capabilities
– Total inspection system performance – Auto analysis capabilities – Maintenance of the Examination Technique Specification
Sheets (ETSS) program
26 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity
P R E S S U R I Z E D W A T E R R E A C T O R O W N E R S G R O U P
Global Expertise • One Voice
Annual Materials Programs Executive Information Exchange Meeting
June 2014 PWROG Materials Subcommittee
Update
Scot Greenlee (Exelon) Technical Chairman of the Materials Action Plan Committee
P R E S S U R I Z E D W A T E R R E A C T O R O W N E R S G R O U P
Annual Materials Programs Executive Information Exchange Meeting June 2014
PWR Owners Group MSC Agenda
2
• PWROG MSC Key Strategic Areas Core/Planning Team Organization
• PWROG MSC/NRC Interactions
• PWROG MSC Areas of Coordination & Strategic Planning with MRP
• PWROG MSC Focus Areas for 2014-2015
P R E S S U R I Z E D W A T E R R E A C T O R O W N E R S G R O U P 3
Annual Materials Programs Executive Information Exchange Meeting June 2014
PWROG MSC Key Strategic Areas Core/Planning Team Organization
Materials Committee Chris Koehler, Xcel (Chairman)
(612) 330-6755
Heather Malikowski, Exelon (Vice-Chair) (610) 765-5864
Reactor Internals Planning Team
Glenn Gardner (860) 440-0373
Stainless Steels Core Team Heather Malikowski, Exelon
(610) 765-5864
Reactor Vessel Integrity Core Team
Jim Nurrenbern, Ameren (314) 225-1908
Zinc Mitigation Core Team Heather Malikowski, Exelon
(610) 765-5864
Jim Molkenthin PWROG PMO (860) 731-6727
Tammy Natour
AREVA (434) 832-2763
BMI Core Team Mike Garner
(361) 972-4004
P R E S S U R I Z E D W A T E R R E A C T O R O W N E R S G R O U P 4
Annual Materials Programs Executive Information Exchange Meeting June 2014 PWROG MSC/NRC Interactions
• NRC Interactions: WCAP-17096 under PA-MSC-0473 “Reactor Internals Acceptance
Criteria Methodology & Data Requirements “ Draft SE received. Working on “A” version of report, which is
scheduled in be completed by the end of 2014.
PWROG MSC participated in the March 2014 Joint Industry Discussion with the NRC and the EPRI MRP on Doel-3 Reactor Vessel Results.
PWROG MSC participated in the March 2014 Joint Industry Discussion with the NRC and the EPRI MRP on Clevis Bolt Questions.
P R E S S U R I Z E D W A T E R R E A C T O R O W N E R S G R O U P 5
Annual Materials Programs Executive Information Exchange Meeting June 2014
PWROG MSC/NRC Interactions • NRC Interactions:
Pre-Submittal Meeting held on June 16 discuss an update to the PWROG Topical Report pertaining to the Master Integrated Reactor Vessel Surveillance Program (MIRVP) for B&W Fabricated Reactor Vessels (PA-MSC-1182).
Meeting to discuss the methodology that is being developed for performing a functionality analysis for the Lower Support Columns. Tentatively to be scheduled for the Fall 2014 (PA-MSC-1103).
Technical meeting to discuss RV Integrity Issues • Present PWROG approach and initial findings under project PA-
MSC-1091 “Demonstrate Appendix G Margins for PWR RPV Nozzles.”
• Discuss the other RV integrity issues as committed in PA-MSC-0554, “Proactively Drive Changes in Reactor Vessel Embrittlement Regulations” Task 1 such as BTP 5-3, RG1.99 revision, and Appendix H.
• Both tentatively to be scheduled for the Fall 2014.
P R E S S U R I Z E D W A T E R R E A C T O R O W N E R S G R O U P 6
Annual Materials Programs Executive Information Exchange Meeting June 2014
PWROG MSC Areas of Coordination & Strategic Planning with MRP
• Reactor Vessel Integrity
Subsidizing the host utilities for the PSSP program. Participating in ASTM E10.02 to develop consensus ETC.
• Reactor Internals
Coordinating with EPRI MRP on MRP-227 LAI/RAI Responses. NRC meetings held in November 2012, January 2013 and March 2014.
Supporting utilities in plant-specific Applicability Determinations, including MRP-191, Fluence, and Cold Worked Stainless.
• Stainless Steel Degradation/BMIs/BMNs Working with the EPRI MRP on the development of I&E guidance
for ID and OD initiated SCC of PWR SS pressure boundary components.
Coordination of industry activities relative to BMIs/BMNs.
P R E S S U R I Z E D W A T E R R E A C T O R O W N E R S G R O U P 7
Annual Materials Programs Executive Information Exchange Meeting June 2014
PWROG MSC Focus Areas for 2014-2015
• PA-MSC-0688 - Westinghouse Upper Internals Guide Tube Card Wear – Fleet-wide Operational Projections Guidance of guide card inspections finalized recommendations endorsed per the
NEI 03-08 recommendations. Six needed elements. EPRI MRP incorporated into MRP-227-A via interim guidance.
• Work to Support MRP-227-A - Reactor Internals PA-MSC-1122 - Reactor Vessel Internals Industry Coordination PA-MSC-1103 - Functionality Analysis: Westinghouse Lower Support Columns PA-MSC-0983 - Support for Applicant Action Items 1, 2, and 7 from the Final
Safety Evaluation on MRP-227, Revision 0 (Working on plant specific requests) PA-MSC-0942 - Dynamic Response Model of Westinghouse Internals PA-MSC-0835 – B&W Internals MRP-227 Phase III Functionality & Core Barrel
Assembly Modeling PA-MSC-0784 - Development of Generic Acceptance Criteria for W and CE
Reactor Internals – MRP-227 Primary and Expansion Components (Grouping of primary and expansion components, adding new ones based on MRP-127-A)
PA-MSC-0473 - Reactor Internals Acceptance Criteria Methodology & Data Requirements (working to complete A-version of report)
P R E S S U R I Z E D W A T E R R E A C T O R O W N E R S G R O U P 8
PA-MSC-1103R0 – “Functionality Analysis: Westinghouse Lower Support Columns”
– The purpose of the program is as follows: Develop a methodology which will form the basis for generic or, if needed,
plant-specific analyses. Complete first steps in substantiating the qualitative safety argument.
– This program is designed to: Potentially eliminate the need for plant-specific evaluations,
Provides a level of confidence that performing a more detailed functionality analysis, if required, will be successful and
Demonstrates to the NRC that the licensees are working to make progress towards a final resolution of the embrittlement issue for lower support columns.
Annual Materials Programs Executive Information Exchange Meeting June 2014
PWROG MSC Focus Areas for 2014-2015
P R E S S U R I Z E D W A T E R R E A C T O R O W N E R S G R O U P 9
PA-MSC-1091R0 – “Demonstrate Excessive Appendix G Margins for PWR RPV Nozzles”
– The purpose of the program is as follows: Identify the magnitude of the various Appendix G margins related to
assessment of the inlet/outlet nozzles. – This program is designed to:
Develop a consistent and less conservative basis for responding to RAIs,
Demonstrate continuous and ongoing compliance with Appendix G,
Minimize, and potentially eliminate, future RAIs on this topic,
Reduce plant costs in updating P-T curves and
Perform generic bounding evaluations.
Annual Materials Programs Executive Information Exchange Meeting June 2014
PWROG MSC Focus Areas for 2014-2015
P R E S S U R I Z E D W A T E R R E A C T O R O W N E R S G R O U P 10
• PA-MSC-0257 - PWSCC Crack Initiation Testing of Farley Unit 2 Alloy
600 CRDM Penetrations Work to be complete in Summer 2014.
o Provides key chemical mitigation input regarding the beneficial effect of zinc addition to delay primary water stress corrosion cracking in nickel based Alloys (A600/A690) and their associated weld metals (A82/182/52M/152) ,
o Used in PWR primary systems. Program will provide inputs to the extremely low probability of rupture (xLPR) program.
• PA-MSC-0551 - Development of I&E Guidelines for ID and OD-
Initiated SCC of PWR SS Pressure Boundary Components The program has three phases:
o Phase 1: Establishing screening criteria (COMPLETE) o Phase 2: Consequences evaluation (IN PROCESS) o Phase 3: Develop I&E guidelines (PLANNED)
Annual Materials Programs Executive Information Exchange Meeting June 2014
PWROG MSC Focus Areas for 2014-2015
P R E S S U R I Z E D W A T E R R E A C T O R O W N E R S G R O U P
Questions?
The Materials Committee is established to provide a forum for the identification and resolution of materials issues including their development, modification and implementation to enhance the
safe, efficient operation of PWR plants.
11
Global Expertise • One Voice www.pwrog.com
Joe Donahue, Duke Energy Chairman, NDE Action Plan Committee
Steve Swilley, EPRI Director, NDE
Robin Dyle, EPRI Technical Executive
Industry / NRC Management Meeting
June 25, 2014
NDE Program
2 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Cross-cutting issues: Actions to address human performance issues • Research directions
– Proficiency maintenance – Technology
• Implementation of post-North Anna guidance – Proceeding well – INPO role
• Vendor engagement – Vendor outreach – Vendor engagement in NDE Program advisory process
3 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Regulatory interface
• Successes – Interaction on PDI bolting issue – Remote VT collaboration – Modeling and simulation collaboration
• Recent improvements – Annual NDE focus meeting – Quarterly calls; maintaining action item list – Project review meeting with RES
• Challenges – Improve communications as to NRC comments – Structure projects in anticipation of supporting regulatory interface
4 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Effects of improving inspections due to continuous learning • We may continue to find flaws that were missed before • Coordinating with licensees
– Help licensees deal with these situations – Got slightly out of step with PG&E on the DCPP OE
• RCE cited areas for improvement • NDE IC sent out an NDE Alert memo addressing the procedure technical items
• Other items were already being addressed, or are being addressed now, through the research program
Together…Shaping the Future of Electricity
Mike Gallagher, Exelon
Chairman, EPRI LTO Advisory Committee Sherry Bernhoft, EPRI
Program Manager, LTO Annual Materials Update to NRC Management
June 25,2014
EPRI Long Term Operations Program
2 © 2014 Electric Power Research Institute, Inc. All rights reserved.
EPRI LTO Program Goals and Objectives • Technical basis for safe, reliable
plant operation through extended lifetime
• Useful results in 2014 to 2019 timeframe
• Demonstrated technologies to support long-term plant management
• Research projects integrated with other EPRI programs
• External collaboration (DOE, NRC Research, EDF, Owners Groups )
Expect first SLR submittals in
2018
3 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Basis for Implementation of Aging Management • R&D to understand aging
degradation – Mechanism and failure modes – Initiation and growth rates – Inspection and Evaluation GLs
• Inspection methods
– Detection and measurement – Non destructive examination and
qualification
• Mitigation strategies – Chemistry – Stress relieving techniques – Weld overlays
• Condition Monitoring – On-line monitoring – In-field detection
• Prediction of Remaining Useful Life
– Health Monitoring software and algorithms
• Repair & Replacement Decisions – Life Cycle Management GLs – Advanced welding for irradiated
materials – Integrated Life Cycle Management
(ILCM)
4 © 2014 Electric Power Research Institute, Inc. All rights reserved.
EPRI LTO R&D Focus Areas • Aging Management
– Primary system metals, welds and piping – Reactor pressure vessel – Steam Generators – Electrical cables – Concrete and containment structures – Buried piping – Coatings – Flow Accelerated Corrosion (FAC)
• Opportunities for Modernization – Advanced Instrumentation & Controls – Advanced risks and PRA – Advanced welding for irradiated materials – Non-destructive testing methodologies (NDE)
• Enabling technologies – Pilot plant projects and demonstrations – Integrated Life Cycle Management
5 © 2014 Electric Power Research Institute, Inc. All rights reserved.
EPRI R&D Projects – Cross Referenced to GALL, Rev 2
• EPRI Report 3002000576 “Assessment of R&D Supporting Aging Management Programs for Long-Term Operations”
• Report cross-references the EPRI R&D Projects to the AMPs
• Three categories of AMPs – On-going long-term R&D – Established Programs – One-time plant specific
inspections
Examples: • On-going long-term R&D (8)
– Effects of irradiation – Thermal effects – Reactor Pressure Vessel
embrittlement • Established Programs (20)
– Chemistry – Steam Generator Inspections – FAC
• Plant Specific (22) – Fuel oil – Fire Protection System
6 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Material Category 1 AMP
GALL AMP ID AMP Name Potential LTO Impact on AMP XI.M9 BWR Vessel Internals Irradiation and environmental effects on material
performance
XI.M11B Cracking of Nickel-Alloy Components and Loss of Material Due to Boric Acid-Induced Corrosion in Reactor Coolant Pressure Boundary Components
Environmental effects on material performance
XI.M12 Thermal Aging Embrittlement of Cast Austenitic Stainless Steel (CASS)
Thermal aging and possible irradiation effects on material performance
XI.M16A PWR Vessel Internals Irradiation and environmental effects on material
XI.M31 Reactor Vessel Surveillance Neutron fluence on reactor pressure vessel materials
7 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Summary of Category 1 Materials AMPs
• The existing AMPs are effective and in use to detect and management aging effects
• R&D is managed by the EPRI Materials Programs – NEI 03-08 – Continuous improvements – Updated based on inspection results, operating
experience and R&D • Continuous improvements will
– Improved modeling of degradation – Improved inspection technologies – Advances in assessment and evaluation methodology – On-line condition monitoring
8 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Summary
• There maybe some plant specific issues but no show stoppers to-date
• Program will need to be dynamic to respond to changing R&D needs when the first US plant applies for SLR
Together…Shaping the Future of Electricity