Material Acceptance Requirements for Battery Energy Storage Systems Alan Price, PE Director, Office of Technical Certification and Research NYC Department of Buildings

Transcript of Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit....

Page 1: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

Material Acceptance Requirements for Battery Energy Storage Systems

Alan Price, PE

Director, Office of Technical Certification and Research

NYC Department of Buildings

Page 2: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 2

Why Material Acceptance

Project

Approval • Construction document approval

Materials are used as prescribed in the

code.

• Permit

• Signoff

Material

Acceptance

• Separate process

required for

alternative

materials.

• Process evaluates

performance and

safety.

Page 3: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 3

Battery Energy Storage Systems

• What is a Battery Energy Storage System? – A battery energy storage system (battery ESS) stores

energy through an electrochemical process for later use to supply the utility or local grids.

– Other energy storage systems (ie flywheels) are not addressed under current evaluations.

– Doesn’t include Emergency power systems, UPS

• Uses for Battery ESS’s – Uses include peak shaving applications, storage with

renewable energy systems, etc.

Page 4: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 4

Material Acceptance Timeline

Plan

Exam Permitting Construction Maintenance

Approval of

Construction

Documents

Permit

Issued

Project

Signoff

Submit OTCR2,

Checklist items,

schedule site

visit.

Obtain OTCR

Conditional Acceptance

Install, inspect & certify

per OTCR CAL

Obtain OTCR Final

Acceptance Letter

Document

submission

Page 5: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 5

FDNY Coordination OTCR Site-specific review for Li-Ion, Lead Acid, Flow batteries

FDNY Review

OTCR Site-

specific Review

Material

Acceptance

Page 6: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 6

Sustainability Board Review OTCR Site-specific review for new chemistries

FDNY Review

OTCR Site-

specific Review

Material

Acceptance

Sustainability

Board

Page 7: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 7

Construction Document Submission

Plan

Exam Permitting Construction Maintenance

Approval of

Construction

Documents

Permit

Issued

Project

Signoff

Submit OTCR2,

Checklist items,

schedule site

visit.

Obtain OTCR

Conditional Acceptance

Install, inspect & certify

per OTCR CAL

Obtain OTCR Final

Acceptance Letter

Document

submission

Page 8: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 8

Construction Document Submission

• PW1 filing / File separate application for BESS and ancillary work

Page 9: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 9

Construction Document Submission

• Submitted under full plan examination (do not file for professional certification)

• Zoning analysis is required for outdoor installations. Outdoor installations include rooftop locations.

• Establish discretionary Required Item for Final Acceptance.

Page 10: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 10

OTCR Submission Requirements

Plan

Exam Permitting Construction Maintenance

Approval of

Construction

Documents

Permit

Issued

Project

Signoff

Submit OTCR2,

Checklist items,

schedule site

visit.

Obtain OTCR

Conditional Acceptance

Install, inspect & certify

per OTCR CAL

Obtain OTCR Final

Acceptance Letter

Document

submission

Page 11: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 11

OTCR Submittal Requirements

• OTCR2 Application (DOB Website)

• Checklist submittal, including: – Listing certification (UL 1973, UL 9540 / UL 1741)

– Large scale testing (UL 9540A)

– Code Analysis (Ventilation, room separation, fire suppression, etc)

– Risk Analysis (address hazard mitigation)

– System monitoring

– Signage

Page 12: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 12

Conditional Acceptance Details

Plan

Exam Permitting Construction Maintenance

Approval of

Construction

Documents

Permit

Issued

Project

Signoff

Submit OTCR2,

Checklist items,

schedule site

visit.

Obtain OTCR

Conditional Acceptance

Install, inspect & certify

per OTCR CAL

Obtain OTCR Final

Acceptance Letter

Document

submission

Page 13: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 13

Conditional Acceptance

• Grants permission to install

• Establishes requirements:

– Installation

– Inspection

– Certification of installation

Page 14: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 14

Final OTCR Acceptance

Plan

Exam Permitting Construction Maintenance

Approval of

Construction

Documents

Permit

Issued

Project

Signoff

Submit OTCR2,

Checklist items,

schedule site

visit.

Obtain OTCR

Conditional Acceptance

Install, inspect & certify

per OTCR CAL

Obtain OTCR Final

Acceptance Letter

Document

submission

Page 15: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 15

Final Acceptance

• Certification is required prior to final acceptance

– (NYS registered design professional certifies compliance with Conditional Acceptance Letter)

• Final Acceptance is required prior to project signoff

Page 16: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 16

Buildings Bulletin 2019-002

Page 17: Material Acceptance Requirements for Battery Energy ... · Checklist items, schedule site visit. Obtain OTCR Conditional Acceptance Install, inspect & certify per OTCR CAL Obtain

build safe | live safe 17

OTCR Contact Info

Office of Technical Certification and Research (OTCR)

280 Broadway, 7th Floor

New York, NY 10007

Attn: Alan Price, Director, OTCR

[email protected]