Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success...
Transcript of Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success...
![Page 1: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/1.jpg)
1 of 204
Feroze R. Vazifdar, S.E.Vice PresidentLiftech Consultants Inc.www.liftech.net
Masterclass on Crane Procurement, Modernization, and MaintenanceTOC Asia 2003
C. Davis RudolfDirector, Engineering & MaintenanceVirginia International Terminals
![Page 2: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/2.jpg)
2 of 204
Masterclass TopicsSection One: Crane Procurement
Section Two: Crane Modernization
Section Three: Crane Useful Life Assessment and Maintenance
![Page 3: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/3.jpg)
3 of 204
Section One:Crane Procurement
![Page 4: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/4.jpg)
4 of 204
Crane Procurement OverviewEvolution of quay crane industry
Demands and restraints
Crane procurement strategies
Options
Case study—tailor made
Mechanical and electrical system choices
AC vs. DC motors and drives
Standard or specialty cranes
Conclusions
![Page 5: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/5.jpg)
5 of 204
Evolution of Container Crane Industry
Paceco 1960
Pioneer
Good quality
Standard features
![Page 6: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/6.jpg)
6 of 204
Evolution
Europeans (Early 1960’s)
Japanese (Late 1960’s)
Repeated with:
Koreans (1970’s)
Others
Chinese (1990’s)
Significant impact in tailor-made procurement
![Page 7: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/7.jpg)
7 of 204
Current Environment
Chinese success
Highly competitive pricing
Cost-cutting measures
![Page 8: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/8.jpg)
8 of 204
Cost-Cutting Measures
Sub-contract fabrication
Remote fabrication
Standardize components
Reduced profits
APL Los Angeles cranesNoell, Abu Dhabi
![Page 9: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/9.jpg)
9 of 204
Crane Procurement OverviewEvolution of quay crane industry
Demands and restraints
Crane procurement strategies
Options
Case study—tailor made
Mechanical and electrical system choices
AC vs. DC motors and drives
Standard or specialty cranes
Conclusions
![Page 10: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/10.jpg)
10 of 204
Terminal Demands and RestraintsTerminal demands
Geometry and restraints
Planning for the future
Source: JWD Group
![Page 11: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/11.jpg)
11 of 204
Crane Geometry vs. Ship Size
Typical values
Pana
max
AP
L C
9
Post
Pa
nam
ax
C10
Reg
ina
M
aers
k
New
M
aers
k St
anda
rd
Suez
-max
Mal
acca
-m
ax
C ontainers across deck 13 16 17 22 23 24
Ship Draft, m 11.6 12.5 13.7 15.2 17.1 21.0
Ship Beam, m 32.0 39.3 41.8 54.3 50.3 54.9
O utreach, m 35.8 45.7 51.6 64.2 66.7 69.2
Setback, m 4.3 4.3 7.6 7.6 7.6 7.6
Gage, m 15.24 30.48 30.48 30.48 30.48 30.48
Backreach, m 9.1 15.2 15.2 15.2 15.2 15.2
Wheels per C orner/ spacing
8 / 1.5
O ut-to -O ut distance between bumpers, m
27.0
C apacity, LT 30 40 50 60 65 65
![Page 12: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/12.jpg)
12 of 204
ClearanceDiagram
![Page 13: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/13.jpg)
13 of 204
Leg/Rail Setback
![Page 14: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/14.jpg)
14 of 204
Future Planning
![Page 15: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/15.jpg)
15 of 204
Tacoma Crane Concept
60’ Gage
100’ Gage
Before Extension
After Extension
![Page 16: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/16.jpg)
16 of 204
Crane Procurement OverviewEvolution of quay crane industry
Demands and restraints
Crane procurement strategies
Options
Case study—tailor made
Mechanical and electrical system choices
AC vs. DC motors and drives
Standard or specialty cranes
Conclusions
![Page 17: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/17.jpg)
17 of 204
Crane Procurement Strategies
Manufacturer selection:
Off-the-shelf
Tailor-made
HybridQuality Price
![Page 18: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/18.jpg)
18 of 204
Off-the-Shelf
Visit operating cranes—2 to 3 vendors
Get input from Operations and Maintenance personnel
Obtain manufacturer specifications
Understand procurement process and quality monitoring effort
![Page 19: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/19.jpg)
19 of 204
Off-the-Shelf Procurement Process
Issue specification outline
Solicit terms
Confirm manufacturer specifications
Negotiate
Implement monitoring effort
![Page 20: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/20.jpg)
20 of 204
Off-the-Shelf Specification Outline
Geometry and capacity requirements
Stability against storm winds
Quay capacity
Power supply
Electrical vendors
Specific features and components
Key Points
![Page 21: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/21.jpg)
21 of 204
Off-the-Shelf Limitations
Suitable for private industryCan use different standardsNot limited to low bidderCan negotiate
May not be suitable for public agencies
![Page 22: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/22.jpg)
22 of 204
Off-the-Shelf Case Study
Public financing of private industry
Small – medium size
Limited monitoring effort
Red Hook Terminal, NY
![Page 23: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/23.jpg)
23 of 204
Tailor-made
Detailed specifications
Confirm technical proposals
Consider bid alternates
Implement quality monitoring program
![Page 24: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/24.jpg)
24 of 204
Specifications & StandardsStandard specifications cover standard cranes, not container cranes
Container cranes are unique for many reasons
Eccentric loads
High speeds
Heavy duty cycles
Very high reliability requirements
Standards and specifications must be interpreted by experienced engineers
![Page 25: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/25.jpg)
25 of 204
Detailed Performance Specifications
Start with detailed baseline specifications
Identify specific components
Identify specific needs
![Page 26: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/26.jpg)
26 of 204
Consider Bid AlternatesRequire bid for specified crane
Alternate bids for vendor specifications
Bidders note exceptions
State reasons for exceptions
Only use proven designs
![Page 27: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/27.jpg)
27 of 204
Confirm Technical Proposals
Specifications compliance
Evaluate standards
![Page 28: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/28.jpg)
28 of 204
Evaluate Commercial Proposals
Capital costs
Lifetime costs
Monitoring costs
![Page 29: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/29.jpg)
29 of 204
Quality Monitoring
Verify designs
Verify manufacturing quality
On-site inspection
Verify commissioning
Punch list
![Page 30: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/30.jpg)
30 of 204
Monitoring CostsDepend on:
Manufacturer location
Manufacturer quality control
Typical monitoring costs:
2.5 – 5.0%Tailor-made
0.5 - 1.5%Off-the-shelf
(as % of price of a two-crane order)
Extent of sub-contracting
Existing relationships:
Purchaser – Manufacturer
Manufacturer – Fabricator
Fabricator – Erector
![Page 31: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/31.jpg)
31 of 204
Crane Procurement OverviewEvolution of quay crane industry
Demands and restraints
Crane procurement strategies
Options
Case study—tailor made
Mechanical and electrical system choices
AC vs. DC motors and drives
Standard or specialty cranes
Conclusions
![Page 32: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/32.jpg)
32 of 204
OptionsProductivity enhancements
Capacity
Trolley type
32.5 LT 32.5 LT
![Page 33: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/33.jpg)
33 of 204
Trolley Types
Rope trolley (RTT)
Continuous support
Catenary trolleys
Self-driven option
Machinery on trolley (MOT)
Rope-towed option
![Page 34: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/34.jpg)
34 of 204
Catenary trolleys Continuous support
RTT
![Page 35: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/35.jpg)
35 of 204
MOT
Plan View
WS
Elevation View WS
![Page 36: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/36.jpg)
36 of 204
Trolley Type Comparison MatrixFleet Thru
Rope Towed Continuous
Fleet Thru Rope Towed Cat. Trolleys
Fleet Thru Self Powered
Machinery On Trolley
Rope Towed Machinery On Trolley
Trolley Weight Moderate Lowest Moderate Highest High
Trolley Motors 1 1 2-4 2-4 1
Trolley Motor Power Moderate Moderate Moderate Highest High
Trolley Acceleration High High Lowest(Wheel Slip)
Moderate (Wheel Slip)
High
Trolley Tow Ropes, Tensioner, Sheaves
Yes Yes No No Yes
Catenary Tow Rope, Tensioner, Sheaves
No Yes No No No
Hoist Rope Length Long Long Medium Short Medium
![Page 37: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/37.jpg)
37 of 204
MOT vs. RTT
Rope Tro lley Machinery Tro lley
Tro lley weight (tons) 25 90
Moving load (tons): Tro lley + Spreader + HB + 65 LT
110
175
Moving load (tons): fo r Fatigue Damage
80 145
Fatigue damage 1.0 6.0
C rane weight (tons) 1,300 1,600
Crane structural fatigue damage & weight comparison
![Page 38: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/38.jpg)
38 of 204
Trolley Trends
Majority: RTT
Increasingly: MOT
APL, Maersk, Modern Terminals
Europe, Hong Kong, Malaysia, PSA
![Page 39: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/39.jpg)
39 of 204
Crane Procurement OverviewEvolution of quay crane industry
Demands and restraints
Crane procurement strategies
Options
Case study—tailor made
Mechanical and electrical system choices
AC vs. DC motors and drives
Standard or specialty cranes
Conclusions
![Page 40: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/40.jpg)
![Page 41: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/41.jpg)
Ground Rules for CranesGround Rules for Cranes
3 crane order
Beyond post-Panamax capability• 21 containers wide on deck
• 7 high deck load
High speed• Capable of 35+ containers per hour
![Page 42: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/42.jpg)
Procurement ProcessProcurement Process
Competitive negotiation (RFP vice IFB)• Not locked in to low price
New ideas• Use a modified performance spec
• Setting a minimum performance standard in CPH
• Let each bidder determine characteristics to attain
CPH through simulation program
![Page 43: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/43.jpg)
What Type of Crane ?What Type of Crane ?
Single hoist
Dual hoist elevating platform
Elevating girder
![Page 44: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/44.jpg)
Contract OptionsContract Options
3 Single Hoist Cranes
2 Single Hoist Cranes
1 Elevating Girder Crane
![Page 45: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/45.jpg)
Technical SpecificationTechnical Specification Section 1
• Proposal• Schedule• Standards
Basic characteristics and features• Capacity 50 LT• Rail gage 30 M• Lift height 37 m• Outreach 22 Containers
Misc. structural, mechanical, electrical Disk containing simulation program
![Page 46: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/46.jpg)
Crane DynamicsCrane Dynamics
•Simulation program includes•physical characteristics•dwells•ship/container configuration•minimum CPH
•speeds
•accelerations motor sizes
![Page 47: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/47.jpg)
Initial Proposal ResultsInitial Proposal Results
13 bidders Option A 6 bidders Option B Only 3 of 13 supplied complete info Option A bids
• Average price for per SHC $6.4M
Option B bids• Average price for ETGC $7.6M • Average differential for ETGC about $2.0M
![Page 48: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/48.jpg)
Evaluation CriteriaEvaluation Criteria
Experience 25
Quality & Suitability 25
Delivery 15
Price 30
Training/Support 5
Total 100
![Page 49: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/49.jpg)
Experience PointsExperience Points
0
5
10
15
20
25
0 10 20 30 40 50 60 70 80
Poin
ts
Number of Cranes
![Page 50: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/50.jpg)
Points for Delivery Points for Delivery
Based on total # of months for 1st, 2nd,
and 3rd cranes
15 points for fastest deliverer
Others in ratio of (fastest : other) x 15.0
![Page 51: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/51.jpg)
Points for PricePoints for Price
30 points to lowest bidder
Others in ratio of (lowest : other) x
15.0
![Page 52: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/52.jpg)
Points SummaryPoints Summary
0102030405060708090
100
A B C D E F G H I J K L M
![Page 53: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/53.jpg)
Negotiation ProcessNegotiation Process
Chose 3 bidders with the highest point totals.
Bidders were provided a detailed (guideline) specification for negotiation of technical details.
Negotiation based on exceptions to detailed spec.
![Page 54: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/54.jpg)
North NIT ZPMC CranesNorth NIT ZPMC Cranes
![Page 55: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/55.jpg)
Did our new ideas work ?Did our new ideas work ?
![Page 56: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/56.jpg)
Modified Performance Spec ?Modified Performance Spec ?
Yes.
Acted as a screen to let suppliers tell us what they intended to provide.
Guideline spec deviations allowed us to define specifics.
![Page 57: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/57.jpg)
CPH Performance Standard ?CPH Performance Standard ?
Yes.
Allowed suppliers to see if their recent drive designs would meet our performance standard.
![Page 58: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/58.jpg)
![Page 59: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/59.jpg)
or
![Page 60: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/60.jpg)
Trolley TypesTrolley Types
1. Fleet Thru – Rope Towed – Catenary Support Trolleys
2. Fleet Thru – Rope Towed – Continuous Catenary Support
3. Fleet Thru – Self Powered
4. Machinery On Trolley
5. Rope Towed Machinery On Trolley
![Page 61: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/61.jpg)
RTT - Fleet Thru with Catenary TrolleysRTT - Fleet Thru with Catenary Trolleys
Catenary trolleys necessary for long spans Provides intermediate festoon support Additional sheaves, reeving, tensioners, and
trolley machinery
![Page 62: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/62.jpg)
RTT - Fleet Thru with Continuous Support
RTT - Fleet Thru with Continuous Support
No catenary trolleysSmaller catenaries = more controlMore sheaves = heavier trolley & larger trolley motor
![Page 63: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/63.jpg)
Fleet Thru Self Powered Fleet Thru Self Powered
Simple reeving No trolley tow ropes or tensioner Possibility of wheel slip Slower acceleration rates
![Page 64: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/64.jpg)
MOT Machinery on TrolleyMOT Machinery on Trolley
Least amount of reeving
Heaviest trolley
Possibility of wheel slip
Slower acceleration rates
Small machinery room
Design for maintenanceaccess is important
![Page 65: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/65.jpg)
Rope Towed MOTRope Towed MOT
Simple reeving
No concern of wheel slip
Full acceleration rates
Requires trolley tow ropes and tensioner
Reduced hoist rope length
![Page 66: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/66.jpg)
Why Consider MOT Crane?Why Consider MOT Crane?
Potential for maintenance expense reduction.
Potential for increased reliability.
Industry trends.
Consider another design prior to wharf design.
![Page 67: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/67.jpg)
MOT
RTT
FestoonFestoon
![Page 68: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/68.jpg)
Boom Design
MOT Monogirder
Boom
RTT Twin-girder
Boom
![Page 69: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/69.jpg)
Trolley WeightTrolley Weight
RRRTTTTTT
MMMOOOTTT
1188 ttoonnss 8822 ttoonnss
![Page 70: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/70.jpg)
Crane WeightCrane Weight
RRRTTTTTT
MMMOOOTTT
11227700 ttoonnss 11660000 ttoonnss
![Page 71: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/71.jpg)
Wheel Loads(operating)
Wheel Loads(operating)
RRRTTTTTT
MMMOOOTTT
WWWaaattteeerrrsssiiidddeee 176 kips/wheel
200 kips/wheel
LLLaaannndddsssiiidddeee 96 kips/wheel 133
kips/wheel
![Page 72: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/72.jpg)
Mechanical SystemsMechanical Systems
RRRTTTTTT
MMMOOOTTT
Total rope length
11,900 ft
1600 ft
# of sheaves 50
4
![Page 73: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/73.jpg)
Maintenance ComparisonMaintenance Comparison
RRRTTTTTT
MMMOOOTTT
MMMaaaiiinnnttteeennnaaannnccceee tttiiimmmeee pppeeerrr cccrrraaannneee pppeeerrr yyyeeeaaarrr
156.5hrs 87.2 hrs
MMMaaaiiinnn hhhoooiiisssttt rrrooopppeee llliiifffeee
1500 hrs 3000+ hrs
HHHoooiiisssttt rrrooopppeee rrreeeppplllaaaccceeemmmeeennnttt cccooosssttt
$21,000 $5,700
![Page 74: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/74.jpg)
Operator Feedback of MOTOperator Feedback of MOT
Trolley speed about the same but acceleration slower than RTT.
Not as responsive. Spreader skew stability
about the same.Tendency for trolley to drift
when coming off stick.
Prefers RTT.
![Page 75: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/75.jpg)
![Page 76: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/76.jpg)
DC Drive TopologyAC Power Line
To Motors
• AC Power Input, DC Power Output• Individual Drives Connected to AC
Power Line• SCR Bridges Provide Power and
Regeneration
AC Circuit Breaker
SCRs
Fuses
![Page 77: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/77.jpg)
Source
AC QC Drive TopologyDC Bus
Inverters
Fuses
ChargeControl
To Motors
AC Power Line
AC Circuit Breaker
Converter IGBTBridge
Stored Energy Capacitors
DC Link Fuses
DC Disconnect
Inverter IGBT Bridge
![Page 78: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/78.jpg)
DC Drives• Speed Dependent• Average 0.55 Lag
IGBT Source• Always Near Unity• Average ~ 0.99 Lag
KVAR
KWcos() = pf
KVA
Power Factor
+
+
Advantage : AC
![Page 79: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/79.jpg)
DC Drives• Poor Power Factor Causes Line Dips• Line Dips can Prevent Regeneration
and Cause Malfunction
IGBT Source• DC Bus Capacitance Stores Energy• Robust to Line Dips, Swells, and
Momentary Power Loss
+
+
Power System Transients
GE Toshiba Automation Systems
Advantage : AC
![Page 80: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/80.jpg)
Size and WeightSize and Weight
DC requires only a single stage power conversion
• Smaller cabinet size
AC motor sized to have sufficient stall torque at lower speeds
• Larger motor for similar characteristics
DC motor has lower rotor inertia• More compact
AC more overall weight
Advantage : DC
![Page 81: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/81.jpg)
MaintenanceMaintenance DC Brush life depends on:
• Commutator temperature• Brush material• Vibration• Humidity• Corrosives in air• Can see up to 8000 hours service
AC Motors• No brush /commutator maintenance• Better sealed for marine environment
for AC motors• No carbon dust to contaminate
bearings
Advantage : AC
![Page 82: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/82.jpg)
PerformancePerformance Performance
• Torque & Speed Control very similar with DC digital encoder feedback and AC vector control.
• DC has wider constant torque range Motion.
• Switching times may increase for or increased cost.
• Operating AC motor at rated torque at under half speed could overheat motor.
Accuracy• Similar level of speed regulation-
approx 0.01%.
Zero speed load holding without brake
• DC - No Drive Limitations• AC - Drive can have Low
Frequency limitations
Advantage : Slightly DC
![Page 83: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/83.jpg)
CostCostIGBTs and control electronics cost
higher for AC.DC motor cost higher.Regeneration cost higher for AC.Separate armature and field control
preferable for shared drives.2<HP<100 AC more economical.
• Premium for AC vector control In high HP applications.
Advantage : DC
![Page 84: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/84.jpg)
Other FactorsOther Factors
Experience of maintenance staff Commonality of existing equipment
Bottom Line:
• Neither type of drive is inferior
• Technology is moving AC along faster than DC
• VIT experience - continue DC procurements
![Page 85: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/85.jpg)
![Page 86: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/86.jpg)
Choices of Specialty Cranes:
Dual Hoist Stationary Platform Dual Elevating Platform Elevating Trolley Girder Others not yet designed or built
![Page 87: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/87.jpg)
PSA Singapore
ECTRotterdam
Dual Hoist CranesDual Hoist Cranes
![Page 88: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/88.jpg)
SeagirtBaltimore
Tokyo
Dual Hoist CranesDual Hoist Cranes
![Page 89: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/89.jpg)
HHLAHamburg
Dual Hoist cranesDual Hoist cranes
![Page 90: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/90.jpg)
Elevating Platform
VIT Norfolk
Dual Hoist CranesDual Hoist Cranes
![Page 91: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/91.jpg)
Elevating Trolley Girder CraneElevating Trolley Girder Crane
![Page 92: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/92.jpg)
Paceco Supertainer©Paceco Supertainer©
![Page 93: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/93.jpg)
CreaTech Technotainer©CreaTech Technotainer©
![Page 94: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/94.jpg)
Delft University Carrier CraneDelft University Carrier Crane
![Page 95: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/95.jpg)
Liftech SuperCrane©Liftech SuperCrane©
![Page 96: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/96.jpg)
ProductivityProductivity
A major factor in making the “bottom line.”Definition is illusive depending on
where measured, how measured, and criteria used.“Apples to Apples” comparison of
port productivity is rare.
![Page 97: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/97.jpg)
Predicting Crane ProductivityPredicting Crane Productivity
* Liftech Consultants
Simulation Screen*
![Page 98: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/98.jpg)
Monitoring an OperationMonitoring an Operation
![Page 99: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/99.jpg)
Data AccumulationData Accumulation
Dual hoist and single hoist15,000 records - 16 fields per record
• Event start and end• Event type - load/discharge/delay• Crane #• Operator• Stevedore• Ship type• Delay type...
![Page 100: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/100.jpg)
DHC vs. SHC Productivity Comparison
DHC vs. SHC Productivity Comparison
3rd Generation• Single hoist crane• Straddle carrier operation• 50 ft rail gage
4th Generation• Dual hoist crane• Chassis / bomb-cart
operation• 50 ft rail gage
5th Generation• Single hoist crane• Straddle carrier operation• 100 ft rail gage
![Page 101: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/101.jpg)
DHC Cycle Time Frequency DistributionDHC Cycle Time Frequency Distribution
0
200
400
600
800
1000
1200
1400
20 180 40
90.0 60 60.0
8045.0
10036.0
12030.0
14025.7
16022.5
18020.0
200 18.0
22016.4
24015.0
26013.8
28012.9
Handling Rate
Cycle TimeCPH
Mode 45 CPH
Mean 32 CPH
![Page 102: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/102.jpg)
0
200
400
600
800
1000
1200
1400
20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290
Cycle Time [sec]
5th Generation Crane44.2 Containers/hr
3rd generation Crane40.2 Containers/hr
SHC Cycle Time Frequency DistributionSHC Cycle Time Frequency Distribution
![Page 103: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/103.jpg)
DHC Theoretical vs. ActualDHC Theoretical vs. Actual
Productivity Mode 45.0 CPH
Actual Productivity 32.0 CPH
+ Delays 6.4 CPH+ Operator Proficiency 3.0 CPH+ Ship Stowage 3.6 CPH
![Page 104: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/104.jpg)
Productivity Measurement Comparison
Productivity Measurement Comparison
0
10
20
30
40
50
3rd Gen SHC 4th Gen DHC 5th Gen SHC
Simulation Measured Mode Measured Mean
![Page 105: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/105.jpg)
![Page 106: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/106.jpg)
Dual Hoist Cranes ExperienceDual Hoist Cranes Experience
High capital outlay
Expensive to maintain
Most require an extra operator
Productivity gains marginal
![Page 107: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/107.jpg)
? Is it possible to have:? Is it possible to have:
One operator
Higher productivity
Operator closer to work• Less than 40 m for smaller ships
Small premium for specialty crane
Simpler maintenance than a DHC
![Page 108: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/108.jpg)
Initial IdeasInitial Ideas
![Page 109: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/109.jpg)
Patent Issued
VIT’s ETGC Concept
![Page 110: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/110.jpg)
NIT North Cranes by ZPMCNIT North Cranes by ZPMC
![Page 111: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/111.jpg)
New Suez ClassNew Suez Class
• 140 meters clear under spreader• 63.5 m outreach - 26 wide• 90 m/min loaded hoist speed• 244 m/min trolley speed
![Page 112: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/112.jpg)
ZPMC/Liftech DesignZPMC/Liftech Design
![Page 113: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/113.jpg)
ZPMC/Liftech DesignZPMC/Liftech Design
![Page 114: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/114.jpg)
Girder PositioningGirder Positioning
Infinite locations within lifting range not feasible
VIT’s experience pointed to: 5 discrete positions - preset prior to
vessel arrivalElevating speed of ½ m/min
Simulation shows increases over standard of 2 – 8 CPH depending on ship and level
![Page 115: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/115.jpg)
Lifting MechanismLifting Mechanism
Geared mechanicalHydraulicElectro-mechanical
winch
Possibilities
![Page 116: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/116.jpg)
Elevating MachineryElevating Machinery
![Page 117: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/117.jpg)
Guide Rollers
Trolley Girder Support Beam
LegLeg
Hydraulic Cylinder
Guide rollers
![Page 118: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/118.jpg)
Pin
Alignment Bushing
Actuating Cylinder
Stop Plate
Lock and Holding Pin MechanismLock and Holding Pin Mechanism
![Page 119: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/119.jpg)
Construction Schedule
Start fabrication March 2003
Testing in plant Oct 2003-Jun 2004
Off-loading in VA Oct 2004
Commissioning Nov 2004
![Page 120: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/120.jpg)
Productivity Influence SummaryProductivity Influence Summary
Specialty Crane 3-5 CPHDelays 3-5 CPHOperator Proficiency 3-5 CPHType of Operation 3-5 CPH Ship Stowage 3-7 CPH
![Page 121: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/121.jpg)
Estimated Initial CostEstimated Initial Cost
0123456789
10
SHC ETGC DHCFixed
DHCElevating
![Page 122: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/122.jpg)
Estimated Cost SummaryEstimated Cost Summary
Annualized Initial Cost 20 years at 8%
Operating Labor Cost @ $45 per hour
Maintenance Cost Labor and Parts
Energy Cost @ $0.10/KWHR
Total Annual Cost 3000 hrs per year
Cost per Container based on 3000 HRS at 70% of Mode
SHC 5th Gen 636$ 270$ 92$ 30$ 1,028$ 11.13$ ETDC 754$ 270$ 120$ 40$ 1,184$ 11.51$ DHC Fixed 835$ 337$ 180$ 61$ 1,413$ 14.32$ DHC Elevating 967$ 390$ 194$ 67$ 1,618$ 16.05$
Note: Numbers in 000’s except last column
![Page 123: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/123.jpg)
Bottom LineBottom Line
Just the procurement of a specialty crane does not necessarily guarantee large leaps in productivity. Several factors having weights of the same order of magnitude influence ship operation productivity.
![Page 124: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/124.jpg)
124 of 204
Crane Procurement OverviewEvolution of quay crane industry
Demands and restraints
Crane procurement strategies
Options
Case study—tailor made
Mechanical and electrical system choices
AC vs. DC motors and drives
Standard or specialty cranes
Conclusions
![Page 125: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/125.jpg)
125 of 204
Conclusions
Highly competitive market
Better and cheaper cranes
Can use off-the-shelf or tailor-made
Requires quality monitoring
More diligence by purchaser
Trend: Tailor-made
Section One: Crane Procurement
![Page 126: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/126.jpg)
126 of 204
Section One:Crane Procurement
End, Section One … Scheduled Coffee Break
![Page 127: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/127.jpg)
127 of 204
Section Two:Crane Modernization
![Page 128: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/128.jpg)
128 of 204
Crane Modernization Overview
Used vs. new cranes
Modification options
Relocation
Costs
Awarding the job
Conclusions
![Page 129: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/129.jpg)
129 of 204
Crane ModernizationWhy modernize?
Major changes in the shipping industryCompetition for new tenantsResponse to economic climateRelocation within countries and across continents
Modernization vs. newLower cost and shorter delivery durationObsolescence—more myth than reality
![Page 130: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/130.jpg)
130 of 204
Used vs. New Cranes
Vintage 1965 to 1985 1996 to present
Capacity 30 to 40 LT 50 to 65 LT (twin lift)
Rail gage, m 10-30.5 15.2-36.5
Outreach, m 29-38 53-69
Backreach, m 8-24 9-16
Clearance between legs, m
12-14 16-19
Lift height 18-27 32-37
Hoist speed, m/min 22-53 60-90
Trolley speed m/min 120-150 240
Manufacturers: Hitachi, IHI, Kocks, Kone, Krupp, Liebherr, Mitsubishi,
MES, Morris, Noell, Paceco, Star, ZPMC
Background data
![Page 131: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/131.jpg)
131 of 204
Crane Modernization Overview
Used vs. new cranes
Modification options
Relocation
Costs
Awarding the job
Conclusions
![Page 132: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/132.jpg)
132 of 204
Modification Options
Geometry changes
Performance changes
Operational changes
Retrofits
![Page 133: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/133.jpg)
133 of 204
Geometry Changes
Increase lift height
Increase outreach
Rail gage change
Miscellaneous changes
![Page 134: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/134.jpg)
134 of 204
Modification Options
Increasing lift height
Geometry Changes
![Page 135: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/135.jpg)
135 of 204
Modification Options
Increasing lift height
Geometry Changes
![Page 136: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/136.jpg)
136 of 204
Modification Options
Increased lift height and gage change
Geometry Changes
![Page 137: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/137.jpg)
137 of 204
Modification Options
Increased outreach
Geometry Changes
Boom insert/addition
![Page 138: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/138.jpg)
138 of 204
Modification Options
Increasing outreach
Geometry Changes
![Page 139: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/139.jpg)
139 of 204
Modification Options
Rail gage changes
Geometry Changes
![Page 140: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/140.jpg)
140 of 204
Modification Options
Increase backreach
Increase portal beam height
Increase clearance between legs
Decrease overall gantry out-to-out
Misc. Geometry Changes
![Page 141: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/141.jpg)
141 of 204
Other Modification Options
Performance Changes
Operational Changes
Electric Drive Retrofit
Typical Retrofit
![Page 142: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/142.jpg)
142 of 204
Crane Modernization Overview
Used vs. new cranes
Modification options
Relocation
Costs
Awarding the job
Conclusions
![Page 143: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/143.jpg)
143 of 204
Relocation
Seattle to Panama Intra-harbor, Buenos Aires
![Page 144: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/144.jpg)
144 of 204
Crane Modernization Overview
Used vs. new cranes
Modification options
Relocation
Costs
Awarding the job
Conclusions
![Page 145: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/145.jpg)
145 of 204
2001 Cost Guidelines
Modification Dimensions USA/EuropeCost ($1,000s)
AsiaCost ($1,000s)
Increase lift height 6 m 750 500
Increase outreach 2 m 4 m 6 m 9 m
100200650750
75150500600
Increase backreach 4-5 m 150 100
Increase portal height 1-2 m 100 75
Widening leg clearance 0.3 m 1 m
35300
35250
Decrease gantry out-to-out 250 200
Geometry Changes
![Page 146: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/146.jpg)
146 of 204
2001 Cost Guidelines
Modification USA/EuropeCost ($1,000s)
Asia Cost ($1,000s)
Increase rated capacity (25% increase) 250 175
Increase main hoist speed, replace drives with digital, replace controls
1,200 700 to 900
Upgrade gantry braking 120 60
Install snag protection 120 120 to 250
Performance Changes
![Page 147: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/147.jpg)
147 of 204
2001 Cost Guidelines
Modification USA/EuropeCost ($1,000s)
Asia Cost ($1,000s)
Convert shore power to diesel power 350 280
Convert diesel power to shore power 180 90
Install man-lift 180 100
Replace operator’s cab 60 40 to 50
Operational Changes
![Page 148: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/148.jpg)
148 of 204
2001 Cost Guidelines
Modification USA/EuropeCost ($1,000s)
Asia Cost ($1,000s)
Change rail span 350 250 to 350
Relocate two cranes 5 km 1000 km5000 km
2005001000
150350 to 400700 to 800
Relocation
![Page 149: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/149.jpg)
149 of 204
Crane Modernization Overview
Used vs. new cranes
Modification options
Relocation
Costs
Awarding the job
Conclusions
![Page 150: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/150.jpg)
150 of 204
Awarding the Job
AdvantagesDetailed performance specs not requiredMay save time, since no bidding requiredManufacturer has all drawings and design expertise
DisadvantagesCrane manufacturer may not be interestedNot equipped for major on-site workMay not own jacking equipmentCost may be high
1. Original crane manufacturer
![Page 151: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/151.jpg)
151 of 204
Awarding the Job
Design/build contract through negotiation or bidding
Pre-qualification and selection based on experience
Contractor assumes product liability
Substantial engineering by contractor
Requires knowledgeable crane designers
May cause contractor to leave large contingency in price
2. Turnkey project with contractor
![Page 152: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/152.jpg)
152 of 204
Awarding the Job
All contractors bid on same package
Owner helped through bidding and construction review by engineer
Costs typically lower
3. Retain crane design professionals
![Page 153: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/153.jpg)
153 of 204
Conclusions
Used vs. new cranes
Modification options
Relocation
Costs
Awarding the job
Section Two: Crane Modernization
![Page 154: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/154.jpg)
154 of 204
Section Two:Crane Modernization
End, Section Two … Scheduled Break
![Page 155: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/155.jpg)
155 of 204
Section Three:Crane Useful Life Assessment and Maintenance
![Page 156: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/156.jpg)
156 of 204
Owner’s Options
Predicting Life
Extending Life
Case Study
Useful Structural Life AssessmentOverview
![Page 157: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/157.jpg)
157 of 204
Useful Structural Life
Definition—Duration for operating the crane with a tolerable risk of fatigue failure
Unrelated to corrosion and mechanical/ electrical failure or obsolescence
Structural maintenance programs extend useful life
![Page 158: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/158.jpg)
158 of 204
Useful Structural Life Depends On
Initial structural design
Load and cycle spectra
Structural details
Manufacturing quality
Operations history
Structural maintenance
![Page 159: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/159.jpg)
159 of 204
You Have an Older Crane–What are Your Options?
Do nothing—ignore risks
Useful structural life assessment
Prolong life with inspection and repair
Reduce use and/or relocate
Dispose
![Page 160: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/160.jpg)
160 of 204
Structural Deterioration
Corrosion
Fatigue crack growth
Overload / damage / abuse
![Page 161: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/161.jpg)
161 of 204
Fatigue phenomenon
Fatigue evaluation
Useful life analysis
Predicting Useful Structural Life
![Page 162: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/162.jpg)
162 of 204
Fatigue Crack Growth
Stress range
Number of cycles
Detailing
Workmanship andquality control
Crack
Crack growth
Cleavage fracture rather than slip lines.
![Page 163: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/163.jpg)
163 of 204
Number of Cracks Accelerates with Use
Number of Cycles
Num
ber
of C
rack
s
![Page 164: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/164.jpg)
164 of 204
Crack Occurrencesand Maintenance
Number of C ycles
Num
ber
of C
rack
s
Original CraneWithout Repair
Inspect andRepair(Typical)
"Design Life"
Envelope ofNew CrackFrequency
• Poor initial details repaired
• More attention during repair
• Threshold stress range
![Page 165: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/165.jpg)
165 of 204
Steps of a Useful Life Analysis
Structural condition survey
Useful life estimate before inspection
Inspection program and structural inspection
Useful life estimate after inspection
![Page 166: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/166.jpg)
166 of 204
Risk of Failure
Current design criteria
1 in 50
Adding structural maintenance program
1 in 1,000
![Page 167: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/167.jpg)
167 of 204
Extending Life
Determine if economic to continue to operate crane
Repair and refurbish crane
Plan for future inspections and repairs
![Page 168: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/168.jpg)
168 of 204
Crane Maintenance
General
Structural
Mechanical & Electrical Considerations
![Page 169: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/169.jpg)
169 of 204
Crane Availability Estimates*Breakdown repair time
Aggressive target: 0.5%
Minimum target: 2%
Preventive maintenance and periodic inspection timeTypically 16 to 30 hrs per wk
Depends on crane age and usage
Routine servicing timeTypically 4 to 8 hrs per wk
Availability
*Based on typical 2,000-3,000 hrs operation per year
![Page 170: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/170.jpg)
170 of 204
Preventive Maintenance Includes
Weekly pre-operational checks to verify
Operations of all motions
Limit switch settings
Wire rope and spreader adjustments
![Page 171: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/171.jpg)
171 of 204
Wire rope
Brake adjustment and testing
Limit switches
Spreaders
Periodic Frequent Maintenance
![Page 172: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/172.jpg)
172 of 204
Availability*
.int.
.int.
.int.
72001.
72001.
72001
maprev
Breakdown
maprevBreakdown
serviceroutinemaprevBreakdown
HrsHrsAvailBreakdown
HrsHrsAvaillOperationa
HrsHrsHrstyAvailabiliTotal
*Based on a typical 300-day work year = 7200 hrs/yr
![Page 173: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/173.jpg)
173 of 204
Replacement and Spare Parts
Inventory
Availability in case of emergency
Interchangeability
Components available in country
![Page 174: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/174.jpg)
174 of 204
Crane Maintenance
General
Structural
Mechanical & Electrical Considerations
![Page 175: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/175.jpg)
175 of 204
Structural Maintenance & Inspection ProgramInspection manuals
Details to be inspected
Classification: FCM or NFCM
Detail location identification
Inspection method: VT, MT, UT, RT
Inspector’s qualifications
Reporting procedures
Repair procedures
Improving details
Inspection frequencies
![Page 176: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/176.jpg)
176 of 204
Inspection Program:Typical General Arrangement
Joint16DHJoint16DL
Joint5BJ
![Page 177: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/177.jpg)
177 of 204
Inspection Program:Typical NDT Manual Pages
16DH 16DL
![Page 178: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/178.jpg)
178 of 204
Inspection Program:Typical NDT Manual Pages
2AJ 5BJ
![Page 179: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/179.jpg)
179 of 204
All Cracks Need to be Repaired
Cracks occur at:
Poorly designed details
Poorly fabricated details
Corrosion-related damage
Important to not only repair crack, but also to improve the detail
Engineering judgment is required
![Page 180: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/180.jpg)
180 of 204
Unstable Fatigue Crack
![Page 181: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/181.jpg)
181 of 204
Reinforcing Plates
![Page 182: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/182.jpg)
182 of 204
Rejuvenation
If cracks are repaired:
Detail at repaired crack becomes rejuvenated
Repaired joint is at least as good as new
![Page 183: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/183.jpg)
183 of 204
Inspection Frequency
Not all joints need inspection at the same interval:
More frequent inspection:
Fracture critical members (FCMs)
Joints with higher stress ranges
Less frequent inspection:
Non-fracture critical members (NFCMs)
Joints with lower stress ranges
Joints in secondary members
More bang for your buck
![Page 184: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/184.jpg)
184 of 204
Example Inspection Intervals
Component Fracture Critical?
No. of Moves Interval(Years)
Tro lley G irder Hanger
Yes 300,000 3
Forestay Yes 600,000 6
Lower Legs No 1,200,000 12
Portal Beam No 2,400,000 24
![Page 185: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/185.jpg)
185 of 204
Case Study: Eight Quayside Cranes
1972 Paceco
2.6 Million Lifts
1985 Hitachi
1.5 Million Lifts
1976 IHI
2.2 Million Lifts
Three Manufacturers
![Page 186: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/186.jpg)
186 of 204
Purpose of Study
Establish a structural maintenance program
Inspection manual
Repair procedures
Structural inspection intervals
Estimate remaining useful life
Recommendations to improve remaining useful life
![Page 187: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/187.jpg)
187 of 204
Results
Number of Cracks Crane Estimate Before NDT
Inspection Detected by NDT Inspection
Paceco 33 to 38 7 to 13 IHI 3 to 8 2 to 11 Hitachi 0 to 1 2 to 3
![Page 188: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/188.jpg)
188 of 204
Results
Useful Life Estimate (Number of Years) Crane Before
NDT Inspection
After NDT Inspection
After Cracks Repaired
Paceco 0 to 1 6 to 11 11 to 16 IHI 8 to 13 6 to 18 10 to 17 Hitachi 15 to 17 8 to 11 13 to 16
![Page 189: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/189.jpg)
189 of 204
Conclusions toCase Study
Findings compared well with the initial estimates
Useful life extended with inspection and repair
Helped client decide what to do
![Page 190: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/190.jpg)
190 of 204
Maintenance Overview
General
Structural
Mechanical & Electrical Considerations
![Page 191: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/191.jpg)
![Page 192: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/192.jpg)
Sway ControlSway Control
Hydraulic• Requires spreader to trolley fleet angle• Adds to hydraulics maintenance load• Reasonably effective
Electronic• Most manufacturers include it in drive• Operators perceive that they can do better• Requires little or no maintenance
Operator• Most effective for controlled periods• Affected by fatigue• No maintenance
![Page 193: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/193.jpg)
Snag DeviceSnag Device Hydraulic
• Most effective• Usually combined with spreader micro-motions• Complex but requires minimal maintenance
Crushable Element• Simple concept• Easy to maintain• Expensive and marginally effective due to
preliminary crushing
![Page 194: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/194.jpg)
Hydraulic Snag DeviceHydraulic Snag Device
![Page 195: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/195.jpg)
Spreader Trim, List, and SkewSpreader Trim, List, and Skew
![Page 196: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/196.jpg)
Spreader Cable Reel or Cable Tub?Spreader Cable Reel or Cable Tub?
• Speeds of recent cranes too high for tub
• Gravity cable installed as back-up with reduced speed
• Problems have been with shock absorber more than drive
![Page 197: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/197.jpg)
Festoon Festoon
Problems with standard festoon:
• Controlling shock from bumping saddles
• Whipping of cables in wind
• Maintenance of wheels
• Increasing size with machinery on trolley cranes
![Page 198: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/198.jpg)
CPS / SMGContactless Power Supply/ Slotted Microwave Guide
CPS / SMGContactless Power Supply/ Slotted Microwave Guide
Electrodes
Slotted Microwave Guide
Pick-up Coils on Trolley
![Page 199: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/199.jpg)
Energy Chain SystemEnergy Chain System
• Simple, easy to maintain
• Impervious to wind
• Works in ice and snow
![Page 200: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/200.jpg)
Electronics TroubleshootingElectronics Troubleshooting
![Page 201: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/201.jpg)
Maintenance Operating StationMaintenance Operating Station
• Start Crane
• E-Stop
• Boom up/down
• Spreader extend retract
• Motions in slowdown• Gantry• Hoist• Trolley
![Page 202: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/202.jpg)
202 of 204
Conclusions
Useful Structural Life Assessment
Maintenance
Section Three: Crane Useful Life Assessment and Maintenance
![Page 203: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/203.jpg)
203 of 204
Masterclass Conclusions
Section One: Crane Procurement
Section Two: Crane Modernization
Section Three: Crane Useful Life Assessment and Maintenance
![Page 204: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/204.jpg)
204 of 204
Feroze R. Vazifdar, S.E.Vice PresidentLiftech Consultants Inc.www.liftech.net
C. Davis RudolfDirector, Engineering & MaintenanceVirginia International Terminals
Thank You
Masterclass on Crane Procurement, Modernization, and Maintenance
TOC Asia 2003
![Page 205: Masterclass on Crane Procurement, Modernization, and … · 2016. 10. 10. · Chinese success Highly competitive ... Cost-cutting measures. 8 of 204 Cost-Cutting Measures Sub-contract](https://reader031.fdocuments.us/reader031/viewer/2022011921/6038525c367c7e028440b763/html5/thumbnails/205.jpg)
Copyright 2003 by Liftech Consultants Inc. All rights reserved.This material may not be duplicated without the written consent of Liftech Consultants Inc., except in the form of excerpts or quotations for the purposes of review.
The information included in this presentation may not be altered, copied, or used for any other project without written authorization from Liftech Consultants Inc. Anyone making use of the information assumes all liability arising from such use. g