Master Sched
description
Transcript of Master Sched
Activity
ID
Activity
Description
LocationOrig
Dur
QTY LOCN PROJ RESP Early
Start
Early
Finish
722 S.MAIN
EN1368 Demo of 722 S. Main - Project on Hold 14-151337 VISCOMI 01JUL15 29AUG15
738 S.MAIN
EN1288 Demo of 738 S. Main -Project on Hold 14-151335 VISCOMI 01JUL15 29AUG15
A-2 Building
EN1498 Cadaver lab renovations - 15-157743 HUDICK 15JUN15 08AUG15
Bio Science
EN1528 Specimen room -in design -for summer 2015 15-2059-00 HUDICK 26MAY15 03JUL15
Alumnae Hall
EN1298 Replace roof & Soffett 14-138164 THAYER 11MAY15 31JUL15
Anthony-Seeger Hall
EN1318 Upgrade Fire Alarms 14-146234 HUDICK 26MAY15 31JUL15
EN1338 Renovations 15-2000-18 J.COMBS 26MAY15 07AUG15
Burruss Hall
EN1248 Fire Alarm Panel change out HUDICK 20JUL15 08AUG15
Carrier Library
EN1268 Starbucks refresh Awaiting drawings 15-2067-00 SHANTZ 01JUN15 08AUG15
CARRIER DR
EN090 Raised crosswalks Carrier Drive 14-2000-33 DERROW 26MAY15 15AUG15
CHAMPION
EN310 Structural Issues- 15-2065-00 THAYER 11MAY15 06AUG15
EN320 Speed Bunps 15-2055-00 THAYER 11MAY15 18JUL15
Chandler Hall
EN998 Re-grout all brick joints (Shops) 15-2043-00 THAYER 26MAY15 10JUL15
EN1918 Lakeside express renovations 15-2069-00 DERROW 01JUN15 01AUG15
EN1008 Replace carpet in 8 rooms 14-149303 VISCOMI 15JUN15 26JUN15
Chappelear Hall
EN1728 Replace Ceiling 15-2037-0 J.COMBS 12MAY15 18JUL15
EN1788 room 100 build wall in all wings 15-2047-00 DERROW 12MAY15 11JUL15
Convocation Center
EN237 refinish floor SHANTZ 27JUL15 01AUG15
Dingledine Hall
EN1818 room 100 build wall in all wings 15-2047-00 DERROW 12MAY15 22AUG15
Weeks
Demo of 722 S. Main - Project on Hold
Demo of 738 S. Main -Project on Hold
Cadaver lab renovations -
Specimen room -in design -for summer 2015
Replace roof & Soffett
Upgrade Fire Alarms
Renovations
Fire Alarm Panel change out
Starbucks refresh Awaiting drawings
Raised crosswalks Carrier Drive
Structural Issues-
Speed Bunps
Re-grout all brick joints (Shops)
Lakeside express renovations
Replace carpet in 8 rooms
Replace Ceiling
room 100 build wall in all wings
refinish floor
room 100 build wall in all wings
© Primavera Systems, Inc.
Start Date 05JAN15
Finish Date
Data Date 05JAN15
Run Date 22JUN15 13:15
Early Bar
Float Bar
Progress Bar
Critical Activity
PLAN
JMU - Facilities Management
JMU FM Master Project Schedule
Classic Schedule Layout
Sheet 1 of 4
Date Revision Checked Approved
Sheet 2 of 4
Activity
ID
Activity
Description
LocationOrig
Dur
QTY LOCN PROJ RESP Early
Start
Early
Finish
E & G
EN198 On going side walk repairs as needed 09-2003-00 THAYER 16DEC13 06SEP14
EN238 Mis small asbestos projects as needed 14-2002-00 VISCOMI 01JAN14 29DEC14
Eagle Hall
EN728 Replace all vanitieis 15-2060-00 DERROW 11MAY15 22JUN15
EN688 Replace Roof 15-2018-00 THAYER 15JUN15 11JUL15
FARM
EN1678 Renovations to JMU Farm 15-2000-13 HUDICK 11MAY15 08AUG15
Festival
EN220 Canopy at Board of Visitors entrance 15-156039 THAYER 11MAY15 18JUL15
Forbes Center
EN200 Covered walkway 14-128603 THAYER 11MAY15 01AUG15
EN230 Paint booth 14-137529 HUDICK 11MAY15 31JUL15
Frederikson Hall
EN1798 room 100 build wall in all wings DERROW 11MAY15 05JUN15
Godwin Hall
EN1638 Repair Pool 15-258-00 SHANTZ 11MAY15 18JUL15
EN1698 repairs to Volleyball court SHANTZ 11MAY15 29MAY15
GR ROW
EN1118 Water intrusion project SHANTZ 11MAY15 11JUL15
EN1108 Floor Tile Lake A, SHANTZ 12MAY15 18JUL15
Grace Street Student Housing
EN888 Grace Street Student Housing 13-2008-04 SHORT 06MAY13 01JUL15
Hanson Hall
EN1808 room 100 build wall in all wings 15-2047-00 DERROW 12MAY15 18JUL15
Hillside Hall
EN1418 Replace floor Tile 15-2046-00 VISCOMI 12MAY15 11JUL15
EN1478 Total Paint JENKINS 12MAY15 31JUL15
EN1488 Replace boiler & Coils 15-2046-00 VISCOMI 12MAY15 01AUG15
Huffman Hall
EN1738 Replace ceiling 15-2037-00 J.COMBS 12MAY15 18JUL15
Ikenberry Hall
EN1748 Install Hand Dryers 15-2036-00 J.COMBS 12MAY15 11JUL15
Johnston Hall
EN1648 Repair water intrusion into basement 14-146200 THAYER 18MAY15 10JUL15
LAKEVIEW
EN1658 Renovations to Lakeview 14-143592 J.COMBS 03NOV14 13JUN15
Memorial Hall
EN1168 Repair roof 14-146204 THAYER 26MAY15 30JUN15
EN1178 Cover stages at amphtheater BAKER 22JUN15 26JUN15
Weeks
On going side walk repairs as needed
Mis small asbestos projects as needed
Replace all vanitieis
Replace Roof
Renovations to JMU Farm
Canopy at Board of Visitors entrance
Covered walkway
Paint booth
room 100 build wall in all wings
Repair Pool
repairs to Volleyball court
Water intrusion project
Floor Tile Lake A,
Grace Street Student Housing
room 100 build wall in all wings
Replace floor Tile
Total Paint
Replace boiler & Coils
Replace ceiling
Install Hand Dryers
Repair water intrusion into basement
Renovations to Lakeview
Repair roof
Cover stages at amphtheater
Sheet 2 of 4
Sheet 3 of 4
Activity
ID
Activity
Description
LocationOrig
Dur
QTY LOCN PROJ RESP Early
Start
Early
Finish
EN1278 refinish Gym floor 15-158786 SHANTZ 25JUN15 03JUL15
Music Building
EN698 Replace roof 1272 THAYER 26MAY15 30JUN15
NORTH CAMP
EN898 Steam line connection - NANCY C 17NOV14 15AUG15
Rockingham Hall
EN1878 Rockingham parking lot 15-2008-06 THAYER 11MAY15 15AUG15
EN1888 Rockingham demo 15-2061-00 VISCOMI 11MAY15 13JUN15
Rose Library
EN1958 room 2300 renovate 15-2062-00 SHANTZ 26MAY15 30JUN15
Spotswood Hall
EN1708 Replace fire Alarms 15-2019-00 HUDICK 11MAY15 25JUL15
EN1948 Upgrade steam radiators HART 11MAY15 25JUL15
EN1778 Install wi-fi J.COMBS 12MAY15 31JUL15
EN1688 replace windows- 14-2049-00 THAYER 01JUN15 17JUL15
Taylor Hall
EN908 Auntie Annes 15-2068-00 HUDICK 26MAY15 02AUG15
University Farm
EN1668 Renovations to Farm 14-153283 HUDICK 04MAY15 01OCT15
University Recreation Center
EN868 UREC Expansion -phase I -in planning 12-2081-00 G.WAY 05MAY14 16JUL16
EN918 Dock Lift 15-161324 SHANTZ 11MAY15 05JUN15
EN928 3rd Floor Lift 14-137164 SHANTZ 11MAY15 05JUN15
EN938 Office renovations 15-2026-00 J.COMBS 11MAY15 20JUN15
Village Halls
EN1458 Village Quad rooms 14-2047-00 DERROW 11MAY15 01AUG15
EN1468 renovate 4 HD appts 15-2049-00 HUDICK 11MAY15 18JUL15
Walnut Lane
EN1378 New Student Housing 216-17949 R.MILLER 16DEC13 04AUG15
Wampler Hall
EN1408 Network Install TELECOM 11MAY15 05JUN15
Warren Hall
EN1238 Post office/bank Renovations 15-2001-02 J.COMBS 15JAN15 15AUG15
Weaver Hall
EN1438 Replace ceiling 15-2035-00 VISCOMI 11MAY15 03JUL15
EN1828 room 100 build wall in all wings 15-2047-00 DERROW 12MAY15 24JUL15
White Hall
EN1428 C302/C303 Bathroom ceiling 14-144880 VISCOMI 07MAR15 14MAR15
EN1928 Network Install 15-158866 J.COMBS 11MAY15 08AUG15
EN1758 Install Hand Dryers 15-2036-00 J.COMBS 12MAY15 18JUL15
Weeks
refinish Gym floor
Replace roof
Steam line connection -
Rockingham parking lot
Rockingham demo
room 2300 renovate
Replace fire Alarms
Upgrade steam radiators
Install wi-fi
replace windows-
Auntie Annes
Renovations to Farm
UREC Expansion -phase I -in planning
Dock Lift
3rd Floor Lift
Office renovations
Village Quad rooms
renovate 4 HD appts
New Student Housing
Network Install
Post office/bank Renovations
Replace ceiling
room 100 build wall in all wings
C302/C303 Bathroom ceiling
Network Install
Install Hand Dryers
Sheet 3 of 4
Sheet 4 of 4
Activity
ID
Activity
Description
LocationOrig
Dur
QTY LOCN PROJ RESP Early
Start
Early
Finish
Wine-Price Hall
EN1388 Install carpet in basement BAKER 08JUL15 09JUL15
Weeks
Install carpet in basement
Sheet 4 of 4