MASTER FACILITY PLANNING COMMITTEE
MIDLAND INDEPENDENT SCHOOL DISTRICT
JULY 22, 2019 RECOMMENDATION TO THE BOARD
![Page 2: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/2.jpg)
SUMMARY
▪ The Committee recommends a $569,000,000 facilities bond election be called for November 2019.
▪ This was difficult. That is why we spent 18 months and had a multi-month gap in the middle.
▪ This recommendation is not filled with “wants”. It is needs based.
▪ This is what it costs when you experience a high level of student growth and don’t build a new high
school for 60 years or a new junior high for 30 years.
▪ We recommend MISD continue to fully utilize all existing secondary buildings – no building retirements.
▪ The Committee is in Consensus.
▪ This recommendation is not a referendum for or against MISD. The community needs additional seats in
order to educate our children. It is as simple as that.
▪ Having said that, these seats will allow MISD to continue its momentum in implementing a System of Great
Schools.
▪ This presentation will outline several fiscal considerations that we think will be important to taxpayers.
▪ As will be shown, there is somewhat of a perfect storm – to the positive – that helps to significantly
mitigate taxpayer impact of the proposed bond.
Page 1
![Page 3: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/3.jpg)
COMMITTEE PURPOSE AND COMPOSITION
Page 2
![Page 4: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/4.jpg)
COMMITTEE PURPOSE
The Midland School Facility Planning Committee was tasked withresearching and developing a District-Wide Facilities Master Plan thatwould meet the following goals:
Provide Capacity for 10 Year Projected Student
Enrollment Growth
Support the District’s Educational Improvement
Efforts
Develop a Recommendation that could be presented to the
Board for its consideration
Page 3
![Page 5: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/5.jpg)
MIDLAND FACILITY PLANNING COMMITTEE
Group of 39 individuals from across the community and within theSchool District were asked to collaboratively study and prioritize thedistrict’s most critical needs and prepare a thoughtfulrecommendation to Trustees.
BY THE COMMUNITY FOR THE COMMUNITY
Page 4
![Page 6: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/6.jpg)
MASTER FACILITY PLANNING COMMITTEE
Brent Hilliard
Brandon Hodges
Paul Hughes
Gary Law
Delia Martinez
John McAfee
Tina Mocksfield
Jose Ortiz
Becky Page
Susan Palmer
Patrick Payton
Laura Roman
Frank Salvato
Luis Sanchez
Michael Sanchez
Ronnie Scott
Austin Booker
Jay Edwards
Kevin Foreman
Wilson Heidelberg
Jill Arthur
Rick Davis
James Fuller
Bryan Murry
Kim Evans
Blake Feldt
Tom Holly
Jeff Horner
Elana Ladd
Orlando Riddick
Community Members (20)
Shelly Haney Diana Hines Stan VanHoozer John Wilks
District Members (5)
District Board /Administrators (14)
Patrick Jones
Elise Kail
James Riggen
Deb Shaw
Melissa Ware
Page 5
![Page 7: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/7.jpg)
COMMITTEE OBJECTIVES
Page 6
![Page 8: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/8.jpg)
FACILITY COMMITTEE OBJECTIVES
▪ Recommend appropriate secondary and Pre-K capacity additions and
upgrades in order to meet anticipated ten-year enrollment growth.
o Primary objective was to address secondary capacity issues.
o Recent legislation presented the opportunity to expand Pre-K availability at
relatively low cost and potentially high benefit.
▪ Address other issues of importance at the secondary school level
including campus security, technology, select capital replacement, and
minor athletic improvements.
▪ Be fiscally responsible.
Page 7
![Page 9: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/9.jpg)
THE PROCESS
Page 8
![Page 10: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/10.jpg)
TIMELINE
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
20192018
Page 9
![Page 11: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/11.jpg)
IMPLEMENTED A PROCESS FOR REACHING CONSENSUS
1. Fully Support: “I like it.”
2. Endorsement with minor concerns: “Basically I like it.”
Enthusiastic Support
3. Agree with Reservation: “I can live with it.”
4. Abstain: ”I have no opinion.”
5. Stand Aside: “I don’t like this, but I don’t want to hold up the group.”
Lukewarm Support
6. Disagreement, but willing to go with majority:
“I want my disagreement noted, but I’ll support the decision.”
7. Disagreement, with request not to be involved in implementation:
“I don’t want to stop anyone else, but I don’t want to be involved moving forward.”
Meager Support
8. Cannot support the proposal
Strong Objection
Page 10
![Page 12: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/12.jpg)
THE COMMITTEE DID A LOT OF HOMEWORK
▪ Historic MISD Membership
▪ Past Demographic Studies (Arnold Oates and DeJong Richter)
▪ Existing Building/Site Capacity (Elementary & Secondary)
▪ Existing MISD Facility Conditions
▪ City Housing/Development Growth
▪ Midland on the Move Data
▪ MISD’s System of Great Schools
▪ MISD’s Grade Configurations
▪ District Program Needs: Academic, Athletic, Fine Arts, CTE
▪ Facility Deferred Maintenance Needs
▪ District Technology Needs
▪ High School Student Forum / Community Forums
▪ Secondary School Safety/Security
▪ Educational Facility Model Review
▪ Existing Campuses Tours (Bunche, Yarbrough, Alamo, Goddard, San Jacinto, Lee Freshman, Coleman, LSHS, MSHS and Rankin H.S.)
▪ Proposed Facility Improvement Cost Review
▪ Tax Impact Analysis
▪ Davis Demographic Study Review
▪ Community Survey Review
▪ MISD Financial/Budget Review
▪ Bond Proposal Development
▪ Consensus Building
Page 11
![Page 13: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/13.jpg)
STUDENT ENROLLMENT PROJECTIONS
20,000
22,000
24,000
26,000
28,000
30,000
32,000
34,000
SY2009
SY2010
SY2011
SY2012
SY2013
SY2014
SY2015
SY2016
SY2017
SY2018
SY2019
SY2020
SY2021
SY2022
SY2023
SY2024
SY2025
SY2026
SY2027
SY2028
MISD - Historical and Projected Enrollment
Historic Committee Demographer
Projected Increase - 2.5% per year
Page 12
![Page 14: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/14.jpg)
FACILITY ASSESSMENT HIGHLIGHTS
Secondary Facilities Require Upgrading
▪ Average Age over 50 years
▪ Roofs Need Replacing
▪ HVAC Upgrades Needed
▪ Landscaping/Turf Needs Upgrade
Secondary Facilities are Overcrowded
▪ 76 Portable Classrooms on Secondary Campuses
Site Constraints
▪ Midland High School Cannot Expand on Current Site
▪ San Jacinto Cannot Expand on Current Site
FACILITY TOURSAlamo Junior High School (1950’s)
Bunche Elementary (2015)
Coleman High School (1992)
Lee Freshman High School (1956)
Lee High School (1961)
Midland High School (1949)
San Jacinto Junior High School (1950’s)
Page 13
![Page 15: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/15.jpg)
• MISD added approximately 1,400 students over the last three years
• Enrollment is projected to increase another 8,600 students over the next 10years, a 33% increase.
• Grades 9-12 are projected to add approximately 3,000 students over thenext 10 years, a 45% increase.
• The Committee recognizes these projections cannot be exact:
• If enrollment is below projections, this plan will provide capacity formore than 10 years.
• If enrollment outpaces projections, the District will have to addresscapacity sooner than 10 years.
ENROLLMENT GROWTH in SECONDARY SCHOOLS
Page 14
![Page 16: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/16.jpg)
• In August 2019, every secondary campus is expected to have morestudents than the facility’s legacy capacity.
• The last new comprehensive high school was built in 1961, 58 years ago.
• The last new junior high school was built in 1993, 26 years ago.
• The average age of district secondary schools is ~50 years old.• This bond will reduce the weighted average age of our secondary
schools to ~ 28 years while also upgrading some of our oldest facilities.
• MISD currently has 76 secondary classrooms in portable buildings.• This number is projected to increase every year
ENROLLMENT GROWTH in SECONDARY SCHOOLS
Page 15
![Page 17: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/17.jpg)
• Currently MISD serves approximately 800 Pre-K students
• The State Legislature approved funding full-day 3- and 4-year-olds
• The community has an additional 1,200 eligible 3- and 4-year-oldsfor fully funded Pre-K education
• The Committee’s Plan provides for capacity for all eligible fullyfunded Pre-K students.
• This is one of the most impactful efforts the community can work onto improve educational outcomes.
ENROLLMENT GROWTH inPRE-K SCHOOLS
Page 16
![Page 18: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/18.jpg)
COMMITTEE RECOMMENDATIONS
Page 17
![Page 19: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/19.jpg)
COMMITTEE RECOMMENDATION
The Midland School Facility Planning Committee recommends to theMISD Board of Trustees to call a bond election in the amount of$569,000,000 on November 5th, 2019.
Page 18
![Page 20: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/20.jpg)
• After examining the facilities and data, we recommend to expand capacityto meet student growth needs by approximately 4,700 seats throughoutthe district:
▪ 9 – 12th 2,200▪ 6 – 8th 1,300▪ Pre-K 1,200▪ TOTAL 4,700
• We also recommend upgrading existing secondary campuses for safety,security, technology and select capital improvements to further extendthe life of the District’s existing secondary campuses.
ENROLLMENT GROWTH
Page 19
![Page 21: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/21.jpg)
We recommend three comprehensive high schools:
• Construct two new Comprehensive High Schools
• 2,400 student capacity each serving grades 9 through 12
• Notionally, one new high school would be located on the east side of Midland and one would be located on the west side of town.
• Renovate and Expand the Existing Lee High School Site:
• 2,400 student capacity serving grades 9 through 12
• Additions/Improvements to Classrooms, Laboratories and Learning Spaces
• Addition of Kitchen and Cafeteria
• Addition of Gymnasiums, Locker Rooms, Fieldhouse, Practice Facilities
Naming of schools outside Committee’s purview (defer naming post-election)
3 COMPREHENSIVE 9th – 12th GRADE CAMPUSES
TOTAL INVESTMENT $440,000,000Page 20
![Page 22: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/22.jpg)
We recommend fully utilizing the Existing Midland High School but re-purposing it into two separate schools on one campus:
• Relocate San Jacinto Junior High to the current MHS campus• Convert it to a comprehensive 6th – 8th grade Middle School• Increase capacity from 850 to 1,140• Consider making it a Fine Arts Middle School Academy (Bowie track)
• Create a New 6th – 12th Grade Specialized Academy• These are not extra seats - the student capacity of this academy is needed to
address overall secondary capacity needs.• Enrollment of approximately 100 students per grade level• May create separate entrance and administration if desired• The Academy provides the community and district flexibility as to its design
(CTE, STEM, Young Men’s Academy, Petroleum Academy or something else).
EXISTING MIDLAND HIGH SCHOOL CAMPUS
TOTAL INVESTMENT $65,000,000Page 21
![Page 23: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/23.jpg)
• We recommend converting the remaining Junior High Schools (Abell, Alamo, and Goddard) intocomprehensive 6th – 8th grade Middle Schools. We further recommend converting the two freshmen schools(Midland Freshman and Lee Freshman) into comprehensive 6th – 8th Middle Schools.• Moving 6th graders onto middle school campuses creates capacity at the existing elementary schools to
expand the Pre-K program. • Pre-K programs are accepted as an important component in improving educational outcomes. This was
most recently demonstrated by the Texas Legislature funding full-day early education programs.• Conversion aligns Midland with state requirements (i.e. 6th grade teachers require specialized certification
as secondary teachers as opposed to elementary certification in grades 1-5). • Interestingly, IDEA and YWLA align their 6th graders in their secondary schools.• This conversion allows more flexibility in course selection at the 6th grade level (e.g. Algebra).
• Converting existing Freshmen schools to Middle Schools:• Means no new Junior High / Middle School buildings will have to be built.• Fully utilizes all existing buildings, an important component of the plan.
MIDDLE SCHOOLS
TOTAL INVESTMENT $0Page 22
![Page 24: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/24.jpg)
We recommend upgrading safety and security at each of the secondary campuses:
• Security Vestibules
• Security Fencing
• Student Pick-up/Drop-off Improvements
• Fire Alarm Upgrades
• Security Cameras and Access Control
SECONDARY SCHOOL SAFETY / SECURITY
TOTAL INVESTMENT $33,000,000
We recommend upgrading technology at each of the secondary campuses:
• Network Infrastructure
• Classroom Technology
• Communication Systems
Page 23
![Page 25: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/25.jpg)
We recommend performing major capital replacements at the secondary campuses to improveoperational efficiency utilizing I&S funds to avoid paying 30% recapture payments to the statefrom the M&O fund:
• Roof Replacements
• Energy Management System Upgrades
• HVAC Improvements
SECONDARY SCHOOL CAPITAL REPLACEMENTS
TOTAL INVESTMENT $16,000,000
We recommend re-purposing the Existing San Jacinto Junior High School Campus into the new Young Women’s Leadership Academy:
• Relocate from Jones Elementary School• Grades 6th through 12th
• Enrollment of 700• This Academy has had tremendous educational success in other Texas communities.
Page 24
![Page 26: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/26.jpg)
We recommend the following athletic and site improvements at the comprehensive middle schools
• Abell/Alamo/Goddard• Practice Track Around Football Field with Lights• Landscape / Site Improvements
• Midland/Lee Freshman• Artificial Turf Practice Field• Practice Track Around Football Field with Lights• Landscape / Site Improvements
• Community/District Benefits• Landscaping Improvements reduce water use and maintenance• Artificial Turf improves student safety• Tracks / Lights enhance community quality of place
These improvements comprise ~2.6% of the proposed bond.
EXISTING JUNIOR HIGH / FRESHMAN CAMPUS ATHLETIC IMPROVEMENTS
TOTAL INVESTMENT $15,000,000Page 25
![Page 27: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/27.jpg)
As a part of the 10-year Facility Master Plan, the Committee recommends that the MISD Board of Trustees call a Bond Election November 5th, 2019 summarized as follows:
• Construct Two New Comprehensive High Schools
• Renovate/Expand Existing Lee High School Site
• Fully Utilize and Re-purpose Existing Midland High School Site
• Fully Utilize and Re-purpose Existing San Jacinto Junior High Site
• Safety and Security Upgrades at Secondary Campuses
• Technology Upgrades at Secondary Campuses
• Select Capital Replacement at Secondary Campuses
• Athletic / Site Improvements at Existing JH/Freshman Campuses
SUMMARY
TOTAL INVESTMENT $569,000,000Page 26
![Page 28: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/28.jpg)
SUMMARY
Item Total
Replace Midland High School (new construction) (2400 student capacity) $171,000,000
New 3rd Comprehensive HS (2400 student capacity) $171,000,000
Upgrade Lee HS for 9th Grade / Upgrade / Refurbish (2400 student capacity) $98,000,000
Re-purpose Existing MHS (Expanded SJ and 6th-12
th Academy) $65,000,000
Convert San Jacinto to YWLA $5,000,000
Schools Safety & Security Upgrades $15,000,000
District-Wide Technology Upgrades for Secondary $18,000,000
Secondary Capital Replacements $11,000,000
Secondary Schools Athletic / Site Upgrades $15,000,000
Total $569,000,000
Newly Constructed Campuses 60% $342,000,000
Upgrade / Refurbishment / Re-purpose / Expand 30% $168,000,000
Security / Technology 6% $33,000,000
Secondary Capital Replacments 2% $11,000,000
Secondary Schools Athletic / Site Upgrades 3% $15,000,000
Total 100% $569,000,000
Midland School Facility Planning Committee Recommendation
Page 27
![Page 29: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/29.jpg)
SUMMARY
Comprehensive 9th - 12th High Schools
Midland East (new construction)
Midland West (new construction)
Midland Central (expanded / refurbished)
Comprehensive 6th - 8th Middle Schools (no new construction)
Abell
Alamo
Goddard
San Jacinto (moved to current MHS site)
SE MS (current MFHS site)
NE MS (current LFHS site)
Schools of Choice / Speciality Schools
Early College High School (9th - 12th, plus 2 years of college)
Coleman High School (9th - 12th)
Young Women's Leadership Academy (6th - 12th)
New Academy at existing MHS site (6th - 12th)
IDEA Public Schools Travis Campus (6th -12th)
IDEA Public Schools Campus #2 (6th -12th)
IDEA Public Schools Campus #3 (6th -12th)
Possible IDEA Public Schools Campus #4 (6th -12th)
Page 28
![Page 30: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/30.jpg)
FISCAL CONSIDERATIONS (Cost and Taxpayer Implications)
Page 29
![Page 31: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/31.jpg)
Fiscal Considerations
Be Fiscally Responsible
• Considerations:
▪ Construction Inflation
▪ Current & Projected Interest Rates
▪ Mineral & Commercial Impacts on Overall Tax Valuations
▪ 2019 Texas Legislature Impacts (HB3)
▪ Impact of Public-Private Partnership
▪ Bond Amortization Period
Page 30
![Page 32: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/32.jpg)
FISCAL CONSIDERATIONS
▪ The impacts of inflation on construction costs can be significant.• For example, if construction inflation averages 5% per year, a $500 million bond today will cost
$638 million in five years.
• If we delay, even moderate inflation costs could cost taxpayers an additional $138 million.
▪ Near record low interest rates can be an important source of taxpayer savings.• Interest rates are forecast to be near record lows over the period the bonds will be issued (i.e.
the next 1-5 years). During this time, the projected interest rates are projected to be ~3% per
year below the average interest rate over the last 60 years.
• If we wait and interest rates return to a historic average, the additional interest costs on a $500
million bond could cost taxpayers an additional $150 million - $240 million (depending on the
bond amortization period).
• Importantly, the cost of a $500 million bond is not the same today as it was in 2005 or 2006 or
2007. Our frame of reference needs to evolve with the cost of interest (and commercial
valuations).
Page 31
![Page 33: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/33.jpg)
FISCAL CONSIDERATIONS
▪ Mineral and commercial valuations are at an all-time record high – this will not
always be the case. • What do these high valuations mean?
• It means that homeowners and small business owners will pay less now for this bond than
they would have before the mineral valuations increased so dramatically and they will pay
less now than they would otherwise pay if we wait until after mineral and commercial
valuations peak and start back down.
• It is difficult to predict when mineral and commercial valuations will peak, but they are at
record levels now so we should consider taking advantage of those valuations.
• Given current valuations, home owners and apartment dwellers will pay less than one half of
the total cost of the property taxes collected for school operations and capital programs.
Page 32
![Page 34: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/34.jpg)
FISCAL CONSIDERATIONS
▪ Recent legislation has given us a significant opportunity to lessen the impact of
a bond on local taxpayers.• The Texas legislature just reduced the school property tax rate by $0.07/$100 valuation
across all school districts in Texas.
• This means that the impact of the proposed bond will be 65% - 95% less to an average
Midland homeowner than it otherwise would have been.
• As we will show, those savings are fairly astounding. These are real savings.
• These savings may not be permanent – we should use them while we have them.
Page 33
![Page 35: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/35.jpg)
FISCAL CONSIDERATIONS
▪ While the Committee was developing its recommendations, a parallel effort in the form of a public-private
partnership was also underway to complement and complete Midland’s overall school facility plan.
• This partnership continues the successful tradition of public-private partnerships implemented by the Hospital
District, the City of Midland, and Midland College.
• It involves Philanthropy, Business, and MISD working together to bring a highly qualified Public Charter
School to Midland-Odessa.
• This Charter School will result in up to 10,000 new seats being built in Midland and Ector County.
• The private side of the partnership (primarily Permian Basin-based foundations along with the PSP)
contributed an extraordinary $55,000,000 in order to make this partnership a reality.
• MISD played an important role in the effort. MISD’s initial in-district partnership school will be the first campus
that goes “live” with instruction beginning in 2020.
• Importantly, it is anticipated this public–private partnership will save Midland taxpayers $150,000,000 -
$180,000,000 - one of the largest public-private partnerships ever completed in the region.
• We feel this partnership was another important piece in the development of the most fiscally responsible plan
possible to address the school facility needs of our community.
Page 34
![Page 36: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/36.jpg)
FISCAL CONSIDERATIONS
▪ Bond Amortization Period Matters
▪ To be clear, the Committee is not recommending a specific bond
amortization period.
▪ Rather, we are recommending the Board give strong consideration to the
major fiscal issues outlined by the Committee and make a conscious,
intentional decision on bond amortization period.
Taxpayer Impact of Bond Current MISD
(including impact of recent Tax Rate 25 Year 20 Year 15 Year
Texas Legislation) ($300,000 House) Amortization Amortization Amortization
$/year $2,744 $10 $40 $96
$/month $229 $1 $3 $8
Annual Homeowner cost vs. 25 year bond $29 $86
Total Interest $425,199,575 $306,000,000 $216,440,388
Interest Savings vs. 25 year bond $112,356,200 $208,759,187
Numbers provided by Hilltop Securities through MISD
Increase for $569,000,000 Bond
Page 35
![Page 37: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/37.jpg)
FISCAL CONSIDERATIONS
Taxpayer Impact of Bond Current MISD
(including impact of recent Tax Rate 25 Year 20 Year 15 Year
Texas Legislation) ($300,000 House) Amortization Amortization Amortization
$/year $2,744 $10 $40 $96
$/month $229 $1 $3 $8
Annual Homeowner cost vs. 25 year bond $29 $86
Total Interest $425,199,575 $306,000,000 $216,440,388
Interest Savings vs. 25 year bond $112,356,200 $208,759,187
Taxpayer Impact of Bond Current MISD
(excluding impact of recent Tax Rate 25 Year 20 Year 15 Year
Texas Legislation) ($300,000 House) Amortization Amortization Amortization
$/year $2,744 $182 $211 $267
$/month $229 $15 $18 $22
Annual Homeowner cost vs. 25 year bond $29 $86
Total Interest $425,199,575 $312,843,375 $216,440,388
Interest Savings vs. 25 year bond $112,356,200 $208,759,187
Numbers provided by Hilltop Securities through MISD
Tax Increase for $569,000,000 Bond
Increase for $569,000,000 Bond
Page 36
![Page 38: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/38.jpg)
CLOSING REMARKS
Page 37
![Page 39: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/39.jpg)
CLOSING REMARKS
▪ By the time construction of the new buildings contemplated under the proposed bond are
completed, it will have been over 60 years since Midland built a new comprehensive high school
and over 30 years since it built a new comprehensive junior high / middle school.
▪ Once approved, it will take another five years to fully implement the attached plan. The longer
we wait, the more seats we may need and the greater the cost will be.
▪ Six decades ago, Midland as a community and through its school leaders positioned Midland
extraordinarily well for its future through their vision, their leadership, and their courage.
▪ In a similar way, MISD, a Committee of Citizens, Philanthropy, Business, and have come
together to develop a thoughtful, coordinated plan based upon needs (not wants) that
incorporates important taxpayer considerations.
Page 38
![Page 40: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/40.jpg)
CLOSING REMARKS
▪ The Committee understands that passing this bond is only one step in many necessary steps to
improving the District’s academic performance.
▪ If this bond is approved, it will in no way relieve MISD of its obligation to improve Midland’s academic
performance from its current levels. If anything it raises the Community’s and the Committee’s
expectations of academic performance.
▪ The Committee recommends the School Board consider establishing a Community Oversight
Committee – possibly including members of the current Facilities Committee – to stay in touch with
project implementation and provide scheduled reports to the community at large of progress and
deviations from the plan.
▪ The Committee appreciates the opportunity to work with the District on such an historic undertaking
and through the consensus process previously described, we submit this proposal to the Board for
its consideration.
Page 39
![Page 41: MASTER FACILITY PLANNING COMMITTEE...SUMMARY The Committee recommends a $569,000,000 facilities bond election be called for November 2019. This was difficult. That is why we spent](https://reader033.fdocuments.us/reader033/viewer/2022042007/5e7075951244ce518d71cb9d/html5/thumbnails/41.jpg)
MASTER FACILITY PLANNING COMMITTEE
MIDLAND INDEPENDENT SCHOOL DISTRICT
JULY 22, 2019 RECOMMENDATION TO THE BOARD