Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

25
Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable March 28, 2003

description

Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable March 28, 2003. EPS. EPS. Customer. Customer. Customer. Customer. Customer. EPS. Customer Facility. Customer Facility. Customer Facility. Customer Facility. - PowerPoint PPT Presentation

Transcript of Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Page 1: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Massachusetts DTEDG Interconnection Collaborative

Collaborative Results

Restructuring RoundtableMarch 28, 2003

Page 2: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

What Is An Interconnect (Nomenclature)?

The interface between Distributed Generation (DG) equipment, (the Facility) and the grid (the area Electrical Power System or EPS)

Load3

EPS

Customer Site

Customer Facility

Customer Facility

Customer Facility

Customer Facility

EPS

DGLoad

2

Point of Common Coupling (PCC)

Load1Customer

CustomerCustomer

CustomerCustomer

EPS EPS

Network

Radial

(generating facility)

(interconnecting facility)

Page 3: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Collaborative Effort Has Resulted in the Creation of Four Processes

Simplified - Radial

Simplified – Network

Expedited – Radial

Standard – Radial or Network

Simplest process Minimal or no costs expected Shortest time

Still reasonably simple Strict limits Modest fees, longer time interval

Standardized process Screens / Supplemental Review technical

approach Moderate fees , longer time interval

Standardized process Similar to current process Essentially based on actual costs Potentially long time interval

Page 4: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Simplified Radial ProcessOne sheet application and approvalOnly three technical screens

Radial distribution systems only Limited to 10kW or less Inverter-based, UL1741 listed

Minimal or no costs expected15 business days max

Customer Submits

Application

Network or Radial

EPS?

Complete Simplified Process

>7.5% of circuit

peak load?

≤10kW Qualified Inverter?Radial Yes

To Network Process

To Supplemental Review

No

Yes

No

To Expedited Screens

Page 5: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Simplified Network ProcessOne sheet application and approvalAdditional technical limits

Spot network only Tighter capacity limit

$100 or $300 fee40 to 100 days max

Spot Network

Area or Grid Network

1

Substation Circuit

2

3

Secondary Bus

Loads

Primary Feeders

Transformer

Network Protector Breaker

Network Protector Fuse

Switch

CustomerCustomer

CustomerCustomer

Customer

NP NPNP

Page 6: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

ExpeditedRadial Process

Standardized applicationFive additional technical screens

If passed, only a review of possible EPSmodifications remains

If not passed, Supplemental Reviewdetermines if application can remain inExpedited or go to Standard process

Fee range from $300 to $3,750,possible EPS upgrades40 or 60 days max

Su

pp

lem

en

tal R

evi

ew

Is Facility Certified?

Company Sends Written Authorization

Pass Starting V

Drop?

Pass Fault

Contrib?

Yes

Yes

No

No

No

Pass Config.

Screen?

Yes

No

Pass Trans.

Stability?

Yes

No

Suppl. Review

Determine Req.?

EPS Modification

Check

Yes

Yes

To Standard ProcessNo

Company makes EPS

Modifications

Customer Installs Facility

Optional Witness Test

(If required)

Page 7: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Basis For ScreensCircuit size versus DG

size

DG contribution to fault

Short circuit interrupting capability limit

Three-wire and four-wire circuit criteria

Nameplate limits

Circuit impact

Fault handling, fuse desensitizing & nuisance trip

Short circuit handling

Proper connection

Single phase imbalance

Page 8: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Standard Review ProcessStandardized applicationInitial review

Initial review Impact study if required Facility study if required

Fee range from $300 to actualcosts (no limit)125 or 150 days max

initial review

Facilities Study if required

Company Sends Written Authorization

Company makes EPS

Modifications

Customer Installs Facility

Optional Witness Test

(If required)

optional scoping meeting

Impact Study if required

Page 9: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Process InReport Customer submits complete application and application fee

1. Is the Point of Common Coupling on a Radial Distribution System?

Go to Figure 2No

2. Is the aggregate generating Facility capacity on the circuit less than 7.5% of circuit annual peak load?

3. Does the facility use a Qualified Inverter with a power rating of 10 kW or less?

Customer opts for Standard Process

Yes

Does the facility pass all the following screens?4. Is the Facility certified?5. Is the Starting Voltage Drop Screen met?6. Is the Fault Current Contribution Screen met?7. Is the Service Configuration Screen met?8. Is the Transient Stability Screen met?

No

PerformSupplemental

ReviewYes

No

No

InitiateStandard

Process initial review

Does Supplemental Review determine requirements?

System Modification Check

Yes

Company provides cost estimate and schedule for Interconnection Study(ies)

Company performs Impact and Facility (if required) Study

Customer accepts

Facility Processed forSimplified Interconnection

Under DG Tariff

Facility Processed forExpedited Interconnection

Under DG Tariff

Facility Processed forStandard Interconnection

Under DG Tariff

Yes

NoYes

Page 10: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Simplified Process For Networks

Is the Point of Common Coupling on a spot network?

Does the facility use a Qualified Inverter? (UL1741)

Yes

Initiate Standard process

System Modification Check

Facility Processed for Simplified Interconnection Under DG Tariff

No

Yes

Is the Facility 10kW or less?

Yes

Is the aggregate generating Facility capacity less than1/15 of Customer’s minimum load?

Yes

No

No

No

Yes

Page 11: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Minimum Technical Requirements Set By

IEEE P1547 – “Draft Standard for Distributed Resources Interconnected with Electric Power Systems”.Underwriters Laboratories Inc. Standard UL 1741, November 1, 2002 “Inverters, Converters and Charge Controllers for Use in Independent Power SystemsIEEE 929-2000, “IEEE Recommended Practice for Utility Interface of Photovoltaic (PV) Systems.”

Page 12: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

IEEE Std P1547 Key ClausesVoltage regulationIntegration with EPS groundingSynchronizationSurge WithstandResponse to EPS abnormal conditionsResponse to EPS faultsEPS reclosing coordinationVoltage detection and limitsFrequency detection and limits

Reconnection to EPSLimitation of FlickerHarmonicsUnintentional islandingDesign testingCommissioning testing

Page 13: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Additional Technical Requirements

For Facilities qualified for Simplified Process Must be “qualified” to UL 1741 Disconnect switch may be required

For Facilities >10kW: Non-export functionality if not allowed to export Disconnect switch or comparable device Possible NPCC criteria

For Facilities with rotating generators Interrupting Device (ID) Synchronizing Device (could be part of ID) Additional protection equipment requirements

For large Facilities Transfer trip? High speed protection Communications channels Reactive capability

(Note: Tariff also covers standby gensets that momentary parallel)

Page 14: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Fee Schedules

Simplified Expedited Standard Simplified Spot Network

Application Fee (covers screens)

0 $3/kW,minimum $300,

maximum $2,500

$3/kW,minimum $300,

maximum $2,500

≤ 3kW $100,> 3kW $300

Supplemental Review or Additional Review (if applicable)

N/a Up to 10 engineering hours at $125/hr ($1,250

maximum)

N/a N/a

Standard Interconnection Initial Review

N/a N/a Included in application fee (if

applicable)

N/a

Impact and Facility Study (if required)

N/a N/a Actual cost N/a

Facility Upgrades N/a Actual cost Actual cost N/a

O and M N/a TBD TBD N/a

Witness Test 0 Actual cost, up to $300 + travel time

Actual cost 0

Qualified Inverter≤ 10 kW

Qualified DG Any DG Qualified Inverter≤ 10 kW

Page 15: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Maximum Time Lines

Simplified Expedited Standard Simplified Spot Network

Acknowledge Receipt of Application

(3 days) (3 days) (3 days) (3 days)

Review Application for Completeness

10 days 10 days 10 days 10 days

Complete Review of All Screens

10 days 25 days N/a Site review 30/90 days

Complete Supplemental Review (if needed)

N/a 20 days N/a N/a

Complete Standard Process Initial Review

N/a N/a 20 days N/a

Send Follow-on Studies Cost/Agreement

N/a N/a 5 days N/a

Complete Impact Study (if needed)

N/a N/a 55 days N/a

Complete Facility Study (if needed)

N/a N/a 30 days N/a

Send Executable Agreement

Done 10 days 15 days Done

Total Maximum Days 15 days 40/60 days 125/150 days 40/100 days

Notice/ Witness Test <1 day with 10 day notice or by mutual

agreement

1-2 days with 10 day notice or by

mutual agreement

By mutual agreement

1 day with 10 day notice or by mutual

agreement

Qualified Inverter≤ 10 kW

Qualified DG Any DG Qualified Inverter≤ 10 kW

Page 16: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Application Process

Prior NoticeOne Point of ContactApplication submittalReview Load flow and Voltage constraints Short Circuit and Protection review

System Modification ReviewAgreement

Page 17: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Application InformationGeneral (Single) or Specific Form?Simplified process (Inverter)

Applicant contact information Location of generator Proof of UL1741

Others Application contact information Location of generator Machine technical data Proposed drawings

Page 18: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Massachusetts Company Contacts

Boston Edison, Cambridge Electric, Com Electric (NStar Electric) Frank Gundal Tel: (781) 441-8151 Email: [email protected]

Fitchburg Gas & Electric (Unitil) John Bonazoli P.E. Tel: (603) 773-6456 e-mail: [email protected]

Massachusetts Electric Co. (National Grid) John J. Bzura, Ph.D., P.E., M.B.A. Tel: (508) 421-7642 e-mail: [email protected]

Western Massachusetts Electric ( Northeast Utilities) Doug Clarke Tel: 413-585-1726 Email: [email protected]

Page 19: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Why is DG Different?Traditional System

Trans. Sta

Gen Gen

Trans. Sta Trans. Sta

Load Load

Trans. Sta Trans. Substa Trans. Sta

Gen Gen

Load Load

Load Load

Page 20: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Distributed Generation

Load Gen

Load Load

Gen Gen

Trans. Substa Trans. StaTrans. Sta

Gen Gen

Gen

Trans. Sta

Gen

Trans. Sta Trans. Sta

Page 21: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

How Does DG Affect Distribution Companies?

Protection Generator Protection Coordination

Reliability EffectsPlanning Procedures Peak Load Planning Firm Capacity

Page 22: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Interconnection Process Advantages

Standard Process Easier planning for customer More Efficient with time Less time Consuming

Consistent FeesKnown Costs to customerKnown Process for customer

Page 23: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Challenges for Distribution Company

General Requirements Interpretations Analysis of compliance

Testing Requirements New devices

Time Lines Reports Interconnection agreement

Page 24: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Future Efforts

Quarterly Collaborative Meetings Interconnection updates Numbers of projects and applications

Annual Documentation sharing Detailed process information

Process Adjustments as needed

Page 25: Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable

Upcoming Tariff Document1.0 Introduction2.0 Responsibility of the Parties3.0 Process Overview4.0 Interconnection Req.5.0 General Operating Req.6.0 Metering, Monitoring, and Communication7.0 Responsibility For Costs of Interconnecting a Facility8.0 Dispute Resolution Process9.0 Confidentiality Statement10.0 Insurance Req.

Exhibit A – Interconnection Service Agreement templateExhibit B – Third Party Owner AgreementExhibit C – Simplified ApplicationExhibit D – Expedited/Standard ApplicationExhibit E – Supplemental Review AgreementExhibit F – Impact Study AgreementExhibit G – Facility Study AgreementExhibit H – Qualifying Facilities

Discussed already, from Collab. report, or new effort

72

131123

1

2

12

7

1

25

1

3

3

2