Mass Haul Diagram TUTORIAL & Solution

3
bdd/kuittho/2006 Tutorial: MASS HAUL DIAGRAM Distance (m) 103 62 67 50 75 77 120 86 71 63 45 66 Volume (m 3 ) 7,012 3,314 3,615 3,216 4,435 4,578 9,315 5,622 4,336 3,282 2,077 3,670 Cut (m 3 ) Fill (m 3 ) Borrow (m 3 ) Waste (m 3 ) Haul (m 3 ) 1. Construct a Mass Haul Diagram. 2. Complete the table. 3. Determine the volume of borrow or waste. 4. Given the following cost estimates, determine the cost of this particular earthwork: Cost of cutting, hauling and filling = RM 10 per cubic meter Cost of removing unwanted soil (waste) = RM 3 per cubic meter Cost of acquiring, hauling and filling of borrow soil = RM 6 per cubic meter 885.00 m Proposed Formation Level Existing Ground Level

Transcript of Mass Haul Diagram TUTORIAL & Solution

Page 1: Mass Haul Diagram TUTORIAL & Solution

bdd/kuittho/2006

Tutorial: MASS HAUL DIAGRAM

Distance (m) 103 62 67 50 75 77 120 86 71 63 45 66

Volume (m3) 7,012 3,314 3,615 3,216 4,435 4,578 9,315 5,622 4,336 3,282 2,077 3,670

Cut (m3)

Fill (m3)

Borrow (m3)

Waste (m3)

Haul (m3)

1. Construct a Mass Haul Diagram.

2. Complete the table.

3. Determine the volume of borrow or waste.

4. Given the following cost estimates, determine the cost of this particular earthwork:

Cost of cutting, hauling and filling = RM 10 per cubic meter

Cost of removing unwanted soil (waste) = RM 3 per cubic meter

Cost of acquiring, hauling and filling of borrow soil = RM 6 per cubic meter

885.00 m

Proposed

Formation

Level

Existing

Ground

Level

Page 2: Mass Haul Diagram TUTORIAL & Solution

bdd/kuittho/2006

Solution:

Distance (m) 103 62 67 50 75 77 120 86 71 63 45 66

Volume (m3) 7,012 3,314 3,615 3,216 4,435 4,578 9,315 5,622 4,336 3,282 2,077 3,670

Cut (m3) 10,326 9,013 7,618

Fill (m3) 6,831 14,937 5,747

Borrow (m3) 558

Waste (m3)

Haul (m3)

6,831

3,495

9.013 5,189

2,429

1. Refer to diagram

2. Refer to the table

3. Borrow = 558 m3

4. Cut-haul-fill volume = 26,957 m3 Cost = RM 10 x 26,957 = RM 269,570

Borrow volume = 558 m3 Cost = RM 6 x 558 = RM 3,348

Total cost = RM 272,918

885.00 m

Proposed

Formation

Level

Existing

Ground

Level

Cut

Fill

Page 3: Mass Haul Diagram TUTORIAL & Solution

bdd/kuittho/2006

Distance (m) 0 103 165 232 282 357 434 554 640 711 774 819 885

Volume (m3) 0 7,012 3,314 -3,615 -3,216 4,435 4,578 -9,315 -5,622 4,336 3,282 -2,077 -3,670

Cumulative Volume (m

3)

0 7,012 10,326 6,711 3,495 7,930 12,508 3,193 -2,429 1,907 5,189 3,112 -558

Mass Haul Diagram

-4000

-3000

-2000

-1000

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

11000

12000

13000

14000

0 103 165 232 282 357 434 554 640 711 774 819 885

Chainage (m)

Cu

mu

lati

ve

Vo

lum

e (

cu

bic

me

ter)