Tutorial: MASS HAUL DIAGRAM
Distance (m) 103 62 67 50 75 77 120 86 71 63 45 66
Volume (m3) 7,012 3,314 3,615 3,216 4,435 4,578 9,315 5,622 4,336 3,282 2,077 3,670
Cut (m3)
Fill (m3)
Borrow (m3)
Waste (m3)
Haul (m3)
1. Construct a Mass Haul Diagram.
2. Complete the table.
3. Determine the volume of borrow or waste.
4. Given the following cost estimates, determine the cost of this particular earthwork:
Cost of cutting, hauling and filling = RM 10 per cubic meter
Cost of removing unwanted soil (waste) = RM 3 per cubic meter
Cost of acquiring, hauling and filling of borrow soil = RM 6 per cubic meter
885.00 m
Proposed
Formation
Level
Existing
Ground
Level
bdd/kuittho/2006
Solution:
Distance (m) 103 62 67 50 75 77 120 86 71 63 45 66
Volume (m3) 7,012 3,314 3,615 3,216 4,435 4,578 9,315 5,622 4,336 3,282 2,077 3,670
Cut (m3) 10,326 9,013 7,618
Fill (m3) 6,831 14,937 5,747
Borrow (m3) 558
Waste (m3)
Haul (m3)
6,831
3,495
9.013 5,189
2,429
1. Refer to diagram
2. Refer to the table
3. Borrow = 558 m3
4. Cut-haul-fill volume = 26,957 m3 Cost = RM 10 x 26,957 = RM 269,570
Borrow volume = 558 m3 Cost = RM 6 x 558 = RM 3,348
Total cost = RM 272,918
885.00 m
Proposed
Formation
Level
Existing
Ground
Level
Cut
Fill
bdd/kuittho/2006
Distance (m) 0 103 165 232 282 357 434 554 640 711 774 819 885
Volume (m3) 0 7,012 3,314 -3,615 -3,216 4,435 4,578 -9,315 -5,622 4,336 3,282 -2,077 -3,670
Cumulative Volume (m
3)
0 7,012 10,326 6,711 3,495 7,930 12,508 3,193 -2,429 1,907 5,189 3,112 -558
Mass Haul Diagram
-4000
-3000
-2000
-1000
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
11000
12000
13000
14000
0 103 165 232 282 357 434 554 640 711 774 819 885
Chainage (m)