Mars Climate Orbiter Project Management Analysis

39
MARS CLIMATE ORBITER MISSION PROJECT MANAGEMENT CASE STUDY BY: FRANCISCO CEBALLOS NELSON ROSARIO BILLY GUERRERO RICARDO CABRAL

Transcript of Mars Climate Orbiter Project Management Analysis

Page 1: Mars Climate Orbiter Project Management Analysis

MARS CLIMATE ORBITER MISSION

PROJECT MANAGEMENT CASE STUDY

BY:

FRANCISCO CEBALLOS

NELSON ROSARIO

BILLY GUERRERO

RICARDO CABRAL

Page 2: Mars Climate Orbiter Project Management Analysis

• Background

- Why the interest in Mars?

- Mars missions under Faster, Better, Cheaper (FBC) approach.

- Account of the Mars Climate Orbiter (MCO) failure.

• Project Management Analysis

- Human Resource

MCO’s personnel characteristics and lessons learned.

- Communication

MCO’s communication deficiencies and lessons learned.

- Quality

MCO’s quality issues and lessons learned.

- Risk

MCO’s risk management errors and lessons learned.

• Conclusions

• Questions

Outline

Page 3: Mars Climate Orbiter Project Management Analysis

Why Mars?

Page 4: Mars Climate Orbiter Project Management Analysis

MISSION STATISTICS

Page 5: Mars Climate Orbiter Project Management Analysis

FASTER BETTER CHEAPER (FBC)

Faster Better Cheaper

Internal and

external pressures

Much emphasis on few missions

Shrinking budget

Utilizing new technology

Creating smaller spacecraft and more frequent

missions

Accepting prudent risk where warranted by

return

Reducing cycle time by eliminating inefficient

and redundant processes

Utilizing proven engineering and

management practices to maximize success

Page 6: Mars Climate Orbiter Project Management Analysis

• Lockheed Martin Astronautic was the main contractor and the Jet Propulsion Laboratory

was the administrator of all these missions.

• Total cost of the Mars missions under FBC of $921.6 Millions.

• Under FBC 3 out off 6 Mars missions failed.

Page 7: Mars Climate Orbiter Project Management Analysis

• Study Mars climate

• Monitor daily weather and atmospheric conditions

• Record changes on Mars surface

• Look for evidence of past climate changes

• Relay communications between MPL and Earth

• Expected to operate for 5 years (1999-2004)

MCO Mission Objectives

Page 8: Mars Climate Orbiter Project Management Analysis

• At Cape Canaveral, FL on December 11th, 1998

• Delta II Lite Launch Vehicle

• Launch sequence lasted 42 minutes

• Hoffman transfer to Mars

• Earth-Mars launch window consideredevery 2 years

MCO Launch

Page 9: Mars Climate Orbiter Project Management Analysis
Page 10: Mars Climate Orbiter Project Management Analysis

• 416 million miles over 9 months

• 4 Trajectory Correction Maneuvers

• Anomalies in trajectory caughtbut dismissed

MCO Cruise

Page 11: Mars Climate Orbiter Project Management Analysis

• Measures thruster performance

• Logs thruster firing events on file

• Installed both in ground & spacecraft

• Wrong unit in log file

• Trajectory modeling from file

• Corrections issued based on this modeling

• Thrusters fired 4.45 times shorter

“Small Forces” Software

Planned trajectory

Actual trajectory

CriticalAltitude

Page 12: Mars Climate Orbiter Project Management Analysis

Human Resource

Management

Develop Human

Resource Plan

Acquire Project Team

Develop Project Team

Manage Project Team

Page 13: Mars Climate Orbiter Project Management Analysis

Develop Human Resource Plan

• The PM is responsible of making sure the team members have the appropriate training according to the task they will be performing.

• The PM must clearly identify the roles and responsibilities of the team.

Acquire project team• The PM must evaluate the risk of resources becoming

unavailable.

Page 14: Mars Climate Orbiter Project Management Analysis

Training

• The Incident, Surprise, Anomaly (ISA) procedure.

• The ground software development process.

• The Mission Operations Software Interface Specification (SIS).

• The MCO attitude control system and related subsystem parameters.

• The Trajectory Correction Maneuver (TCM) -5.

Page 15: Mars Climate Orbiter Project Management Analysis

Staffing

• The Mars Surveyor Operations Project (MSOP) was running 3 missions simultaneously (MGS, MCO, MPL).

• The absence of a mission assurance manager.

• Absence of mission science personnel in the management process.

Page 16: Mars Climate Orbiter Project Management Analysis

Roles and responsibilities

• Hesitancy and wavering was perceived on the people attempting to answer these questions:

Who is in charge? Who is the Mission Manager?

• The lack of an adequate systems engineering function.

Page 17: Mars Climate Orbiter Project Management Analysis

Lessons Learned

• The team should be provided with proper training and detailed information regarding systems which may have a high impact on the well behavioral of the project.

• The project manager should identify or provide backup personnel that could be available to serve in some of the critical roles when needed.

• The human resource department should provide a staff with well defined roles and responsibilities.

Page 18: Mars Climate Orbiter Project Management Analysis

Communication Management

Distribute Information

IdentifyStakeholders

Report Performance

Plan Communications

MangeStakeholderExpectations

Page 19: Mars Climate Orbiter Project Management Analysis

Communications ManagementTHE PROBLEM START IN FBC

Page 20: Mars Climate Orbiter Project Management Analysis

Communications ManagementInterfaces and Relationships

Page 21: Mars Climate Orbiter Project Management Analysis

Communications ManagementNASA- JPL RELATIONSHIP

Page 22: Mars Climate Orbiter Project Management Analysis

Communications ManagementNASA- JPL RELATIONSHIP

Absence of a single interface resulted in multiple inputs to the JPL Mars Program

Input 1

Input 2

Input 3

Input 3

Input 2

Input 1

Page 23: Mars Climate Orbiter Project Management Analysis

Communications ManagementJPL-LMA RELATIONSHIP

RISK

Page 24: Mars Climate Orbiter Project Management Analysis

Communications Management• COMMUNICATION BARRIERS

Page 25: Mars Climate Orbiter Project Management Analysis

Communications ManagementLESSONS LEARNED

• Senior management must be receptive to communications of problems and risks.

• A dedicated single interface at NASA Headquarters for the Mars Program is essential.

• Contractor responsibilities must include formal notification to the customer of project risk and deviations.

• Increase the amount of formal and informal face-to-face communications with all team elements and especially for those elements that have critical interfaces.

Page 26: Mars Climate Orbiter Project Management Analysis

Quality Management

Plan Quality

Perform Quality

Assurance

Perform Quality Control

Page 27: Mars Climate Orbiter Project Management Analysis

• Assess whether correct processes are being followed usingmeasurements from QC

• Determine if organizational & project processes, policies and procedures are being followed

Perform Quality Assurance Process

• Measure quality of deliverables

• Validate deliverables

Perform Quality Control Process

Page 28: Mars Climate Orbiter Project Management Analysis

Perform Quality Assurance• Verification & Validation (V&V) procedures not followed

• No user testing of the code

• Poor Code review process

• Non-conformance with SIS

• Increasingly frequent anomalous events disregarded

Page 29: Mars Climate Orbiter Project Management Analysis

Issue TrackingSummary

Perform Quality Control

• Insufficient rigor interface control process

•Global issue-tracking database not usedfor anomalies

• Issues left unresolved

•Need to improve quality not identified

Identification

Review

Solve

Lessons Learned

Page 30: Mars Climate Orbiter Project Management Analysis

Quality Lessons Learned

• Perform thorough code review

• Metrification

• Develop comprehensive mission requirements down to subsystem level

• Iteratively verify mission requirements conformance

Page 31: Mars Climate Orbiter Project Management Analysis

Risk

Management

Identify

Risk

Perform

Qualitative Risk

Analysis

Plan Risk

Management

Perform

Qualitative Risk

Analysis

Plan

Risk

Response

Monitor

And

Control Risk

Page 32: Mars Climate Orbiter Project Management Analysis

Risk Management Overview

• Identify uncertainty, positive and negative.

• It’s comprised of six sequential processes: Plan Risk Management, Identify Risks,

Perform Qualitative Risks Analysis, Perform Quantitative Risks Analysis, Plan Risk

Responses and Monitor and Control Risks.

• Starts at initiation and finish with project closure.

• It’s iterative, ones planned, should be reassessed and control.

• Could impact costs, schedule, scope, quality, customer’s satisfaction and stakeholders

interests.

• When it’s integrated in a project prevents unnecessary threats and promote wanted

opportunities.

• Unmitigated risks has an owner with a clear contingency plan, launch depending on

risk triggers.

Page 33: Mars Climate Orbiter Project Management Analysis

Risk Management Failures

• No a sound Risk Management plan in place.

• FBC didn’t describe clearly what were prudent risks.

• Each project manager interpreted risks differently under FBC policy.

• MCO was significantly underfunded compared to other comparable missions.

• System engineering didn’t play its rolling in help in risks identification and management.

Page 34: Mars Climate Orbiter Project Management Analysis

• Project managers put more emphasis on lower cost and

schedule, and more ambitious scope, while risks increase

was not considered.

• No proper procedure to implement TCM-5 as an

emergency plan.

Page 35: Mars Climate Orbiter Project Management Analysis

Lessons Learned

• Risks caused by deviation from project management principle shouldn’t be allow.

• All team members should know what is acceptable risks.

• All mission should perform the six processes of risk management.

• In all project meetings and reviews risks mitigation plan should be reported and reassessed.

Page 36: Mars Climate Orbiter Project Management Analysis

Success

Cost

Time

Risk

Scope

• Risk management a fourth dimension of project management.

• Earn value management could be applied to risk management.

• All unmitigated risks should have a risk owner and a clear

contingency plan.

Page 37: Mars Climate Orbiter Project Management Analysis

C O N C L U S I O N S

• "Faster, better, cheaper" missions place too much emphasis on cost andschedule reduction and too little on management, oversight, leadership andevaluating risk.

• Key positions in the staff and well trained personnel are critical points thatany PM must not sacrifice because of reducing cost strategies.

• A routine forum should be established for informal communication between allteam members at the same time so everyone can hear what is happening.

• The absence of a sound Risk Management Plan prevented that the missioncould overcome any important threat, reducing significantly its chances forsuccess.

• A comprehensive contingency plan to execute TCM-5 could have increasedthe probability of success of the mission.

Page 38: Mars Climate Orbiter Project Management Analysis

QUESTIONS

Page 39: Mars Climate Orbiter Project Management Analysis

THANK YOU !!