November 4, 2019
Park Board Committee Meeting
MARPOLE COMMUNITY
CENTRE RENEWAL Outdoor Pool &
Oak Park Schematic
Master Plan
![Page 2: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/2.jpg)
To provide an update on the Marpole Community Centre
Renewal and outdoor pool planning process, and to seek
Board approval of the Oak Park Schematic Master Plan.
Purpose of Presentation
2
![Page 3: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/3.jpg)
Previous Decisions & Policies
Background
Marpole CC Renewal: Process
Summary
A. Needs Assessment/Program
Definition
B. Outdoor Pool
C. Schematic Park Master Plan
Next Steps
3
Presentation Outline
![Page 4: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/4.jpg)
June 2016 Motion: “THAT the Vancouver Park Board move forward with consultation
and planning for the renewal of the Marpole-Oakridge Community Centre on the
existing site located at Oak Street & 59th Avenue at Oak Park."
January 2018 Motion: “THAT the Vancouver Park Board approve the location for a
new full-sized outdoor pool in South Vancouver co-located at Marpole Community
Centre in Oak Park."
July 2018: Park Board approved the Park Board 2019-2022 Capital Plan
(subsequently approved by Council) which included:
• $38.6M of funding for a new Marpole Community Centre (40,000+/- GSF)
• $15M of funding for an outdoor pool
Previous Board Decisions
4
Previous Board Decisions
![Page 5: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/5.jpg)
5
Park Board & City Policies
![Page 6: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/6.jpg)
Background 6
![Page 7: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/7.jpg)
7
Background: The Marpole Neighbourhood
Inhabited since time immemorial by the Musqueam
people;
Ancestral Musqueam village site, c̓əsnaʔəm, is
located within the current Marpole neighbourhood’s
boundaries
European settlement led to urbanization and
dispossession of Musqueam people from their
lands.
Current neighbourhood form began to develop in
1860s.
Experienced 43% population growth from 1981 to
2011, in line with Vancouver’s growth of 41%;
Now a growing community of long-time residents,
newcomers, families and seniors.
Marpole from the air, looking north, 1948
![Page 8: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/8.jpg)
8
![Page 9: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/9.jpg)
9
Background: Marpole-Oakridge Community Centre Building
Opened in 1949
70 years as Marpole’s community
hub
Gross area of 31,800 square feet
Located at Oak Street & 59th
Avenue in Oak Park
Identified for renewal in Park Board
Facilities Renewal Plan (2009) and
Marpole Community Plan (2014)
![Page 10: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/10.jpg)
10
Marpole CC Renewal: Process Summary
![Page 11: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/11.jpg)
11
Marpole CC Renewal: Process Summary
“What goes in the
building”? “Where should the
building/pool go?”
“How do we design
the building/pool?”
![Page 12: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/12.jpg)
Working Group:
Park Board Staff
City staff from Real Estate & Facilities Management, Planning Urban Design & Sustainability, and Arts, Culture & Community
Services
Members of the Marpole/Oakridge Community Centre Association
Advisory Group:
Representatives of Marpole Business Association, Neighbourhood
House, Marpole/Oakridge Family Place, Marpole Residents Coalition and community residents
12
Marpole CC Renewal: Process Summary
![Page 13: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/13.jpg)
13
Marpole CC Renewal: Process Summary
• Youth (42)
• Seniors (30)
• Chinese language (27)
Engagement Phases 1 (2018) and 2 (2019)
• Marpole-Oakridge Community
Association (5)
• Sports Groups (4) • External Advisory group (6)
• TalkVancouver Surveys (1020)
• 2 Open Houses (222)
• 2 Pop-Up Events (110)
Over 1400 conversations started
![Page 14: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/14.jpg)
14
A. Needs Assessment/Program Definition What goes in the building?
![Page 15: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/15.jpg)
15
Fall 2017: A Needs Assessment Study for a new Marpole Community
Centre began
Recreation programming needs were identified, based on current
building function, service levels, best practices, recreation context,
relevant policy, community engagement, and expected growth
Late 2018: A preliminary program definition was developed for the
building, which includes high level room program definitions,
interrelationships and rough sizes
A. Needs Assessment/Program Definition
![Page 16: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/16.jpg)
16
Challenges with current
building include:
Lack of space needed for
programs
Aging, inadequate building
systems
Barriers to universal access
Outdated kitchen facilities
A. Needs Assessment/Program Definition
![Page 17: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/17.jpg)
A. Needs Assessment/Program Definition
17
A preliminary program
definition identifies:
Room programs
Interrelationships between rooms/spaces
Approximate room sizes and volumes
Basis for functional program for
building
![Page 18: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/18.jpg)
A. Needs Assessment/Program Definition
18
1. Most popular recreation activities: fitness classes/activities
and swimming
2. Barriers to participation in recreation: challenges getting to and from facilities, overcrowding
3. Desirable indoor amenities: indoor swimming, fitness centre, gym, multipurpose rooms, and commercial-grade kitchen.
4. Desirable outdoor amenities: play space, walking paths, and
social spaces (plaza/festival space/picnic areas).
5. Not enough services for seniors’ health and wellness, youth
drop-in and academic support, and childminding.
6. Engagement responses validated Oak Park as the preferred location for the new community centre.
Phase 1 Engagement: Key findings
![Page 19: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/19.jpg)
A. Needs Assessment/Program Definition
19
Program Definition: Four Key Priorities
![Page 20: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/20.jpg)
20
Program Definition:
Proposed Room
Interrelationships
![Page 21: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/21.jpg)
A. Needs Assessment/Program Definition
21
Approximate Building Size
![Page 22: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/22.jpg)
B. Outdoor Pool 22
![Page 23: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/23.jpg)
January 2018 Motion: “THAT the Vancouver Park Board approve the
location for a new full-sized outdoor pool in South Vancouver co-
located at Marpole Community Centre in Oak Park."
Recommendation from VanSplash: “Provide a new co-located
outdoor pool in South Vancouver”
23
B. Outdoor Pool
![Page 24: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/24.jpg)
C. Oak Park Schematic Master Plan How do we design the building/pool?
24
![Page 25: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/25.jpg)
25
C. Schematic Master Plan
park elements at a diagrammatic level
Shows locations of new and existing elements
Enough detail to determine what features can fit where (e.g. community centre, outdoor pool)
a first step towards a full park master plan
A Schematic Master Plan illustrates:
![Page 26: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/26.jpg)
26
Spring 2019: A Schematic Master Plan Study for Oak Park began
Purpose of this work was to find the best possible location for the
new community centre while balancing existing park uses, and
also to properly site the outdoor pool to have a strong relationship
to the building
October 2019: A preferred schematic master plan was developed
for Oak Park
C. Schematic Master Plan
![Page 27: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/27.jpg)
27
C. Schematic Master Plan
Needs Assessment Study informed the schematic
master planning for Oak Park
including siting building and outdoor pool
Engagement was done to
understand tradeoffs with
existing park elements
Continuity of Community
Centre service to be ensured
Oak Park: Existing Elements
![Page 28: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/28.jpg)
28
C. Schematic Master Plan
Oak Park: Existing Elements
Oak Park:
Proposed
Elements
Needs Assessment Study informed the schematic
master planning for Oak Park
including siting building and outdoor pool
Engagement for schematic
master plan to understand
tradeoffs with existing park
elements
Continuity of Community Centre service to be ensured
![Page 29: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/29.jpg)
29
C. Schematic Master Plan
1. Preferred existing park activities/features
2. Perceived barriers and challenges to using
Oak Park
3. Ideas and priorities for park improvements
4. Preferences on three proposed schematic
plan options
Phase 2 Engagement: Stakeholder Input
![Page 30: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/30.jpg)
30
C. Schematic Master Plan
Key priorities for Oak Park, the new community centre and
pool have emerged through engagement:
1. Retain tree canopy and ecological function
2. Maximize green space for casual uses
3. Minimize disruption to existing facilities
4. Expand playground/splash park, locate near building
5. Maintain lit field and 2 ball diamonds
6. Enhance visibility and access from Oak St.
7. Minimize pollution and exposure from Oak St.
Phase 2 Engagement: Key Findings
![Page 31: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/31.jpg)
C. Schematic Master Plan: Key Design Highlights:
31
Safe pedestrian and bike access
is important
- Vehicular and service access from Park Drive
- Minimize traffic on 59th (bike route) and Fremlin St.
Visible, accessible and inviting - Locate building at SW corner of Oak Park
More parking, minimize impact
to the park
- Locate parking underground
- Some surface spots for drop off/accessibility
Retain trees and maximize
green space for casual use
- Preservation of greatest number of established trees
- NE corner of park dedicated to green space for casual use - Incorporate safe, accessible and inviting walking paths and
loops within Oak Park
Continue to provide fields and
diamonds for local sports groups. Improve gravel field.
- Upgrade lit gravel field to multi-purpose all weather
- Remove 1 t-ball diamond, upgrade remaining t-ball
What We Heard What We Did
![Page 32: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/32.jpg)
32
Preferred
Schematic
Master Plan
![Page 33: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/33.jpg)
33
Next Steps
![Page 34: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/34.jpg)
Next Steps: Community Centre Renewal Schedule
34
![Page 35: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/35.jpg)
A. THAT the Vancouver Park Board approve the proposed Schematic
Park Master Plan for Oak Park as shown in Appendix C, which
includes the location of the renewed Marpole Community Centre
and a new full-sized outdoor pool.
B. THAT the Vancouver Park Board direct staff to proceed with
detailed planning and design of the community centre and outdoor
pool, in collaboration with City staff.
Recommendation
35
![Page 36: MARPOLE COMMUNITY CENTRE RENEWAL - Vancouver Park Board€¦ · Key priorities for Oak Park, the new community centre and pool have emerged through engagement: 1. Retain tree canopy](https://reader033.fdocuments.us/reader033/viewer/2022052016/602eb4995d068e37516f6943/html5/thumbnails/36.jpg)
36