Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma...

41
/ Marley Sigma 1000/1200 Cooling Tower /

Transcript of Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma...

Page 1: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

/ Marley Sigma 1000/1200 Cooling Tower /

Page 2: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

2

You’ll enjoy single source responsibility and reliability

because we design and manufacture virtually all major

cooling tower components.

All Marley components are designed and selected to be

part of an integrated system. For example, the spray pattern

from nozzles and the pressure drop through drift eliminators

both affect a fill’s heat transfer capacity. So, we include that

impact in our thermal analysis.

Drift eliminators must be effective at the air velocities

where fill is most efficient. So, we’ve carefully designed both

components to work together efficiently.

How many other cooling tower companies can offer you

this assurance? They may use Brand “A” nozzles with Brand

“B” fill and Brand “C” drift eliminators. When they all come

together, the whole may be less than the sum of the parts.

Our total system approach assures that all the parts

work together to provide you the greatest total performance.

And because we design specifically for cooling towers,

all our components will provide many years of service with

minimal maintenance.

/ The Marley Difference /

Series 1200 Cross-Section

Page 3: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

3

/ Sigma Advantage /

• GuaranteedPerformance. Don’t rely on outside

agencies with limited enforcement powers. We’ll stand

by our responsibility for reliable thermal performance.

We designed it. We rate it. We guarantee it!

• Exclusive5-YearMechanicalWarranty. Your no-

cost assurance of trouble-free mechanical operation

for 5 years. Isn’t that where a lot of your tower

maintenance dollars have gone in the past?

• LongServiceLife. We’ve carefully chosen all the

materials used in Sigma towers for their corrosion

resistance and suitability for cooling tower service.

Pressure-treated lumber, heavy-galvanized steel,

stainless steel, PVC and fiberglass keep your Sigma

tower working year after year.

• EfficientFieldAssembly. Precise factory fabrication

assures that every component in your Sigma tower will

fit as designed. And SPX Cooling Technologies offers

an unparalleled nationwide construction organization to

build your tower quickly and economically.

• LowOperatingCosts. Marley’s high-efficiency fill

and fans, gravity-flow water distribution, and efficient

Geareducer® drive work together to offer maximum

cooling with minimum power use.

• LowMaintenanceCosts. Induced-draft propeller

fans on Marley right-angle Geareducer units; TEFC,

1.15 service factor motors; and heavy-duty mechanical

equipment supports assure long service life with

minimal maintenance.

• All-SeasonReliability. Sigma towers perform as

specified in the heat of summer. They respond well to

energy management techniques in the spring and fall.

They operate virtually ice-free in the dead of winter.

And they offer simple maintenance all year long. We

guarantee it!

• SingleSourcePartsAvailability. SPX designs,

manufactures, guarantees, and stocks all major

components of the Sigma cooling tower except

motors. We’ll have the parts if you ever need them.

Series 1000 Cross-Section

Page 4: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

4

/ Construction and Components /

Fill/Louvers/Drift Eliminators

Marley high-performance film fill is the heart of every

Sigma tower. A repeating chevron pattern provides the

wetted surface and air turbulence necessary for proper heat

transfer, while minimizing resistance to airflow so you’ll save

on fan power. Molded protrusions on each fill sheet assure

uniform spacing.

Fill sheets include both louvers and drift eliminators.

The louvers in this patented arrangement keep water on the

fill sheets and in your tower, and also assure proper heat

transfer throughout wide variations in airflow. Users find this

fill operates ice-free even in extremely cold weather.

Fill sheets are vacuum formed 15 mil (.015") thick

polyvinyl-chloride (PVC) capable of service at hot water

temperatures up to 125°F. Stainless steel structural tubes

resting in stainless steel hangers support the fill, and PVC

tubes control alignment. Series 1000 fill includes two

stainless supports, and Series 1200 fill uses four stainless

supports. This system also holds the bottom of the fill sheets

above the cold water basin floor to simplify basin cleaning.

Integral drift eliminators prevent the costly nuisance of

drift spotting on objects in the sur round ing environment.

Their unique shape induces the air flow through three distinct

direction changes as illustrated above. The final turn directs

air toward the fan to save you fan horsepower. Moisture

carried in the air stream can’t make these abrupt turns, so

drift is 0.010% or less of the circulating water flow rate.

Page 5: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

5

fans, used on larger models, include hollow GRE (glass-

reinforced epoxy) blades and epoxy-coated cast iron hubs.

Blades on both fan types are adjustable in pitch, so you can

take full advantage of rated horsepower or adjust the pitch

to compensate for unusual job site restrictions. The true

airfoil blades, designed specifically for cooling towers, offer

efficient, quiet operation and long service life.

Mechanical Equipment

You’ll receive a 5-year warranty against failure of any

mechanical component in the fan drive system (except the

motor, which is warranted by its manufacturer).

The Marley Geareducer speed reducers used in the

Sigma line contribute a long record of dependability, long

service life, and low maintenance to this assurance of

reliability. Their designs meet or exceed the requirements

of CTI STD-111 and AGMA Std. 420.04. We run-in every

Geareducer unit under load prior to shipment to make sure

that it will operate properly on your tower.

Housings are gray cast iron. Gears are high-strength,

case hardened alloy steel. And all bearings are tapered roller

bearings. A variety of available horsepower capacities and

reduction ratios lets us choose the optimum Geareducer

model and fan speed for your job. Service factors are always

at least 2.0 as applied.

Splash-type lubrication and integral cooling fins preclude

the need for maintenance-intensive oil pumps and coolers. A

constant oil bath or flow lubricates every bearing in forward or

reverse motion – at full or half speed.

All Marley Geareducer assemblies are right-angle type

with motors located outside the tower’s saturated airstream.

A galvanized steel lube line runs from the Geareducer unit

to a standpipe near the motor on each cell, so you can check

oil level and change or add oil while standing on the fan deck.

All Sigma Series 1000/1200 towers offer the benefits of

adjustable pitch propeller type Marley fans. The H-3 series

fans normally used on smaller models incorporate cast

aluminum blades and machined aluminum hubs. HP-7 series

Fans operate inside structural GRP (glass-reinforced

polyester) eased-inlet fan cylinders designed and applied to

maximize fan performance. Cylinder height varies from 3'-5"

to 7'-0", depending on fan diameter. Cylinders less than

6'-0" tall include galvanized welded fan guards. (See Access

and Safety on page 7.)

Marley-manufactured driveshafts transmit power

from the motor to the Geareducer assembly. All Marley

driveshafts include 304 stainless steel tubes with welded-

on stainless steel flanges and bonded neoprene flexible

elements to transmit torque. Marley driveshafts are full-

floating assemblies with non-lubricated flexible couplings

on each end. Their tolerance to misalignment and torsional

shock is unequalled in nonspecialized units. All Marley

driveshafts are dynamically balanced at the factory to

minimize operating vibrations.

Welded unitized hot-dip galvanized steel supports

maintain alignment throughout the mechanical equipment

system. Marley torque-tubes provide superior strength and

stability. Their cylindrical shape also keeps operating costs

down by minimizing airflow restrictions and reducing air

turbulence in the fan entrance region.

/ Construction and Components /

Page 6: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

6

Water Distribution System

The gravity-flow water distribution system designed into

the Sigma tower essentially reduces pump head to its most

basic component – static lift – saving you money on pump

power. You won’t have to force water through internal piping

and pressure spray nozzles, as you would in a counterflow

tower.

Warm water enters the system through the Sigma

galvanized crossover pipe. Inlet connections for your piping

are standard 125# flanges. Marley flow-control valves balance

the flow to both distribution basins of each cell. Water flows

projected area and the design meets 5%g seismic loading,

based on a maximum water temperature of 120°F.

Pressure-treated Douglas Fir is the standard material

for structural members in Sigma towers because it offers

predictably consistent structural strength and provides long

service life in cooling towers. Treated redwood structure

from each valve through a splash-suppression chamber into

the treated fir plywood distribution basin.

Polypropylene patented “Spiral Target” nozzles in the

basin floor then distribute the water uniformly over the fill.

All materials in the water distribution system offer long life

and minimal maintenance. Valves consist of cast iron bodies

and grease-lubricated stainless steel operating stems. All

plywood is treated exterior grade. The nozzles are chemically

and biologically inert, so they’ll last indefinitely.

Structure and Materials

Sigma tower design conforms to the latest edition of the

National Design Specification for Wood Construction (NDS)

published by the National Forest Products Association.

Wind load criterion is normally 30 pounds per square foot of

is available as an option. However, you will benefit in the

long run from specifying redwood very selectively and very

carefully.

Unless otherwise specified, all lumber – regardless

of species – is pressure treated after fabrication. Lumber

treatment is CCA, infused into the wood by the full-cell

process to 0.40 lb/ft3 retention.

The primary structural elements of all Sigma towers

are the 4" x 4" columns. Column bent lines occur on 4'-0"

longitudinal centers.

/ Construction and Components /

Page 7: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

7

The 4" x" 4 tower diagonals carry loads to heavy-

duty hot-dip galvanized steel anchor plates or hot-dip

galvanized anchor weldments. The system of longitudinal

and transverse diagonal bracing provides stability in a true

tension-compression design.

the mechanical equipment. The taller fan cylinders used on

Series 1200 models effectively keep personnel away from

the fan, eliminating the need for guards.

All mechanical equipment is accessible both from the

interior of the tower and through the fan cylinder.

Every component of every tower is removable and

replaceable.

Casing

Tower endwalls are cased with gray 8 oz/sq ft rib-type,

fiber reinforced polyester sheets. Water and corrosion-proof,

All structural framing connections use 1/2" dia.

galvanized machine bolts with either fiber-reinforced nylon

shear connectors or FRP connector straps.

The fan deck is pressure treated exterior grade fir

plywood designed for a uniform live load of 60 psf.

Access and Safety

The Sigma tower is designed to meet all OSHA

requirements. A 3'-6" high guardrail system, complete with

toprails, intermediate rails and toeboards, surrounds the

entire top perimeter of the tower.

Aluminum ladders attached to the tower endwalls

provide access to the fan deck level. Ladders begin at the

cold water basin level and end at the top of the guarddrail.

Each tower normally includes two ladders—one at each

endwall.

Hinged doors through the endwall casing permit access

to the interior of the tower at the basin level. Single-cell

towers have one door. Multicell towers have doors in both

endwalls, plus accessways through any and all partition

walls.

Removable fan guards on Series 1000 models keep

personnel away from operating fans. The galvanized,

heavy-gauge welded rod guards lift off for easy access to

FRP is immune to biological deterioration and requires no

maintenance.

Casing ribs run vertically. Vertical joints between sheets

are overlapped one rib and are sealed in the fill areas.

Casing attaches to the structural members with stainless

steel fasteners and neoprene bonded washers. Corner trim

pieces are 12 oz/sq ft molded FRP.

/ Construction and Components /

Cold Water Collection Basin

Most Sigma owners install their towers over concrete

cold water basins provided by others. However, you can

choose a Marley wood collection basin as an optional

accessory. (See page 11).

Consult your Marley sales representative for detailed

dimensioned drawings and load schedules to help you with

your basin design.

Page 8: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

8

/ Available Options /

Accessory Description and RemarksAccessory Description and Remarks

Plywood Cold Water

Collection Basin

Pressure-treated Douglas fir plywood collection

basin for towers located above grade.

See page 11.

Bottom-Outlet Sump Square-plan galvanized steel sump with bottom

outlet. Outlet connection is a hole and bolt circle

conforming to 125# ASME pipe connection.

Includes a plugged drain connection in sump

bottom.

Additional Access

Door

Extra access door on single-cell towers

offers easy access through either endwall.

Wood Stairway Pressure-treated Douglas fir 45° stairway located

at tower endwall provides access to the fan

deck. Choose a stairway in place of one endwall

ladder, or use both ladders as well as the

stairway. Handrails and kneerails are standard,

so design conforms to OSHA standards.

Steel Ladder Galvanized steel ladder conforms to OSHA

standards. May be in place of or in addition to

standard aluminum ladders.

Ladder Safety Cage Galvanized steel circular framework, bolts

to ladder siderails and conforms to OSHA

standards. Cages extend from the top of the

guardrail to about 7’ above the base of the

ladder. If the tower fan deck is more than 20'

above roof or grade, OSHA requires safety cages.

Plenum Walkway Pressure-treated Douglas fir plenum walkways

extend the full length of the tower from access

door to access door above the water line.

Guardrails are optional. However, OSHA requires

guardrails if the walkway is 4'-0" or more above

the basin floor.

Ladder Extensions Used when tower is elevated appreciably above

working level. Extensions attach to the normal

ladder and may require base anchorage

(depending on length).

Premium

Hardware

Choose from several corrosion-resistant

hardware options, providing different degrees of

protection.

Fire Protection Sprinkler systems and overlay materials let you

choose from a range of fire protection options.

See page 10.

Redwood Fan Deck,

Distribution Basin, or

Tower Structure

You can choose redwood instead of Douglas fir

for any or all of these tower elements.

Interior tower columns can be extended to

permit concrete basin depth of up to 5’-6”.

Some exceptions apply, so consult your

Marley sales representative

Fan Cylinder

ExtensionsOptional flared fan cylinder extensions improve

fan efficiency to reduce your operating costs.

Extensions on Sigma 1000 Series towers

conform to OSHA requirements without fan

guards.

Cell Partitions Extra partitions between fan cells for specific

operating considerations. See page 9.

Vibration Limit

Switch

Robertshaw or Metrix single-pole, double-throw

vibration switches in NEMA 4 housing. Double-

pole, double-throw models are also available.

Oil Level Sight Glass A brass-fitted oil level sight glass takes the place

of the dip stick on the external oil fill and drain

system. Permits easy reading of oil level and also

lets you change oil through the lube line.

Air Inlet Screens Galvanized wire mesh screens over the air inlets

keep leaves and trash out of the tower. Easily

removable. Choose either treated fir frames or

galvanized steel U-edge frames.

Plywood

Distribution Basin

Covers

Removable, treated fir plywood covers keep

upper basins free of leaves and debris. They

also tend to retard growth of algae by keeping

ultraviolet radiation away from the warm

water in the basins. Covers may be used as a

working surface for tower maintenance.

Extended

Columns for Deep

Collection Basin

Page 9: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

9

Cell Partition Options

Every Sigma tower includes plenum chamber partitions

and hot water distribution basin partitions between

adjacent cells. Plenum partitions ensure consistent thermal

performance as you shut off one fan at a time. They keep air

from entering an operating cell through an adjacent idle fan,

maintaining efficient thermal performance. Basin partitions

let you inspect and clean individual basins while the rest of

the tower continues to operate.

Specify extra partitions carefully because excess

partitions can sometimes discourage routine maintenance

and good housekeeping procedures. Two options are

available to meet specific design goals:

• Fillareapartitionsareavailable,butusuallynot

necessary. The solid sheet design of film fill prevents

water and air migration between the fill areas of

adjacent cells, regardless of operating mode.

• Completewatertightpartitionsprovidetotalcell

isolation. These partitions let you use adjacent cells

to serve separate loads with incompatible system

temperatures. Watertight partitions extend from louver-

face to louver-face and cover the full internal height of

the tower, including the cold water basin. Partitions

usually consist of exterior grade, pressure-treated fir

plywood, sealed to cold water basin partitions made

from the same material as the basin sides. For concrete

basin partitions, design drawings are available that

specify the appropriate Marley dimensions.

Optional weir gates in wood basin partitions let you

mix or segregate the water in the basin to meet

your operating needs. Marley weir gates come with

removable cover plates.

/ Available Options /

Oil-Level Sight Glass

Wood Stairway with Access Platform

Page 10: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

10

Fire Protection Options

The PVC fill, louvers and drift eliminators used on Sigma

towers are fire-retardant, having flame spread ratings less

than 25 per ASTM E-84. Standard fan decking material

is pressure-treated fir plywood which ignites poorly and

burns slowly. For these reasons, governing agencies (such

as Factory Mutual) may not require fire protection sprinkler

systems on Sigma towers.

On specific jobs you may want to weigh the cost of

various modifications against the cost (and maintenance)

of a sprinkler system – or the cost of higher insurance

premiums. One or more of the following tower modifications

may negate the need for a sprinkler system:

• Fire-retardantfancylindersandoptionalcasingoffer

flame spread less than 25 per ASTM E-84.

• A1/4"thickfiber-reinforcedcementboard(FRC)overlay

on the fan deck acts as a fire stop and provides a

nonskid walking surface.

• A1/4"FRCoverlayonthedistributionbasincoversacts

as a fire stop.

• Barrierwallskeepfirefromspreadingbetweencells

in multicell towers. Specify barrier wall design by

containment period, such as a “20-minute fire wall”.

Barrier walls are full-width, full-height of the tower

interior (except cold water basin), and consist of

pressure-treated fir plywood both sides of the column

line between cells. Plywood thickness (and cost) vary

according to the specified containment time.

• Steelconstruction.RememberthattheSigmaseries

is available in steel construction – either galvanized or

stainless – as are a number of other Marley series, all of

which meet all established fire code requirements.

If your insurance carrier insists on a sprinkler system for

your tower, consult your Marley sales representative. We can

provide a sprinkler system to fit your needs, or work with

your people to be sure that the sprinkler system and tower

will meet your specification.

Non-Standard Motors

Although you can buy your Sigma tower “less motor” at

a cost reduction, it is not normally recommended. Motors

supplied on Marley towers meet rigorous specifications

developed from environmental chamber tests at our

Development Center. These specifications represent prudent

minimum design requirements.

Unless otherwise specified, motors provided on

Marley cooling towers are TEFC, 1.0 or 1.15 service

factor (appropriate to the applied load), 1800 RPM. Other

enclosures (such as Explosion Proof) and motors specially

wound for non-standard voltages are available at extra cost.

Two-speed motors are also available, and their

advantages are discussed on page 22.

/ Special Component Options /

Page 11: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

11

Cold Water Collection Basins

If you plan to locate your tower above grade, a treated

Douglas fir Marley cold water collection basin is available,

complete with the necessary operating accessories. The

basin floor is exterior grade, pressure-treated fir plywood,

supported on joists. Basin sides are plywood, machined to

fit the basin floor, providing a water-tight joint after sealing.

The standard wood basin includes at least one

depressed, side-outlet sump. The number and size of

sumps depends on the circulating water rate and the overall

size of the tower. Unless otherwise specified, sumps include

plugged drains and hot-dip galvanized debris screens.

Standard sumps are FRP construction or hot-dip galvanized

steel, depending on outlet size.

Stainless steel sumps and screens are available as

options at extra cost.

Each basin includes an overflow/cleanout connection

consisting of a galvanized full coupling and standpipe. The

normally-installed standpipe ensures adequate freeboard in

the cold water basin and removes easily for flush-out basin

cleaning.

A float-operated, mechanical make-up valve provided

with each basin automatically replenishes water lost from

the system. The valve is located in the plenum chamber

between fill banks, just inside the endwall access door to

facilitate adjustment and maintenance.

/ Special Component Options /

High Design Loadings

Our engineers will make sure that your Sigma tower

will withstand any higher-than-normal design loadings

(wind, earthquake, decking, etc.) that you may specify.

Clearly define any special design requirements in your tower

specifications. We’ll make any necessary changes to the

tower’s structural design. This is equally true if you anticipate

incoming hot water temperatures above 120°F.

The specification should also describe the type of load

system served by the tower, and include the expected

water quality analysis, so that our engineers can select and

recommend appropriate changes in component materials

to assure satisfactory service. Discuss any questions about

technical requirements with your trained Marley sales

representative.

Page 12: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

/ Additional Services /

SPX Cooling Technologies is dedicated to satisfying the needs of our customers—needs which begin far in advance of the actual

purchase of a new Marley cooling tower, and vary over the operating lifetime of the project. Here is a partial listing of the additional

services offered by SPX Cooling Technologies to help you do your job most effectively:

Application/Sizing/Layout Services—Sales Engineers are

trained to help you choose the proper type and size

of cooling tower, and will guide you in its appropri-

ate location on site. They will also help you write the

specifications for its purchase. As the only manufacturer

who makes all types of cooling products, SPX Cooling

Technologies can offer you a wide range of options to

meet your requirements.

Construction Service—We can supply supervision only—or a

complete, experienced crew to handle construction.

Parts Service—We maintain a stock of spare parts specific

to your Marley tower.

Maintenance Service—In addition to providing complete

instructions and continuing guidance, we will provide

as much “hands on” maintenance as you require, or will

recommend a local service contractor for your consider-

ation.

Condition Inspection Service—From time to time, for your

peace of mind, our engineers can give your tower a

thorough inspection to evaluate its current condition.

This usually allows you to foresee and forestall problems

before they become serious.

Reconstruction Service—Due to operating or atmospheric

conditions, or age, sooner or later your tower will be in

need of repairs above and beyond those categorized

as normal maintenance. Our reconstruction service can

return your tower to as new condition

Performance Improvement Service—Systems served by

cooling towers grow in response to demand for the

product produced by that system. Most customers find

that they could produce more product if the cooling

tower could deliver colder water. Fortunately, cooling

tower technology advances with time, and we can ap-

ply this increased technology to upgrade your tower’s

thermal performance.

Tower Replacement Service—Occasionally, customers will

benefit from replacing an installed tower, rather than

refurbishing it. SPX Cooling Technologies stands ready

to assist you in that endeavor—and, in most cases,

the replacement will require little or no change to your

concrete basin or support structure.

7401 WEST 129 STREETOVERLAND PARK, KANSAS 66213UNITED STATES913 664 [email protected]

In the interest of technological progress, all products are subject to design and/or material change without notice. ©2008 SPX Cooling Technologies, Inc. Printed in USA | SIG-07

Page 13: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

/ Marley Sigma 1000/1200 Cooling Tower /Engineering Data & Specifications

Page 14: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Marley / Sigma 1000/1200 Cooling Tower / Table of Contents

Engineering Data

1000 Schematic 41000 Piping 51000 Support 61200 Schematic 81200 Piping 91200 Support 10Energy Management 12Environmental 13

Specifications / Base

Base 14Thermal Performance 15Construction 16Fan Deck and Fan Cylinder 17Mechanical Equipment 18Fill, Louvers and Drift Eliminators 19Hot Water Distribution System 20Casing 20Access 20Cold Water Collection Basin 21Scope of Work 21

Specifications / Options

Control OptionsControl System 22Basin Heater 23Fan Motor Variable Speed Drive 23Marley Premium VFD System 24Vibration Limit Switch 25

Convenience and Safety OptionsStairway 26Plenum Walkway 26Ladder Extension 26Ladder Safety Cage 26Oil Level Sight Glass 27

Miscellaneous OptionsWood Cold Water Basin 27Redwood Components 27Hot Water Basin Covers 27Air Inlet Screens 27Low Noise Tower 28Watertight Partitions Between Cells 29Fire Safety Options 29

Page 15: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Marley / Sigma 1000/1200 Cooling Tower / 3

Sigma 1000/1200 towers are field-erected, general purpose crossflow wood cooling towers, designed to

serve normal air conditioning and refrigeration systems as well as medium sized industrial loads. They evolve from the crossflow concept of towers pioneered by Marley in 1938, and incorporate over 65 years of design advancements that our customers have found valuable. Sigma cooling towers represent the current state of the art in this cooling tower category.

This publication not only relates the language to use in describing an appropriate Sigma cooling tower—but also defines why certain items and features are important enough to specify with the intention of insisting upon compliance by all bidders. The left hand column of pages 15 through 29 provides appropriate text for the various specification paragraphs, whereas the right hand column comments on the meaning of the subject matter and explains its value.

Pages 15 through 22 indicate those paragraphs which will result in the purchase of a cooling tower which will

not only accomplish the specified thermal performance, but which will include normal operation and maintenance-enhancing accessories and features. It will also incorporate those standard materials which testing and experience has proven to provide best results in normal operating conditions.

Pages 23 through 29 provide some paragraphs intended to add those features, components, and materials that will customize the tower to meet the user's requirements.

Space does not permit definition and explanation of all of the possible options that can be applied to the Sigma. SPX Cooling Technologies realizes that you, the purchaser, must be happy with the tower's characteristics, and we are prepared to provide—or provide for—any reasonable enhancement that you are willing to define and purchase.

Your needs will become part of the continuing improvement of this Marley product line.

Page 16: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Marley / Sigma 1000 Cooling Tower / Engineering Data : Schematic 4

B

H

TOP OFFAN CYLINDER

BASE OFTOWER COLUMNS

TOP OFFAN DECK

W O

UT

TO O

UT

OF

TOW

ER

5"

CL COL.A BAYS @ 4'-0 = L

CLCOL.CL COL.5"

C DIA. FAN

PLAN

ENdwALLELEvAtioN

NotE1 Last number of model indicates number of cells. Change as

appropriate for your selection. Primary engineering data is per cell.

2 Fan hp is usually less than shown here.

3 Height shown is from base of tower columns to fan deck. Wood basin, if used, elevates tower 61⁄4". If concrete basin is used, subtract 1'-6" for height above top of basin curb.

Tower Model

GPMper cell

WidthW

LengthL

HeightH A B C Maximum

Motor hpStatic

Lift

1011 380 - 2140 21'-5" 8'-0" 11'-85⁄8" 2 3'-8" 84" 30 11.7'

1021 580 - 3220 21'-5" 12'-0" 11'-85⁄8" 3 3'-5" 96" 30 11.7'

1031 580 - 3220 23'-9" 12'-0" 11'-85⁄8" 3 3'-8" 120" 50 11.7'

1041 790 - 4300 26'-0" 16'-0" 11'-85⁄8" 4 4'-0" 144" 60 11.7'

Page 17: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Marley / Sigma 1000 Cooling Tower / Engineering Data : Piping 5

F M

INIM

UM

CL INLETCL COL.

CCL INLET

D TYP. MULTI-CELLPIPING SHOWN WITHDASHED LINES IS BY OTHERS

E

FACE OF A DIA.INLET PIPING

C LTO

WER

FA

N

C LTO

WER

FA

N

B DIA. FLOW CONTROLVALVE AND CROSS OVERPIPING

PLAN

G

BASE OFTOWER COLUMNS

C LIN

LET

ENdwALLELEvAtioN

NotE1 Use this bulletin for preliminary layouts only. Obtain current

drawings from your Marley sales representative.2 Pumping head contributed by the tower is static lift shown

on page 5. Actual pumping head will vary according to tower circulating GPM. Total pumping head will be furnished at time of proposal.

3 If your application requires a bypass system, recommended location is through tower endwall into plenum area. Review of the system by SPX Cooling Technologies engineering is required.

4 Marley piping terminates at face of a cast iron flat face flange which conforms to class 125 lb ASME B 16.1 specifications.

5 Supports on tower for crossover piping are part of the tower design. Do not support the riser’s dead load or operating load from the tower. Do not brace the riser’s seismic or thrust loads against the tower.

Tower Model

GPMper cell

Dimensions

A B C D E F G

1011 380 - 2140 10" 8" 4'-0" 8'-0" 8'-111⁄8" 11'-8" 12'-57⁄8"

1021 580 - 3220 10" 8" 6'-0" 12'-0" 8'-111⁄8" 11'-8" 12'-57⁄8"

1031 580 - 3220 10" 8" 6'-0" 12'-0" 10'-11⁄8" 12'-10" 12'-57⁄8"

1041 790 - 3240 10" 8" 8'-0" 16'-0" 11'-25⁄8" 13'-111⁄2" 12'-57⁄8"

1041 3241 - 4300 16" 12" 8'-0" 16'-0" 11'-55⁄8" 13'-111⁄2" 12'-87⁄8"

Page 18: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Marley / Sigma 1000 Cooling Tower / Engineering Data : Support 6

W O

VER

ALL

WID

TH O

F BA

SIN

C BAYS @ 4'-0 = L

EACH ADDITIONAL CELL = L

7 1/2" 7 1/2"

AIR INLET FACE

11 1/2"

A

C LC L

OVERALL LENGTH OF BASIN

CL CL

B

A

B

C LTO

WER

C LC L

AIR INLET FACE

END

WAL

L FA

CE

END

WAL

L FA

CE

OVERFLOW

SUMP

ADDITIONAL SUMPWHEN REQUIRED

11 1/2"

7/8"

AN

CH

OR

BOLT

HO

LES

7/8"

AN

CH

OR

BOLT

HO

LES

7/8" ANCHORBOLT HOLES

CL 7/8" ANCHORBOLT HOLES

7/8" ANCHORBOLT HOLES

PLAN

NotE1 Use this bulletin for preliminary layouts only. All

dimensions show anchor bolt locations. Obtain current drawings from your Marley sales representative before designing supports.

2 Other contractors or purchaser must design and erect supporting steel.

3 If steel beams are used, they must include 7⁄8" dia. holes to accept anchor bolts provided. If concrete beams or pilasters are used, 3⁄4" dia. anchor bolts embedded in the concrete must be provided by others.

4 Maintain no less than 2'-0" of clear space at endwall faces for construction purposes. Air inlet faces must have unobstructed air supply. Consult your Marley sales representative if nearby obstructions may interfere.

5 Operating weight is wet weight of tower and wood basin, including 6" of water in the collection basin. This is the recommended operating water level for all models.

Tower Model

Dimensions Operating Weight lb

W A B C L Single Cell Each Cell Add

1011 22'-1" 4'-10" 5'-3" 2 8'-0" 23620 20500

1021 22'-1" 4'-10" 5'-3" 3 12'-0" 32140 28980

1031 24'-5" 4'-10" 6'-5" 3 12'-0" 34440 31020

1041 26'-8" 4'-10" 7'-61⁄2" 4 16'-0" 47620 44000

Page 19: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Marley / Sigma 1000 Cooling Tower / Engineering Data : Concrete Basin 7

NotE1 Use this bulletin for preliminary layouts only. Do not use for

construction. Obtain current drawings from your Marley sales representative. Concrete basin design and construction are by other contractors or purchaser.

2 Operating weight is total wet operating weight of tower only, excluding water in concrete basin.

3 Maintain at least 2'-0" of clear space at endwall faces for construction purposes. Air inlet faces must have unobstructed air supply. Consult your Marley sales representative for recommendations if nearby obstructions may interfere.

4 Minimum basin depth is 1'-6". Maximum basin depth is 5'-6". Extended interior columns for deep basins are available as an option. Perimeter columns remain at 1'-6" below top of basin curb.

5 All anchor bolts complete with nut and washer must be furnished by others. Bolts must be 3⁄4"diameter with 2" all-thread projection.

6 Other contractors or purchaser must design, construct, and furnish sump and overflow to suit requirements.

TowerModel

Dimensions Operating Weigt lb

W A B Single Cell Each Cell Add

1011 21'-10" 2 8'-0" 15120 13500

1021 21'-10" 3 12'-0" 20160 18400

1031 24'-2" 3 12'-0" 21240 19500

1041 26'-5" 4 16'-0" 29020 27200

1’-6 1'-0 RECOMMENDED OPERATING WATER LEVEL

1’-6 1'-0 RECOMMENDED OPERATING WATER LEVEL

A BAYS @ 4'-0" = B PER CELL

6"

AIR INLET FACE CLCOL.CL COL.

6" MIN. 6" MIN. 6"

W IN

TO

IN O

F BA

SIN

WAL

LS

AIR INLET FACE

END

WAL

L FA

CE

END

WAL

L FA

CE

6" MIN.

6" MIN.

FLAt BAsiN sEctioN dEEP BAsiN sEctioN

PLAN

Page 20: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Marley / Sigma 1200 Cooling Tower / Engineering Data : Schematic 8

NotE1 Last number of model indicates number of cells. Change as

appropriate for your selection. Primary engineering data is per cell.

2 Fan hp is usually less than shown here.

3 Height shown is from base of tower columns to fan deck. Wood basin, if used, elevates tower 61⁄4". If concrete basin is used, subtract 1'-6" for height above top of basin curb.

B

H

TOP OFFAN CYLINDER

BASE OFTOWER COLUMNS

TOP OFFAN DECK

ENdwALLELEvAtioN

W O

UT

TO O

UT

OF

TOW

ER

5"

CL COL.A BAYS @ 4'-0 = L

CLCOL.CL COL.5"

C DIA. FAN

PLAN

Tower Model

GPMPer Cell

WidthW

LengthL

HeightH A B C Maximum

Motor hpStatic

Lift

1211 1050 - 5750 31'-2" 16'-0" 14'-51⁄8" 4 6'-0" 144" 60 14.5'

1221 1050 - 5750 33'-2" 16'-0" 14'-51⁄8" 4 7'-0" 168" 75 14.5'

1231 1320 - 7200 33'-2" 20'-0" 14'-51⁄8" 5 7'-0" 168" 75 14.5'

1241 1500 - 8650 33'-2" 24'-0" 14'-51⁄8" 6 7'-0" 168" 75 14.5'

1251 1500 - 8650 37'-2" 24'-0" 14'-51⁄8" 6 7'-0" 216" 100 14.5'

1261 1850 - 10100 37'-2" 28'-0" 14'-51⁄8" 7 7'-0" 216" 100 14.5'

Page 21: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Marley / Sigma 1200 Cooling Tower / Engineering Data : Piping 9

NotE1 Use this bulletin for preliminary layouts only. Obtain current

drawings from your Marley sales representative.2 Pumping head contributed by the tower is static lift shown

on page 9. Actual pumping head will vary according to tower circulating GPM. Total pumping head will be furnished at time of proposal.

3 If your application requires a bypass system, recommended location is through tower endwall into plenum area. Review of the system by SPX Cooling Technologies engineering is required.

4 Marley piping terminates at face of a cast iron flat face flange which conforms to class 125 lb. ASME B 16.1 specifications.

5 Supports on tower for crossover piping are are part of the tower design. Do not support the riser’s dead load or operating load from the tower. Do not brace the riser’s seismic or thrust loads against the tower.

TowerModel

GPMPer Cell

Dimensions

A B C D E F G

1211 1050 - 5750 16" 12" 8'-0" 16'-0" 13'-23⁄4" 16'-63⁄8" 15'-63⁄8"

1221 1050 - 5750 16" 12" 8'-0" 16'-0" 14'-23⁄4" 17'-63⁄8" 15'-63⁄8"

1231 1320 - 7200 16" 12" 10'-0" 20'-0" 14'-23⁄4" 17'-63⁄8" 15'-63⁄8"

1241 1500 - 7050 16" 12" 12'-0" 24'-0" 14'-23⁄4" 17'-63⁄8" 15'-63⁄8"

1241 7051 - 8650 20" 16" 12'-0" 24'-0" 14'-53⁄4" 17'-63⁄8" 15'-83⁄8"

1251 1500 - 7050 16" 12" 12'-0" 24'-0" 16'-23⁄4" 19'-63⁄8" 15'-63⁄8"

1251 7051 - 8650 20" 16" 12'-0" 24'-0" 16'-53⁄4" 19'-63⁄8" 15'-83⁄8"

1261 1850 - 7050 16" 12" 14'-0" 28'-0" 16'-23⁄4" 19'-63⁄8" 15'-63⁄8"

1261 7051 - 10100 20" 16" 14'-0" 28'-0" 16'-53⁄4" 19'-63⁄8" 15'-83⁄8"

G

BASE OFTOWER COLUMNS

C LIN

LET

F M

INIM

UM

CL INLETCL COL.

CCL INLET

D TYP. MULTI-CELL PIPING SHOWN WITHDASHED LINES IS BY OTHERS

E

FACE OF A DIA.INLET PIPING

C LTO

WER

FA

N

C LTO

WER

FA

N

B DIA. FLOW CONTROLVALVE AND CROSS OVERPIPING

PLAN

ENdwALLELEvAtioN

Page 22: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Marley / Sigma 1200 Cooling Tower / Engineering Data : Support 10

NotE1 Use this bulletin for preliminary layouts only. All

dimensions show anchor bolt locations. Obtain current drawings from your Marley sales representative before designing supports.

2 Note carefully anchor bolt location relative to beam orientation. See plan above.

3 Other contractors or purchaser must design and erect supporting steel.

4 If steel beams are used, they must include 7⁄8" dia. holes to accept anchor bolts provided. If concrete beams or pilasters are used, 3⁄4" dia. anchor bolts embedded in the concrete must be provided by others.

5 Maintain no less than 2'-0" of clear space at Endwall Faces for construction purposes. Air Inlet Faces must have unobstructed air supply. Consult your Marley sales representative if nearby obstructions may interfere.

6 Operating weight is wet weight of tower and wood basin, including 6" of water in the collection basin. This is the recommended operating water level for all models.

TowerModel

Dimensions Operating Weight lb

W A B C L Single Cell Each Cell Add

1211 31'-10" 8'-6" 7'-10" 4 16'-0" 61250 55900

1221 33'-10" 9'-6" 8'-10" 4 16'-0" 65530 60660

1231 33'-10" 9'-6" 8'-10" 5 20'-0" 77960 73110

1241 33'-10" 9'-6" 8'-10" 6 24'-0" 93790 88940

1251 37'-10" 11'-6" 10'-10" 6 24'-0" 101020 95740

1261 37'-10" 11'-6" 10'-10" 7 28'-0" 116260 111000

PLAN

W O

VER

ALL

WID

TH O

F BA

SIN

C BAYS @ 4'-0 = L

EACH ADDITIONAL CELL = L

7 1/2" 7 1/2"

AIR INLET FACE

OVERALL LENGTH OF BASIN

CL CL CLCOL.

B

A

C LTO

WER

C LAN

CH

OR

BOLT

C LAN

CH

OR

BOLT

C LAN

CH

OR

BOLT

C LAN

CH

OR

BOLT

C LAN

CH

OR

BOLT

ANCHOR BOLT ANCHOR BOLT

AIR INLET FACE

END

WAL

L FA

CE

END

WAL

L FA

CE

OVERFLOW

SUMP

ADDITIONAL SUMPWHEN REQUIRED

11 5/8"

11 5/8"6'

-9 3

/8"

4"

6'-9

3/8

"BA

SIN

Page 23: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Marley / Sigma 1200 Cooling Tower / Engineering Data : Concrete Basin 11

NotE1 Use this bulletin for preliminary layouts only. Do not use for

construction. Obtain current drawings from your Marley sales representative. Concrete basin design and construction are by other contractors or purchaser.

2 Operating weight is total wet operating weight of tower only, excluding water in concrete basin.

3 Maintain at least 2'-0" of clear space at endwall faces for construction purposes. Air inlet faces must have an unobstructed air supply. Consult your Marley sales representative for recommendations if nearby obstructions may interfere.

4 Minimum basin depth is 1'-6". Maximum basin depth is 5'-6". Extended interior columns for deep basins are available as an option. Perimeter columns remain at 1'-6" below top of basin curb.

5 All anchor bolts complete with nut and washer must be furnished by others. Bolts must be 3⁄4" diameter with 2" all-thread projection.

6 Other contractors or purchaser must design, construct, and furnish sump and overflow to suit requirements.

TowerModel

Dimensions Operating Weight lb

W A B Single Cell Each Cell Add

1211 31'-63⁄4" 4 16'-0" 39040 35910

1221 33'-63⁄4" 4 16'-0" 41960 39420

1231 33'-63⁄4" 5 20'-0" 49100 46560

1241 33'-63⁄4" 6 24'-0" 59020 56470

1251 37'-63⁄4" 6 24'-0" 61200 58530

1261 37'-63⁄4" 7 28'-0" 70900 68240

1’-6 1'-0 RECOMMENDED OPERATING WATER LEVEL

1’-6 1'-0 RECOMMENDED OPERATING WATER LEVEL

FLAt BAsiN sEctioN dEEP BAsiN sEctioN

A BAYS @ 4'-0" = B PER CELL

6"

AIR INLET FACE CLCOL.CL COL.

6" MIN. 6" MIN. 6"

W IN

TO

IN O

F BA

SIN

WAL

LS

AIR INLET FACE

END

WAL

L FA

CE

END

WAL

L FA

CE

6" MIN.

6" MIN.

PLAN

Page 24: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Marley / Sigma 1000/1200 Cooling Tower / Engineering Data: Energy Management 12

Cooling towers are usually selected to produce a specific cold water temperature at the higher summer-time wet-bulb temperatures. During the remainder of the year, the cooling tower is capable of producing much colder water. Unless your system will benefit from the coldest possible water tempera-ture, you should consider controlling cold water temperatures to higher levels. You’ll also save energy by using such control. See Marley Technical Report #H-001A, “Cooling Tower Energy and its Management”.

Always control leaving water temperature by manipulating the quantity of air that the fan moves through the tower. Vary-ing the quantity of water flow is not normally recommended and can be harmful in freezing weather. You can alternately start and stop single-speed motors to maintain water tempera-tures within an acceptable range. However, exceeding a total acceleration time of 30 seconds per hour can overheat the mo-tor, causing the insulation to fail. Limiting the number of motor starts, on the other hand, can produce significant variations in the temperature of the water delivered to the process.

Increased flexibility can simplify your operating procedures and save you money in the long run, both on operation and on maintenance. Here are two of the more popular options.

Two-Speed Motors

Two-speed motors improve operating flexibility by increas-ing the number of potential operating modes. Users in north-ern climates will find that the tower can carry winter loads at half-speed; reducing fan power requirements by 85+% during that time. Two-speed motors also help to control icing during wintertime operation. See Marley Technical Report #H-003, “Operating Cooling Towers During Freezing Weather”.

Normally, two-speed motors are provided in 1800/900 RPM, single winding configuration, which is the least expen-sive two-speed option. They are also available in other combi-nations including the more expensive double winding.

Variable Speed Control

Frequency modulation devices work well on induced draft, propeller fan cooling towers such as the Sigma. However, their design must include the capability to lock out any critical fan speeds and the very low fan speed ranges.

Marley VFD drive systems are designed to combine abso-lute temperature control with ideal energy management. The cooling tower user selects a cold water temperature and the drive system will vary the fan speed to maintain that tem-perature. Precise temperature control is accomplished with far less stress to the mechanical equipment components. The improved energy management provides fast payback. Indeed, many utilities offer generous rebates for users having installed VFD drives.

Page 25: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Marley / Sigma 1000/1200 Cooling Tower / Engineering Data: Environmental 13

Enclosures

Occasionally, cooling towers are located inside architectural enclosures for aesthetic reasons. Although Sigma towers adapt well to enclosures, a poorly designed enclosure can impair proper operation. An effective design includes gener-ous air inlet paths, with the tower’s fan cylinder discharge at or above the top of the enclosure. See Marley Technical Report #H-004, “External Influences on Cooling Tower Perfor-mance”, for design recommendations.

It may also be advisable to increase your design wet-bulb temperature by 1°F to compensate for potential recirculation initiated by the enclosure. You’ll benefit from discussing your project with your Marley sales representative.

Sound Control

A Sigma tower operating in an unobstructed environment will meet all but the most restrictive noise limitations – and will react favorably to natural attenuation. Where the tower will operate within an enclosure, the enclosure itself will usually have a damping effect on sound. Distance will also reduce sound – by about 5 dBA each time the distance is doubled. Where noise at a critical point is likely to exceed an acceptable limit, you have several options, listed below in ascending order of cost impact:

Noise concerns are often limited to nighttime, when ambi-ent noise levels are lower and neighbors are trying to sleep. You can usually resolve these situations by using two-speed motors in either 1800/900 or 1800/1200 RPM configuration; and operating the fans at reduced speed without cycling “after hours”. This relatively inexpensive solution pays for itself quickly in reduced energy costs.

Where the problem can exist at all times (such as near a hospital), the best solution is to oversize the tower so it can operate continuously at reduced (1200 or 900 RPM) motor speed. Typical sound reductions are 7 dB at 2/3 fan speed or 10 dB at 1/2 fan speed.

Extreme cases may require inlet and discharge sound at-tenuator sections; however, the static pressure loss imposed by attenuators may necessitate an increase in tower size. This is the least desirable approach because of its significant cost impact – and because it obstructs normal maintenance procedures.

Your Marley sales representative can help you meet your sound requirements.

System Cleanliness

Cooling towers are very effective air washers. Atmospheric dust able to pass through the relatively small louver openings will enter the circulating water system. Increased concentra-tions can intensify system maintenance by clogging screens and strainers; and smaller particulates can coat system heat transfer surfaces. In areas of low flow velocity (such as the cold water basin), sedimentary deposits can provide a breed-ing ground for bacteria.

In areas prone to dust and sedimentation, you should con-sider installing some means for keeping the cold water basin clean. Typical devices include side stream filters and a variety of filtration media.

You should also plan ahead to develop a consistent, ef-fective program of water treatment. A good water treatment program will help to assure long service life, while keeping your tower free of potentially harmful biological growths.

CAUTIONThe cooling tower must be located at such distance and direction to avoid the possibility of contaminated discharge air being drawn into building fresh air intake ducts. The purchaser should obtain the services of a Licensed professional Engineer or Registered Architect to certify that the location of the cooling tower is in compliance with applicable air pollution, fire and clean air codes.

Page 26: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications Specification Value

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Base 14

1.0 Base:

1.1 Furnish and install an induced-draft, crossflow-type, field-erected, wood-framed, PVC fill, industrial-duty cooling tower of _____ cell(s), as shown on Plans. The limiting overall dimensions of the tower shall be _____ wide, _____ long, and _____ high to the top of the fan cylinder. Total operating horse-power of all fans shall not exceed ____ hp, consisting of ___ @ _____ hp motor(s). Tower shall be similar and equal in all respects to Marley Model _______.

■ Your specification base establishes the type, configuration, base material, and physical limitations of the cooling tower to be quoted. During the planning and layout stages of your project, you will have focused your attention on a cooling tower selection that fits your space allotment, and whose power usage is accept-able. Limitations on physical size and total operating horsepower avoid the introduction of unforeseen operational and site-related influences. Specifying the number of cells, and the maximum fan hp/cell will work to your advantage. Crossflow towers are noted for the accessibility and maintainabil-ity of all operating components. The spacious interior provides easy access to fill, drift eliminators, all basin accessories—and is one of two primary accessways to the fan, Geareducer, and other mechanical components. At the fan deck level, the hot water distribution basins are easily inspected and cleaned—while the tower is operating, if you wish. The mechanical equipment can also be readily accessed from this level. Except for the cold water basin, no counterflow tower component requiring routine maintenance is as easily accessed. The confined areas that typify counterflow designs can make difficult work for maintenance personnel!

Page 27: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications Specification Value

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Base 15

2.0 Thermal Performance:

2.1 The tower shall be capable of cooling _____ GPM of water from ____ °F to _____ °F at a design entering air wet-bulb temperature of _____ °F. The cool-ing tower manufacturer shall guarantee that the tower supplied will meet the specified performance conditions when the tower is installed according to plans.

2.2 The purchaser will arrange for an on-site thermal performance test, to be conducted in the presence of the manufacturer and owner, and under the supervision of a qualified, disinter-ested third party in accordance with CTI (Cooling Technology Institute) ATC-105 standards during the first full year of operation. If the tower fails to per-form within the limits of test tolerance, then the cooling tower manufacturer will install additional cells and/or make such corrections as are agreeable to the owner and shall pay for the cost of a retest. If the tower still fails to per-form as specified, then the manufac-turer shall make such reimbursements as are appropriate and agreeable to the owner to compensate for the perfor-mance deficiency.

■ Your reason for purchasing a cooling tower is to obtain a con-

tinuing flow of cooled water as defined in the first paragraph at left. If the tower that you purchase is incapable of performing as specified, then you will not have received full value for your money. Bear in mind that the size—and cost—of a cooling tower var-ies directly with its true thermal capability. This paragraph is intended to protect you against either intentional or inadvertent under sizing of the tower by the manufacturer. Judging the level of performance of a cooling tower on critical processes is never easy, and the potential risk of a non-performing cooling tower usually causes the requirement for a mandatory acceptance test to be very desirable. Your contract with the successful bidder should establish the acceptable remedies for missed performance, which might include: • The addition of one or more cells of tower, as necessary, to

bring the cooling tower to the specified level of performance. This is usually limited to the scope of work as defined in the specs, which means that you (the owner) will have to pay for the additional basin, wiring, starters, piping, etc.

• The reimbursement of a portion of the total contract price equal to the percentage deficiency in performance.

Under no circumstances should you allow the manufacturer to re-pitch the fans to increase motor brake horsepower above that shown in the proposal. That creates additional operating costs that will continue for the life of the tower—and imposes no pen-alty on the manufacturer.

Typical cooling tower performance curve.

55°

50° 55° 60° 65° 70° 75° 80°

5°F RANGE10°F RANGE15°F RANGE

60°

65°

70°

75°

CO

LD

WA

TE

R T

EM

P. (

°F)

WET BULB TEMP. (°F)

80°

85°

90°

95°

Page 28: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications Specification Value

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Base 16

3.0 Construction:

3.1 The tower shall be capable of with-standing water having a pH of 6.5 to 8.0; a chloride content (NaCl) up to 750 ppm; a sulfate content (SO4 ) up to 1200 ppm; a sodium bicarbonate con-tent (NaHCO3) up to 200 ppm; a cal-cium content (CaCO3) up to 800 ppm; silica (SiO2) up to 150 ppm; and design hot water temperatures up to 120°F. The circulating water will contain no oil, grease, fatty acids, or organic sol-vents.

3.2 The structural framework of the tower shall be Douglas Fir, designed in accor-dance with CTI STD-114. Nylon shear plates shall be utilized to transmit loads at critical joints, and all fasteners shall be in accordance with CTI STD-119. Basic design criteria shall be 30 psf wind load and 5%g seismic load.

3.3 All wood components shall be treated after fabrication with chromated cop-per arsenate (CCA) by the full-cell process to a chemical retention of 0.4 lbs/ft3.

3.4 Structural columns and diagonals shall be 4"x4". Framing girts may be 2"x4", except for those supporting the hot water basins and fill. Those girts shall be 2"x6" minimum, located both sides of the support columns.

3.5 Multicell towers shall include treated Douglas Fir plywood partitions between cells in the plenum area. Partitions shall extend the full height of the tower from the base of fill to the underneath side of the fan deck.

3.6 Column lines shall be on no greater than 4'-0" longitudinal centers, and the base of all perimeter columns shall be firmly anchored to galvanized steel base plates. Framing joints shall be made with 1/2" diameter or larger series 300 stainless steel machine bolts, nuts and washers.

■ The limiting water quality values indicated are those which are acceptable for the normal materials of construction specified. If water of more aggressive quality is anticipated please change hardware material requirement to 300 Series stainless steel, as indicated below and following.

Cooling Technology Institute standards take into account the hot, humid environment in which a cooling tower normally operates. This environment can render the limits of customary construction standards inadequate for cooling tower design. The importance of shear plates is discussed at length in Marley Difference, “Item S-3”. Ask your Marley representative for a copy. See notes on page 27 regarding the use and availability of red-wood. Specification of minimum member sizes assures that all offerings will conform to an industrial level of construction. Multicell towers must have plenum partitions between cells. Otherwise, air will be induced downward through an inoperative fan, bypassing the fill entirely. Without these partitions, part-load or off-season operation of the tower would be completely unsat-isfactory.

Page 29: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications Specification Value

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Base 17

4.0 Fan Deck and Fan Cylinder:

4.1 The fan deck shall act as a working platform for maintenance personnel. It shall be fabricated of no less than 1" thick, 7 ply, exterior grade, treated Douglas Fir plywood, and shall be designed for a uniform live load of 60 psf or a concentrated load of 600 pounds.

4.2 Fan cylinders shall be molded FRP. They shall be anchored to the fan deck structure to provide a consistently stable operating shroud for the fan. Fan cylinders less than 72" in height shall be equipped with a heavy gauge, removable, hot-dip galvanized steel fan guard for the protection of operating personnel.

■ The indicated design values for framing and decking not only give you assurance that the tower can withstand long term operation in a hostile environment—but that it will accept many years of inspection and maintenance traffic by your operating personnel. Fiberglass-reinforced polyester fan cylinders provide the close tip clearances and smooth airflow contour necessary for good fan performance. The inert, noncorroding nature of FRP assures that these characteristics will persist. Even in aggressive water conditions, the heavy construction of the fan guard normally precludes the need for stainless steel.

Diagonal ConnectorDiagonal and Column Anchorage

Page 30: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications Specification Value

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Base 18

5.0 Mechanical Equipment:

5.1 Fan(s) shall be propeller-type, incorpo-rating heavy duty blades of cast alumi-num or high strength, inert composite material. Blades shall be individually adjustable and replaceable. Fan(s) shall be driven through a rightangle, indus-trial-duty, oil-lubricated, geared speed reducer. Speed reducers employing pulleys and belts will not be accepted.

5.2 Motor(s) shall be ____ hp maximum, TEFC, 1.15 service factor, and specially insulated for cooling tower duty. Speed and electrical characteristics shall be 1800 (1800/900) RPM, single winding, ___ phase, ___ hertz, ___ volts.

5.3 Motor shall be located outside the fan

cylinder at the fan deck, and shall be connected to the speed reducer by a tubular stainless steel, dynamically balanced driveshaft equipped with neo-prene flexible coupling elements.

5.4 A galvanized oil gauge and drain line shall extend from the gear reducer to the vicinity of the motor, and shall be equipped with a dip stick for oil level measurement.

5.5 The complete mechanical equipment

assembly for each cell shall be sup-ported by a rigid, unitized support that resists misalignment between the motor and the gear reducer. Support shall be heavy-wall tubular steel, to which heavy plate platforms for the motor and gear reducer have been welded and the assembly shall be hot-dip galvanized after fabrication. The support assembly shall also provide an inlet connection for incoming hot water, and shall serve as a crossover pipe to deliver water to both sides of the tower.

5.6 The mechanical equipment assembly shall be warranted for no less than five (5) years. This warranty shall cover the fan(s), speed reducers, driveshafts and couplings, and the unitized supports.

■ Standard fan drives of other manufacturers may use V-belts. Considering the size of fans involved—and the horsepowers applied—this is not good design practice. Geareducer® drive is far more reliable and trouble free, and is currently offered as an option by at least two other cooling tower manufacturers. Unless otherwise specified, motor speed will be 1800 RPM in 60 Hertz areas and 1500 RPM in 50 Hertz areas. If you prefer the operating flexibility of two-speed operation, please specify the RPM to be 1800/900 (1500/750 in 50 Hertz regions). The driveshaft turns at the motor speed and is, therefore, most sensitive to operational imbalance. Stainless steel manufacture assures that the driveshaft will not become unbalanced as a result of corrosion. The extended oil line to an external dip stick provides a conve-nient means of checking the level of oil in the Geareducer. As indicated on page 27, a sight glass is also available in lieu of the dip stick. Fans of the size used on large cooling towers are applied at speeds and horsepowers that generate considerable torque—and structural tubular steel resists this torque very effectively. The Marley torque-tube assures that all of the mechan-ical equipment remains aligned, and that the rotating fan is prop-erly positioned within the fan cylinder. Hot-dip galvanizing after fabrication assures that all steel surfaces will be heavily coated with zinc for long-term protection against corrosion. Even in aggressive water conditions, the heavy construction of the unitized support normally precludes the need for stainless steel. The value of a 5 year mechanical equipment warranty speaks for itself. Except for the motor, all of the mechanical equipment on a Marley tower is made by SPX Cooling Technologies. Cooling tower vendors who purchase commercial fans, gear boxes, driveshafts, etc. may require that you deal directly with those commercial suppliers for warranty satisfaction.

Page 31: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications Specification Value

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Base 19

6.0 Fill, Louvers and Drift Eliminators:

6.1 Fill shall be film-type, 15 mil thick, thermoformed PVC, with louvers formed as part of each fill sheet. Fill shall be suspended from stainless steel structural tubing supported from the upper tower structure, and shall be elevated above the floor of the cold water basin to facilitate cleaning. Air inlet faces of the tower shall be free of water splash-out.

6.2 Drift eliminators shall be PVC, triple-pass, and shall limit drift losses to no more than 0.010% of the design GPM flow rate.

■ Louvers integral with the fill keep the flowing water within the confines of the fill. The sep-arate external louvers used by others permit water to escape the fill and form ice or produce an unsightly situation adjacent to the tower. If you plan to use your tower in the wintertime, particularly for free cooling, integral louvers will put your operating concerns to rest. Vertical blade-type eliminators, as well as misdirected cellular types, cause much of the fan power to be wasted in turn-ing the horizontal flow of air vertical for its exit through the fan cylinder. This power is, of course, not available for contribution to thermal performance. Drift rate varies with design water loading and air rate, as well as drift eliminator depth and number of directional changes. The indicated rate of 0.010% or less is easily achievable without pre-mium cost. If a lower rate is required, please discuss with your Marley sales representative.

LouverSection

Drift EliminatorSection

Fill Section

Page 32: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications Specification Value

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Base 20

7.0 Hot Water Distribution System:

7.1 The mechanical equipment support/crossover pipe shall deliver water to two open hot water basins per cell at the fan deck elevation. Water shall exit these basins to the fill by gravity through metering orifice-type polypro-pylene nozzles situated in the basin floor. Nozzles shall be easily removable and replaceable.

7.2 Heavy-duty, industrial grade flow-control valves shall be provided at the inlet to each basin. These valves shall permit both flow balancing and maintenance shut-off to selected cells, or portions of cells. Valves shall have machined cast iron bodies, with stain-less steel operating stems, and heavy-duty locking handles.

8.0 Casing:

8.1 Tower endwalls shall be cased with ribbed FRP panels, lapped and sealed to prevent leakage. Tower corners shall be finished with FRP corner rolls.

9.0 Access:

9.1 Single cell towers shall include a 33" wide by 61" high molded FRP access door in one endwall casing for access to the interior of the tower. Casing access door shall be hinged and equipped with a latch operable from both inside and outside the tower. Multicell towers shall have an access door in both endwalls, and shall include a lift-out door in each transverse parti-tion to give free access through the tower.

9.2 The top of the tower shall be equipped with a sturdy 42" high wood guardrail system; top rails, intermediate rails, and toeboards; conforming to OSHA standards. Posts shall be 4"x4", on no greater than 8'-0" centers. Guardrails shall be 2"x4". Single 2"x4" top rail will be acceptable up to 6'-0" span. Above 6'-0" span, an additional 2"x4" cap strip shall be included.

■ Gravity-flow distribution basins are a feature of crossflow type towers. These basins are out where they can be easily inspect-ed—even maintained—while the tower is in operation. Spray systems of counterflow towers, sandwiched between the top of the fill and the drift eliminators, are extremely awkward to access and maintain. Marley flow-control valves remain serviceable for the life of the tower, and provide a continuing means of flow-regulation between hot water basins—and between cells of multicell towers as well. Towers without valves do not provide this valuable oper-ating flexibility.

■ The access doors on other towers may be unreasonably small. Specifying the size of the door will cause those bidders to take exception, alerting you to a potential maintenance headache. Good maintenance practice requires periodic access to the top of the tower to inspect the distribution basins, as well as the struc-tural integrity of the fan deck, fan cylinder, and fan—especially the fan blade securing hardware. And there are no induced-draft cool-ing tower designs that are immune to this need!

Page 33: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications Specification Value

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Base 21

9.3 Each endwall of the tower shall be equipped with a 20" wide aluminum vertical ladder, through-bolted to the endwall structure. Ladder shall rise from the cold water basin level to the top of the fan deck guardrail, and shall be designed and installed in confor-mance with OSHA standards.

10.0 Cold Water Collection Basin:

10.1 The cold water collection basin shall be of poured-in-place concrete, provided under scope of work done by others. The concrete basin design shall be based upon certified loads and dimen-sions provided by the cooling tower manufacturer.

11.0 Scope of Work:

11.1 The cooling tower manufacturer shall be responsible for the design, fabrica-tion, and delivery of materials to the project site, and for the erection of the tower over supports provided by others. Unless otherwise specified, all external piping, pumps, controls, and electrical wiring will be outside the cooling tower manufacturer's scope of work.

For the comfort and safety of your operat-ing personnel, the Sigma tower includes a ladder and guardrail of the quality and design indicated—and we strongly recommend that you require it of all bidders! Portable ladders and other “make-do” access means are inappro-priate for equipment of this size and complexity.

■ This basic specification assumes that the tower will be erected over a concrete basin at grade level. If the tower is to be installed on an elevated supporting platform, the plywood cold water collection basin indicated on page 17 should be included in the specifications.

■ Please be clear in your specifications and inquiry documents regarding the full scope of work expected. That will help assure that your bid comparisons will be made on as equal a basis as possible—and will help to avoid any misunder-standings during the execution and implementation of the contract.

Page 34: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Options 22

Specification Value

Control Options

Control System:

5.7 Add the following paragraph in the Mechanical Equipment section: Each cell of the cooling tower shall be equipped with a UL listed control system in a NEMA 3R or 4X outdoor enclosure capable of controlling single-speed or two-speed motors as required, and designed specifi-cally for cooling tower applications. The panel shall include a main fused disconnect with an external operating handle, lockable in the off position for safety. Across-the-line magnetic start-ers or solid state soft-start starters as required shall be controlled with a thermostatic or solid state tempera-ture controller. Door mounted selector switches shall be provided to enable automatic or manual control and wired for 120VAC control. Control circuit to be wired out to terminal blocks for field connection to a remote vibration switch and for access to extra 120VAC 50VA control power, overload trip alarms and remote temperature control devices. The temperature controller shall be adjustable for the required cold water temperature. If a thermostatic controller is used it shall be mounted on the side of the tower with the tem-perature sensing bulb installed in the cold water basin using a suspension mounting bracket. If a solid state tem-perature controller is used the control-ler will be door mounted on the control panel. The temperature controller will display two temperatures, one for outgoing water and the other for set point. Water temperature input shall be obtained using a three-wire RTD with dry well in the outlet water piping and wired back to the solid state tempera-ture controller in the control panel.

■ If it is your opinion that the control system for the cooling tower should be part of the tower manufacturer’s responsibility, we are in wholehearted agreement with you. Who better to determine the most efficient mode and manner of a tower’s operation—and to apply a system most compatible with it—than the designer and manufacturer of the cooling tower?

Page 35: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Options 23

Specification Value

Basin Heater:

10.2 Add the following paragraph in the Cold Water Basin section: Provide a system of electric immersion heat-ers and controls for each cell of the tower to prevent freezing of water in the collection basin during periods of shutdown. The system shall consist of one or more stainless steel elec-tric immersion heaters installed in a galvanized steel heat shield provided in the floor of the basin. A NEMA 4 enclosure shall house a magnetic contactor to energize heaters; a trans-former to provide 24 volt control circuit power; and a solid state circuit board for temperature and low water cutoff. A control probe shall be located in the basin to monitor water level and tem-perature. The system shall be capable of maintaining 40°F water temperature at an ambient air temperature of __ °F. Wiring of the heaters and controls shall be the responsibility of the purchaser.

Fan Motor Variable Speed Drive:

Marley All Weather ACH550 System

6.4 Add the following paragraph in the Mechanical Equipment section when VFD is used with customers Building Management System: A complete UL listed Variable Speed Drive system in a NEMA 1 indoor, NEMA 12 indoor or NEMA 3R outdoor enclosure shall be provided. The VFD shall use PWM technology with IGBT switching and integrated bypass design. VFD out put switching shall not cause mechanical issues with gearbox teeth or drive shafts. The VFD shall catch a fan spinning in the reverse direction without tripping. The panel shall include a main discon-nect with short circuit protection and external operating handle, lockable in the off position for safety. The VFD system shall receive a speed reference signal from the Building Management System monitoring the tower fluid temperature. As an option to receiving the speed reference signal from a building manage-ment system, the drive must have the capability to receive a 4-20 ma tempera-ture signal from an RTD transmitter. The VFD shall have an internal PI regulator

■ The basin heater components described at left represent our rec-ommendation for a reliable automatic system for the prevention of basin freezing. They are shipped separately for installation at the jobsite. If aggressive operating conditions are anticipated, change “galva-nized” in paragraph 10.2 to “Series 300 SS”. The ambient air temperature that you fill in should be the lowest 1% level of winter temperature prevalent at site. Ask for Marley drawing 92-3627.

■ Marley VFD drive systems are designed to combine absolute temperature control with ideal energy management. The cool-ing tower user selects a cold water temperature and the drive system will vary the fan speed to maintain that temperature. Precise temperature control is accomplished with far less stress to the mechanical equipment components. The improved energy management provides fast payback. Indeed, many utilities offer generous rebates for users having installed VFD drives.

Page 36: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Options 24

Specification Value

to modulate fan speed maintaining set point temperature. The drive's panel dis-play shall be able to display the set-point temperature and cold-fluid temperature on two separate lines. The bypass shall include a complete magnetic bypass circuit and with capability to isolate the VFD when in the bypass mode. Transfer to the bypass mode shall be manual in the event of VFD failure. Once the motor is transferred to the by-pass circuit the fan motor will run at constant full speed. The bypass circuit will not modulate ON and OFF based on fluid temperature. The application must be able to handle very cold fluid temperatures while the VFD is in a by-pass mode. Operator controls shall be mounted on the front of the enclosure and shall consist of start and stop control, bypass/VFD selection, Auto/Manual selections, manual speed control. To prevent heating problems in the fluid cooloer fan motor and to assure proper gear reducer lubrication the VFD system shall de energize the motor once 25% motor speed is reached and cooling is no longer required. The fluid cooler manu-facturer shall supply VFD start-up assis-tance. Tower vibration testing throughout the speed range is required to identify and lockout any natural frequency vibra-tion levels which may exceed CTI guide-lines.

Marley Premium VFD System

6.4 Add the following paragraph in the Mechanical Equipment section when VFD is used as a stand alone system: A complete UL listed Variable Speed Drive system in a NEMA 12 indoor or NEMA 3R outdoor enclosure shall be provided. The VFD shall use PWM technology with IGBT switching and integrated bypass design. VFD output switching shall not cause mechanical issues with gearbox teeth or drive shafts. The VFD shall catch a fan spinning in the reverse direction without tripping. The panel shall include a main disconnect with short circuit protection and external operating handle, lockable in the off posi-tion for safety. The system shall include a solid state, PI temperature controller to adjust frequency output of the drive in response to the tower fluid tempera-ture. The temperature of the fluid and

Page 37: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Options 25

Specification Value

set point shall be displayed on the door of the control panel. The bypass shall include a complete magnetic bypass circuit with capability to isolate the VFD when in the bypass mode. Transfer to the bypass mode shall be automatic in the event of VFD failure or for specific trip conditions allowing safe transfer of utility voltage to the motor. Automatic bypass with an earth ground condition is not allowed. The bypass contactor shall be cycled on and off while operat-ing in bypass, to maintain the set-point temperature of the cold water. The drive design shall be operated as a stand-alone system without the need for a BMS sys-tem. Operator controls shall be mounted on the front of the enclosure and shall consist of start and stop control, bypass/VFD selector switch, Auto/Manual selec-tor switch, manual speed control, and solid-state temperature controller. An emergency bypass selector switch inter-nal to the panel allowing the fluid cooler fan motor to be run at full speed shall be furnished. To prevent heating problems in the fluid cooler fan motor and to assure proper gear box lubrication the VFD sys-tem shall de energize the motor once 25% motor speed is reached and cool-ing is no longer required. The VFD shall include de-icing logic with auto canceling and adjustable time. Speed in De-Ice mode shall not exceed 50% motor speed. The fluid cooler manufacturer shall supply VFD start-up assistance. Tower vibration testing throughout the speed range is required to identify and lockout any natural frequency vibration levels which may exceed CTI guidelines.

Vibration Limit Switch:

5.8 Add the following paragraph in the Mechanical Equipment section: A single-pole, double-throw vibration limit switch in a NEMA 4 housing shall be installed on the mechanical equipment support for wiring into the owner’s control panel. The purpose of this switch will be to interrupt power to the motor in the event of excessive vibra-tion. It shall be adjustable for sensitiv-ity, and shall require manual reset.

■ Unless specified otherwise, a Marley M-5 vibration switch will be provided. The requirement for manual reset assures that the tower will be visited to determine the cause of excessive vibration.

Page 38: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Options 26

Specification Value

Convenience and Safety Options

Stairway:

9.3 Replace paragraph 9.3 with the fol-lowing: A 30" wide, column supported, 45° stairway with 8" rise and run of treated Douglas Fir shall be provided at the tower endwall rising from grade (roof) to the fan deck elevation. Stair columns shall be 4x4. Guardrails shall be 2"x4". The upper guardrail shall have an eased edge for the protection of operating personnel. Stairway founda-tion shall be by others, designed in accordance with drawings provided by the cooling tower manufacturer. The stairway shall conform to OSHA stan-dards.

Plenum Walkway:

9.1 Add the following to the end of this paragraph: Provide a 30" wide walkway extending from one endwall access door to the other through the length of the tower. Walkway shall be constructed of treated Douglas Fir, and the top of the walkway shall be above the cold water basin overflow level. If the cold water basin is deeper than 4'-0", the walkway shall be equipped with guardrails.

Ladder Extension:

9.4 Add the following paragraph in the Access and Safety section: Provide a ladder extension for connection to the base of the ladder attached to the tower casing. This extension shall be long enough to rise from the roof (grade) level to the base of the tower. Anchorage and lateral bracing of the ladder extension shall be by others.

Ladder Safety Cage:

9.3 Add the following to the end of this paragraph: A heavy gauge galvanized steel safety cage shall surround the ladder, extending from a point approxi-mately 7'-0" above the base of the ladder to the top of the guardrail sur-rounding the fan deck.

■ Although they are not neces-sary for routine operation and maintenance, stairways do provide a safe and comfort-able means of access to the top of the tower that is often overlooked in the initial cool-ing tower purchase. They are designed in straight-run or double-back configurations to accommodate your site requirements.

■ This option permits freedom of movement for inspection or main-tenance within the tower without the need for wading boots or tower drainage. It also helps prevent maintenance personnel from damaging submerged accessories in the cold water basin (such as screens, probes, basin heaters, etc.).

■ Many towers are installed such that the base of the tower is 2’-0” or more above the roof or grade level. This makes it difficult to get up to the base of the attached ladder. The ladder extension alleviates this problem. Marley ladder extensions are available in standard 5’-0” and 11’-0” lengths, and will be field-cut to fit.

■ To meet OSHA guidelines, towers whose fan decks are 20'-0" or more above roof or grade, and which are equipped with lad-ders, are required to have safety cages sur-rounding the ladders.

Page 39: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Options 27

Specification Value

Oil Level Sight Glass:

5.4 Replace paragraph 5.4 with the fol-lowing: A galvanized oil gauge and drain line shall extend from the gear reducer to the vicinity of the motor, and shall be equipped with a bronze-bodied oil level sight glass.

Miscellaneous Options

Wood Cold Water Basin:

10.1 Replace paragraph 10.1 with the fol-lowing: Include a cold water collection basin constructed of pressure treated Douglas Fir plywood. Basin floor shall be 3/4" thick 5-ply, supported by 6" deep joists on 2'-0" centers. Basin sides shall be 1" thick, 7 ply. The basin floor shall lock into a dado groove in the sides to form a watertight seal. A depressed, side outlet sump of either FRP or hot-dip galvanized steel having a 1/4" thick faceplate drilled for a stan-dard class 125 ASME flange connec-tion will be included. An appropriately sized (4" diameter or larger) galvanized standpipe overflow shall be provided. The standpipe shall be removable for flush-out cleaning of the basin. A float-operated, mechanical makeup valve shall also be included, installed adja-cent to the endwall access door.

Redwood Components:

Hot Water Basin Covers:

7.3 Add the following paragraph in the Hot Water Distribution System section: The distribution basins shall include treated Douglas Fir plywood covers at least 3/4" thick. These covers shall be designed to withstand 60 psf live load, and shall be easily removable for maintenance.

Air Inlet Screens: 6.3 Add the following paragraph to the

Fill, Louvers and Drift Eliminators Section: The air inlet faces of the tower shall be covered by 1" mesh hot-dip galvanized welded wire screens. Screens shall be mounted in galvanized steel U-edging and shall be removable.

■ The oil level sight glass is a convenience item that is preferred by many users. The same purpose is, of course, served by either the dip stick or the sight glass.

■ Marley basins are used to permit the installation of towers on elevated platforms or foundations. The cross section drawing on page 4 shows the relationship of the optional basin, sump and overflow to a typical steel I-beam support platform.

■ Most of the wood components in the tower are available of pres-sure treated redwood. However, redwood lacks the strength of Douglas Fir, which may require structural modifications of the tower. Please discuss the available redwood options with your Marley sales representative.

■ These covers are designed to keep leaves and debris out of the circulating water system. They also serve to suppress algae for-mation by shielding the incoming hot water from direct sunlight.

■ In wooded or windy areas, these screens help to keep leaves or blowing debris out of the cooling tower and circulating water system.

Page 40: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Options 28

Specification Value

Low Noise Tower:

1.1 Add the following at the end of this paragraph: The cooling tower shall be quiet operating, and shall produce an overall level of sound no higher than ____ dBA at the critical location indicated on the Plans.

■ Sound produced by a Sigma Steel tower operating in an unob-structed environment will meet all but the most restrictive noise limitations – and will react favorably to natural attenuation. Where the tower has been sized to operate within an enclosure, the enclosure itself will have a damping effect on sound. Sound also declines with distance – by about 5 or 6 dBA each time the distance doubles. Where noise at a critical point is likely to exceed an acceptable limit, you have several options – listed below in ascending order of cost impact: • Where only a slight reduction in noise will satisfy — and the source of concern is in a particular direction — merely turning the tower may be the answer. Less sound emanates from the cased face of the tower than does from the air intake face.

• In many cases, noise concerns are limited to nighttime, when ambient noise levels are lower and neighbors are trying to sleep. You can usually resolve these situations by using two-speed motors in either 1800/900 or 1800/1200 RPM configura-tion; and operating the fans at reduced speed without cycling “after hours”. (The natural nighttime reduction in wet-bulb tem-perature makes this a very feasible solution in most areas of the world, but the need to avoid cycling may cause the cold water temperature to vary significantly.)

• Variable speed drives automatically minimize the tower's noise level during periods of reduced load and/or reduced ambient without sacrificing the system's ability to maintain a constant cold water temperature. This is a relatively inexpensive solution, and can pay for itself quickly in reduced energy costs.

• Where noise is a concern at all times (for example, near a hos-pital), the best solution is to oversize the tower so it can operate continuously at reduced (1200 or 900 RPM) motor speed even at the highest design wet-bulb temperature. Typical sound reduc-tions are 7 dBA at 2/3 fan speed or 10 dBA at 1/2 fan speed, but larger reductions are often possible.

• Extreme cases may require inlet and discharge sound attenu-ator sections; however, the static pressure loss imposed by attenuators may necessitate an increase in tower size. This is the least desirable approach because of the significant cost impact – and because of the obstruction to normal maintenance procedures.

Your Marley representative can help you meet your sound requirements.

Page 41: Marley Sigma 1000/1200 Cooling Tower - Bid on Equipmentbidonequipment.info/s/SPX - MARLEY Sigma 1000,1200 Cooling... · cooling tower components. All Marley components are designed

Specifications

Marley / Sigma 1000/1200 Cooling Tower / Specifications: Options 29

Specification Value

Watertight Partitions Between Cells: 3.5 Replace the last sentence in this

paragraph with the following: Partitions shall be 3/4" x 5-ply, factory-fabricated, grooved and splined treated Douglas Fir plywood sheets, installed and sealed watertight to permit inde-pendent cell operation.

Fire Safety Options:

■ In addition to the normal partition function of preventing air bypass (page 17), this option allows you to use each partitioned cell of your tower independently. This is valuable where a single multicell tower is serving several separate systems—or where winter operation may require less than full tower capability.

■ Occasionally, critical processes or local codes may require you to install a fire-protection sprinkler system on a wood tower—or pay higher insurance premiums—or both. Our first recommendation in such a case would be for you to consider using a Sigma Steel cooling tower, as listed in the Factory Mutual Approval Guide. Another alternative that could be acceptable to your insurance carrier, and which you may wish to evaluate, would be to make your Sigma tower as fire resistant as possible. This can be done by any or all of the following measures:

• FRP casing having a flame spread rating of 25 or less. (Para. 8.1)

• Fan cylinders of fire-retardant FRP having a flame spread rating of 25 or less. (Para. 4.2)

• 1⁄4" thick fireproof fiber reinforced cement overlay over the fan deck—and will provide FRC overlaid distribution basin covers. (Para. 4.1)

• 3⁄4" thick plywood partitions both sides of the column line between cells to achieve a fire rating of at least 30 minutes. (Para. 3.5 and this page.)