Market Performance and Planning Forum...Market Performance and Planning Forum May 11, 2011....
Transcript of Market Performance and Planning Forum...Market Performance and Planning Forum May 11, 2011....
Market Performance and Planning
Forum
May 11, 2011
Objective: Enable dialogue on implementation
planning and market performance issues
• Review key market performance topics
• Share updates to 2011-2012 release plans, resulting
from stakeholders inputs
• Provide information on specific initiatives
– to support Market Participants in budget and resource
planning
• Focus on implementation planning; not on policy
• Clarify implementation timelines
• Discuss external impacts of implementation plans
• Launch joint implementation planning process
Slide 2
Agenda
Slide 3
TIME TOPIC PRESENTER9:00 -9:15 Overview, Objectives Mercy Parker Helget
9:15-11:00 Market Performance and Quality Update Mark Rothleder
11:00-11:30 Policy Update Greg Cook
11:30 – 12:00 Technical Update
- MSG
- LMPM Enhancements Impact Assessment
Li Zhou
12:00 –1:00 Lunch – all are welcome to use the new ISO cafeteria
1:00 – 2:30
2:30 – 3:00
Release Plan Update
- Pre-Summer 2011 Releases
- Fall 2011 Release
- Generation of Bids for NRS-RA / Subset of Hours
- GMC Rate Structure Change
- Regulation Energy Management
- SLIC to SIBR Interface
Ongoing Data Release
Outage Management System – Phase 3
Janet Morris
Jami Long
Market Performance and Quality Update
Mark Rothleder, Director
Market Analysis & Development
Slide 4
Slide 5
Price volatility and market convergence
MIP Gap performance
Convergence Bidding
RT Energy Offset
MSG (There are currently 15 MSG resources)
Exceptional Dispatch
Bid Cost Recovery
Price volatility and market convergence (1)
Slide 6
0.0%
0.5%
1.0%
1.5%
2.0%
2.5%
3.0%
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
2010 2011
Pe
rce
nt
of
real
-tim
e in
terv
als
$250 to $500 $501 to $750 $751 to $1000 > $1000
$500 bid cap $750 bid cap
Price volatility and market convergence (2)
Slide 7
$0
$10
$20
$30
$40
$50
$60
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2010 2011
Pri
ce ($
/MW
h)
Day-ahead Hour-ahead Real-Time
In March additional actions taken improve convergence
of conditions between the HASP and RTD prices.
Slide 8
0
0.5
1
1.5
2
2.5
3
$0
$1
$2
$3
$4
$5
$6
$7
$8
$9
$10
3/2
/20
11
3/4
/20
11
3/6
/20
11
3/8
/20
11
3/1
0/2
01
1
3/1
2/2
01
1
3/1
4/2
01
1
3/1
6/2
01
1
3/1
8/2
01
1
3/2
0/2
01
1
3/2
2/2
01
1
3/2
4/2
01
1
3/2
6/2
01
1
3/2
8/2
01
1
3/3
0/2
01
1
4/1
/20
11
4/3
/20
11
4/5
/20
11
4/7
/20
11
4/9
/20
11
4/1
1/2
01
1
4/1
3/2
01
1
4/1
5/2
01
1
4/1
7/2
01
1
4/1
9/2
01
1
4/2
1/2
01
1
4/2
3/2
01
1
4/2
5/2
01
1
4/2
7/2
01
1
4/2
9/2
01
1
5/1
/20
11
5/3
/20
11
5/5
/20
11
Ave
rage
Nu
mb
er o
f Sp
ike/
Day
Ave
rge
HA
SP-R
T P
rice
Dif
fere
nce
($/M
wh
)
30-Day Rolling Average Price Volatility and HASP/RTD Price Differences
HASP - RTD Price Difference Number of Price Spikes (>$500)
Actions taken to improve HASP and RTD imbalance
conditions. (1)
Slide 9
Software:
• Intertie ramp profile data issue resolved May 2, 2011
3,500
3,550
3,600
3,650
3,700
3,750
3,800
3,850
3,900
7:20:00 7:25:00 7:30:00 7:35:00 7:40:00 7:45:00 7:50:00 7:55:00 8:00:00 8:05:00 8:10:00 8:15:00 8:20:00 8:25:00 8:30:00 8:35:00 8:40:00 8:45:00 8:50:00
Net
Impo
rt (m
W)
Time
Example of Interchange Ramp
Ramp Error Correct Error
Actions taken to improve HASP and RTD imbalance
conditions. (2)
Slide 10
Software:
• Variable resource’s expected delivery were reverting to schedule
instead of telemetry mid-hour (issue started April 12, resolved April 19)
Actions taken to improve HASP and RTD imbalance
conditions.
Slide 11
HASP Forecast Adjustment
• Adjust HASP load during load pull and drop by approximately 25% of
load change
• Adjust HASP load by approximately 2% of raw forecast across peaks
• Use maximum of 5 minute load within 15 minute interval
RTD Imbalance Adjustment
• Adjusted imbalance to account resource shutdown profile instead of
instantaneous shutdown
Other contributing factor to price HASP / RTD price
divergence.
Slide 12
• Deviations of resources
• Intertie schedules not being tagged
• Resources not position to provide maximum ramp capability
MIP Gap performance
Slide 13
• Bid cap raised to $1000 on April 1.
• MIP gap tolerance (%) reduced in anticipation of bid cap increase.
• Small increase in optimization objective function cost due to bid cap
increase, mitigated by reduction in % tolerance.
Increase in optimization objective function cost due to
bid cap increase.
Slide 14
$0
$5,000,000
$10,000,000
$15,000,000
$20,000,000
$25,000,000
$30,000,000
$35,000,000
12/8/2010 12/28/2010 1/17/2011 2/6/2011 2/26/2011 3/18/2011 4/7/2011 4/27/2011 5/17/2011
Ob
jecti
ve C
ost
Date
Series1
Bid Cap increased to $1000 on April 1, 2011
Reduced MIP Gap tolerance to 0.02% in anticipation of
bid cap increase on April 1, 2011.
Slide 15
-0.20%
0.00%
0.20%
0.40%
0.60%
0.80%
1.00%
1.20%
12/8/2010 12/28/2010 1/17/2011 2/6/2011 2/26/2011 3/18/2011 4/7/2011 4/27/2011 5/17/2011
MIP
Gap
%
Series1In response to higher
objective cost reduced MIP
Gap tolerance in IFM to
maintain high quality solution
Average absolute MIP Gap tolerance less than $2,000
since April 1, 2011.
Slide 16
-$10,000
$0
$10,000
$20,000
$30,000
$40,000
$50,000
8/15
/200
9
9/4/
2009
9/24
/200
9
10
/14
/20
09
11/3
/200
9
11/2
3/20
09
12
/13
/20
09
1/2/
2010
1/22
/201
0
2/11
/201
0
3/3/
2010
3/23
/201
0
4/12
/201
0
5/2/
2010
5/22
/201
0
6/11
/201
0
7/1/
2010
7/21
/201
0
8/10
/201
0
8/30
/201
0
9/19
/201
0
10/9
/201
0
10
/29
/20
10
11
/18
/20
10
12/8
/201
0
12/2
8/20
10
1/17
/201
1
2/6/
2011
2/26
/201
1
3/18
/201
1
4/7/
2011
4/27
/201
1
5/17
/201
1
6/6/
2011
MIP
Gap
($
)
Day
MIP Gap ($ difference)
Series1 30 per. Mov. Avg. (Series1)
10-Day Moving Average of Cleared Convergence Bids
Slide 17
10-Day moving average of cleared convergence bids for
internal nodes
Slide 18
10-Day moving average of cleared convergence bids for
interties
Slide 19
10-Day moving average of daily profits/losses
Slide 20
10-Day moving average of daily profits/losses for
internal nodes
Slide 21
10-Day moving average of daily profits/losses for
interties
Slide 22
Convergence among Day-Ahead, Hour-Ahead, and
Real-Time Dispatch prices is expected to develop as
market participants gain experience with CB.
Slide 23
-30
-20
-10
0
10
20
30
40
50
2/1
/11 0
:00
2/4
/11 0
:00
2/7
/11 0
:00
2/1
0/1
1 0
:00
2/1
3/1
1 0
:00
2/1
6/1
1 0
:00
2/1
9/1
1 0
:00
2/2
2/1
1 0
:00
2/2
5/1
1 0
:00
2/2
8/1
1 0
:00
3/3
/11 0
:00
3/6
/11 0
:00
3/9
/11 0
:00
3/1
2/1
1 0
:00
3/1
5/1
1 0
:00
3/1
8/1
1 0
:00
3/2
1/1
1 0
:00
3/2
4/1
1 0
:00
3/2
7/1
1 0
:00
3/3
0/1
1 0
:00
4/2
/11 0
:00
4/5
/11 0
:00
4/8
/11 0
:00
4/1
1/1
1 0
:00
4/1
4/1
1 0
:00
4/1
7/1
1 0
:00
4/2
0/1
1 0
:00
4/2
3/1
1 0
:00
4/2
6/1
1 0
:00
4/2
9/1
1 0
:00
$/M
Wh
Hour Ending
RTD - DA HASP - DA RTD - HASP
Awarded RUC capacity has been low on days with net
virtual demand & up to 5% of daily demand for net virtual
supply, and uses mostly Resource Adequacy resources
Slide 24
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
Fe
b 1
Fe
b 5
Fe
b 9
Fe
b 1
3
Fe
b 1
7
Fe
b 2
1
Fe
b 2
5
Ma
r 1
Ma
r 5
Ma
r 9
Ma
r 13
Ma
r 17
Ma
r 21
Ma
r 25
Ma
r 29
Ap
r 2
Ap
r 6
Ap
r 10
Ap
r 14
Ap
r 18
Ap
r 22
Ap
r 26
Ap
r 30
% o
f S
yste
m L
oa
d
RA RUC Capacity Non-RA RUC Capacity
ANode vs. APNode LMPs for NP15 Trading Hub:
2/1/2011 – 4/29/2011.
Slide 25
-20
-10
0
10
20
30
40
50
60
70
-10
0
10
20
30
40
50
60
70
80
90
2/1
/11
2/4
/11
2/7
/11
2/1
0/1
1
2/1
3/1
1
2/1
6/1
1
2/1
9/1
1
2/2
2/1
1
2/2
5/1
1
2/2
8/1
1
3/3
/11
3/6
/11
3/9
/11
3/1
2/1
1
3/1
5/1
1
3/1
8/1
1
3/2
1/1
1
3/2
4/1
1
3/2
7/1
1
3/3
0/1
1
4/2
/11
4/5
/11
4/8
/11
4/1
1/1
1
4/1
4/1
1
4/1
7/1
1
4/2
0/1
1
4/2
3/1
1
4/2
6/1
1
4/2
9/1
1
Dif
fere
nc
e ($
/MW
h)
$/M
Wh
Hour Ending
NP15 ANode LMP NP15 APNode LMP Difference
Observed instances of larger
differences due to error in a
distribution factor. Resolved
March 1, 2011
Smaller observed differences
result of disconnected nodes
and Point of Delivery
Convergence Bidding affect on physical ties
• LMP could be off awarded bid curve when physical
congestion is binding
• Stakeholder process underway
• Two options were presented
• Option one is preferred
– separate physical and virtual prices when physical
only constraint is binding
• Observe approximately $250,000/month LMP vs bid
shortfall to exports
• Observe offsetting higher LMP payment to imports
Page 26
Real-time Energy Offset
Page 27
$0
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
$14,000,000
$16,000,000
$18,000,000
$20,000,0003
/2/2
01
1
3/9
/20
11
3/1
6/2
01
1
3/2
3/2
01
1
3/3
0/2
01
1
4/6
/20
11
4/1
3/2
01
1
4/2
0/2
01
1
4/2
7/2
01
1
5/4
/20
11
Co
ntr
ibu
tio
n t
o R
eal
-Tim
e E
ne
rgy
Off
set
($)
Date
30-Day Rolling Cummulative(Based on HASP, RT System Marginal Energy Cost)
SC Balanced Virtual Residual Balanced Virtual across SCs
Real-time Energy Offset (cont.)
Page 28
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
1,800,000
2,000,000
3/2
/20
11
3/9
/20
11
3/1
6/2
01
1
3/2
3/2
01
1
3/3
0/2
01
1
4/6
/20
11
4/1
3/2
01
1
4/2
0/2
01
1
4/2
7/2
01
1
5/4
/20
11V
olu
me
of
Bal
ance
d V
irtu
al (
MW
)
Date
30-Day Rolling Cummulative(Volume of balanced offsetting virtual intertie supply
and virtual internal demand)
SC Balanced Virtual Residual Balanced Virtual across SCs
Real-time Energy Offset (cont.)
Page 29
$0
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
$14,000,000
$16,000,000
$18,000,000
$20,000,000
Feb-2011 March-2011 April-2011
Real-
Tim
e E
nerg
y O
ffset
($)
Date
Monthly Real-Time Energy Offset
Total RT Energy Offset
Attributable to Virtual Bids (Based on balaned virtual import and internal virtual demand and SMEC)
MSG – Configuration change from day-ahead self-
scheduled
Page 30
-20%
0%
20%
40%
60%
80%
100%
120%
1/1
/19
00
1/5
/19
00
1/9
/19
00
1/1
3/1
90
0
1/1
7/1
90
0
1/2
1/1
90
0
1/25
/190
0
1/2
9/1
90
0
2/2
/19
00
2/6
/19
00
2/10
/190
0
2/1
4/1
90
0
2/18
/190
0
2/2
2/1
90
0
2/26
/190
0
3/1
/19
00
3/5
/19
00
3/9
/19
00
3/13
/190
0
3/1
7/1
90
0
3/2
1/1
90
0
3/2
5/1
90
0
3/2
9/1
90
0
4/2
/19
00
4/6
/19
00
4/10
/190
0
4/1
4/1
90
0
4/18
/190
0
4/2
2/1
90
0
4/26
/190
0
4/3
0/1
90
0
5/4
/19
00
5/8
/19
00
5/12
/190
0
5/1
6/1
90
0
5/20
/190
0
Pe
rce
nt
of
Un
it H
ou
rs
Date
Day-Ahead Clearing in Different Configuration Than Self -Schedule
Pct of unit- hours cleared in different configration than self -scheduled
10 per. Mov. Avg. (Pct of unit - hours cleared in different configration than self -scheduled)
MSG – Real-Time configuration change from
day-ahead or self-scheduled
Page 31
0%
5%
10%
15%
20%
25%
30%
35%
40%
1/1/
1900
1/4/
1900
1/7/
1900
1/1
0/1
90
0
1/1
3/1
90
0
1/16
/190
0
1/1
9/1
90
0
1/2
2/1
90
0
1/2
5/1
90
0
1/2
8/1
90
0
1/31
/190
0
2/3/
1900
2/6/
1900
2/9/
1900
2/1
2/1
90
0
2/15
/190
0
2/1
8/1
90
0
2/2
1/1
90
0
2/24
/190
0
2/2
7/1
90
0
3/1/
1900
3/4/
1900
3/7/
1900
3/10
/190
0
3/1
3/1
90
0
3/16
/190
0
3/1
9/1
90
0
3/2
2/1
90
0
3/25
/190
0
3/2
8/1
90
0
3/31
/190
0
4/3/
1900
4/6/
1900
4/9/
1900
4/1
2/1
90
0
4/15
/190
0
4/1
8/1
90
0
4/2
1/1
90
0
4/24
/190
0
4/2
7/1
90
0
4/30
/190
0
5/3/
1900
5/6/
1900
5/9/
1900
5/1
2/1
90
0
5/15
/190
0
5/1
8/1
90
0
5/2
1/1
90
0
5/24
/190
0
Pe
rce
nt
of U
nit
Ho
urs
Date
Real Time Clearing in Different Configuration Than Self-Scheduled or Scheduled Day-Ahead
Pct Hours Cleared in Different Config 10 per. Mov. Avg. (Pct Hours Cleared in Different Config)
MSG – Day Ahead cleared MWh versus self-
scheduled MWh
Page 32
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
12
/7/2
01
0
12
/14
/20
10
12
/21
/20
10
12
/28
/20
10
1/4
/20
11
1/1
1/2
01
1
1/1
8/2
01
1
1/2
5/2
01
1
2/1
/20
11
2/8
/20
11
2/1
5/2
01
1
2/2
2/2
01
1
3/1
/20
11
3/8
/20
11
3/1
5/2
01
1
3/2
2/2
01
1
3/2
9/2
01
1
4/5
/20
11
4/1
2/2
01
1
4/1
9/2
01
1
4/2
6/2
01
1
Cle
are
d/S
elf
Sch
ed
uled
Mw
h
Date
Day-Ahead Cleared/Self Scheduled Mwh
Self_Scheduled_Mwh Cleared_Mwh
MSG – Day Ahead Cleared / Real-Time Cleared
Page 33
-30,000
-20,000
-10,000
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
12
/7/2
01
0
12
/14
/20
10
12
/21
/20
10
12
/28
/20
10
1/4
/20
11
1/1
1/2
01
1
1/1
8/2
01
1
1/2
5/2
01
1
2/1
/20
11
2/8
/20
11
2/1
5/2
01
1
2/2
2/2
01
1
3/1
/20
11
3/8
/20
11
3/1
5/2
01
1
3/2
2/2
01
1
3/2
9/2
01
1
4/5
/20
11
4/1
2/2
01
1
4/1
9/2
01
1
4/2
6/2
01
1
Cle
are
d M
wh
Date
Day-Ahead Cleared Mwh / Real-Time Cleared Mwh
DA_Cleared_Mwh RT Clearned Mwh
MSG – Real-time Exceptional Dispatch
Page 34
-
100
200
300
400
500
600
700
800 R
eal
Tim
e (
Un
it In
terv
als)
date
Real-Time Exceptional Dispatch - MSG
Note: Humboldt management large portion of MSG exceptional dispatches
Exceptional Dispatches volumes increased in February and
March associated with system capacity and ramp-rate needs.
Slide 35
Approx. 1% of total daily energy
Approx. 1% of
total Demand
Note: To reduce exceptional dispatch to position resource to support awarded
A/S ramp, dynamic ramp will be used to constrain awarded A/S. Refer to
dynamic ancillary ramp solution discussion later in presentation.
Day-Ahead bid cost recovery increased significantly Q1-2011.
Slide 36
$0
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
$14,000,000
$16,000,000
$18,000,000
Apr
-09
May
-09
Jun-
09
Jul-0
9
Aug
-09
Sep-
09
Oct
-09
Nov
-09
Dec
-09
Jan-
10
Feb-
10
Mar
-10
Apr
-10
May
-10
Jun-
10
Jul-1
0
Aug
-10
Sep-
10
Oct
-10
Nov
-10
Dec
-10
Jan-
11
Feb-
11
Mar
-11
Apr
-11
Series1
Increases in BCR due to revenue
associated with day-ahead
minimum load and schedule when
resource is dispatched down in
real-time. ISO filed and FERC
approved change to bid cost
recovery.
RTM Bid cost recovery increased in Q1-2011.
Slide 37
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
Ap
r-0
9
May
-09
Jun
-09
Jul-
09
Au
g-0
9
Sep
-09
Oct
-09
No
v-0
9
De
c-0
9
Jan
-10
Feb
-10
Mar
-10
Ap
r-1
0
May
-10
Jun
-10
Jul-
10
Au
g-1
0
Sep
-10
Oct
-10
No
v-1
0
De
c-1
0
Jan
-11
Feb
-11
Mar
-11
Ap
r-1
1
Series1
ISO is reviewing sources of
increased real-time BCR
Daily Performance Results of DA LDF Adjustments
Since Production in 12/2010
-80%
-60%
-40%
-20%
0%
20%
40%
60%
80%
12
/20
/20
10
12
/27
/20
10
1/3
/20
11
1/1
0/2
011
1/1
7/2
011
1/2
4/2
011
1/3
1/2
011
2/7
/20
11
2/1
4/2
011
2/2
1/2
011
2/2
8/2
011
3/7
/20
11
3/1
4/2
011
3/2
1/2
011
3/2
8/2
011
4/4
/20
11
4/1
1/2
011
4/1
8/2
011
4/2
5/2
011
5/2
/20
11
Imp
rove
me
nt
of
Ad
juste
d L
DF
s o
ve
r O
rig
ina
l L
DF
(%
)
Date
Performance of DA LDF Adjustment Since December 2010
Improvement of Adjusted LDFs over Original LDFs
= (1 – Adjusted LDFs Deviation / Original LDFs Deviation )100%
Referencing SE distribution in deviation calculation
Ramping Requirements
1. Implementing Flexi-ramp Reliability Tool
– Nomogram to better manage bid in ramping capacity
– Initially upward constraint only
– Enforce in RTPD and RTD (non-binding intervals)
– Enforce constraint to improve operational preparedness to
changes in imbalance conditions
2. Working Towards Ramping Product
a. Consider opportunity cost compensation
– Review market results for three months (June-August)
– Conduct expedited stakeholder process starting in September/
Board in December
– Implementation plan to be determined
b. Comprehensive product design through Renewable
Integration Market & Product Review Phase 2
Page 39
Policy Update
Greg Cook, Director
Market & Infrastructure Policy
Slide 40
Market Initiatives In Progress
Initiative Board Presentation
Data Release Phase 3 May 2011
Dynamic Transfers May 2011
GMC Rate Structure Change May 2011
Credit Reform in Organized Energy
Markets
May 2011
Renewable Integration Market &
Product Review Phase 1
June 2011
CRR Enhancements 2011 June 2011
LMPM Enhancements June 2011
Real-Time Imbalance Energy Offset June 2011
Page 41
Market Initiatives In Progress
Initiative Board Presentation
Regulatory Must-Take Generation June 2011
Regulatory Must-Run Pump Load June 2011
Price Inconsistency caused by Intertie
Constraints
June 2011
Deliverability of Resource Adequacy
on Interties
Resource Transitions
GIP Phase 2 August 2011
Page 42
Other Market Initiatives Activities
• Renewable Integration Market & Product Review Phase 2
– Complete comprehensive vision and roadmap for end-state
market design to meet 33 percent RPS
– Targeted to be presented to Board in December
• Market Initiatives Roadmap Process
– Targeted to start in June 2011
• Release 2 (year three) FERC Mandated Items – these items
may be delayed in order to address them more holistically
– Export of AS
– Bid Cost Recovery for Unit over Multiple Days
– Two Tier Real-Time Uplift
Page 43
Technical Updates
Li Zhou, Senior Advisor
Power Systems Technology Development
Page 44
Open Ties
Page 45
• CAISO is currently testing the fix for the following issue
identified in Market Simulation,
“When an one MW virtual bid is submitted at an open tie, it
does not get rejected. It should.”
Market participants shall be able to see the effect of this fix
by 05/10/11 in market simulation environment.
Energy Self-Schedule Requirement for Regulation Self
Provision
Page 46
• Tariff Filing on 05/03/11
• SIBR rule change has been posted
• Go-live day on 05/24/11 (Operation Date), i.e., effective
for any market that is open at the time of deployment
Energy Self-Schedule Requirement for Regulation Self
Provision
Page 47
• A submission to self-provide Regulation Down must be
supported by an Energy Self-Schedule at a level that
would permit the resource to provide Regulation Down to
its lower Regulation Limit. A submission to self-provide
Regulation Up must be supported by an Energy Self-
Schedule at a level that would permit the resource to
provide Regulation Up within its Regulation Limit
• In real-time, self provisions also include day-ahead
awarded regulation up or down capacity;
• Not applicable to MSS load following;
• Bids will be rejected if not meeting the requirement.
Enforcement of Physical and Physical plus Virtual
constraints for MSL
Page 48
• Background
Because the market enforces the physical only and
physical + virtual on ITCs while only enforces the physical
+ virtual on the MSLs, there may be a counter flow caused
by virtual that may result is over-scheduling physicals that
will need to be cut in real-time. Due to this reason, CAISO
has disabled some inter-tie scheduling points from virtual
Bidding.
Enforcement of Physical and Physical plus Virtual
constraints for MSL
Page 49
• Update on the Enhancement
The enhancement is to actually enforce both Physical only
and Physical + Virtual constraints for MSLs as well.
Development is complete;
CAISO will start testing this week.
Planned production dated in the first half of June. Upon
successful test, CAISO will issue market notice and those
nodes disabled due to this reason will be enabled for virtual
bidding on production date.
Dynamic Ancillary Service Ramp - Problem Statement
Page 50
• Currently in the co-optimization of energy and ancillary
service, operation ramp-rate curve is used for energy
while ancillary service ramp-rate is used for ancillary
service.
• The procurement of AS in the co-optimization of energy
and AS does not consider the possible ramp-rate change
when energy is dispatched at different MW level.
• Hence, the procured AS capacity may not be feasible to
be dispatched for energy due to ramp-rate limit.
• This may cause a reliability concern in production that
may result in increase in number of exceptional
dispatches.
Dynamic Ancillary Service Ramp - Proposed Solution
Page 51
• ISO is currently evaluating and testing a solution in
which operation ramp-rate curve will be also considered
in the AS procurement.
• Effectively, the procurement of AS in the software will
use the minimum of AS ramp rate, and the operating
ramp rate at the scheduled energy MW.
Dynamic Ancillary Service Ramp – Numerical Example
Page 52
• Unit 1 has the following operational ramp-rate curve
(20MW, 190MW) 1.6 MW/min;
(190MW, 250MW) 6.4 MW/min;
Spin ramp-rate 6.4 MW/min
Dynamic Ancillary Service Ramp – before fix
Page 53
• With existing method for AS procurement, the following
energy and Spin results are possible:
EN Spin
HE1: 138 64
HE2: 42 64
HE3: 20 64
• Note: the spin capacity is procured with 6.4 MW/min
even the unit is at 20MW of energy with an effective 1.6
MW/min operation ramp-rate.
Dynamic Ancillary Service Ramp – after fix
Page 54
• After enforcing the operational ramp-rate for AS, the
energy and Spin results are:
EN Spin
HE1: 138 16
HE2: 94 16
HE3: 190 64
• The spin capacities for HE 1, 2 are now limited with the
1.6 MW/min operational ramp-rate.
MSG Enhancement
Page 55
• MSG Enhancement List was presented to Stake Holders
on 03/14/11
• Stake Holders have given inputs and comments on
priorities
• Currently finalizing requirement and evaluating timeline
Following is the list for the selected MSG enhancements,
1. RTPD needs to consider telemetry – Currently RTPD
does not take the telemetry into consideration for MSG
resources. RTD does recognize the telemetry;
2. Extension of the terminal condition to consider
configuration level minimum down time when making
transition decisions;
MSG Enhancement
Page 56
3. Following enforcements will always take the submitted
Bid from MP first, if an energy bid is not submitted for a
Lower configuration, the default energy bid will be used for
That lower configuration.
3.1). Bids for non-RA resources in RTM with DA award.
SIBR shall enforce the bids to be available for all
configurations below the DA schedule even the DA
scheduled configuration is startup-able;
3.2). SIBR rule changes to tighten real-time bid submission
including support of DA awarded AS or sufficient bids to
allow transition across trading hours. Similarly to item 3.1,
MSG Enhancement
Page 57
SIBR shall enforce the lower configurations to be bid in.
3.3). Whenever a capacity is offered, the MSG resource
shall offer the entire capacity range underneath that
capacity.
4. Transition Cost registration – Formula needs to be
revised (Policy change required);
5. Extension of the Real-time limit on maximum number of
configurations (Tariff change required);
6. Allow at least two ramp rates within configuration in
IFM/RTD (or at least RTD). This is also related to the
need to be able to provide more spin service when it can
move from a configuration into duct firing in 10 minutes
inclusive of ramp and transition.;
Reliability Demand Response Product (RDRP)
Page 58
• Currently in the development of system requirement
specification and design
• SIBR rules will be posted by 05/13/11
Reliability Demand Response Product (RDRP)
Page 59
RDRP will be modeled like a supply resource relying on the
functionality and infrastructure designed for the ISO’s
recently implemented Proxy Demand Resource (PDR)
product.
In addition to the regular PDR features, RDRP resources
• Will have a discrete dispatch capability;
• Will deliver “reliability energy” in real-time as specified in
CAISO Electrical System Emergency Operating
Procedures; and
• Will be subject to availability limits of 15 events and/or 48
hours (2,880 minutes) within any six (6) month RDRP
Term.
Release Plan Update
Janet Morris, Director
Program Office
Slide 60
Master Stakeholder Engagement Plan
http://www.caiso.com/2825/2825e37f44400.pdf
(now includes revision log)
Page 61
Project Updates
• MSG Market Simulation Update
• Convergence Bidding Update
• Pre-Summer 2011 Monthly Releases– Open Ties milestones
– Flexible Ramping
– Commitment Costs 1.1
– Reporting Platform Migration
• Fall 2011 release– 72 Hour RUC milestones
– RDRP milestones
– Commitment Costs Phase 2
– Flex Ramping milestones
– FERC Order 741 Credit Reform
• December 2011 monthly release– Generation of bids for NRS-RA
– GMC rate structure change
• Spring 2011 release– Regulation Energy Management
– LMPM Enhancements
– SLIC to SIBR Interface
Page 62
Slide 63
Registration
• Following the third MSG activation window, MSG resources may be
activated for any trade date subject to 16 business days for processing of
the MSG registration.
Testing
• One to two week testing intervals will be planned with each monthly release,
occurring three weeks prior to the second Tuesday of the month.
• External testing will be conducted in the MAP-Stage environment.
• At least one settlement statement will be offered during that testing interval.
• Further testing requests will need to be coordinated in advance with the
ISO.
• Please indicate if you would like to modify your Master File data during the
market simulation.
Ongoing MSG Activation Process
Convergence Bidding Update
Two notable post go-live issues are being addressed:
– The OASIS Day-Ahead Market Summary report has been
restored as of 5/3/11.
– Tie points modeling as MSLs were not held to the correct limits
by the dual intertie constraint functionality and nine MSL intertie
locations have been suspended. We are expecting to resolve
this by the end of May.
Page 64
May Release - Open Ties Project Milestones
Milestone Open Ties / Market Scheduling Limit
BPM Changes Feb 4th, 2011
Publish external business
requirements
Feb 7th, 2011
Publish Technical Specifications Feb 7th, 2011
Market Simulation April 12th, 2011
Go-Live May 18th, 2011 Rescheduled
API changes to show Open Tie
condition in the CleanBid XSD
October 1, 2011
Page 65
May Release - Flexible Ramping Project Milestones
Milestone Date
Technical bulletin published February 24, 2011
Publish external OASIS requirements April 1, 2011
BPM change management process April – May, 2011 In Progress
Market Simulation May 5 – May 9 In Progress
Production Deployment (inactive) May 24, 2011 On Track
Activation May 31, 2011 On Track
Page 66
June Monthly Release - Commitment Costs Phase 1.1
Application impacted: Master File
• Release Details
– Addition of the following flags in the Resource Data Template (RDT)
• Pre Hourly Dispatch, Cert DAM, Cert RTM, and Stranded Load to the Gen RDT as non-modifiable.
• ML Cost Basis Type and SU Cost Basis Type to Gen RDT as modifiable
• Stranded Load to the Intertie RDT as non-modifiable.
– Removal of Cost Basis Type from Gen RDT.
– Support backward compatibility with version 3.0 of the Generator RDT and version 1.0 of Inter-Tie RDT.
– Rounding of submitted Heat Rate to 3 decimal places (no changes to the RDT).
• Market Simulation Schedule
• Monday 05/16 (08:00 AM)- Wednesday 05/18 (05:00 PM):
– Scheduling Coordinators (SCs) test items listed in CC 1.1 release above.
– Please restrict submission to only three resources per SC
• By Monday 05/23 (05:00 PM)
– ISO performs bare minimum manual validation on the submitted Batches and approves the batches.
– ISO will send a notification (via outlook email) to all the SCs who submitted a batch informing them
that their submitted batch has been approved or rejected.
Slide 67
June Monthly Release - Report Platform Migration
• Overview– The California ISO is planning to release software affecting the external
facing graphical user interface (GUI) reports generating MasterFile
(MF), MSSA Load Forecast, Scheduling Infrastructure Business Rules
(SiBR), Business Practice Manual (BPM), Transmission Register (TR),
and Resource Interconnection Management System (RIMS) information
to market participants in the production environment during the Monthly
Release slated on June 14, 2011.
– This release is mainly a software conversion of the existing reports
based on the newly ISO-adopted reporting technology.
– A pre-production external testing period within the stage environment is
planned to be available from May 24 to June 3, 2011.
Page 68
Fall 2011 Release - 72 hours RUC Release Milestones
Milestone Date
Publish business requirements September 23, 2010
Implementation plan December 10, 2010
Technical specifications N/A
Publish draft BPM July 19, 2011 On Track
Market simulation Aug 23 – Sept 8, 2011 On Track
Production Deployment October 1, 2011 On Track
Page 69
Fall 2011 Release - Reliability Demand Response
Product (RDRP) Release Milestones
Milestone Date
Publish business requirements March 29, 2011
Publish draft BPM June 2011 On Track
Technical specifications June 27, 2011 On Track
Implementation plan July 2011 On Track
Market simulation Aug 23 – Sept 8, 2011 On Track
Production Deployment October 1, 2011 On Track
Page 70
Fall 2011 Release - Change in Commitment Costs
Phase 2
Application
Software
Changes
Enhance the Master File (MF) system
Enhance the MF RDT to collection Start-Up cost for
MSG configurations not capable of direct start-up
Provide comparison and validation Report via MF
User Interface (UI)
RDT Processing status updates via automated E-mail
Notification
Enhancements to the validation and processing of
data changes submitted to the MF system (Internal to
ISO)
Policy
ImplementationReview default O&M adder default values and revise as
needed.
Changes (if any) would be effective on April 1, 2012
No application changes anticipated
Page 71
Fall 2011 Release - Credit Reform Release Milestones
Milestone Date
Post final implementation proposal April 8, 2011
Board approval May 15, 2011 On Track
Tariff stakeholders’ process May 18 – June 29, 2011 On Track
FERC filing June 30, 2011 On Track
Technical specifications N/A
BPM change management process July 1 - Sept 30, 2011 On Track
Configuration guides July 15, 2011 (tentative)
Market simulation August 15 – Sept 2, 2011 On Track
Production deployment October 1, 2011 On Track
Page 72
• Business Requirements Posted February 25, 2011
• Implementation Workshop (March 10, 2011)
• Scope of project refined to accommodate timeline.
• Insertion of Bids for NRS-RA resources limited to:
– Insertion of bids for NRS resources with RA obligation.
– Subset of hours bids apply to NRS resources with RA obligations only.
– SLIC Outage reporting at NRS resource level for NRS resources with RA
obligations.
– Recognition of the SLIC outages in the market applications for SLIC Outage at
NRS resource level for NRS resources with RA obligations
• Deferred scope due to refined implementation impact analysis showed more
effort than previously considered for subset of hours RA for internal RA
resources to CPM, SCP and RA business processes
• Market Simulation: October/November 2011
• Proposed Implementation Timeframe: January 1, 2012
December Monthly Release - Insertion of Bids for
NRS-RA Impact Assessment
Page 73
December Monthly Release - GMC Rate Structure
Impact Assessment
Application Software Changes • Congestion Revenue Rights (CRR)
• Settlements
BPM Changes • Congestion Revenue Rights (CRR)
• Settlements & Billing
• Definitions & Acronyms
Business Process Changes • Manage Billing & Settlements
Business Requirements • Under development
Operational Procedures • N/A
Market Simulation • Fall 2011
Proposed Implementation Timeframe • January 1, 2012
Page 74
Spring 2012 Release - Regulation Energy Management (REM)
Model REM in the framework of Non-Generator Resource (NGR)
Page 75
Project Technology Model
Option to REM
(Special Treatment)
RegulationSpin/Non-
SpinEnergy
Qualified MW
Non-Generator Resource
(NGR) (2012)
New functions in
EMS, market from bid to
Bill
Energy Storage Resource (ESR)
(Flywheel, battery, energy storage)
Operation range between negative (Charge) and positive (Discharge),
constrained by State of Charge (SOC)
REM SC Bid No No15 minute continuous
delivery
Non REM SC Bid SC Bid SC Bid
Depending on
registration and
certification
Dispatchable Demand Response (DDR) --
Implementation of the PLR model
Operation range is non positive, constrained by
limited curtailable energy.
REM SC Bid No No15 minute continuous
delivery
Non REM SC Bid SC Bid SC Bid
Depending on
registration and
certification
Regulation Energy Management (REM)
Model NGR in EMS with supply range of negative to positive
• EMS shall model NGR as a generation resource with supply range of
negative to positive.
– For ESR, the operation output is positive when the ESR discharging and inject
the power into the grid; the output is negative when the ESR is charging and
withdraw the power from the grid.
Ex: A battery is discharging at 2 MW, the operation output will be 2MW. A battery
is charging at 2 MW, the output will be -2 MW.
– For DDR, the operation output is non positive.
Ex: DDR Load level is 10 MW, the operation output = -10 MW. DDR load level is
curtailed by 2 MW, operate at 8 MW, the operation output = -8 MW.
• EMS AGC module shall dispatch NGR for regulation up and down
– NGR provides regulation up if AGC dispatches the NGR above its DOT
– NGR provides regulation Down if AGC dispatches the NGR below its DOT
Page 76
Regulation Energy Management (REM)
EMS shall receive NGR telemetry every four (4) seconds;
• EMS shall receive NGR telemetry of the following data every four (4)
seconds:
– Resource Instantaneous Output (MW);
– State of Charge (SOC), which is the actual stored Energy (MWh) in the device;
ESR Instantaneous Output (MW) telemetry is negative when the ESR is charging.
ESR Instantaneous Output (MW) telemetry is positive when the ESR is discharging.
DDR Instantaneous Output (MW) telemetry is negative for its load level. DDR
Instantaneous Output (MW) telemetry is zero if the load shut down totally
• EMS shall send to RTM every minute the SE solution and all telemetry for
each NGR, including the state of charge (SOC) for ESR
Page 77
Regulation Energy Management (REM)
DAM/RTM model NGR as a generation resource with supply range of
negative to positive
• Optimize NGR energy and AS awards in DAM/RTM subject to:
– Capacity Constraints;
– Ramping (Charge/Discharge rates) Constraints;
– State of Charge (SOC) constraints for ESR;
– Daily energy limits and continuous energy limits for DDR;
• NGR optimal schedule and AS awards shall be based on its Energy bid
curve and AS bids.
• DAM/RTM will model NGR with energy and/or AS bids as on-line unit; No
binary commitment decision variables are needed for NGR. No start up cost
/time, No commitment cost recovery.
• RTM shall receive from EMS telemetry for each NGR, including the actual
SOC for each ESR, to calculate initial condition. ESR optimal schedule and
AS awards shall be limited by the available SOC.
Page 78
Regulation Energy Management (REM)
REM modeling as a NGR
• REM shall be allowed to bid or self-schedule Regulation Up and Regulation
Down capacity in DAM/RTM
• REM will not bid or self-schedule Energy in DAM/RTM
• The SOC constraints will be enforced in the market for REM. SOC
constraints and regulation bids will determine the REM regulation up and
down awards and energy schedule DOT (dispatch operating target).
• The ISO shall manage REM energy offset through AGC in EMS. AGC will
dispatch REM based on DOT and regulation awards. REM must response
AGC dispatch.
• Settle Regulation Awards in DAM and RTPD.
• Settle REM at RT LMP for each interval of net metered energy.
(equivalent to settle REM at RT LMP for the energy offset and regulation energy
dispatched by AGC)
Page 79
Regulation Energy Management (REM)
NGR Settlement
• NGR shall be subject to all existing AS/RUC No Pay categories.
• ESR shall be subject to a new AS/RUC No Pay category: Insufficient Stored
Energy
– The relevant No Pay quantity (MW) shall be calculated for each dispatch interval
to see if SOC level can provide enough energy once the awarded AS called upon
• Settle the NGR energy schedule at LMP in IFM and RTD.
• Settle the NGR AS awards same as Generators in IFM and RTPD.
Page 80
REM Market Simulation Notification Date
• REM is planned for deployment in Spring 2012
• In order to participate in the REM market simulation, you
must notify the ISO by July 1, 2011:
– Submit the WDAT (Wholesale Direct Access Tariff)
– If you intend to connect to the transmission system
directly, participate in the fast-track interconnection
process (for less than 5 MW)
Page 81
SLIC to SIBR Interface – Background
September 2006 FERC Order
• FERC’s September 2006 order directed the ISO to implement an
interface between SLIC and SIBR by “MRTU Release 2,” a feature
that the ISO had itself proposed for Release 2.
• The ISO is reconsidering whether this feature would provide
sufficient benefit to the market to justify the costs of implementation
especially in light of other high priority enhancements
• As noted in the September 2006 order, even if SIBR generated bids
for derated capacity, the day-ahead and real-time markets will see
derates entered into SLIC and bids for capacity that is not available
will not result in market awards
Page 82
SLIC to SIBR Interface – Impact Assessment
Significant system changes would be required• In order to properly handle in the case of a generation outage/de-rate/re-
rate, around 500 generator processing and validation rules will have to be
revisited and revised;
• In the case that there are multiple commodity bid in (energy and ancillary
services) and the unit is de-rated or re-rated, there is no clean way to adjust
or curtail the bids. CAISO will need to reject the bids.
• In the case that the particular generator is associated with any
ETC/TOR/CVR contract, the adjustment will require to follow the contract
and potentially the chain to all the impacted sources and sinks.
• Outage Management System will replace SLIC in 2012
• Testing and market simulation would be extensive
Page 83
SLIC to SIBR Interface – Impact Assessment
Benefit to market participants appears to be limited
• Planned Outages: When markets are open, the SC can resubmit
their bids based on planned outages
• Forced Outages: When markets are already closed, bids cannot be
requested and it will be recognized in real time
Page 84
SLIC to SIBR Interface – Next Steps
• The ISO is seeking comments on the current need to
provide a SLIC to SIBR interface
• Submit comments by 5/25/11 to [email protected]
• Based on comments received, the ISO will publish an
issue paper in the June timeframe
Page 85
Implementation Updates
Jami Long, Director
Business Solutions and Quality
Page 86
Outage Management System – Background
• In 2007, the ISO defined its expectations of an Outage Management
System (OMS).
– An OMS strategy was developed to replace the current Scheduling,
Logging for ISO California (SLIC) and CAISO Outage Modeling
Tool (COMT) systems by creating and incrementally deploying a
consolidated modular OMS. Each module targets a specific outage
domain including transmission, generation, analytical tools, and
reporting.
• Phase 1 was deployed in December 2010 for transmission and
systems analysis. The COMT application was sunset.
• Phase 2 is currently underway and scheduled to deploy to production
in Fall 2011 to provide visualization enhancements to transmission.
• Phase 3 will start with a twenty-two week requirements effort from May
through October 2011, with working group touch-points throughout.
OMS Phase 3 – Project Objectives
• OMS Phase 3 will incorporate generation outage
management functionality currently provided from SLIC
into the new OMS framework.
• Simplification and Usability Improvements
• Market Participant Collaboration
• OMS will decommission the SLIC application upon
deployment.
OMS Phase 3 - Scope
• Proposed Scope:
– Development of web client for external users
– Quick Find
– Search/Reports for Generation Outages
– Process Generation Outages
– Outage/Version Comparison
– Process/Assign User Tasks
– Notifications
– Visualization
– API Simplification
OMS Phase 3 – High Level Milestones
# Milestone DescriptionTarget Delivery
Timeframe
1. Requirements Analysis and Development Q3 2011
2. External User Checkpoints Q3 2011
3. Phase 3 Design and Development Q2 2012
4. BPM Revision Cycle Q2 2012
5. Phase 3 Testing Q3 2012
6. Market Simulation Q3 2012
7. Tariff Changes Q3 2012
8. Deployment Q4 2012
9. Production Validation Q4 2012
10. End-of-Life SLIC API Q4 2012
Data Release Ongoing Process
• Data release requests will be made through the
Business Practice Manual (BPM) Process leveraging the
existing process and timelines.
• A new BPM will be created and maintained to describe
data published by the ISO, both confidential and public
data.
• Proposed Revision Requests (PRR) will be available for
the drafted BPM in Q3.