Mark collinson wrap community energy rural community energy fund 300715

40
Rural Community Energy Fund Mark Collinson Energy Sector Specialist WRAP

Transcript of Mark collinson wrap community energy rural community energy fund 300715

Page 1: Mark collinson wrap community energy rural community energy fund 300715

Rural Community Energy FundMark Collinson

Energy Sector Specialist

WRAP

Page 2: Mark collinson wrap community energy rural community energy fund 300715

What is RCEF ?

• £15m fund, £7.5 each from Defra and DECC – rolling programme

Rural Community Energy Fund

Page 3: Mark collinson wrap community energy rural community energy fund 300715

What is RCEF ?

• £15m fund, £7.5 each from Defra and DECC – rolling programme

• Community energy generation projects in rural areas

Rural Community Energy Fund

Page 4: Mark collinson wrap community energy rural community energy fund 300715

What is RCEF ?

• £15m fund, £7.5 each from Defra and DECC – rolling programme

• Community energy generation projects in rural areas

• Provides pre-planning development finance – NOT capital costs*; via:

• Stage 1: Grants up to £20k for a project’s feasibility study

• Stage 2: Loans up to £130k for detailed pre-planning process

Rural Community Energy Fund

Page 5: Mark collinson wrap community energy rural community energy fund 300715

Who can Apply ?

• Applicants must be a legally constituted community based entity:

• Parish Council

• CIC

• Bencom

• IPS (Co-operative)

• Charity

Rural Community Energy Fund

Page 6: Mark collinson wrap community energy rural community energy fund 300715

What have we achieved ?• 99 Stage 1 applications – 61 awarded (60%)

• Hydro; Wind; Biomass; PV; G/WSHP

• £980,000

• 55MW combined capacity - 50MWp; 5MWth

Rural Community Energy Fund

Page 7: Mark collinson wrap community energy rural community energy fund 300715

What have we achieved ?• 99 Stage 1 applications – 61 awarded (60%)

• Hydro; Wind; Biomass; PV; G/WSHP

• £980,000

• 55MW combined capacity - 50MWp; 5MWth

• 5 Stage 2 applications – 2 awarded (2 pending, 1 on hold)

• AD; Hydro

• £224,000

• Combined capacity 650kW – 400kWp; 250kWth

Rural Community Energy Fund

Page 8: Mark collinson wrap community energy rural community energy fund 300715

How does that breakdown? (14th May 2015)

Rural Community Energy Fund

6

13

13

20

3

AD

Biomass

Hydro

Solar PV

Wind

0

1000

2000

3000

4000

5000

6000

Page 9: Mark collinson wrap community energy rural community energy fund 300715

Application process• Visit the website: wrap.org.uk/renewables

Rural Community Energy Fund

Page 10: Mark collinson wrap community energy rural community energy fund 300715

Application process• Visit the website: wrap.org.uk/renewables

• Read the guidance and FAQs

Rural Community Energy Fund

Page 11: Mark collinson wrap community energy rural community energy fund 300715

Application process• Visit the website: wrap.org.uk/renewables

• Read the guidance and FAQs

• Download the pack

Rural Community Energy Fund

Page 12: Mark collinson wrap community energy rural community energy fund 300715

Application process• Visit the website: wrap.org.uk/renewables

• Read the guidance and FAQs

• Download the pack

• Return to WRAP

Rural Community Energy Fund

Page 13: Mark collinson wrap community energy rural community energy fund 300715

Application process• Visit the website: wrap.org.uk/renewables

• Read the guidance and FAQs

• Download the pack

• Return to WRAP

• 2 week – 6 week turn around process*

Rural Community Energy Fund

Page 14: Mark collinson wrap community energy rural community energy fund 300715

What makes a good application ?• Community benefit – independent fund ? Legacy – what is it ?

Rural Community Energy Fund

Page 15: Mark collinson wrap community energy rural community energy fund 300715

What makes a good application ?• Community benefit – independent fund ? Legacy – what is it ?

• Clearly defined (single ?) project idea

Rural Community Energy Fund

Page 16: Mark collinson wrap community energy rural community energy fund 300715

What makes a good application ?• Community benefit – independent fund ? Legacy – what is it ?

• Clearly defined (single ?) project idea

• How will this project actually make a difference to the community ?

Rural Community Energy Fund

Page 17: Mark collinson wrap community energy rural community energy fund 300715

What makes a good application ?• Community benefit – independent fund ? Legacy – what is it ?

• Clearly defined (single ?) project idea

• How will this project actually make a difference to the community ?

• Demonstration of your decision to choose said project

Rural Community Energy Fund

Page 18: Mark collinson wrap community energy rural community energy fund 300715

What makes a good application ?• Community benefit – independent fund ? Legacy – what is it ?

• Clearly defined (single ?) project idea

• How will this project actually make a difference to the community ?

• Demonstration of your decision to choose said project

• Evidence of prior community engagement and acceptability of ideas

Rural Community Energy Fund

Page 19: Mark collinson wrap community energy rural community energy fund 300715

What makes a good application ?• Community benefit – independent fund ? Legacy – what is it ?

• Clearly defined (single ?) project idea

• How will this project actually make a difference to the community ?

• Demonstration of your decision to choose said project

• Evidence of prior community engagement and acceptability of ideas

• Evidence of prior key stakeholder engagement (EA, planners, anglers)

Rural Community Energy Fund

Page 20: Mark collinson wrap community energy rural community energy fund 300715

What makes a good application ?• Evidence of grid connection possibilities for power projects

Rural Community Energy Fund

Page 21: Mark collinson wrap community energy rural community energy fund 300715

What makes a good application ?• Evidence of grid connection possibilities for power projects

• Evidence of a clear, transparent consultancy procurement process

Rural Community Energy Fund

Page 22: Mark collinson wrap community energy rural community energy fund 300715

What makes a good application ?• Evidence of grid connection possibilities for power projects

• Evidence of a clear, transparent consultancy procurement process

• Avoid self-awarding – at all costs

Rural Community Energy Fund

Page 23: Mark collinson wrap community energy rural community energy fund 300715

What makes a good application ?• Evidence of grid connection possibilities for power projects

• Evidence of a clear, transparent consultancy procurement process

• Avoid self-awarding – at all costs

• Application from a suitable and demonstrable legal entity

Rural Community Energy Fund

Page 24: Mark collinson wrap community energy rural community energy fund 300715

What makes a good application ?• Evidence of grid connection possibilities for power projects

• Evidence of a clear, transparent consultancy procurement process

• Avoid self-awarding – at all costs

• Application from a suitable and demonstrable legal entity

• Consider any reasons the funders may have to turn down the project

Rural Community Energy Fund

Page 25: Mark collinson wrap community energy rural community energy fund 300715

What makes a good application ?• Evidence of grid connection possibilities for power projects

• Evidence of a clear, transparent consultancy procurement process

• Avoid self-awarding – at all costs

• Application from a suitable and demonstrable legal entity

• Consider any reasons the funders may have to turn down the project

• THEN ADDRESS THEM !

Rural Community Energy Fund

Page 26: Mark collinson wrap community energy rural community energy fund 300715

Rural Community Energy Fund

Page 27: Mark collinson wrap community energy rural community energy fund 300715

Rural Community Energy Fund

Page 28: Mark collinson wrap community energy rural community energy fund 300715

Rural Community Energy Fund

Page 29: Mark collinson wrap community energy rural community energy fund 300715

What’s in a feasibility study ?• Executive Summary

• Community Engagement

• Community Benefit

• Technology (i.e., the project)

• Financial Projections

Rural Community Energy Fund

Page 30: Mark collinson wrap community energy rural community energy fund 300715

What’s in a feasibility study ?• Planning and Permitting

• Site details (i.e., landowner agreements, lease costs, grid connection)

• Operation and Governance

• Scheduling

• Conclusions and next steps

Rural Community Energy Fund

Page 31: Mark collinson wrap community energy rural community energy fund 300715

What happens next ?• New Government:

`

Rural Community Energy Fund

Page 32: Mark collinson wrap community energy rural community energy fund 300715

What happens next ?• New Government:

• Amber Rudd, Sec of State - Andrea Leadsom, Minister of State;

`

Rural Community Energy Fund

Page 33: Mark collinson wrap community energy rural community energy fund 300715

What happens next ?• New Government:

• Amber Rudd, Sec of State - Andrea Leadsom, Minister of State;

• Incentives stability ?

`

Rural Community Energy Fund

Page 34: Mark collinson wrap community energy rural community energy fund 300715

What happens next ?• New Government:

• Amber Rudd, Sec of State - Andrea Leadsom, Minister of State;

• Incentives stability ?

• Policy ?

`

Rural Community Energy Fund

Page 35: Mark collinson wrap community energy rural community energy fund 300715

What happens next ?• New Government:

• Amber Rudd, Sec of State - Andrea Leadsom, Minister of State;

• Incentives stability ?

• Policy ?

• Wind Moratorium

`

Rural Community Energy Fund

Page 36: Mark collinson wrap community energy rural community energy fund 300715

What happens next ?• New Government:

• Amber Rudd, Sec of State - Andrea Leadsom, Minister of State;

• Incentives stability ?

• Policy ?

• Wind Moratorium – ROCs only.

Rural Community Energy Fund

Page 37: Mark collinson wrap community energy rural community energy fund 300715

What happens next ?• New Government:

• Amber Rudd, Sec of State - Andrea Leadsom, Minister of State;

• Incentives stability ?

• Policy ?

• Wind Moratorium – ROCs only.

• Ground mount large scale PV:

Rural Community Energy Fund

Page 38: Mark collinson wrap community energy rural community energy fund 300715

What happens next ?• New Government:

• Amber Rudd, Sec of State - Andrea Leadsom, Minister of State;

• Incentives stability ?

• Policy ?

• Wind Moratorium – ROCs only.

• Ground mount large scale PV:

• C&I rooftop feasibility ? Legal/structural issues ?

Rural Community Energy Fund

Page 39: Mark collinson wrap community energy rural community energy fund 300715

What happens next ?• New Government:

• Amber Rudd, Sec of State - Andrea Leadsom, Minister of State;

• Incentives stability ?

• Policy ?

• Wind Moratorium – ROCs only.

• Ground mount large scale PV:

• C&I rooftop feasibility ? Legal/structural issues ?

• Grid connection – Route F, LV, PW, heat.

Rural Community Energy Fund

Page 40: Mark collinson wrap community energy rural community energy fund 300715

Rural Community Energy Fund