Manual Standards Guidelines Ahec Roorkee

download Manual Standards Guidelines Ahec Roorkee

of 28

Transcript of Manual Standards Guidelines Ahec Roorkee

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    1/28

    DRAFT July 03, 2008

    STANDARDS / MANUALS / GUIDELINES

    FOR SMALL HYDRO DEVELOPMENT

    SPONSOR:

    MINISTRY OF NEW AND RENEWABLE

    ENERGY

    GOVERNMENT OF INDIA

    GENERAL

    MANUAL ON PROJECT HYDROLOGY AND

    INSTALLED CAPACITY

    LEAD ORGANIZATION:ALTERNATE HYDRO ENERGY CENTREINDIAN INSTITUTE OF TECHNOLOGY, ROORKEE

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    2/28

    CONTENTS

    S.No. TITLE Page No.

    1. SCOPE AND OBJECTIVE 12. DATE REQUIREMENT 13. RESOURCES OF DATA 14. COLLECTION OF DATA 15. ASSESSMENT OF QUALITY OF DATA 36. FILLING IN MISSING DATA 47. CONSISTENCY CHECKS 48. PROCESSING AND PRESENTATION OF DATA 5

    8.1. Rainfall Data 5

    8.2. Stream Flow Data 5

    9. EXTENSION OF PERIOD RECORD OF STREAM FLOW DATA 69.1.When Short Term Data Is Available At Project Site 6

    9.2. When Stream Flow Data To Two Lean Seasons And One Flood 6

    Season At Site Are Recorded

    10.FLOW ASSESSMENT FOR AN UNGAUGED CATCHMENT 710.1. Long Term Data Of Some Other Site 710.2. Regional Specific Discharge 710.3. Regional Model 8

    11.WATER AVAILABILITY ASSESSMENT 811.1. Application of FDC 811.2. Application of NIH Model 911.3. When Only Observed Discharge of Two Non-monsoon 11

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    3/28

    Seasons are Available

    11.4. Energy Curve 1111.5. Daily Pondage 11

    12.ESTIMATION OF FLOOD DISCHARGE 1212.1. Computation of Design Flood 1212.2. Spillway Design Flood and Construction Floods 17

    13.SEDIMENTATION 1814.WATER QUALITY 1915.OTHER HYDROLOGICAL AND METEOROLOGICAL 19

    DATA REQUIREMENT

    15.1. Tail Race Rating Curve 1915.2. Meteorological Data 20

    16.REFERENCES 20

    Table 1: Regional Flow Estimate For Various Levels of Dependability

    Table 2: Values of the parameters of the Regional Models for Mean Flow

    Fig. 1: Annual Rainfall Duration Curve

    Fig. 2: Regional Hydrographs with 50% dependability

    Fig. 3:

    Fig. 4: Flow Duration Curve for July Flows

    Fig. 5: Flood frequency peak flow vs. return period

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    4/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 1

    GUIDELINES ON PROJECT HYDROLOGY

    1. Scope and Objective

    The scope and objective of these guidelines is limited to hydrological data

    collection, estimation / assessment and data analysis to establish a reliable flow

    quantity with time variability and the peak flood discharge at the project site

    alongwith other hydrological inputs required for project preparation. A large

    number of text books (Chow, Mutreja, Varshney etc.) on the subject are available

    alongwith the guidelines of CWC and CEA for the preparation of hydrology

    chapter of the DPR of the Hydro Power Projects. For specific hydrological issues

    I.S. Codes and publications of NIH Roorkee are also of great help. Unfortunately

    the available literature is not of much help in Small Hydro Projects where

    observed stream flow is either available for a very short period or no data is

    available or data from other sources is made use of. For the project report

    preparation of a small hydropower project guide lines of CBI&P (Pub. No. 280)

    and CEA are available. A publication by Jack J. Fritz is also of help. The purpose

    of these guidelines is to familiarize the user with the data requirement, the source

    of data and analysis techniques to be used, considering different constraints in

    assessing hydrologic inputs, in determining water availability and the peak flooddischarge at the project site. Water availability decides the techno-economic

    feasibility of the project and flood discharge is important for safe design of the

    structures.

    In general the objectives of these guidelines are:

    (1) To provide the user the knowledge of data requirement, about the

    source of data, and evaluation and extension of data.

    (2) To familiarize the user with various methods of synthesizing data at an

    ungauged site.

    (3) To provide an overview of various analysis techniques available to

    work out stream flows with time variability and peak flood discharge.

    (4) To provide knowledge and hydrologic considerations for inputs other

    than stream flow.

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    5/28

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    6/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 3

    (c) Forest Department

    (d) District Revenue Department.

    4. Collection of Data

    The data from above sources may be obtained after receiving permission

    from competent authority or on payment if available on sale.

    As stated earlier, the observed stream flow data is generally not available

    at the proposed SHP site and in many cases not even a single rain gauge exists

    in the entire catchment. In such a situation, a gauging station near the site and a

    few rain gauges in the catchment should be established. The existing guidelines

    of CEA, CBI&P and IREDA recommend that discharge measurements should be

    carried out for a minimum of two years covering two lean seasons and one

    monsoon season. Two years discharge data is too short to develop a long term

    series but it gives an idea about minimum discharge expected to be available

    and can be used with the data from other sources to make use of indirect

    methods for estimating flows and flood discharge. In order to have a longer

    period observed discharges, the gauging site should be established at the

    earliest and the data till the preparation of DPR should be made use of in

    hydrological studies. For gauging and discharge measurement techniques

    readers may refer guidelines for site investigations.

    5. Assessment of Quality of Data

    For assessing the quality of data, knowledge of methods of measurement

    and observations, the instruments used and the frequency of observations is

    essential. For example if discharge measurement is done with the help of floats,

    the discharge data should be corrected with a suitable factor which is taken as

    0.89. The adequate length of data is essential for any hydrologic analysis. The

    longer the length of data more is the confidence on the reliability of the analysis.

    Generally data of 25 to 30 years is considered adequate for any statistical

    analysis. Quality of data is also adversely affected if there are missing data and

    to increase length of data the missing data is filled-in. The normal procedures

    adopted are mentioned in following para.

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    7/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 4

    6. Filling-in Missing Data

    It is generally observed that rainfall and discharge data in many cases are

    found missing for some days and even for months. Attempt are made to fill-in

    missing links using standard methods to make a continuous record. The

    techniques used are:

    (i) Using values observed earlier for the missing period

    (ii) Interpolation from adjoining values by plotting a smooth curve.

    (iii) Using the average proportion with normals for the adjoining stations.

    Atleast three stations be used.

    Nx =

    ++

    c

    c

    b

    b

    a

    ax

    P

    N

    P

    N

    P

    NP

    3

    a , b & c are three adjoining stations. N is normal (mean) precipitation, P is

    precipitation during shorter period, and x is station of missing data. Use of

    this method is generally limited to precipitation time periods of not less

    than a months duration.

    (iv) Rainfall run-off correlation may be used. Runoff at a downstream site

    should be adjusted for upstream withdrawals before establishing rainfall

    runoff correlation. Missing gaps in rainfall data can be conveniently filled-in

    by using HEC- 4/6 programme of US Army Corps of Engineers.7. Consistency Checks

    The consistency of the precipitation as well as the stream flow data can be

    checked by the technique of double mass analysis. In this method a graph is

    plotted of cumulative monthly (or any other time period) values at a station to be

    checked against those of a reliable or a group of adjoining reliable gauging

    stations of the same period. The data of the station in question is consistent if the

    above plot is a straight line. The change in the slope of the double mass curve

    shall be investigated as it may be caused by change in location of gauging site,

    change in measurement techniques, changes in river regime or any other man

    made interference.

    The consistency of data can also be checked by:

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    8/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 5

    (i) A study of stage discharge curve of different periods and outliers

    may be examined and corrected.

    (ii) Comparing the monthly and annual runoff with corresponding rainfall in

    the catchment.

    (iii) Comparing monthly specific flows (flow per unit catchment area) with

    corresponding figures at other sites on same river or the adjoining

    rivers.

    8. Processing and Presentation of Data

    8.1 Rainfall Data

    It is, generally, used to develop rainfall runoff correlation. The rain gauge

    records point rainfall and the areal distribution is worked out from the rain-gauge

    records of the rain-gauges located in side or around the catchment. The average

    catchment rainfall is estimated on 10-daily or monthly or annual basis by using

    one of the following methods.

    (i) Arithmatic mean method used commonly when large number of

    rain-gauges are uniformly distributed in catchment.

    (ii) Thiessen Polygon method used when a few rain-gauges are

    located in and around the catchment.

    (iii) Isohyetal. method

    used when large number of rain-gauges arelocated in the catchment. It is time consuming.

    HEC 4/6 package can be used to compute average rainfall in the

    catchment. If long term data is available then 50%, 75% and 90% dependable

    rainfall can be worked out and used for further hydrological analysis.

    This analysis of rainfall data is very useful if the raingauges in the

    catchment and their long term record is available but generally it is rarely

    available in the catchments of small hydro projects, which harness flow of small

    catchments.

    8.2 Stream Flow Data

    The stream flow data shall be processed and compiled in suitable formats

    / tables for appropriate time units generally as 10 day average, monthly and

    annual runoff, annual maximum flow.

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    9/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 6

    9. Extension of Period of Record of Stream Flow Data

    9.1 When Short Term Data (5 to 10 years) is available at Project Site

    Stream flow data of long duration is generally, not available at the

    proposed project site. The short term data is normally extended with the help of

    long term data of other sites on the same stream or in the adjoining catchments.

    Sometimes the rainfall data is also used to extend the short term discharge data.

    The correlations are generally developed through regression analysis of short

    term data of the site with the corresponding period data of other sites where long

    term data is available. Generally following two regression models are used:

    Bivariate linear y = a + bx

    Bivariate curvilinear y = axm (log y = log a + m log x)

    A correlation is considered good when correlation coefficient is near unity.

    In a discharge discharge correlation x and y are discharges of two sites

    and by using the correlation the short term discharge data is extended with the

    help of long term data. In a rainfall runoff correlation x may be for rainfall values

    and y the runoff.

    Standard computer programmes for statistical relations can be used to

    determine the best fit regression model. This can also be done manually using

    least square method (any standard book on hydrology, CBI&P manual etc. may

    be referred for the computations).

    9.2 When stream flow data of two lean seasons and one flood season at

    site are recorded:

    In small hydro project sites even the short term data is generally not

    available and project reports are based on the minimum requirement of

    discharge observations of two lean seasons and one flood season. In such

    situations the following approximate method of determining discharges of

    different dependability utilizing the rainfall data may be used:

    (i) An annual rainfall duration curve for the catchment of the project is

    developed (a typical curve is shown in fig. 1).

    (ii) Find annual rainfall of different dependability (R50, R75, R90) from the

    curve.

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    10/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 7

    (iii) Find mean annual rainfall of the catchment for the period of discharge

    observation (Rm).

    (iv) Find the ratios of annual rainfalls of different dependabilities (as

    determined in (ii) to the mean annual rainfall of the catchment (as

    determined in (iii)).

    mmm R

    R

    R

    R

    R

    Rr 9090

    75

    75

    50

    50 and; ===

    (v) Mean monthly discharges of 50%, 75% and 90% can be computed by

    multiplying the mean monthly discharges of the observed period by the

    corresponding ratios (as determined in (iv)).

    10.0 Flow Assessment for an Ungauged Catchment

    Many times situation arises when the discharge observations are available

    and flow assessment has to be made for the preparation of project report.

    Depending on the availability of data of other sites or basins one of the following

    method may be adopted.

    10.1 Long Term Data of some other site:

    When long term flow measurement data of a site on the same stream or

    adjoining stream is available. It can be transposed to the proposed site in

    proportion to the catchment areas of the two sites.

    2

    2

    11

    2

    1

    2

    1 Qi.e. QA

    A

    A

    A

    Q

    Q==

    1. Denotes ungauged site and 2 the site for which flow data is available.

    10.2 Regional Specific Discharge

    In this method the discharge data of hydro meteorologically similars river

    basin is used. The data is converted with specific discharges which is defined as

    discharge per unit catchment area. Generally monthly hydrographs of specific

    discharges of a specific dependability of a number of adjoining basins are plotted

    on a graph. Typical 50% dependable specific discharge hydrograph of a number

    of basins are shown in Fig. 2. A mean hydrograph may be drawn which will

    approximately represent the specific discharges of 50% dependability for the

    ungauged catchment in the region. The monthly specific discharge values of the

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    11/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 8

    mean hydrograph when multiplied by the area of the ungauged catchment will

    give the 50% dependable discharge series. Similarly the discharge series of

    other dependabilities such as 75%, 90% can be generated.

    10.3 Regional Model

    A regional model for generating flows of different dependabilities has been

    developed by AHEC and Department of Earth Sciences of I.I.T. Roorkee and NIH

    Roorkee under UNDP GEF Program (MNES, Govt. of India) which is useful for

    generating the flow duration curve of an ungauged catchment in Himalayas.

    11.0 Water Availability Assessment

    Water availability with time variability at the proposed project site is

    essential to estimate the power potential and annual energy generation on which

    depends the financial variability of the project. Since small hydro project is a run-

    of-river scheme the flow duration curve (FDC) is used to know the time variability

    of flow at a location. The FDC is a simple depiction of flow at a location against

    percentage of time. It shows a discharge which has equaled or exceeded certain

    percentage of time out of the total time period which is generally taken as one

    year. Typical FDCs are shown in Fig. 3. The shape of FDC reflects the

    hydrological characteristics of the stream. FDC of shape A in Fig. 3 belongs to a

    flashy stream in which high floods occur for a very short duration and shape C

    reflects the characteristics of a stream in which variation between high and low

    flows throughout the year is not large.

    11.1 Application of FDC

    For water availability studies for a SHP the FDC is drawn for 90%

    dependable years. The 90% dependable year is calculated by arranging in

    descending order, the annual runoff of all the years for which observed or

    extrapolated / extended discharge data is available and using Weilbuls formula:

    100x1+

    =N

    mP

    P is dependability percent, m is the rank of runoff of the desired

    dependability, N is the number of data. If P is 90% N = 19, m works out as

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    12/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 9

    181)(19x100

    90=+ . Thus 90% dependable flow year will correspond to the runoff

    which is at rank 18 from the top.

    For working out the FDC for 90% dependable year, the 10-day discharge

    series of that year is considered. These 36 discharges are arranged in

    descending order and percentage of time each has exceeded or equaled is

    worked out using the above Weilbuls formula. Discharge of rank first will be

    equaled or exceeded by 100x136

    1

    +i.e. 2.7% of time. Similarly discharge of rank

    2 will be equaled or exceeded by 5.4% of time. In this manner percentage of time

    equaled or exceeded by all the 36 discharges can be worked out and potted. A

    typical FDC is shown in Fig. 4. From this curve discharges of variousdependability such as Q90, Q75, Q50 etc. may be obtained. The energy

    corresponding to Q90 will be the firm energy from the project. Secondary energy

    can be generated if the system is designed for a higher discharge. This will,

    however, be generated for a part period of the year. To decide the design

    discharge cost of generation is worked out for four or five discharges of

    dependability less than 90% and the discharge which gives the minimum cost of

    generation is selected for further planning and design of project.

    This procedure of developing and using FDC is possible when long term

    discharge data at site observed or extended is available.

    11.2 Application of NIH Model

    Generally long term discharge data at the site of SHP is not available, the

    model developed by NIH for ungauged catchments based on

    hydrometereologically similar regional catchments can be used. In this model

    FDC for an ungauged catchment is derived using regionalization procedure. The

    regions are identified as below:

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    13/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 10

    Regions States covered

    A&B Jammu and Kashmir

    C Himachal PradeshD Uttarakhand

    E Jharkhand

    F Sikkim

    F West Bengal

    G Assam

    G Arunachal Pradesh

    H Meghalaya

    I Manipur, Nagaland, Tripura, Mizoram

    For each region based on available data of gauged catchments a mean

    FDC of that region in terms of Q/Qman and percentage of time is developed. The

    regional flow estimated values for (Q/qmean)D for various dependability levels (D)

    are given in Table 1. Qmean for each gauged catchment is related with catchment

    area (A) in the following form.

    Qmean = CAm

    Where C is coefficient and m is exponent. The values of C and m for each region

    (A to I) are given in Table 2.

    Knowing the area of ungauged catchment Qmean can be worked out using

    the values of C & m of the region in which the ungauged catchment lies. This

    value of Qmean multiplied by the factor (Q /Qmean )D for that region from table 1 will

    give the required D% dependability flow (QD) for that ungauged catchment. After

    obtaining QD for different value of D the FDC of the ungauged catchment can be

    plotted for further planning purposes.

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    14/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 11

    11.3 When Only Observed Discharge of Two Non-monsoon Seasons areavailable:When no other information except the discharges of two non-monsoon

    season at the proposed site is available and no analysis for extension of data is

    possible, the design discharge for the feasibility stage planning may be taken asthree times the minimum observed discharge at site during two non-monsoon

    seasons.

    11.4 Energy Curve

    The FDC on a different scale represents the energy curve because the

    energy is power multiplied by time and the power is directly proportional to

    discharge. It is given by

    P = 9.81 Q H

    Where,

    P is power in kW

    Q is discharge is cumec

    H is net head to be utilized in generation in metre

    is overall efficiency of generating equipment.

    11.5 Daily Pondage

    A run-of-the river scheme or a small hydro project can be run as a peaking

    station if daily pondage capacity is provided at the diversion site. It is generally

    provided by installing high head gates.

    When a scheme is designed for a discharge more than Q90, all the

    machines provided will generate when during monsoon the design discharge is

    available and during non monsoon period when discharges are low most of the

    machines will be idle. If daily pondage capacity is provided say for 20 hours in a

    day, the power plant can be run at full capacity for four hours during peak

    demand. The pondage requirement estimation is as illustrated below:Design discharge is 5 cumec, the minimum flow is 1 cumec. Let the hours

    for which the ponding of minimum flow is required to run the power plant for

    peaking are X

    X = L = (24 - X ) (5 1)

    X = 19.2 hours.

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    15/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 12

    The power plant will run at design discharge of 5 cumec for 4.8 hours in a

    day. The pondage capacity between FRL and MDDL required will be 1 x 3600 x

    19.2 = 69120 cum.

    12.0 Estimation of Flood Discharge

    Estimation of flood discharge is essential for the safety of the diversion

    structure of the SHP which is generally a weir or barrage or small dam without

    large storage capacity. In such a case moderation of flood peak is not possible

    and so the waterway to pass flood should be of adequate capacity. The flood

    discharge for which the structure is designed is called design flood. It is fixed

    after due consideration of economic, hydrologic factor and safety of life and

    property in the downstream. On the basis of the guidelines set out in IS Code

    11223 1985 the design flood for the diversion structure shall be a discharge of

    100 year return period.

    12.1 Computation of Design Flood

    12.1.1 Flood Frequency Method

    For estimating the design flood one of the standard flood frequency

    methods may be used. Large number of flood frequency methods are available

    for which the reader can refer any standard book on Hydrology. For the use of

    any method of flood frequency analysis long term record (about 30 years) of

    observed flood peak discharges is required. Gumbels method is generally

    recommended for small hydro projects.

    (a) According to Gumbels method of moment the flood frequency equation is

    XT = x + s (0.78 Y 0.45)

    Where,

    XT is flood peak of return period T.

    x is average value of annual flood peaks.

    s is standard deviation of flood peak series.

    Y is called reduced variable and is a function of T and its values are as

    below:

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    16/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 13

    T Y

    2 0.37

    5 1.5

    10 2.25

    25 3.2

    50 3.9

    100 4.6

    (b) Method of least square can also be used. The flood frequency equation is

    of the following form:

    XT = A + B.Y

    Where,

    Y = - log log1T

    Tand

    T =m

    N 1+

    m is the rank of peak discharge in descending series of flood peaks and N

    is the number of flood peaks considered, A & B are constants and can be

    worked out by using method of least square.

    After determining A and B, XT for any value of T desired can be worked out from

    the above equation.

    (c) Data Plotting Method

    The annual flood peak data shall be plotted on a semi log paper. The

    data events are plotted on the ordinate which has the rectangular scale and the

    return periods are plotted on the abscissa which has the logarithmic scale. For

    example, if 20-years flood data is available and arranged in descending order

    then highest flow is assumed to have a return period of 20 years, the second

    highest flow a return period of 10-years, the third highest a return period of 6.67

    years and so on. Such a plot is shown in Fig. 5. It is seen that peak flows of

    watersheds generally produce linear or near linear curves when plotted on semi

    log paper. The extrapolation of these linear plots can give the peak flood of 100

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    17/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 14

    year return period. This extrapolation can also be done by developing the best fit

    line using method of least square to determine the constants in the following

    equations:

    XT = A + B log10 T

    12.1.2 When Peak Flood Data at Site is not available

    Generally, long record of flood peaks at SHP sites is not available. In that

    case one of the following approaches may be adopted depending on availability

    of data.

    (a) If long term record of flood peaks of some other site on the same stream

    or a site in adjoining hydrometereologically similar catchment is available, the

    flood frequency analysis can be carried out, by methods given above, to

    determine the peak flood of 100-year return period and the same can be

    transposed to the ungauged site of the SHP in proportion to area by using

    following equation:

    4/3

    =

    u

    g

    u

    g

    A

    A

    Q

    Q

    Where,

    Qg is flood peak of 100 year return period of site of which record is

    available.Ag is catchment area of site of which record is available.

    Qu is flood peak of 100 year return period of ungauged site.

    Au is catchment area of ungauged site.

    (b) In planning SHP, records of long term flood discharges are seldom

    available. In such cases an alternative approach would be to estimate

    storm rainfall of suitable duration with desired return period say 100 years.

    This information can be obtained from IMD. A suitable unit hydrograph (a

    characteristic of hydrological the catchment) is derived for the catchment.

    It is defined as a flood hydrograph of surface runoff resulting from a unit

    depth (1 cm) of excess rainfall distributed uniformly over the basin area at

    a uniform rate during unit period (say 3 hr, 3 hr, 4 hr, 6 hr etc.). It can be

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    18/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 15

    derived from the observed flood hydrographs of a few years if available at

    the site and the storm rainfall record causing these flood hydrographs.

    If observed flood hydrographs are not available, a synthetic unit

    hydrograph based on catchment characteristics can be developed. The

    procedure for computations of flood hydrograph using the unit hydrograph

    and the storm rainfall is given in CWC Publication Estimation of Design

    flood Recommended Procedures 1972, Readers can refer to any

    standard text book on hydrology for unit hydrograph method of working

    out flood hydrograph.

    (c) Use of Regional Unit Hydrograph

    When no discharge data at site is available, the parameters of unit

    hydrograph are evaluated by a regional approach using data of adjoining

    basins. CWC has made extensive studies of small catchments of river

    basins dividing them in 27 sub zones and has developed regional unit

    hydrograph parameters to estimate peak flood discharges resulting from

    50 and 100 year return period storm rainfalls. For the derivation of regional

    unit hydrograph and its application to compute flood hydrograph,

    reference may be made to relevant CWC study report of the sub zone to

    which the catchment of proposed SHP belongs.

    (d) Regional Flood Frequency Analysis:

    Flood frequency analysis by Gumbels method should be carried out and

    curve prepared for as many gauging stations in the region as possible

    whose flood records of atleast 10-15-years are available. A homogeneity

    check should be carried out.

    A set of flood ratios (ratio of flood to mean annual flood) is computed for

    each station over a range of arbitrarily selected return periods with the

    help of frequency curves.

    For each of selected return periods the mean of the ratios of all the

    stations is computed. The resulting means are the flood ratios for the

    regional frequency curve. These are plotted on extreme value probability

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    19/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 16

    paper and best fit line by method of least square can be determined. This

    line is the required regional frequency curve.

    This curve can be used to determine flood of a specific return period only

    when mean annual flood of ungauged catchment is known. For this

    purpose the mean annual floods of all the gauged stations used for

    developing regional frequency curve are correlated with their catchment

    areas either by plotting the data on a logarithmic paper or through a

    suitable regression model. By using this relation the mean annual flood of

    ungauged catchment corresponding to its area is worked out. This mean

    annual flood multiplied with flood ratio corresponding to the desired return

    period obtained from regional frequency curve will give the flood of desired

    return period of ungauged catchment.

    (e) When no data of discharges and rainfall are available, the following two

    methods can be used to assess the peak flood at site.

    (1) Based on Field Information:

    A study of physical features near the stream at site shall be made to find

    the signs of high flood mark which shall be confirmed from local enquiry

    from old persons living near the stream and the records of local revenue

    officials and department of Bridge and Roads. After ascertaining the high

    flood level, the flood discharge corresponding to this level can be

    computed by using Mannings equation. Area of river cross section (A) at

    site and river slope (S) shall be obtained by conducting the surveys. The

    coefficient of Manning n shall be assumed on the basis of physical

    features of river at site for working out the peak flow from the following

    equations:

    2/13/21SR

    nV =

    Where, ,P

    AR = P is the perimeter below high flood mark.

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    20/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 17

    (2) Use of Empirical Formulae:

    There are a large number of empirical relations to estimate peak flood

    flows on the basis of catchment area. The most commonly used formulae

    is of Dickens.

    Q = CA3/4

    Where, C is the coefficient which varies from region to region. On the

    basis of discharge observations of long periods at various locations the

    country is divided into regions and each region is assigned a value of C for

    the use in Dickens formulae.

    12.2 Spillway Design Flood and Construction Floods

    As already stated above, a SHP is a run-of-river project where there is no

    significant storage at river diversion site. Hence, peak flood cannot be

    moderated. Therefore, the water way for the barrage / weir or spill way of

    low height diversion dams shall be provided for the design flood. The

    design flood is decided on consideration of economic and hydrological

    factors as well as the safety in the downstream. Normally the design flood

    for barrage / weir is taken as flood of 100 year return period and SPF for

    the spillway of a diversion dam.

    During construction of a diversion structure the river flow has to be

    diverted. The diversion arrangement has to be planned and designed for a

    certain discharge which is always associated with some amount of risk of

    being exceeded. This again depends on hydrologic, economic factors and

    the construction sequence and schedule. When the diversion is to be

    done for non-monsoon flow and monsoon flood can be allowed to pass

    over in complete barrage / weir, the diversion arrangement can be

    planned and designed for the maximum non-monsoon flow in the past 10

    years. In case the monsoon flood can not be allowed to pass the

    incomplete structure the diversion for a SHP project can be planned for a

    flood a return period of 4 to 5 times the construction period of the project.

    Suppose the construction will take 3 years to complete, the diversion

    design flood shall be of 15 to 20 years return period. However, there is

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    21/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 18

    always a risk of its being exceeded. In that case the expected damage

    should be assessed and compared with the extra cost involved in

    designing diversion arrangement for a flood of higher return period.

    13.0 Sedimentation

    SHPs generally operate at full installed capacity during monsoon period

    like any other run-of-river scheme with a small diversion structure without

    storage. During this operation silt laden water of monsoon flows is diverted into

    water conductor. It is seen to cause damage and sometimes very serious

    damage to under water components of the generating equipment such as

    runners, guide vanes etc. resulting in loss of generation and costly repair and

    maintenance of equipment. The problem is more severe in projects located on

    Himalayan streams which carry lot of sediment during monsoon.

    Studies have shown that the rate of sediment erosion may be expressed

    as:

    W S1, S2, S3, S4, Mr Vx

    Where, w is rate of erosion, S1, S2 S3, S4 are the coefficients of sediment

    characteristics such as concentration, hardness, size and shape, Mr is

    coefficient of erosion resistance of base metal of equipment, and Vx is

    relative velocity of flow in turbine with exponent x which depends on typeof turbine (x = 3 for Francis turbine, 2.5 for guide vanes, 2.5 for nozzles of

    Pelton wheel and 1.2 for Pelton wheel buckets).

    It has been observed that high concentration of even fine angular quartz

    particles (hardness 7 on Mohs scale) cause maximum erosion in high

    head power plants. A variety of sediment exclusion and extraction

    measures are provided to reduce size and concentration of sediment

    particles in the flow reaching the generating equipment in order to reduce

    the damage due to silt erosion. The planning and design of these

    measures depend on the sediment characteristics. Hence, even at the

    planning stage the above characteristics of sediment i.e. size, shape,

    hardness and concentration, which are site specific should be assessed

    with as much accuracy as possible for planning and design of cost

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    22/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 19

    effective sediment exclusion and extraction measures. Sediment sampling

    at site for concentration, sieve analysis and petrographic analysis (for

    mineral composition and shape) is essential at the diversion site. The

    knowledge of these sediment characteristics is also important for turbine

    manufactures.

    The design and dimensions of desilting measures depend on the size of

    particles which is to be extracted. There is no universally accepted

    criterion to decide the size of particle to be extracted. As a guide line if the

    presence of quartz in sediment is not significant, extraction of (+) 0.5 mm

    size particles through vortex type desilting measures is adequate for

    medium and high head plants. If quartz is predominant desilting basin to

    extract + 0.2 mm is generally provided. It may be combined with other

    measures such as vortex tube, ejector etc. for greater effectiveness.

    14.0 Water Quality

    Besides the sediment, the chemical analysis of water is important to have

    a knowledge of presence of salts and the nature of water (acidic or alkaline)

    which will have the effect on the metal of gates and equipment, and concrete

    structure. The parameters generally determined in chemical analysis are:

    1. Dissolved solids

    2. pH value

    3. Suspended solids

    4. Total hardness

    5. Sulphates, carbonates, bi-carbonates, chlorides

    6. iron, calcium, magnesium

    7. Electrical conductivity.

    8.

    15.0 Other Hydrological and Meterelogical Data Required:

    15.1 Tail water rating curve:

    15.1.1 It is the stage vs discharge curve and is required at the diversion site and

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    23/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 20

    at the downstream of the power house for the planning design and

    operation of the project. If gauge discharge data for a couple of years is

    available the required curve can be obtained by plotting this data. On

    logarithmic paper this is generally a straight line. It can be extrapolated for

    peak flow.

    15.1.2 If the gauge discharge data is not available, it can be developed by using

    Mannings equation as described in para 12.1. From the river cross

    section, discharges are worked out for different water depths in the section

    and the plot gives stage discharge curve.

    15.2 Metereological Data

    Besides the rainfall data the following metereological data of the proposed

    site for SHP are required for proper planning, design and operation of the project.

    These can also be obtained from IMD.

    (i) Air and water temperature in different days of the year with monthly

    and seasonal maxima and minima.

    (ii) Wind velocity and direction: Maximum velocity is required for design of

    structures.

    (iii) Evaporation : It is required to assess loss of water in reservoir, if

    storage is provided.

    (iv) Annual Climatic Changes: It is needed to plan the construction

    sequence and schedule.

    (v) Seismicity: It is required for design of structures. Based on

    geographical location of project, it can be assessed from IS:1839.

    References:

    1. Hydrology by Ven-ta-Chaw

    2. Hydrology by K.N. Mutraja

    3. Hydrology by R.S. Varshney

    4. Manual on Planning and Design of SHP, Pub. No. 280 CBI&P.

    5. Guidelines for Planning SHP, CEA.

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    24/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 21

    6. Report on UNDP- GEF Hilly Hydro Project, Vol. III Regional FDC

    Published by MNES, Govt. of India, 2002.

    7. Estimation of Design Flood Recommended Procedure CWC, Sept.

    1972.

    8. Sub-Zone Flood Estimation Reports, CWC.

    9. IS : 11223 1983.

    10. IS : 1839.

    11. Small and Mini Hydropower Systems Jack, J. Fritz., McGraw Hill,

    1982.

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    25/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 22

    Table 1: Regional Flow Estimates for Various levels of Dependability

    Region Regional Values for (Q/Qmean)D For Various Dependability Levels

    D = 25% D = 50% D = 60% D = 75% D = 80% D = 90%

    A 1.1562 0.6584 0.5428 0.4011 0.3577 0.2686

    B 1.2240 0.8434 0.7360 0.5888 0.5396 0.4304

    C 1.1797 0.6609 0.5399 0.3917 0.3466 0.2544

    D 1.2828 0.8364 0.7078 0.5315 0.4729 0.3447

    E 0.7374 0.2711 0.1974 0.1226 0.1031 0.0675

    F 1.0942 0.5089 0.3896 0.2551 0.2171 0.1444

    G 1.3075 0.8500 0.7148 0.5270 0.4640 0.3257

    H 1.1436 0.4909 0.3551 0.2053 0.1646 0.0913

    I 1.2451 0.5511 0.3957 0.2198 0.1716 0.0856

    Table 2: Values of the parameters of the Regional Models for Mean Flow

    Sl.No.

    Region State covered m C Coefficient ofcorrelation

    (R)1. A Jammu & Kashmir

    (Except Leh & Kargil)

    0.06046 3.8189 0.0808

    2. B Jammu & Kashmir

    (Leh & Kargil)*

    Q/A = (1/2)(Q/A)Leh + (Q/A)Kargil

    = 0.05804

    3. C Himachal Pradesh 0.86811 0.1200 0.8759

    4. D Uttar Pradesh/Uttarakhand 0.89075 0.0463 0.8174

    5. E Bihar/Jharkhand 0.74795 0.0652 0.7742

    6. F West Bengal & Sikkim 0.98920 0.0577 0.8467

    7. G North Assam & Arunachal

    Pradesh

    0.26817 2.2807 0.3706

    8. H South Assam & Meghalaya 0.48589 1.4136 0.6820

    9. I Manipur, Nagaland,

    Mizoram & Tripura

    1.22343 0.0151 0.9435

    *An average model developed due to lack of data.

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    26/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 23

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    27/28

    AHEC/MNRE/SHP Standards/General Manual on Project Hydrology /July 2008 24

  • 8/6/2019 Manual Standards Guidelines Ahec Roorkee

    28/28