Manpower Loading Cck Loykrathong Direct

download Manpower Loading Cck Loykrathong Direct

of 1

Embed Size (px)

description

รร

Transcript of Manpower Loading Cck Loykrathong Direct

  • Project:Loykrathong (Solvay)

    W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36

    1 Foreman piping 2 2 2 2 2 2 2 2 2 2 2 2 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 2 2 2 2 2 2

    2 Foreman Equipment 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1

    3 Welder pipe C/S 0 0 0 0 2 2 4 4 4 4 4 4 4 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 2 2 2 2

    4 Welder pipe S/S 0 0 0 0 2 2 4 4 8 8 8 8 8 8 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 6 4

    5 Welder pipe support 0 0 0 0 2 2 2 2 2 2 2 2 4 4 4 4 4 4 4 4 6 6 6 6 5 6 6 6 6 6 4 4 4 4 2 2

    6 Fitter pipe 0 0 12 12 16 16 16 16 16 16 16 16 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 16 16 16 16 16 16

    7 Fitter Mechanic 0 0 8 8 8 8 8 8 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 8 8 8 8 8 8 8 8

    8 Millwright 0 0 0 0 2 2 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 2 1 1 1 1 1 1

    9 Rigger 4 4 4 4 4 4 4 4 8 8 8 8 12 12 12 12 16 16 16 16 16 16 16 16 12 12 8 8 8 8 4 4 4 4 4 4

    10 Painter 0 0 0 0 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 12 12 12 12 12 12 12 12 6 6 6 6

    11 Scraffolder 0 0 0 0 24 24 24 24 24 24 24 24 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 24 24 24 24 24 24

    12 Civil Helper 6 6 6 6 6 6 6 6 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 6 6 6 6 6 6 6 6

    TOTAL DIRECT 13 13 33 33 75 75 79 79 104 104 104 104 173 173 175 175 181 181 181 181 183 183 183 183 184 185 179 179 164 164 94 94 84 84 78 76

    CCK Engineering and Construction Co.,Ltd. (Piping and Mechanical)

    NOV'14 DEC'14 JAN'15 FEB'15 MAR'15 APR'15

    MANPOWER LOADING

    REV.00

    DIRECT MANPOWER DATE:27.07.14

    NO PositionJULY'14 AUG'14 SEP'14