MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director,...
Transcript of MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director,...
![Page 1: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/1.jpg)
^z-
MANATEE COUNTY GOVERNMENT
AGENDA MEMORANDUM
SUBJECT IFB 00-6699-MP / Rehabilitation of Lift
Stations TYPE AGENDATTEM Consent
BATE REQUESTED IS October 3, 2000 DATE SUBMITTED/REVISED September 18, 2000
BRIEFINGS'/WHO? N/A CONSEQUENCES IFCEFERRED,,; N/A
DEPARTMENT/DIVISION Financial Management/Purchasing AUTHORIZED BY TITLE Jim Seuffert, Dire
TE^lS^TE|%. Rob cuthbert' Purchasing, 3054 TE^PIS^NS^, Janet MCAfee- Director pro^ ^ 5047
ADMIMS|E^^ APPROVAL
1111111:;,,,. ,„:„„,^ 111111 ,_
1 .,,.,„ 11111:::::'^-•ACnON DESIRED ^ . 1 ——— ,:!„„,,, ;,:,,., „,,!:, •^•
INDrcaTEWHETHER "REPORT or "DISCUSSION, "FORM OF MOTION, or ''OTHER ACTION REQUIRED:
Authorization to award Bid No. 00-6699-MP Rehabilitation of Lift Stations to the lowest responsive, responsible bidder meeting
specifications, TLC Diversified, Inc., Sarasota, FL, for a total cost of $263,460 and; subsequent execution of contract and simultaneous
dating of performance/payment bond and acceptance of insurance certificate.
"'::::: 11111' 11: — 1111
- : 1' -":' ":
"ENABLING/REGULATING 'AUTHORITY -:,?, | '17.11111
, ',::;. .
'w'
Federal/Stnte law(s), adminiitratlve ruling(a). Manatee Count)' Comp Plan/Land Development Code, ordinances, reaolutioni, policy.)
Ordinance 99-37, Purchasing Code Article 4
:, ̂ : ,-11 - , , ^ :.:« i S K,:,:,:',;: „ ^ "'^':: 13 ifi S:l 3,::::: ,„ „:._, , !
BACKGROUND/DISCUSSION 1 1111""::''"'" ' 1:':'
i. a ,:•:, • . ,:„„:::. , „ :;1 :; E, , ,::: i:" 1
Public Works requires the rehabilitation of eight triplex submersible pump lift stations at various sites throughout the County
to maintain sewage flows. Project Management is managing this work for the Public Works Department, Bayshore Lift Stations
and Collections.
Continued on page 2
HAS COUNTY ATTORNEY REVIEW BEEN REQUESTED 1 Indicate "NO" or "YES" ®1 right.
,,' If "NO," proceed tottA/lBtelow.1 if'yES," proceed to2A/2B below::,;111; • • lli1:11:1:: ft i:;:s •:. NO
1):::i:IF"NO"TOABdvE11. : ,,:.:„;, ''"ilillll,,,
: :l:::::::::::::::'::8:il,:l 111:" 1, ' -1.::;'1;:'1'1 \ •
A) PllEASE EXPLAIN BELOW: (see alMi following aeetionIB re: contntct, agreement, leane, et<-) ,
Not Required. This is a pre-printed purchase order form using the County's terms and conditions.
B) IF A CONTRACT, AGREEMENT, LEASE OROTHER DOCUMENT WAS PREVIOUSLY APPROVED, STATE YEAR OF LAST USE @ RIGHT:
2) IF "YES" TOTIRST QUESTION IN THIS SECTION, ,,, _, 1" l"i ::::i: :1::11 11 1 111 1"11 ;;:: ;• ,
111 " ".';::,:;::;;"1,,;,; ,,,;:;:; :: „:: ,:,::\"'' 11 1
; ;':::;" ":> 1:1 . ,, '„',
A) HAS ENTIRE MATTER, OR ONLY A PORTION. BEEN REVIEWED? IF ONLY A PORTION, WHICH PORTION?
B) Di IP NOT; PLEASE EXPLAIN. A COPY OF FINAL COUNTY
ATTORNEY MEMO RE THIS MATTER MUST BE ATTACHED (If comments were verbal. »o imiicnte.)
ATTACHMENTS: (List in order ill attached)
Ltr. Recommendation: Tabulation of Bids; Vendor Report(various
correspondence); Sarasota County Ltr.
INSTRUCTIONS TO BOARD RECORDS:
N/A
COST $263,460 8 ̂ SOURCE (ACCTJt^ NAME): !:: 4046022181563/Upgrade Lift Stations
COMMENTS:!,| N/A AMTJFREQ. OF RECURRING COSTS
(ADWCH FISCAL IMPACT STATEMENT) 1 •••'11:'":'; l1?^^/^_____^________^______'
N/A
F:\USER\MARGEP\WPDOCS\AGENDA\006699mp.agn.wpd
^1
/^
![Page 2: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/2.jpg)
AGENDA MEMORANDUM (cont'd) Page 2
• 06/20/00 through 07/14/00 appropriate bid procedures were followed. Notice of bid's availability was sent to 112
prospective bidders, subcontractors, and suppliers; five bids were received.
• Apparent low bidder, DeJonge Excavating Contractors, Inc., Venice, FL ($234,056) was non-responsive as this bidder
does not hold a General Contractor's license (confirmed with Homer Williams of the Florida Department of Business
and Professional Regulation on August 28, 2000).
• Estimated start-up for construction is 11/01/00 with completion within 210 days for an estimated completion date of
05/30/01.
Agenda Memorandum Fonn Last Revised: 1/7/98 @ 2:16 pm 006699mp.agn.wpd last revised on 9/18/00 @ 3:26 PM by:
![Page 3: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/3.jpg)
MANATEE COUNTY GOVERNMENT T r
;
MEMORANDUM
DATE: September 14, 2000
TO: R.C. "Rob" Cuthbert, C.P.M., Purchasing Manager
^^-<c ^y^
FROM: Janet E. McAfee, Director, Project Management
SUBJECT: Recommendation of Award-IFB #00-6699MP
Rehabilitation of Lift Stations
The bids for the above referenced project have been reviewed by staff. The bid tabulation
form is attached for your review. Based on the factors described below, we recommend
award of the above referenced contract to the lowest responsive, responsible bidder, TLC
Diversified, Inc. in the amount of $263,460. The construction cost estimate was $200,000.
The additional funding required to award the project is available in the project.
The apparent low bidder on the project was DeJonge Excavating Contractors, Inc.
However, as stated in Section 00020-1, B.02 "Bidder shall possess a General Contractor's
License for the work which is the subject of this bid..." We have been informed by Marge
Perenich that Florida Department of Business and Professional Regulation records indicate
DeJonge does not possess such a license.
The Contractor's Questionnaire, which is required to be submitted with each bid, asks
"Have you ever failed to complete work awarded to you?" Based on discussions with
Sarasota County's Construction Prequalification Coordinator, DeJonge failed to complete
the Proctor Road/Honore Avenue Force Main project for the County. Therefore, it appears
that inaccurate information was provided in the questionnaire.
The contractor included Manatee County and Sarasota County as references in the
questionnaire. Attached for your review is an interim vendor report from a currently
ongoing Manatee County project which describes the contractor's unsatisfactory work on
the project. Also, attached is a copy of Sarasota County's letter suspending DeJonge
Excavating Contractors, Inc.'s Prequalification Certification with Sarasota County.
Attached to that letter are Performance Evaluations for two recent Sarasota County
projects which show unsatisfactory performance by DeJonge Excavating.
Manatee County has previously awarded several projects to DeJonge which were
$150,000 or less and has not had significant problems with them on these projects.
Therefore, at this time we would not dispute the award of projects of $150,000 or less to
PROJECT MANAGEMENT DEPARTMENT
![Page 4: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/4.jpg)
Memorandum to Rob Cuthbert
September 14, 2000
Page 2
DeJonge Excavating Contractors, Inc. However, this position could change based on the
results of these recently awarded projects.
In summary, based on all of the above we recommend that the Rehabilitation of Lift
Stations contract be awarded to TLC Diversified, Inc. as the lowest responsive, responsible
bidder in the amount of $263,460.
To ensure proper coordination, please provide the Project Manager, Mr. Tim Hochuli,
copies of all pertinent correspondence associated with this project.
Thank you for your continued cooperation.
cc: Mike Limoge, Acting Project Management Manager
Len Bramble, P.E., Public Works Director
T^/ Timothy A. Hochuli, P.E., Project Manager
Project File: 6022181 w/enc.
<F:\USER\PUBWKS14\WPDOCS\8810\RECAWARDTRI.WPD>
PROJECT MANAGEMENT DEPARTMENT
![Page 5: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/5.jpg)
![Page 6: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/6.jpg)
VENDOR PERFORMANCE REPORT
Use this form to report unsatisfactory or good vendor performance.
A copy will be given to vendor and will become a permanent part of
The vendor's file.
Department Submitting Report: Pro-iect Management__________
Contact Person: Janet McAfee______________ Phone: x5048
Address: _________________________________________
Vendor Name: DeJonge Excavating Contractors, Inc.__________
Address: P.O. Box 3421, Venice. FL. 34293_________________
Purchase Order No.: P0000153______________ Date: 10/15/99
Commodity: Utility Construction_________________________
I. Check appropriate reason. Give explanation in Remarks
Section. Suggest remedy, if any.
Vendor failed to deliver by date on P.O. ____
Balance of order not delivered by vendor. ____
Delivery made after specified receiving hours ____
Under/over shipment ____
Damaged shipment ____
Vendor substituted for brand specified ____
Merchandise not labeled as specified ____
Vendor refuses to deliver ____
Grade or inspection evidence missing ____
Replacement request refused or unsatisfactory ____
Other - Explain in Remarks Section _X_
II. Remarks. Be accurate, complete, factual. Use reverse side if
necessary. Thank you.
See attached__________________________________________
Person initiating form: person initiating rorm: ./-, .
Tim Hochuli______________________^A^h Date: <0^2.7-<yo
Return to: Purchasing Division, 1112 Manatee Avenue West,
Eighth Floor, Bradenton, Florida 34205
![Page 7: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/7.jpg)
MANATEE COUNTY GOVERNMENT
MEMORANDUM
DATE: August 23, 2000
TO: R.C. " Rob" Cuthbert, C.P.M., Purchasing Manager
FROM: Timothy A. Hochuli, P.E., Project Manager TA^
SUBJECT: NRWTP - STORAGE PONDS/PUMPBACK STATIONS
The purpose of this memorandum is to serve as an attachment to an interim vendor report
for DeJonge Excavating Contractor's work on the above referenced project. When the
project is complete, either a complete vendor report will be prepared or this report will be
amended as needed to include new information. The Purchase Order No. is P0000153,
dated 10/15/99.
The contractor's work on the above project was unsatisfactory for the reasons summarized
below:
• Contractor did not meet submittal deadlines
• Contractor did not comply with contract document defined lines of communication
• Contractor did not properly schedule its material ordering
• Contractor made incorrect and misleading statements throughout the project
• Contractor provided inaccurate information in the submission of its bid
• Current quality of project construction
More detailed information regarding these items is provided below:
Contractor did not meet submittal deadlines
As stated in the project contract documents (Section 00030-6, C.16) "The successful
bidder will be required to submit a detailed construction schedule upon notification of award
or its intent." The notice of intent was dated 9/20/99 (see attached). At the 11/3/99
preconstruction meeting (see attached minutes) no schedule had been submitted and as
discussed at the meeting the contractor committed to having the schedule submitted by
11/12/99. A "tentative" schedule was submitted on 12/21/99 (see attached) with it being
returned for correction by the engineer on 12/22/99 (see attached). An acceptable
schedule was received in early February, 2000. The schedule was submitted over 90 days
PROJECT MANAGEMENT DEPARTMENT
![Page 8: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/8.jpg)
Memorandum to Rob Cuthbert
August 23, 2000
Page 2
after the notice of intent. Due to the tardiness of the submittal, the County could not
properly schedule emptying several effluent storage ponds which was a critical part of the
overall project. The emptying of the ponds was to be performed in a specific sequence
with guidelines provided in the contract documents, however, the specific sequence was
to be provided by the contractor.
Section 01030-3, 1.07A of the contract documents requires the Hurricane Preparedness
Plan to be submitted within 30 days after the Notice To Proceed. The Notice To Proceed
(NTP) was dated 10/18/99 with the Plan submitted 2/4/00 (see attached letter of 2/4/00).
Therefore, the Plan was submitted approximately 75 days late.
Contractor did not comply with contract document defined lines of communication
As discussed at length at the preconstruction meeting and required per the Agreement for •
the project (00500-1, see attached) "All communications involving the project will be
addressed to the County's project manager and Kimley-Horn and Associates, Inc. (design
engineer)." To facilitate minor changes it was further discussed at the preconstruction
meeting that the project inspector and plant chief operator could approve minor field
changes which had no effect on the project cost or time. During the project and to this date
the contractor has sought guidance and discussed various aspects of the project with the
engineer, and not the County's project manager, where both are called for and various
treatment plant staff who can not provide formal County direction on the project. Letters
from the contractor have included statements verifying that they had indeed sought
information from the parties described. These activities by the contractor complicated the
project's lines of communication and were discussed on several occasions with no change
in the contractor's approach.
The contractor was requested to ask project questions via Requests For Information
(RFI's). The project has had one RFI despite the numerous questions asked directly of the
engineer by the contractor during phone conversations. This approach further complicated
proper lines of communication. In addition, the contractor neglected to copy the County
on a series of shop drawing submittals as requested at the preconstruction meeting and
required in Section 00500.
Contractor on several occasions scheduled meetings, in writing, without consulting all
parties and subsequently commented how non-attendance at the meetings was delaying
their work. Examples of this problem are included in the attached correspondence dated
April 11,13, 17 and 20,2000.
Contractor did not properly schedule its material ordering
The contractor noted in correspondence dated 3/1/00 and 3/2/00 the difficulty they were
having in obtaining the specified butterfly valves for the project. The shop drawings for the
valves were received on 12/22/99 and returned 1/24/00. As stated above, the NTP was
PROJECT MANAGEMENT DEPARTMENT
![Page 9: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/9.jpg)
Memorandum to Rob Cuthbert
August 23,2000
Page 3
issued in October, 1999 apparently giving the contractor ample time to prepare shop
drawings for the project. At the preconstruction meeting it was specifically stated that shop
drawings would be accepted prior to the commencement of the contract time. It is the
contractor's responsibility to determine items that have extensive lead time and schedule
appropriately. It appears that this planning did not occur. To keep the project proceeding,
the County agreed to accept a modified valve which was not our preference.
Contractor made incorrect and misleading statements throughout the project
In several schedule submittals the contractor included statements that were opinions or
related to issues under dispute by the two parties. These statements were included as fact
according to the contractor and caused further disputes regarding the project.
The contractor submitted shop drawings for hatch covers constructed by Halliday Products
which were approved by the engineer. When the covers were received on site they were
provided by U.S. Foundry & Mfg., Corp. rather than the approved vendor. Although the
quality of the hatches was satisfactory, as determined by shop drawings that the County
required to be submitted after it was found that the incorrect manufacturer had provided
the materials, standard construction practice is to submit shop drawings for the alternate
vendor prior to receiving the materials onsite. In addition, as with many other events
discussed herein, the change resulted in additional time consuming efforts on the part of
County staff to ensure quality control and proper completion of the project. These efforts
were beyond those on a typical project of this size and complexity.
Throughout the project, the contractor submitted correspondence which included incorrect
statements which, in many cases, required County staff and design engineer time to
correct. The attached March 6, 2000 letter discusses a GTE utility issue which no party
present at the meeting referenced in the third paragraph recalled, with the exception of the
contractor. The meeting minutes issued by the engineer, which are submitted to the
contractor for review and correction if necessary, also did not include such a statement.
Also, the attached letter of March 21, 2000 included statements that were later corrected
via the attached letter of March 22, 2000 from the County. No further correspondence
disputed this March 22, 2000 correction. Finally, the attached letter of June 20, 2000 at
the top of the page stated that "Unfortunately, it appears to us that slope elevations have
been erroneously identified as bottom elevations" when the drawing specifically labels the
elevations'as "pond bot" which appears to be referring to the pond bottom.
Contractor provided inaccurate information in the submission of its bid
In the Contractor's Questionnaire, submitted with their bid, the contractor made several
incorrect statements. The questionnaire asks about subcontractors used on the work and
the contractor identified electrician and fencing. In addition to these, dirt hauling, sodding,
telemetry installation and possibly other items were subcontracted without any
PROJECT MANAGEMENT DEPARTMENT
![Page 10: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/10.jpg)
Memorandum to Rob Cuthbert
August 23,2000
Page 4
supplemental list of subcontractors provided to the County.
The questionnaire also asks about equipment being rented for the project. Small hand
machinery is the only item identified. Several major pieces of construction equipment such
as dump trucks were rented without any notification to the County.
Current quality of project construction
Although the project has not yet been completed and accepted for use by the County, two
significant issues have arisen regarding the quality of the final product. First, a concrete
overflow structure for the on-site ponds currently contains several cracks that both our
inspection staff and consulting engineer state are not acceptable. The contractor has been
notified of the lack of acceptability of the condition of this structure. This item is still
currently in dispute, however, during construction of the structure the contractor was
informed on several occasions that they needed to place the reinforcing wire higher in the
concrete pour. The contractor was allowing the wire to settle at the bottom of the pour
which is not conducive to proper construction results.
The other area of concern is related to the approximately three weeks of repairs which the
contractor has been making to the pipeline portion of the project. These repairs have been
necessary because the pipeline can not maintain the pressure required in the contract
documents. This amount of time is not typical for a line of this size and length. While it is
possible that the contractor may make all the repairs required to have the pipe pass the
pressure test this event reflects negatively on the quality of the construction.
The issues presented above are only a portion of the problems caused by the contractor
in their prosecution of the referenced project. These are the most easily presented with
written backup information. Many of the above events have occurred repeatedly over the
course of the project.
The above events and many others have caused the County to expend many hours of time
addressing issues which are not typical of a project of this size. The described events,
specifically scheduling, subcontracting, material ordering and communication issues, are
areas of concern that are more extensive in larger and more complex projects.
cc: Janet E. McAfee, Director, Project Management
Mike Limoge, Acting Project Management Manager
Project File: 6011080
<F;\USER\PUBWKS14\WPDOCS\8705\VEND.WPD>
PROJECT MANAGEMENT DEPARTMENT
![Page 11: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/11.jpg)
IFB#99-3131DC
C.13 INSURANCE (cont'd)
Nothing herein shall in any manner create any liability of the County in connection
with any claim against the contractor for labor, services, or materials, or of
subcontractors; and nothing herein shall limit the liability of the contractor or
contractor's sureties to the County or to any workers, suppliers, materialmen or
employees in relation to this contract.
C.14 BID BOND/CERTIFIED CHECK
By offering a submission to this Invitation for Bid the bidder agrees, should the
bidder's bid be accepted, to execute the form of contract and present the same to
Manatee County for approval within 15 days after being notified of the awarding of
the contract. The bidder further agrees that failure to execute and deliver said form
of contract within 15 days will result in damages to Manatee County and as
guarantee of payment of same a bid bond/certified check shall be enclosed within the
submitted sealed bid in the amount of five (5%) percent of the total amount of the
bid. The bidder further agrees that in case the bidder fails to enter into a contract, as
prescribed by Manatee County, the bid bond/certified check accompanying the bid
shall be forfeited to Manatee County as agreed liquidated damages. If the County
enters into a contract with a bidder, or if the County rejects any and/or all bids,
accompanying bond will be promptly returned.
C.15 PERFORMANCE AND PAYMENT BONDS
The successful bidder shall furnish surety bonds as security for faithful performance
of the contract awarded as a result of this bid, and for the payment of all persons
performing labor and/or furnishing material in connection therewith. Surety of such
bonds shall be in an amount equal to the bid award (100% each) and from a duly
authorized and nationally recognized surety company, authorized to do business in
Florida, satisfactory to this County. The attomey-in-fact who signs the bonds must
file with the bonds a certificate and effective dated copy of power-of-attomey.
(Reference Florida Statute 255.05)
Furnishing the performance and payment bonds shall be requisite to execution of a
contract with the County. Said performance and payment bonds will remain in force
for the duration of the contract with the premiums paid by the contractor. Failure of
successful bidder to execute such contract and to supply the required bonds shall be
just cause for annulment of the award. The County may then contract with another
acceptable bidder or readvertise this Invitation for Bid. If another bidder is accepted,
and notice given within 90 days after the opening of bids, this acceptance shall bind
the bidder as though they were originally the successful bidder.
Failure of the County at any time, to require performance by the contractor of any
provisions set out in the contract will in no way affect the right of the County,
thereafter, to enforce the provisions. Bonds to remain in effect for one year after
final payment becomes due.
C.16 PROJECT SCHEDULE
The successful bidder will be required to submit a detailed construction schedule
upon notification of award or its intent.
00030-6
![Page 12: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/12.jpg)
^//^tff^r
MANATEE COUNTY
GOVERNMENT
FINANCIAL MANAGEMENT DEPARTMENT,
PURCHASING DIVISION
'TO SERVE WITH EXCELLENCE-
EgssssKassasassKss^aasiSis^i^^
CERTIFIED
September 20, ^999
P^CEiVFO
.^P 2 2 1999
DeJonge Excavating Contractors, Inc.
Post Office Box 743
Venice, Florida 34284
Attention: Ms. Eileen DeJonge, President
....PKOJECT MGMT
Madam:
Re: Notice of Intent to Award for
IFB 99-3131DC Reclaimed Water Pumpback Station and Storage Pond - NRWTP
In review of your Bid dated August 4. 1999 for the referenced project, you are the apparent
successful bidder and will be recommended for award in the amount of Two Million, Two Hundred
Ninety-six Thousand, Two Hundred Sixty-six Dollars and Fifty Cents (52,296,266.50).
Award shall be made only by a majority vote of a quorum of Manatee County Board of County
Commissioners in open session. Award is anticipated by the Board on October 5, 1999. The
Manatee County Project Management Department will be contacting you soon after to schedule the
pre-construction meeting and any other preliminary requirements.
To expedite procedures, enclosed are two copies of the Contract Documents for the referenced
project for your execution and subsequent return to this office for further processing. The following
items are to be included with your executed Contract:
1. Two copies of the Performance-Payment Bond in accordance with bid documents.
Do not date the bonds; this will be accomplished upon execution of the Contract by
the Chairman of the Board of County Commissioners. Submit written
authori- ;tion, signed and sealed by attorney-in-fact, for the Board of County
Commi aioners to date the bonds upon Contract execution. Instructions to the
Surety and the Principal for execution of the bonds are as follows:
• 1112 Manatee Avenue West, Suite 803 • Bradenton, Florida 34205 • (941)749-3014 • FAX (941) 749-3034 j-^
yswswifjseffKssiwmssffifes^^
Recycled Paper
![Page 13: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/13.jpg)
September 20, 1999
Dejonge Excavating Contracotrs, Inc.
IFB 993131 DC-Award
Page Two
Neither signatures nor the Corporate Seal may appear by facsimile unless the
authority for them to appear in that form is plainly disclosed on the face of the
document. The Secretary or other properly authorized Officer must certify and seal
a statement declaring that the authority granted by the power-of-attomey remained
in force on the date that the bond was executed by the Attomey-in-Fact.
2. Two copies of the Certificate of Insurance in accordance with the Bidding
Documents. The Certificate must name the County of Manatee, Florida as an
additional insured and the standard cancellation clause should read as follows:
"Should any of the above described policies be cancelled or changed by restricted
amendment before the expiration date thereof, the issuing Company will give 30 days
written notice to the certificate holder, County of Manatee, Florida."
If you have any questions, or if we can be of any further assistance, please do not hesitate to contact
me.
Sincerely,
Deborah Carey-Reed
Buyer
/dcr
Enclosure
cc: Tim Hochuli, Project Management Department
![Page 14: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/14.jpg)
Preconstruction Meeting Agenda
Date of Preconstruction Meeting: November 3, 1999
Project Name & Locations: NRWTP - Reclaimed Water Pumpback Station & Storage
Pond
Project Number: 60110SO BidNumber: 99-3131D.C
1) Introduction.-Each Individual states the Agency represented & sign attendance sheet
a) Owner: Manatee County
Project Engineer: Rick Schappacher, P.E.
Project Manager: Timothy A. Hochuli, P.E.
Project Inspector: Bob Walker
b) Contractor: DeJonge Excavating Contractors, Inc.
Name Telephone
Construction Manager: . See attached list of numbers
Construction Supt.:
Emergency Numbers: Day
(more than one) Night
2) Review of Work
a) Contractor responsible for obtaining applicable permits (County Bidg. Dept.)
b) Contractor to submit Construction Schedule within 10 working days and explain
in detail the proposed method of construction (to be provided by 11/12/99)
c) Names of all subcontractors (to be provided by 11/12/99)
d) All correspondence, pay requests, change proposals, schedules, shop drawing
transmittal letters and field notifications to be delivered to:
Project Manager,
4422 66th Street West, Building "A",
Bradenton, Florida 34210
e) Shop drawings shall be submitted directly to engineering consultant. Shop
drawing submittal schedule shall be submitted within 30 days (to be provided)
![Page 15: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/15.jpg)
Preconstruction Meeting Agenda
Page 2
3) Utilities
a) GTE
b) FPL
c) Cable.
4) Application for Payment
a) Forms (copies furnished) included with bid package (3 originals required) and
must include construction photographs and updated construction schedules. Final
Pay Application shall include Warranty of Title, Final Reconciliation Agreement,
and Final Release of Lien.
b) Submit to Project Manager after field agreement with Project Inspector.
c) Stored materials will be paid only if they are on site, protected and include a paid
invoice.
5) Changes and Modifications
a) Change Orders/Proposals to be submitted to Project Manager and will include
complete breakdown and documentation of costs.
b) Work Directive Change will be issued by County if necessary.
- 6) Record Drawings
a) Required before substantial completion is approved.
7) Safety- and Protection
1) Contractor shall be responsible for initiating, maintaining and supervising all
safety precautions and programs in connection with the work
2) Job will be posted as a hard hat area. All personnel will wear hard hats.
3) Within 30 days of Notice to Proceed, the Contractor will submit his Hurricane
Preparedness Plan
4) No alcoholic beverages allowed on site.
![Page 16: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/16.jpg)
Preconstruction Meeting Agenda
Page 3
8) Temporary Utilities - If Applicable
a) Power, telephone and water to be scheduled (if required) and paid for by the Contractor
9) Field office - Not Applicable
1) Contractor's office trailer
2) Engineering office trailer
10) Construction Plans and Specifications
1) The County furnished five sets total (two previously furnished).
11) Progress Meetings
1) To be called as necessary - anticipated to be held monthly.
12) Comments (other Business)
Project Sign - sample and County logo provided
Shop drawings - 4 sets plus quantity needed by contractor to be provided. Please
number sets and stamp reviewed by contractor.
RFI's - important questions/issues shall be submitted in writing and tracked by
numbering each.
Testing services shall be provided by Ardaman & Associates, Sarasota (922-3526)
Contractor shall schedule testing with Ardaman.
Submit Schedule of Values for any lump sum items.
Only Chris West and Bob Walker can approve minor field changes.
Construction phasing was discussed and the outline provided in the addenda shall
be followed.
13) Notice to Proceed Completion Date June 27, 2000
Liquidated Damages S250/day
14) Adjourn
Attached is attendance list and emergency numbers
cc: Meeting attendees
Project File 6011080
F:\USER\PUB\VKS14\\\TDOCS\8705\PRECON1.WTD
![Page 17: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/17.jpg)
^e j^mge S^catofac] CW/iacto/ig, Aic.
facauaUon, Q/iading & ^Inde/ig/ioimd ^LUtees ^
November 2, 1999
Manatee County Government
Project Management Department
4422-A 66th Street West
Bradenton,FL 34210
Attn: Mr. Timothy A. HochuU, P.E.
RE: NRWTP Reclaimed Water Pumpback Station and Storage Pond
IFB #99-3131 DC
Dear Mr. Hochuli:
Below you will please find pertinent telephone numbers for during construction or should
an emergency arise.
Office: (941)493-1202
FAX: (941) 493-1204
EUeenDeJonge - President (941) 468-5316 - mobile
Henry DeJonge - V.P./Superintendent (941) 468-2646 - mobile
Henry Davidson - Chief Estimator (941) 468-5317 - mobile
Ernie Miles - Foreman '
(941) 468-7276 - mobile
Michael Monzo - Foreman (941) 468-0338 - mobile
If you should have any questions regarding the above information, please feel free to
contact us.
Respectfully,
DeJONGE EXCAVATING CONTRACTORS INC.
Henry Davidson
Chief Estimator
manpl
P.O. Box 743 • Venice, FL 34284-0743 * Office (941) 493-1202 « Fax (941) 493-1204
Florida State License CU C054928 • FDOTDBE • State Certified MBE
![Page 18: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/18.jpg)
^G//O£Q
PRECONSTRUCTION MEETING
NRWTP - RECLAIMED WATER PUMPBACK STATION & STORAGE POND
NOVEMBER 3,1999
NAME COMPANY PHONE/FAX
NUMBERS
Dghf;g( ^SXuf^; 5-kr /^C7 PUD '7c)Z8g]i ^^29)
tv>3 ^ p.^r F's ^ fi- Lc?<o .-^
^ ^r^ ^^S-^^^
^fi^r^he^- ^gs)— AJ^^ -7^5-- 3^.4//7^/-^•^^
•T^^ZC/^ f ^0, ^ A/^ A/P-^ 7^-?^7^
/
Z?^4^1^/<; /r/ c -p ^ D ^-^Pj
/9^^/^z^6^^ /^^.^^'^ 7^-^^^
/2^-^/ /^^
y
^ .c. /e^^ •7^--r^^^
1?ick Sdi^pp^
>• — i 11 \ i,
w^^ KHA 74/ - g7 Z-L
^Z>L i^7>.\\^^ ^c^M\ py^^jo//^^/
/r€^R,^ J^)ft-^ i F's o i^->
v ' * yi
J)£^wiff><i C^; c/^/f-T^f Lonv^i\ ^if - -VPJ'-'/Zd^
/rs'/u^ ^s^b^cyo. \J)£. )oic)^Cf,c>a^v/f^ (^vJ^r, ^1- ^73-»Z<3-
//'/>l fT^c-^c^/' f^^r} 7^ -^11 ^ ;T^ 7/7^7^
![Page 19: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/19.jpg)
De Jonge Excavating Contractors Inc.
P.O. Box 743
Venice. Fl 34284-0743
^^//a££>
-S'^ ^^^
TRANSMITTAl.
DATE: •T)^- ^). y? JOB NO: 9916 SUBMITTAL NO: 38
TO:
^ , , ,.
KIMLEY-HORN AND ASSOCIATES, INC.
1215 MANATEE AVENUE WEST
BRADENTON, FL 34205
ATTN: MR. RICK SCHAPPACHER, P.E.
MANATEE COUNTY NORTH REGIONAL WWTP
RECLAIMED WATER PUMPBACK STATIONS
RE:
WE ARE SENDING YOU:
X_ ATTACHED _
UNDER SEPARATE COVER VIA.
X_ SHOP DRAWINGS _PRINTS/PLANS _SAMPLES
NUMBER OF COPIES DATE NO.
THE FOLLOWING ITEMS:
. SPECIFICATIONS
__ CHANGE ORDER
DESCRIPTION
7 //?/-?/A9 —r—7-—f———
' 'T^'/^r/yT'/Uf C ^7S 7??oc TTw ,^C'/r-/.y
HESE ARE TRANSMITTED AS CHECKED BELOW;
FOR YOUR USE
AS REQUESTED
X FOR APPROVAL
APPROVED AS SUBMITTED
APPROVED AS NOTED
RETURNED FOR CORRECTIONS
SUBMIT COPIES FOR DISTRIBUTION
RETURN CORRECTED PRINTS
EMARKS
^ ^ ^
/ / \
<•
lONE'4:941.493-1202'^ €.
-X: 941-493-1204
SIGNED
'^•^a^^' ^HenryUavidson
^•^"^g1 Chlef^^mator"
W ^
S6?:'
![Page 20: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/20.jpg)
Kimley-Hom
and Associates, Inc.
Transm'ittal
Date: be^SM^ ^Z/999 Job No: ' "' • — — f " •-' ' ' "
To: A^ry Dan'^:>^
1215 Manatee Avenue East
Bradenton, Ftorida
34205
TEL 941 741 8722
FAX 941 747 7351
D^J^/i^g- ^C^Y^yh'w ^QY)fy7^-£>fS, 'The..
. P. o. ^x. 743
^
\/g^l^ FL g^g4'^'743________
Re: /^/a^^?^. z^). /y^/i ^WTP Pi^phs^ S-^rf)pyi5
We are sending you
D Attached D Under separate cover via the following items:
a Shop Drawings D Prints/Plans D Samples n Specifications D Change order
D
Copies Date No. Description
3 3S le^yf?^- ^y^T^&^'pr? 5^^^€.
These are transmitted as checked below:
D For your use D Approved as submitted ^ Resubmit 7 copies for approval
D As requested
D For review / comment
D Approved as noted D Submit.
D Returned for corrections D Return
. copies for distribution
_ corrected prints
Remarks 5^^i/k /Ut/sf 2c^M^^€ Golf ^W(L ^/<y
-^^^h /V^t/ I ,Z£>s€> 3-^ t^,r /{cfc^ikffuw- ^2.. P/fSy?-
^-i/l 're 2^ ^g-^kK/7 ^-k^ •Sc-h^tA<_
'flM l^>C.hcll!
S^b (^^Ik/
C^f]'s i^e^
![Page 21: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/21.jpg)
^DeJoge^CG^aUng Ccmt/iacto/is, Aic.
fixation. Q/iading fi QAide/cgAound ^LUtoes '
^^
February 4, 2000 "T ••:'• •'•:'••"''
:
! FEB - 7 2000
LPKOJ^G!' ^
Manatee County Government
Project Management
4422A 66th'Street, West
Bradenton,FL 34210
Attn: Mr. Tim Hochuli
RE: Reclaimed Water Pumpback Stations and Storage Ponds
IFB #99-3131-DC
Hurricane Preparedness Plan
Dear Mr. Hochuli:
The referenced contract specifications require that we submit our Hurricane Preparedness
plan for the project. Briefly speaking, our plan is as follows:
Upon the issuance of a Hurricane Watch, the site will be inspected and all excess or
unnecessary materials will be removed. Stored equipment (i.e. parked and not
being utilized) will be removed from site.
s
Upon the issuance of a Hurricane Warning, all excavations will be filled, the site will be
graded and all remaining equipment will be removed (if possible). In addition,
all materials and equipment which can be moved manually by up to two men will
be removed from the work site. All remaining materials will be positioned and/or
restrained from possible movement. It should be emphasized that all construction
fencing (to include straw bales, filter fencing and traffic control signs will be
removed from the sight.
Should you have any questions, or wish to discuss this further, please feel free to contact
us.
Respectfully,
DeJONGE EXCAVATING CONTRACTORS INC.
^y ^)- •
^^^^c^^^,
Henry Davidson
Senior Administrative Project Manager
manp5
cc: Mr. Rick Schappacher, Kimley-Hom & Assoc.
P.O. Box 743 - Venice, FL 34284-0743 • Office (941) 493-1202 « Fax (941) 493-1204
Florida State License CU C054928 • FDOT DBE • State Certified MBE
![Page 22: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/22.jpg)
FORM OF AGREEMENT
BETWEEN THE
COUNTY OF MANATEE, FLORIDA
AND THE CONTRACTOR AS IDENTIFIED BELOW
ON THE BASIS OF A STIPULATED UNIT COST CONTRACT PRICE
THIS AGREEMENT is made and entered into by and between the COUNTY OF MANATEE, a
political subdivision of the state of Florida, hereinafter referred to as the "OWNER" and
DEJONGE EXCAVATING CONTRACTORS. INC.. hereinafter referred to as the
"CONTRACTOR," duly authorized to transact business in the state of Florida, with offices located
at 3506 Tundra Road. Post Office Box 743. Venice. Florida 34284 fPhone: 941/493-1202V
Article 1. WORK
CONTRACTOR shall furnish all labor, materials, supplies, and other items required to complete the
Work for IFB No. North Regional Wastewater Treatment Plant Reclaimed Water Pumpback Station
and Storage Pond in strict accordance with specifications and any duly authorized subsequent
addenda thereto, all of which are made a part hereof.
Article 2. ENGINEER
The County of Manatee, Project Management Department, is responsible as the OWNER. Kimley-
Hom and Associates, Inc., hereinafter referred to as "ENGINEER," designed this project and is
responsible for technical/engineering reviews and decisions. The ENGINEER is a member of the
OWNER'S project management team which is collectively responsible in ensuring the Work is
completed in accordance with the Contract Documents. All communications involving this project
will be addressed to:
County of Manatee
Project Management Department
Attn: Tim Hochuli, Project Manager
IFB 99-3131DC
4422A West 66th Street
Bradenton, Florida 34210
(Phone: 941/792-8811 ext.5053)
Kimley-Hom and Associates, Inc.
8586 Potter Park Drive
Suite 100
Sarasota, Florida 34238
(Phone:9417922-8187)
Where the terms ENGINEER and/or OWNER are used in the Contract Documents, it shall mean the
OWNER'S project management team.
00500-1
![Page 23: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/23.jpg)
LJ e -j u 11 LJ c. c.AL.nfniini-i aTl'ta^fi^ljT P • d
€.oilo££>
^De J^cmgc ^cpvQfag CWftacto/[S, ^ic.__________
.facavdion, QWing & ^IndeftgAoiind ^Ut^illes ^
April 11,2000
Manatee County Government
Project Management Department
P.O. BOX 25010
Bradenton,FL 34206
Attn: Mr. Timothy A. Hochuli
Re: Reclaimed Water Pumpback Stations and Storage Pond
IFB #99-3131 DC
Irrigation Pump Station Tie-in
Dear Mr. Hochuli:
Original work required us to tie-in to the pump station main underground. Addendum #3
(without any design) revised this to an above ground tie-in. Sight inspection indicates to
us that this cannot be done due to existing DEP monitoring points.
We request an on-site meeting at the pump station at 11:00 a.m. on April 12, 2000.
Your earliest attention/response to this matter would be appreciated.
Respectfully,
'-'yUuu
Henry DeJonge
Vice President
cc: Mr. Rick Schappacber, P.E.
Kimley-Hom and Assoc., Inc.
manp54
P.O. Box 743 » Venice. FL 34284-0743 ' Office (941) 493-1202 » Fax (941) 493-1204
Florida State License CU C054928 • FDOTDBE • State Certified MBE
![Page 24: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/24.jpg)
6^//^Q
^De j^ge fi^caitot^ig Co^/iacto/is, Aic.
fi^caucto, Q/iading 6 ^nde/cg/cound ^tees ,A
F
RECEIVED
APR ( 8 2000
TOJECT MGM7 •
April 13, 2000
Manatee County Government
Project Management Department
P.O. Box 25010
Bradenton,FL 34206
Attn: Mr. Timothy A. Hochuli
RE: Reclaimed Water Pumpback Stations and Storage Pond
IFB #99-3131 DC
Irrigation Pump Station Tie-in
Dear Mr. Hochuli:
In our letter, dated April 11, 2000 (manp54), we requested a meeting at the irrigation
pump station to discuss tie in methods. Although we received information from the
engineer, we have not yet heard from your office. In a continuing spirit of cooperation,
we again respectfully request a meeting be held at 1:30 PM on Monday, April 24, 2000, at
the pump station. This date has already been approved by the engineer.
As this tie in has recently been identified as a critical path activity, we respectfully urge
you to attend.
Respectfully,
•Uju ft^^l
Henry DeJonge ^
Vice President
cc: Mr. Rick Schappacher, P.E.
Kimley-Hom and Associates, Inc.
manp55
P.O. Box 743 « Venice. FL 34284-0743 » Office (941) 493-1202 • Fax (941) 493-1204
Florida State License CU C054928 • FDOT DBE • State Certified MBE
![Page 25: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/25.jpg)
^^//^^
^De J^gG ^cc^atog Ccmtefo/is, Aic.
faca^ation, QWing & ^IWe/ig/iound ^LUltes ^^
April 17,2000 |RECEIVED
F
RECEIVED
APR 2 1 2000
TOJECT MfiMT •
Manatee County Government
Project Management Department
P.O. Box 25010
Bradenton,FL 34206
Attn: Mr. Timothy A. Hochuli
RE: Reclaimed Water Pumpback Stations and Storage Pond
IFB #99-3131 DC
Lines of Communications
Dear Mr. Hochuli:
On April 11, 2000, we received your letter in which you stated: "Once again. Manatee
County requests that DeJonge Excavating Contractors Inc. comply with the lines of
communication outlined in the preconstruction meeting and frequently reiterated
throughout the duration of the project."
DeJonge Excavating Contractors Inc. herein states that we have no idea of what you are
talking about. We have, since the start of the project followed your instructions to the
letter. We will admit that your instructions change with each meeting and do not agree
with the guidance given to and understood by the County and Engineer inspectors.
Perhaps that is where the problems lie.
During the preconstruction meeting, we were directed to bring all minor problems to Mr.
Chris West and Mr. Bob Walker. The minutes of the preconstruction meeting clearly state
that "Only Chris West and Bob Walker can approve minor field changes." Even as
recently as 12:00 noon April 14, 2000, Mr. Walker considered himself the eyes, ears and
mouth of the County's project manager and that informing him of all problems constitutes
simultaneous notification of the County Project Manager. When we informed him Friday,
April 14, 2000 that we had been directed to communicate only to the project manager in
the future and informed him that you had stated "Communicating information to various
?County staff has not been approved by the engineer or the appropriate County staff
provides no useful purpose in properly constructing the project". He did not believe us.
P.O. Box 743 • Venice. FL 34284-0743 « Office (941) 493-1202 • Fax (941) 493-1204
Florida State License CU C054928 • FDOTDBE • State Certified MBE
![Page 26: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/26.jpg)
Manatee County Government
April 17,2000
Page Two
In the minutes of the monthly status meeting held on Tuesday, April 4, 2000 under
Miscellaneous, it states:
"The Contractor anticipates finishing the grading of the west pond banks by the
end of the week. The 24" equalizer pipe valves will be open to allow flow from
the east pond back to the west pond."
During that meeting we were told to inform "us" when we were ready to have the
equalizer pipes open. For what it is worth, at the time we assumed the term "us" meant
any responsible county person at that meeting. Late in the afternoon of April 6, 2000, Mr.
Daryl Young, Chris West's designated assistant came by the work site and asked if we
were ready to have the equalization valve opened. Naturally, as we were on Schedule and
the opening of the valve was per the status meeting, we stated that we were ready. Mr
Young went ahead and opened it. There was not a change in time and frankly, we did not
notify them. They notified us.
It has become obvious that there seems to be an overall problem clouding this project.
We are beginning to become irritated at what we see as constant unsubstantiated
accusations, delaying tactics, interference and frankly general uncooperativeness. We
would like to sit down and settle what ever problems exist in a professional and courteous
manner. We are open to your suggestions, a county mediator would be acceptable. The
current actions can not continue.
Should you have any questions or wish to discuss this matter further, please feel free to
contact us.
Respectfully,
Henry DeJonge
Vice President
cc: Mr. Rick Schappacher, P.E.
Kimley-Hom and Assoc., Inc.
manp62
![Page 27: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/27.jpg)
MANATEE COUNTY
GOVERNMENT
Project Management Department
VIA FACSIMILE & US MAIL
April 20, 2000
Mr. Henry DeJonge
DeJonge Excavating Contractors, Inc.
P.O. Box 743 •
Venice, FL. 34284-0743
Re: NRWTP - STORAGE PONDS/PUMPBACK STATIONS
Dear Mr. DeJonge:
In response to your letter of April 17,2000 regarding communication between the County and
DeJonge Excavating this letter exemplifies the issues raised in my previous letter. I am not
familiar with a County request to have DeJonge only communicate with the County's project
manager. Please clarify the source of that information. Also, please refrain from making
characterizations of the County inspector's opinions. The inspector is more than able to do
so himself and I would venture to say that he would not want your firm making statements as
to his opinions.
It does not appear productive at this point to further discuss the lines of communication in
detail. However, as a point of clarification the preconstruction meeting defined Bob Walker
and Chris West as points of contact for minor on site questions and myself for issues which
would involve cost or time to the County. This has been revised once to remove Chris West
as a point of contact. This was intended to streamline communication because your firm was
asking questions of both parties when one may have already given a response to a question.
This has been the only change to the system. As I am sure you recall we discussed this at
length at the preconstruction meeting. At that time I described that we do this on all of our
construction projects to help the contractor eliminate the possibility of performing work for
which he would not be compensated.
If you have any questions please give me a call.
Sincerely,
^•/^^
Timothy A. Hochuli, P.E.
Project Manager
cc: Rick Schappacher, P.E., Project Engineer
Bob Walker, Project Inspector
Bill Parks, WW Maintenance Superintendent
PrOJeCt File 6011080 <F:\USER\PUBWKS14VWPDOCS\8705\RESPONS.WPD>
4422-A- 66th Street West, Bradenton, Florida 34210 • (941) 792-8811 • FAX (941) 795-3442
P.O. Box 25010. Bradenton. Florida 34206
![Page 28: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/28.jpg)
^DG ^cmgG S^cc^Qting Conteto/i9, Aic.
^"<^7<$b
fi^cavafclon, Q/iading & ^nde/ig/iound ^U^lUes ^^
March 6, 2000
RECCED
Manatee County Government ; ,^p _ Q ^ ,
Project Management Department "•'" ~ y '-uuu
P.O.Box 25010 -—-
Bradenton, FL 34206 _
'• ,'
Attn: Mr. Timothy A. Hochuli, P.E.
Re: Reclaimed Water Pumpback Stations and Storage Pond
IFB #99-3131 DC
GTE Cable South Side of Road on North Side of Site Reject Pond
Dear Mr. Hochuli:
When we were preparing to excavate and install the new effluent water mains, we called
Sunshine and requested utility locates as is required us by state law. As is also required by
state law, the various utilities (except for Manatee County) in turn came out to the work
site and located their lines.
To our surprise, GTE located a cable on the south side of the road to the north side of the
Site Project Pond. This cable was not indicated on the contract plans, even though it's
existence was apparently known by Manatee County. The conduit was in direct conflict
with the proposed 12" effluent main and would have to be removed, prior to the
installation of the 12" main and then reinstalled after the 12" main was installed and tested.
Because of the contract plan deficiency, we were unable to know about the additional
work requirement and therefore we were unable to include this added cost in our bid
price.
During the first monthly construction status meeting, Mr. Henry DeJonge ofDeJonge
Excavating Contractors, Inc. informed all those present of the need to remove and replace
the GTE cable. He asked whether the county wanted GTE to do the additional work or
have DeJonge do it. We were directed to perform the additional work. Mr. DeJonge
was quite clear in his informing those present that the cost to perform this added work
was an additional cost.
Accordingly, DeJonge Excavating Contractors, Inc. herein requests that a contract change
order be issued in the total amount of $1,166.58 representing the additional cost which has
been and will be incurred while performing the above cited additional work.
P.O. Box 743 • Venice, FL 34284-0743 * Office (941) 493-1202 « Fax (941) 493-1204
Florida State License CU C054928 • FOOT DBE • State Certified MBE
![Page 29: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/29.jpg)
Manatee County Government
March 6, 2000
Page Two
Should you have any questions, or wish to discuss this matter further, please feel free to
contact us.
Respectfully,
DeJONGE EXCAVATINGrCONTRACTORS INC.
Henry Davidson
Senior Administrative Project Manager
cc: Mr. Rick Schappacher, P.E.
Kimley-Hom and Assoc. Inc.
manp25
![Page 30: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/30.jpg)
6 ^//Os5a
^De ^ojjgg^CQ^at^g Ccmteto/tS, ^ic.
facc^aUon, Q/cadlncj & ^nde/ig/iound ^tites ^
March 21,2000
Manatee County Government
Project Management Department ^p ^ ^ p/yin
P.O. Box 25010
Bradenton, FL 34206
_ PROJECT'MfiMT
Attn: Mr. Timothy A. Hochuli
RECEIVED
Re: Reclaimed Water Pumpback Stations and Storage Pond
IFB #99-3131 DC
Modification to the Proposed Effluent Transfer Pump Station Pump Separation
Dear Mr. Hochuli:
On Monday, March 20, 2000, we received authorization to modify the placement of the
pumps for the proposed effluent transfer pump station within its wet well. The wet well
top slab will be rotated 180 degrees and the pumps will be installed with a 38" separation
(rather than the 35 inches in the contract plans).
This change will be at no additional cost to Manatee County. The authorization was
passed on to us by Mr. Rick Schappacher, P.E. the project engineer with Kimley-Hom &
Assoc., Inc. which included approval by Mr. Tim Hochuli, P.E. the project manager with
Manatee County.
We greatly thank Mr. Schappacher for his rapid review and approval recommendation.
Due to his actions we incurred no delay while solving the problems which had been
discovered.
Should you have any questions, or wish to discuss this matter farther, please feel free to
contact us.
Respectfully, -^-.^ ^•-"'V^
r^ "\
^//^•^•- -/•••'^ .-^^w ^,
Henry Davidson
'Senior Admmistrative Project Manager
cc: Mr. Rick Schappacher, P.E.
Kimley-Hom and Assoc., Inc.
manp42
P.O. Box 743 » Venice. FL 34284-0743 ' Office (941) 493-1202 • Fax (941) 493-1204
Florida State License CU C054928 • FOOT DBE • State Certified MBE
![Page 31: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/31.jpg)
MANATEE COUNTY
GOVERNMENT
Project Management Department
••fsya-szs^.-x^-:
March 22, 2000
VIA FACSIMILE & US MAIL
Mr. Henry Davidson
DeJonge Excavating Contractors, Inc.
P.O. Box 743
Venice, FL. 34284-0743
Re: NRWTP STORAGE POND IMPROVEMENTS
Dear Mr. Davidson:
In response to your letter of March 21, 2000 regarding modifications to the proposed
effluent transfer pump station pump separation please have this letter serve as notification
that Manatee County has not approved the revision you describe. More specifically no
approval by me has been issued and in fact the County has not received a description of
the proposed modification. Any changes performed by yourfirm based on the assumptions
stated in the above letter are at your own risk.
Please give me a call if you have any questions.
Sincerely,
^•^
Timothy A. Hochuli, P.E.
Project Manager
cc: Rick Schappacher, P.E., Project Engineer via facsimile
Bill Parks, WW Maintenance Superintendent
Bob Walker, Project Inspector
Project File 6011080
<F;\LISERIPU8WKS14\WPDOCS\8705\LSTOP.WPD>
4422-A-66th Street West, Bradenton, Florida 34210 • (941) 792-8811 • FAX (941) 795-3442
P.O. Box 25010, Bradenton, Florida 3420R •
![Page 32: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/32.jpg)
^DG ^onge ^CQVafag Contoto^s, ^ic.
fi^cauatlon, Q/iading & ^nde/ig/iound ^U^Ues //
June 20, 2000
Manatee County Government
Project Management Department
P.O. Box 25010
Bradenton,FL 34206
Attn: Mr. Timothy A. Hochuli
RE: Reclaimed Water Pumpback Stations and Storage Pond Improvements
IFB #96-3131 DC
Reject Pond Bottom Elevation Changes
Dear Mr. Hochuli:
In our letter, subject as above, dated May 1, 2000, we requested $16,650.56 in additional
compensation for performing additional excavation of the material from the bottom of the
reject pond.
In your response to our request you forwarded Mr. Schappacher's letter to you outlining
his position on our request. At this time, we would like to briefly comment on his
obersavations.
Paragraph 1: Mr. Schappacher seems to be making some kind of point by pointing out
that "The inspector's daily report indicated that contractor excavated materials from the
western half of the reject pond on March 16 and 17 and hauled the materials to the spoil
area". Considering that in our original letter, we too listed the personnel, equipment and
dump truck. We do not understand the engineer's statement. The inspector's daily report
seems to have been confirmation.
Paragraph 2: The photograph forwarded with our May 1, 2000 letter clearly shows that
we were conducting work on the banks before the pond was dewatered. We stated in our
letter that the surveyor was denied access to the bottom of the pond as a result of Manatee
County's actions of not permitting us to dewater the reject pond. The statement made by
the engineer that "In addition, there was a discharge from the plant into the reject pond
that could have altered the pond bottom elevations slightly due to the exposed slopes". It
would appear that we are being blamed for the actions of Manatee County's personnel in
discharging treated sewage water into the reject pond. We must question this action.
P.O. Box 743 • Venice. FL 34284-0743 « Office (941) 493-1202 « Fax (941) 493-1204
Florida State License C(J C054928 • FOOT DBE • State Certified MBE
![Page 33: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/33.jpg)
Manatee County Government
June 20, 2000
Page Two
Paragraph 3: The engineer makes reference to various elevations indicated on the
contract drawing. Unfortunately, it appears to us that slope elevations have been
erroneously identified as bottom elevations.
What has upset .us is that for an extended period of time we were denied the ability to
dewater the reject pond and when we could, our efforts were repeatedly all but interfered
with. Then acting in conjunction with the engineer and county inspector's observations,
we had our surveyors verify the pond bottom elevations once we were permitted to drain
the reject pond. The end results are ignored and denied.
Accordingly, under article 11.2 of Section 00700, General Conditions of the Contract
Specifications, we herein request conferencing with the County Purchasing Director prior
to any further action. This conferencing may be held in reserve until the full extent (and
numbers) of actions have been determined which will be before the final payment request.
Should you have any questions, or wish to discuss this matter further, please feel free to
contact us.
Respectfully,
,^^ /,^^9^
Henry DeJonge cY v <^Z^
Vice President
cc: Mr. Rick Schappacher, P.E.
Kimley - Horn and Assoc., Inc.
manp92
![Page 34: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/34.jpg)
ui•roi •-uuu .LU.-U r.i-i a-ti. if-to i^..-i jAy rAU>^l.A£,.'i£,.^J. l^JUUl
n SARASOTA COUNTY
'Dedicated to Quality Service"
VIA CERTIFIED MAIL P261682001
April 10,2000
Ms. Eileen DeJonge, President
DeJonge Excavating Contractors, Inc.
P.O. Box 3421
Venice, Florida 34293
Subject; Prequalification Revocation
Dear Ms. DeJonge:
In accordance with Administrative 2.03A, Section 10, your Sarasota County Prequalification
Certification has been suspended for one year, beginning April 10, 2000.
The Construction Prequalification Committee has reviewed your performance in the execution of the
Contract for the Proctor Road/Honore Avenue Force Main, Contract No. 99-328 and for the
Longwood-Meadowood Force Main and Lift Stations, Contract No. 98-333. It has been determined
that your performance was "non-responsible" on both projects- Copies of performance evaluations
are attached-
Ifyou have any questions please refer to Administrative Directive 2.03A. A copy has been enclosed
for your reference. If you have any additional questions please call me at (941) 951-5266.
Robert R. Walendzik, Construction Prequalification Coordinator
Sarasota County.
Approved:
iemadette C- O'Brien
Procurement Manager
3attch/as
• CC: Warren Wagner, Jody Kirkman and Joe Griffin of Environmental Services, Tom Wilcox, Public
Works, Adriana Consuelos, Esq., Office of the County Attorney, Dale Roberts,. Procurement
![Page 35: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/35.jpg)
•-/A\*a< * ^\iw"» t_ i.'t^.r.t,^. . j
SARASOTA COUNTY GOVERNMENT
ADMINISTRATIVE DIREdTVE
NO: 2.03A
ISSXIKD: February 13,1998
EFFECTIVE: DATE: February 13,1998
SUBJECT:
PrequaUfication of construction contractors.
AUTHORITY: •
Ordinance Number 9MO authorizes the County Administrator to determine the eligibility of
contractors to bid on County construction projects.
PURPOSE:
To establish a process for prequalii^ing contractors for County .construction projects.
^ •• • .
POLICY:
It is the policy of Sarasota. CountyGovemment to utiBze only qualified contractois to construct or
renovate buHdiags, roads axui other large construction projects.
RESPONSIBILITY-. .
AH County Government departments are responsible for adhering to the provisions of this
Ajdnumstrafive Directive. The Purchasing & Contracts Management Division of the General Services
Department is responsible for implementing and managing the constniction .contractor
prequalificarion program.
PROCEDURES:
•..-"} All constmcdon contractors wishing to do business with Sarasota County roust first apply for
prequalincation certification with the Construction Prequalification Committee.
![Page 36: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/36.jpg)
s?r\.*.< ,t-^\<^^ L A£.-U£..^ X l^J UU 1^
1. The CONSTRUCTION PREQUALDFICATION COMMITTEE ("Committee") consists of:
Three permanent members as follows:
General Services Director (Chairman)
Transportation Director . .
Utilities Director
Non voting Committee Staff:
The Construction Prequalification Coordinator (Coordinator) under the direction of
the Purchasing & Contracts Management Division.
The Committee will review and investigate ^U Prequalificadon Questionnaires and renewals. The
Committee win determine its own manner of operation adhering to tile requirements of this Directive,
The Coordinator will establish and maintain an official file of all prequalification applications,
questionnaires and supporting material, certificates of prequalification, record of contractor
performance, records of disqualification and will print an updated list of pcequalified contractors
whenever needed.
2.. APPLICATION FOR CERTIFICATION - PREQUALIFIED BIDDER: A propedy
completed application for certification as a prequalified contractor must be submitted to the
Coordinator by each contractor intending to bid on County construction contracts estimated by the
County to cos^ in excess of S100,000. Certification is for a two. year period renewable every two.
years thereafter. A copy of the Application is shown as Attachment I to this Directive.
3. RENEWAL OF CERTIFICATION A propedy completed application for renewal of
certification must be submitted to the Coordinator. Failure to submit a propedy completed Renewal
Application 30 days prior to expiration, may result in the lapse of a contractor's certification.
* ' ^ - . '
Updated information must be submitted immediately by a .prequalified contractor should there be:
a. a. change of ownership, - - . • •
b. any event that adversely affects the contractor's financial condition, or
c. a surety rating change.
4- The Construction Prequalification Coordinator will obtain the review and recommendation
of the Committee within 30 calendar days of receipt of each propedy completed Prequauncation
Application and Renewal Application, (or a processing status update sheet will be sent to the
applicant)
4
5. EVALUATION OF CONTRACTOR Based on a positive recommendation by the
Committee, Sarasota. County Government will Issue a Certificate (sample form attached) as a
prequalified construction contractor executed by the County Administrator or his deslgnee. The
Certificate will specify the construction categories for which the contractor is prequalified and will
be issued subject to the bonding restrictions for contract dollar limitation-
2
![Page 37: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/37.jpg)
ui-.^'-uuu .1.0.-1 r.T^i. a-t.1. ^.LO ij.-t o^y mu^i-ru-.ii&.M ^juu-t
6. If the Committee denies certification, the Committee Chair will send a letter to the contractor
outlining the reasons for this denial. A contractor may appeal such a decision to the County
Administrator by providing an appeal letter to the General Services Director within seven (7) calendar
days from issuance of the denial.
7. A service fee of $200.00 for each Application and $75.00 for each Renewal Application must
be submitted with each contractor's application. Checks should be made payable to Sarasota County
Board of County Commissioners and are non-refundable.
8- Only those contractors holding a valid Prequauficadon Certificate will be permitted to bid on.
construction contracts estimated by the County to cost in excess of $100,000. Bids received from
bidders who do not hold a vaHd Certificate should not be opened. Such bids are not to be recognized
and, if opened by mistake, will not be considered for award.
9. PERFORMANCE EVALUATION-CONSTRUCTION CONTRACTS Contractor's on
the job performance will be evaluated at least annually using the form shown in Attachment 3 - The
County will maintain records of contractor performance on each project The original records will
be maintained by the user department and a copy maintained by the Coordmator-
10. A contractor's prequalification may be suspended or revoked by the County for Good Cause
upon written notification to the contractor and its surety. Suspension is a temporary termination of
prcquaBficafion status for a stated period of time which shall be determined by tile Committee, based
on the severity of the cause and the circumstances involved- Revocation is -a :tennination of
prequalificalion status which shall be based only on the most serious causes. -Good Cause for
suspension or r€^o<^on of prequalifi<^tion static may include, but.is not limited to:
a. Delinquency. A contractor is delinquent when unsatisfactory progress has beea made on a
construction project or when the allowed contract time has expired .and the contract work is
not complete. Unsatisfactory progress shall be determined by the express language of the
contract t
b. Non-responsible. A contactor may be determined non-responsible when there is .Good
Cause. Good Cause includes, but is not limited to, drcumstances in which the contractor or
the contractor's official representative:
(1) Makes or submits to the County false, deceptive, or fraudulent statements
in any bid or proposal, or any application for a certificate of qualification;
(2) Becomes insolvent or is the subject of a bankruptcy petition; \
(3) Fails to comply with the contract requirements in terms of payment or
performance record, or to timely furnish contract .documents as required by
the contract or any state or federal agency,
![Page 38: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/38.jpg)
'o--» ony rj\.>j^Livc.,'ir,.\i
(4) Wrong&iUy employs or otherwise provides compensation to any employee
or officer of the County,
C5) Is an affiliate of a contractor who has been determined non-responsible or
whose certificate of qualification has been suspended or revoked and the
affiliate is dependent upon such contractor for personnel, equipment, bonding
or finance.
The Contractor may contest the suspension or revocation by providing written justification to halt
the suspension or revocation within seven (7) calendar days to the Committee Chairman. The
contracting firm will be granted the opportunity for a meeting with the Committee to present its
appeal. The Committee will reevaluate the suspension or revocation taking into consideration the
information provided by the contractor in the appeal and issue a written decision to the contractor'.
The contractor may appeal the Committee's decision by providing written justification, within seven
(7) calendar days to the County Administrator or his designee.
At the end of suspension, the Committee may restore a contractoi's prequalified status upon a
detennination that the cause for suspension has been corrected by the contractor.
11. All determinations of the Cbmnutteeor the County Administrator, or his designee, uQd.ec-flns
Administrative Directive, including determinations to limit prequalificarion eligibility, to deaf
prequalificatioff, to limit or deny renewal of prequalificataon, to determine that a contractor is
delinquent or to suspend or revoke a contractor's prequalification, maybe appealed to the Board of
County Commissioners.
Appeals shall be addressed to the Board in writing and be filed within seven (7) calendar days of the
date of the detcnrimation which is being appealed. Appeals shall include the following:
a. Name and address of appdhnL
"b. • Identification of the determination that is being appealed.
<c. Statement as to why the suspension or revocation is unwarranted.
d. Copies of all documents pertinent to the appeaL
c. A statement of the relief which the appellant seeks from the Board-
The decision of the Board shall constitute final administrative action..
SUPERSEDES:
This Administrative Directive supersedes Administrative Directive 2.03 issued August 14,1991.
![Page 39: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/39.jpg)
ui'-.j'-uuu .Lu-rO r A-^ a •* j. ^ i. o i 0 - -i oAy rKtu- Liu-.iir.N i ifiy UUD
PERFORMANCE EVALUATION-CONSTRUCTION CONTRACTS
CONTRACT NUMBER: 98-333 CONTRACT TITLE: Longwood - Meadowood Force Main and Lift Stations
CONTRACTOR (COMPANY NAME. ADDRESS, TELEPHONE NUMBER, POINT OF CONTACT):
DeJonge Excavating Contractors, Inc.
P.O. Box 743
Venice, Florida 34284
(941)-493-1202
Mrs. EUeen DeJonge. President
DATE OF AWARD
July 28,1998
ORIGINAL CONTRACT
COMPLETION DATE
March 8,1999
REVISED CONTRACT
COMPLETION DATE
June 1,1999
DATE WORK ACCEPTED
October 26,1999
DESCRIPTION AND LOCATION OF WORK:
The project consisted of installing IO", 12", 16" and 24" force mains- The project included three (3) master lift stations. The sewer
system included service manholes, structure crossing, directional bores, valve installations, minor WWTP plant •work, and automatic air
release structures-
The project boundaries consisted of Longwood Park to the north, and the Meadowood WWTP to the south. The pipeline was installed via
DeSoto Road to North Metro Park, at the park, the pipe line turned south and was installed to die main entrance of the Park. The pipeline
then tunicd 10 the west to Honore ave. where it turned south and ran to 17'1' Street. The pipelina was installed west oa 17'1' Street to the
Meadowoood WWTP. On site, the pipeline was installed to both the existing lift station and the CKisting headworks of the Plant
PERFORMANCE ELEMENTS
QUALITY OF WORK '
TIMELY PERFORMANCE, INCLUDING
ADHERENCE TO SCHEDULE
COORDINATION WITH OWNERDS
REPRESENTATIVE
SUPERVISION OF SUBCONTRACTORS
COMPLIANCE WITH SAFETY STANDARDS
RELATIONS WITH THE PUBLIC
OVERALL EVALUATION
OUTSTANDING GOOD SATISFACTORY
x
. x
UNSATISFACTORY
X
X
X
X
x
Note: Please supply comments on Page 2 for all Performance Elements evaluated other than DSatisfactory
EVALUATED BY: DEPARTMENT: Environmental Services. Utilities Engineering
Jody C. Kirkman, Senior Engineer
EVALUATOR
OSD Fonn 2.03897
Patrick D. Zoeller, P.E., Engineering Section Supervisor
REVIEWER
![Page 40: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/40.jpg)
oi<.y rr<.u'-i-t<£..'LC.t'.i ifijuu;
COMMENTS
1. Quality of Work: The quality of the Contractor's final product was rated satisfactory. It is noted that the
Contractor did have to re-excavate the pipeline to make adjustments to the deflection of the pipe. It was
noted that the Contractor exceeded the project specification deflection rate as it applies to PVC material. All
pipe installed passed all testing as described in the Contract.
2. Timely Performance; The original Contract completion date was March 8, 1999. It is noted in Section
00500 (General Section of the Technical Specifications) that the work shall be constructed within the eagle
non-nesting season (May 16 to September 30) for that portion of the pipeline within the primary and
secondary zones. The Contractor was reminded of this note during the August 28,1998 pre-construction
meeting and failed to meet the date restriction. The Contractor did not begin installing pipe until December
15,1998, which was well after the specified time period to address the eagle nest area. The Contract would
not be complete until after the next years nesting season posing a schedule problem that the County would
have to deal with- The County offered change order number one (1) to add extra force main work. The
Contractor and County negotiated the change order with respect to time and money. The new completion
date was May 15, 1999. The County then issued change order number two (2) for additional expenses for
general work and included all additional time as deemed executable. Change order number two (2) changed
the completion date to June 1,1999. The Contractor completed me project on October 26,1999. The
Contractor bad 146 days of liquidated damages assessed and was charged with the engineering fees for all
time spent by the engineer during the LD period. The Contractor submitted a schedule late in the pre-
construction phase of the project The schedule was reviewed by the engineer and was not excepted. The
schedule was rejected because it was incomplete with respect to detailed work items. The Contractor was
informed that the County required a updated schedule every month. This was to be reviewed with each pay
request. The Contractor submitted a schedule with each pay request but failed to revise as requested by both
the County and the Engineer. The schedule never incorporated the critical path of the project and was never
accepted by the County for official use. The schedule was a key variable in noting that the Contractor was
not prepared for this project. DeJonge failed to value the importance of the schedule as it applied. With a
project of this magnitude, the schedule is a major tool in helping deliver a project on time. The schedule
would have helped in determining the extra time needed, if any. With the information provided, the
Contractor had no support for the time overage. Also note, the Contractor used valuable time in requesting
to use an unspecified product. It was noted that the Contractor requested the County on the use of PERMITS
coating in lieu ofPROTECTO 401 coating. The 401 coating was specified in the Contract and the
Contractor took the request as far as potential litigation between the County and the supplier of the
PERMTTE coating system- On December 2,1998, the Contractor opted to use the specified product after
wasting months of valuable time. The Contract documents outlines the process of substitution of materials
which the Contractor failed to follow.
3. Coordination w/ Owners Representative: In the early days of the Contract, the Contractor would submit
questions to only the engineer or the County but would not copy both. The Contractor would seek the
answer he wanted without justification from the owner in all cases. The Contractor bombarded alTparties
with correspondences- During the short life of the project, over 250 letters were produced by the Contractor.
Most of the correspondences, some 80%, were request for additional money. Most of the request were time
consuming, not justified and denied by the County and engineer. The County and the engineer spent
numerous hours on these items. The Contractor actually stopped work on every occasion he could muster.
An example of such action was when the Contractor actually stopped pipe installation when he ran. into a
existing fence line. He stated that he needed direction of the fence removal and would charge for "idle
![Page 41: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/41.jpg)
'' equipment" for such a delay. These types of actions continued during the life of the project Instead of
monthly progress meeting, as established by the pre-construction meeting, the County and the engineer were
forced to conduct weekly meeting with the Contractor. This action was created after a meeting on March 9,
1999 where the Contractor was threatening to walk away from the project and take legal actions against the
County. The meeting, which was held on March 9,1999, established goals that all parties tried to reach.
The task of weekly meetings was needed to keep the Contractor on track and to reduce the conflicts that the
Contractor was creating. This action caused additional cost to the County via engineering fees and in-house
cost. The Contractor stated directly to Jody Kirkman, the project manager, "I don't bid a project that I can't
recover on change orders".
4. Supervision of Subcontractors: No real problem were noted with the Contractor's subcontractors. It
should be noted that the Contractor did request multiple meetings between the County and the subcontractors
to resolve or negotiate change orders. The Contractor was informed early on that the County does not have
contractual obligations to subcontractors, but the Contractor failed to follow this fact The meeting consisted
of threats of "do the work my way or don't do it at all". The County was able to negotiate without to much
lost time or money.
5. Compliance with Safety Standards: The Contractor failed to follow all safety standards within the
Contract. The Contractor was warned daily for the use of hard hats and sheering and/or shoring deep trench
lines. Daily, the County informed the Contractor that he would be graded on his safety compliance with
respect to the hard hat issue. The County inspector reported the non-compliance via the daily report.
6. Relations with the Public: During site clearing operations behind the Longwood Run Subdivision, it was
noted that the Contractor confronted a homeowner on the method of removing trees and overhanging
branches. It was noted that the Contractor informed the homeown&r thai it was his business to determine the
method of removing trees and overhanging branches on County owned lands. It was understood that the
Contractor actually used the track hoe to "strip" the trees of branches. This method outraged me
homcowners and the comments offered by the Contractor did not help. Also noted was the lack of
cooperation with staff at the longwood Run Park while the Contractor worked at Longwood Park. The
original plans included a thirty-foot (30') deep installation of a lift station know as NC #1. The lift station
had to be revised with respect to the depth because the Contractor did not include the task of working around
the Park's schedule. This was done to keep the project on track. The revision did cost the County valuable
time and money.
OVERALL EVALUATION; DeJonge Excavating, Inc. did not fulfill the Contract requirements. DeJonge
failed to follow the requirements in which the County required on this project. Due to numerous letter
submittals, the County and the engineer dedicated many unnecessary hours to the project. DeJonge would work
up to a conflict then stop and charge for delays. The Contract was very clear on handling unforeseen items,
DeJonge on the other hand was clear that they were not going to follow the defined documents. The project was
argument from day one in which DeJonge excavating wanted to win, at whatever cost. Currently, DeJonge
Excavating, Inc. has entered into legation against the County to recover claims in which the County has denied.
The Contractor has carried this style of work ethics over to other utility proj ect with Sarasota County. DeJonge
has proven to seek change,orders at whatever means available and this work ethic will cost the awarding
business center more dollars than awarding to the next lowest bidders. This statement has been proven based on
past performance with the Sarasota County Environmental Business Center.
-'It is our strongest recommendation that Purchasing remove the Contractor from the pre-qualified status until
such time that they can adequately prove/provide a successful track record in utility related work. This should
![Page 42: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/42.jpg)
ui'.j-.uuu j.o:ju r.i-k. a-t-i. >>.L& ia--i on.y rn.u'-nvc.iLc.-'.A >touu.>
'include underground water, sewer and storm pipe work, lift station installations, any treatment plant work and/or
Governmental construction projects above the hundred thousand dollar ($100,000) mark.
INITIALS
JCK PDZ
4
![Page 43: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/43.jpg)
y ; • « o' » u y u j. o ; ^ u r AA ^-u. ^xu < ^ - -i •JA^ mu^ i- IVC..AU-,.-' j.
PERFORMANCE EVALUATION - CONSTRUCTION CONTRACTS
CONTRACT NUMBER: 99-328 CONTRACT TITLE: Proctor Road/Honore Avenue Force Main
CONTRACTOR (COMPANY NAME, ADDRESS, TELEPHONE NUMBER, POINT OF CONTACT):
DeJonge Excavating Contractors, Inc.
P.O. Box 743
Venice, Florida 34284
(941>493-1202
Mrs. Eileen DeJonge, President
DATE OF AWARD
July 27,1999
ORIGINAL CONTRACT
COMPLETION DATE
November 6,1999
REVISED CONTRACT COMPLETION DATE
DATE WORK ACCEPTED
DESCRIPTION AND LOCATION OF WORK:
The project consisted of installing 8", 10", and 12" force mains. The project included associated valves, fittings and directional bores.
Work is located within Sarasota Counly Transportation right-of-way or easements on Honore Avenue from Ashton to Proctor Road and on
Proctor Road from Honore Avenue TO Gantt.
. Place an 0x0 in the appropriate column
PERFORMANCE ELEMENTS
QUALITY OF WORK
TIMELY PERFORMANCE, INCLUDING
ADHERENCE TO SCHEDULE
COORDINATION WITH OWNERDS
REPRESENTATIVE
SUPERVISION OF SUBCONTRACTORS
COMPLIANCE WITH SAFETY STANDARDS
RELATIONS WITH THE PUBLIC
OVERALL EVALUATION
OUTSTANDING GOOD SATISFACTORY UNSATISFACTORY
X
X
X
X
X
X
X
Note; Please supply comments on Page 2 for all Performance Elements evaluated other than OSatisfactory
EVALUATED BY: . BUSINESS CENTER- Environmental Services. Utilities Engineering
Joseph A. Griffin, P.E., Project Manager
EVALUATOR
Patrick. D. Zoeller, P-E., Engineering Manager
REVIEWER
•GSDFonn 2.03 897
![Page 44: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/44.jpg)
jr^y rx\,u^ L i\r..U£,.\ i
COMMENTS
1. Quality of Work: The Contractor did not perform in a satisfactory manner. The Contractor was given directives to complete the
project by letter dated December 2,1999 from our Consultant The system as installed was never tested. (Letter Attached)
2. Timely Performance: The original Contract completion date was November 6.1999. The Contractor had 91 days of liquidated
damages assessed and was charged with engineering fees for all time spent by the Engineer during the liquidated damages period.
This project was started on August 6, 1999. From the beginning the Contractor took it upon himself to meet with the Forestry,
Risk Management, Stomiwater Maintenance, and the Health Dept without our knowledge. The Contractor was required to submit
an updated schedule with each pay request. The schedule never incorporated the critical path of the project The schedule wa$ a
key variable in noting that the Contractor was not prepared for this project All contractors need to understand the importance of
the schedule as it applies to the overall timeline.
3. Coordination w/Qwaers Representative: This Contractor initiated 167 letters. The Contractor did not provide preconstruction
videos or project photos prior to doing directional drill work and was so notified- Response from their chief estimator. Hank
Davidson was "video was taken for record and not for approval and could not see the need for panic". At the preconstruction
conference meeting the Contractor was to provide video for approval prior to starting any work. On an almost daily basis the
Contractor was submitting requests for more time and monies. Our Consultant was prompt in responding to Contractor's requests
and requesting backup information from the Contractor. The Contractor bombarded all parties with excessive correspondence,
sending it to whomever they deemed correct, not as directed and repeatedly instructed. On August 12, 1999 DeJonge met with
Norm Easy of Forestry regarding the trees along Proctor Road (sta. 75+00 to 89 +69) without consultant or Utility knowledge.
Correspondence from Dejonge regarding the issue and their arrogance was the catalyst for the County requesting that Hank
Davidson be removed from this project, letter atttached dated August 20,1999.
4. Supervision of Subcontractors: UNSATISFACTORY - When requested by them, we authorized DeJonge to order HDPE for
additional directional bores and we would negotiate the final cost without ordering delays involved. They received the HDPE, did
not bill for stored materials, and when we could not agree on final costs DeJonge allowed Piore (Directional Bore Contractor) to
use it on another job.
5. Compliance with Safety Standards: Compliance with the Florida Safe Trench Act was questionable (Engineer can provide
Photos) County Public Works shut them down because barricade lights were not functioning.
6. Relations with the Poblic: DeJonge used private property at 533 8 Proctor Road for three months to store materials, without
compensation. We were advised of the situation and required compensation to die owner. The contractor, DeJonge used Mr. Billy
Groves' property, without his permission, to park their equipment
OVERALL EVALUATION: UNSATISFACTORY - Their methods cost us all a lot of time and money. DeJonge refused to
follow directives unless their demands were met resulting in their claims for idle equipment and refusal to complete the work. The
best example of this is the trees on Proctor where they ended up doing tile work as perthe plans and as repeatedly directed but only
after we removed the adjacent tree. Too much time was spent getting them to do the work as bid. Norm Easy told us that the trees
could be removed as long as the county was addressing the impact that would some day happen to the privately owned trees.
October 1\, November 19,1999 and January 26, 2000 meetings were held to resolve various issues. The Contractor had claims
totaling $183,000 that included claims for material, loss of efficiency, and idle equipment The County and the Contractor were at
an impasse. DeJonge was relieved of continuing the project as of February 8, 2000.
The major stopping issues were as follows: Well issue at sta-17+00 on September 22,1999-The Contractor was given direction
to install the force main around the existing well using fittings. He chose not to follow direction. On December 2,1999 he was
directed to install the fittings. He requested demobilization/remobilization costs of S2,948 and reduction in work efficiency of
S3,443. Claim was denied per letter dated January 24,2000. The tree issue at sta. 58+58 - The Contractor was to install the force
main by removing the tree. The tree removal on private property did not delay construction. The claim of$ 1,618 was denied- The
.48" CMP at sta 71+80 - The Contractor chose to ignore directive given by County and Engineer, all costs associated by claim
were denied S 14719.
![Page 45: MANATEE COUNTY GOVERNMENT AGENDA MEMORANDUM...Oct 03, 2000 · FROM: Janet E. McAfee, Director, Project Management SUBJECT: Recommendation of Award-IFB #00-6699MP Rehabilitation of](https://reader033.fdocuments.us/reader033/viewer/2022050516/5f9ff0892b895c74d64978a6/html5/thumbnails/45.jpg)
•J^\^ 1 r\^/^ L AV^.-AI-
It is our strongest recommendation that Procurement remove the Contractor from the pre-qualified status until such time that they
can adequately prove/provide a successful track record in utility related work. This should include underground water, sewer,
storm pipe work, lift station installations, any treatment plant work and/or Governmental construction projects above the one
hundred thousand dollar ($100,000) mark.
______/______ INITIALS
JAG PDZ