MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE...
Transcript of MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE...
![Page 1: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/1.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 1
//
Prath Mehta PE, PSP, CCMAndrew Kosiba MSc, PMP2016 Project Management Symposium
MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE (EV) METRICS.
![Page 2: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/2.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 2
//
Prath Mehta, P.E., PSP, CCMAnd
Andrew Kosiba MSc, PMP
Johnson, Mirmiran & Thompson, Inc.,72 Loveton Circle, Sparks, MD 21152
[email protected]@jmt.com
Presented by:
![Page 3: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/3.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 3
//
• “You cannot manage what you cannot measure…and what gets measured gets done.”
— Bill Hewlett, Hewlett Packard
![Page 4: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/4.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 4
//
Outline• Introduction
– Project Life Cycle– Organizational Challenges
• Cost Management– Establish UCC– PMISTechnology
• Project Costs– Design – Operations– Construction
• EV Reporting Metrics
![Page 5: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/5.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 5
//
Introduction – Project Life Cycle• Traditional project delivery method
– Plan > Design > Bid > Build• Costs and related documents in individual silos• Disconnected costs information• Inability to forecast costs• Lessons Learned
Planning(Conceptual Estimate)
•Conceptual Planning
•Traffic Impact Studies
•Community Outreach
Design(Engineer's Estimate)
•Bridge Design•Pavement Designs•Sidwalks and Reconstruction
Construction(Bid Costs)
•Bridges•Reconstruction•Resurfacing•Allys and Footways
![Page 6: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/6.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 6
//
Introduction – Organizational Challenges• General
– Communication within the agency– Costs data in excel silos
• Project Delivery Challenges– Skilled resources– Definition of requirements
• Organization Challenges– Planning– Design– Construction
![Page 7: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/7.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 7
//
Introduction - Challenges• Planning
– Efforts are not estimated per project – Operational costs
• Design– Lack of consistency between bid items– Accuracy and validation of engineer’s estimate– Budget for construction contracts
• Construction– Status of the project – Tools and resources to track and compare
progress
![Page 8: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/8.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 8
//
Cost Management
• Total Cost Management – Inception in planning
– Completion in construction
• Owner Agency– Public funding for budget
• Tool set for the agency– Track project from design estimate (PS&E)
– Comparison of bids during advertisement
– Construction costs tracking in construction phase
![Page 9: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/9.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 9
//
Cost Management - UCC• Traditional method
– Agency accounting– Not so standardized– Lack of enforcement
• Establishment of UCC– Not an innovation– Old recipe in new package– Enforcement
1 2 3 4 5 6
Cost Category Item Number
For Example:
400 340 Steel HP 10 x 42 Bearing Pile
200 010 Class 1 Excavation
LF
CY
300 090 Flowable Backfill for Utility Cuts
CY
![Page 10: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/10.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 10
//
Cost Management - UCC
• Benefits of UC
– Standardization
– Similar to account codes
– Step closer to total cost management
• Agency Account Codes
– 26 digit code shared across multiple agencies
– Includes operational budget
– Initiated in project planning phase
![Page 11: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/11.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 11
//
Cost Management - UCC
• Benefits of UCC
– Standardization
– Similar to account codes
– Step closer to TCM
• Agency Account Codes
– 26 digit code shared across multiple agency
– Includes operational budget
– Initiated in project planning phase
![Page 12: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/12.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 12
//
Cost Management - PMIS
• Project Management Information Systems– Not an agency information systems– Project cost accounting– Spanned across departments– All project related information
• Documents (IDR, Submittals, RFI, Meetings)• Contracts / Payments• Change Orders• Schedule and Costs
– Ability to report on-demand and on everything !!!
![Page 13: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/13.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 13
//
Cost Management - Technology
• Resistance for custom solution• Off-the-shelf product
– Licensing– Implementation– Configuration – Plug-ins or customization– Reports
• Schedule driven organization– P6 : a must have ???
• Paper process replication
![Page 14: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/14.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 14
//
Cost Management - Technology
![Page 15: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/15.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 15
//
Cost Management - Goal
![Page 16: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/16.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 16
//
Project Costs
![Page 17: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/17.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 17
//
Project Costs - Design• Challenges
– Unique identifier for tasks under a contract
– Use of UCC for engineer’s estimate
• Tools– Estimate validation tool
![Page 18: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/18.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 18
//
Project Costs - Design• Tools – Estimate Validation Tool
![Page 19: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/19.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 19
//
Project Costs – Bid Costs and Evaluation • Comparison to Engineer’s Estimate• Linked with UCC• Estimate Validation Tool• Bid Comparison Report
![Page 20: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/20.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 20
//
Project Costs – Bid Costs and Evaluation• Trend Analysis using UCC codes• Accepted bid costs values• Received bid costs values• Engineer’s Estimate comparison
$-
$100.00
$200.00
$300.00
$400.00
$500.00
$600.00
Avg Item Pricing
![Page 21: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/21.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 21
//
Project Costs – Construction Costs• Contract Pay Items in IDR module• Weekly reconciliation of recorded quantities• Review on-going cost trends using UCC
Change Order NegotiationExtra Work Order Authorization
![Page 22: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/22.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 22
//
Project Costs – Construction Costs• Cost loaded schedule and approved updates• Reconciliation with installed quantities • Update Program Schedule using installed
quantities
• Manage program cash-flow using P6
![Page 23: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/23.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 23
//
Project Costs – Construction Costs
![Page 24: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/24.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 24
//
EV Reporting Metrics• Project Status Report
– Installed Costs– Approved Costs– CO Costs– Duration % Complete (Approved CPM)
![Page 25: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/25.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 25
//
EV Reporting Metrics• Program Report
– Basic project information– Installed costs and Estimate to Complete– SPI using installed and approved costs
![Page 26: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/26.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 26
//
EV Reporting Metrics
![Page 27: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/27.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 27
//
EV Reporting Metrics• P6 EPPM Dashboards
– Cost loaded program schedule– Standard portlets and indicators– Construction
![Page 28: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/28.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 28
//
Summary• Challenges with public agencies
– Paper to electronic processes
• Standardization across the department using UCC• Enabled better estimates for construction projects• Provided EV metrics to manage construction
performance• Improved construction budget through validation of
engineer’s estimate
![Page 29: MANAGING OWNER’S COST AND DEVELOPING EARNED VALUE …pmsymposium.umd.edu/wp-content/uploads/2016/05/Mehta_Prath.pdf · Prath Mehta, P.E., PSP, CCM. And . Andrew Kosiba MSc, PMP.](https://reader033.fdocuments.us/reader033/viewer/2022042911/5f43969d98cff1042874900e/html5/thumbnails/29.jpg)
Mehta/Kosiba UMD Project Management SymposiumMay 12-13, 2016Slide 29
//
Questions/Comments?
29