Managing Capital Projects FINAL PRESENTATION Sept 14 2016 · managing capital projects and how you...
Transcript of Managing Capital Projects FINAL PRESENTATION Sept 14 2016 · managing capital projects and how you...
Webinar Series
Managing Capital Projects
What YOU Need to Know
Speaker
Bill Bacon DpIT, CET, PMP
Senior Project Manager, Technical Services DepartmentHousing Services Corporation
Sept 14,2016
Questions?
Control Panel-
Questions pane
Type your questions here
then click send
About SHARE ONLINE RESOURCE HUB
Revitalization
ONLINE RESOURCE HUB
• EOA Resource Centre
• Building Capacity
• Revitalization
EVENT SERIES
Regeneration Forum
EVENT SERIES
• Webinar Series
• Innovation Events
• Regeneration Forum
http: //share.hscorp.ca
Fall SHARE 2016 Webinars
Sept 26 Oct 19
Fall SHARE 2016 WebinarsNov 2
Nov 16
Visit the SHARE- EVENTS
for more info
http://share.hscorp.ca
Speaker: Bill Bacon
Senior Technical Project Manager
About this Webinar
� Intended to equip you with the fundamentals of
managing capital projects and how you can get the
most value from your capital budget efficiently and
effectively.
� Provide insight and practical tips on how to
maximize the chances of capital project success by
anticipating common pitfalls, early on, and taking
appropriate actions to avoid them or deal with
them should they present themselves.
Webinar will cover:
� How to avoid or manage common pitfalls
� Practical tips on how to maximize the changes of
capital project success
� Understanding project constraints and taking
action early on
� Managing and avoiding risk
� Value of professional project management
Capital Projects
Capital projects can be for new construction,
expansion, renovation, or a replacement project for
an existing facility or major components within a
facility
Because capital projects involve
many different processes and
stakeholders, there is always a
chance that the project will be
hindered by unknown risks,
and/or unexpected problems.
How to avoid or manage common pitfalls
Caution – Pitfalls Ahead!
Why does it matter:
Common pitfalls, if not avoided or properly managed, will cause a project to take longer and cost more than expected.
Why are we
are running
out of time
and money?
Anticipating common pitfalls and understandinghow to avoid or manage them is one of the most important steps towards ensuring a project’s objectives can be successfully achieved.
So what can you do
While not all pitfalls can be avoided, having an experienced project manager guide you through the process will help minimize or mitigate the many risks related with capital projects.
A Project Manager can help!
The pitfall monster
... I want more, faster and cheaper!
How could we
avoid or manage
this potential
risk?
Where the pitfall monster hides
1. Site investigation and feasibility studies
2. Stakeholder alignment
3. Scope, schedule and budget definition
4. Acceptance criteria for deliverables
5. Risk management
6. Performance monitoring & control
7. Reporting and Communications
8. Change control
9. Project close out
10. Project Management
#1 Site Investigations & Feasibility Studies
� By conducting appropriate site investigations and
feasibility studies while your project is still in its
concept stage you determine what you can afford
and how to get what you want.
� It can also identify things in your project that will
likely increase the cost of construction.
#2 – Stakeholder Alignment
� Sufficient time must be spent in the planning phase
to make sure that all stakeholders are on the same
page.
� Stakeholder alignment (buy-in and support) is KEY to
the success of any project!
Create a Stakeholder Map
Identify your
stakeholders
Create a RACI Chart
A RACI Chart is a tool that can be used to help
identify the roles and responsibilities of those
involved in the project and help avoid confusion
of those roles and responsibilities.
What’s RACI?
RACI - Definition
RACI – Example
# 3 – Scope, Schedule & Budget Definition
Capital projects completed “within budget” and
“on schedule” are an exception, not the rule!
Understanding the Triple Constraints
Clearly Define Constraints!
Ensure scope, budget available, and time is
clearly defined during initial project plan and
again at project initiation.
Ensure stakeholders are aware of what the
ramifications might be for any requested or
mandated changes.
Develop Comprehensive Schedule
Ensure ALL project activities are in the schedule
Breakdown, breakdown, breakdown work!
Review schedule and get input from stakeholders
Consider “history” – other similar projects
Once project is implemented, monitor scheduled activities
#4 – Acceptance criteria for deliverables
“Acceptance criteria represents specific and defined list
of conditions that must be met before a project has
been considered completed and the project
deliverables can and will be accepted by the client.”
Poorly defined acceptance criteria for deliverables is
another of the major causes of project failures.
Do NOT assume a listed deliverable (requirement) =
“acceptance criteria”
Define SMART Acceptance Criteria
S – Specific
M – Measurable
A - Achievable
R – Realistic
T – Time Bound
#5 Risk Management
• Failing to be pro-active and openly consider risks
and issues is a major pitfall you will want to
avoid.
• Recognize risks and issues will be part of the
project and take time “early on” to identify them
and make plans to avoid or management them
Managing Risk
For negative project risks ...
• some we can AVOID ☺
• some we can CONTROL ☺
• some we can TRANSFER ☺
• some we must ASSUME �
Avoiding Risk
Example:
Choosing a vendor/ design/product-
with a proven track record at a higher
price over a new vendor that is
providing a significant price incentives
to avoid the risks related with working
with a new system.ie: exterior stucco cladding
Controlling Risk
Some practical steps you could take include:
�experienced project management
�trying a less risky option
�ensuring an up-to-date DSS is in place and made available to the Constructor
�understanding legislation related to Constructor /Owner duties
• preventing access to the hazards
• ensuring work by the constructor is set up to reduce exposure to the hazard(s)
Transferring Risk
BondingBid bonding or deposit
Labour and material bonds
Performance bond
InsuranceLiability
Un-owned vehicle
Builder’s risk or umbrella coverage
Assuming Risk
�Accepting risk occurs when the cost of
managing a certain type of risk is accepted,
because the risk involved is not adequate
enough to warrant the added cost it will take
to avoid that risk.
� i.e., landscape covering when repairing exterior walls.
Develop a Contingency Plan
Contingency funds are funds set aside by the
project to address unforeseen events that cause
the project costs to increase
� Project with “high risks” will typically require a large
contingency budget.
� After risks are identified and evaluated, develop a risk
mitigation plan – what you will do to minimize the impact of
the unexpected event.
Questions?
Control Panel- Questions pane
Type your questions here
then click send
#6 – Performance Monitoring & Control
� Your project should have clearly defined
“milestones” so that all stakeholders
understand what “successfully
completed” means. (SMART Acceptance Criteria)
� Performance should be measures against
these clearly defined milestones.
� Take corrective actions as soon as issues
emerge.
#7 – Reporting and Communications
• Create a reporting and communication plan based on your
stakeholder needs (refer to your Stakeholder Map and RACI Chart).
Stakeholder(s) Information Method Frequency Who is
responsible?
Board members Project status E-mail report Monthly Project Manager
Building Owner Detailed project
reporting
Meeting,
report
Every other
week
Project Manager
Financial Funder Project status Meeting Monthly Project Manager
Vendors Project initiation Meeting 1 month prior
to Project
Project Manager
Develop a Communication Plan
Communications & Reporting
� clearly defining where the project is relative to
Budget, Schedule and Scope.
� status reporting- include details on any
contingency expenditures and change orders
(requests, approvals, completed, or rejected).
� performance is based on clearly defined and
understood measurements (milestones).
� planned versus actual – be comprehensive.
Your reporting should include:
#8 – Change Control• Failing to define and execute an integrated change
control process will surely reap ‘disaster’
• Create a well-defined change control process that provides a mechanism for evaluating, approving or rejecting changes
• Ensure changes are assessed for their impact on constraints of the project before making decisions and enacting change
• Engage all stakeholders in change control
(RACI chart)
#9 – Project close out
Critical steps often overlooked: � Deficiency review
� Final inspection / close out of permits / record drawings
� System start up, verification, demonstration
� Testing and verification reports
� Warranties / Guarantees / Certifications
� Construction lien requirements and release
� Payment certifications (final)
� Insurers notifications (handover)
� Occupancy permits, surveys, title registrations
� End of warranty period review
It’s better to be looked over than overlooked!
#10 Project Management
Consider: Who is managing your project?
• Ensure all team members follow value-added
project management processes; these
processes will help you effectively execute,
monitor, and control your project
HSC Technical Services Can Help with Your
Capital Projects To-Do List
Ontario & across Canada
Procurement Management
Full Project Management
Services
Multi-Year Project
Management
Preventive Maintenance
Planning
Building Inspection
Reports
Data Verification
for Asset Planner
Thank you
If you need Project Management assistance:
Bill Bacon, DplT, CET, PMP
Senior Technical Project Manager
Telephone: 705-618-0512
E-mail: [email protected]
Questions?
Control Panel- Questions pane
Type your questions here
then click send
http: //share.hscorp.ca
Email: [email protected]