Man Hour Estimate
-
Upload
dana-guerrero -
Category
Documents
-
view
30 -
download
2
description
Transcript of Man Hour Estimate
4.8.2.P Piping Engineering Company
Man Hours
Index
Drawings/Documents List P R200 50000
Line Index/Piping Line list P R 150 37500
Tie-in Schedule F A 250 62500Specification
F A120 30000
F A120 30000
P A60 15000
F A60 15000
Data Sheet
P R
60 15000
P R
60 15000
Procurement Related Documents
P R
160 40000
Calculations
F R
400 100000
P I400 100000
p R
300 75000
Engineering Dwg & 3-D Model
Overall Plot Plan F A100 25000
Contractor’s Deliverables
Phase 5Cost $ 250/Hr
Piping Material Selection Specification/Line class index
Piping Material Specification (Pipe Class)
Heat Tracing/Jacketing Specifications (If applicable)
Insulation specification & Thickness Table (Job Specification)
Special Piping Item Schedule & Data Sheets (Strainers, Traps, etc..) (if applicable)
Spring Support Schedule and Data sheets (If applicable)
Long Lead Item List & Material Requisitions, TBE, POR/PO (if applicable)
Piping Wall thickness Calculation Sheets (All Line Classes)
Material Take Off (1st , 2nd, 3rd or final)
Stress Reports along with Stress isometrics for critical lines including executable CAESAR-II input (If applicable)
F A
100 25000
P R
250 62500
Underground piping layout Plan P A300 75000
P A300 75000
P A300 75000
TOTAL 3690 922500
Unit Area Plot Plan/Equipment Layout plan, elevation and sectional elevation
Piping Study Drawings (Critical Piping only)
Eye wash/ Safety shower location Drawings
Tie-in Location Plan & Detailed Drawings
4.8.2.G Machinery Company Man Hours
Critical and Long lead equipment List F A 200
Drawings/Document List F A 500
F(LLE) A
500
General/ Project Specifications F A 250
Equipment Data Sheets F A 700
F(LLE) A200
F(LLE) A500
Requisitions for Packaged Units F A 500
Vendor Deviations / Exceptions F(LLE) A 125
F(LLE) A600
Machinery Painting Specification F I 150
Machinery Insulation Specification F R 150
P A0
Machine Monitoring System Scope F A 300
F(LLE) R300
F(LLE) A300
List of Special Tools F(LLE) A 300
F(LLE) A300
TOTAL 5875
Contractor’s Deliverables
Phase 5
Complete List of Vendor Data and Drawings in accordance with the Vendor Data section of all applicable Standards / SES.
Rotating Machinery Final Selection Document
Rotating Equipment Requisitions including completed Data Sheets
Technical Bid Tabulation/ Evaluation & Recommendations
Rotating Machinery Protective Instrumentation (Instrumentation)
Electrical Motors/ Generators Mechanical Details
List of Capital, Pre-commissioning, Commissioning & Start-up and Operational Spare parts.
Inspection and Testing surveillance plan, procedures and third party inspection scope
50000125000
12500062500
175000
50000
12500012500031250
1500003750037500
075000
75000
7500075000
750001468750
Cost $ 250/Hr
4.8.2.Q Stationary Company
General
Equipment List F R 200
F A
600
F R
500
F A400
Identification of two-year operational spare parts P R100
Specification
Mechanical Data Sheets (for Critical items / LLE) F A700
Mechanical Data Sheets (for other equipment) P A 200
Project Specifications (for Critical items / LLE) F R 400
Project Specifications (for all other equipment) P R 200
Equipment Internals specifications (for Critical items / LLE) F R800
P R
300
P R300
Fireproofing Specification P R150
Rust Prevention Specification P R150
P R150
Technical specification for equipment modification F R
500
F R
500
TOTAL 7200
Contractor’s Deliverables
Phase 5
Man Hours
Technical bid evaluation & tabulation for Critical items (based on service and MOC) & LLE 1
Purchase Inquiry Specifications (RFQ/ MR for equipment vendors) - for Critical items / LLE 1
Purchase Specification – “Ready for order” stage for Critical items / LLE 1
Refractory Specifications (including MOC and types of anchors with spacing details)
Painting Specifications (for special applications not covered by SES, if any)
Internal lining specification (ex. elastomers/GRP/FRP/glass etc.)
A complete Inspection Report addressing the current condition of the pressure components and attachments
General
50000
150000
125000
100000
25000Specification
175000
50000
10000050000
200000
75000
75000
37500
37500
37500
125000
1250001800000
Cost $ 250/Hr