DIFFERENCE IN AMOUNT BETWEEN PRE AND POST SANCTIONED ESTIMATEof Malay Barrag
HEAD WORKS:-
SN ITEMS
PRE
SANCTIONED
AMOUNT
POST
SANCTIONED
AMOUNT Diff. of amount
1 E/W Excavation in foundation 1650700.09 1775908.78 -125208.69
2 Extra for marshy land 372738.73 0 372738.73
3 Extra for wet soil 61836.84 44352 17484.84
4 Etra for lift in cutting 247347.36 266109.12 -18761.76
5 Etra for lead in cutting 123673.68 0 123673.68
6 E/W in filling 3890651.97 1500106.8 2390545.17
7 Extra for lift in filling 617019.7 237902.4 379117.3
8 Exra for lead in filling 617019.7 0 617019.7
9 Compaction 1242609.11 479109 763500.11
10 Stripping 1050557.45 0 1050557.45
11 Filling in foundation 356706.75 0 356706.75
12 P.C.C.-M 10 5398829.77 782017.86 4616811.91
13 P.C.C.-M15 29044519.27 29122267.7 -77748.43
14 C.C. BLOCK pitching 9012094.45 7073002.36 1939092.09
15 R.C.C. M20- 27677241 26996864.76 680376.24
16 Deck slab 1267134.75 1267134.75 0
17 Brick work 973833.25 1850419.71 -876586.46
18 Sheet pile 27072486 17853201.33 9219284.67
19 M.S Steel bar 45244012.7 15146789.24 30097223.46
20 Stone boulder 19628353.39 10096422.5 9531930.89
21 Pitching above apron and on slope 2474613.6 0 2474613.6
22 Gravel filter 115226.84 115234.56 -7.72
23 Dewatering 10237984.6 2891428.25 7346556.35
24 Shuttering in barrage portion 2025908.94 2006924.18 18984.76
25 Shuttering in deck slab 363317.33 363317.33 0
26 Brick on edge 1777133.6 0 1777133.6
27 Copper seal 2400804 2130378.74 270425.26
28 Rubber seal 400000 346000 54000
29 Bituminous board 18231940 15770628.1 2461311.9
30 Outlet in Kasath & Bhojpur distry. 400000 0 400000
31 Transformer purchase 20000000 0 20000000
32 Weep holes 179840 98055 81785
33 Carriage Sheet pile Lead-150 km 300437.78 198126.42 102311.36
34 Carriage of stonechips Lead-260 km 43099367.29 39037826.4 4061540.89
35 Carriage of sand Lead-65 km p+1 km k 6446691.01 5758550.07 688140.94
37 Carriage of steel Lead-30 km 214811.59 99441.9 115369.69
38 Carriage of bricks lead-7 km p+ 1 km k 314452.52 141674.62 172777.9
39 Carriage of cement Lead-30 km 1796494.83 1596911.93 199582.9
40 Carriage of gravel Lead-260 km 439911.01 439941.99 -30.98
TOTAL 286768300.9 185486047.8 101282253.1
E/W Excavation in foundation 1650700.09 1775908.78 -125208.69
Extra for marshy land 372738.73 0 372738.73
Extra for wet soil 61836.84 44352 17484.84
Etra for lift in cutting 247347.36 266109.12 -18761.76
Etra for lead in cutting 123673.68 0 123673.68
E/W in filling 3890651.97 1500106.8 2390545.17
Extra for lift in filling 617019.7 237902.4 379117.3
Exra for lead in filling 617019.7 0 617019.7
Compaction 1242609.11 479109 763500.11
Stripping 1050557.45 0 1050557.45
Filling in foundation 356706.75 0 356706.75
P.C.C.-M 10 5398829.77 782017.86 4616811.91
P.C.C.-M15 29044519.27 29122267.7 -77748.43
C.C. BLOCK pitching 9012094.45 7073002.36 1939092.09
R.C.C. M20- 27677241 26996864.76 680376.24
Deck slab 1267134.75 1267134.75 0
Brick work 973833.25 1850419.71 -876586.46
Sheet pile 27072486 17853201.33 9219284.67
M.S Steel bar 45244012.7 15146789.24 30097223.46
Stone boulder 19628353.39 10096422.5 9531930.89
Pitching above apron and on slope 2474613.6 0 2474613.6
Gravel filter 115226.84 115234.56 -7.72
Dewatering 10237984.6 2891428.25 7346556.35
Shuttering in barrage portion 2025908.94 2006924.18 18984.76
Shuttering in deck slab 363317.33 363317.33 0
Brick on edge 1777133.6 0 1777133.6
Copper seal 2400804 2130378.74 270425.26
Rubber seal 400000 346000 54000
Bituminous board 18231940 15770628.1 2461311.9
Outlet in Kasath & Bhojpur distry. 400000 0 400000
Transformer purchase 20000000 0 20000000
Weep holes 179840 98055 81785
Carriage Sheet pile Lead-150 km 300437.78 198126.42 102311.36
Carriage of stonechips Lead-260 km 43099367.29 39037826.4 4061540.89
Carriage of sand Lead-65 km p+1 km k 6446691.01 5758550.07 688140.94
Carriage of steel Lead-30 km 214811.59 99441.9 115369.69
Carriage of bricks lead-7 km p+ 1 km k 314452.52 141674.62 172777.9
Carriage of cement Lead-30 km 1796494.83 1596911.93 199582.9
Carriage of gravel Lead-260 km 439911.01 439941.99 -30.98
TOTAL 286768300.9 185486047.8 101282253.1
MALAY BARRAGE EATIMATE OF S.L.R.
SN ITEMS
PRE
SANCTIONED
AMOUNT
POST
SANCTIONED
AMOUNT Diff. of amount
1 E/W in excavation in foundation 9738.93 9738.93
2 Sand filling in foundation 6006.06 6006.06
3 Brick flat soling in foundation 48331.44 48331.44
4 Foundation slab -P.C.C.-M150 (1:2:4) 345244.46 345244.46
5a Brick work in foundation (1:4) 134579.29 134579.29
5b Brick work in super structure (1:4) 262312.7 262312.7
6 R.C.C. in super structure M200(1:1.5:3) 28356.59 28356.59
7 Weep holes 5395.2 5395.2
8 R.C.C. in super structure M200(1:1.5:3) 167391.52 167391.52
9 M.S. Steel Fe 415 0 0
M.S. Steel Fe 515 327828.49 327828.49
10 Cement plaster (1:3) 24258.79 24258.79
11 Shuttering 11783.08 11783.08
12 Back fillinf of foundation 99286.95 99286.95
13 E xtra for lift of E/W 7143.9 7143.9
14 Carriage of materials 0 0
Bricks 41804.08 41804.08
cement 16831.88 16831.88
Sand 105783.4 105783.4
Stone chips 319196.05 319196.05
Steel 1556.14 1556.14
Local sand 7094.7 7094.7
1969923.65 1969923.65
Part B Dismentalling
15 Dismentalling of cement/Lime concrete 6662.85 6662.85
16 Dismentalling of R. concrete cement 5925.31 5925.31
17 Dismentalling of Brick work 10422.29 10422.29
23010.45 23010.45
Part C temporary Diversion work
18 E/W in filling 9550.99 9550.99
19 Extra for lift 2639.00 2639
20 Sand filljng 1137.34 1137.34
21 Brick on edge soling 21230.14 21230.14
22 E/W in excavation 9141.42 9141.42
23 Carriage of materials 0
Bricks 2678.21 2678.21
Local sand 1343.82 1343.82
47720.92 47720.92
GRAND TOTAL= 2040655.02 2040655.02
MALAY BARRAGE EATIMATE OF CULVERTS
SN ITEMS
PRE
SANCTIONED
AMOUNT
POST
SANCTIONED
AMOUNT Diff. of amount
1 E/W in excavation in foundation 7493.18 7493.18
2 Sand filling in foundation 2361.86 2361.86
3 Brick flat soling in foundation 34261.56 34261.56
4 Foundation slab -P.C.C.-M150 (1:2:4) 261866.25 261866.25
5a Brick work in foundation (1:4) 102145.5 102145.5
5b Brick work in super structure (1:4) 190254.00 190254
6 R.C.C. in super structure M200(1:1.5:3) 214012 214012
7 Weep holes 3596.8 3596.8
8 R.C.C. in super structure M200(1:1.5:3) 101691.96 101691.96
9 M.S. Steel Fe 415 0 0
M.S. Steel Fe 515 201822.29 201822.29
10 Cement plaster (1:3) 17468.51 17468.51
11 Shuttering 8317.77 8317.77
12 Back fillinf of foundation 47623.73 47623.73
13 E xtra for lift of E/W 3426.62 3426.62
14 Carriage of materials 0 0
Bricks 28785.59 28785.59
cement 9562.05 9562.05
Sand 52179.86 52179.86
Stone chips 215615.44 215615.44
Steel 957.89 957.89
Local sand 2789.56 2789.56
1506232.42 1506232.42
Part B Dismentalling
15 Dismentalling of cement/Lime concrete 6662.85 6662.85
16 Dismentalling of R. concrete cement 5925.31 5925.31
17 Dismentalling of Brick work 10422.29 10422.29
23010.45 23010.45
Part C temporary Diversion work
18 E/W in filling 9550.99 9550.99
19 Extra for lift 2639.00 2639
20 Sand filljng 1137.34 1137.34
21 Brick on edge soling 21230.14 21230.14
22 E/W in excavation 9141.42 9141.42
23 Carriage of materials 0
Bricks 2678.21 2678.21
Local sand 1343.82 1343.82
47720.92 47720.92
GRAND TOTAL= 1576963.79 1576963.79
MALAY BARRAGE ESTIMATE OF OUTLETS
SN ITEMS
PRE
SANCTIONED
AMOUNT
POST
SANCTIONED
AMOUNT Diff. of amount
1 E/W in excavation in foundation 2728.43 2728.43
2 Sand filling in foundation 223.08 223.08
3 Brick flat soling in foundation 2672.16 2672.16
4 Foundation slab -P.C.C.-M150 (1:2:4) 5586.48 5586.48
5a Brick work in foundation (1:4) 33098.49 33098.49
6 Cement plaster (1:3) 1038.09 1038.09
7 Laying fitting fixing og NP2 PIPE 1502.06 1502.06
8 Supply of NP2 Pipe 1823.12 1823.12
14 Carriage of materials 0 0
Bricks 2532.28 2532.28
cement 352.91 352.91
Sand 2159.43 2159.43
Stone chips 3484.95 3484.95
Local sand 263.58 263.58
57465.06 57465.06
A CLEARIFICATION ABOUT RATE OF BITUMINOUS BOARD FOR EXPANSION JOINTS
The rate for Supplying, fitting and fixing of bituminous board in expansion joints has
been provided as item no. 5. 3. 8 in the present schedule of rate, Water Resources
,effective from 01.10.2012, which is Rs.45579.10/sqm. It is erroneous one which will be
cleared from following para.
The schedule of rate Book of Darbhanga zone ,which was effective from 08.11.2005 ,
has given the following rates for bituminous shaltex board for expansion joints:-
Thichness of the board Rate Rs.per sqm Percentage increase with respect to
12 mm thick board
12 mm thick 332.0 0%
18 mm thick 487.0 146.58 % , say 147 %
25 mm thick 581.0 175%
The above rates are mentioned on page no. 53 of the said Schedule of rate of
Darbhanga zone , whose photcopy has been attached hereby.
In the same way ,the rate of the same board is mentioned on page no. 89 of the
present Schedule of Rate, WRD, Bihar, effective from 01.10.2012 in following way:-
Thichness of the board Rate Rs.per sqm Percentage increase with respect to
12 mm thick board
12 mm thick 346.0 0%
18 mm thick 507.0 146.53 % , say 147 %
25 mm thick 37587.0 10863% Which is highly abrupt.
If we compare the incremental rate of Darbhanga zone and present Schedule of rate,
the incremental percentage from 12 mm to 18 mm is same( i.e. 147 %) ,but in 25 mm thick
it is highly abrupt and not acceptable in any case and the same figure has been taken for
analysis part too, so it has brought incremental error in the final rate. It is clearly a printing
mistake and it needs correction.
In the logical way ,we can increase the rate of 25 mm thick board by 175 % of the
rate of 12 mm thick board on the basis of Darbhanga zone Schedule of Rate. In this way,
the rate for 25 mm thick board becomes 1.75 x 346 = Rs.605.50 per sqm say Rs. 610.0 /sqm.
The analysis part becomes as follows for 25 mm thick board for S/F/F :-
Taking out 9.3 sqm
Bituminous board- 25 mm thick-9.3 sqm @610.0/sqm = 5673.00
Saltexprimer 2.25 kg @ 42.0/ kg = 94.50
Labour
Mason Gr. II 0.25 NO. @ 190.00 = 47.50
Unskilled mazdoor 0.25 no. @157 = 39.25
Total= 5854.25
Add 20 % as overhead charge & C.P. 1170.85
Total= 7025.10
Add 1 % cess 70.25
GRAND TOTAL 7095.35
So , rate per sqm = 7095.35 / 9.3= 762.9409677
Say Rs. 765.00/sqm
But it should be approved by the Departmental Schedule of Rate Committee