Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18...

296
[Type text] Environmental and Social Management and Monitoring Plan Prepared by Earth Systems SARL for Mako Exploration Company SA FINAL December 2015 MAKO GOLD PROJECT

Transcript of Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18...

Page 1: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

[Type text]

Environmental and Social Management and Monitoring Plan Prepared by Earth Systems SARL for Mako Exploration Company SA

FINAL

December 2015

Chapter 9 | Biological Impacts and Management Measures

MAKO GOLD PROJECT

Page 2: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

EARTH SYSTEMS

Environment | Water | Sustainability

Australian Business Number 42 120 062 544

RECORD DISTRIBUTION

Copy No. Company / Position Name

1 Toro Gold / Mako Exploration Company Paul Cannon

DOCUMENT REVISION LIST

Revision Status/Number Revision Date Description of Revision Approved By

Rev0 April 2015 Draft Nigel Murphy

Rev1 August 2015 Draft Nigel Murphy

Rev2 August 2015 Draft Nigel Murphy

Rev3 August 2015 Draft Nigel Murphy

Rev4 November 2015 Revised Nigel Murphy

Rev5 December 2015 Final Nigel Murphy

This report is not to be used for purposes other than that for which it was intended. Environmental conditions change with time.

The site conditions described in this report are based on observations made during the site visit and on subsequent monitoring

results. Earth Systems does not imply that the site conditions described in this report are representative of past or future

conditions. Where this report is to be made available, either in part or in its entirety, to a third party, Earth Systems reserves the

right to review the information and documentation contained in the report and revisit and update findings, conclusions and

recommendations.

Page 3: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

CONTENTS

TERMS AND DEFINITIONS ...........................................................................................

LIST OF ABBREVIATIONS .............................................................................................

1 INTRODUCTION .................................................................................................. 1

1.1 General Background ........................................................................................................................... 1

1.2 Structure ............................................................................................................................................ 1

1.2.1 Overview of Management Plans and Procedures ................................................................... 2

1.3 Presentation of the Project................................................................................................................ 4

1.3.1 Project Proponent ................................................................................................................. 4

1.3.2 Project Overview ................................................................................................................... 4

1.4 Report Author .................................................................................................................................. 10

2 LEGISLATIVE REQUIREMENTS, GUIDELINES AND COMMITMENTS ..................... 12

2.1 Toro Gold Environmental and Social Commitments .......................................................................... 12

2.1.1 Environmental and Social Performance Framework ............................................................. 14

2.1.2 Environmental and Social Design Criteria ............................................................................. 14

2.2 Legislative Requirement and Guidelines ........................................................................................... 14

2.2.1 Mining Convention Agreement ............................................................................................. 14

2.2.2 Relevant Legislation and Guidelines ..................................................................................... 15

2.3 International Standards ................................................................................................................... 20

2.3.1 IFC Performance Standards .................................................................................................. 21

2.3.2 World Bank General Environmental Health and Safety Guidelines ........................................ 21

2.3.3 International Cyanide Management Code ............................................................................. 22

2.3.4 UN Guiding Principles on Business and Human Rights .......................................................... 22

2.3.5 International Union on the Conservation of Nature Guidelines .............................................. 22

2.3.6 Extractive Industries Transparency Initiative ......................................................................... 23

2.4 Project Discharge Standards ............................................................................................................ 23

2.5 International Conventions, Treaties and Agreements ....................................................................... 40

3 ESMMP FRAMEWORK ........................................................................................43

3.1 Purpose of the ESMMP .................................................................................................................... 43

Page 4: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

3.2 Responsibilities and Human Resources ............................................................................................ 44

3.2.1 Responsibilities - Internal Parties ......................................................................................... 44

3.2.2 Responsibilities - External Parties ........................................................................................ 45

3.3 Capacity Building ............................................................................................................................ 46

3.3.1 Project Capacity Building ..................................................................................................... 46

3.3.2 External Capacity Building ................................................................................................... 48

3.4 Monitoring Systems ........................................................................................................................ 48

3.5 Reporting Systems .......................................................................................................................... 49

3.5.1 Data Management .............................................................................................................. 49

3.5.2 Project Reporting Commitments .......................................................................................... 50

3.5.3 Incident and Project Grievances Reporting .......................................................................... 52

3.6 Auditing and Facility Inspections ..................................................................................................... 52

3.7 Emergency Preparedness and Response .......................................................................................... 53

3.7.1 Assessment of Risk and Priority ............................................................................................ 53

3.7.2 Emergency Preparedness and Response Planning ............................................................... 54

3.7.3 Spill management ............................................................................................................... 54

3.8 Continuous Improvement ................................................................................................................. 55

4 PROJECT DEVELOPMENT AREA ........................................................................ 56

4.1 Objectives ....................................................................................................................................... 56

4.2 Context ........................................................................................................................................... 56

4.2.1 Pre-construction and Construction Phase ............................................................................ 56

4.2.2 Operations Phase ................................................................................................................ 56

4.2.3 Decommissioning and Closure Phase ................................................................................... 57

4.3 Management and Mitigation Measures ............................................................................................ 57

4.3.1 Pre-construction and Construction Phase ............................................................................. 57

4.3.2 Operations Phase ................................................................................................................ 58

4.3.3 Decommissioning and Closure Phase .................................................................................. 58

4.4 Monitoring Measures ...................................................................................................................... 59

5 OPEN PIT, MINING AND WASTE ROCK ............................................................... 60

5.1 Objectives ....................................................................................................................................... 60

5.2 Context ........................................................................................................................................... 60

5.2.1 Pre-construction and Construction Phase ............................................................................ 60

5.2.2 Operations Phase ................................................................................................................. 61

5.2.3 Decommissioning and Closure Phase .................................................................................. 62

Page 5: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

5.3 Management and Mitigation Measures ........................................................................................... 62

5.3.1 Pre-construction and Construction Phase ............................................................................ 62

5.3.2 Operations Phase ................................................................................................................. 63

5.3.3 Decommissioning and Closure Phase .................................................................................. 66

5.4 Monitoring Measures ....................................................................................................................... 67

6 MINERAL PROCESSING AND TAILINGS MANAGEMENT ....................................... 70

6.1 Objectives ........................................................................................................................................ 70

6.2 Context ............................................................................................................................................ 70

6.2.1 Pre-construction and Construction Phase ............................................................................. 70

6.2.2 Operations Phase ................................................................................................................. 71

6.2.3 Decommissioning and Closure Phase ................................................................................... 72

6.3 Management and Mitigation Measures ............................................................................................ 72

6.3.1 Pre-construction and Construction Phase ............................................................................. 72

6.3.2 Operations phase ................................................................................................................. 73

6.3.3 Decommissioning and closure phase .................................................................................... 78

6.4 Monitoring Measures ...................................................................................................................... 80

7 WATER SUPPLY................................................................................................. 84

7.1 Objectives ....................................................................................................................................... 84

7.2 Context ........................................................................................................................................... 84

7.2.1 Pre-construction and Construction Phase ............................................................................ 84

7.2.2 Operations Phase ................................................................................................................ 84

7.2.3 Decommissioning and Closure Phase .................................................................................. 85

7.3 Management and Mitigation Measures ........................................................................................... 85

7.3.1 Pre-construction and Construction Phase ............................................................................ 85

7.3.2 Operations Phase ................................................................................................................ 86

7.3.3 Decommissioning and Closure Phase .................................................................................. 86

7.4 Monitoring Measures ....................................................................................................................... 87

8 POWER SUPPLY ................................................................................................ 89

8.1 Objectives ....................................................................................................................................... 89

8.2 Context ........................................................................................................................................... 89

8.2.1 Pre-construction and Construction Phase ............................................................................ 89

8.2.2 Operations Phase ................................................................................................................ 89

8.2.3 Decommissioning and Closure Phase .................................................................................. 89

Page 6: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

8.3 Management and Mitigation Measures ........................................................................................... 90

8.3.1 Pre-construction and Construction Phase ............................................................................ 90

8.3.2 Operations Phase ................................................................................................................ 90

8.3.3 Decommissioning and Closure Phase .................................................................................. 92

8.4 Monitoring Measures ...................................................................................................................... 92

9 ROADS AND TRANSPORT ................................................................................. 94

9.1 Objectives ....................................................................................................................................... 94

9.2 Context ........................................................................................................................................... 94

9.2.2 Pre-construction and Construction Phase ............................................................................ 96

9.2.3 Operations Phase ................................................................................................................ 96

9.2.4 Decommissioning and Closure Phase .................................................................................. 96

9.3 Management and Mitigation Measures ........................................................................................... 96

9.3.1 Pre-construction and Construction Phase ............................................................................. 97

9.3.2 Operations Phase ............................................................................................................... 102

9.3.3 Decommissioning and Closure Phase ................................................................................. 104

9.4 Monitoring Measures ..................................................................................................................... 104

10 ACCOMMODATION FACILITIES ......................................................................... 109

10.1 Objectives ...................................................................................................................................... 109

10.2 Context .......................................................................................................................................... 109

10.2.1 Pre-construction and Construction Phase ........................................................................... 110

10.2.2 Operations Phase ............................................................................................................... 110

10.2.3 Decommissioning and Closure Phase ................................................................................. 110

10.3 Management and Mitigation Measures .......................................................................................... 111

10.3.1 Pre-construction and Construction Phase ........................................................................... 111

10.3.2 Operations Phase ............................................................................................................... 111

10.3.3 Decommissioning and Closure phase.................................................................................. 113

10.4 Monitoring Measures ..................................................................................................................... 113

11 BORROW AREAS AND QUARRIES ..................................................................... 116

11.1 Objectives ...................................................................................................................................... 116

11.2 Context .......................................................................................................................................... 116

11.2.1 Pre-construction and Construction Phase ........................................................................... 116

11.2.2 Operations Phase ............................................................................................................... 117

11.2.3 Decommissioning and Closure Phase ................................................................................. 117

Page 7: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

11.3 Management and Mitigation Measures .......................................................................................... 117

11.3.1 Pre-construction and Construction Phase ........................................................................... 117

11.3.2 Operations Phase ............................................................................................................... 118

11.3.3 Decommissioning and Closure Phase ................................................................................. 118

11.4 Monitoring Measures ..................................................................................................................... 118

12 LAND MANAGEMENT AND LIVELIHOOD RESTORATION ................................... 120

12.1 Context .......................................................................................................................................... 120

12.2 Management and Mitigation Measures .......................................................................................... 120

12.2.1 Land clearance ................................................................................................................... 120

12.2.2 Land acquisition and livelihood restoration ........................................................................ 121

12.2.3 Decommissioning and Closure Phase ................................................................................. 124

12.2.4 Livelihood Improvement Programmes ............................................................................... 125

12.2.5 Vulnerable Groups .............................................................................................................. 125

12.2.6 Gender ............................................................................................................................... 125

12.3 Monitoring Measures ..................................................................................................................... 126

13 COMMUNITY ENGAGEMENT ............................................................................ 128

13.1 Objectives ...................................................................................................................................... 128

13.2 Context .......................................................................................................................................... 128

13.3 Management and Mitigation Measures .......................................................................................... 128

13.3.1 Ongoing Public Disclosure and Consultation ....................................................................... 128

13.3.2 Community Awareness and Education Programme ............................................................ 129

13.3.3 Grievance Management ..................................................................................................... 130

13.4 Monitoring Measures ..................................................................................................................... 131

14 COMMUNITY SAFETY AND HEALTH.................................................................. 132

14.1 Objectives ...................................................................................................................................... 132

14.2 Context .......................................................................................................................................... 132

14.2.1 Disease transmission and HIV/AIDS .................................................................................... 132

14.2.2 Water and Sanitation .......................................................................................................... 132

14.2.3 General Community Health and Safety ............................................................................... 133

14.3 Management and Mitigation Measures .......................................................................................... 133

14.3.1 Pre-construction and Construction Phase ........................................................................... 133

14.3.2 Operations Phase ............................................................................................................... 135

14.3.3 Decommissioning and Closure Phase ................................................................................. 135

Page 8: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

14.4 Monitoring Measures ..................................................................................................................... 135

15 IN-MIGRATION................................................................................................. 137

15.1 Objectives ...................................................................................................................................... 137

15.2 Context .......................................................................................................................................... 137

15.2.1 Pre-construction and Construction Phase ........................................................................... 137

15.2.2 Operations Phase ............................................................................................................... 138

15.2.3 Decommissioning and Closure Phase ................................................................................. 138

15.3 Management and Mitigation Measures .......................................................................................... 138

15.3.1 Pre-construction and Construction Phase ........................................................................... 139

15.3.2 Operations Phase ............................................................................................................... 140

15.3.3 Decommissioning and Closure Phase ................................................................................. 140

15.4 Monitoring Measures ..................................................................................................................... 140

16 BIODIVERSITY MANAGEMENT ......................................................................... 142

16.1 Objectives ...................................................................................................................................... 142

16.2 Context .......................................................................................................................................... 142

16.2.1 Pre-construction and Construction Phase ........................................................................... 142

16.2.2 Operations Phase ............................................................................................................... 143

16.2.3 Decommissioning and Closure Phase ................................................................................. 143

16.3 Management and Mitigation Measures .......................................................................................... 143

16.3.1 Pre-construction and Construction Phase ........................................................................... 144

16.3.2 Operations Phase ............................................................................................................... 146

16.3.3 Decommissioning and Closure Phase ................................................................................. 146

16.4 Monitoring Measures ..................................................................................................................... 146

17 ESTIMATED COSTS .......................................................................................... 151

18 REGISTERS OF ENVIRONMENTAL AND SOCIAL MANAGEMENT AND

MONITORING MEASURES ................................................................................ 159

18.1 Summary of Environmental Management and Monitoring Measures ............................................. 159

18.2 Summary of Physical Management and Monitoring Measures ....................................................... 167

18.3 Summary of Biological Environment Management and Monitoring Measures ................................ 207

18.4 Summary of Social Management and Monitoring Measures ........................................................... 219

19 REFERENCES ................................................................................................... 229

APPENDIX A ........................................................................................................... 231

Standard Operating Procedures (SOPs) .................................................................... 231

SOP01: Erosion and Sediment Control .................................................................................................... 235

Page 9: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

SOP02: Water Quality and Pollution Management .................................................................................. 237

SOP03: Hydrology and Water Management ........................................................................................... 242

SOP04: Emission and Dust Control ........................................................................................................ 244

SOP05: Noise and Vibration Management ............................................................................................. 248

SOP06: Waste Management ................................................................................................................... 252

SOP07: Hazardous Materials Management ............................................................................................. 257

SOP08: Blasting Management ............................................................................................................... 266

SOP09: Land Clearance and Soil Stockpiling .......................................................................................... 269

SOP10: Cultural Heritage Management .................................................................................................. 275

SOP11: Lighting and Visual Amenity Management.................................................................................. 277

APPENDIX B ........................................................................................................... 279

Chance Find Procedure ............................................................................................ 279

APPENDIX C ........................................................................................................... 280

Monitoring Maps ..................................................................................................... 280

Appendices APPENDIX A Standard Operating Procedures

APPENDIX B Chance Find Procedure

APPENDIX C Monitoring Maps

Page 10: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

TERMS AND DEFINITIONS

Term Definition

Acid and Metalliferous

Drainage (AMD)

Refers to the outflow of acidic water from metal mines or coal mines.

Baseline Refers to the biophysical and socio-economic state of the environment at a given time, prior to

development of a particular project.

Batter Receding slope – backward and upward slope on a face of a bank

Berm Dirt and rock piled alongside a haulage road or along the edge of a dump point. A safety measure

Biodiversity Diversity within and among flora and fauna in an environment.

Bio-indicators Bio-indicators are molecular tools used in ecology, physiology, environmental microbiology and other

disciplines, to detect stressors and other environmental conditions surrounding an organisms or cells.

Blast hole Holes into which explosive is added in order to fragment the rock

Blasting Blasting is a primary means of extracting minerals and ores at surface mining operations.

Borrow area A pit created to provide material (borrow) that can be used as fill at another site.

CALPUFF Advanced non-steady-state meteorological and air quality modelling system developed by Exponent

scientists.

Catchment An area in which rainwater is collected; a natural drainage area.

Chemical oxygen

demand

The amount of organic compounds in water.

Compensation The payment – in cash or kind – for an asset (e.g. land, house, trees) or livelihood income (cash or

kind) affected by the Project

Concentrate A metal-rich product resulting from a mineral enrichment process such as gravity concentration or

flotation

Consultation A process of communication with those potentially affected by a project, policy, plan or programme.

Contamination Pollution, including the presence of particles, chemicals and/or other undesirable substances.

Cultural heritage The legacy of physical artefacts and intangible attributes of a group or society that are inherited from

past generations, maintained in the present and bestowed for the benefit of future generations.

Culvert A drain or channel crossing under a road, sidewalk, etc.; sewer; conduit

Cumulative impact The effects of an action are added to or interact with other effects in a particular place and within a

particular time. It is a combination of these effects and the resulting environmental degradation that

should be the focus of the cumulative effects analysis.

Decibel (dB) describes the sound pressure level of a noise source. It is a logarithmic scale referenced to the

threshold of hearing

Decommissioning The shut down or closure of the mine

Dissolved Oxygen Refers to a relative measure of the amount of oxygen that is dissolved or carried in a given medium.

Electrical Conductivity Refers to a measure of a material's ability to conduct (transport) an electric current.

Endangered species An animal or plant in danger of extinction.

Environment The combination of elements whose complex interrelationships make up the settings, surroundings

and conditions of life of the individual and society as they are or are felt.

Page 11: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

Term Definition

Ephemeral Temporary/short lived.

Erosion Weathering of surface soil through the action of water and wind, or displaced in response to gravity.

Fauna The animals of a particular region, habitat, or geologic period.

Flora The plants of a particular region, habitat or geologic period.

Flyrock Fragments of rock projected outside the declared danger zone by a quarry blast.

Grievance Mechanism A way for socially responsible businesses to meet requirements of corporate responsibility-related

agreements or pacts, reduce risk while capacity-building or developing internationally, and assist larger

processes that create positive social change.

Groundwater Water that exists in the pore spaces and fractures in rock and sediment beneath the Earth’s surface.

Habitat The natural home or environment of an animal, plant, or other organism.

Hydrocarbon An organic compound consisting entirely of hydrogen and carbon.

Hydrology The science dealing with the occurrence, circulation, distribution, and properties of the waters of the

earth and atmosphere.

ICP-MS Inductively coupled plasma mass spectrometry is a type of mass spectrometry which is capable of

detecting metals and several non-metals at concentrations as low as one part in 1015.

Impact The consequence of an action or activity on the human or natural environment. Impacts may be

positive, negative or neutral.

IUCN Red List The IUCN Red List of Threatened Species (also known as the IUCN Red List or Red Data List) is the

world's most comprehensive inventory of the global conservation status of biological species.

LA90 A LA90 level is an A-weighted noise level which is exceeded for 90 percent of the measurement

period. An LA90 level is considered to represent the “background” noise level.

LAeq The equivalent steady-state A-weighted sound level (“equal energy”) which, in a specified time period,

contains the same acoustic energy as the time-varying level during the same period. It is considered to

represent the “average” noise level.

LAmax A LAmax level is the maximum A-weighted noise level during the measurement period.

Leachate The solution resulting from the dissolution of soluble substances from the downward percolation of

water.

Livelihood The full range of means that individuals, families, and communities utilise to make a living, such as

wage-based income, agriculture, fishing, foraging, other natural resource-based livelihoods, petty

trade, and bartering.

Nutrients Nutrients are the components in foods that an organism utilizes to survive and grow.

Open pit, open cut Surface mining in which the ore is extracted from a pit or quarry. The geometry of the pit may vary with

the characteristic of the ore body.

Ore Mineral bearing rock that contains one or more minerals, at least one of which can be mined and

treated profitably under current or immediately foreseeable economic conditions.

pH A measure of concentration of hydrogen ions (grams of atom/L) used to represent the alkalinity or

acidity of a solution. Measured on a logarithmic scale.

Piezometer A piezometer is either a device used to measure static liquid pressure in a system by measuring the

height to which a column of the liquid rises against gravity, or a device which measures the pressure

(more precisely, the piezometric head) of groundwater at a specific point.

PM10 Particulate matter less than 10 microns in diameter.

PM2.5 Particulate matter less than 2.5 microns in diameter.

Process water Means any water which, during manufacturing or processing, comes into direct contact with or results

Page 12: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

Term Definition

from the production or use of any raw material, intermediate product, finished product, byproduct, or

waste product.

Project Development

Area (PDA)

Includes physical footprint of main Project components (Mine Pit, Waste Rock Dump, Tailing

Management Facility etc.) and a buffer area. Excludes Water Storage Dam (WSD) and Project Access

Corridor.

Project Footprint Areas potentially directly affected by the Project including buffer zones.

Proponent The proposer, or applicant, of a project.

Protected area Clearly defined geographical space, recognised, dedicated and managed, through legal or other

effective means, to achieve the long term conservation of nature with associated ecosystem services

and cultural values. (IUCN Definition, 2008).

Quarry A type of shallow open-pit mine from which rock is extracted, usually for building purposes.

Rehabilitation The process by which lands disturbed as a result of mining activity are rehabilitated back to a

beneficial land use. Rehabilitation activity includes the removal of buildings, equipment, machinery

and other physical remnants of mining, closure of tailings impoundments, leach pads and other mine

features, and contouring, covering and revegetation of waste rock piles and other disturbed areas.

Riparian The terrestrial region around a body of water or along a river bank.

Risk The likelihood of occurrence of an adverse project effect.

Runoff Precipitation falling on the ground that is not absorbed and eventually reaches rivers, lakes or other

water bodies.

Run-of-mine Pad Run-of-mine is coal that is not graded according to quality or size

Sediment Solid material that has settled down from a state of suspension in a liquid. More generally, solid

fragmental material transported and deposited by wind, water or ice, chemically participated from

solution, or secreted by organisms, and that forms in layer in loose unconsolidated form.

Spoil Waste material brought up during the course of an excavation.

Stakeholder Someone who has an interest in the outcome of a project, or a decision affecting them.

Total Dissolved Solids Total Dissolved Solids (often abbreviated TDS) is a measure of the combined content of all inorganic

and organic substances contained in a liquid in: molecular, ionized or micro-granular (colloidal sol)

suspended form.

Total Suspended Solids A measure of the organic and inorganic solids dispersed in a water body.

Tributary The name given to a stream that flows into a larger stream of body of water.

Turbidity Turbidity is the cloudiness or haziness of a fluid caused by individual particles (suspended solids) that

are generally invisible to the naked eye, similar to smoke in air. The measurement of turbidity is a key

test of water quality.

UNESCO’s List of

World Heritage in

Danger

UNESCO’s List of World Heritage in Danger is designed to inform the international community of

conditions which threaten the very characteristics for which a property was inscribed on the World

Heritage List, and to encourage corrective action.

Vulnerable groups Groups that experience a higher risk of poverty and social exclusion than the general population

Waste rock Rock containing no target element, or an un-economic quantity of the target element

Waste Water Treatment

Plant

A treatment plant where various physical, biological or chemical processes are used to change the

properties of the wastewater (e.g. by removing harmful substances) in order to turn it into a type of

water (also called effluent) that can be safely discharged into the environment or for reuse.

Water quality The chemical, physical or biological characteristics of water relative to the requirements of biotic

species and/or to any human need or purpose.

Woodland Is a low-density forest forming open habitats with plenty of sunlight and limited shade. Woodlands may

Page 13: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

Term Definition

support an understory of shrubs and herbaceous plants including grasses.

Zoonotic Transmissible disease that can pass between animals and humans.

Page 14: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

LIST OF ABBREVIATIONS

Acronym Full Term

AMD Acid and Metalliferous Drainage

ANC Acid Neutralising Capacity

ANFO Ammonium Nitrate Fuel Oil

ARD Acid Rock Drainage

BAP Biodiversity Action Plan

BOD Biological Oxygen Demand

CEMP Construction Environmental Management Plan

CIL Carbon In Leach

CO Carbon monoxide

COD Chemical Oxygen Demand

DEEC Direction de l’Environnement et des Etablissements Classés

DMG Direction des Mines et de la Géologie

DO Dissolved oxygen

DPN Department of National Parks (Direction des Parcs Nationaux)

DREEC Division Régionale de l’Environnement et des Etablissements Classés

EITI Extractive Industries Transparency Initiative

ESIA Environmental and Social Impact Assessment

GRS Government of the Republic of Senegal

HDPE High-density polyethylene

HIV / AIDS Human Immunodeficiency Virus Infection and Acquired Immune Deficiency Syndrome

IFC International Finance Corporation

IFC PS International Financial Corporation Performance Standard

km kilometres

L litres

LEPP Local Economic Participation Plan

M metres

MEC Mako Exploration Company

Mt/y Million tonnes per year

NGO Non-governmental Organisation

NMD Neutral and Metalliferous Drainage

NO2 Nitrogen dioxide

NOx Nitrogen oxides

OHS&E Occupational Health, Safety and Environment

Page 15: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

Acronym Full Term

ORP Oxidation Reduction Potential

PDA Project Development Area

PM Particulate Matter

PNNK Parc National du Niokolo Koba (Niokolo-Koba National Park)

POI Plan d’Opération Interne (Emergency response plan)

PPI Plan Particulier D’Intervention (Local Authority Emergency Plan)

ppm Parts per million

ROM Run-of-mine

SO2 Sulfur dioxide

SOP01 SOP01: Erosion and Sediment Control Procedure

SOP02 SOP02: Water Quality and Pollution Management Procedure

SOP03 SOP03: Hydrology and Water Management Procedure

SOP04 SOP04: Emission and Dust Control Procedure

SOP05 SOP05: Noise and Vibration Management Procedure

SOP06 SOP06: Waste Management Procedure

SOP07 SOP07: Hazardous Materials Management Procedure

SOP08 SOP08: Blasting Management Procedure

SOP09 SOP09: Land Clearance and Soil Stockpiling Procedure

SOP10 SOP10: Cultural Heritage Management Procedure

SOP11 SOP11: Lighting and Visual Amenity Management Procedure

TDS Total Dissolved Solids

TMF Tailings Management Facility

TSS Total Suspended Solids

VOCs Volatile Organic Compounds

WAD Weak Acid Dissociable

WHO World Health Organisation

WRD Waste Rock Dump

WSD Water Storage Dam

Page 16: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 1

1 INTRODUCTION

1.1 General Background

This Environmental and Social Management and Monitoring Plan (ESMMP) for the Mako Gold Project (hereafter 'the

Project’) has been prepared by Earth Systems for Mako Exploration Company SA (MEC), a wholly owned subsidiary

of Toro Gold Limited (Toro Gold). It forms part of the Environmental and Social Impact Assessment (ESIA)

documents for the Project.

The ESMMP details the environmental and social commitments, management and monitoring requirements that

must be carried out by MEC (hereafter ‘the Company’) and its contractors throughout the life of the Project, in order

to achieve the following objectives:

1. The Company will strive to prevent or mitigate potentially adverse environmental or social impact that may

result from Project implementation;

2. The Company will maximise beneficial impacts and minimise unavoidable residual impacts to an acceptable

level for the receiving environment and communities;

3. The Company will meet environmental and social commitments and measures outlined in the ESIA Report

(Volume A) as well as relevant corporate policies and environmental management systems; and

4. The Company will comply with national legislation as well as relevant international environmental and social

standards and regulations.

The ESMMP incorporates the key findings and environmental and social management, mitigation, and monitoring

measures and strategies of the ESIA report (Volume A) based on currently available Project information for pre-

construction, construction, operations, decommissioning, and closure.

The ESMMP will be a dynamic document, reviewed and updated by the Company on a yearly basis during the pre-

construction and construction phase and every 3 years during Project operations to reflect changes to Project

activities, commitments, environmental and social conditions, regulatory requirements, and potential optimisation

of best management practices.

In line with the Government of the Republic of Senegal (GRS) requirements, this ESMMP is prepared in accordance

with Arrêté n° 9472 du 28 Novembre 2001 portant Contenu du Rapport d'étude d'impact and the approved Terms of the

Reference for the ESIA for the Project, and requires approval by the Direction of Environment and Classified

Establishments (Direction de l’Environnement et des Etablissements Classés) (DEEC) prior to Project construction.

1.2 Structure

The scope of this ESMMP includes:

Summary of legislative requirements as well as the Company’s policies and commitments with respect to

environmental and social management of the Project;

Overview of the ESMMP framework, including details on:

» The regulatory and institutional frameworks as well as the company organisational responsibilities for

effective implementation of environmental and social management and monitoring measures;

» Capacity building requirements for Project employees, government and external organisations involved in

the implementation of the ESMMP;

» Monitoring, reporting and auditing systems to assess the effectiveness of implementation;

» Approach to emergency response and continuous improvement; and

Page 17: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 2

» Budget for implementing the environmental and social management measures and monitoring

programme inclusive of capacity building requirements.

Environmental and social management and monitoring sub-plans for Project components, which provide:

» A summary of the environmental and social context of the Project and its potential impacts;

» A summary of proposed measures to avoid or mitigate adverse impacts as well as optimising positive

effects of the Project;

» Monitoring locations, monitoring protocols, and trigger values (Project guidelines) requiring corrective

actions; and

» Registers summarising the proposed environmental and social management and monitoring measures for

the Project.

Supporting Standard Operating Procedures (SOPs) providing general environmental and social management

measures to manage potential Project impacts.

1.2.1 Overview of Management Plans and Procedures

Legal obligations, commitments, and environmental and social risks and potential impacts from the Mako Gold

Project will be primarily managed through specific plans and procedures developed under a Project environmental

and social management framework for particular aspects and activities during all Project phases.

These management plans and procedures will be updated as further information becomes available or when site or

Project conditions change significantly. Furthermore, they will be regularly reviewed and updated during all relevant

phases of the Project based on the results of monitoring, feedback and audits.

Chapters 4 to 11 of this ESMMP detail specific impact management and monitoring measures for implementation as

part of the environmental and social management framework for the following Project components:

Project Development Area (PDA) (Chapter 4);

Open Pit, Mining and Waste Rock (Chapter 5);

Mineral Processing and Tailings Management (Chapter 6);

Water Supply (Chapter 7);

Power Supply (Chapter 8);

Roads and Transport (Chapter 9);

Accommodation Facilities (Chapter 10); and

Borrow Areas and Quarries (Chapter 11).

Chapters 12 to 15 provide social impact management and monitoring measures for the Project:

Land Management and Livelihood Restoration (Chapter 12);

Community Engagement (Chapter 13);

Community Health and Safety (Chapter 14); and

In-Migration (Chapter 15).

Chapter 16 (Biodiversity Management) outlines the management and monitoring of biodiversity aspects in relation

to the Biodiversity Action Plan (Volume C) and Offset Strategy developed for the Project.

This ESMMP will be used in coordination with the following thematic management plans, provided with the ESIA:

Biodiversity Action Plan (Volume C);

Local Economic Participation Plan (Volume D);

Livelihood Restoration Plan (Volume D);

Page 18: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 3

Stakeholder Engagement Plan (Volume C); and

Rehabilitation and Conceptual Mine Closure Plan (Volume E).

Standard Operating Procedures

A number of Standard Operating Procedures (SOPs) have been provided in Appendix A to facilitate the

implementation of general environmental and social management measures by the Company and its contractors for

the Mako Gold Project. These include:

SOP01: Erosion and Sediment Control;

SOP02: Water Quality and Pollution Management;

SOP03: Hydrology and Water Management;

SOP04: Emission and Dust Control;

SOP05: Noise and Vibration Management;

SOP06: Waste Management;

SOP07: Hazardous Materials Management;

SOP08: Blasting Management;

SOP09: Land Clearance and Soil Stockpiling;

SOP10: Cultural Heritage Management; and

SOP11: Lighting and Visual Amenity Management.

Construction Environmental Management Plan

A Construction Environmental Management Plan (CEMP) will be developed and implemented after final

engineering plans are completed. Where required, these specific management plans have been identified in the

ESMMP (e.g. Blast Management Plan, etc.) and will be prepared by the Company or its Contractors to include the

following details as a minimum:

Overall objectives and targets;

Assigned responsibilities and resources for implementation;

Key risks and sensitivities;

Specific competencies and training required, where relevant;

Proposed avoidance, management and mitigation measures; and

Monitoring, reporting and audit/review for improvement.

Page 19: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 4

1.3 Presentation of the Project

1.3.1 Project Proponent

Toro Gold entered into a Joint Venture with Kansala Resources in September 2009 and acquired 100% of the

Exploration Permit for the Mako Gold Project in 2011. MEC (a fully owned subsidiary of Toro Gold) is the proponent

of the Project, which comprises the development of an open pit gold mine and ore processing facility within the

Exploration Permit in eastern Senegal. Toro Gold currently has a number of exploration projects in Senegal and

Gabon, including its flagship Mako Gold Project.

MEC intends to apply for a Mining Convention from the Senegalese Government for the Mako Gold Project, which

requires a Feasibility Study and ESIA to be carried out and approved by the Ministry of Environment.

1.3.2 Project Overview

The Mako Gold Project will consist of the development of the Petowal gold deposit, located in the Kedougou region

of Senegal, approximately 650 km south-east of Dakar. The Petowal deposit is located in the western section of the

proposed Mako Mining Concession (refer to Figure 1-1). The preferred development scenario involves standard gold

extraction and processing methods, which include the mining of ore via an open pit, processing of ore through

gravity separation and carbon in leach (CIL), and construction of supporting infrastructure including a waste rock

dump (WRD), tailings management facility (TMF), water storage dam (WSD), power station and accommodation

camp.

The Project will be comprised of the following key components and is depicted in Figure 1-1:

Open pit mine (also referred to as the Mine Pit);

Run-of-mine (ROM) Pad, ROM Pad stockpile and primary crusher;

Process Plant;

Tailings Management Facility (TMF) and sediment pond;

Waste Rock Dump (WRD);

Ore Stockpile;

Water Storage Dam (WSD);

Pump station and raw water pipeline;

Power Station and reticulation;

Haul route and Project access infrastructure (including Main Access Road and WSD Access Road);

Mine Services Area (including office / workshops / warehouse); and

Accommodation camp(s).

The Life of Mine is anticipated to be approximately nine years, with a total estimated production of approximately

996 kilo ounces of gold (Toro Gold, 2015). High grade ore will be mined and processed over a six year period at a rate

of 1.8 Million tonnes per year (Mt/y), followed by a further two to three year period (when mining is complete) in

which low grade ore will be processed. Construction is currently scheduled to commence in Quarter 4 of 2015 and

production is expected to start in April 2017. Plant operations will cease in the third quarter of year 8 (Toro Gold,

2015 Pers. Comm.). Once mining has been completed in the area, the site will be fully rehabilitated.

The Project description is based on information provided in the Pre-Feasibility Study (PFS) completed in July 2014,

and updated as per the latest Design Feasibility Study (DFS) findings.

The Project workforce is expected to comprise:

Up to 221 staff during the peak pre-construction period;

Between 300 and 900 staff (in peak periods) during the construction period of 14 months;

Page 20: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 5

Up to 500 staff for a commissioning period of two months;

Up to 361 personnel at full production during operations (130 of which will require on-site accommodation);

Up to 150 workers during decommissioning and mine closure.

The majority of the Project workforce will be sourced locally and from within Senegal to be in accordance with the

Senegalese Mining Convention requirements. Construction activity will be undertaken primarily six days a week,

during daylight hours, although some night-time work may be required to achieve ore production by early 2017.

A more detailed Project description is provided in the ESIA (Volume A, Chapter 4).

Description of Pre-construction works

The programmed early works phase aims to enable site access, preliminary works for the Accommodation Camp(s)

and preparation of the WSD facility before December 2015, at which time full construction and manning the site will

commence.

Early works (from October to December 2015) will include the following principal activities:

Detailed design for Main Access Road, WSD and Accommodation Camp;

Award of earthwork contract(s), or hiring of equipment if self-managed by the Company;

Commencement of Main Access Road construction from the RN7 through the Wayako Valley;

Preparation, clearing and grubbing of the minor valley floor which forms the WSD facility;

Ordering of the demountable buildings which form part of the new accommodation camp;

Ordering owner mobile equipment; generators, pumps etc; and

Commencement of quarry activities (no blasting required) to generate aggregate for road building and civil

works.

In addition to the primary production fleet, a small pioneering fleet, comprising a single 50t back-hoe excavator and

two 40t capacity articulated dump trucks, may be deployed in order to establish the mining operation during pre-

production, including haul roads and initial bench development.

Description of construction works

Project construction activities will be carefully scheduled to a compressed timeline targeting a first gold pour in

Quarter 1 of 2017. Project construction will primarily involve the following activities:

Site clearance and preparation of areas to be developed, including vegetation clearing, grubbing, soil

stripping and stockpiling, and grading;

Bulk earthworks, including cut and fill or cut to spoil levelling of access roads, drainage channels, Process

Plant site, ROM Pad, TMF, new Accommodation Camp and Mine Pit area. Some blasting may be required for

sections of access road and occasional footings (such as for the Process Plant mill);

Erection of buildings and mine ancillary infrastructure and services;

Sourcing and transportation of construction material and workforce to and from worksites;

Project road infrastructure construction and upgrades;

Installation of drainage and erosion management facilities (ponds, culverts, channels etc.);

Security fencing of Project components, where required; and

Compaction of site areas.

Once site access has been established in the Pre-construction phase, activities will progress in the following

simplified sequence:

Construction of sediment retention pond downstream of the TMF (prior to the onset of the wet season);

Page 21: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 6

Clearing and grubbing of areas to be developed;

Bulk earthworks, including cut and fill or cut to spoil levelling of access roads, drainage channels, Process

Plant site, ROM Pad, TMF, Accommodation Camp and Mine Pit area. Some blasting may be required for

sections of access road and occasional footings (such as the mill);

Mobilise civil contractor(s) to commence critical path concrete pours in February (civil works completed by

September 2016);

Complete installation of the WSD and river abstraction system and commission before June 2016;

Mechanical contractor to mobilise by end of July 2016, to commence tank erection at Process Plant;

Mine contractor or owner fleet to commence pre-strip by August 2016;

Power Station installation to commence by December 2016. This will be an optimal owner-operated or

independently operated diesel Power Station; and

Process Plant commissioning expected to commence in February 2017, and last for two months..

Vegetation clearance will be conducted during the dry season and confined to the minimum area required for safe

operations to reduce the potential for dust, erosion and sediment transport. Any commercially valuable timber will

be salvaged from the Project Footprint where possible.

Construction material will include sand, fill, and gravel, which will be sourced from within the Project Footprint

(where suitability permits), with additional gravel, sand and fill sourced externally to meet demand as needed

(primarily from the existing quarry near the RN7).

Description of mining operations

Mining method and waste rock

The Petowal deposit will be developed as an open pit mine by conventional methods of drilling, blasting, loading and

hauling with standard industry equipment. Top hammers, down-the hole hammers or rotary drills will be used for

drilling and blasting (depending on the rock characteristics and the optimum blast hole size selected), with reverse

circulation drilling for grade control, and diesel-powered hydraulic excavators (120 t) and 90 t haul trucks as the

primary loading and hauling equipment. The pit will be mined at a rate of 24 million tonnes (Mt) of ore per annum,

producing 74 Mt of waste rock over the Project lifetime.

Mining overburden and waste rock will be disposed of via haul trucks out of the Mine Pit, either to the specifically

designed WRD facility adjacent to the Pit (refer to Figure 1-1), or to facilities requiring waste rock as construction

material (if suitable). The WRD will be constructed and managed to ensure the long-term geochemical and

geotechnical stability of the landform during operation and post-closure. It will be positioned upstream of the TMF

to capture seepage and potentially sediment laden surface water run-off from the catchment for re-use on-site

during operations.

Ore Processing and Tailings Management

The Project will use standard gold mining and processing techniques: open pit mining, followed by crushing and

milling of the ore, then leaching of the gold via a standard gravity / Carbon in Leach (CIL) processing plant

(comprising batch gravity with intensive cyanidation of concentrate and CIL on the batch gravity tails), and finally

elution and electrowinning. The amount of ore produced over the life of mine is expected at approximately 13.9 Mt

with a feed grade of 2.16 g/t of gold.

Ore processing facilities at the proposed mine site will include:

ROM Pad (with an approximate 200,000 m3 capacity);

Process Plant with built-in crushing circuit, conveyors, grinding and classification circuit, pre-leach thickening

circuit, leach and carbon adsorption circuit, cyanide destruction circuit, elution and goldroom;

Water and air services; and

Page 22: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 7

Reagent and hazardous materials storage facility and storage tanks.

Mined ore will be processed into gold concentrate for export using cyanide solution and additional reagents at the

Process Plant at an annual ore throughput of 1.8 Mt/y. The Process Plant is planned to operate on a 24 hours a day,

seven days a week, and 52-week a year basis.

The unit process operations will involve crushing and grinding, cyanide leaching and adsorption, cyanide

detoxification, carbon regeneration and tailings disposal, elution and electrowinning, and smelting. Further details

of the process are provided in Chapter 4 of the ESIA (Volume A).

The Process Plant will involve the following unit process operations:

Primary jaw crushing and partial secondary cone crushing of ROM ore to produce a crushed product size of

80% passing (P80) 143 mm;

A crushed ore surge bin and overflow dead stockpile with reclaim of crushed ore from the surge bin;

Single stage SAG milling in closed circuit with a pebble crusher and hydrocyclones to produce an 80% passing

125 micron grind size;

Pre-leach thickening to increase the slurry density feeding the CIL circuit to minimise CIL tankage, improve

slurry mixing characteristics and reduce overall reagent consumption;

A CIL circuit which will leach and adsorb gold and silver values from the milled ore onto activated carbon in six

stages of leaching with carbon in all stages for gold adsorption providing a total of 24 hours leach time;

A Zadra elution circuit treating loaded carbon, followed by electrowinning and smelting to produce doré;

An INCO-based1 SO2 / air cyanide destruction circuit to reduce the tailings cyanide concentration to be

consistent with the International Cyanide Management Code (ICMC) requirement of <50mg/l WAD cyanide on

discharge; and

Tailings transfer to the TMF.

Cyanide destruction at the Process Plant will consist of a whole ore cyanide destruction circuit using the air / SO2

process to reduce cyanide concentrations prior to discharge of tailings to the TMF.

Tailings from the Process Plant will be discharged into the TMF, which has been designed to permanently store 13.9

Mt of tailings at a production rate of 1.8 Mt/y. The establishment of the TMF will be staged, and designed to

ANCOLD and ICOLD standards.

Process water from the grinding and gravity circuits will be reused. Wash water from the CIL circuit will be returned

to the leach feed distribution box for reuse. Tailings from the cyanide destruction circuit will be pumped to the TMF

for storage and treatment while supernatant water from the TMF will be recovered and returned as process water

decant for reuse.

Reagents required for the above process includes quicklime, grinding media, flocculent, caustic soda (sodium

hydroxide), activated carbon, sodium cyanide, copper sulphate, sodium metabisulphite, leach aid, diesel and

hydrochloric acid.

Water storage dam

The Water Storage Dam (WSD) will provide the raw and clean process for Process Plant water requirements as well

as water for dust suppression and drinking. The WSD embankment will be constructed across the Kobokou Creek, a

Gambia River tributary in Wayako Valley. The facility will store surface water from the 56 ha upstream catchment

area and water abstracted from the Gambia River during the rainy season, at a rate ranging from 1.6 m3/s (seven

months pumping) to 2.95 m3/s (four months pumping) to meet Project requirements (Toro Gold, 2015c). The WSD

will have a maximum storage capacity of 1.04 million m3 and an embankment height of 21 m. Duty / stand-by water

pumps will be provided for raw water distribution from these tanks to the plant. Water will be recovered from the

WSD by a floating decant barge (Knight Piesold, 2015a).

1 This refers to the sulfur dioxide (SO2) and air process developed by INCO Limited in the1980’s.

Page 23: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 8

Mine services and ancillary facilities

The Mine Services Area will be constructed in the south-western portion of the PDA, comprised of the following

components (refer to Figure 1-1):

Mine management / services/ administrative office;

Mine warehouse;

Vehicle maintenance workshop for heavy and light vehicles;

Mine vehicle wash-down bay, with water management and oil/water separation;

Heavy / light vehicle diesel day storage tank (approximately 30 m3) and refuelling bay;

Boiler-maker workshop;

Mine staff mess;

Shift change building with showers and ablutions; and

Waste Management Area (Landfill Pit, Hazardous Waste Pit and Incinerator).

Administration and other buildings will be single storey, with final dimensions based on the number of staff

occupying them.

Power supply

The Power Station will supply all the electricity onsite for the Project, particularly the Process Plant, Mine Services

Area, accommodation camps, and water supply. The diesel fuelled Power Station will be operated continuously to

supply a base load of 9.8 MW for steady state operations. The maximum power demand from plant and

infrastructure will be 9, 729 kW and energy consumption per year for plant and infrastructure will be 75.7 GWhr/yr.

Main access road and road infrastructure

The Main Access Road to the PDA will be from the RN7 highway, passing through the Wayako Valley, as shown in

Figure 1-1. The first section of the road running from the RN7 to the Mako-Tambanoumouya road will be 7.1 km in

length and 9 m wide. The second section will run parallel to the Mako-Tambanoumouya road for a 1.3 km stretch

and will then head north-west for a further 4 km towards the PDA, in part following an existing exploration track.

Parts of the road (in steep sections) may be sealed (Toro Gold, 2015c).

There will also be a short access road of approximately 750 m leading from the Mako-Tambanoumouya road to the

WSD (see Figure 1-1).

The road between Mako and Tambanoumouya will be upgraded for use during the Pre-construction phase. There will

be limited ongoing use of this road by light vehicles during operations, where necessary.

Additional mine access roads both within the Mine Pit area to access higher areas as well as external permanent haul

roads will be established. These roads are predominantly cut into the slopes due to the steepness of the terrain

within the pit design areas, and the external permanent roads are a combination of cut and fill to provide a

reasonably consistent haul road profile limited to maximum gradients of +/- 10% percent.

Description of decommissioning, rehabilitation and closure works

The majority of mine related infrastructure, utilities and services will be decommissioned and either removed or

rehabilitated, while a number of assets may be transferred for government or community use (e.g. access roads) or

left in situ (e.g. buried pipelines), where practicable.

Rehabilitation of mining areas (i.e. Mine Pit, WRD) will be carried out progressively over the mine life, where

practicable, and upon closure. The Company’s overall closure objective will be to prevent or minimise adverse long-

term environmental, physical, social and economic impacts for the greater Project Area and to create stable

landforms that provide self-sustaining ecosystems.

Page 24: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 9

Detailed information on decommissioning and rehabilitation of various Project components is provided in the

Rehabilitation and Conceptual Mine Closure Plan (RCMCP, Volume E).

Accommodation facilities

During the pre-construction and construction phase, the existing camp used during the Exploration phase of the

Project will be used to accommodate staff who require on-site accommodation (i.e. expatriate and senior national

staff from outside the Kedougou Region). The camp is located between Linguekoto and Mako towards the Gambia

River (refer to Figure 1-1Figure 1-1) and can accommodate up to 70 staff (Toro Gold, 2015a).

Construction of the new Accommodation Camp will commence upon completion of the earthworks and following

delivery of the first phase of the buildings (Coffey, 2015). The preferred location for the new Accommodation Camp is

onsite on the northern side of the Mako-Tambanoumouya road, north-east of the WSD and approximately 7 km east

of the Process Plant, in the Wayako Valley (refer to Figure 1-1). It will be a purpose-built accommodation facility of

up to 130 beds primarily for expats, senior nationals, and essential skilled staff. Once the Accommodation Camp is

constructed, up to 200 beds will be available for use between the Exploration Camp and Accommodation Camp.

During the peak construction period however, it is anticipated that an additional 50 to 80 additional beds will be

temporarily supplied through demountable accommodation located adjacent to the new Accommodation Camp,

due to insufficient beds available at both camps for the workforce.

During the operations phase, it is expected that only the new Accommodation Camp onsite will be used for

accommodating Project staff, while the Exploration Camp may be used for accommodating Project visitors.

The majority of staff will either be hired from the local area (and therefore already have local accommodation), or be

expected to relocate to a community in the local area, and to Kedougou in particular. This approach is

recommended under the 2009 IFC / EBRD Public Guidance Note ‘Worker Accommodation: Processes and Standards’,

and is intended to create a wide range of economic opportunities (such as rental income) as well as aid in the

development of local businesses (e.g. restaurants, shops, etc.).

Table 1-1 shows the number of staff that will be housed on- and offsite during the construction and operations

phases.

Table 1-1 Total Staff and Accommodation Requirements

Project Phase / Location Total Staff / Total Beds

Construction Phase 900

On-site (New Accommodation Camp and existing

Exploration Camp) 200

On-site (temporary demountable accommodation) 50-80

Off-site (non-locals who lodge in Kedougou

region) 350

Off-site (locals) 300

Operations Phase 361

On-site (main Accommodation Camp) 130

Off-site 231

Source: Toro Gold, 2015.

The accommodation camp facilities will include power distribution, catering, maintenance, potable water supply,

telecommunications, ablutions, camp administration, medical and recreational facilities, and effluent and waste

management systems. The power for accommodation facilities will be supplied by diesel generators. Water will be

sourced from the Gambia River and treated for use in the accommodation camps. Separate accommodation units,

bathroom and ablution facilities will be provided for men and women.

Page 25: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 10

1.4 Report Author

The Company has engaged Earth Systems to prepare the ESIA documents, including this ESMMP. Earth Systems is

an international multidisciplinary environmental and social consulting firm registered in Australia with a head office

in Melbourne (Australia); additional Australian offices in Perth, Darwin and Brisbane; and international offices in

Dakar (Senegal), Bristol (United Kingdom), Vientiane (Lao PDR), Shanghai (China), and Auckland (New Zealand).

The contact details for Earth Systems, Toro Gold and MEC are provided as follows.

Earth Systems Pty Ltd (Head Office) Earth Systems SARL (Senegal Office)

Address:

AUSTRALIA

14 Church St,

Hawthorn, Melbourne,

Victoria 3122

Australia

Email: [email protected]

Web: www.earthsystems.com.au

Address:

SENEGAL

3ème

étage

Immeuble Serigne Saliou Mbacké

Route de l'Aeroport

Ngor, Dakar, Senegal

Email: [email protected]

Web: www.earthsystemsafrica.com

Toro Gold Ltd / MEC (Head Office) MEC (Senegal Office)

Address:

UNITED KINGDOM

Toro Technical Services

Egyptian House

170-173 Piccadilly

London W1J 9EJ

United Kingdom

Email: [email protected]

Tel: +221 33 868 30 57

Web: http://www.torogold.com

Address:

SENEGAL

Mako Exploration Company SA

8 Route du Méridien Président

Almadies

Dakar

Senegal

Page 26: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 11

Figure 1-1 Project Development Area and Mine Layout

Page 27: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 12

2 LEGISLATIVE REQUIREMENTS, GUIDELINES AND COMMITMENTS

2.1 Toro Gold Environmental and Social Commitments

Toro Gold and its wholly owned subsidiary MEC (the ‘Company’) are committed to meeting international standards

of best practice for social development, environmental protection, health and safety, security, and in support of

human rights. Toro Gold has developed an Environmental and Social Performance Framework (ESPF) (refer to

Section 2.1.1) and Environmental and Social Design Criteria to assist the company to operate according to

international standards (refer to Section 2.1.2).

Toro Gold’s business principles and commitments are outlined below with respect to social, environment, and

health, safety and security matters.

Social

Business principles:

Toro Gold will work with and listen to the concerns and interests of local communities and will seek to

ensure that they benefit from its presence on a long term basis.

Toro Gold will support human rights within its reasonable area of influence and undertake appropriate

Human Rights due diligence related to its activities.

Commitments:

Assess the social impacts of our operations in advance of commencement and work to avoid or mitigate

negative impacts and meet standards of international good practice.

Work in partnership with communities, Governments and other stakeholders to understand their priorities

and contribute to social development through economic growth.

Work to build good relationships with communities and to take community impacts into account

respecting their cultures and traditions.

Work to ensure that local communities benefit on an enduring basis through opportunities such as

employment, local supply and contracting, and training. Where appropriate seek to ensure that local

opportunities are prioritised throughout our supply chain.

Include appropriate conditions within sub-contractor and supplier agreements to seek to ensure their

consistency with these commitments.

Selectively invest in social projects that benefit local communities and support the Toro Gold business.

Support human rights through our work activities, including work conditions for employees, special

sensitivity towards dealing with indigenous populations, conducting security operations, and in seeking to

ensure that local communities benefit from our presence. In particular, support the UN Guiding Principles

on Business and Human Rights and the Voluntary Principle on Security and Human Rights.

Page 28: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 13

Environmental

Business principles:

Toro Gold will meet internationally accepted best practice and where necessary exceed local regulatory

standards to achieve that.

Toro Gold will work to minimise the environmental impact of its operations at all times and will work to

enhance the environment around its projects as far as is practicable.

Toro Gold will seek to implement a No Net Loss approach to biodiversity conservation at its operational

sites.

Commitments:

Assess the environmental impacts of our operations in advance of commencement and prevent or

mitigate any harmful effects.

Always comply with local regulation but apply international standards (IFC performance standards)

where these are more rigorous.

Work proactively with others, to contribute to biodiversity conservation through scientific, practical and

educational activity. In projects with biodiversity impacts, develop a biodiversity strategy, which will set

out an appropriate mitigation hierarchy and how we plan to achieve a ‘No Net Loss’ biodiversity

conservation.

Minimise the carbon footprint of our operations through appropriate investment in efficient technology.

Work to continuously improve its performance.

Health, Safety and Security

Business principles:

Toro Gold will provide secure work environments which are healthy and safe.

Toro Gold will treat all employees with fairness and respect and help them to develop their potential

through training.

Commitments:

Conduct all operations consistent with industry best practice with respect to Health, Safety and Security.

Apply rigorous standards, guidelines and management systems to hazardous activities and effectively

implement them with employees and contractors.

Develop a workplace culture which is conducive to a healthy and safe environment and prevents dangers

and abuses and train employees to that effect.

Work with contractors to ensure that the supply chain does not include forced or harmful child labour or

abusive labour practices.

Support the Voluntary Principles on Security and Human rights and include them in private security

contracts.

Page 29: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 14

2.1.1 Environmental and Social Performance Framework

The ESPF consists of a set of Performance Standards drawn primarily from the International Finance Corporation

(IFC) Performance Standards, and reference the ‘Voluntary Principles on Security and Human Rights’, the ‘UN

Guiding Principles on Business and Human Rights’, as well as the ‘Sustainable Development Framework’ of the

International Council on Mining and Minerals (ICMM) (refer to Section 2.3). The ESPF refers to a set of Operational

Guidelines, embodied in the Toro Gold ‘Exploration Code of Conduct’ to be used in field-based operations.

Chapter 3 of the ESIA (Volume A) provides further details on Toro Gold’s performance standards, and their

implication for the Mako Gold Project.

2.1.2 Environmental and Social Design Criteria

Environmental and social design criteria were developed during the feasibility process to provide guidance for the

design and development of the Mako Gold Project.

These design criteria are aimed at protecting the following priority environmental and social values in the Project

Area:

The Niokolo-Koba National Park (PNNK) (classed as a World Heritage site, UNESCO-MAB Biosphere

Reserve and national nature reserve);

Habitat of importance to endangered species, and threatened / unique ecosystems;

The aquatic environment of the Gambia River and its tributaries; and

Community land and water use.

Relevant environmental and social standards and guidelines considered critical for the Project design are discussed

in the ESIA, Chapter 3 (Volume A).

2.2 Legislative Requirement and Guidelines

2.2.1 Mining Convention Agreement

The Project is subject to a Mining Convention signed in March 2007 between GRS and Kansala Resources SA for

the Mako Permit (Convention Minière pour l’or et les substances connexes passée en application de la Loi 2003-36 du

24/11/2003 portant Code Minier entre le Gouvernement de la République du Senegal et Kansala Resource SA). The

Mining Convention covers both the exploration and operations phases of the Project, and defines the legal,

administrative, financial and fiscal conditions of the Project.

The Convention includes relevant provisions to the ESMMP, including:

Access to land and resources for exploration and mining (Article 34);

Protection of the environment and cultural heritage (Article 35), including specific provisions for:

» Taking the necessary measures to protect the environment;

» Informing relevant authorities of discoveries of cultural heritage objects and artefacts, and of leaving

national artefacts in situ for up to one month following notification of authorities (Article 35.7); and

» Conducting regular monitoring, following a pre-determined schedule, of water quality, soil and air in the

work zone and surrounding areas during the exploitation phase of the Project.

A rehabilitation programme to be implemented when the mining title expires, and the creation of a

rehabilitation fund (Articles 35.3 and 35.4).

Page 30: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 15

2.2.2 Relevant Legislation and Guidelines

An ESMMP is a requirement of Senegalese regulations as per Arrêté n° 9472 du 28 Novembre 2001 portant Contenu

du Rapport d'étude d'impact. It is also specified in the Terms of the Reference for the ESIA for the Project approved

by the DEEC.

Key Senegalese legislation relevant to Project permitting includes:

Mining Code (2003);

Environment Code (2001);

Water Code (1981);

Forestry Code (1998); and

National Domain (1964).

A list of relevant national laws, regulations and best practice guidance applicable to the environmental and social

management of the Project are presented in Table 2-1. Key legislation and regulations that apply to the Mako Gold

Project are summarised further below.

Table 2-1 Relevant national laws, regulations and guidelines

English Title French Title Date

Decreed

MINING

Mining Code Loi No. 2003-36 du 24 novembre 2003 portant Code Minier

2003

Decree No. 2004-647 (17 May 2004) – Application of the Mining Code

Le décret No. 2004-647 du 17 mai 2004 portant application du Code Minier

2004

Order No. 009249 of 14 June 2013 on the Organization of Artisanal Mining Activity in Senegal.

Arête N°009249 du 14 juin 2013 portant Organisation de l’activité d’orpaillage au Sénégal

2013

ENVIRONMENT

Environment Code Loi No. 2001-01 du 15 janvier 2001 portant Code de l’Environnement

1983, updated 2001

Decree No. 2001-282 (12 April 2001) – Application of the Environment Code

Le décret No. 2001-282 du 12 avril 2001 portant application du Code de l’Environnement

2001

Ministerial Order No. 9468 MJEHP-DEEC of 28 November 2001 defining public participation in the EIA

Arrêté ministériel n°9468 MJEHP/DEEC du 28 Novembre 2001 portant règlementation de la participation du public à l’étude d’impact environnemental

2001

Ministerial Order No. 9469 MJEHP-DEEC of 28 November 2001 defining the organisation and function of the Technical Committee

Arrêté ministériel n°9469 MJEHP/DEEC du 28 Novembre 2001 portant organisation et fonctionnement du Comité technique

2001

Ministerial Order No. 9470 MJEHP-DEEC of 28 November 2001 defining the conditions for granting approval for the conduct of Environmental Impact Assessments

Arrêté ministériel n°9470 MJEHP/DEEC du 28 Novembre 2001 fixant les conditions de délivrance de l’Agrément pour l’exercice des activités relatives aux études d’impact sur l’Environnement

2001

Ministerial Order No. 9471 of 28 November 2001 on the contents of the Terms of Reference for Environmental Impact Assessments

Arrêté ministériel n°9471 MJEHP/DEEC du 28 Novembre 2001 portant contenu des termes de référence des études d’impact

2001

Ministerial Order No. 9472 of 28 November 2001 on the contents of the Environmental Impact Assessment report

Arrêté ministériel n°9472 MJEHP/DEEC du 28 Novembre 2001 portant contenu du rapport de l'Etude d'impact environnemental

2001

Page 31: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 16

English Title French Title Date

Decreed

Interministerial Order No. 4862 of 14 July 1999 on the development of a POI in certain classified establishments and the development of a PPI in local collectives inside the perimeter of a classified establishment that requires a POI

Arrêté Interministériel n°4862 du 14 juillet 1999 rendant obligatoire l’établissement d’un Plan d’Opération Interne (POI) dans certains établissements classés et d’un Plan Particulier d’Intervention (PPI) dans les collectivités locales présentant à l’intérieur de leur périmètre territorial des installations classées soumises à l’élaboration d’un POI

1999

Forestry Code Loi No. 98-03 du 8 janvier 1998 portant Code Forestier 1998

Hunting and Fauna Protection Code Loi No. 86-04 du 24 janvier 1986 portant Code de la Chasse and de la Protection de la Faune

1986

Decree No. 86-844 (14 July 1986) to fix basis for fauna protection and management, supplemented by decree of application on 25 June 1998

Le décret d’application No. 86-844 du 14 juillet 1986 et les décrets d’application du 25 juin 1998

1986, updated 1998

Agro-forestry-pastoral Orientation Law La loi No. 2004-16 du 4 juin 2004 portant loi d’orientation agro-sylvo-pastorale

2004

Cattle-Run Regulation Le décret No. 80-268 du 10 mars 1980 portant organisation du parcours de bétail

1980

Water Code Loi No. 81-13 de 4 mars 1981 portant Code de l’Eau 1981

Wastewater Discharge Standard La norme sur les rejets des eaux (NS 05-061) 2001

Inter-ministerial decree No. 1555 (15 March 2002) applying wastewater discharge standard NS 05-061

L’arrêté interministériel No. 1555 de 15 mars 2002 portant application de la norme NS 05-061 sur les rejets des eaux usées

2002

Atmospheric Pollution Standard La Norme de rejets NS 05-062 – pollution atmosphérique 2004

Law No. 64-46 (17 June 1964) concerning the national domain

La loi No. 64-46 du 17 juin 1964 relative au domaine national

1964

Law No. 76-66 (2 July 1976) pertaining to the State Code

La loi No. 76-66 du 2 juillet 1976 portant Code du Domaine de l’Etat

1976

Civil Code and the Decree of 26 July 1932 Le Code civil et le décret de 26 juillet 1932 1932

Public Health Code Loi No. 54-418 du 15 avril 1954 portant Code de la Santé publique

1954

Reproductive Health Law Loi No. 2005-18 du 5 août 2005 relative à la santé de la reproduction

2005

Sanitation Code Loi n° 2009-24 du 8 juillet 2009 portant Code de l’Assainissement

2009

Hygiene Code Loi No. 83-71 de 5 juillet 1983 portant Code de l’Hygiène 1983

Labour Code Loi No. 97-17 du 1 décembre 1997 portant Code du Travail

1997

Monument and Site Preservation Law La loi no.71-12 du 25 janvier 1971 fixé le régime des monuments historiques et celui des fouilles et découvertes

1971

Decree No. 73-746 (8 August 1973) on the application of the Monument and Site Preservation Law

Le décret No. 73-746 du 8 août 1973 portant application de la loi no.71-12

1973

Local Communities Code La loi No. 96-06 du 22 mars 1996 portant Code des Collectivités Locales

1996

Page 32: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 17

English Title French Title Date

Decreed

Law No. 96-07 (22 March 1996) transferring jurisdiction to local communities

La loi No. 96-07 du 22 mars 1996 portant transfert de compétences aux régions, aux

communes et aux communautés rurales

1996

Decree No. 96-1134 (27 December 1996) on the application of the law transferring jurisdiction of environmental matters and management to regions, communes and rural communities

Le décret No. 96-1134 du 27 décembre 1996 portant application de la loi portant transfert de competences aux regions, aux communes et aux communautés rurales, en matière d’environnement et de gestion des ressources naturelles

1996

Draft Standard on Management of Solid Waste Projet de Norme relative à la Gestion des Déchets Solides

In preparation since 2005

LAND ADMINISTRATION, COMPENSATION AND RESETTLEMENT

Constitution of Senegal, 7 January 2001 La constitution du Sénégal du 7 janvier 2001 2001

Decree of 26 July 1932 reorganizing the system of land ownership in the AOF

Décret du 26 juillet 1932 réorganisant le régime de la propriété foncière en AOF

1932

Law No. 64-46 (June 17, 1964) concerning the National Domain

La loi n° 64-46 du 17 juin 1964 relative au domaine national

1964

Decree No. 64-573 (July 30, 1964), Application of the Law on National Domain

Le décret No. 64-573 du 30 juillet 1964, fixant les conditions d’application de la loi n° 64-46 du 11 (sic) juin 1964 relative au domaine national

1964

Law No. 76-66 (July 2, 1976) pertaining to the State Code

La Loi n° 76-66 du 2 juillet 1976 portant Code du Domaine de l’Etat

1976

Decree No. 81-557 (21st May 1981) pertaining to the implementation of the State Code

Décret 81-557 du 21 mai 1981 portant application du code du domaine de l’État

1981

Civil Code and the Decree of July 26, 1932 Le Code civil et le décret du 26 juillet 1932 1932

Law No. 76-67 (July 2, 1976), Expropriation Applicable for Public Works

La Loi No. 76-67 du 2 juillet 1976 relative a l’expropriation pour cause d’utilité publique aux autres préfectures foncières d’utilité publique.

1976

Decree No. 77-563 (July 3, 1977) Expropriation Applicable for Public Works

Le décret No. 77-563 du 3 juillet 1977, portant application de la loi No. 76-67 du 2 juillet 1976 relative a l’expropriation pour cause d’utilité publique aux autres préfectures foncières d’utilité publique

1977

Law No. 96-07 (March 22, 1996) relating to the transfer of powers to regions, municipalities, and rural communities

La Loi 96-07 du 22 mars 1996 portant transfert des compétences aux régions, aux communes et aux communautés rurales

1996

Law No 96-06 (March 22, 1996) pertaining to the administration of local collectives

Loi 96-06 du 22 mars 1996 portant code des collectivités locales

1996

Decree 96-1130 (27th December 1996) pertaining to the implementation of the Law on the transfer of powers to regions, municipalities and rural communities in regards to management and utilisation of natural resources

Décret 96 1130 du 27 décembre 1996 portant application de la loi portant transfert de compétences aux régions, aux communes et aux communautés rurales, en matière de gestion des ressources naturelles

1996

Decree No 72-1288 (27 October 1972) pertaining to the conditions for allocation / disallocation of land in the national domain (community land)

Décret n° 72-1288 du 27 octobre 1972 fixant les conditions d’affectation et de désaffectation des terres du domaine national situées en zone de terroirs

1972

Decree No 91-938 (22 August 1991) permitting all occupants to be compensated

Décret 91-838 du 22 août 1991 permet à tous les occupants d’être indemnisés

1991

Page 33: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 18

English Title French Title Date

Decreed

Decree No. 2010-439 (6 April 2010) repealing and replacing No. 88-074 (January 18, 1988), Price Scale for Land Applicable upon the Expropriation for Public Works

Décret n° 2010-439 du 6 avril 2010 abrogeant et remplaçant le décret n° 88-74 du 18 janvier 1988 fixant le barème du prix des terrains nus et des terrains bâtis, applicable en matière de loyer.

2010

Circular No. 2237/DGPA (October 7, 1974), Price Scale for Calculation of Compensation in Case of Destruction of Plantations and Cultivation or Delocalisation from the National Domain

La circulaire No. 2237/DGPA le 7 octobre 1974, barème de prix pour l’estimation des préfectures à payer en cas de destruction de plantations et de culture ou de déguerpissement du domaine national.

1974

Decree No. 81-683 of July 7, 1981 pertaining to the calculation for payment of premises for residential use

Décret n° 81-683 du 7 juillet 1981 portant fixation des éléments de calcul du loyer des locaux à usage d’habitation

1981

Mining Regulatory Framework

The Mining Code (2003) is the primary legislation regulating the mining industry in Senegal, covering both

exploration and mining activities. Sections of the code relevant to the environmental and social management of

mining projects include:

Title IX, Chapter 5 ‘Environmental Protection’ – Specifies the requirement for an environmental impact

study; for setting funds aside for rehabilitation and closure; and compliance with the Forestry Code (Art.

L44);

Title VIII, Article 55, ‘Equalisation and Support’ – Ensures that a portion of income from the mining

operation is set aside as a fund for the local communities (Community Equalization Fund);

Article 76 of the Mining Code requires the holder of the mining title to compensate owners or occupants

of land occupied by the mining title holder;

Article 81 covers compensation of third parties and the state;

Article 82 addresses the need for rehabilitation of mine sites;

The requirement for an EIA is in Article 83, which requires an EIA to be prepared when a permit of

exploitation or mining concession is requested. This is further elaborated in Article 26 of Decree No.

2004-647. Decree No. 2004-647 in article 93 stipulates compensation requirements for impacts; and

Article 84 requires a Mine Site Rehabilitation Fund to be established with terms and conditions fixed by

decree.

The objective of the Environment Code (2001) is to establish a set of principles to manage and protect the

environment against all forms of degradation. The Code defines procedures for environmental impact

assessment. The Code also defines key environmental terms and sets out the Government’s environmental

policies for five key areas: classified installations (any source, mobile or fixed, capable of posing a threat to the

environment; divided into two classes based on potential impact); water pollution; noise pollution; air pollution

and unpleasant odours; and soil and sub-surface pollution.

Senegal‘s Mineral Policy Statement (2003) provides for the abandonment of state monopoly over any mineral

resources and refocusing on regulating private mining companies. The policy statement limits to 20% the state‘s

participation in ventures and encourages participation of private investors, both domestic and foreign. The state

will also support the diversification of mineral production and the beneficiation (initial processing) of mineral

products before export in order to generate employment opportunities in the industry. The need for an ESIA prior

to mining operations is reiterated in the Statement.

Pursuant to the Mining Code 2003, the Decree N° 2009-1335 Mine Rehabilitation and Closure Fund / Décret N°

2009-1335 portant création et fixant les modalités d’alimentation et de fonctionnement du Fonds De Réhabilitation

Page 34: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 19

Des Sites Miniers was established to provide the mechanisms and operating framework for a Mine Rehabilitation

Fund.

The main points relevant to the Mako Gold Project are:

All holders of an exploitation permit are required to carry out rehabilitation of mine sites when their

mining exploitation permit expires, unless it has been approved to be renewed;

The Permit Owner is required to establish a Mine Rehabilitation and Closure Fund, which will be used to

finance the rehabilitation requirements for the following year. Financial contributions will be provided

annually from exploitation profits of the permit owner from the date of first production for an amount

equal to the average annual cost for rehabilitation;

The amount should be at least equal to the cost for rehabilitation as approved in the latest version of the

ESMMP (taking into account any updates);

The exploitation permit owner should also provide a contingency budget equal to 5 times the average

annual cost for rehabilitation from the date of first production;

Fund is to be jointly managed by the permit owner and the Ministry for Mines and the Environment

through a formal agreement; and

Fund will be valid for the duration of the exploitation permit, taking into account the time required to

carry out post-mine closure and rehabilitation activities.

Water Framework

The Water Code (Code de l’Eau, Law No. 81-13 of 4 March 1981) establishes the main legal framework for the

management and use of water resources in Senegal. Article 9 (Title I) states that authorisation must be sought

from the Hydraulic and Sanitation Ministry before installing infrastructure to exploit groundwater or surface water

resources. Title II regulates the protection of water quality, including all discharges or deposits that may have an

impact on surface and sub-surface water bodies. Article 75 establishes that human consumption is the priority in

the allocation of water resources.

The Company will require permission from OMVG for development within the Gambia River basin and to abstract

water and discharge to the Gambia River, in accordance with the Convention relating to the Status of the River

Gambia / Convention relating to the Creation of the Gambia River Basin Development Organisation (Organisation

de Mise en Valeur du fleuve Gambie or OMVG).

Land and Forest Resources Framework

National legislation relevant to forestry, wildlife and Protected Areas include:

Law No. 93-06 of February 04, 1993 and its enforcement Decree No. 95-357 of 11 April 1995 put the

protection of forests under the authority of the Direction des Eaux et Forêts, Chasse et de la Conservation

des Sols (DEFCCS).

The Forestry Code (Law No. 98/03 of 8th January 1998 and Decree No. 98/164 of 20th February 1998).

The Hunting and Wildlife Protection Code (established by Law No. 86-04 of January 24, 1986 and Decree

No. 86-844 of July 14, 1986) regulates hunting and defines the types of offenses related to the

destruction of wildlife.

Decree No. 96-1134 of 27 December 1996 provides for the implementation of Law No. 96-07 of March 22,

1996 concerning natural resources. This gives the responsibility for wildlife protection to local authorities.

Senegal’s legislation relevant to the protection of biodiversity includes the following laws and conventions:

The Hunting and Wildlife Protection Code (established by Law No. 86-04 of 24 January 1986 and Decree

No. 86-844 of July 14, 1986) provides for a system of reserves to protect fauna (including the PNNK),

regulates hunting and defines the types of offenses related to the destruction of wildlife.

Law No. 98-03 of 8 January 1998 regarding the Forestry Code.

Page 35: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 20

Decree No. 96-1134 of 27 December 1996 provides for the implementation of Law No. 96-07 of March 22,

1996 concerning natural resources. This gives the responsibility for wildlife protection to local authorities,

particularly relating to the authority to create natural animal reserves.

A range of decrees relating to the establishment of the PNNK, including Decree No. 2002-271 of 7 March

2002 regarding the up-date of the Niokolo-Koba National Park (PNNK) boundary and periphery.

Land Acquisition and Compensation Regulatory Framework

The Company is committed to mitigating the impacts from land acquisition by providing compensation for loss of

land, assets and livelihood with appropriate stakeholder engagement. The requirement to provide compensation

under Senegalese law is described in the following:

Article 76 of the Mining Code (2003) states that the holder of a permit (including exploration permits) is

required to compensate the owners or occupants of land “for all loss suffered”. This is reiterated in Articles

89, 90, 92 and 93 of the Mining Code Application Decree No. 2004-647 of 17 May 2004 and includes

compensation of the State for any damages or losses resulting from mining operations.

Decree for application (64-573) of 30 July 1964 fixes the application conditions of Law No. 64-46 of June 17,

1964 relating to national property. Article 23 of the decree specifies that where reallocation of land occurs,

the new land holder must pay the previous landholder compensation equal to the value of built

improvements and planted crops estimated on the day that the new allocation is pronounced.

Decree No 91-938 (22 August 1991) amends Section 38 of Decree No. 64-573 of 30 July 1964 on the

application of the Law of the National Domain. It permits illegal / informal occupants subject to

displacement to be eligible for compensation.

Circular no. 2237/DGPA (October 7, 1974), Price scale for calculation of compensation in case of destruction

of plantations/cultivated land or delocalisation from the National Domain.

2.3 International Standards

The Company has adopted the IFC Performance Standards as an appropriate benchmark of international good

practice. These are supplemented as required by reference to the United Nations Guiding Principles on Business

and Human Rights and the International Council on Mining and Metals (ICMM) Sustainable Development

Framework, where relevant.

International agreements relevant to the Mako Gold Project are summarised in Table 2-2. Key international

standards and guidelines are further described below and in the ESIA (Chapter 3, Volume A).

Table 2-2 Relevant international environmental and social standards, safeguards and guidelines

Organisation Document Date Released

International Finance Corporation (IFC) Policy on Environmental and Social Sustainability and

associated IFC Performance Standards

2012

The World Bank / IFC General Environmental, Health and Safety Guidelines 2007

International Cyanide Management

Code

International Cyanide Management Code for the Manufacture,

Transport and Use of Cyanide in the Production of Gold

2014

International Union on the Conservation

of Nature (IUCN)

World Heritage Advice Note: Environmental Assessment;

World Heritage Advice Note: Mining and Oil/Gas Projects

2013

International Council on Metals and

Minerals (ICMM)

Sustainable Development Framework 2003

Extractive Industries Transparency

Initiative (EITI)

The EITI Standard 2013

Page 36: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 21

USA and UK Governments Voluntary Principles on Security and Human Rights 2000

UN Guiding Principles on Business and Human Rights 2011

2.3.1 IFC Performance Standards

The IFC is the private lending arm of the World Bank Group and the largest multilateral source of loan and equity

financing for private sector projects in developing nations. The environmental and social policies and procedures

of the World Bank are widely regarded as de facto international standards for the environmental and social

management of resource development projects in countries with developing or absent regulatory frameworks.

The IFC Performance Standards were introduced to provide guidance for IFC clients to manage and improve their

environmental and social performance through a risk and outcomes based approach. Direction to IFC’s clients and

staff on the application of the Performance Standards is provided in the IFC Guidance Notes, a companion

document to the Policy on Environmental and Social Sustainability. The updated IFC Performance Standards (PS)

comprise the following:

PS 1: Assessment and Management of Environmental and Social Risks and Impacts;

PS 2: Labour and Working Conditions;

PS 3: Resource Efficiency and Pollution Reduction;

PS 4: Community Health, Safety and Security;

PS 5: Land Acquisition and Involuntary Resettlement;

PS 6: Biodiversity Conservation and Sustainable Management of Living Natural Resources;

PS 7: Indigenous Peoples; and

PS 8: Cultural Heritage.

Implications of the above performance standards for the Mako Gold Project are discussed in the ESIA (Chapter 3,

Volume A).

2.3.2 World Bank General Environmental Health and Safety Guidelines

To support the Performance Standards, the IFC uses the World Bank “General Environmental, Health and Safety

Guidelines” of 2007 (EHS Guidelines) as a technical source of information during project appraisal. The EHS

Guidelines contain the industry best practices acceptable to the IFC. For IFC-financed projects, application of the

EHS Guidelines to existing facilities may involve the establishment of site-specific targets with an appropriate

timetable for achieving them. While implementation of the EHS Guidelines is not a mandatory condition in the

provision of financing, application of the guidelines is intended to ensure compliance with the IFC Performance

Standards.

The EHS Guidelines contain information on cross-cutting environmental, health, and safety issues potentially

applicable to all industry sectors, and should be considered together with the relevant industry sector guidelines.

Of specific relevance to the Mako Gold Project is an industry sector guideline developed for the mining sector, the

“Environmental, Health and Safety Guidelines for Mining” of 2007. The EHS Guidelines for Mining apply to

underground and open-pit mining, alluvial mining, solution mining, and marine dredging. The guideline addresses

industry-specific impacts and management techniques related to environmental impacts; occupational and

community health and safety; and mine closure and rehabilitation. The document also outlines sector-specific

performance indicators and monitoring methods related to the environment and occupational health and safety.

Where host-country regulations and standards differ from the levels and measures presented in the EHS

Guidelines, projects are encouraged to strive to achieve whichever is more stringent.

Page 37: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 22

2.3.3 International Cyanide Management Code

The Project will be consistent with the International Cyanide Management Institute (ICMI) Cyanide Management

Code (Cyanide Code) Principles and Standards of Practice (2014) for cyanide transportation, including independent

auditing of procedures and Transportation Verification Protocols; and Cyanide Code Standards of Practice for

handling and storage of Cyanide and associated reagents.

2.3.4 UN Guiding Principles on Business and Human Rights

The Guiding Principles on Business and Human Rights were endorsed by the UN Human Rights Council in 2011.

The Principles cover three main aspects:

1. The State duty to protect human rights;

2. The corporate responsibility to respect human rights; and

3. Access to effective remedy through judicial, administrative, legislative or other appropriate means, where

abuses to human rights occur.

Of relevance to the Mako Gold Project is the need for businesses to establish or participate in effective

operational-level grievance mechanisms for individuals or communities who may be adversely impacted by the

business. Such grievance mechanisms perform the following two key functions:

i) Support the identification of adverse human rights impacts as a part of an enterprise’s ongoing

human rights due diligence; and

ii) Allow grievances to be addressed and for adverse impacts to be remediated early and directly by the

business, thereby preventing harms from compounding and grievances from escalating.

The Guiding Principles state that to ensure effectiveness in practice, grievance mechanisms should be:

Legitimate – enabling trust from stakeholder groups and being accountable;

Accessible – known to all stakeholders. Assistance should be provided to those who may face barriers to

access;

Predictable – providing a clear and known procedure with indicative time frames;

Equitable – aggrieved parties have reasonable access to sources of information, advice and expertise;

Transparent – up-dates on grievance progress provided, as well as sufficient information about the

mechanism’s performance;

Rights-compatible – outcomes and remedies accord with internationally recognised human rights;

A source of continuous learning – identifying lessons for mechanism improvement; and

Based on engagement and dialogue – stakeholder consultation and focusing on dialogues to address and

resolve grievances.

2.3.5 International Union on the Conservation of Nature Guidelines

The IUCN has two key guidance documents pertaining to World Heritage:

World Heritage Advice Note: Environmental Assessment; and

World Heritage Advice Note: Mining and Oil/Gas Projects.

These guidelines are of relevance to the Project due to the presence of the World Heritage-listed Niokolo-Koba

National Park (Parc National de Niokolo-Koba or PNNK) and associated 1 km buffer zone adjacent to the east of the

Project. The Advice Notes detail the IUCN’s position on projects located within and in proximity to World Heritage

sites, and provides guidance on the steps to be undertaken to ensure that projects do not impact upon the

Outstanding Universal Values of World Heritage sites. The Advice Note on Environmental Assessment also

Page 38: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 23

presents eight World Heritage Impact Assessment Principles that must be implemented in undertaking an ESIA for

such projects.

The requirements of these advice notes have been taken into account by the Company and are presented in the

ESIA.

2.3.6 Extractive Industries Transparency Initiative

Senegal’s application to be a part of the Extractive Industries Transparency Initiative (EITI) was approved in

October 2013. Senegal will now implement the EITI Standard, which will ensure transparency in payments made

to the government by the extractives sector in the country. Senegal is required to publish its first EITI Report

within two years of becoming a Candidate (i.e. by October 2015). Validation will begin within three years of

becoming a Candidate (EITI, 2013). The Company will ensure that its activities are in line with the requirements of

the EITI.

2.4 Project Discharge Standards

The Project will consider and comply with:

Discharge and emissions guidelines for off-site releases of water, waste and potential airborne

contaminants; and

Ambient guidelines for the protection of environmental values (e.g. protection of aquatic fauna and

fisheries, drinking water, etc.).

A list of relevant national and international standards is presented in Table 2-3. Where standards or limits do not

exist in Senegalese Law, guidelines, standards or limits used by other countries (e.g. EU, USEPA, UK) or

organisations (e.g. WHO) are adopted in lieu.

Specific environmental criteria adopted for assessing discharge compliance by the Project are listed from Table 2-4

to Table 2-10.

Table 2-3 Relevant environmental standards and guidelines for the Mako Gold Project

Source Relevant Guidelines Year

WASTE / WASTEWATER DISCHARGE AND MONITORING

Senegal Interministerial Decree no 1555 Discharge Water Guidelines / L’arrêté interministériel No.

1555 de 15 mars 2002 portant application de la norme NS 05-061 sur les rejets des eaux

usées

2002

Waste Water Discharge Standard, NS 05-061 / La norme sur les rejets des eaux (NS 05-

061)

2001

Draft Standard on Management of Solid Waste / Projet de Norme relative à la Gestion des

Déchets Solides

In preparation

since 2005

IFC

Environmental Health and Safety Guidelines – Mining 2007

Environmental Health and Safety Guidelines – General – Environmental 2007

General EHS Guidelines: Wastewater and Ambient Water Quality. 2007

ICMI International Cyanide Management Code. 2009

AIR QUALITY

Senegal Atmospheric Pollution Standard, NS 05-062 / La Norme de rejets NS 05-062 – pollution

atmosphérique

2004

IFC Environmental Health and Safety Guidelines for Mining. 2007

Page 39: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 24

Source Relevant Guidelines Year

General EHS Guidelines: Air Emissions and Ambient Air Quality. 2007

WHO Air Quality Guidelines – Global Update 2005

SOIL QUALITY

UK Soil Guideline Value 2009

AQUATIC FAUNA / FRESH WATERS

Senegal n/a n/a

United States National recommended water quality criteria; republication. United States Environmental

Protection Agency (USEPA)

2009

European

Union

Directive 2008/105/EC of the European Parliament and of the Council of 16 December 2008

on environmental quality standards in the field of water policy, amending and subsequently

repealing Council Directives 82/176/EEC, 83/513/EEC, 84/156/EEC, 84/491/EEC,

86/280/EEC and amending Directive 2000/60/EC of the European Parliament and of the

Council.

2008

European

Union

Directive 2006/44/EC of the European Parliament and of the Council of 6 September 2006

on the quality of fresh waters needing protection or improvement in order to support fish life

(E.U., 2006).

2006

DRINKING WATER

Senegal n/a n/a

WHO Guidelines for Drinking Water Quality, fourth edition 2011

European

Union

Council directive 9883/EC of November 1998 on the quality of water intended for human

consumption.

1998

NOISE AND VIBRATION

Senegal Environment Code (noise) / Code de l’Environnement 2001

UK British Standards (vibration) BS 6472:2008, 4866:2010 and 7385-2:1993 1993, 2008,

2010

IFC Environmental Health and Safety Guidelines for Mining. 2007

Table 2-4 Air quality standards adopted for the Mako Gold Project

Pollutant Averaging Period WHO Standard1 Senegal Standard2

Particulate Matter <10 µm (PM10) 24 hour 50 µg/m3 260 µg/m3

1 year 20 µg/m3 80 µg/m3

Particulate Matter <2.5 µm (PM2.5) 24 hour 25 µg/m3 -

1 year 10 µg/m3 -

Nitrogen dioxide (NO2) 1 hour 200 µg/m3 200 µg/m3

1 year 40 µg/m3 40 µg/m3

Sulfur doxide (SO2) 24 hour 20 µg/m3 125 µg/m3

1 year - 50 µg/m3

Page 40: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 25

Pollutant Averaging Period WHO Standard1 Senegal Standard2

Carbon monoxide (CO) 1 hour 30 mg/m3 -

24 hour - 30 mg/m3

Ozone (O3) 8 hour 100 µg/m3 120 µg/m3

1. World Health Organization (WHO) Air Quality Guidelines (2005)

2. Senegalese Atmospheric Pollution Standard, NS 05-062 / La Norme de rejets NS 05-062 – pollution atmosphérique 2004

Page 41: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 26

Table 2-5 Ambient surface water quality standards adopted for the Mako Gold Project

Parameter

USEPA National recommended water criteria for freshwater (μg/L)

(2009)

EU Directive on the quality of fresh waters (2006) (μg/l)

EU Directive on Environmental Quality Standards in the field of

Water Policy (2008) (μg/L)3

International Cyanide Management Code (µg/L)

(2009)

Maximum (CMC**)

Continuous (CCC***)

Guideline Mandatory Annual Average Maximum

Aluminium (Al); pH 6.5-9.0 750 i 87

i,S - - - - -

Ammonia (NH3) Criteria are pH, temperature and

life-stage dependent. 5 25

t - - -

Arsenic (As) 340 a, d

150 a, d

- - - - -

Boron (B) 750,000b

- - - - -

Cadmium (Cd) 2 d,e

0.25 d,e

- - 0.08 - 0.25 f 0.45 - 1.5

f -

Chloride (Cl-) 860,000 230,000 - - - - -

Chlorine (Cl) 19 11 - 5 - - -

Page 42: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 27

Parameter

USEPA National recommended water criteria for freshwater (μg/L)

(2009)

EU Directive on the quality of fresh waters (2006) (μg/l)

EU Directive on Environmental Quality Standards in the field of

Water Policy (2008) (μg/L)3

International Cyanide Management Code (µg/L)

(2009)

Maximum (CMC**)

Continuous (CCC***)

Guideline Mandatory Annual Average Maximum

Chromium III (Cr3+

) 570 d,e

74 d,e

- - - - -

Chromium VI (Cr6+

) 16 d 11

d - - - - -

Copper (Cu)

Freshwater criteria calculated using biotic ligand model see “Aquatic Life Ambient Freshwater Quality

Criteria – Copper” 2007 EPA-822-R-07-001.

40 - - - -

Free cyanide 22 5.2 22n

Dissolved Oxygen See “Quality Criteria for Water”

1986. EPA 440/5-86-001.

50% of monitoring events are ≥

8 mg/L; 100% of

monitoring events are ≥

5 mg/L

50% of monitoring events are ≥

7 mg/Lo

- - -

Iron (Fe) - 1000c - - - - -

Lead (Pb) 65 d,e

2.5 d,e

- - 7.2 - -

Page 43: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 28

Parameter

USEPA National recommended water criteria for freshwater (μg/L)

(2009)

EU Directive on the quality of fresh waters (2006) (μg/l)

EU Directive on Environmental Quality Standards in the field of

Water Policy (2008) (μg/L)3

International Cyanide Management Code (µg/L)

(2009)

Maximum (CMC**)

Continuous (CCC***)

Guideline Mandatory Annual Average Maximum

Mercury (Hg) 1.4 d,hh

0.77 d,hh

- - 0.059 0.07 -

Nickel (Ni) 470 d,e

52 d,e

- - 20 - -

pH - 6.5 - 9.0 - 6.0 - 9.0p

- - -

Selenium - total (Se) l 5 - - - - -

Silver (Ag) 3.2 d,e

- - - - - -

Oil and Grease See “Quality Criteria for Water”

1986. EPA 440/5-86-001. g

- - - - -

Page 44: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 29

Parameter

USEPA National recommended water criteria for freshwater (μg/L)

(2009)

EU Directive on the quality of fresh waters (2006) (μg/l)

EU Directive on Environmental Quality Standards in the field of

Water Policy (2008) (μg/L)3

International Cyanide Management Code (µg/L)

(2009)

Maximum (CMC**)

Continuous (CCC***)

Guideline Mandatory Annual Average Maximum

Total Suspended Solids (TSS) See “Quality Criteria for Water”

1986. EPA 440/5-86-001. 25,000 - - - -

Turbidity (NTU) See “Quality Criteria for Water”

1986. EPA 440/5-86-001.t - - - - -

Zinc (Zn) 120 d,e

120 d,e

- 1,000 - - -

* Note that ambient water quality criteria apply to the receiving water downstream of the Project site, below a designated mixing zone(s). Selection of suitable mixing zone(s) will depend on the location of

discharge point(s).

Page 45: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 30

^ Relevant criteria are shaded in blue. As there are no existing GRS or World Bank / IFC ambient water quality guidelines, the European Union (EU) water quality standards have generally been selected as the

relevant criteria. While the EU water quality standards are generally more stringent than the corresponding USEPA criteria, they are more relevant to the Mako Gold Project as it is primarily owned by a United

Kingdom based company. Nevertheless, the USEPA criteria have been shaded where corresponding EU criteria are not provided.

** The Criteria Maximum Concentration (CMC) is an estimate of the highest concentration of a material in surface water to which an aquatic community can be exposed briefly without resulting in an unacceptable

effect.

*** The Criteria Continuous Concentration (CCC) is an estimate of the highest concentration of a material in surface water to which an aquatic community can be exposed indefinitely without resulting in an

unacceptable effect.

3 = With the exception of cadmium, lead, mercury and nickel (hereinafter ‘metals’) the EQS set up in this Annex are expressed as total concentrations in the whole water sample. In the case of metals the EQS refers

to the dissolved concentration, i.e. the dissolved phase of a water sample obtained by filtration through a 0.45 μm filter or any equivalent pre-treatment.

a = This recommended water quality criterion was derived from data for arsenic (III), but is applied here to total arsenic, which might imply that arsenic (III) and arsenic (V) are equally toxic to aquatic life and that

their toxicities are additive. In the arsenic criteria document (PDF, 74 pp., 3.2M) (USEPA, 1985), Species Mean Acute Values (SMAVs) are given for both arsenic (III) and arsenic (V) for five species and the ratios of the

SMAVs for each species range from 0.6 to 1.7. Chronic values are available for both arsenic (III) and arsenic (V) for one species; for the fathead minnow, the chronic value for arsenic (V) is 0.29 times the chronic value

for arsenic (III). No data are known to be available concerning whether the toxicities of the forms of arsenic to aquatic organisms are additive.

b – Criterion refers to the long-term irrigation for sensitive crops, refer to “Quality Criteria for Water” 1986. EPA 440/5-86-001 for further detail.

c = The derivation of this value is presented in the Red Book (EPA 440/9-76-023, July, 1976). The CCC of 20 mg/L is a minimum value except where alkalinity is naturally lower, in which case the criterion cannot be

lower than 25% of the natural level.

d = Freshwater criteria for metals are expressed in terms of the dissolved metal in the water column. See “Office of Water Policy and Technical Guidance on Interpretation and Implementation of Aquatic Life Metals

Criteria” October 1, 1993, by Martha G. Prothro, Acting Assistant Administrator for Water, available on NSCEP’s web site and 40CFR131.36(b)(1). Conversion Factors applied in the table can be found in Appendix A

to the Preamble-Conversion Factors for Dissolved Metals.

e = The freshwater criterion for this metal is expressed as a function of hardness (mg/L) in the water column. The value given here corresponds to a hardness of 100 mg/L. Criteria values for other hardness may be

calculated per the equation presented in the criteria document.

f = For cadmium the EU environmental quality standards values vary depending on the hardness of the water as specified in five class categories (Class 1: < 40 mg CaCO3/l,

Class 2: 40 to < 50 mg CaCO3/l, Class 3: 50 to < 100 mg CaCO3/l, Class 4: 100 to < 200 mg CaCO3/l and Class 5: ≥ 200 mg CaCO3/l).

g = A factor of 0.01 of the 96-hour LC50 as determined by using continuous flow with a sensitive resident species, should be employed for individual petrochemical components. Surface waters shall be virtually free

from floating non-petroleum oils of vegetable or animal origin, as well as petroleum-derived oils.

i = This value for aluminum is expressed in terms of total recoverable metal in the water column.

s = There are three major reasons why the use of the water-effect ratios might be appropriate.

t = Settleable and suspended solids should not reduce the depth of the compensation point for photosynthetic activity by more than 10 % from the seasonally established norm for aquatic life.

Page 46: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 31

1. The value of 87 µg/L is based on a toxicity test with the striped bass in water with pH = 6.5-6.6 and hardness <10 mg/L. Data in “Aluminium Water-Effect Ratio for the 3M Plant Effluent Discharge,

Middleway, West Virginia” (May, 1994) indicate that aluminium is substantially less toxic at higher pH and hardness, but the effects of pH and hardness are not well quantified at this time.

2. In tests with the brook trout at low pH and hardness, effects increased with increasing concentrations of total aluminium even though the concentration of dissolved aluminium was constant, indicating

that total recoverable is a more appropriate measurement than dissolved, at least when particulate aluminium is primarily aluminium hydroxide particles. In surface waters, however, the total recoverable

procedure might measure aluminium associated with clay particles, which might be less toxic than aluminium associated with aluminium hydroxide.

hh = This recommended water quality criterion was derived from data for inorganic mercury (II), but is applied here to total mercury. If a substantial portion of the mercury in the water column is methylmercury,

this criterion will probably be under protective. In addition, even though inorganic mercury is converted to methylmercury and methylmercury bioaccumulates to a great extent, this criterion does not account for

uptake via the food chain because sufficient data were not available when the criterion was derived.

l = The CMC = 1/[(f1/CMC1) + (f2/CMC2)] where f1 and f2 are the fractions of total selenium that are treated as selenite and selenate, respectively, and CMC1 and CMC2 are 185.9 mg/l and 12.82 mg/l, respectively.

O = When the oxygen concentration falls below 4 mg/L, Member States shall implement the provisions of Article 7(3). The competent authority must prove that this situation will have no consequences for the

balanced development of the fish population.

N = Free cyanide concentrations should not exceed 0.022 mg/L downstream of any established mixing zone.

P = Artificial pH variations with respect to the unaffected values shall not exceed ± 0.5 of a pH unit within the limits falling between 6.0 and 9.0 provided that these variations do not increase the harmfulness of other

substances present in the water.

T = In order to diminish the risk of toxicity due to the non-ionised ammonia, of oxygen consumption due to nitrification and of eutrophication, the concentration of total ammonium should not exceed the following:

≤0.2 mg/L NH4 (Guide) or ≤1 mg/L NH4 (Mandatory), in particular geographical or climatic conditions and particularly in cases of low water temperature and of reduced nitrification or where the competent water

authority can prove that there are no harmful consequences for the balanced development of the fish population, Member states may fix values higher than 1 mg/L.

9 = If Member States do not apply EQS for biota they shall introduce stricter EQS for water in order to achieve the same level of protection as the EQS for biota set out in Article 3 (2) of this Directive. They shall

notify the Commission and other Member States, through the Committee referred toin Article 21 of Directive 2000/60/EC, of the reasons and basis for using this approach, the alternative EQS for water established,

including the data and the methodology by which the alternative EQS were derived, and the categories of surface water to which they would apply.

Page 47: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 32

Table 2-6 Drinking water quality standards adopted for the Mako Gold Project

Parameter Units World Health Organisation

(WHO) - Drinking Water Guidelines (2011)

EU Directive on the water intended for

human consumption (1998)

Aluminium (Al) mg/L - 0.2i

Ammonium (NH4) mg/L - 0.5i

Antimony (Sb) mg/L 0.02 0.005

Arsenic (As) mg/L 0.01 A,T 0.01

Barium (Ba) mg/L 0.7 -

Beryllium (Be) mg/L - -

Boron (B) mg/L 2.4 1

Cadmium (Cd) mg/L 0.003 0.005

Chloride (Cl-) mg/L - 250i

Chlorine (Cl) mg/L 5 C -

Chromium - total (Cr) mg/L 0.05 P 0.05

Copper (Cu) mg/L 2 2

Page 48: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 33

Parameter Units World Health Organisation

(WHO) - Drinking Water Guidelines (2011)

EU Directive on the water intended for

human consumption (1998)

Colour TCU - Acceptable to consumers and no abnormal changei

Conductivity µS/cm - 2,500 at 20°Ci

Cyanide (CN) mg/L - 0.05

E. coli MPN**/100ml 0 0

Fluoride (F) mg/L 1.5 1.5

Iron (Fe) mg/L - 0.2i

Lead (Pb) mg/L 0.01 A,T 0.01

Manganese (Mn) mg/L - 0.05i

Mercury (Hg) mg/L 0.006 0.001

Nickel (Ni) mg/L 0.07 0.02

Page 49: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 34

Parameter Units World Health Organisation

(WHO) - Drinking Water Guidelines (2011)

EU Directive on the water intended for

human consumption (1998)

Nitrate (NO3) mg/L 50 (short term exposure) 50

Nitrite (NO2) mg/L 3 (short term exposure) 0.5

pH log units - 6.5 to 9.5i

Selenium (Se) mg/L 0.04 P 0.01

Silver (Ag) mg/L ID -

Sodium (Na) mg/L - 200i

Sulfate (SO4) mg/L - 250i

Thallium (Tl) mg/L - -

Page 50: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 35

Parameter Units World Health Organisation

(WHO) - Drinking Water Guidelines (2011)

EU Directive on the water intended for

human consumption (1998)

Total coliforms MPN**/100ml 0 0i

Total Dissolved Solids (TDS)

mg/L - -

Total organic carbon (TOC)

- - No abnormal changei

Turbidity NTU - Acceptable to consumers and no abnormal changei

Uranium (U) mg/L 0.03 P -

Zinc (Zn) mg/L - -

* Relevant criteria are shaded in blue. In general, the WHO guidelines have been shaded as these represent international standards for human

health and are applicable to developing and developed countries world-wide. Where WHO guidelines are not provided, the European Union

values have been shaded. There are no existing GRS drinking water quality guidelines.

** MPN = Most Probable Number.

ID = Insufficient data to set a guideline value based on health considerations.

A= Provisional guideline value because calculated guideline value is below achievable quantification level.

P = Provisional guideline value, as there is evidence of a hazard, but the available information on health effects is limited.

T = Provisional guideline value because calculated guideline value is below the level that can be achieved through practical treatment

methods, source protection, etc.

C = Concentrations of the substance at or below the health-based guideline value may affect the appearance, taste or odour of the water,

leading to consumer complaints.

I= Indicator values. Whereas, in the event of non-compliance with a parameter that has an indicator function, the Member State concerned

must consider whether that non-compliance poses any risk to human health; whereas it should take remedial action to restore the quality of

the water where that is necessary to protect human health.

Table 2-7 Discharge water quality standards adopted for the Mako Gold Project

Page 51: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 36

Parameter Unit

Discharge Water Guidelines GRS (2002)

Mining Discharge

Treated Sanitary Sewage Effluent

International Management Cyanide Code

General Non

Protected Protected IFC (2007)**

IFC (2007)**

ICMI (2009)

Arsenic (As) mg/L 0.3 (for loads

>3g/day) 1 0.5 0.1# - -

Biological oxygen demand (BOD5)

mg/L - 50 20 50 30 -

Cadmium (Cd)

mg/L - - - 0.05# - -

Chromium, trivalent (Cr(III))

mg/L 1 (for loads >10g/day)

1 0.5 - - -

Chromium, hexavalent

(Cr(VI)) mg/L

0.2 (for loads

>5g/day) 0.2 0.2 0.1# - -

Chemical oxygen demand

(COD)

mg/L

200 (for loads

≤100 kg/day); 100

otherwise

200 90 150 125 -

Copper (Cu) mg/L - 1 0.5 0.3# - -

Cyanide (free CN)

mg/L - - - 0.1 - 0.022c

Cyanide (WAD CN)

mg/L - - - 0.5 - 0.5

Cyanide (CN total)

mg/L 0.2 (for loads

>3g/day) 1 0.5 1 -

Faecal coliforms

MPN/ 100ml

2,000 -

Faecal streptococci

MPN/ 100ml

1,000 -

Flow m3

When the authorised daily maximum flow exceeds 1/10 of the nominal capacity of the river or if it exceeds 100m3/day, the decree also fixes a limit at the monthly average of the daily output as well as an instantaneous limiting value.

- - -

Page 52: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 37

Parameter Unit

Discharge Water Guidelines GRS (2002)

Mining Discharge

Treated Sanitary Sewage Effluent

International Management Cyanide Code

General Non

Protected Protected IFC (2007)**

IFC (2007)**

ICMI (2009)

Fluoride (F-) mg/L 25 (for

loads> 250 g/day)

100 20 - - -

Iron, total (Fe)

mg/L - - - 2.0# - -

Lead (Pb) mg/L - - - 0.2# - -

Mercury (Hg) mg/L - - - 0.002# - -

Nickel (Ni) mg/L - - - 0.5# - -

Nitrogen – total (N)

mg/L 30 (for loads

>50 kg/day) 20 10 - 10 -

Oil and grease

mg/L 15 (for loads

>150 g/day) 50 20 10 10 -

pH - 5.5 – 9.5 - - 6.0-9.0 6.0-9.0 -

Phenols mg/L 0.5 (for loads

>5 g/day) - - 0.5 - -

Phosphorus – total (P)

mg/L 10 (for loads

>15 kg/day) 10 5 - 2 -

Salmonella MPN/

5000ml 0 - - -

Page 53: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 38

Parameter Unit

Discharge Water Guidelines GRS (2002)

Mining Discharge

Treated Sanitary Sewage Effluent

International Management Cyanide Code

General Non

Protected Protected IFC (2007)**

IFC (2007)**

ICMI (2009)

Temperature (differential)

C

≤ 30C (if receiving

water body temperatur

e >30C, then a

difference

of 5C is allowed)

- - <3 degree

differential - -

Total coliforms

MPNa/100 ml

- - - - 400b -

Total suspended solids (TSS)

mg/L 50 40 30 50 50 -

Vibrio cholera

MPN/ 5000ml

0 - - -

Zinc (Zn) mg/L - - - 0.5# - -

* Relevant criteria are shaded in blue. The shaded values represent the most stringent criteria (IFC and/or GRS) for each parameter. Note that

discharge criteria apply to process wastewater, drainage (from active or closed Project areas), surface runoff from paved or unpaved areas, and

sanitary waste water (unless passing to a sewage treatment system), before it enters the receiving environment. Below a designated mixing

zone(s), ambient water quality criteria also apply (see Table 2.2). Selection of suitable mixing zone(s) will depend on the location of discharge

point(s).

** In addition to the criteria in this table, discharges to surface water should not result in contaminant concentrations in excess of local

ambient water quality criteria outside a scientifically established mixing zone. Receiving water-body use and assimilative capacity, including

the impact of outer sources of discharges to the receiving water, should be considered with respect to acceptable contaminant loadings and

effluent discharge quality as described in IFC (2007)

# Metal concentrations represent total metals.

a MPN is Most probable number.

b Not applicable to centralised, municipal, wastewater treatment systems which are included in EHS Guidelines for Water and Sanitation.

c Direct or indirect discharge of water from site should not result in a concentration of free cyanide in excess of 0.022 mg/L downstream of any

established mixing zones.

Table 2-8 Noise standards adopted for the Mako Gold Project

Receptor LAeq 1 hour dB(A)

Day-time (07:00 – 22:00) Night-time (22:00 – 07:00)

IFC/WBC EHS Guidelines – Noise Management 2007

Page 54: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 39

Table 2-9 Vibration standards adopted for the Mako Gold Project

1. Australia / NSW Department of Environment and Climate Change (2006) vibration criteria for human comfort and building damage.

Table 2-10 Airblast and blasting standards adopted for the Mako Gold Project

Residential; institutional; educational 55 45

Industrial; Commercial 70 70

Noise Pollution Standards Article R84 of Decree 2001-282

Residential; institutional; educational 60 40

Article 14 of Decree 2006-1252

Level of workers’ daily exposure to noise 85 85

Receptor Vibration Criteria (maximum Peak Particle Velocity (mm/s))1

Human Comfort Building Damage

Residential buildings during the day time 0.28 10

Residential buildings during the night time 0.20 10

Offices during the day 0.56 10

Receptor Airblast1 Ground-Vibration1

Sensitive site (more than 12 months or more than 20 blasts) 115 dB(L) for 95% of

blasts

120 dB(L) maximum –

unless agreement with

occupier that higher limit

may apply

5 mm/s for 95% blasts

10 mm/s maximum - unless

agreement with occupier that

higher limit may apply

Sensitive site (less than 12 months or less than 20 blasts) 120 dB(L) for 95% of

blasts

125 dB(L) maximum –

unless agreement with

occupier that higher limit

may apply

10 mm/s maximum - unless

agreement with occupier that

higher limit may apply

Non-sensitive site

(factory or commercial premises)

125 dB(L) maximum –

unless agreement with

occupier that higher limit

may apply

Vibrations should be kept

below specifications of

sensitive operating

equipment

25 mm/s maximum - unless

agreement with occupier that

higher limit may apply

Vibrations should be kept

below specifications of

sensitive operating

equipment

Structures (masonry, plaster, concrete, steel etc) 133 dB(L) maximum –

unless agreement with

occupier that higher limit

may apply

15 mm/s - light framed

structure at 4Hz

20 mm/s – light framed

structure at 15 Hz

50 mm/s – light framed

Page 55: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 40

1. Australian Standard AS2187.2, Explosives – Storage and use, Appendix J: Ground Vibration and Airblast Overpressure, 2006; which is based

on the US Bureau of Mines USBM RI-8507 and British Standard (vibration) BS 7385-2.

2.5 International Conventions, Treaties and Agreements

Senegal is a party to a number of international policies, conventions and agreements which have relevance to the

project and are listed in Table 2-11. The Company will develop the Mako Gold Project in accordance with these

commitments.

Table 2-11 International commitments observed by Senegal and relevant to the Mako Gold Project

Commitment Overview and Requirements Implications for Mako Gold Project

Additional Act No. 01/2000 of 14 December 2000 of UEMOA regarding the adoption of a Common Mining Policy

(Acte additionnel n°01/2000 du 14 décembre 2000 de l’UEMOA portant adoption de la politique minière commune)

Makes specific reference to the importance of environmental protection and coexistence between industrial and artisanal miners.

Project will need to consider environmental issues and social issues relating to industrial vs artisanal mining.

Regulation No. 18/2003/CM/UEMOA of 23 December 2003 regarding the UEMOA Mining Code

(Règlement n°18/2003/CM/UEMOA du 23 décembre 2003 portant code minier de l’UEMOA)

Contains requirements that mining companies carry out an EIA for exploitation, respect environmental regulations, put in a monitoring plan and develop a rehabilitation programme.

Requirement for an ESIA prior to commencement of exploitation activities, to contain monitoring plans and a rehabilitation programme.

ECOWAS Directive C/DIR.3/05/09 on the Harmonization of the Guiding Principles and Policies in the Mining Sector

Lists several requirements with regards to human rights, sustainable development and local community interests which relate to the operations of mining companies.

Activities need to consider and promote such issues as human rights, empowerment of women and community participation and consultation.

Convention on International Trade in Endangered Species (CITES)

Avoidance of trade in endangered species. No trade in endangered species to be undertaken as part of this Project.

United Nations Convention on Biological Diversity (CBD)

Identify processes and categories of activities which have or are likely to have significant adverse impacts on the conservation and sustainable use of biological diversity, and monitor their effects through sampling and other techniques.

Introduce appropriate procedures requiring environmental impact assessment of proposed projects that are likely to have significant adverse effects on biological

Pre-mining baseline study on biodiversity in areas of potential impact required as part of ESIA. ESIA needs to assess impacts and develop appropriate mitigation measures to address impacts on threatened species, with full stakeholder consultation. Also requires development of re-vegetation plan.

structure at 40 Hz

50 mm/s – reinforced

structure above 4Hz

Un-occupied structures (reinforced concrete or steel construction) n/a - use133 dB(L) 100 mm/s maximum - unless

agreement with owner that

higher limit may apply

Above-ground services (pipelines, power-lines, cables) Limit to be determined by

structural design

Limit to be determined by

structural design

Page 56: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 41

Commitment Overview and Requirements Implications for Mako Gold Project

diversity with a view to avoiding or minimizing such effects and, where appropriate, allow for public participation in such procedures.

United Nations Framework Convention on Climate Change and the Kyoto Protocol

Greenhouse gas (GHG) emissions from mining activities (including electricity generation) should be less than 100,000 tonnes of CO2 equivalent per year if 100% heavy fuel oil is used, and approximately 66,000 tonnes of CO2 equivalent per year if natural gas is used. If the project produces more than 100,000 tonnes CO2 equivalent per year, then annual quantification and monitoring of GHG emissions would be necessary to satisfy IFC Performance Standard 3, Clauses 10 and 11.

The Project is not expected to exceed emissions of 100,000 CO2 equivalent annually.

Under the Kyoto Protocol, Senegal has no restrictions on its greenhouse gas emissions because it is a Non-Annex 1 country. It is possible for Senegal to trade in Carbon Credits with Annex 1 countries.

Convention on the Protection of World Cultural and Natural Heritage

World Cultural and Natural Heritage refers to cultural and natural heritage sites of outstanding universal value. The Convention requires countries to conserve biodiversity, sustainably use the various components of biodiversity, and share benefits arising from the use of biodiversity fairly and equitably.

Five sites have been identified in Senegal: the Island of Goree; the Djoudj Bird Sanctuary; Niokolo-Koba National Park; Island of Saint-Louis; and Stone Circles of Senegambia. The sites are protected by law and have minimum exclusion buffer zones.

The Project exploration permit area lies adjacent to Niokolo-Koba National Park. It does not fall within either the park itself or the 1 km exclusion buffer.

Convention on Protection of Wetlands of International Importance (RAMSAR Convention)

Four wetlands in Senegal are listed under the RAMSAR Convention, none of which are located within or near the Project area.

The Project is not expected to significantly affect any RAMSAR-listed wetlands.

Montreal Protocol on substances which deplete the ozone layer

The Montreal Protocol stipulates that the production and consumption of compounds that deplete ozone in the stratosphere - chlorofluorocarbons (CFCs), halons, carbon tetrachloride, and methyl chloroform - were to be phased out by 2000 (2005 for methyl chloroform).

No substances listed on the Montreal Protocol should be used in the development of the Project.

Stockholm Convention on Persistent Organic Pollutants (POPs)

Senegal is a signatory to the Stockholm Convention, which targets the reduction in manufacture, use and by-production of 21 organic pollutants that persist and bio-accumulate in the environment.

Target species include pesticides aldrin, dieldrin and DDT, also PCDFs, PCBs, PFOS, and dioxins and furans.

Electrical components, electronics, plastics, and heat exchange fluids should not be burnt. Some flame retardants and foams contain POPs and alternatives should be sought. Use non-POP insecticides to prevent mosquitos. Disposal of all wastes to be considered as part of an effective waste management program.

United Nations Convention to Combat Desertification

Desertification is the degradation of land in arid, semi-arid and dry sub-humid areas. It is caused primarily by human activities and climatic variations.

The Convention provides criteria for developing action programmes to combat desertification, through enabling local people to reverse land degradation.

Re-vegetation will need to be undertaken as part of the rehabilitation of the site to assist in local efforts to combat desertification. Local expertise should be involved in developing and implementing the re-vegetation plan.

Page 57: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 42

Commitment Overview and Requirements Implications for Mako Gold Project

Convention Concerning Basic Aims and Standards of Social Policy (International Labour Organisation Convention)

Protection of basic rights for workers including: fair treatment, non-discrimination, equal opportunity, safe and healthy working conditions.

The Company will need to respect workers’ basic rights and provide a safe and healthy working environment, in accordance with IFC Performance Standard 2 on Labour and Working Conditions.

Convention Relating to the Status of the River Gambia / Convention Relating to the Creation of the Gambia River Basin Development Organization (OMVG)

No project which is likely to bring about serious modifications of a number of riverine characteristics, including its navigation conditions, the agricultural and industrial exploitation of the river, the sanitary state of the waters, the biological characteristics of its fauna and its flora, as well as its water level, will be implemented without the prior approval of the contracting States.

The Company will require permission from OMVG to abstract water and discharge to the Gambia River.

Bonn Convention / Convention on Migrating Species of Wild Animals (CMS)

Intergovernmental treaty that aims to conserve terrestrial, aquatic and avian migratory species, their habitats and migration routes throughout their range, especially relating to endangered migratory species.

Government of Senegal has signed a Memorandum of Understanding under this convention covering the African Elephant, which encourages signatories to ‘Take steps to conserve and, when and where appropriate, to strictly protect the African Elephant and to conserve and sustainably use the habitats essential for its survival.

Page 58: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 43

3 ESMMP FRAMEWORK

3.1 Purpose of the ESMMP

The ESMMP brings together into a single document the Company’s legal obligations and other requirements

associated with the Mako Gold Project with the environmental and social commitments specified in the ESIA for

inclusion in the suite of management measures and monitoring programmes to be implemented during the

construction and operations phases.

To assist with the effective implementation of the ESMMP for this Project, the Company will adopt a formal

Environmental Management System (EMS) which is consistent with GRS legislation and aligned with the following

guidelines and international standards:

OHSAS 18001 Occupational health and safety management systems;

ISO 14001 Environmental management systems;

ISO 26000 Guidance on social responsibility;

IFC Performance Standards; and

Global Reporting Initiative Sustainability Reporting Guidelines.

This management system provides the Company with a procedural framework for implementing, achieving,

reviewing and maintaining the Company’s environmental and community policies and all environmental and social

management targets. This function of the ESMMP is represented schematically in Figure 3-1.

Targets set in this ESMMP will be used to guide the implementation of environmental and social management and

monitoring programmes until the next revision of the ESMMP, and facilitate continuous improvement in

environmental and social management. The targets are expected to be updated following public disclosure of the

Draft ESIA based on regulator and stakeholder feedback, and as required when a significant change arises or

following annual or biennial updates of the ESMMP.

The Company will ultimately be responsible for implementing the Project ESMMP throughout the life of Project,

and will ensure that contractors engaged during the course of the Project comply with this document for their

works (e.g. include contractual provisions for Contractors to have an appropriate EMS in place prior to CEMP

preparation).

Page 59: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 44

Figure 3-1 Schematic diagram of the ESMMP framework

3.2 Responsibilities and Human Resources

Implementation of the ESMMP will require appropriate staff, financial resources, equipment and support systems.

It is the responsibility of all the Company staff and contractors to comply with the requirements set out in the

ESMMP. The responsibility of Project contractors and suppliers will be defined through standard terms and

conditions of contracts that are consistent with the commitments of the ESMMP.

The key roles, responsibilities and other requirements for the implementation of the Project ESMMP are outlined

below.

3.2.1 Responsibilities - Internal Parties

The Company is responsible for setting up a suitably experienced and qualified team to implement ESMMP

responsibilities for the Project. The Occupational Health, Safety, and Environment (OHS&E) Manager, supported

by a team of environment and social advisors, will have the following responsibilities:

Complying with legal obligations and ESIA commitments by establishing and maintaining appropriate

management and monitoring systems;

Sustainability Policy

Planning

Management Review

Implementation and Operation

Checking and Corrective Action

Environmental Management System

Environmental and Social Management and Monitoring Plan

Updated regularly

Internal and External Auditing

Annual Sustainability Reports

Standard Operating Procedures (SOPs): - General SOPs - Emergency Preparedness and Response Plans - Monitoring Procedures - Rehabilitation Procedures

Environment and Social Performance Framework

Environmental and Social Impact Assessment

Rehabilitation and

Mine Closure Plan

Page 60: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 45

Ensuring the environmental and social management and monitoring described in the ESMMP are

implemented effectively;

Ensuring management measures and commitments contained in the ESMMP are included in Contractor

Contracts (as relevant) and that contractors fulfil their contractual environmental and social obligations;

Reviewing and approving the Construction Environmental Management Plan (CEMP) to ensure it is

adequate, complies with the ESMMP and any mining licence conditions, and up-to-date with any changes

in Project scope, legislation, or policies;

Proactively engaging and liaising with relevant Government Authorities, communities and other

stakeholders - including dissemination of Project updates and regular, meaningful, inclusive and

participatory consultations with affected communities;

Preparing and submitting reports regarding progress of implementation, performance of environmental

management measures and monitoring data, and relevant environmental information and data required

by regulators;

Ensuring the Company personnel and contractors receive appropriate training and awareness regarding

their environmental and social responsibilities; and

Monitoring the performance of the environmental and social management measures in the ESMMP.

Under the direction of the OHS&E Manager, the Environment Department will comprise a team of qualified

professionals responsible for the day-to-day implementation of rehab activities, compliance monitoring and the

Biodiversity Action plan. The Social Department will comprise a team of qualified professionals responsible for the

day-to-day implementation of the livelihood programme, community relations activities, and local participation

programme. Each department will be led by a coordinator who shall report to the OHS&E Manager on a daily

basis or as required for fulfilment of duties.

3.2.2 Responsibilities - External Parties

Government Authorities

The Project will require coordination with a number of institutional structures at all levels of Government. Key

responsibilities of such governmental institutional structures are summarised in Table 3-1 below.

The participation of external parties in the monitoring programme of the Project will be the subject of consultation

during Project permitting and subject to annual review thereafter. The Company will work with the existing

Regional Environmental Monitoring Committee (Comité Régional de Suivi Environnemental et Social, CRSE) to

enable GRS to conduct independent monitoring of the Project in the Kedougou Region. The CRSE will be used to

monitor current and future Company’s activity within the Kedougou Region across the construction, operations

and closure phases of the Mako Gold Project.

Plans for forest management will also be approved by the Directorate of Water, Forests, Hunting and Soil

Conservation prior to implementation.

Table 3-1 Overview of Government authorities

Relevant Authority Key responsibilities for the Mako Gold Project

Direction of Civil Protection (Direction de la

Protection Civile) (DPC)

Review of the emergency response plans, including the Plan

d’Opération Interne (POI)); and

Conduct of site audits.

Direction of Mining and Geology (Direction des

Mines et de la Géologie (DMG))

Monitoring of compliance to the Mining Code requirements; and

Participation with the CRSE to the monitoring of the ESMMP

implementation.

Direction of Environment (Direction de

l’Environnement et des Etablissements Classés

Environmental and social monitoring through:

Page 61: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 46

Relevant Authority Key responsibilities for the Mako Gold Project

(DEEC)) Validation of the ESMMP for the Project; and

Conduct of periodic monitoring site visits.

Regional Environment Service (Division Régionale

de l’Environnement et des Etablissements Classés

(DREEC))

Coordination of the environmental and social monitoring

committee; and

Conduct of periodic monitoring site visits.

Niokolo-Koba National Park Regional Service

(PNNK)

Monitoring of the implementation of management measures in the PNNK

at a local level through:

Biodiversity Action Plan; and

Relevant sections of the ESMMP.

Direction of National Parks (Direction des Parcs

Nationaux (DPN))

Monitoring of the implementation of management measures in the PNNK

at a national level.

Regional Environmental Monitoring Committee

(REMC) (Comité Régional de Suivi

Environnemental et Social (CRSE))

Monitoring of the implementation of the ESMMP of the Mako Gold

Project.

Directorate of Water, Forests, Hunting and Soil

Conservation

Approve plans for forest management.

Contractors

A CEMP will be developed in line with this ESMMP prior to construction and provide greater detail to meet

environmental and social management requirements.

In addition, the Construction Contractor(s) will:

Secure relevant permits and licences, as appropriate;

Prepare and maintain records and all required reporting data as stipulated by this ESMMP, for submission

to the Company;

Report regularly to the Company’s OHS&E Manager regarding environmental and community

performance;

Review and update the CEMP during construction if any significant changes occur; and

Ensure that all construction employees and subcontractors are fully informed of the CEMP and

understand the required measures for environmental and social compliance and performance.

3.3 Capacity Building

3.3.1 Project Capacity Building

Induction and Training

Company employees and Contractors will undertake an environmental and social induction, as appropriate for

their role and responsibilities, before commencing work. The programme will cover the following aspects:

Project legislative requirements and obligations under relevant corporate policies and commitments;

Anticipated impacts of the Project and mitigation measures to be employed;

Site layout and environmental sensitivities;

Page 62: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 47

Social sensitivities and cultural awareness;

Project operating procedures, environmental management procedures, and supporting documentation;

General health and safety aspects, including disease transmission prevention, proper hygiene and

sanitation, waste management, and the Emergency Response Plan (Plan d’Opération Interne, POI) and

Local Authority Emergency Plan (Plan Particulier d’Intervention, PPI) (to be developed);

Importance of biodiversity values and prohibition of hunting, trading or buying wildlife products or

harvesting and collecting forestry products (including timber and non-timber forest products);

Grievance management procedure; and

Incident and non-compliance reporting requirements and processes (including occupational near misses

and accidents, chemical and hydrocarbon spills, observed illegal activities such as logging or poaching,

wildlife or livestock collisions, fauna poisoning, accidental environmental release of contaminated water,

etc.).

During periodic site inspections, workers’ knowledge of general environmental, health and safety issues will be

examined to monitor enforcement and compliance with Project procedures and plans.

In addition, occupation-specific training will be implemented for applicable Company employees and contractors

to meet environmental and social commitments associated with their respective technical jobs. This training will

include:

Occupation-specific health and safety requirements, including proper handling, transporting and storing

of hazardous materials and dangerous goods as well as use of specific personal protective equipment

(PPE) and equipment;

Transport safety protocols (e.g. driver safety training, fatigue management, etc.);

Specific environmental (e.g. water quality sampling techniques) and social (e.g. household surveying)

monitoring requirements;

Standard operating procedures (SOPs) for various environmental management practices (e.g. erosion and

sediment controls, dust and noise controls, land clearance, blast management, etc.) and

operation/maintenance of specific machinery and equipment;

Stakeholder engagement and response to community complaints; and

Response to environmental incidents and emergencies, including specific environmental emergency

response procedures, first aid, fire-safety training, and cyanide specific and other chemical spill response

and clean-up procedures and neutralisation techniques.

Cross-cultural awareness will be a key consideration in the delivery of both the induction and training programme

by suitably qualified employees in a language and format understood by workers. Opportunities for ongoing

training for Company employees to improve environmental and social awareness and performance will be

provided. Records of training and competency levels will be retained in a database, including information on name

of trainer and attendees, date of training session, and the next scheduled refresher session (if applicable).

Employees who have undergone occupation-specific training will be periodically tested in relation to their

knowledge and competence skills, and will be subjected to re-training, if required. Records of examination results

and any re-training will be kept as part of the training database.

The overall environmental and social programme will be updated when required to reflect changes in the Project

scope, legislation, or other circumstances.

Recruitment

In accordance with the Company’s preferential local recruitment policy, nationals and locals employed for the

Project will be maximised as per the Local Economic Participation Plan (LEPP, Volume D).

The Company will recruit appropriately experienced and competent employees to ensure the necessary technical

knowledge and skills are available onsite to comply with environment and social requirements, objectives and

Page 63: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 48

commitments. External consultants who are suitably qualified to support site employees will be engaged where

there is a need for additional expertise.

Equipment and logistics

The Company will provide logistical and material support for the Government to undertake routine monitoring

missions of Project activities.

Refer to Chapter 17 for a preliminary list of equipment, logistics and resources required for the implementation of

the Project ESMMP.

3.3.2 External Capacity Building

Regional Environmental Monitoring Committee

The Company will support the Government of Senegal to conduct independent monitoring through the Regional

Environmental Monitoring Committee (Comité Régional de Suivi Environnemental et Social, CRSE). It is expected

that the CRSE will conduct an annual, independent audit of Project activities.

The Company proposes the following support to the CRSE:

1. Annual operating costs for the CRSE to conduct independent monitoring and compliance activities of the

Project in accordance with the approved ESMMP and ESIA;

2. Capacity building for CRSE staff employed in monitoring and compliance functions associated with

Company activities, including training and skills development;

3. Financial contributions to the CRSE in the Kedougou Region will cease once the Company no longer has

operating projects and is no longer actively undertaking mineral exploration in the Kedougou Region.

Contributions will however extend over a period of three years during the closure phase of the Mako Gold

Project. In consultation with the CRSE the Company will agree on the requirement for support and review

the support programme on an annual basis.

Capacity Building Workshops

If required, the Company will provide technically focussed workshops to assist relevant government

representatives responsible for Project regulatory compliance and monitoring to improve their core functions and

duties as necessary (e.g. in the areas of biodiversity, water resources, and community resource use).

Apprenticeship Programme

In partnership with local training and education providers, the Project will provide paid apprenticeships for local

and regional students. Apprenticeships will be based on Project skill requirements and will provide practical work

experience to students.

Plan and Budget for Capacity Building

A proposed budget for capacity building for local authorities, including the Regional Environmental Monitoring

Committee, has been proposed in Chapter 17. The final plan and budget for capacity building for the Project will be

determined in consultation with relevant agencies.

3.4 Monitoring Systems

The implementation of an appropriate monitoring strategy as part of the ESMMP is important to ensure that

existing management measures are effective, and to identify the need for improved or additional measures. The

objectives of the Project environmental and social monitoring programme are to:

Detect and analyse environmental and social trends or changes to develop an appropriate response,

where required;

Ensure relevant environmental legislation and licensing commitments of the Project are complied with;

Page 64: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 49

Measure the performance of environmental and social management measures to ensure impacts remain

at an acceptable level and there is ongoing improvement of Project’s operations; and

Provide early warning of potential impacts, determine the extent of anticipated impacts and identify any

unforeseen impacts associated with Project activities.

The environmental and social monitoring programme for the construction and operation phases includes the

following main categories of monitoring:

Construction monitoring: Routine construction monitoring including visual inspections and ‘toolbox’

meetings with Project personnel to ensure management measures are employed adequately during

construction works.

Operations monitoring: Routine operations monitoring including visual inspections, ‘toolbox’ meetings

with Project personnel. Monitoring is for operations and process control, cost control, technical efficiency

and safety reasons, as well as for environmental purposes. This will be primarily the responsibility of the

Mine and Process Department personnel.

Discharge (emission) monitoring: The monitoring of potential contaminants discharged or emitted from

the Project to the environment, measured at or near the point of discharge (e.g. discharge from sewage

treatment plant at the accommodation camp).

Ambient monitoring: The monitoring of background conditions and the receiving environments that may

be affected by Project activities. Ambient monitoring will be undertaken in upstream and downstream

surface waters, along with ambient dust and noise monitoring at nearby villages. While operational and

discharge monitoring will determine if environmentally significant releases have occurred, effects on

sensitive receptors within the receiving environment can only be determined by ambient monitoring.

Social monitoring: The monitoring of socio-economic indicators and feedback from Project affected

communities, to identify and quantify the direct and indirect impacts of the Project on the surrounding

community.

A fourth category, investigation monitoring, will also be carried out when necessary, to determine the

occurrence, nature and extent of impacts following an environmental incident (oil leakage, etc.) from the Project,

or to verify/refute third-party claims of environmental / social impact.

During the closure phase, post-closure monitoring will be undertaken to assess progress in achieving closure

completion criteria as specified in the Rehabilitation and Conceptual Mine Closure Plan (Volume E).

All relevant employees involved in monitoring activities (particularly for field monitoring) will be given appropriate

training, where required, by a competent person in the use of:

Monitoring techniques, including: use, calibration and maintenance of field monitoring equipment,

sample collection, labelling and transport;

Review and interpretation of field and laboratory monitoring results; and

Record keeping and reporting procedures, including using standard forms and databases.

Relevant environmental and social monitoring programmes summarised for each Project component are provided

in Chapters 4 – 16, respectively. These monitoring programmes will be revised as appropriate when Project

activities or conditions change significantly.

3.5 Reporting Systems

3.5.1 Data Management

The Company will establish relevant Project environmental management documentation on a web-based platform

readily accessible to employees, contractors and consultants. Key documents for inclusion are the Project ESIA

and ESMMP, associated management plans, CEMP and Standard Operating Procedures (SOPs), registers, forms,

and relevant legislation, guidelines and discharge standards.

Page 65: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 50

In addition, computer based databases will be developed and maintained by the Company to capture and analyse

Project related information collected from the environmental and social monitoring programmes, including:

Environmental management databases comprising the following information:

» Relevant legislation, regulations and guidelines for Project compliance as well as the Company’s

progress in meeting its obligations and environmental and social commitments;

» Field sampling information, including monitoring locations, description and map reference;

sampling frequency, date and time; measurement parameters and unit of measure; monitoring

results and comparison with relevant guidelines and standards; and quality assurance / quality

control information;

» Non-compliances and reported incidents/issues with corrective action required and

implementation data, and outcome of corrective actions;

» Site water balance, consumption and remaining water storage capacity;

» Waste inventory, including the quantities, locations and types of materials (e.g. hazardous

wastes and non-hazardous waste) for environmental management and rehabilitation/disposal

purposes;

» Hazardous materials and dangerous goods inventory, including type, source, quantity, storage

location and physical state of stored materials, relevant Material Safety Data Sheets (MSDS), and

transport records);

» Cultural heritage register;

» Contaminated soil and spill inventory;

» Nursery inventory, including the number and species of seedlings available for revegetation;

» Soil stockpile inventory, including location of temporary and long-term stockpiles and

approximate volume of material;

» Project workforce induction and training records.

Stakeholder management databases to document information on:

» Information obtained from Project stakeholder engagement activities;

» Contact details of Project affected people and other stakeholders;

» Logged community complaints and grievances through the Project grievance management

process;

» Outcome of investigations and agreed outcomes/actions with affected parties;

» Requests for community support and funding;

» Compensation and resettlement information for each Project affected person.

Supporting forms and templates used to capture relevant information for database recording will be prepared to

ensure data is captured consistently, accurately, and meaningfully.

3.5.2 Project Reporting Commitments

The Company commits to employing the following environmental and social reporting systems for the Mako Gold

Project:

Quarterly reporting; and

Annual reporting.

These are further discussed in the following subsections. In addition, significant results from the environmental

and social monitoring programme may be reported at weekly and monthly management meetings, where

required.

Page 66: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 51

Quarterly Reporting

The Company will prepare a quarterly operations report to summarise its environmental and social performance

and significant activities, incidents and event for that period. The report will include:

Brief presentation of the Company environmental and social management systems;

Discussion of the Company environmental and social management and monitoring programmes,

Discussion of ongoing Environmental and Social Investment Programme;

Discussion of environmental and social performance relative to commitments and guidelines against

continuous improvement targets and KPIs (with opportunities for improvement identified), non-

compliance issues and corrective actions (or lack thereof);

Progress against planned tasks and key highlights (e.g. targets achieved, preventative measures

implemented or processes changed);

Any significant incidents that have occurred including cause of incident and corrective actions; and

Results of ongoing stakeholder engagement;

A summary of water quality monitoring data; and

Any significant grievances.

Quarterly reporting will commence immediately following receipt of the Mining Concession and will continue

through construction, operations and post-closure phases. The report will be submitted to the following

Senegalese authorities on a quarterly basis:

DMG, Dakar and Kedougou;

DPN, Dakar and Kedougou;

DEEC, Dakar;

DGPRE, Dakar;

PNNK Conservateur, Kedougou; DREEC, Kedougou;

Governor, Kedougou; and

Prefect and Sub-prefect.

Annual Reporting

MEC will prepare an Annual Sustainability Report to summarise business and environmental and social

performance for each calendar year (either integrated or as a standalone report). The report will include:

Collation and evaluation of quarterly reports;

Detailed discussion of performance relative to licensing commitments with focus on:

» Longer lead indicators;

» Improvement projects; and

» Overview of significant findings of audits and facility inspections.

The Global Reporting Initiative (GRI) Sustainability Reporting Guidelines will be used to guide the preparation of

the report to the extent possible. The Annual Sustainability Report will be submitted to the Board of Directors,

made available on the company website, and sent to relevant authorities (same as for the quarterly report) as part

of the annual reporting commitments.

If required, the Project ESMMP will be updated according to the recommended improvements identified in the

Annual Sustainability Report.

Page 67: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 52

3.5.3 Incident and Project Grievances Reporting

An incident is any event that impacts on, or may potentially impact on the safety, health, environment or

community, or any activity resulting in regulatory non-compliance or breach of company policies, standards or

commitments. Project grievances include any complaints or disputes raised by local communities regarding

Project activities.

To assist with the management and reporting of environmental and community incidents, the Company will utilise

a computer-based event management system (e.g. INX InControl). These systems are designed for the efficient

and effective management and reporting of environmental and social-related incidents. The system will also allow

a reporting scheme that includes:

Description of the incident and its causes;

Risk rating of the incident;

Description of corrective and preventative actions;

Description of repairs, clean-up or other remedial measures; and

Actual or estimated costs of repair, clean-up or other remedial measures.

The following situations will constitute an incident:

Injury or property damage;

Near miss or hazard;

Cyanide and other chemical spills;

Spills of fuel or oil outside of primary containment areas greater than 50 L (environment incident);

Non-contained fires within operational areas;

Uncontrolled gas emissions;

Biodiversity incidents - e.g. uncontrolled access within exclusion zones, injured or dead animals within the

PDA; and

Community incidents - primarily related to community grievances, uncontrolled access within exclusion

zones.

Incidents will be classified according to their actual and potential safety, environmental or social impact using a

standard consequence matrix to ensure consistency. Incidents and significant near misses will be reported to the

Company’s OHS&E Manager within 24 hours of the occurrence of the incident, and presented at the first

management meeting following the incident, unless the severity of the incident (dependent on the risk ranking of

the event) requires immediate notification.

The Company will develop a comprehensive grievance management system. The system will be developed in

consultation with a multi-stakeholder forum. All logged community grievances filed will be recorded and

addressed at management meetings and summaries of grievance-related information will be prepared on a

regular basis for public disclosure.

More information on incident response procedures are provided in Section 3.7, Emergency Response.

3.6 Auditing and Facility Inspections

Regular audits of the Project ESMMP and associated management systems will be undertaken internally and

externally. The audits will assess:

Adequacy of the ESMMP and associated plans with respect to the scale and nature of anticipated impacts

and current development stage of the Project;

Workforce awareness, competence and compliance with the ESMMP and associated plans and procedures;

Page 68: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 53

Performance of managers and operators in implementing, maintaining and enforcing the ESMMP and

associated plans; and

Suitability of allocated resources, equipment and budget for implementation of the ESMMP.

All audit recommendations will be discussed with the relevant departmental managers, including the Operations

Manager, OHS&E Manager and Security Manager, where appropriate. Corrective actions will be documented and

progress towards resolution reported.

Independent external audits will be conducted during the construction phase and on an annual basis for the first

two years of operation. The frequency of subsequent operational audits will be based on the recommendations

from the initial audits. As part of the audit of the ESMMP, an independent external audit of the RCMCP (Volume E)

will also be conducted as key operational and closure milestones are reached. Changes to the RCMCP and the cost

provisions will incorporate any significant changes for the Project, and be reviewed and adjusted every three years.

These changes will be reported within the Annual Sustainability Report.

In addition, the Environment Department will undertake a site inspection of all Project facilities on a routine basis

using a visual inspection form to record observations onsite. The frequency of inspection will be informed by risk

but typically on a monthly basis. KPIs will be developed to enable environmental performance to be assessed

objectively and quantitatively across the operation.

If required, independent external audit reports will be submitted to the Ministry of Environment and Sustainable

Development (Ministère de l’Environnement et du Développement Durable) via the DEEC, as well as relevant

authorities in the Kedougou Region (including DREEC).

3.7 Emergency Preparedness and Response

3.7.1 Assessment of Risk and Priority

Where an event takes place that impacts on or may potentially impact on the environment, or triggers the specific

conditions or limitations of a license or permit to be exceeded, the event is classified as an environmental incident.

The following situations are environmental incidents which require an emergency response for the Project:

All hazardous chemical spills;

Uncontrolled release from TMF;

Breach of WSD;

All spills of fuel or oil greater than 500 litres within workshop areas and pits;

All spills of fuel or oil outside of primary containment areas greater than 500 litres;

All non-contained fires within operational areas; and

All uncontrolled gas emissions.

Emergency response to an incident prioritises actions undertaken according to the following sequence:

1. Protection and rescue of human life;

2. Minimisation of the area impacted by the incident;

3. Protection of the environment and property;

4. Rendering the area safe in which the emergency has occurred;

5. Restoration of all disrupted services; and

Decontamination and rehabilitation of the incident scene and surrounding area (if applicable).The Company will

undertake routine environmental and social risk assessments on a regular basis to review potential emergency

situations that may arise from the Project. The methodology to be used for the periodic risk assessments will be

consistent with that outlined in the ESIA and below.

Page 69: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 54

Depending upon the severity of an environmental incident, emergency response may also involve using or

notifying external agencies and groups, including the police, ambulances and medical clinics, government

authorities, and nominated representatives within the local community.

3.7.2 Emergency Preparedness and Response Planning

A Risk Assessment established for the Mako Gold Project based on the guidelines of the ‘Risk Assessment Guide’

published by DEEC (2007) is presented in Volume B of the ESIA. The Project risk assessment will be reviewed on an

annual basis to identify potential environmental emergency situations that may arise.

The risk assessment will form the basis for the preparation of Emergency Preparedness and Response Plans.

Project specific plans will be developed prior to construction and updated prior to the start of operations and will

include a POI in line with Senegalese guidelines and a Cyanide Spill Contingency Plan, and appropriate spill

prevention and response procedures in line with industry best practice, IFC General EHS Guidelines, and the ICMI

Cyanide Code. Key elements of the EPRP will include:

Emergency response procedures:

» Informing the public and emergency response agencies;

» Taking emergency response actions; and

» Reviewing and updating the emergency response plans to reflect changes, and ensuring that employees

are informed of such changes.

Communication procedure;

Functions and responsibilities;

Evacuation and shutdown procedures;

Risk management;

Emergency response equipment – procedures should be prepared for using, inspecting, testing and

maintaining the emergency response equipment; and

Emergency Response Training – employees and contractors should be trained on emergency response

procedures.

3.7.3 Spill management

Spills may pose environmental risk depending on the chemical constituents of the spill, the size of the spill and the

location of the spill. Spill management broadly covers the management of a range of liquids including fuel, oil,

process water, wastewater and chemical reagents. Spill ratings definitions fall within the following categories:

Contained within primary protection system (i.e. spills contained within first bund);

Contained within secondary protection area (i.e. spills contained by second bund or drainage control);

Contained within operational area (i.e. spills that occur away from fixed spill containment structures such as

bunds but within the operational area. Examples include the haul road and pit);

Contained within non-operational area (i.e. spills that occur away from fixed spill containment structures

such as bunds but not within the normal operational areas);

Off-site spill (i.e. spills that originate from activities not within the Project area. Example includes container

transport to site); and

Non-compliance discharge (i.e. all spills that originate from within the Project Area and escape this area.

Examples include spills that affect the river environment or flow down creeks beyond the Project Area).

Response to spills will be further specified in the Emergency Preparedness and Response Plans for the Project (to be

developed).

Page 70: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 55

3.8 Continuous Improvement

Continuous improvement of various management systems in place will be an ongoing effort to ensure the Project

is implemented appropriately and effectively. These efforts can seek ‘incremental’ improvement over time or

‘breakthrough’ improvement all at once.

Continuous improvement of social, environment, and health, safety and security matters associated with the

Project will be managed by the Company’s Environment Department and be based the ‘Plan-Do-Check-Act’ model

(Figure 3-2). The model broadly follows an iterative process for continuous improvement as follows:

Plan: Identify an opportunity and plan for change.

Do: Implement the change on a small scale.

Check: Use data to analyse the results of the change and determine whether it made a difference.

Act: If the change was successful, implement it on a wider scale and continuously assess your results. If the

change did not work, begin the cycle again.

Figure 3-2 Plan-do-check-act cycle

The Environment Department will develop a continual improvement plan which lists identified information gaps

and non-conformances as well as recommended improvement actions including estimated timing and cost for trial

and implementation. Each item will be prioritised according to their level of risk rating and assigned to a

responsible person for implementing and reviewing corrective actions within an agreed timeframe. Key

performance indicators (KPIs) will be developed following the SMART principles of continual improvement plans,

which are “Specific, Measurable, Achievable, Realistic and Timely”. KPIs will be reviewed and adapted as the

Project progresses.

Page 71: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 56

4 PROJECT DEVELOPMENT AREA

4.1 Objectives

The Company has developed a ‘Project Development Area’ (PDA) for the Mako Gold Project (refer to Figure 1-1)

covering approximately 541 ha of the 7,700 ha proposed Mako Mining Concession, to protect the health and safety

of communities and Project personnel and to minimise the area of potential environmental and social impacts.

The Company, with the assistance of applicable government authorities, will restrict non-Project related building

within the PDA and will restrict access during various activities that are considered hazardous to those in proximity

to the work (i.e. blasting).

4.2 Context

The PDA is a community health and safety initiative to avoid serious hazards (e.g. flyrock) and to minimise

nuisance level impacts (e.g. noise, dust, vibration, etc.). The Company, via stakeholder consultation with

applicable government authorities and communities, will restrict access to buffer areas around Project facilities

(Figure 1-1) during construction, operations, and decommissioning to minimise potential health and safety risks.

Government enforcement of the PDA will increase the area of Project-associated temporary impacts via access

restriction but will not increase the area of physical impacts from Project implementation.

Physical impacts for the Project Footprint (i.e. Project components) and management, mitigation, monitoring and

reporting for those impacts are discussed below in subsequent sections. This section considers the potential

effects of PDA establishment and management required to mitigate the potential impacts.

The general public will not be able to enter the PDA for safety and security reasons. Additional PDA access

restriction areas will include:

Flyrock Safety Exclusion Zone: Minimum 500 m exclusion zone around the perimeter of the Mine Pit,

which encompasses the majority of Project components (i.e. Badalla Valley components).

Accommodation Camp Restriction Zone: Minimum 50 m restriction zone around the perimeter of the

accommodation camp. Community structures (e.g. food and general goods stalls) will be prohibited from

establishment within this boundary.

Project component buffer zones: Project components that exist outside of the PDA (e.g. Water Storage

Dam) will have 30 m exclusion zones whereby installation of community structures will be prohibited.

Access Road buffer zones: Roads constructed for the Project will have a 30 m exclusion zone, whereby

installation of community structures will be prohibited during construction and operations.

4.2.1 Pre-construction and Construction Phase

The PDA area will be greatest during pre-construction and construction, as blasting activities will occur in

association with road construction (as opposed to only the Mine Pit during operations). PDA enforcement during

this phase may impact communities by restricting or prohibiting access to:

Agricultural lands and livestock grazing areas;

Artisanal mining areas; and

Areas currently utilised for timber collection and non-timber forest product (NTFP).

4.2.2 Operations Phase

The PDA area will remain the same throughout Project operations as blasting will be confined to the Mine Pit.

Potential impacts will be the same as for construction, whereby community access to agricultural areas, livestock

Page 72: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 57

grazing areas, artisanal mining areas, timber and NTFP collection, and current hunting / fishing sites may be

prohibited.

4.2.3 Decommissioning and Closure Phase

The PDA will be eliminated following Project decommissioning and will not be enforced following Project closure.

Former community agricultural areas, livestock grazing areas, artisanal mining areas etc., will be returned to

previous landholders, although it may not be feasible to use certain areas for livelihood purposes (e.g. WRD site).

4.3 Management and Mitigation Measures

The Project layout has been designed to minimise permanent impacts on settlement areas and existing

agricultural land and the PDA minimised to the extent practicable to provide for safety of local residents and the

workforce. In addition, the Company has committed to implementing the following mitigation and management

measures to minimise the impact of the PDA on land users:

The Company will undertake a comprehensive land and asset survey after finalising infrastructure sites, and

identify the ownership of any productive land that will be temporarily or permanently lost to the Project

PDA at the household level;

Land for inclusion in the PDA will be clearly defined and marked to avoid unnecessary exclusion;

The Company will compensate for any productive land and community land assets that will be temporarily

or permanently lost to the PDA (refer to the Livelihood Restoration Plan, Appendix D);

The Company will provide appropriate compensation for any loss of access to productive land and will

ensure continued access to productive areas located outside the PDA. Where practical, alternative access

routes will be provided; and

The Company will undertake regular public consultation to ensure the effectiveness of management and

mitigation strategies.

4.3.1 Pre-construction and Construction Phase

Fly Rock Exclusion from Blasting

The PDA will be developed to ensure health and safety of local residents and the Project workforce from blasting

during construction by ensuring a 500 m exclusion zone (minimum) is enforced from blasting activities. This will

require careful consideration during construction as blasting sites will vary according to Project need. Blasting will

potentially be required along various locations for the construction of the Main Access Road.

The Company will develop a Blast Management Plan that will incorporate the following (at a minimum):

Methods for denying access to the 500 m radius exclusion zone (e.g. manning road access points,

conducting surveys to ensure people are outside of the PDA, etc.);

Blasting conducted a specified times during the day (during daylight hours), with at least 24 hour notice

given to local villages;

Blast times and locations will be posted on boards in local villages;

Flyrock to be visually monitored to confirm that the exclusion zone is sufficient to protect sensitive

receptors (biological and social);

Engaging a blast contractor with relevant expertise and experience; and

Training Project staff on fly rock safety and conduct a public education programme regarding community

safety issues associated with blasting.

Page 73: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 58

Compensation for inaccessible lands

The Company has developed a LRP (Appendix D) that includes restoration measures for land / activities lost or

disrupted via development of the PDA. This is discussed in Chapter 12.

Community Infrastructure Development

Development of community infrastructure within 50 m of Project components and 30 m of Project road

infrastructure will be prohibited to reduce the likelihood for damage to village structures in proximity to

construction.

Access

The Company will ensure continued access to resources outside of the PDA through staged upgrades to road

infrastructure that do not prohibit access to areas outside the PDA.

Grievance Mechanism

The Project Grievance Mechanism will provide for continued stakeholder consultation, allowing local residents to

voice concerns regarding losses of access via PDA development during construction and appropriate

compensation, if necessary.

4.3.2 Operations Phase

The PDA will be more clearly defined during Project operations as blasting will be limited to the Mako Pit (Figure 1-

1). Mitigation measures employed for the PDA will be the same as for construction, including:

Enforcement of the fly rock exclusion zone for blasting in the Mine Pit (and all associated measures listed

above and provided in the Blast Management Plan);

Existing access roads / paths to resources outside of the PDA will be ensured; and

Stakeholder consultation will continue throughout operations, with the Grievance Mechanism provided to

ensure adequate response to community complaints / issues.

4.3.3 Decommissioning and Closure Phase

Stakeholder consultation will continue during decommissioning and post-closure to ensure that areas within the

PDA that were temporarily restricted from utilisation are restored, where feasible, to provide a similar value to the

community as per before PDA implementation.

Page 74: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 59

4.4 Monitoring Measures

Table 4-1 presents key monitoring measures related to the PDA. These will be incorporated into the detailed

monitoring programs prepared by the Company and its contractors for all phases of the Mako Gold Project.

Relevant guidelines and standards applicable to the Project are specified in Section 2.4 and in the Registers of

Environmental and Social Management and Monitoring Commitments in Chapter 18 of this Plan.

Table 4-1 Register of Environmental Monitoring Measures – Project Development Area

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Fly Rock

Blast exclusion zone Construction,

Operations

Visual

observation for

unauthorised

people within

the PDA

Project

compliance

Zero incident

record for

blasts

Prior to each

blasting

event

Within 500 m of

any blast area

At key access

points (roads /

paths) near blast

sites

Communication and

notification

Construction,

Operations

Community

consultation

Grievance

register

Logged

complaints and

concerns

As required /

ongoing

Surrounding

communities

Blast

impact

Routine monitoring

of noise, airblast,

and ground vibration

impacts

Refer to SOP08: Blast Management (Appendix A) and Tables 2-8 to 2-10 for applicable

blast criteria.

Air Quality Air quality discharge

monitoring

Refer to SOP04: Emission and Dust Control (Appendix A), Table 2-4 for applicable air

quality criteria (Section 2.4), and Figure A1 (Appendix C) for monitoring sites.

Noise Noise emission

monitoring

Refer to SOP05: Noise and Vibration Management (Appendix A), Table 2-4 for applicable

noise criteria (Section 2.4), and Figure A1 (Appendix C) for monitoring sites.

Page 75: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 60

5 OPEN PIT, MINING AND WASTE ROCK

5.1 Objectives

Key management objectives associated with the Mako Gold Project open pit, mining and waste rock disposal

include:

Design, construction and operation of the Mine Pit, Ore Stockpiles and WRD facilities to ensure adequate

operational safety and compliance with relevant legislative requirements and environmental / social

commitments;

Provision of appropriate measures to manage or mitigate potential environmental and social impacts from

mining, ore stockpiling and waste rock disposal activities over the Project life; and

Development and implementation of an appropriate mine closure and rehabilitation plan that successfully

meets environmental and social permitting requirements, regulatory requirements, and is in-line with

community expectations.

5.2 Context

Anticipated environmental and social impacts from the mine site will vary according to the stage of mine

development. Site preparation for the Mine Pit and ancillary facilities will require land clearing and earthmoving

during construction and ongoing development of the open pit, pit void and WRD throughout the operations phase.

As such, the majority of potential impacts will occur during the operations phase. Mine closure and rehabilitation

may also pose a number of significant issues if not appropriately managed.

Key environmental and social sensitivities in proximity to the mining and waste rock disposal operation include: (i)

the protected PNNK (located approximately 2 km west of the Pit); (ii) local populations of IUCN listed species

found within and around the PDA including the West African chimpanzee (Pan troglodytes, Endangered); (iii) local

residential areas within 5 km of the PDA (in particular Tambanoumouya and Linguekoto); (iv) and downstream

water resources and aquatic habitat including Badalla Creek and the Gambia River.

Chapters 9-12 of the ESIA (Volume A) provide a detailed discussion of the potential impacts from open pit, mining

and waste rock disposal during all phases of the Project. The primary issues and impacts are summarised below.

5.2.1 Pre-construction and Construction Phase

Site preparation activities for the Mine Pit and WRD will require significant land clearance, earthworks, and soil

stockpiling for subsequent reuse in revegetation efforts (e.g. topsoil) and fill material (e.g. rock, subsoil) for various

Project components (e.g. TMF and WSD dam material, road fill, etc.), depending on suitability following detailed

geotechnical investigations. The primary direct impacts will include:

Petowal Mine Pit: The 35.4 ha Pit surface will be stripped of topsoil, where feasible. It is anticipated that

subsoil will also be excavated and transported for construction fill.

Waste Rock Dump: Topsoil will be stripped from the 77.3 ha WRD footprint, where feasible, to a maximum

depth of 0.5 m, permanently impacting the landform and temporarily impacting the site’s ability to support

native vegetation. In some areas it may not be feasible to clear vegetation or topsoil in advance of rock

disposal.

Potential indirect impacts may include:

Removal of approximately 113 ha of natural vegetation and habitat for terrestrial species (refer to Chapter

10 of the ESIA, Volume A);

Erosion and sedimentation associated with disturbed surfaces (refer to Chapter 9 of the ESIA, Volume A);

Page 76: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 61

Hydrocarbon spillage (refer to Chapter 9 of the ESIA, Volume A);

Soil compaction and erosion (refer to Chapter 9 of the ESIA, Volume A);

Particulate matter (dust) and vehicle exhaust emissions (refer to Chapter 9 of the ESIA, Volume A);

Noise (refer to Chapter 9 of the ESIA, Volume A);

Vibration (refer to Chapter 9 of the ESIA, Volume A); and

Hydrology (refer to Chapter 9 of the ESIA, Volume A).

During construction, surface water from seasonal streams will be diverted around the open pit and WRD footprints

at the onset of site preparations. Impacts are not expected to be significant as surface water will remain within the

Badalla catchment, discharging to Badalla Creek prior to its confluence with the Gambia River.

Potential Air Quality and Noise Issues for Mine Workers

Impacts to workers are expected to be negligible with the implementation of best practice dust and noise control

measures. Worker health and safety will be specifically addressed in the next phase of the Project as part of the

CEMP. Additionally, the Company will prepare an Occupational Health and Safety Plan prior to Project Operations,

which will identify appropriate controls to ensure the health and safety of its workforce during operations (refer

Vol B Hazard Assessment, Section 7).

5.2.2 Operations Phase

Open-pit mining

Development of the Mine Pit will permanently impact 35.4 ha of surface land. A portion of the ridge encompassing

the boundary of the Badalla and Kelendourou catchments will progressively be converted to a pit throughout

operations. Approximately 88.6 Mt of material will be excavated and transported to the ROM Pad / Process Plant,

Ore Stockpile, or WRD during development of the pit.

Excavation of the Petowal deposit may create geotechnical and geochemical instability during operations,

providing the potential for landslips and acid and metalliferous drainage (AMD) / neutral and metalliferous

drainage (NMD) generation and / or sulfate salinity generation within the Mine Pit. Geochemical testwork

conducted for wall rock indicates a very low probability of AMD generation, NMD generation, and sulfate salinity

generation (refer to ESIA Chapter 9).

Potential impacts of the Mine Pit development may include:

Surface and groundwater quality impacts from contaminated mine wastewater containing suspended

sediment, saline water, oils and grease, AMD / NMD, and nutrients (from blast residues) with associated

indirect impacts on downstream biological and community receptors;

Minor air quality impacts, including generation of particulate matter (dust) and diesel fuel combustion

emissions (e.g. SOx, NOx, etc.) potentially affecting local sensitive receptors (e.g. local communities and

PNNK), particularly during the dry season and ‘Harmattan’ wind conditions;

Safety hazards for local communities and the workforce from flyrock (the propulsion of material potentially

resulting from blasting activities); and

Noise and vibration (airblast) impacts from blasting and operating heavy equipment that may exceed

international criteria for noise, creating an intermittent nuisance for local residents in Tambanoumouya,

Linguekoto, Wassadou, Dalakoy and Kerekonko and employees in the Accommodation Camp; as well as

local livestock and terrestrial fauna found in and near the PNNK, particularly in the wet season.

Waste Rock Dump

During operations, approximately 74.6 Mt of waste material/rock will be gradually moved from the Mine Pit to the

WRD, permanently altering the landform. The morphology of a significant portion of the Badalla Creek Valley will

also progressively be transformed to a higher elevation landform throughout this phase.

Page 77: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 62

Deposition of waste rock on the WRD may create geotechnical and geochemical instability during operations,

providing the potential for landslips and AMD / NMD and / or sulfate salinity generation that has the potential to

impact downstream / down gradient surface or groundwater. Geochemical testwork conducted for waste rock

indicates a low probability of AMD generation, NMD generation, and sulfate salinity generation.

Potential impacts from waste rock disposal may include:

Erosion of the landform and suspended sediment transport to local receiving waters (i.e. Badalla Creek and

the Gambia River);

The introduction of hydrocarbons to receiving surface and groundwater from accidental spillage; and

Spread of invasive plant species to the disturbed land surface.

Ore Stockpile

Ore (in excess of that which can be processed immediately) will be stockpiled during operations in the western

footprint of the WRD (refer to Figure 1-1). Waste rock will initially be placed in this area and then lower grade ore

will be progressively stockpiled on the waste rock layer. Construction of the stockpiling area will require clearing

and grubbing, stripping of topsoil, and construction of cut-off drains, temporarily altering the landform for

approximately 6.31 ha of surface land.

The potential geotechnical and geochemical impacts from the ore stockpile is expected be the similar to that of

the WRD and require management strategies to avoid water quality impacts and geotechnical instability.

Dust generated from the mining operation will be low in metals due to the geology of the deposit. Silica and some

fibrous minerals such as actinolite are present within the waste and ore material and may be present in dust at

levels that could potentially affect the health of workers if exposure is high.

5.2.3 Decommissioning and Closure Phase

Key environmental and social issues related to the Mine Pit, WRD, and Ore Stockpile during the decommissioning

and closure phase will be less significant with the implementation of measures detailed in the Rehabilitation and

Conceptual Mine Closure Plan (RCMCP) (Volume E).

Impacts associated with WRD decommissioning will be similar to the pre-construction and construction phase

impacts while the WRD is rehabilitated, potentially including:

Erosion and sedimentation;

Noise; and

Dust emission.

The Mine Pit will remain, and will progressively fill with ground and surface water, permanently transforming the

Wooded Savannah Bamboo mosaic vegetative community to a pit lake.

5.3 Management and Mitigation Measures

5.3.1 Pre-construction and Construction Phase

The Company has minimised the footprints for the Mine Pit, WRD and Ore Stockpile to the extent practicable to

limit the area of impact to productive land. The Company will divert surface water around the pit and WRD

footprints at the onset of site preparations, to minimise erosion and sediment transport.

The Company has developed a series of Standard Operating Procedures (Appendix A) for implementation to avoid,

minimise, or mitigate anticipated impacts associated with land clearance / topsoil removal from the Pit and WRD

footprints. The SOPs provide key management measures for adoption during all phases of the Project to address

primary issues and risks, including:

Impacts from vegetation clearance (refer to SOP09: Land Clearance and Soil Stockpiling);

Page 78: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 63

Erosion and sedimentation associated with disturbed construction surfaces (refer to SOP01: Erosion and

Sediment Control);

Surface water quality and hydrology management (refer to SOP02: Water Quality and Pollution

Management and SOP03: Hydrology and Water Management);

Potential hydrocarbon spillage and handling/storage of hazardous materials and dangerous goods (refer to

SOP07: Hazardous Materials Management); and

Air quality, noise and vibration emissions (refer to SOP04: Emission and Dust Control, and SOP05: Noise

and Vibration Management, respectively).

The Company will prepare an Occupational Health and Safety Plan prior to Project Operations, which will cover

preventative measures for potential impacts on workers from air quality and noise emissions from the Project. As

part of this plan:

Dust and noise levels on site will be routinely monitored and controlled to ensure the operation applies with

applicable standards and workers are not significantly affected by dust and noise exposure;

Occupational health and safety standards for dust and noise will be consistent with international mining

standards and Senegalese legislative requirements;

Staff will be required to wear appropriate personal protective equipment (PPE) to ensure health and safety

risks are minimised;

Training will be provided to staff regarding the use of personal protective equipment (PPE); and

Regular health checks for staff will be conducted.

The Company has developed a separate Biodiversity Action Plan (Volume C) that identifies procedures for the

protection and management of biodiversity during Project construction, operations and closure.

5.3.2 Operations Phase

The exclusion of new settlement construction within the PDA will assist in ensuring that community health and

safety and dust / noise related impacts are adequately minimised for sensitive community receptors. The

Company management and mitigation measures to avoid or minimise potential operations phase impacts are

listed below.

Land and soil management

The Company will progressively rehabilitate the WRD from the bottom up during the Operations Phase. Lifts will

be progressively contoured on the outer WRD face and will be planted with species of native provenance.

Utilisation of erosion control blankets (e.g. Jute netting) and fibre rolls may be used, allowing the WRD batter

slopes to be constructed to 20º slopes. The WRD will be designed with an overall slope angle of 20 degrees for

geotechnical stability and operational safety, and incorporate features to minimise the effect of contaminant

leaching.

Development of the Mine Pit will permanently impact 35.4 ha of surface land. Measures for land acquisition,

management and compensation / restoration are provided in Chapter 11 and described in the Livelihood

Restoration Plan (Volume D).

If the geochemical risk is found to increase during operations, a geochemistry management plan will be developed

to ensure that potential impacts associated with mine material geochemistry post-closure are minimised.

Water management

The mine will function as a ‘zero-discharge’ operation. Surface water will not discharge to receiving waters during

operations, and runoff from the Mine Pit, WRD, Ore Stockpile and TMF will be contained by the TMF embankment

(refer to ESIA, Volume A, Chapter 4). Key measures of the water management system include:

Stormwater management infrastructure has been designed to accommodate peak flows from a 100 year

rainfall event; and

Page 79: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 64

Regular inspection of surface water management features to ensure their efficacy.

Water quality and AMD management

The Company will carefully manage potentially contaminated water from within the Mine Pit and contributing

drainage areas to prevent potential impacts to sensitive receptors downstream.

While the risk for AMD and salinity generation are low, the Company will routinely sample and analyse waste rock

and ore stockpile geochemistry to manage potentially acid forming material in the WRD and Ore Stockpile (i.e. by

encapsulating the material within non-acid forming or potentially acid consuming waste rock material). Ore

stockpiled for the Process Plant will be stockpiled to minimise felsic material surface exposure. Basalt and other

rock material will be placed on the bottom and outer perimeter of the stockpile footprint, where practicable.

The Company will adopt additional surface and groundwater quality management measures for the Pit, WRD, and

Ore Stockpile throughout the operations phase (refer to Chapter 9 of the ESIA, Volume A), including:

Reuse and recycle process water to reduce the requirement for raw water abstraction from the Gambia

River;

Use of erosion and sediment control measures as detailed in SOP01: Erosion and Sediment Control;

WRD to be progressively rehabilitated during operations using contoured batter slopes, native species

planting for groundcover, and erosion control blankets (e.g. Jute netting) and fibre rolls to minimise water

quality issues at the base;

Surface runoff to be diverted around the Project site; and

Adherence to proper handling and storage of hazardous materials onsite in fully bunded, weatherproof

areas, including appropriate emergency response and spill clean-up procedures (refer to relevant measures

specified in SOP07: Hazardous Materials Management).

During Project operations a routine water quality monitoring programme will be conducted of surface, ground and

discharge water. This will include multi-element testing of samples using ICP-MS to fully characterise water

quality.

Mine safety

The Company will conduct regular inspections of the Mine Pit, WRD and Ore Stockpile for structural integrity to

ensure the potential for landslips and other geotechnical and geochemical instability issues are adequately

managed. A safety berm and signage at key locations around the Pit rim perimeter will be installed to prevent falls

into the Pit.

To reduce WRD instability risks, drainage measures will be provided to direct surface water away from the WRD, to

reduce water infiltration and to reduce the level of the phreatic surface that develops. The WRD will be

constructed from the bottom up so that the toe support is provided to the sections of WRD located on steeper and

higher ground. An additional recommendation is that during the initial mining phase a further stability

and deformation investigation analysis is undertaken to refine the WRD stability analysis.

In addition, the Company has incorporated the following safety measures and mechanisms for managing mine

blasts, in addition to those specified in SOP07.21 and 08 (Appendix A):

Provision of 24 hour security guards and restricted access safeguards (e.g. perimeter security fencing and

authorised personnel only) to provide a high level of security for the explosives magazine and Process Plant;

(refer Figure 1-1);

The explosives magazine will comprise two separate containments for the secure storage of (i) high

explosives and (ii) accessories (i.e. initiators). Each containment will be surrounded by an earth barricade;

The magazine will be located a minimum of 800 m buffer distance from human settlement, land use areas,

and/or built structures. (Distance subject to review during detailed design when the quantities of explosive

has been confirmed);

Ammonium Nitrate Fuel Oil (ANFO) will be used as a low cost and high stability blasting agent. It will be

mixed, transported and loaded into blast holes using a specialised truck;

Page 80: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 65

A 500 m blast exclusion zone (minimum) will be enforced for all blasting activities for the Project;

To ensure people are outside the blast exclusion zone, the Company will deploy methods including: sirens,

amplified verbal warnings, the posting of sentries, the closure of access roads and pre-blast surveys; and

Appropriate handling and storage of explosives (refer to SOP07: Hazardous Materials Management) and

established procedures for initiating blasts (refer to SOP08: Blasting Management, Appendix A) will be

followed by appropriately trained staff.

The Company will develop a detailed Blast Management Plan that will further specify blasting procedures, training,

auditing, PPE and other requirements. Drill and blast procedures will be designed by blasting specialists to ensure

the safety of the mine workforce and surrounding local population, the control of flyrock, noise and vibration.

Air quality management

The Company will implement the following management and mitigation measures to minimise impacts to air

quality from Mine Pit and WRD development:

Limitation of clearing to the minimum required area to reduce the potential for dust generation;

Topsoil stripping conducted at times when soil moisture can be expected to be optimal to minimise dust

formation; and

Incorporation of source control procedures provided in SOP04: Emission and Dust Control, where

applicable.

The Company has been monitoring air quality with dust deposition gauges at key locations since mid-2013. The

Company will continue monitoring dust deposition throughout construction and operations. The Company will

consult with local villages and will address potential complaints regarding dust via the Project Grievance

Mechanism.

Noise management

The Company will implement measures documented in SOP05: Noise and Vibration Management and SOP08:

Blasting Management (Appendix A) during the operations, including:

Integration of physical barriers (such as vegetation, soil banks/berms and commercially-available acoustic

shields) with site components (e.g. stockpiles and constructed buildings) to strategically act as noise

barriers for potential sensitive receptors;

Commercial acoustic shielding (typically insulator material panels) placed around noise sources and will

adopt high frequency technology for fans, ducting and electrical systems; and

Vibration-proofing and noise-reduction measures applied for various noise sources within the Mine site,

including treatment measures provided in Table 5-1.

Table 5-1 Mine equipment noise controls

Equipment source Noise treatment measures

Hydraulic excavator Reversing vehicles will be fitted with “smart alarms” rather than tonal reversing horns.

Noise control options such as exhaust and radiator silencers will be fitted to mining equipment.

Limiting the operating hours of equipment during night time

Crawler bull-dozer

Rubber-tired loader

Jaw crusher Vibration insulating base, insulation

The Company will establish a stakeholder consultation programme covering all mine related activities as well as a

Project Grievance Mechanism to record and respond to noise complaints appropriately.

In addition, the Company may consider further noise reduction and mitigation options during the mine

establishment and operations as per the Leading Practice Sustainable Development Program for the Mining Industry:

Airborne Contaminants, Noise & Vibration (Australian Government, 2009), where required, including:

Page 81: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 66

Selecting low noise options;

Providing additional silencing of fixed and mobile site and mine ventilation fans;

Installing acoustic enclosures around site;

Providing bund walls for acoustical screening;

Incorporating buffer zones and landscaped setbacks;

Reducing the maximum instantaneous charge (MIC);

Using the minimum sub-drilling possible;

Using “smart” alarms to minimise complaints regarding mine vehicle reversing alarms; and

Minimising tonal components or impulsive or intermittent characteristics of noise where possible.

Blast, air blast and vibration management

The Company will implement measures specified in SOP08: Blasting Management during the operations,

including:

Use of electronic detonation to significantly reduce vibrations caused by the blast;

No explosive charge per blast hole will exceed the estimated maximum charge weight per delay (i.e. 285

kg);

Only one charge detonated per delay and every charge will be able to break and displace its burden with

reasonable ease;

Inter-row delays that are long enough to give good progressive relief of burden; and

Detonating cord trunklines are used only to fire pre-split blasts and that these trunklines have a core load of

only 5 g/m and are covered by at least 250 mm of sand or fine screenings.

The Company will also inspect and review any reported structure damage after each blast, with immediate

investigation and follow-up control measures implemented, if required.

5.3.3 Decommissioning and Closure Phase

General management measures that will be implemented during the decommissioning and closure phase for the

Mako Gold Project include:

Access to facilities that present safety risks to be removed (e.g. Mine Pit);

All equipment and vehicles to be removed from the site;

All chemicals, fuels and oils to be removed from the PDA, and appropriately disposed;

Buildings and structures to be demolished and the rubble transported to an appropriate disposal area;

Buildings / facilities with significant residual value to the Company may be sold for dismantling, relocation

and/or recycling;

Buried pipelines cleaned, sealed and left in-situ;

Power lines and above ground pipelines removed to an approved disposal area;

Footings / foundations to be removed;

Stormwater management systems (i.e. drainage channel and sediment pond below the TMF) will be

retained until they are no longer needed;

Design and implementation of a contaminated land survey conducted to identify any such areas and

appropriate clean up measures;

Compacted areas, including roads and building footprints to ripped and graded to blend into surrounding

contours and to ensure drainage patterns are similar to pre-mining conditions;

Page 82: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 67

Engineered erosion control measures to be established where needed;

All seeding and planting to be sourced from native stock of local provenance; and

Fencing to be removed, unless retained for public and livestock safety reasons.

The Company will implement the following specific decommissioning and closure strategies for the Mine Pit and

WRD (refer to the RMCP, Volume E):

Mine Pit: Rehabilitation and revegetation of Pit margins and temporary equipment access roads. A safety

berm will be constructed around the Pit void for public safety. Targeted species may be planted on pit

benches, pending the suitability of the material to support plant life. The 35.4 ha (surface area) Pit void will

be a permanent feature in the landscape.

WRD: The WRD will be graded to contours that align with adjacent topography. Where possible, the WRD

surface will be progressively revegetated to establish a Shrub savannah and grassland vegetative

community comprised of native species of local provenance. Rock-lined drains will be constructed, where

required, to ensure excess run-off is controlled and directed down to sediment traps or to the TMF.

In addition, the following management and mitigation measures will be undertaken during decommissioning and

closure to ensure the facilities fulfil closure success criteria:

Water quality in the Pit void monitored to ensure potential discharge will meet applicable discharge

standards and Badalla Creek / Gambia River surface water will meet applicable ambient water quality

guidelines;

Surface water quality monitored at the downstream compliance points (Badalla Creek and Gambia River) to

ensure applicable discharge and ambient water quality guidelines are met;

Analysis of TMF supernatant water wi to determine whether treatment is required before establishment of

a permanent discharge channel. Suitable remedial measures, frequency of treatment, and ongoing

requirements will be determined, if post-closure treatment is required;

Monitoring of planted / seeded vegetation for successful establishment. These will be maintained where

necessary;

Rehabilitated landforms monitored for maintenance requirements, particularly with respect to erosion; and

Monitoring of biodiversity as per the Project Biodiversity Action Plan (Volume C) to assess the effectiveness

of mitigation measures for rehabilitation. Monitoring will be undertaken in both dry and wet seasons to

allow comparisons to be made between seasons over time and in key areas such as chimpanzee nesting

habitat.

5.4 Monitoring Measures

Table 5-2 presents key monitoring measures related to the open pit and waste rock management. These measures

will be incorporated into the detailed monitoring programs of contractors (as applicable) for construction,

operation and decommissioning/closure of the Mako Gold Project.

Relevant guidelines and standards applicable to the Project are specified in Section 2.4 and the Registers of

Environmental and Social Management and Monitoring Commitments in Chapter 18 of this Plan.

Table 5-2 Register of Environmental Monitoring Measures – Open Pit, Mining and Waste Rock

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Water

quality

Surface and

groundwater

quality

monitoring

Pre-construction,

Construction

Visual checks for

sedimentation, oils

and grease (refer

to SOP2.10)

Key parameters:

Turbidity, TSS, DO,

temperature, electrical

conductivity (EC), and

pH (refer to SOP02.9)

Threshold limits

Weekly

Discharge

points (refer

to monitoring

sites shown

in Figure A2,

Appendix C)

Page 83: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 68

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

provided in Table 2-5

to Table 2-7

Operations,

Decommissioning

Refer to

SOP02.13 and

SOP02.16

Key parameters:

Cyanide (including

free cyanide, weak

acid dissociable, and

total), salinity, total and

dissolved metals (full

suite), and nutrients.

Field parameters (e.g.

pH, EC, ORP, DO,

Temp. etc.)

Threshold limits

provided in Table 2-5

to Table 2-7

Monthly for

Operations

Once-off for

Decommissi

oning

Pit sumps

and Mine

water (refer

to monitoring

sites show in

Figure A2,

Appendix C)

Blast

impact

Mine blast

monitoring

Construction,

Operations

Routine monitoring

of noise, airblast,

ground vibration,

and flyrock

impacts (refer to

SOP08.12)

Blast analysis and

audits

Noise, airblast, ground

vibration, and flyrock

parameters

Threshold limits

provided in Table 2-4

to Table 2-10

Periodic

(e.g. when

there is a

change of

blast

location)

PDA (within

500 m of pit

or other blast

areas)

Blast

exclusion

zone

Construction,

Operations

Visual observation

for unauthorised

people within the

PDA

Project compliance

Zero incident record

for blasts

Prior to

blasting

Air quality Dust

monitoring

Construction,

Operations

Visual check (refer

to SOP04.16)

Excessive dust levels

(refer to Table 2-4) Daily

Near the

Mine Pit

(refer to

monitoring

sites shown

in Figure A1,

Appendix C)

Construction,

Operations

Monitoring using

dust gauges (refer

to SOP04.16)

Dust deposition rate

(refer to Table 2-4) Monthly

Mine

safety

Monitor

structural

instability (for

possible Pit

edge

subsidence

or Pit wall

collapse)

Operations

Conduct regular

inspection of Mine

pit edge,

maintaining a

safety berm and

signage around Pit

rim.

Project compliance

Verification of security

practices

Verification of safety

controls and

inspection records

Daily Mine Pit

Biodiversit

y

Threatened

species and

habitat (e.g.

nest sites)

Refer to Chapter

16 (Biodiversity

Management) and

Biodiversity Action

Plan (Volume C).

Camera trapping

and transect

monitoring

Reportable

incidents involving

Refer to Chapter 16 (Biodiversity Management) and

Biodiversity Action Plan (Volume C) for details on

monitoring parameters, frequency and sites.

Page 84: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 69

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

wildlife

Page 85: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 70

6 MINERAL PROCESSING AND TAILINGS MANAGEMENT

6.1 Objectives

Key management objectives related to minerals processing and tailings management for the Mako Gold Project

will include:

Avoiding impacts to surface and groundwater quality and associated impacts to the receiving environment

and beneficial uses of the resource;

Ensuring the Process Plant and Tailings Management Facility (TMF) are constructed for ‘no discharge’ of

surface water to the receiving environment (as designed);

Ensuring that post-closure water quality for surface and groundwater discharge from the rehabilitated TMF

is compliant with applicable guidelines, legislative and licensing requirements; and

Minimising any long-term liabilities in relation to rehabilitating the Process Plant and TMF footprints by

creating natural ecosystems post-closure.

6.2 Context

The major issues associated with the construction, operations and decommissioning/closure of the Process Plant

and the TMF for the Mako Gold Project are summarised below. Key environmental sensitivities associated with the

TMF and Process Plant include Badalla Creek and the Gambia River, and proximity to local populations of

threatened wildlife.

6.2.1 Pre-construction and Construction Phase

While the primary potential impacts from mineral processing and TMF development will occur during operations,

significant construction impacts of the Process Plant and TMF embankment include:

Water quality impacts, including erosion and sedimentation and inadvertent hydrocarbons discharge from

construction vehicles and associated impacts to the receiving environment (including downstream water

use, and aquatic / terrestrial biodiversity values);

Air quality impacts, including dust and exhaust emissions from land clearing, general construction

activities, and Project traffic potentially affecting local communities;

Noise generation and associated nuisance to local communities and terrestrial fauna; and

General and hazardous waste generation, including inert construction material, domestic rubbish, metal

scrap, empty containers or packaging for general wastes; and hydrocarbons.

The TMF embankment will be constructed to a height of 22 m during Stage 1 and will be incrementally increased to

a final height of 48 m during mine operations. Construction of the dam will initially impact 31 ha of land for the

dam footprint (increasing to 67 ha for the final TMF embankment) and will require a significant volume of suitable

engineering material (clay rich material). This material may be sourced from the Mine Pit overburden or WRD

footprint, however it may require excavation from local borrow areas which would expand the area of physical

impact for TMF construction (refer to Chapter 9, Borrow Areas and Quarries).

Construction of the Process Plant and ROM Pad will require clearing and grubbing; stripping of topsoil for post-

closure rehabilitation; and import of foundation material (e.g. sand and gravel), temporarily converting 15.84 ha

(9.27 ha for the Process Plant inclusive of the Power Station, and 6.57 ha for the ROM Pad) of Wooded Savannah

to a built environment.

Page 86: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 71

6.2.2 Operations Phase

Process Plant

A number of key hazardous substances and reagents will be stored, handled and disposed of during Project

operations (refer to Table 6-1).

Table 6-1 Overview of hazardous substances for the Project

Reagent Type Use Form of transport Estimated usage

Copper Sulphate 1.1 t bags Used in Cyanide Detoxification

Circuit.

Delivered by truck in crystal

form on pallet. 540 kg/ day

Hydrochloric Acid 1000 L isotainers

at 33% m/v

Used in washing of carbon in

acid wash tank. Minor

quantities also used in water

treatment.

Delivered by truck. 413 L/ day

Sodium Cyanide

(NaCN)

Briquettes in 1 t

bulk bags,

approximately

98% (± 1%) NaCN

Reagent for extracting gold

from the ore. NaCN will be the

main reagent used for the

Project.

Delivered by truck. 1,296 kg/day

Sodium

Hydroxide

(Caustic Soda)

Bulk 1 t bags

Elution of gold from carbon.

Minor quantities also to be

used for water treatment.

Delivered by truck as crystals. 909 kg/ day

Sodium

Metabisulphite 1.1 kg bulk bag

Used in Cyanide Detoxification

Circuit. Delivered by truck as powder. 1,917 kg/ day

Sulphuric Acid 1 m3 isotainers Standby reagents in the

Cyanide Detoxification Circuit. Delivered by truck. 413 L/ day

Gold Room

Chemicals (for

smelting)

Nitre, Biocide,

Borax, Silica, Soda

Ash, Antiscalant –

all in 25 kg bags

Used in smelting. Delivered by truck. Only minor

quantities required

Diesel

Bulk deliveries as

part of general

supply

Used by Mine, Project vehicles

and site power generation.

Stored onsite in storage tanks

and supplier operated fuel

depot.

Delivered in bulk tankers.

24,000 m3 diesel

per annum (6,000

m3 for the mine

and 18,000 m3 for

the Power Station)

Ammonium

nitrate (for

blasting)

Not available For blasting. Not available. 0.8 kg/t

The primary environmental and social risks associated with operations of the Process Plant include:

The transport, storage, handling and use of hazardous and non-hazardous materials at the Process Plant

provide a potential source for contamination of surface or groundwater within the Badalla catchment. If

released, some of these materials are significant pollutants (e.g. cyanide), posing a risk to local communities

and regional biodiversity;

Fire, explosion or other major incident in the Process Plant which could result in mortality, serious injury or

significant environmental harm to the local and regional environment;

Dust and other air pollutants (e.g. CO, CO2, SO2, O3, VOCs, Dust) from the crushing and screening area and

in stack emissions;

Stormwater runoff from the Process Plant footprint may contain elevated levels of sediment and / or

hydrocarbons;

Page 87: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 72

Elevated continuous noise above the current background levels from the 24 hour operations of the Process

Plant; and

Localised light spillage and visual amenity impacts from the Process Plant.

Additional potential impacts from Process Plant operations (e.g. localised vibration) may occur during Process

Plant operations, with associated management measures provided in Appendix A.

Tailings Management Facility

During operations, tailings discharged from the Process Plant will be transported to the TMF by pipeline and sub-

aerially discharged onto the beach from an open end pipe or spigot. The TMF is designed and will be managed so

that it will not discharge to receiving waters during operations (zero discharge Project), therefore impacts to

downstream surface waters are not anticipated.

Tailings discharged to the TMF will likely be alkaline and may contain varying concentrations of cyanide, salinity,

heavy metals (e.g. copper, arsenic, cadmium, manganese and zinc) and nutrients (breakdown products of cyanide).

The TMF reservoir water, though within ICMI guidelines for cyanide concentration, will provide a potential source

for contamination of receiving waters via seepage through the TMF embankment and / or direct migration to

groundwater / aquifers. In addition, the supernatant water may be deleterious for local birds, if utilised for

drinking water.

Consequently, during Project operations, a routine water quality monitoring programme will be conducted of

surface, ground and discharge to ensure that contaminants are not migrating to groundwater aquifers and

potentially surface waters via springs (refer to below). In addition, the geotechnical stability of the embankment

and the water volume of the reservoir will be monitored to ensure failure or overtopping of the dam wall does not

occur. The facility has been designed to avoid such an event. Nevertheless, such an event possesses the greatest

potential risk to receiving waters and associated receptors.

6.2.3 Decommissioning and Closure Phase

The TMF will have an estimated water volume of between 15,000 m3 and 1,116,000 m

3 within the supernatant

pond, depending on the timing of closure with respect to the wet season, during the final 12 months of operation

(Knight Piesold, 2015c). Upon Project decommissioning / closure, the TMF will discharge from a constructed

spillway into Badalla Creek, a first-order tributary of the Gambia River upstream from the PNNK.

If unmitigated, discharge from the TMF post closure may impact downstream surface water quality. Potential

pollutants in discharge include: cyanide, metals (particularly Cu and Mn), AMD, nutrients, saline water and

suspended sediment.

Additional impacts similar to those identified during the pre-construction and construction phase (i.e. erosion and

sedimentation, noise, dust) are likely to occur from decommissioning activities (e.g. major earthworks, operation

of heavy plant and machinery, etc.) required for demolition and removal of infrastructure rehabilitation and

restoration (planting) of the TMF and Process Plant footprints.

Refer to the Rehabilitation and Conceptual Closure Plan (Volume E) for a preliminary assessment of potential

impacts during the decommissioning and closure of the Process Plant and TMF.

6.3 Management and Mitigation Measures

The Company will manage potential environmental and social issues associated with the construction, operations

and decommissioning/closure of the Process Plant and the TMF through adoption of leading practice design,

industry best practices, and management of risks associated with mineral processing and tailings management, as

are identified in the following sub-sections.

6.3.1 Pre-construction and Construction Phase

The Process Plant and TMF footprints have been minimised to the extent practicable to limit construction impacts

to surrounding land.

Page 88: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 73

The Company will implement management measures specified in applicable SOPs (Appendix A) to manage

potential impacts that may occur for the Process Plant and TMF, including:

Vegetation clearance (refer to SOP09: Land Clearance and Soil Stockpiling);

Land erosion, compaction and sedimentation (refer to SOP01: Erosion and Sediment Control);

Hazardous materials transport, handling and disposal (refer to SOP07: Hazardous Materials Management);

General wastes (refer to SOP06: Waste Management);

Dust, noise and vibration emissions (refer to SOP04: Emission and Dust Control, and SOP05: Noise and

Vibration Management, respectively); and

Cultural heritage (refer to SOP10: Cultural Heritage Management).

In addition, additional measures to be implemented for the Process Plant and TMF throughout the Project life are

also provided in Chapter 9 (Roads and Transport), with respect to transport safety measures and protocols for

Project traffic.

6.3.2 Operations phase

Storage and handling of hazardous materials

Process Plant

As part of SOP07: Hazardous Materials Management procedure, the Company will ensure all hazardous materials

and wastes (including reagents) for the Process Plant will be transported, handled and stored in accordance with

IFC General EHS Guidelines 2007 and SOP07: Hazardous Materials Management. Additionally, the Process Plant

design has integrated a closed drainage system to contain any spills/leaks.

The Company will adopt the following provisions for hazardous materials stored and handled at the Process Plant:

Hazardous wastes in the process circuit to be reused to the extent practicable, including process water, used

carbon (which will be recovered and reactivated) and spent electrolyte required for the electrowinning

process;

Primary containment (bunding) integrated for all hazardous materials storage, handling and transfer areas

in the Process Plant (refer to below) to ensure rainwater or spillage does not discharge into the receiving

environment. Secondary containment has been designed for potential discharges outside of primary

bunding;

All pipe work and pumps to be within bunds or routed above ground to allow the early identification of any

leaks;

Steel framed reagent storage shed constructed with concrete floor, sumps and appropriate layout and

facilities to isolate, separate and handle hazardous goods;

Plant areas subject to possible contamination from chemical or slurry spills to have concrete slabs and

bunds (with 110% holding capacity) installed;

Bunded areas equipped with sump pumps to recover any spilled material or rain falling on the slabs, for

reclaim to the process;

Site run-off and spillage exceeding the capacity of the bunds that are potentially contaminated with

cyanide and reagents will report to a lined event pond with a submersible pump for reclaim to the process

circuit (contaminated spillage will ultimately report to the TMF), or discharge to the TMF;

The distance for the tailings / return pipelines to the TMF has been minimised and the pipeline will follow an

alignment that runs down a continuous downhill slope to the TMF with no ‘dead legs’ in the line requiring

drain valves and scour pits to minimise potential for leakage; and

Routine monitoring of water quality discharge from the Process Plant to be conducted (refer to below).

Page 89: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 74

Consistent with the International Cyanide Management Code and Guidelines (Cyanide Code) (ICMI 2014), the

Company will implement the following measures for cyanide management at the Process Plant:

Materials handling, containment and bunding in all plant areas to conform to the Cyanide Code (ICMI 2014)

as well as well as Senegalese legislative requirements, in particular Law No. 2001-01 of 15 January 2001 on

the Environment Code;

Cyanide storage, handling, destruction, and disposal compliant with Cyanide Code (ICMI 2014) and be

conducted in a manner that avoids potential releases to receiving waters;

Cyanide will be purchased from a member of the International Council of Chemical Associations Responsible

Care Program compliant with the Cyanide Code (ICMI, 2014);

As a minimum, two people with rigorous cyanide and emergency specific training will always be present for

cyanide unloading, storage and automated mixing (to minimise human handling, exposure and error);

Cyanide destruction methodology will ensure residual cyanide from the CIL circuit in the Process Plant will

be less than 50 parts per million (ppm);

Preparation of a specific Cyanide Spill Contingency Plan as part of the Project Emergency Preparedness and

Response Plans (to be developed); and

Monthly water quality monitoring of tailings and supernatant water for cyanide concentrations (including

breakdown products of cyanide) to ensure Cyanide Code (ICMI 2014) compliance.

Additional measures to avoid or minimise potential impacts associated with the handling and disposal of

hazardous materials and wastes are provided in SOP07: Hazardous Materials Management and SOP06: Waste

Management, respectively (Appendix A). Specific transport requirements for hazardous materials, including

cyanide transport, are detailed in Chapter 9 (Roads and Transport).

Disposal of hazardous wastes

During Project operations, the Company is committed to ensuring the safe storage and disposal of residual wastes

and process residues from the Project, consistent with international best practice. Approximately 225 tonnes per

hour of solids process tailings and 225 tonnes per hour of process water will be generated from the Process Plant.

Tailings will be disposed of in the TMF. Approximately 50% of the process water will be entrained in saturated

tailings in the TMF, while the remaining will be recovered and returned to the Process Plant for re-use.

General safety

The Company will secure the facilities with a patrolled 2.1 m high security fencing topped with razor wire and a

gatehouse at the entrance of the plant manned by security personnel to restrict unauthorised access. These areas

will be under continuous camera surveillance.

The Company will incorporate the following key safety measures for the Process Plant:

Plant design accounts for seismic events;

Adequate lightning and surge protection to be provided for the Process Plant building structures and

sensitive equipment;

Fire protection and control system for the Process Plant and Power Station that will supply fire water at the

required pressure and flowrate in the event of a fire emergency;

Fire hydrants and hose reels provided at strategic locations throughout each facility and fuel storage areas

to ensure complete coverage in areas where flammable materials are present;

Provision of backup critical plant and equipment (e.g. process water pumps, emergency diesel-powered fire

water pump) with proper safety controls in place to ensure there is sufficient redundancy in the plant

system if there is a process failure or maintenance work is required;

Safety showers provided for workers accidentally exposed to hazardous chemicals;

Maintenance of the mechanical integrity and operability of the plant process systems (e.g. relief and vent

valves, shutdown systems, pumps, containment infrastructure, pressure tanks, etc.);

Page 90: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 75

Use of fire breaks to prevent bushfire risks;

Extensive camera surveillance installed (e.g. in the gravity circuit and goldroom areas) and entry points

monitored and alarmed to provide a high level of security;

Access to the goldroom within the plant will be restricted and strictly controlled. All personnel allowed into

the area will be accompanied and monitored by security staff. Persons leaving the area will be subject to a

comprehensive search; and

Built-in emergency warning system and plant shutdown mechanisms (e.g. statutory interlocks such as

emergency stops and thermal protection to be hardwired).

For operational safety of the TMF, independent audits of the TMF will be conducted by a suitably qualified

specialist on a regular basis to ensure structural integrity of the dam facility is maintained. The Company will

continually manage the TMF to ensure sufficient freeboard to accommodate for a maximum precipitation event.

An emergency spillway will be provided in the event that rainfall exceeds the 1 in 100 year storm event (i.e. greater

than the TMF design criteria), with appropriate scouring controls integrated into the design. Discharge under these

conditions is required in order to protect the integrity of the embankments from overtopping failure.

As described in Section 3.7, Emergency Preparedness and Response Plans for the Project will be developed in the

next phase informed by the Risk Assessment (refer to Volume B). These plans will include an Emergency Response

Plan, cyanide management processes in a Cyanide Spill Contingency Plan, and appropriate spill prevention and

response procedures in line with industry best practice, IFC General EHS Guidelines, and the ICMI Cyanide Code.

Chapter 14 (Community Health and Safety) provides additional measures to manage potential impacts associated

with the construction and operation of the TMF and Process Plant.

Dust and air quality management

The Company’s air quality management measures are provided in SOP04: Emission and Dust Control (Appendix

A). In addition, the Company has included the following dust suppression and air quality design and mitigation

measures for the Process Plant:

Optimised Process Plant design that resulted in the reduction of three conveyors from the preliminary

design;

The quick lime silo fitted with a dust collector;

Coarse spillage in the crusher area to be cleaned up by front end loaders and transported to the ROM pad

for drying or fed directly to the primary crusher;

Spillage in the crushing and screening area to be cleaned up by skid-steer loader and added directly onto

the mill feed belt via the clean-up hopper;

The gravity circuit area will be fully enclosed;

Water sprays and two dust collection systems installed for dust suppression in the crushing and screening

circuit and lime addition point, where feasible;

As required, the Company will further consider containing fugitive emissions within the Process Plant to the

extent practicable by either:

» Enclosing or covering all fugitive source emissions such as the conveyors, hoppers, bins;

» Watering roads or gravel sheeting in ore-handling areas to minimise windblown and traffic generated

dust; and

» Controlling a fugitive emission source from feed ore handling by employing air extraction and treatment

through a baghouse or cyclone.

The Company will routinely monitor fugitive dust emissions at the Process Plant.

The Company will manage and mitigate potential air quality impacts from the TMF, including:

Re-using suitable material from the open pit stripping to maintain the TMF embankment wall to the extent

practicable, to minimise the need for borrow pits and quarries (and associated air quality impacts); and

Page 91: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 76

Regular water spraying of exposed tailings when excessive dust generation is evident.

Water quality management

The TMF, Process Plant / ROM Pad, Mine Pit, WRD, ore stockpiles, (and additional Project components including

the Mine Services Area) will be located in the Badalla Valley (refer to Figure 1-1) to contain potential pollution

sources within the single catchment. Surface water flowing from upstream of Project facilities will be diverted

around the Project Footprint for discharge into the TMF. Runoff from within the Process Plant and TMF areas will

drain to the TMF (in some cases via a series of event pond or sediment control facilities). Additional secondary

containment downstream of the TMF will ensure zero discharge to receiving waters outside of the PDA during

operations.

Though the TMF dam will be constructed to minimise seepage, there is the potential for a minimal amount of

seepage to occur through embankment foundations or into groundwater. To monitor this seepage and

groundwater quality in general, a number of groundwater bores will be installed both up-gradient and down-

gradient of the TMF.

Wastewater and sewage from the Process Plant ablutions and mess facilities will be treated by a water treatment

plant within the Mine Services Area to meet applicable water quality discharge standards.

During Project operations, the Company will incorporate the following water quality monitoring measures:

Monthly water quality monitoring of tailings, supernatant water and seepage water (if applicable) for key

parameters, including cyanide (including free cyanide, weak acid dissociable cyanide, and total cyanide),

salinity, dissolved and total metals, nutrients, and AMD (via drainage sump and piezometers); and

Monthly groundwater quality monitoring of the installed bores downgradient of the TMF for water level and

key parameters including cyanide (including free cyanide, weak acid dissociable cyanide, and total cyanide),

salinity, dissolved and total metals, nutrients, and AMD.

Once operations commences, this monitoring programme should be re-evaluated based upon previous results and

existing operations and environmental conditions.

Further surface water management measures associated with the TMF are detailed below.

Tailings management

The establishment of the TMF will be staged, and designed to ANCOLD and ICOLD standards. The TMF has been

designed for geotechnical and geochemical stability and will be operated as a zero discharge facility. The TMF has

sufficient stormwater capacity for all design storm events and rainfall sequences for a 1 in 100 year storm event

(particularly during the wet season), with an additional 1 m contingency freeboard. The embankment, TMF surface

and piping facilities have been engineered to minimise the potential for groundwater contamination or seepage.

In summary, the TMF will incorporate the following water quality management measures:

A soil liner with permeability less than 1 x 10-8

m/s will minimise the potential for seepage over the extent of

the basin area;

An HDPE geomembrane liner will be installed in the lower reaches of the TMF basin and on the TMF

embankment upstream face. The liner will conform to Nevada’s Water Controls for Mining Facilities

Standards (Nevada Administrative Code: NAC 445A.438). This stipulates that synthetic liners must have a

resistance to the passage of process fluids equal to a permeability coefficient of 1 x 10-11

cm/sec;

Two drainage collection systems implemented for TMF drainage:

» A Leakage Collection and Recover System (LCRS) will be placed under the HDPE liner. The LCRS water

will be collected using a sump with an inclined outlet riser pipe on the upstream face of the

embankment; and

» Tailings Underdrainage Collection System placed over the HDPE liner. The underdrainage will be spaced

at 50 m spacing on the HDPE with the spacing being reduced to 25 m if HDPE liner is not used. Similar

to the LCRS, the underdrainage will be collected via a sump and inclined riser on the upstream face of

the embankment.

Page 92: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 77

Groundwater drains constructed in the existing stream channels below the low permeability soil liner, and

above liner drains at the TMF embankment. This will reduce the pressure on the liner and reduce any

potential seepage. This underdrainage system will comprise a network of finger and collector drains;

All drainage pipes directed to a lined seepage collection pond (event pond) located downstream of the TMF

embankment for subsequent pumping of event pond water back into the TMF if required;

Seepage and supernatant water will be collected and stored in the seepage collection system to decant

prior to be recirculated back to the Process Plant. The system will operate as a pump-out decant utilising a

slotted concrete tower with a pump and pipeline on an access causeway;

Recycling of up to 80% of the TMF decant / supernatant water in the Process Plant via a return water

pipeline to supplement water sourced from the WSD. All event pond water will be pumped back to the

Process Plant or TMF;

A stormwater interception and diversion system to be installed around the TMF perimeter (with a raised

access road) to capture and divert all surface water runoff. The diversion will intercept seasonal slope runoff

from the catchment area outside of the TMF and divert it around the TMF to spillways on the east and west

abutments. At each raising of the embankment, temporary connections to the spillway will be provided;

Stormwater and sediment control structures (e.g. culverts and small sediment control ponds) will be

installed within the facility perimeter to capture and divert all site runoff into the decant system (during and

after construction of the facility);

Tailing and return water pipelines to be constructed in a lined trench (about 1 m deep) and contained to

report to the TMF in the event of a spill or leakage;

Monitoring of groundwater bores and surface water sampling stations downstream of the TMF; and

Regular inspection and maintenance of the TMF and associated pipelines (tailing and return water) in

accordance with the TMF Operation and Monitoring Manual.

Specific measures to ensure stability of the TMF dam include:

An emergency spillway provided at all times in the event that rainfall exceeds the 1 in 100 year storm event

(i.e. greater than the dam design criteria). Discharge under these conditions is required in order to protect

the integrity of the embankments from overtopping;

Dam embankment constructed with at least a slope of 2.5H:1V, with rock armouring (i.e. rip rap) provided

on the outer banks and spillway to prevent potential scouring, erosion and embankment instability;

Security fencing around the site perimeter of the TMF to limit the public and livestock from accessing the

area;

Ongoing review of the site water balance and inventory to avoid potential water overcapacity or shortages

at the Project site;

A regular inspection and maintenance schedule of TMF and WSD dam infrastructure (i.e. spillway,

embankment, pipelines, flanges, seals and pumps;

Independent audits of the TMF and WSD conducted by a suitably qualified geotechnical engineer on an

annual basis to ensure structural and operational integrity of the dam facility is maintained; and

The TMF Operating and Monitoring Manual to be finalised prior to Operations.

Acid mine drainage management

The following measures will be implemented to avoid potential for acid and metal generation during the

operations and decommissioning / closure phase:

Grading of the ROM pad towards the Badalla Valley so that surface water flows are retained onsite for reuse

in Process Plant;

Processing of only basalt ore material when approaching closure to achieve a final NAF basalt layer of

tailings (0.5 to 1 m thickness) as the final upper layer of tailings for the TMF. Consideration will be given to

Page 93: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 78

blending this tailings material with low oxygen / water permeability substrates (e.g. clay) to minimise

atmospheric oxygen infiltration into the tailings material;

Depending on the solute loads generated, an engineered passive anaerobic wetland system may be

effective in further lowering sulfate salinity and arsenic loads released from the TMF supernatant pond and

TMF seepage post-closure, if required; and

Cover the TMF with a suitable low permeability capping layer to minimise infiltration and oxygen transfer.

The Company will determine preferred method following more detailed investigation during Project

operations.

Routine monitoring of geochemistry and water quality will be conducted to ensure potential risk of acid generation

is appropriately managed.

Noise management

The Company has designed the Process Plant for enclosure in a concrete building on three sides, with the fourth

side partially open for access. The Company will implement the following additional measures to minimise noise

emitted by the Process Plant operations, as required:

Selection of the quietest plant and equipment;

Use of barriers (e.g. near vibrating screen) and other noise abatement technologies (e.g. ventilation fan size

or use of windscreens near ventilation fan);

Full acoustic enclosure of high noise emitting areas such as the crushing and grinding areas;

Sound insulation of plant and machinery engines, if required; and

Provision of noise protection PPE for workers in areas where plant equipment emits noise in excess of

80 dB(A).

Visual amenity management

The visual impacts of the Process Plant and ROM will be minimised by implementing the following measures:

Vegetation clearance restricted to the minimum extent practicable for Project construction;

Cleared areas around facilities progressively rehabilitated and revegetated to the extent practicable as soon

as respective areas are no longer required for construction / operations;

Project structures painted in muted colours in keeping with the local area and vegetation;

Construction sites to be well maintained and kept tidy;

Physical barriers such as earth/rock banks or vegetation to be considered for concealing Project

components to the extent feasible;

Where relevant, visual amenity management and mitigation measures will be incorporated into the Construction

Environmental Management Plan (CEMP).The SOP11: Lighting and Visual Amenity Management (Appendix A)

provides additional measures, where relevant.

Biodiversity management

A combination of bird-scaring techniques or measures will be employed to prevent fauna poisoning from drinking

tailings water. The Company will incorporate management, mitigation, and monitoring as detailed in the

Biodiversity Action Plan (Volume C).

6.3.3 Decommissioning and closure phase

The Company will rehabilitate and revegetate the Process Plant, ROM Pad and TMF areas according to

methodologies detailed in the RMCP (Volume E). As with all facilities that will be revegetated, rehabilitation will

be conducted to ensure closure criteria are met for the facilities (development of self-sustaining Shrub savannah

for the TMF and grassland for the Process Plant area).

Page 94: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 79

Decommissioning of the Process Plant and TMF will require careful management, mitigation, and monitoring with

respect to the following:

Surface water from the TMF (which includes runoff from the WRD and the Mine Pit) will be reconnected to

Badalla Creek and discharge from the Project Area will resume. Therefore the Company will have to ensure

water quality meets applicable discharge and ambient water quality guidelines prior to discharge; and

Soil and groundwater at the Process Plant, associated facilities, and TMF may be subjected to pollutants

during operations, with remedial actions required to meet closure criteria.

Further details for each of the facilities are specified below.

Tailings Management Facility

Upon Project decommissioning / closure, the Company will implement the following management and monitoring

measures at the TMF site to ensure closure objectives are met:

Partially cap the facility with waste rock in order to prevent seepage and engineer the surface at the top to

prevent water pooling;

Grade to a stable 1 in 100 slope and engineer the slopes to encourage sheet flow of run-off water and

prevent excessive channelling and erosion;

Rehabilitate the TMF and develop armoured drainage channels to ensure that tailings material is securely

stored (i.e. erosion resistant);

At closure, the stormwater spillway on the eastern abutment of the TMF will be converted into a

permanent to discharge channel to allow surface water to freely discharge from the surface of the

rehabilitated facility;

Sample TMF supernatant water laboratory analysis, including the full suite of dissolved and total metals,

cyanide (total cyanide, free cyanide, and WAD cyanide), salinity, pH, nutrients, etc. to determine whether

treatment is required; and

If treatment is required, consider remedial measures, frequency of treatment, and requirements for

ongoing post-closure treatment, if necessary.

As surface water from the facility will discharge into Badalla Creek, a key environmental issue related to the

closure of the TMF will be water management and potential downstream water quality impacts. As such, surface

water from this spillway will be continually monitored for compliance with relevant water quality standards and

guidelines.

In addition, the Company will monitor the success of revegetation activities to ensure that tailings material are

securely stored (i.e. erosion resistant) for an indefinite period and present no hazard to public health and safety or

the environment. Closure criteria will be established for the Final Rehabilitation and Mine Closure Plan. Examples

of measureable completion criteria that will be met for the TMF include:

On-site and downstream water quality (i.e. with respect to baseline conditions and applicable discharge

guidelines);

Revegetation success (e.g. % coverage, species diversity, % weeds); and

Geotechnical and landform stability.

Process Plant and ROM Pad

A specific Decommissioning Plan will be developed for the Process Plant and ROM Pad. The following

management and monitoring measures will be taken in relation to the decommissioning and rehabilitation of

these facilities:

The Company will implement a strategy for the disposal of processing reagents, decontamination of

equipment, removal of water from pond surfaces, reduction of cyanide concentration to a level protective

of human health and wildlife, and installation of equipment necessary for long-term protection of ground

and surface water quality during the facility’s closure period;

Page 95: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 80

At the end of operations, the Process Plant and ROM pad will be cleared to ground level. The concrete will

be broken up and rehabilitated;

All exposed soil will be re-contoured and ripped and re-vegetated to a landform consistent with the

surrounds upon mine closure to minimise potential for erosion;

A strategy for the disposal of processing reagents, decontamination of equipment, removal of water from

pond surfaces, reduction of cyanide concentration will be developed to a level protective of human health

and wildlife, and installation of equipment necessary for long-term protection of ground and surface water

quality during the Process Plant’s closure period;

Soil and groundwater testing will be undertaken to determine whether contamination has occurred with

treatment/remediation implemented if required. The faces of the ROM pad, the immediate surrounds of

the Process Plant and any exposed areas of soil within the Process Plant site will be tested for contaminants

and re-vegetated as early as possible after deconstruction (unless remediation for waste is required first);

Any concrete foundations or soil contaminated by metals, hydrocarbons or other contaminants will be

decontaminated (volatilisation) and disposed of in a lined landfill;

Treatment strategies will be further refined before commissioning of operations; and

Drainage will be redirected as necessary to minimise erosion until vegetation is established. Water in the

sediment control structures will be treated to achieve compliance with appropriate discharge standards.

6.4 Monitoring Measures

The primary monitoring measures related to the mineral processing and tailings management associated with the

Process Plant and TMF are summarised in Table 6-2. These will be incorporated into the detailed monitoring

programmes prepared by the Company and its contractors for all phases of the Mako Gold Project.

Relevant guidelines and standards applicable to the Project are specified in Section 2.4 and the Registers of

Environmental and Social Management and Monitoring Commitments in Chapter 18 of this Plan.

Table 6-2 Register of Environmental Monitoring Measures - Minerals Processing and Tailings Management

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Water

quality

Routine water

quality

monitoring

Pre-

construction,

Construction

Refer to SOP02.9

and SOP2.10

Key parameters:

Turbidity, TSS, DO,

temperature, electrical

conductivity (EC), and

pH

Visual checks for

sedimentation, oils and

grease

Threshold limits

provided in Table 2-5 to

Table 2-7

Weekly

Discharge

points (refer to

monitoring

sites shown in

Figure A2,

Appendix C)

Water quality

monitoring of

tailings,

supernatant

water and

seepage water

collected in the

seepage

collection

system

Operations Refer to SOP02.13

Key parameters:

Cyanide (including free

cyanide, weak acid

dissociable, and total),

salinity, total and

dissolved metals (full

suite), nutrients, and

field parameters (e.g.

pH, EC, ORP, DO, etc.)

Threshold limits

Monthly

TMF

supernatant

water,

drainage

sump, and

piezometers

(refer to

monitoring

sites shown in

Figure A2,

Page 96: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 81

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

provided in Table 2-5 to

Table 2-7

Appendix C)

Groundwater

quality

monitoring via

piezometers

and concrete

monitoring

weirs

Operations Refer to SOP02.14

and SOP02.15

Key parameters:

Groundwater level,

cyanide (free, weak

acid dissociable, and

total), related

breakdown products of

cyanide (e.g. ammonia,

nitrate, thiocyanate),

salinity, nutrients, and

field parameters (e.g.

pH, EC, ORP, DO,

temp. etc.); acidity /

alkalinity, sulfate, and

dissolved metals (to be

determined by waste

rock characterisation)

Threshold limits

provided in Table 2-5 to

Table 2-7

Monthly

Groundwater

monitoring

bores down

hydraulic

gradient of the

TMF, Mine Pit

and WRD

(refer to

monitoring

sites shown in

Figure A2,

Appendix C)

Regular

inspection for

potential

leakage or

seepage of

contaminated

water

Operations

Visual check for

visible leakage or

seepage (refer to

SOP02.19(

Project compliance Monthly

Process Plant,

TMF and

associated

pipelines

(tailing and

return water)

Water

Quality

(discharge

)

Discharge

monitoring of

surface and

groundwater

quality upon

mine closure

Upon mine

closure,

Decommissio

ning

Refer to SOP02.14

and SOP02.15

Key parameters:

Cyanide (free, weak

acid dissociable, and

total), related

breakdown products of

cyanide (e.g. ammonia,

nitrate, thiocyanate),

salinity, nutrients, and

field parameters (e.g.

pH, EC, ORP, DO,

temp. etc.); acidity /

alkalinity, sulfate, and

dissolved metals (to be

determined by waste

rock characterisation)

Threshold limits

provided in Table 2-5 to

Table 2-7

Once-off

TMF

Reservoir and

down-gradient

groundwater

monitoring

bores (refer to

monitoring

sites shown in

Figure A2,

Appendix C)

Acid mine

drainage

Static geo-

chemistry

testing to

Operations,

DecommissioRefer to SOP02.17

Static geochemistry of Monthly

Tailings

samples from

the thickener

Page 97: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 82

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

monitor any

potential

change in the

geochemical

risk

classification

of the tailings

material

ning tailings samples for

total sulphur, acid

neutralizing capacity,

and net acid producing

potential

Threshold limits

provided in Table 2-5 to

Table 2-7

underflow of

the TMF

Air quality

and dust

Dust

monitoring

Construction,

Operations Refer to SOP04.16

Daily visual check for

fugitive dust

Monitoring of PM10, and

PM2.5, SO2, NOx, CO

and dust deposition

rates

Threshold limits

provided in Table 2-4

Monthly

Existing dust

monitoring

point near the

Process Plant

(refer to

monitoring

sites shown in

Figure A1,

Appendix C)

Noise

Noise

monitoring

Construction,

Operations Refer to SOP 05.12

Noise levels in dB(A)

LAeq (daytime and

night-time period

Threshold limits

provided in Table 2-8

Bi-annually

Process Plant

(refer to

monitoring

sites shown in

Figure A1,

Appendix C)

Hazardou

s

materials

leakage /

spillage

Regular

inspection for

potential

leakage or

seepage of

hazardous

materials and

wastes

All Project

phases

Visual check for

visible leakage or

seepage (refer to

SOP07.28)

Project compliance Weekly

Project-wide

(including

Process Plant

and

hazardous

storage areas)

Spills

inventory

All Project

phases

Review of relevant

registers and records

maintained by the

Company (refer to

SOP07.28)

Number, type (e.g.

cyanide, hydrocarbons,

chemical, etc.) and

scale of spills (i.e.

small, large, major)

occurring at the Project

Volume of accidental

releases to the

receiving environment

(including soils and

water), if any

Actions taken for

immediate remediation

Ongoing

Hazardou

s wastes

Hazardous

waste

inventory

All Project

phases

Review of relevant

registers and records

maintained by the

Company (refer to

SOP07.28)

Volume of hazardous

waste generated by the

Project

Volume of hazardous

waste disposed of

offsite but not recycled

(e.g. no longer in

Ongoing

Project-wide

(including

Process Plant

and TMF)

Page 98: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 83

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

temporary storage)

Volume of hazardous

waste recycled offsite;

Volume of

contaminated spillage

treated onsite

Trends for hazardous

waste volumes

compared to previous

years

Volume of hazardous

waste transported

across international

boundaries

TMF dam

integrity

Monitoring of

the TMF

structural

integrity

Operations

Independent audit of

dam structural

integrity by a suitably

qualified specialist for

operational safety

(refer to SOP03.13).

Project compliance

Inspection records for

geotechnical and

landform stability

Annual

TMF

Operations

Regular inspection of

dam toe, emergency

spillway,

embankment, tailings

pipelines, and

monitor the

groundwater

downstream to

inform any remedial

works required (refer

to SOP03.13 and

SOP03.14).

Project compliance

Verification of security

practices

Verification of safety

controls and inspection

records

Periodic

(e.g.

weekly)

Monitoring of

the TMF water

levels

Operations

Routine visual

inspection of the

TMF for freeboard

management to

maintain sufficient

freeboard for

operational safety

(refer to SOP03.13).

Project compliance

Verification of security

practices

Verification of safety

controls and inspection

records

Daily

Page 99: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 84

7 WATER SUPPLY

7.1 Objectives

Key Company management objectives for the Mako Gold Project water supply include:

Providing adequate raw water storage capacity to satisfy Project needs for Process Plant water

requirements and dust suppression;

Minimising site water consumption by maximising reuse of water; and

Developing a sustainable water supply programme that avoids potential downstream impacts to the

Gambia River and its tributaries in conformance with applicable discharge water quality guidelines.

7.2 Context

The WSD embankment will be constructed across the Kobokou Creek (an ephemeral creek), a Gambia River

tributary in Wayako Valley, to impound water for the reservoir. The facility will store surface water from the 56 ha

upstream catchment area and water abstracted from the Gambia River during the rainy season. Abstraction will

require pumping raw water from the Gambia River to the WSD via a floating decant barge (to prevent a shortfall

for a 1 in 100 dry year at any stage of operation). A water supply pipeline will transfer raw water from the Gambia

River to the WSD, and to the Mine Site for reticulation.

Key sensitivities related to water supply for the Mako Gold Project primarily include the aquatic environment and

downstream water users of the Gambia River and its tributaries.

7.2.1 Pre-construction and Construction Phase

Impacts from the WSD will primarily be limited to the pre-construction and construction phase, with site

preparation activities including land clearance, earthworks and excavation to establish the dam embankment and

spillway infrastructure. Construction water will be sourced, using temporary portable diesel pumps, from the

Gambia River (Coffey, 2015). Temporary water ponds will be constructed to hold water during early construction

activities. Once the WSD is completed, water will be drawn directly from the dam.

Potential construction impacts associated with the creation of the WSD include:

Removal of approximately 14.84 ha of natural vegetation and habitat for terrestrial species (refer to Chapter

10 of the ESIA, Volume A);

Altered hydrology (refer to Chapter 9 of the ESIA, Volume A);

Erosion and sediment transport from disturbed surfaces (refer to Chapter 9 of the ESIA, Volume A);

Hydrocarbon spillage (refer to Chapter 9 of the ESIA, Volume A); and

Vehicle emissions and dust generation (refer to Chapter 9 of the ESIA, Volume A).

The primary impact will be impoundment of surface water from the ephemeral stream in the WSD for operations.

7.2.2 Operations Phase

Potential impacts during operations will be minor. Standing water stored in the WSD during operations may

provide breeding grounds for waterborne vectors such as mosquitoes, and a potential drinking water source for

local wildlife. Safety hazards typically associated with dams will not be significant given the small scale of the

WSD. The WSD is not likely to support aquatic life.

Page 100: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 85

Potential impacts from Gambia River abstraction have been evaluated in the ESIA (refer to Chapter 9), and are

considered minor as abstraction will occur during the rainy season.

7.2.3 Decommissioning and Closure Phase

The Company will fully decommission the WSD prior to mine closure, and reconstruct and rehabilitate the area to a

self-sustaining natural ecosystem. The potential impacts during this phase will be similar to those in the pre-

construction and construction phase, including the potential for soil erosion, sedimentation, and potential

accidental hydrocarbon spillage.

7.3 Management and Mitigation Measures

7.3.1 Pre-construction and Construction Phase

Construction environmental management

Historical rainfall, evaporation and runoff data have been used to inform the WSD design and construction (refer

to Knight Piesold, Mako Gold Project – TSF and WSD Design Summary (2015b)). Additional measures that have

been adopted by the Company in the design and implementation of the WSD to minimise potential environmental

impacts include:

Optimised water efficiency onsite by maximising reuse and recycling of mine and process water during all

phases of the Project;

Construction footprint has been minimised to limit vegetation clearing to the extent practicable;

Dam infrastructure (including engineered embankment and spillway) has been designed to accommodate a

1 in 100 year rainfall event plus contingency freeboard;

WSD will have a 21 m high engineered embankment formed of compacted low permeability earth , and

upstream and downstream structural fill zones, to create an impervious barrier to minimise loss of the

stored water by seepage. A cut off trench will be located beneath the WSD embankment, which will be

excavated to extend through to competent low permeability foundation material (depth to be confirmed).

The cut off trench will be constructed continuously along the embankment and backfilled with low

permeability fill;

An emergency spillway provided at all times in the event that rainfall exceeds the 1 in 100 year storm event

(i.e. greater than the dam design criteria). Discharge under these conditions is required in order to protect

the integrity of the embankments from overtopping;

WSD embankment constructed with a slope of 2.5H:1V, with rock armouring (i.e. rip rap) provided on the

outer banks and spillway to prevent potential scouring, erosion and embankment instability;

Ongoing review of the site water balance and inventory to avoid potential water overcapacity or shortages

at the Project site; and

Topsoil from the disturbed area to be progressively stripped and stockpiled for use during site

rehabilitation.

During construction, the Company will implement the following SOPs to address risks and potential impacts

associated with the creation of the WSD include (refer to Appendix A):

SOP09: Land Clearance and Soil Stockpiling;

SOP01: Erosion and Sediment Control;

SOP02: Water Quality and Pollution Management;

SOP03: Hydrology and Water Management;

SOP07: Hazardous Materials Management;

SOP04: Emission and Dust Control, and

Page 101: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 86

SOP05: Noise and Vibration Management.

The Biodiversity Action Plan (Volume C) will provide biodiversity mitigation and offset measures relevant for the

WSD on a Project level.

7.3.2 Operations Phase

The Company has adopted the following management measures to minimise potential environmental impacts

during the operations of the WSD:

Regular review of site water consumption for ongoing improvements in water efficiency, reuse and

recycling strategies within the Mine site (refer to SOP03: Hydrology and Water Management, for further

details on a site water balance and inventory);

Project abstraction from the Gambia River will not exceed 3% of the instantaneous volumetric flow.

Abstraction will be limited to periods when the Gambia River discharge exceeds 5 m3/sec;

Security fencing to be provided around the site perimeter of the WSD to limit the public and livestock from

accessing the area;

Automated water level gauge sensors will detect any excessive water loss from seepage/leakage;

Discharge from the WSD will occur in a controlled manner via an engineered spillway, excavated into the

eastern abutment of the WSD embankment;

A regular inspection and maintenance schedule of the dam infrastructure to ensure sufficient freeboard for

a 1 in 100 year rainfall event is maintained to prevent overtopping of the dam wall and dam failure during

periods of high or extended rainfall;

A regular inspection and maintenance schedule of the water supply pipeline, flanges, seals and pumps.

Channels will be kept free of vegetation and physical obstructions. Sediment and debris traps around the

perimeter of the reservoir will also be maintained in order to reduce the amount of dirt in the reservoir. The

Company will engage with the community, and in particular herders, to prevent deliberate tapping of the

pipe;

Vegetation buffers may be used where necessary to help stabilise the soil and reduce evaporation rates

caused be wind and thermal exposure;

Training and awareness provided to employees and contractors regarding:

» Prevention of vector-borne diseases, including malaria transmission from mosquitoes; and

» Water efficiency, recycling and reuse strategies in place at the Mine Site.

Independent audits of the WSD to be conducted by a suitably qualified geotechnical engineer on an annual

basis to ensure structural and operational integrity of the dam facility is maintained; and

The TMF and WSD Operating and Monitoring Manual will be finalised prior to Operations.

In addition, ongoing management and monitoring of the WSD will assist to ensure water shortages are avoided

onsite, particularly in the dry season.

7.3.3 Decommissioning and Closure Phase

The RCMCP (Volume E) details the rehabilitation plan for restoring the temporarily impounded Kobokou Creek.

The WSD embankment will be breached after mine closure and the channel re-established so that the watercourse

will resume its natural flow regime post-closure. The WSD footprint will be rehabilitated with local non-invasive

plant species.

Upon decommissioning, the Company will carry out appropriate water quality testing prior to discharging the

remaining water from the WSD into the Gambia River, to ensure it meets applicable water quality discharge

standards (particularly for salinity and turbidity). Where appropriate, the Company will ensure adequate water

treatment is carried out prior to discharging into the Gambia River.

Page 102: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 87

7.4 Monitoring Measures

Table 7-1 presents the monitoring regime related to water supply for the Mako Gold Project during construction,

operation and decommissioning/closure. The Company will ensure contractors incorporate the monitoring

programme into a Construction Environmental Management Plan, where appropriate.

Relevant guidelines and standards applicable to the Project are specified in Section 2.4 and the Registers of

Environmental and Social Management and Monitoring Commitments in Chapter 18 of this Plan.

Table 7-1 Register of Environmental Monitoring Measures – Water Supply

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Water

quality

Routine water

quality

monitoring

Construction Refer to SOP02.9

and SOP2.10

Key parameters:

Turbidity, TSS, DO,

temperature, electrical

conductivity (EC), and

pH

Visual checks for

sedimentation, oils

and grease

Threshold limits

provided in Table 2-5

to Table 2-7

Weekly

Discharge points

(refer to

monitoring sites

shown in

Figures A2 and

A3, Appendix C)

Discharge

water quality

monitoring of

reservoir

Decommission

ing Refer to SOP02.14

Key parameters;

Salinity, Turbidity, TSS,

temperature, EC,

ORP, pH

Threshold limits

provided in Table 2-5

to Table 2-7

Once-off

prior to

discharge

WSD discharge

point

Water

managem

ent

Site water

balance

monitoring

Operations

Refer to SOP04.17

and SOP03.10 to

avoid potential water

shortages onsite.

Monitor rainfall,

temperature,

evaporation rates and

other relevant site

water balance

parameters (refer to

SOP03.10)

Continuousl

y

Meteorological

monitoring at

site based

existing weather

stations near the

WSD (refer to

monitoring sites

shown in Figure

A1, Appendix C)

Dam

safety and

integrity

Monitoring of

the WSD

structural

integrity and

water levels

Operations

Independent audit of

dam structural

integrity by a

suitably qualified

specialist for

operational safety

(refer to SOP03.13)

Project compliance

Inspection records for

geotechnical and

landform stability Annual

WSD

Operations

Regular visual

inspections of the

WSD reservoir

levels for sufficient

freeboard

management (refer

to SOP03.13).

Project compliance

Verification of security

practices

Verification of safety

controls and

inspection records

Daily

Page 103: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 88

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Operations

Regular inspection

of dam toe,

emergency spillway,

embankment, and

water supply

pipelines to inform

any remedial works

required (refer to

SOP03.13 and

SOP03.14)

Project compliance

Verification of security

practices

Verification of safety

controls and

inspection records

Periodic

(e.g. weekly)

Air quality Dust

monitoring Construction

Visual check for

excessive dust and

Project Grievance

mechanism (refer to

SOP04.16)

Project compliance,

logged dust

complaints

Threshold limits

provided in Table 2-4

Daily

Active

construction

areas (refer to

monitoring sites

shown in Figure

A1, Appendix C)

Hydrocarb

on

leakage /

spillage

Monitoring for

potential

leakage or

seepage of

hydrocarbon

(e.g. diesel)

Construction

Visual check for

signs of leakage or

spillage and

observation of

hydrocarbon

management

effectiveness

Project compliance

with relevant

procedures, presence

of spill clean-up

materials, etc.

Daily

Active

construction

areas

Page 104: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 89

8 POWER SUPPLY

8.1 Objectives

Key management objectives related to power supply for the Mako Gold Project will include:

Provision of sufficient power supply for the Project without compromising environmental and social values;

Implementation of a power supply that minimises energy consumption / maximises efficiency; and

Design of a Project power supply to minimise potential pollutant emissions.

8.2 Context

The Company has indicated that a diesel fuelled Power Station will be constructed to supply power to the Mako

Gold Project. The Power Station will be located within the Process Plant perimeter fence and will comprise nine

1.8 MW diesel generators. It will incorporate 4 x 20 kL 'day tanks' for fuel, which will be topped up as required from

the main fuel depot. Overhead power lines of 11 kV will distribute power across the site (Coffey, 2015).

Power Station operations, construction equipment, and fuel delivery (including transportation) have the potential

to produce significant hydrocarbon combustion emissions, including carbon monoxide (CO), ozone (O3), nitrogen

oxides (NOx) and sulfur dioxide (SO2), and particulate matter (measured as PM2.5 and PM10) during Project

construction and operations. These are unlikely to affect air quality significantly in key sensitive areas such as

surrounding villages and PNNK if appropriately managed.

The impact assessment for the ESIA utilised the CALPUFF air quality model to predict dispersion of target

pollutants. All emission sources included in the simulations were treated individually with continuous, un-

mitigated emissions for each source estimated from the Australian National Pollutant Inventory (NPI) Emissions

Estimation Technique Manual for Mining v3.1 (2012) during the operational phase of the Project. According to the

detailed modelling, the Process Plant and Power Station area predicts higher particulate concentrations due to the

number of individual emission sources located in close proximity. Refer to the ESIA (Volume A, Chapter 9) for

more details. However, concentrations will fall sharply with distance.

8.2.1 Pre-construction and Construction Phase

Air emissions during construction will primarily be from construction vehicular activity, material transportation and

use of diesel powered generators. Associated emissions will contribute to existing concentrations of particulate

matter (PM10, PM2.5), sulfur dioxide (SO2), nitrogen oxides (NOx), carbon monoxide (CO) and volatile organic

compounds (VOCs).

8.2.2 Operations Phase

Air pollutant emissions

Combustion emissions sources during Project operations will primarily originate from the diesel Power Station,

fuel depot, and fuel delivery (including transportation). Combustion emissions from the Power Plant will include

CO, SO2, nitrogen dioxide (NO2), and particulates (PM10 and PM2.5).

8.2.3 Decommissioning and Closure Phase

The Power Station will be dismantled and the area rehabilitated to a self-sustaining natural ecosystems (refer to

Rehabilitation and Conceptual Mine Closure Plan, Volume E). Power generation requirements as well as

decommissioning and closure activities will be similar to that of construction (i.e. diesel powered generators,

vehicles, etc.)

Page 105: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 90

8.3 Management and Mitigation Measures

The management, mitigation and monitoring measures provided in the below subsections are applicable to each

of the power supply options and may require revision following identification of the final design for the Power

Station.

8.3.1 Pre-construction and Construction Phase

The design and layout of the Power Station footprint has been minimised to limit construction impacts to

surrounding land. The Company will follow international industry practices for minimising Project related

greenhouse gas emissions. Measures will include:

Selection of Power Station generators compliant with IFC Ambient Air Guidelines (2007);

Integrate energy efficiency principles in building or facility design;

Ensure contractors comply with relevant energy conservation measures outlined in the ESMMP;

Conduct awareness training on energy conservation and greenhouse gas reduction for Project employees

and workforce; and

Establish energy conservation targets for the Project for measuring improvement in greenhouse intensity of

mining operations in accordance with good international industry practices.

The Company will also apply relevant SOPs (refer to Appendix A) to manage construction impacts of the Power

Station, including:

Vegetation clearance (refer to SOP09: Land Clearance and Soil Stockpiling);

Land erosion, compaction and sedimentation (refer to SOP01: Erosion and Sediment Control);

Hazardous materials transport, handling and disposal (refer to SOP07: Hazardous Materials Management);

General wastes (refer to SOP06: Waste Management);

Dust, noise and vibration emissions (refer to SOP04: Emission and Dust Control, and SOP05: Noise and

Vibration Management, respectively); and

Cultural heritage (refer to SOP10: Cultural Heritage Management).

8.3.2 Operations Phase

Where appropriate, SOPs in Appendix A will continue to apply during Project operations, particularly for the

management of hazardous materials transport, handling and disposal.

Air quality management

Management of source emissions from power stations include using primary (dry) methods to meet IFC Thermal

Power Plant Guidelines (2008), and secondary flue gas treatments for low grade fuels or for stringent local and

national regulations. Where appropriate, the following primary and secondary methods will be applied to the

Power Station to reduce emissions:

Use of low-sulfur/low-emission diesel fuel where available and compatible with generators;

Primary Dry Methods – where a low NOx combustion process is used in liquid fuel engines, including:

» Late fuel injection start;

» High compression ratio;

» Optimised combustion chamber;

» Optimised fuel injection rate; and

» Suppressed peak temperatures for NOx reduction.

Page 106: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 91

Secondary Methods - the IFC provides guidelines for flue gas emissions reduction techniques and

efficiencies. Most of the technologies available on the market require specific provisions for transport,

waste handling and disposal, which may prove challenging in developing countries. These include:

» Wet scrubber – Wet Flue Gas De-sulfurisation (FGD) technology e.g. wet sodium hydroxide (NaOH) in

smaller plants and wet calcium carbonate (CaCO3) in larger plants. These require additional power and

considerable water resources to operate;

» Dry scrubber – Dry Flue Gas De-sulfurisation (FGD) technology e.g.; lime powder (CaO). There are

options available for the lime to be re-used by the cement industry;

» Electrostatic Precipitator (ESP) – repetitive electrostatic pulse drops out particulates from stack flue.

The composition of the collected fly ash depends on the fuel and lubrication oil used. A sulfur trioxide

(SO3) or ammonia (NH4) mist can also be sprayed;

» Cyclone – a flue gas fan that collects particulates. Requires additional power and may lead to

swirling/stratified gas flow in system that can concentrate gas emissions;

» Fabric Filter (Baghouse) – large fabric bags that collect particulates. These require cooling below 160° C,

pressure drop and additional flue gas fans. Particulate matter can clog filters and require regular bag

maintenance, replacement and adequate environmental disposal; and

» Electron-Ammonia – a new technology where an electron beam, similar to that of a cathode ray TV,

ionises an ammonia mist to react flue gas SO2 to form ammonium sulfate.

Selective catalytic reduction (SCR) process, which can be added to reduce NOx emissions by 80-90% using

an aqueous reagent of urea or ammonia (catalysts may not be compatible with high-sulfur-content diesel

fuel).

Transportation of hydrocarbons

Refer to Sections 9.3 for relevant management measures that will be applied for the bulk transportation of diesel

fuel for the Power Station during Project operations.

Safety management

Fire suppression water for the Power Station will be drawn from the raw water tank located at the nearby Process

Plant. Suctions for other water services fed from the raw water tank will be at an elevated level to ensure a fire

water reserve always remains in the raw water tank. The fire water pumping system will contain an electric jockey

pump to maintain pressure, an electric fire water delivery pump to supply fire water at the required pressure and

flowrate, and a diesel driven fire water pump will serve as a backup (automatically starting in the event that the

electric pump fails to maintain pressure in the fire water system). Additional measures include:

Security fencing and authorised personnel only around the site perimeter for the Power Station;

Fire hydrants and hose reels provided at strategic locations (e.g. Power Station, flammable material storage

areas, offices and camps) to ensure complete coverage in areas where flammable materials are present;

Plant operations and transport fuels will avoid using petrol and LPG where feasible, thereby limiting the risk

from explosive materials to only explosives and diesel fuel;

Bushfire prevention controls to be in place, including Project ban on open-burning of wastes, establishment

of fire breaks near sensitive buildings (e.g. at explosives magazine, fuel storage areas, Process Plant, Power

Station or accommodation camps), and no controlled burning activities for vegetation maintenance will be

allowed; and

Training provided to the Project personnel, as appropriate for their role and responsibilities, for fire-

fighting, emergency response, and hydrocarbon management.

Noise management

The Power Station has been designed to be fully enclosed, with noise abatement insulation and protection for the

equipment provided.

Page 107: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 92

8.3.3 Decommissioning and Closure Phase

Pre-construction and construction phase management measures will be applied for decommissioning and closure

activities associated with the Power Station, where relevant. The final end land use for the Power Station will be

determined through ongoing stakeholder consultation.

8.4 Monitoring Measures

Table 8-1 presents the key monitoring measures related to power supply for the Project. These will be

incorporated into the detailed monitoring programmes prepared by the Company and its contractors for all phases

of the Mako Gold Project.

Relevant guidelines and standards applicable to the Project are specified in Section 2.4 and the Registers of

Environmental and Social Management and Monitoring Commitments in Chapter 18 of this Plan.

Table 8-1 Register of Environmental Monitoring Measures – Power Station

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Power

Station

emissions

Ambient air

quality monitoring

All Project

phases

Air quality

monitoring

station (refer to

SOP04.16)

PM10, PM2.5,

SO2, NOx, CO

Threshold limits

provided in

Table 2-4

Bi-annually

Refer to monitoring

sites shown in

Figure A1

(Appendix C),

including:

Near Power

Station

At sensitive

receptors (e.g.

Tambanoumouya,

Linguekoto,

Niemenike, PNNK

Buffer Zone Site 1,

PNNK Buffer Zone

Site 2)

Road and

transport

Refer to Sections 9.4 for monitoring measures associated with road and transport for the Project, including for

vehicle exhaust emissions and transportation of hazardous materials (i.e. hydrocarbons).

Fire safety Fire safety

compliance

All Project

phases

Fire safety

compliance

monitoring

Fire safety

inspection

records

Checks of all fire

suppression

equipment to

ensure regular

maintenance

has been

undertaken

Training records

for fire-fighting

Weekly Power Station

Hydrocarb

on spills

and leaks

Routine

inspection for

potential leakage

or seepage of

hydrocarbons

All Project

phases

Visual check to

ensure there are

no visible

leakage or

seepage (refer

to SOP07.28)

Project

compliance

Regular (e.g.

weekly)

Power Station,

Fuel Depot and

other areas where

fuel is stored or

handled

Hydrocarbon All Project Review of Number , type Monthly and

Page 108: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 93

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

spills inventory phases relevant

registers and

records

maintained by

the Company

(refer to

SOP07.28)

(e.g. diesel, etc.)

and scale of

spills (i.e. small,

large, major)

occurred

Volume of

accidental

releases to the

receiving

environment

(including soils

an water), if any

Actions taken for

immediate

remediation

Annual

Power Station,

Fuel Depot and

other areas where

fuel is stored or

handled

Page 109: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 94

9 ROADS AND TRANSPORT

9.1 Objectives

Key objectives related to managing roads and transport for the Mako Gold Project include:

Ensuring compliance with international guidelines for transport of hazardous materials (including cyanide

and additional process reagents);

Minimising the impact of Project mine traffic and road infrastructure on the local communities and the

environment;

Managing transport safety for the Project; and

Maximising community benefits of Project road infrastructure.

9.2 Context

The paved National Road 7 (RN7) and the Main Access Road will be used as the primary haulage route during all

Project phases for supplies and material delivery. The RN7 is in varying states of repair and is primarily used by

heavy vehicles (39% of traffic) and light vehicles (33%), with five Niemenike villages, Mako and Badian 2 (a hamlet

of Marougoukoto) located directly adjacent this road. Vehicular use of this road also includes frequent

transportation of various goods and supplies for mining projects in the region, including hazardous materials and

hydrocarbon.

From the RN7, the existing rural Mako-Tambanoumouya access road network is comprised of unsealed roads.

Vehicle access is difficult during the wet season, particularly to Tambanoumouya, Kerekonko, Bomboya and

Soukouta (Socio-Economic, Land and Water Use Study, Earth Systems, 2015).

Project implementation will comprise the following road development:

Main Access Road: The Main Access Road will be constructed from RN7 to the PDA. The first section of the

road running from the RN7 west of Niemenike to the Mako-Tambanoumouya road will be 7.1 km in length

and 9 m wide. The second section will run parallel to the Mako-Tambanoumouya road for a 1.3 km stretch

and will then head north-west for a further 4 km towards the PDA, in part following an existing exploration

track. Parts of the road (in steep sections) may be sealed. There will also be a short access road of

approximately 750 m leading from the Mako-Tambanoumouya road to the WSD.

Additional Construction Phase Road Infrastructure: The existing road running parallel to the Gambia

River between Mako and Tambanoumouya will be upgraded for use during the Pre-Construction Phase

(prior to completion of the Main Access Road). The environmental and social impacts that may result from

the construction, operation and decommissioning / closure of proposed road developments are listed in

Table 9-2. The Company will conform to best industry practices for road construction and maintenance in

addition to implementing measures outlined in Section 9.3 to ensure these impacts are minimised.

Page 110: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 95

Table 9-1 Summary of potential environmental and social impacts associated with Project road infrastructure

Aspect Primary Potential Impact Phase of Project Initiating Project activity Impact

Duration C O D

Biodiversity Loss of habitat and biodiversity. Road establishment.

Permanent

Increased pressure on forested areas.

Habitat fragmentation and disruption to

local fauna migration between the Project

Area and PNNK.

Soil erosion Erosion. Vegetation removal and

ground disturbance during

construction; ongoing

sediment runoff from

unsealed access roads.

Permanent

Air quality Dust emissions. Construction activities and

Project road use.

Temporary

Noise Noise emissions. Construction activities and

Project road use.

Temporary

Water quality Sedimentation.

Ground disturbance during

construction.

Permanent /

Temporary

Pollution of surface and groundwater. Hazardous materials

storage and handling.

Waste Disposal of road construction debris and

wastes.

Construction activities. Permanent /

Temporary

Settlements

and land use

Permanent land use change. Road establishment. Permanent

Loss of timber and NTFP resources. Road establishment and

construction activities.

Permanent

Encroachment into communal and private

properties (e.g. farming land).

Construction activities. Permanent

Health and

safety

Injury and sickness to workers to the

community (e.g. flyrock from blasts, traffic

accidents, etc.).

Construction activities (e.g.

blasting)

Permanent /

Temporary

Project road use.

Local village

activities

Disruption to local village activities (e.g.

farming).

Construction activities. Temporary

Assets and

infrastructure

Impact to existing private and communal

infrastructure.

Road establishment and

construction activities.

Permanent /

Temporary

Archaeology

and cultural

heritage

Direct or indirect impacts on archaeology

and/or cultural heritage sites.

Road establishment and

construction activities.

Permanent /

Temporary

Page 111: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 96

9.2.2 Pre-construction and Construction Phase

No major disruption to existing roads are envisaged, however pre-construction phase upgrade of the access road

between Mako and Linguekoto may slow movement on this road for a short duration.

The majority of direct impacts will be from land clearance, road construction / upgrade and conversion of existing

land use to access roads. Biodiversity impacts will include habitat loss and fragmentation as well as increased

access to forested areas from construction of a new road making these areas more readily accessible for forest

resource extraction (e.g. increased hunting, timber, NTFP collection) (refer to ESIA, Volume A, Chapter 10).

If unmanaged, water quality impacts may occur from sedimentation of downstream watercourses from erosion of

cleared areas and unsealed road surfaces, and surface or groundwater pollution from fuel leakage or spillage

during construction activities.

Significant dust emissions during this period (from the perspective of social receptors) are expected to result from

using the current road network, construction of the Main Access Road near its intersection with RN7, and upgrades

to the existing road network during construction, particularly during the extensive dry season and annual

Harmattan winds.

Villages along the Project access road infrastructure and RN7 may also be exposed to increased risk of traffic

accidents from Project vehicles and moderate nuisance noise. Health and safety risks to construction personnel

and the community may also occur from flyrock associated with blasting for road construction.

9.2.3 Operations Phase

Unmitigated Project traffic on the local road network may lead to a number of environmental and social impacts

during Project operations, including:

Traffic related health and safety impacts to roadside communities, including increased road accidents and

moderate dust and noise nuisance;

Water quality impacts, including from erosion and sediment transport from unsealed access roads;

Road hazards from bulk transportation of hazardous materials (e.g. hydrocarbons, cyanide) and dangerous

goods (e.g. explosives) required for the Project. The potential for road accidents involving Project vehicles

that could lead to environmentally hazardous discharges have been considered in Chapter 9 of the ESIA

(Volume A) and the Risk Assessment (Volume B);

Increased traffic volumes and cumulative degradation of the local road network; and

Potential economic / livelihood / health impacts to roadside communities.

9.2.4 Decommissioning and Closure Phase

Following Project closure, the most significant impact will likely occur from the greater accessibility of the Wayako

Valley, which was previously less isolated from vehicles. This may lead to increased hunting pressure, timber

harvest and NTFP collection.

It is anticipated that the Company will transfer the majority of Project road infrastructure to the local government

or communities, providing lasting benefits to the region. Accordingly, the primary potential impacts may include:

Greater accessibility to forested areas, which could lead to increased illegal exploitation of forest resources

(e.g. hunting, timber and NTFPs), as above;

Maintenance costs for government / communities; and

Ongoing erosion of the unsealed road network and associated sedimentation of surface waters.

9.3 Management and Mitigation Measures

The Company will implement management and mitigation measures provided in this sub-section (and will include

them in the CEMP), to address potential impacts from Project road construction / upgrade and use of roads.

Page 112: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 97

Principal contractors for the Project will also be required to develop specific Environmental Management Plans

(EMPs) which incorporate measures detailed in the following subsections and as relevant to their work activities.

The Company will continue to monitor and adapt relevant measures throughout the life of the Project to ensure

they remain effective.

9.3.1 Pre-construction and Construction Phase

Construction environmental management

The Company has integrated best road design practices, and require contractors implement construction

techniques that are consistent with good industry practice. The full suite of SOPs provided in Appendix A will be

considered in the CEMP to manage environmental impacts as required, including:

SOP01: Erosion and Sediment Control;

SOP02: Water Quality and Pollution Management;

SOP04: Emission and Dust Control;

SOP05: Noise and Vibration Management;

SOP06: Waste Management;

SOP07: Hazardous Materials Management;

SOP08: Blasting Management;

SOP09: Land Clearance and Soil Stockpiling;

SOP10: Cultural Heritage Management; and

SOP11: Lighting and Visual Amenity Management.

Additional management measures to be implemented during this phase are specified below.

Vegetation and biodiversity management

As stated in Section 9.2, Project roads have been aligned to minimise vegetation clearance and habitat

fragmentation, and avoid environmentally sensitive areas such as an important water source (i.e. a spring used by

wildlife for drinking during the dry season).

The Company will implement key biodiversity management measures during construction including:

Applying applicable elements of the Biodiversity Action Plan (Volume C);

Minimising road and clearing widths to allow for greater connectivity of habitat (so that some species may

cross a small clearance width), and clearly define their boundaries with marker posts or equivalent to

prevent vehicles from deviating outside these boundaries;

Avoid impacts to environmentally sensitive areas wherever practicable as identified through the land

disturbance permitting system in place (SOPO9: Land Clearance and Soil Stockpiling). Sensitive areas will

be marked as ‘No Go Zones’;

Maintaining a relatively continuous canopy above linear or narrow clearings (e.g. roads) to reduce edge

effects (e.g. microclimate, light) and allow arboreal fauna to move without coming to the ground;

Night-driving to be avoided where practical, and night-driving techniques employed to avoid wildlife

collision, e.g. reduced speed limits and use of vehicle high beam lights;

Avoiding impacts to waterways and riparian vegetation during road construction to the extent practicable;

Progressively rehabilitate temporarily disturbed areas as soon as possible;

Restricting access to Project roads within the PDA (where appropriate) to authorised people only;

Page 113: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 98

Mandatory reporting of observed illegal activities (e.g. poaching, logging) and reportable wildlife incidents

that includes road accidents (e.g. collision with wildlife or livestock) for all Project workers and contractors

(refer to Chapter 16 , Biodiversity Management); and

In accordance with the Injured Wildlife Protocol (refer to Chapter 16, Biodiversity Management), roadkill will

be moved to the sides of roads so that scavenging wildlife (e.g. vultures, leopards) are not hit by other

vehicles, where practical. Appropriate PPE (e.g. gloves) will be used to minimise possible transmission of

zoonotic diseases (that can pass between animals and humans).

Water quality management

The Company will implement the following measures (adapted from the Mine site Water Management Handbook

(MCA, 1997) to minimise erosion and sedimentation to receiving waters from Project road infrastructure:

Appropriate road specification standards will be selected to minimise excessive earthworks with

subsequent requirements for large amounts of fill material;

Design of roads to include drainage systems that channel water from the road surfaces to outlets with

erosion and sediment control facilities, including rip-rap at inlets and outlets of culverts and channels and

sediment control basins constructed for larger catchment areas;

The gradient of all roads and tracks restricted to no more than +/- 10% to reduce erosion caused by runoff;

Roads to be constructed during the dry season to the extent possible. Erosion and sediment controls for

unsealed roads will be completed before the onset of the wet season;

Roads to be constructed with cross-fall slopes of (maximum 3%) to promote rapid drainage from unsealed

road surfaces to avoid scouring. Where cross-fall is insufficient, waterbars will be constructed to direct

water to road discharge channels that will be outfitted with velocity dissipaters and sediment control (e.g.

rip-rap, sumps and/or silt fencing);

Drainage from upslope of road surfaces to be diverted via roadside drainage channels to culverts with

velocity dissipaters and sediment control at outlets;

Culverts installed at drainage crossings s;

Permanent structures designed using an average peak storm recurrence interval of 100 years, and

temporary structures designed using an average recurrence interval of 2 years (24 hour storm events);

Batter slope angles will be minimised to the extent feasible; and

Where feasible, vegetation will be left intact on road verges and roadside batters to reduce surface flow

velocity and erosive potential.

In addition, relevant measures from SOP07: Hazardous Materials Management will be employed to manage any

potential for hydrocarbon or chemical spills during road construction activities.

Community road safety management

The Company will regularly engage with affected communities throughout the pre-construction and construction

phase to ensure associated impacts are appropriately managed (refer to Chapter 13, Community Engagement). In

addition, the Company will implement the following measures for managing community health and safety in

relation to transport:

Road design and construction methods will consider community road safety issues, including ensuring the

junction of the Main Access Road does not pass close to village settlement areas, lane closures, and

providing safe turning lanes off the RN7;

Appropriate traffic safety controls implemented and enforced, including road signage in both pictures and

words written in French for all roads within the PDA, (e.g. for reduced speed zone limits, warning signs,

pedestrian crossings) and speed bumps or pedestrian crossings through high risk areas (e.g. schools,

livestock crossings, etc.);

Page 114: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 99

Vehicular speed limits as follows: Maximum of 50 km/h for Main Access Road and other Project roads, Haul

Roads, and other Project roads; National speed limit on the RN7; and 20 km/h through villages, residences

or sensitive areas (e.g. school, known wildlife (e.g. West African chimpanzee) and livestock road crossings,

and environmentally sensitive areas, etc.);

Prior to construction, the Company will educate local villagers about traffic safety in collaboration with

relevant government authorities. This may include conducting road safety education classes in local

primary and secondary schools at key roadside communities along the Project transport routes;

Monitor and enforce transport safety protocols for all employees and contractors to minimise road

accidents, including:

» A ‘driver code of conduct’ for Project drivers and contractors;

» The use of private vehicles restricted once past the Project entrance boundary;

» Project vehicles to follow designated Project transport routes within permitted driving hours, subject to

approval by the Company’s OHS&E Manager. Approved routes to avoid passing through villages and

settlement areas (e.g. Niemenike) wherever possible;

» Off-site vehicle movements (e.g. delivery of supplies) to the day time, where practicable;

» Regular Project driver and contractor checks for adherence to local traffic laws;

» Speed restrictions for Project vehicles (see above for further details on speed limits to be provided);

» No driving is permitted on the Main Access Road during night-time. Employees and contractors will

require prior approval if night-use of the road is required during exceptional circumstances;

» Training to be provided to vehicle drivers on safe driving (e.g. collision avoidance), fatigue

management, and first aid training;

» Project vehicles equipped with first aid equipment and appropriate personal protection equipment

(PPE) (e.g. high visibility vest);

» Vehicles transporting oversized loads to be preceded by an escort ‘warning’ vehicle;

» Transportation of dangerous goods and hazardous materials to comply with measures specified in

Section 9.3.2 (including available spill kits);

» Zero tolerance on driving under the influence of drug and alcohol and proper fatigue management for

Project drivers. The Company will conduct regular compliance monitoring such as random breathalyser

and remote monitoring of driver performance;

» Project vehicles to meet road weight limits on the designated routes, including for bridge crossings;

» Safety inspections of Project vehicles will be conducted on a regular basis; and

» Road safety precautionary controls, such as restricting material deliveries (particularly for hazardous

materials and dangerous goods transport) and workforce movements during periods when more

vulnerable road users are present on the route (e.g. during school opening and closing times).

Detailed procedures and training as part of the Project-specific Emergency Preparedness and Response

Plans to be developed (refer to Section 3.7) for managing road accidents and transporting hazardous

materials; and

A road incident log and reporting system that enables road users and Project drivers to report road

accidents as well as unsafe driving / speeding involving Project vehicles. The database will capture relevant

information, e.g. date, time, location, persons involved, and any response required or action taken by the

Company.

Traffic and transport management

The Company will implement the following measures during construction to minimise road construction and

Project traffic impacts to road users on the local road network:

Page 115: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 100

Schedule for road works to be coordinated with relevant agencies and stakeholders to minimise traffic

disruption for public and private road users;

Community use of all Project roads will be permitted. However, there will be a control post just north of

Tambanoumouya to control access to the mine facilities;

Prior notification of planned road construction activities likely to cause nuisance noise and dust (e.g. blasts)

to potentially affected villagers;

Appropriate signage and traffic safety measures (e.g. barriers) for road works will be undertaken in

consultation with local government and key stakeholders;

All Project roads within the PDA signposted in French to provide directions to traffic movements;

Vehicle road trips and transport distances for material deliveries and workforce movements will be

minimised to the extent practicable by prioritising local materials and labour;

Optimised transport logistics for workers and materials delivery to minimise the number of Project vehicles

on the road. The Company will provide daily bus transportation for staff to and from the camp and work

sites, and to and from nearby villages and Kedougou;

The use of private vehicles restricted once past the Project entrance boundary;

Journey management plans and in-vehicle monitoring system to track all Project vehicles. Disciplinary and

corrective actions to be applied for non-compliances recorded (e.g. speeding, fatigue management, etc.);

Establishment of a vehicle and machinery maintenance programme for the Project to comply with relevant

standards and guidelines for transport safety and vehicle manufacturers’ instructions; and

Project Grievance Management Procedure for road users and villagers to register issues and complaints in

relation to road degradation caused by Project vehicles.

Community and land use management

Where possible, a number of Project road alignments have been refined to avoid impacts to settlement areas and

land uses. The Company will implement the following key measures to minimise potential settlement and land use

impacts and in-migration caused by Project road construction / upgrades:

Prior consultation with potentially affected villagers and local government on planned road construction

activities to minimise or mitigate potential impacts, where possible;

Prior to construction commencing, adequate compensation to directly and indirectly affected villagers

adversely affected by land or asset loss, to ensure that households achieve at least their pre-Project

wellbeing and standard of living;

Maintaining existing access routes to local sites and land uses to the extent practicable, or alternative

temporary access may be considered for unavoidable restrictions over a long period following proper

consultation with affected parties; and

Project Grievance Management Procedure to ensure that unanticipated land and village complaints can be

identified and resolved in a timely manner.

The Company will continue ongoing community engagement for the Project with affected communities to confirm

the effectiveness of strategies and make any improvements where necessary.

Blast management

The Company will ensure an appropriate Blast Management Plan is prepared and implemented prior to any blast

activities required for road construction. This plan will incorporate key safety measures to avoid potential health

and safety impacts from flyrock, including ensuring that no unauthorised vehicles or pedestrians can access the

blast exclusion zone, and restricting access controls at entry and exit points along Project roads.

Page 116: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 101

Air quality and noise management

The Company will establish an appropriate community consultation programme (refer to Chapter 13, Community

Engagement) covering all mine related traffic as well as a Project Grievance Mechanism to record and respond to

air quality, noise and vibration related complaints appropriately.

During road construction, the Company will implement the following measures to minimise air quality and noise

impacts:

Prior notification of planned road construction activities likely to cause nuisance noise and dust (e.g. blasts)

to potentially affected villagers;

Scheduling of road construction works to avoid night time near roadside communities to limit potential

disruption;

Blasts to avoid being conducted during unfavourable weather (e.g. dry and windy conditions from

Harmattan winds) to avoid excessive dust generation and dispersion, where possible; and

Implementation of the Project Grievance Procedure to enable villagers and road users to report any noise or

dust related complaints in relation to Project vehicles.

The Company will employ additional measures for managing air quality and dust impacts associated with

transport for the Project, including:

Regular watering of unsealed road surfaces and trafficked areas during the dry season or when excessive

dust generation is evident near sensitive receptors (e.g. villages / settlements). Dust suppression water will

be sourced from treated wastewater or raw water from the WSD. Frequency of watering will be increased

during periods of high risk (e.g. dry and windy conditions);

Project vehicle speed limits through villages 20 km/h;

Low emission diesel engines and/or catalytic convertors for Project heavy vehicles, trucks, and excavators

will be used, where possible;

Dusty material loads will be covered where transport is required through settlements;

Unsealed roads heavily trafficked by Project vehicles over a long period will be considered for future

application of gravel or paving; and

Regular maintenance of unsealed Project roads.

Key mitigation measures for the Project to manage noise and vibration impacts associated with transport include:

Ensure Project vehicles avoid overloading or unnecessary revving and queuing, particularly near community

sensitive receptors;

Prohibit idling, use of air brakes and reduce noise level of loud warning devices in settlement areas. Vehicles

will be turned off if parked near residences, offices or eating areas;

Retain existing vegetation screening to the extent practicable along Project road infrastructure and

consider planting vegetation buffers or creating earth mounds for noise shielding in particularly sensitive

areas (e.g. residential areas);

Seal uneven or rough road surfaces, or maintain road surfaces regularly to minimise surface unevenness,

particularly where trucks pass through (particularly for the Main Access Road); and

Train Project drivers in good driving practices to minimise noise impacts.

Waste management

All waste generated by road construction / upgrades will be managed in accordance with SOP06: Waste

Management. Hazardous wastes will be addressed with measures specified in SOP07: Hazardous Materials

Management.

Page 117: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 102

Cultural heritage management

Detailed archaeology and cultural heritage studies will be conducted in advance of all land disturbance activities.

Infrastructure corridors will be the subject of an archaeology and cultural heritage study in advance of Project

construction.

The Company will implement the Chance Find Procedure for the protection of physical cultural resources in the

PDA, as per Appendix B and SOP10: Cultural Heritage Management (Appendix A). Staff will be trained in the

implementation of SOP10, as relevant to their roles and responsibilities. A register will be maintained of all areas

that have been the subject of detailed archaeology and cultural heritage studies. The register will include all sites

and artefacts identified in the Project area. The Company will liaise with specialists regarding the documentation

and display of archaeology and cultural heritage artefacts identified in the Project area.

9.3.2 Operations Phase

Where appropriate, the Company will apply relevant management measures identified for the pre-construction

and construction phase during operations. Additional measures for implementation during the operations phase

are listed below.

Transportation of hazardous materials and dangerous goods

The Company has developed preliminary emergency response procedures for managing risks associated with

transportation of dangerous goods and hazardous materials, which are detailed in SOP07: Hazardous Materials

Management (Appendix A). The procedures will be further refined in the Emergency Preparedness and Response

Plans to be developed for the Project (refer to Section 3.7).

As per SOP07, hazardous substances and dangerous goods will be transported in accordance with relevant

legislative requirements and applicable international and national standards and guidelines, including:

International Cyanide Management Code Principles and Standards of Practice for cyanide handling, storage

and transportation (ICMI, 2014);

IFC General Environmental, Health and Safety (EHS) Guidelines 2007 (particularly Chapter 1.5 Hazardous

Materials Management and Chapter 3.5 Transport of Hazardous Materials);

United Nations, Transport of Dangerous Goods - Model Regulations. 17th Revised Edition (Volume 1)

Geneva 2011;

AS 1940 – The Storage and Handling of Flammable and Combustible Liquids. (Current 2004 ed.); and

AS 2187 – Explosives – Storage, Transport and Use. (Current 1998 ed.).

Explosives and other hazardous materials will be transported by a suitably licensed and reputable carrier (e.g. ICMI

2014 Cyanide Code-compliant transporter). Management of risks and emergency response to spills or accidents

during the transport of hazardous materials and dangerous goods will be the responsibility of the licensed carrier.

Key measures to adopt by the contractor for the transportation of hazardous materials and dangerous goods

include:

A road safety and maintenance programme for transport vehicles that includes procedures for vehicle and

tire inspections, preventive maintenance, drivers fatigue management and permitted driving hours, tie-

down of loads, and actions to be taken if severe weather conditions are encountered;

Careful consideration of transport distances and routes;

Where appropriate, the Contractor will arrange for a specialised escort ‘warning’ vehicle where transport

routes present safety or security concerns for the transport of cyanide, explosives and other dangerous

goods or hazardous materials;

Audit of health and safety documentation of transporters for hazardous materials and dangerous goods to

be engaged, to ensure they are adequate and compliant with legislative requirements;

Cyanide transporters to be compliant with the Cyanide Code (ICMI, 2014). The code-compliant transporters

will be required to prepare a detailed procedure for cyanide transport to the Project site, and provide

Page 118: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 103

options where necessary to minimise risks in consultation with community and other stakeholders. The

escort contractor must be a signatory to the Cyanide Code (ICMI, 2014) for cyanide transport;

Project vehicles carrying dangerous goods and hazardous materials will travel in off-peak times when there

is less traffic on roads to the extent practicable. Procedures for regular communications between transport

vehicles and the transporter contractor will be in place;

Drivers of dangerous goods and hazardous materials adequately trained to handle local road conditions and

follow safety protocols;

The contractor will develop specific emergency response and clean-up procedures for road transport ;

Drivers transporting dangerous goods and hazardous materials will be adequately trained on appropriate

emergency response and clean-up procedures to follow in the case of a spill;

The contractor will provide appropriate PPE and clean-up skill kits (including for cyanide specific PPE and

neutralising agents, where appropriate) for drivers transporting hazardous materials and dangerous goods,

including gloves, plastic coveralls, safety glasses and self-contained respirators, etc.; and

Inventory controls and/or chain of custody documentation in place to identify the loss of any hazardous

material during transport (refer to SOP7, Appendix A).

Prior to Project construction, a specific Waste Management Plan will be developed for the Project incorporating

key measures and procedures to follow for the safe transportation, handling, and disposal of cyanide, hydrocarbon

and other hazardous materials and dangerous goods.

Vegetation and biodiversity management

The Company will implement relevant measures to minimise potential impacts on aquatic and terrestrial

biodiversity as detailed in Chapter 16, Biodiversity Management and the Biodiversity Action Plan (Volume C),

including:

Collaboration with the PNNK area managers to ensure impacts on the integrity of the PNNK and

surrounding forested areas are adequately mitigated;

Requirement for employees and contractors to report any observed illegal activities and wildlife encounters

(including injured wildlife) that may impact biodiversity values along access roads; and

Specific procedures that will be followed to prevent invasive weed spread, vehicle washdown, regrowth

maintenance, and injured wildlife management.

Page 119: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 104

9.3.3 Decommissioning and Closure Phase

It is anticipated that the Main Access Road, remaining Road Infrastructure, and workforce accommodation

facilities will be transferred to the local government or communities (pending stakeholder consultation). Road

infrastructure in the PDA will be rehabilitated. The RCMCP (Volume E) specifies management measures for the

decommissioning of access roads, including:

Road borders and embankments to be progressively re-vegetated where necessary for erosion control;

Rehabilitation of roads will be undertaken by:

» Road related structures will be removed where practicable, including road signage, culverts, oil or

grease traps and hydrocarbons (if applicable).

» Rehabilitate Project roads (unless they will be made available for community use) by ripping road

surfaces, re-shaping to pre-construction contours, and stabilising and revegetating with native plant

species of local provenance; and

» Road drainage will be re-directed as necessary to minimise erosion until vegetation is established.

An earth berm will be constructed across the Main Access Road to maintain community safety.

For Project infrastructure that will be transferred for future use by local government or community, the Company

will consult and negotiate with the relevant parties and stakeholders to ensure that:

Remaining mine facilities (e.g. TMF) that may pose a safety risk to the public are adequately secured; and

Maintenance requirements and associated costs are clearly defined.

9.4 Monitoring Measures

Table 9-2 lists the key monitoring measures related to Project roads and transport. These will be incorporated into

the detailed monitoring programmes prepared by the Company and its contractors for all phases of the Mako Gold

Project.

Relevant guidelines and standards applicable to the Project are specified in Section 2.4 and the Registers of

Environmental and Social Management and Monitoring Commitments in Chapter 18.

Table 9-2 Register of Environmental Monitoring Measures – Roads and Transport

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Air quality

and dust

Dust

monitoring

Pre-

construction,

Construction,

Operations

Visual check for

excessive dust and

Project Grievance

mechanism (refer to

SOP04.16)

Project

compliance and

logged dust

complaints

Threshold limits

provided in Table

2-4

Daily

Key sensitive

receptors (e.g.

residence,

school) in

roadside

communities

along Project

road transport

routes (note

there are no

monitoring

sites proposed

for Project road

transport

routes at

present)

Pre-

construction,

Construction,

Operations

Monitoring using dust

gauges (refer to

SOP04.16).

Dust deposition

rate, PM10, and

PM2.5

Threshold limits

provided in Table

2-4

Bi-annual (no

sensitive receptors

currently directly

on Project access

roads - if new

receptors are

located directly

along routes, this

will be updated to

continuous

monitoring)

Page 120: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 105

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Noise

and

vibration

Noise and

vibration

monitoring

Construction,

Operations Refer to SOP 05.12

Noise levels in

dB(A) LAeq

(daytime and

night-time period

Threshold limits

provided in Table

2-8

Bi-annual

Process Plant

(refer to

monitoring

sites shown in

Figure A1,

Appendix C)

All Project

phases

Refer to SOP 05.12

and Project

Grievance

mechanism

Project

compliance and

logged noise

complaints

Threshold limits

provided in Table

2-8 and Table

2-9

Ongoing

Key sensitive

receptors (e.g.

roadside

communities)

along the

Project road

transport

routes,

particularly for

the Main

Access Road

(refer to

monitoring

sites shown in

Figure A1,

Appendix C)

Water

quality -

ambient

Routine

ambient

water quality

monitoring

Construction

Visual checks for

sedimentation, oils

and grease (refer to

SOP2.10)

Project

compliance Weekly

Discharge

points (refer to

monitoring

sites shown in

Figure A2,

Appendix C)

All Project

phases Refer to SOP02.12

Field parameters

and laboratory

testing as listed

in SOP02.12

Threshold limits

provided in Table

2-5 to Table 2-7

Monthly

Upstream and

downstream of

Badalla creek

and Gambia

River (refer to

monitoring

sites shown in

Figure A2,

Appendix C)

Transport

ation of

hazardou

s

materials

and

dangerou

Monitor

compliance

with

international

and national

requirements

for the

All Project

phases

Audit and review of

licensed and certified

suppliers /

transporters (refer to

SOP07.09)

Project

compliance Annual

Project-wide

(including road

transport

routes)

Page 121: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 106

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

s goods transportation

of hazardous

materials and

dangerous

goods

All Project

phases

Review of hazardous

materials and

dangerous goods

inventory, tracking

and chain of custody

documentation

maintained by the

Company (refer to

SOP07.28)

Volume of

hazardous

material and

dangerous

goods

transported

Volume of

hazardous

materials and

dangerous

goods

transported

across

international

boundaries

Project-wide

(including road

transport

routes)

Incident

register to

include spills

All Project

phases

Record any road

transport related spills

of hazardous

materials in the

Project spills

inventory (refer to

SOP07.28)

Number, type,

scale

Volume

Remediation

actions taken

Ongoing

Loss of

habitat,

vegetatio

n and

biodiversi

ty

impacts

Monitoring of

vegetation

clearing

Pre-

Construction,

Construction

Monitor vegetation

clearing to check it is

confined to clearly

demarcated areas of

disturbance (refer to

SOP09.2).

Extent of

vegetation

cleared for the

Project

During vegetation

clearing

Project-wide

(including for

Project road

infrastructure

and upgrades)

Incident

reporting

system for

Project staff

and

contractors

All Project

phases

Incident reporting

system maintained by

the Company

Reportable

observed illegal

activities (e.g.

poaching, illegal

logging, etc.)

and road

incidents (e.g.

collision with

wildlife or

livestock)

Ongoing

Road

safety

and

environm

ental

complian

ce

Safety

inspections of

Project

vehicles

All Project

phases

Audit of vehicle

checklist to complete

Schedule and

records of

completed

checklists

Daily prior to

driving a vehicle

Project-wide

(including for

Project road

infrastructure

and upgrades)

Road safety

and

environmenta

l compliance

of Project

vehicle and

equipment

fleet

All Project

phases

In-vehicle monitoring

system

Traffic incident

reporting system for

the community and

Project workers

Road safety and

driver compliance

monitoring

Records of traffic

incidents,

including date,

time, location,

persons

involved, and

any actions

taken or

required by the

contractor or the

Ongoing

Page 122: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 107

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Company

Records of

driving training

and

qualifications

Random

breathalyser and

remote

monitoring of

driver

performance

All Project

phases

Project vehicle fleet

database and

maintenance

programme

General vehicle

condition and

safety

Check of vehicle

brakes and tyre

air pressure

Regular vehicle

exhaust and

noise emission

test for

compliance with

relevant

emissions

standards for

noise and air

pollution

Maintenance in

accordance with

the vehicle

manufacturer’s

instructions

Smoke belching

vehicles and

equipment will

be fixed or

replaced

Any leakage of

engine fluids will

be immediately

fixed

Periodic

Vehicle

Workshop and

other vehicle

maintenance

areas as

appropriate

Road

integrity

Routine

maintenance

of Project

roads

All Project

phases

Visual check of road

condition

Project Grievance

mechanism

Incident register

Reportable

traffic

observations,

complaints and

incidents

Ongoing

Project-wide

(including for

Project road

infrastructure

and upgrades)

Blast

impact

Mine blast

monitoring

Construction,

Operations

Routine monitoring of

noise, airblast,

ground vibration, and

flyrock impacts (refer

Blast analysis

and audits

Noise, airblast,

ground vibration,

Periodic (e.g.

when there is a

change of blast

location)

Within 500 m

of blast areas

Page 123: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 108

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

to SOP08.12)

and flyrock

parameters

(refer to

SOP08.12)

Threshold limits

provided in Table

2-4 to Table 2-10

Blast

exclusion

zone

Construction,

Operations

Visual observation for

unauthorised people

within the PDA

Project

compliance

Zero incident

record for blasts

Prior to blasting

Page 124: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 109

10 ACCOMMODATION FACILITIES

10.1 Objectives

Key management objectives related to accommodation facilities for the Mako Gold Project will include mitigating

potential impacts of the construction and operation of Project accommodation and complying with associated

legislative requirements.

Furthermore, the Company is committed to ensuring Project accommodation maximises the economic benefits

for villages directly impacted by the Project, by implementing the measures specified in the Worker

Accommodation Guidance Note (rePlan, 2015a), which includes the development of a Worker Accommodation Plan

for the Project.

10.2 Context

The Company has developed worker accommodation strategies detailed in the Worker Accommodation Guidance

Note (rePlan, 2015a). Key outcomes of the worker accommodation strategies established is summarised as

follows:

The need for accommodation facilities has been minimised via sourcing local personnel (where workers can

potentially live at home) to the extent practicable. Accommodation support from the Company will be

largely for non-local workers. Kedougou has the highest capacity to absorb influx of the communities in the

Project area, and this area will be the focus of worker accommodation strategies;

The Company will provide eligible workers accommodation onsite while the remaining workforce will be

lodged off-site within daily commuting distance of the Project, i.e. within the Tomboronkoto Commune and

broader Kedougou Region;

Pre-construction workers will be housed in the existing Exploration Camp onsite, which was previously used

for exploration activities for the Project. Construction of a new Accommodation Camp located onsite near

the WSD will commence concurrently and it is intended that this facility will provide accommodation

during Project construction and operations;

Construction workers will be accommodated both in the existing Exploration Camp and new

Accommodation Camp onsite. As a shortage of approximately 50 to 80 camp beds is expected during the

peak construction period, temporary demountable accommodation facilities will be provided near the new

Accommodation Camp to meet the temporary shortage;

The new Accommodation Camp will fully provide for all Project on-site staff accommodation requirements

during the operations phase; and

Incentives will be used to help support and encourage workers to find safe, affordable and comfortable

living arrangements locally, as further described in the Worker Accommodation Guidance Note (rePlan,

2015a).

The primary potential impacts associated with workforce accommodation during each phase of the Project,

detailed in the ESIA (Volume A), are summarised below.

Page 125: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 110

10.2.1 Pre-construction and Construction Phase

The environmental and social impacts associated with construction of the on-site new Accommodation Camp are

expected to be typical of site preparation and establishment of building infrastructure and services.

If unmitigated, the primary impacts from this workforce accommodation during the pre-construction and

construction phase may include:

Surface and groundwater quality pollution (e.g. accommodation effluent and waste, sediment transport

from disturbed areas, hydrocarbons from vehicles/equipment, and inputs from general construction refuse);

and

Nuisance level air quality and noise for nearby sensitive receptors resulting from site preparation,

construction and vehicle movements.

In addition, the existing Exploration Camp and off-site workforce accommodation also poses transport safety

impacts risks to road users and roadside communities from staff and contractors daily movements to and from the

Project site on the local road network, and greater vehicular noise and dust impacts. Nearby sensitive receptors

(e.g. residences) may also experience minor noise disturbance from residing workers (e.g. audible chatter, TV and

radio noise, etc.), depending on their proximity.

Further impacts are discussed in the ESIA (Volume A). The Company will adopt appropriate environmental

management practices to ensure adverse impacts during this phase are adequately minimised.

10.2.2 Operations Phase

During Project operations, the following potential water quality impacts from workforce accommodation will

require careful management, mitigation and monitoring:

Surface water quality impacts associated with greywater and raw sewage generation (e.g. nutrients and

pathogens) from kitchen / ablution facilities if discharging into the receiving environment;

Pollution from general refuse (e.g. kitchen waste, packaging, metal and plastic); and

Contamination of water or soil from hydrocarbon leakage or spills in the diesel storage areas.

In-migration (including migrant workforce and expatriates) associated with the Mako Gold Project also has the

potential to affect local communities, primarily in the following ways:

Changes to the local demography (including gender imbalance and reduced availability of labour for non-

mining related activities such as farming and agriculture);

Increased pressure on existing community services and infrastructure such as the road network, health

facilities and law enforcement;

Ethnic and religious conflicts, increased incidents of illegal or immoral activities such as crime, alcohol and

drug abuse, and exploitation of vulnerable groups (e.g. prostitution of women and children) and Indigenous

people; and

Community health and safety impacts, including the spread of sexually transmittable infections (STIs) and

other communicable diseases (e.g. malaria, dengue fever, etc.).

10.2.3 Decommissioning and Closure Phase

Much of the accommodation infrastructure will be designed to facilitate ease of dismantling and reuse following

closure. It is anticipated that impacts will be negligible, and likely similar in nature to the pre-construction and

construction phase impacts.

Depending on the outcome of ongoing stakeholder consultation, the Company may transfer the ownership of

existing accommodation camps to the local government or village for future reuse following decommissioning.

Page 126: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 111

10.3 Management and Mitigation Measures

The new Accommodation Camp will be located onsite at a significant distance from surrounding communities (i.e.

no closer than 3 km). The rural siting of the camp sites will substantially help minimise potential impacts to

community and social receptors, e.g. avoidance of noise, visual amenity (e.g. lighting), and negative interactions

between Project staff and local people.

The following sub-sections details the management measures that the Company will adopt to manage adequately

environmental and social impacts associated with workforce accommodation facilities for the Mako Gold Project.

10.3.1 Pre-construction and Construction Phase

The Company will implement relevant SOPs provided in Appendix A to manage potential impacts generated

during construction, including:

SOP01: Erosion and Sediment Control;

SOP02: Water Quality and Pollution Management;

SOP04: Emission and Dust Control;

SOP05: Noise and Vibration Management;

SOP06: Waste Management;

SOP07: Hazardous Materials Management;

SOP09: Land Clearance and Soil Stockpiling; and

SOP11: Lighting and Visual Amenity Management.

The Company will undertake a final review of proposed locations for the new Accommodation Camp and

temporary demountable accommodation camp site to confirm no significant environmental, social or cultural

values will be affected prior to construction commencing.

10.3.2 Operations Phase

Applicable environmental management SOPs provided in Appendix A will be employed as necessary during

Project operations in combination with the below strategies and measures for worker accommodation.

In-migration

The Company will mitigate the adverse impacts arising from Project induced in-migration. The Company will

monitor the impacts of in-migration in consultation with local authorities and communities in Project affected

villages. Chapter 15 provides further details of the Company’s planned actions for managing in-migration, which

will primarily comprise of:

Provision of daily bus transportation for Project staff between the Project site and Kedougou town to

enable workers to live and commute from Kedougou without suffering from fatigue;

A social and environmental awareness programme to educate non-local Project workers about local cultural

and environmental sensitivities. Local staff will also receive cultural awareness training to promote

understanding of migrant and expatriate workers;

Provision of proper hygiene and sanitation practices and facilities (e.g. camp water treatment plant for

sewage and wastewater, waste management facilities), and preventive measures to avoid the transmission

of communicable diseases (including STIs) between Project staff and the local community, as further

detailed in Section 14 (Community Health and Safety);

Where practicable, integrating sustainable design options in camp facilities to minimise electricity and

water requirements, such as solar panels, solar hot water systems, and stormwater capture and reuse

systems (e.g. rainwater tanks); and

Page 127: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 112

Ongoing community engagement and consultation throughout the life of Project to ensure community

concerns or grievances with respect to workforce accommodation are appropriately addressed.

Sanitation and hygiene

The Company will ensure augmentation of potable water supplies as necessary. Enough potable water (compliant

with WHO 2011 drinking water standards) will be provided to staff accommodated in camp sites, and all

wastewater and raw sewage generated from kitchen, bathrooms, and toilets will be treated to meet relevant

discharge standards (refer to SOP02: Water Quality and Pollution Management, Appendix A). Raw water from the

Gambia River will be treated for potable use in the accommodation camps via a modular potable water treatment

plant (including filtration, ultra-violet sterilisation and chlorination) and distributed for drinking, site ablutions,

safety showers and other potable water outlets. The plant will have additional capacity for providing potable

water to allow for future workforce expansion.

During Project operations, a site based sewage treatment plant (STP) will treat raw sewage and wastewater from

various sources, including from the accommodation camps. Suitable treatment plant sludge from the STP

(estimated at < 50 kg/day) will most likely be disposed of by direct landfill burial in unlined pits (Coffey, 2015).

Treated effluent water from camp sites (estimated at 50 – 100 m3/day) will be disposed of via leach drains.

Medical and sanitary waste will be disposed of as per SOP07: Hazardous Waste Management, while relevant

worker disease prevention measures will be employed as detailed in Chapter 14, Community Health and Safety. In

addition, accommodation camps will be made ‘mosquito proof’ as far as practicable by ensuring doors and

windows are adequately sealed, suitable ventilation systems are installed, and mosquito nets provided as required.

Waste management

The Company will implement proper waste management procedures for the collection, separation, and disposal of

Project wastes (refer to above). Suitable waste management facilities will be constructed and operated in

accordance with SOP06: Waste Management (Appendix A). The Company will apply the preferred waste

management hierarchy, with opportunities for waste minimisation, reuse and recycling implemented where

practicable.

Putrescible waste such as food scraps and kitchen wastes from the site based accommodation camps will be

disposed of in a suitably designed and lined landfill within the PDA. Other non-recyclable and non-hazardous solid

waste will also be disposed of at the engineered landfill, while recyclables will be recycled with an approved

contractor, where available.

General safety and hydrocarbon storage and handling

Liquid hydrocarbon products (e.g. diesel) required for site power generation at accommodation facilities will be

stored in appropriately bunded tanks (to meet 110% of stored volume capacity) in accordance with SOP07:

Hazardous Materials Management (Appendix A). Regular machinery maintenance (e.g. of diesel generators) will

help minimise the risk of diesel spillage/leakage.

The Company will ensure that each accommodation facility is equipped with adequate fire-fighting equipment

(e.g. fire extinguishers), first aid kits, medical waste disposal facilities, alarm systems; and nominated staff are

provided suitable emergency training (e.g. fire warden). Emergency procedures will be developed to respond to

emergency situations such as fires as part of the Project Emergency Preparedness and Response Plans (to be

developed), with fire evacuation plans posted at strategic locations throughout each facility.

Access to the accommodation camps will be restricted to Project staff and people with an authorised visitor pass.

No staff will be allowed outside the camps between the hours of seven pm till morning.

Dust management

A dust suppression programme for the Project will be employed, involving regular water of unsealed roads, heavily

trafficked areas, and where excessive dust is evident.

Revegetation of disturbed areas around camp sites immediately following construction will also assist in

minimising localised dust generation and attenuate potential visual and noise impacts.

Page 128: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 113

Transport safety risks

The Company will provide mandatory induction for safe driving practices for all relevant Project staff (including

staff living offsite) to minimise potential transport safety risks. These are further specified in detail in Chapter 9

(Roads and Transport), but include relevant measures such as:

Mandatory driving licence and induction for Project drivers on local road rules and safety;

Road safety protocols including speed limits through settlement areas, zero tolerance for drugs and alcohol

use while driving, and fatigue management;

Establishment of a notification system (Grievance Mechanism) where road users and residents may report

dangerous driving by Project drivers to the Company; and

Established procedures for the proper transportation of flammable materials (e.g. diesel) and emergency

response for traffic accidents involving Project vehicles.

In addition, the Company will provide a shuttle bus service between accommodation camp sites and work sites as

well as to and from nearby villages and Kedougou, to minimise Project road safety impacts. Further details are

specified in Chapter 9 (Roads and Transport).

Noise management

The new Accommodation Camp has been sited to ensure mine related noise and vibration emissions do not cause

unacceptable disturbance for residing staff. For the off-site camp sites, quiet hours will be enforced whereby noisy

activities will be prohibited for a suitable timeframe.

10.3.3 Decommissioning and Closure phase

If transferring ownership for an accommodation facility is agreed to with the government or local communities

(pending the results of stakeholder consultation), the Company will conduct site soil and groundwater testing to

determine whether treatment is required for any unintentional contamination from a hydrocarbon spill or other

hazardous substances. Where hydrocarbons are found in soils, the material will be volatilised, with the residual

waste transferred to the TMF. Accommodation facilities will meet all closure criteria prior to asset transfer or

decommissioning and rehabilitation (refer to the RCMCP, Volume E).

10.4 Monitoring Measures

Table 10-1 summarises the key monitoring measures that will apply for accommodation facilities associated with

the Project. These will be incorporated into the detailed monitoring programmes prepared by the Company and

its contractors for all phases of the Mako Gold Project.

Relevant guidelines and standards applicable to the Project are specified in Section 2.4 and the Registers of

Environmental and Social Management and Monitoring Commitments in Chapter 18 of this Plan.

Page 129: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 114

Table 10-1 Register of Environmental Monitoring Measures– Accommodation Facilities

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

In-migration

related

issues

Refer to Sections 14.4 and 15.4 for relevant monitoring measures associated with community health and safety,

and Project in-migration.

Water

quality -

discharge,

ambient

and

drinking

water

Routine water

quality monitoring

Pre-

construction,

Construction

Refer to

SOP02.9 and

SOP2.10

Key parameters:

Turbidity, TSS,

DO, temperature,

electrical

conductivity

(EC), and pH

Visual checks for

sedimentation,

oils and grease

Threshold limits

provided in Table

2-5 to Table 2-7

Weekly

Discharge

points (refer to

monitoring sites

shown in Figure

A2, Appendix C)

Discharge water

quality monitoring of

treated effluent and

wastewater from

water treatment

plants

Pre-

construction,

Construction,

Operations

Refer to

SOP2.14

Key parameters:

Total and faecal

coliform, Total

nitrogen, Total

Phosphorous,

COD, and BOD

Threshold limits

provided in Table

2-7

Periodic

(during

discharge)

At treated

effluent

discharge points

(refer to

monitoring sites

shown in Figure

A2, Appendix C)

General

waste

Detailed inventory

of waste streams

generated by

workforce

accommodation

All Project

phases

Refer to

SOP06.16

Composition and

waste type

according to

different waste

streams

Quantity and

storage location

Transport and

disposal

methods (e.g.

safe disposal

certificates)

Final destination,

including amount

of each waste

type that has

been recycled or

reused

Ongoing

At each

accommodation

facility

Hydrocarbo

n leakage /

spillage

Routine inspection

for potential leakage

or seepage of

hydrocarbons (e.g.

diesel)

All Project

phases

Visual check to

ensure there are

no visible

leakage or

seepage (refer to

SOP07.28)

Project

compliance

Regular

(e.g.

weekly)

Hydrocarbon

storage areas at

each

accommodation

facility Hydrocarbon spills

inventory

All Project

phases Review of

hydrocarbon

Number , type

(e.g. diesel, etc.)

Monthly and

Annual

Page 130: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 115

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

spills inventory

maintained by

the Company

(refer to

SOP07.28)

and scale of

spills (i.e. small,

large, major)

occurred

Volume of

accidental

releases to the

receiving

environment

(including soils

an water), if any

Actions taken for

immediate

remediation

Air quality Dust monitoring All Project

phases

Visual check for

excessive dust

and Project

Grievance

mechanism

(refer to

SOP04.16)

Project

compliance,

logged dust

complaints

Threshold limits

provided in Table

2-4

Daily

At sensitive

receptor, e.g.

residence near

a camp site

(refer to

monitoring sites

shown in Figure

A1, Appendix C)

Transport

safety Refer to Sections 9.4 and 10.4 for relevant monitoring associated with Project traffic and workforce transport.

Noise

Investigative

monitoring of

nuisance noise

All Project

phases

Project

Grievance

mechanism

(refer to SOP

05.12).

Project

compliance,

logged noise

complaints

Threshold limits

provided in Table

2-8

As required

At sensitive

receptor, e.g.

residence near

a camp site

(refer to

monitoring sites

shown in Figure

A1, Appendix C)

Page 131: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 116

11 BORROW AREAS AND QUARRIES

11.1 Objectives

Key management objectives related to borrow area and quarries for the Mako Gold Project will include:

Complying with legal requirements and environmental and social standards and guidelines;

Minimising potential impacts of quarry and borrow area operations; and

Meet safety requirements of quarry and borrow area operations.

11.2 Context

The Project will require significant amounts of gravel, fill and sand as construction material for the Mine Pit, WRD,

and TMF as well as ancillary mine facilities (e.g. Process Plant, and access roads). Based on the current Project

designs, approximately 6,500 t of aggregate and rip-rap (crushed stone), 4,950 t of sand, and fill material

(engineering grade clay-rich material) will be required to support the mine development and associated

infrastructure.

Where possible, these will be obtained from suitable sources available onsite during the pre-construction and

construction phase, and ongoing mine development. However, a number of borrow areas and quarries will likely

be required to supplement the needs for Project construction material requirements, where the amount of suitable

material available onsite is insufficient.

A preliminary study of local sand availability indicates additional sand supplies will most likely be required from a

larger source outside the Mining Concession to fully satisfy Project demand for sand. An initial 2,000 t of sand will

be required in the months preceding civil works, followed by an average of three to four trucks per week during

construction to provide the remaining material progressively in small quantities stockpiled onsite (used as

required, with additional sand delivered to the site as needed).

The development of borrow pits and quarries will primarily occur during the pre-construction and construction

phase, with the majority of impacts expected to be limited to this phase. The Company envisages engaging a

contractor to produce the required aggregate at the quarry sites, operating a portable crushing plant over a two to

three month period (excluding time for mobilisation). Aggregate will be stockpiled at the quarry site and

progressively trucked to the Project site over the following seven months. It is expected the production of

aggregate will be a one-off activity meeting the full Project requirements.

The full impact assessment of borrow areas and quarries for the Project is provided in the ESIA (Volume A). The

Company will conduct further investigation of the stone and sand quality required to confirm suitability.

11.2.1 Pre-construction and Construction Phase

The Company has undertaken an initial site evaluation of existing borrow pits and quarry sites situated locally, and

has identified three existing quarry sites, including the quarry and gravel stockpile recently used for the RN7

upgrade. This site is equipped with a loading ramp and laydown area for stockpiling crushed aggregate and is

ready for immediate re-commissioning. Preliminary investigations of the basalt rock available at this site confirm

it as the preferred site as it can provide suitable materials.

The new Main Access Road entering the Project site is planned for establishment during pre-construction, before

trucking of bulk materials (including gravel, sand and fill) transportation commences.

Borrow pits and quarries no longer required at the end of this phase will be progressively decommissioned and

rehabilitated.

Page 132: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 117

11.2.2 Operations Phase

During Project operations, a small number of borrow areas and quarries will be retained to provide fill material and

gravel for ongoing development of the TMF and WSD embankment, and Project road maintenance, as needed.

These sites will be managed and operated as per during the construction phase.

11.2.3 Decommissioning and Closure Phase

Where required, borrow pits and quarries no longer required during Project operations will be progressively

decommissioned and rehabilitated at the end of this phase.

11.3 Management and Mitigation Measures

11.3.1 Pre-construction and Construction Phase

The use of existing quarries and borrow pits including the preferred one located on the RN7, will greatly assist in

avoiding significant construction impacts associated with site preparation for a new quarry site or borrow pit, e.g.

change to existing landform, land clearance, and vegetation removal. The Company will require contractors to

operate the portable crushing plant during daytime only, to avoid potential night-time disturbance.

The establishment of the Main Access Road initially during this phase will also assist in minimising potential

transport impacts on the local communities and the environment, by avoiding direct impacts on the existing local

road network.

Best management practices will be adopted by the Company and contractors for the development and operation

of borrow pits and quarries including:

Minimising the footprint disturbance area;

Limiting the number of rock and borrow pit cuts required;

Minimising site erosion and sedimentation through appropriate control measures (SOP01);

Restricting access to the public; and

Progressive rehabilitation of sites as they become no longer needed.

SOP09 (Appendix A) provides specific requirements for the construction and operations of borrow pits and quarry

sites in an environmentally responsible manner. The Company will further require contractors to incorporate these

in its CEMP, as well as applying other SOPs for managing significant impacts associated, such as (refer to Appendix

A):

SOP1, SOP2 and SOP3 for managing water quality impacts associated with disturbed surfaces and surface

water management;

SOP07 for the adequately storing, handling and disposing of hazardous materials onsite (e.g. hydrocarbons,

explosives, etc.);

SOP04 for managing dust and air quality impacts associated with handling of dusty materials;

SOP05 for managing noise and vibration impacts to nearby community receptors, if applicable; and

SOP10 for managing potential cultural heritage impacts, including use of the Chance Find Procedure

developed for the Project (Appendix B).

The management of vehicle emissions and road safety / transport (including for hazardous materials and

dangerous goods) associated with trucking sand, gravel and fill material to the Project site are provided in Section

9.3 and will be incorporated into the CEMP. Additional measures that will be applied to these sites for managing

biodiversity impacts are provided in Chapter 16 (Biodiversity Management), and the Biodiversity Action Plan

(Volume C).

Page 133: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 118

Monitoring for water quality, air quality and safety aspects of borrow pits and quarries used by the Project will be

conducted, where necessary. Ongoing consultation and the implementation of a Project grievance management

system will ensure that unanticipated community impacts will be adequately managed.

The selection of any new quarry or borrow pit will follow the protocol detailed in SOP09: Land Clearance and Soil

Stockpiling (Appendix A).

Decommissioning and rehabilitation

The progressive decommissioning and rehabilitation of borrow pits and quarries no longer required throughout

the life of the Project will be undertaken as per the strategies and measures detailed in the Rehabilitation and

Conceptual Mine Closure Plan (RCMCP) (Volume E). The main aspects that will be adopted by the Company and

contractors include:

Rehabilitation of the site as soon as possible to final natural landform taking into account pre-disturbance

state, public and wildlife safety, and community consultation outcomes;

Stabilisation of disturbed land surfaces to promote natural revegetation; and

Adequate site drainage to avoid water quality issues and erosion.

11.3.2 Operations Phase

The management measures and strategies specified for the pre-construction and construction phase management

will continue to be applied during Project operations, where relevant.

11.3.3 Decommissioning and Closure Phase

Refer to Section 11.3.1 for detailed measures on the decommissioning and rehabilitation of borrow areas and

quarries no longer used throughout the life of the Project.

11.4 Monitoring Measures

Table 11-1 summarises the key monitoring measures that will apply for borrow areas and quarries required for the

Mako Gold Project. These will be incorporated into the detailed monitoring programmes prepared by the

Company and its contractors for all phases of the Project.

Relevant guidelines and standards applicable to the Project are specified in Section 2.4 and the Registers of

Environmental and Social Management and Monitoring Commitments in Chapter 18 of this Plan.

Table 11-1 Register of Environmental Monitoring Measures– Borrow Areas and Quarries

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Water

quality

Routine water

quality

monitoring

Pre-

construction,

Construction

Refer to SOP02.9

and SOP2.10

Key parameters:

Turbidity, TSS, DO,

temperature,

electrical

conductivity (EC),

and pH

Visual checks for

sedimentation, oils

and grease

Threshold limits

provided in Table 2-5

to Table 2-7

Weekly

Discharge

points (refer

to monitoring

sites shown in

Figure A2,

Appendix C)

Routine ambient

water quality

All Project

phases Refer to SOP02.12

Field parameters

Monthly Upstream and

downstream

Page 134: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 119

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

monitoring and laboratory

testing as per

SOP02.12

Threshold limits

provided in Table 2-5

to Table 2-7

of Badalla

creek and

Gambia River

(refer to

monitoring

sites shown in

Figure A2,

Appendix C)

Quarry

and

borrow pit

safety and

integrity

Routine safety

monitoring

Pre-

construction,

Construction

Operations

Regular visual

inspections of the

borrow pits and

quarries for safety

and structural

integrity

Project compliance

Inspection records

for geotechnical and

landform stability

Verification of

security practices

Verification of safety

controls and

inspection records

Weekly

Actively used

borrow areas

and quarry

sites

Air quality Dust monitoring All Project

phases

Visual check for

excessive dust

(refer to SOP04.16)

and Project

Grievance

mechanism

Project compliance

Logged dust

complaints

Threshold limits

provided in Table 2-4

Daily

At sensitive

receptor, e.g.

residence

near a quarry

site (refer to

monitoring

sites shown in

Figure A1,

Appendix C)

Hydrocarb

on

leakage /

spillage

Routine

inspection for

potential

leakage or

seepage of

hydrocarbons

(e.g. diesel)

All Project

phases

Visual check for

visible leakage or

seepage (refer to

SOP07.28)

Project compliance

Regular (e.g.

daily)

Active

construction

areas

Noise

Investigative

monitoring of

nuisance noise

All Project

phases

Refer to SOP 05.12

and Project

Grievance

mechanism

Project compliance

Logged noise

complaints

Threshold limits

provided in Table 2-8

As required

At sensitive

receptor, e.g.

residence

near a quarry

site (refer to

monitoring

sites shown in

Figure A1,

Appendix C)

Acid rock

drainage

and

suitability

Monitoring of

acid rock

drainage

potential and

construction

material

suitability

Construction

Operations

Routine testing of

acid rock drainage

potential and

engineering grade

suitability

Project compliance

Periodic (e.g.

quarterly)

Actively used

borrow areas

and quarry

sites

Page 135: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 120

12 LAND MANAGEMENT AND LIVELIHOOD RESTORATION

The Company has identified the following key management objectives related to land management and livelihood

restoration for the Mako Gold Project:

Identify principles to compensate those who are affected by inevitable impacts from the Project activities

such as land loss and associated impacts on livelihoods;

Implement mitigation measures to address community concerns or grievances, or if there are no feasible

measures, provide appropriate compensation to affected community members;

Meet or exceed Senegalese requirements, international standards and best practices, and corporate

policies; and

Actively seek and engage community input in consultation sessions with respect to mine activities,

environmental performance and community initiatives for improvement purposes.

12.1 Context

The Company intends to either lease or purchase the land within the PDAs and pay any appropriate compensation.

The Company will formally registering all privately owned and community assets that are likely to be impacted by

Project development. This registration process will be done in consultation with local communities and

government authorities.

Potential issues with land acquisition include loss of agricultural land and grazing land as well as the economic

displacement of miners from the artisanal mine sites within the proposed PDAs. Other livelihoods at risk of being

affected by the Project development are collection of timber and non-timber products.

12.2 Management and Mitigation Measures

12.2.1 Land clearance

Impacts to community land will be minimised to the extent feasible. Prior to any land clearance, the SOP09: Land

Clearance and Soil Stockpiling will be implemented (refer to Appendix A). Where appropriate, the procedure for

land clearance includes consultation with local villagers regarding current land uses, and social and cultural assets

in the area prior to disturbance. A register will be maintained of all land disturbed by the Project.

Management measures to be implemented during the Pre-Construction and Construction phases to minimise

adverse impacts on cultural heritage include:

A cultural heritage survey undertaken along the alignment of the Main Access Road in advance of

construction;

The Company and its contractors will follow the Chance Find Procedure developed and SOP10: Cultural

Heritage Management (Appendix A), and ensure that staff are adequately trained during road

construction/upgrade works involving ground disturbance;

Known cultural heritage sites from the Cultural Heritage Study to be clearly marked on construction maps

as ‘No Go Zones’;

Impacts to cultural heritage sites to be avoided where possible;

Ensure that inductions and training regarding the protection of cultural heritage values is conducted for all

staff and contractors on site, as relevant to their role and responsibilities;

Where practical, refine the alignment of the Main Access Road to avoid disturbance of a prayer tree;

Page 136: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 121

Engage a Senegalese cultural anthropologist or sociologist to carry out the consultation process regarding

the prayer trees to be impacted and supervise any compensation;

Prohibit Project staff from accessing culturally significant sites;

Implement noise, vibration and lighting mitigation measures to minimise disturbance to cultural practices

performed adjacent to the PDA; and

Implement the Grievance Procedure.

Management measures to be implemented during the Pre-Construction/ Construction and Operation phases to

minimise adverse impacts on archaeology include:

Further excavations and a detailed archaeological investigation to be undertaken if sites are likely to be

impacted by construction activities (i.e. Sites Arch 04, 05, 15, 18, 26, 27, 28, 105, 120, 121, 122, 124, 128);

Test pitting and material recovery for the archaeological sites that fall directly in the footprint of Project

components;

An archaeological and cultural heritage register to be maintained for the life of the Project. Confirmed sites

of cultural heritage or archaeological significance will be accurately mapped and added to the register to

prevent accidental disturbance and avoid direct disturbance to these sites to the extent feasible;

Project employees and contractors educated (through mandatory inductions and training) to raise

awareness of the protection measures undertaken by local archaeological contractors;

Implement the management measures as described in the Chance Find Procedure for the Project (refer to

ESMMP, Volume C);All staff and contractors involved in any ground disturbance works will be informed of

the measures described in the Chance Find Procedure ; and

Establish protection measures (fencing, signage) for sites at risk of impact due to proximity to Project

activities.

The Project Access Road alignment has been designed to avoid impacts to settlement areas and land uses. The

Company will implement the following key measures, in addition to relevant measures from the LRP (Volume D),

to minimise potential settlement and land use impacts caused by Project road construction / upgrades:

Prior consultation with potentially affected villagers and local government on refinement of road alignment

and planned road construction activities to minimise or mitigate potential impacts, where possible;

Existing access routes to be maintained to local sites and land uses to the extent practicable, or alternative

temporary access may be considered for unavoidable restrictions;

Project Grievance Management Procedure to ensure that unanticipated land and village complaints can be

identified and resolved in a timely manner.

12.2.2 Land acquisition and livelihood restoration

The Company’s approach to land acquisition, land management and livelihood restoration will follow all applicable

national legislation, IFC Performance Standards, and Company policies. Any economic displacement resulting

from the Project will be managed as outlined in the Livelihood Restoration Plan (Volume D). The following

principles are the basis of the LRP:

Minimise negative impact on livelihoods;

Identify livelihood impacts systematically;

Recognise advantage of location as an asset;

Plan and negotiate mitigation measures with affected people;

Livelihood restoration is individual;

Plan to over-compensate;

Page 137: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 122

Give preference to replacement of existing livelihood activities, rather than introduction of alternative

livelihoods;

Implement pilot activities where possible; and

Maintain intervention until success is demonstrated.

Provide compensation/restoration for lost land and associated livelihoods (refer to the Livelihood

Restoration Plan, Volume D). This includes:

» Grazing land restoration;

» Forest resource restoration;

» Agricultural land restoration;

» Mitigation for loss of artisanal mining sites; and

» Mitigation for restrictions on access to other lands.

The livelihood restoration programmes will have the following outcomes relevant to crop production:

» Facilitation of allocation of fallow agricultural land between Project-affected villages/people and

Commune authorities and compensation (in kind or in cash) to assist in improving replacement land;

and

» Where active land has been impacted, in-kind assistance to prepare replacement land.

The livelihood of all impacted households will be restored and, where possible, improved.

To minimise the effect of loss of grazing land and disturbance of livestock associated with Project facilities, the

following management and mitigation measures will be implemented during Construction and Operation Phases:

Restrict clearance of land to only the land required for construction of Project components. Clearance of

buffer zones around Project infrastructure will be minimised where possible;

Refine alignment of Main Access Road to minimise disturbance to pastoral land and livestock

management practices;

In consultation with Tambanoumouya and Linguekoto, identify and manage one or two preferred cattle

grazing areas to improve pastures and facilitate change to livestock management practices to minimise

interaction and/or conflict with Project facilities, particularly road corridors;

Establish vehicle speed limits and other traffic control measures; and

Undertake regular public consultation through existing structures such as the Groupe de Contact to

ensure the effectiveness of management and mitigation strategies.

To minimise impacts on land access, the following management and mitigation measures will be implemented

during Construction and Operation Phases:

Limit the extent and period of exclusion from land areas, for example through the implementation of the

blast exclusion zone at required times only; and

Allow community access to the Main Access Road.

The following key measures will be implemented during the Pre-Construction/Construction and Operation Phase

to minimise impacts on artisanal mining:

Minimise the extent of the safety exclusion zone in artisanal mining areas downstream of Project

components;

Continue consultation with artisanal miners through the Groupe Technique – Orpaillage already established

by the Company;

Support the Government of Senegal with the legalisation of artisanal miners where they operate in the

Company’s Mining Concession area; and

Page 138: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 123

Contribute to the development of a permanent alternative to artisanal mining for the affected households

of Tambanoumouya, Linguekoto, Niemenike and Mako. The Company will support affected households to

engage in profitable and sustainable irrigated agriculture on approximately 0.25 ha of land per household

(refer to Livelihood Restoration Plan, Volume D for more details).

To minimise impacts on ecosystem services associated with the use of forest resources during the Pre-

Construction/ Construction and Operation Phase, the following avoidance, management and mitigation measures

will be implemented:

Livelihood restoration measures in relation to hunting and the collection of forest resources implemented,

as per the Livelihood Restoration Plan (Volume D), including the planting of useful tree species in

consultation with the residents of Tambanoumouya and Linguekoto;

Maintenance and upgrade of existing public roads to facilitate access to forest resources;

Environmental and social inductions for all Company employees and contractors. The programme will

cover the importance of biodiversity values and prohibition of hunting, trading or buying wildlife products

or harvesting and collecting forestry products (including timber and NTFPs).;

Company employees and contractors to be prohibited from hunting, buying or trading wildlife products as a

condition of their Code of Conduct;

Monitor forest resources to identify the impact of any additional pressure resulting from in-migration and

pursuit of alternative livelihoods reliant on forest products such as construction, artisanal mining, hunting,

etc. Monitoring can be undertaken by regular consultation with local communities and authorities;

In consultation with local residents and the authorities, ensure that they have had the opportunity to

remove timber, firewood and other forest resources from Project areas to be cleared prior to any vegetation

clearance; and

Consider the potential impact on forest resources when planning livelihood restoration activities.

The following mitigation and management measures will help to minimise potential impacts on fishing, water and

aquatic resource use during Pre-construction/Construction:

Minimise disturbance of streams and riparian areas where possible, and prioritise re-vegetation activities in

riparian areas if disturbance is required;

Ensure appropriate management of general waste and hazardous materials to minimise potential impacts

on water quality;

Undertake earthworks associated with construction of access roads and clearance of land for Project

facilities in a manner that minimises erosion and impacts on watercourses;

Minimise impact on riparian habitats during the construction of the Gambia River pump station;

Undertake environmental education and awareness programmes to raise awareness among Project staff

regarding the importance of aquatic resource use for local residents and the need to minimise impacts on

waterways;

Prohibit Project staff and contractors from fishing, collection and hunting of other aquatic species, including

invertebrates, fish and herpetofauna;

Continue the water quality monitoring programme;

Periodic monitoring of habitat and key terrestrial and aquatic wildlife species will be conducted as part of

the Project-specific Biodiversity Action Plan (Volume C) to assess whether any further mitigation or

management measures are required, to include aquatic macroinvertebrate surveys, hippo surveys and fish

catch surveys;

Monitor potential impacts of the Project on food security, health and livelihoods through the biennial socio-

economic surveys of local villages.

The following mitigation and management measures are proposed to minimise the potential impacts on water

and aquatic resource use during Operations:

Page 139: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 124

The setting of a minimum environmental flow (5 m3/s) under which water supply abstraction will not take

place, resulting in less than 3% of the Gambia River’s flow being abstracted at any one time;

Abstraction from the Gambia River only during the months of higher flows (approximately July –

December); and

Recycling of Project-affected waters on-site during operations.

Land management and livelihood restoration will be managed in coordination with local authorities (village, rural

community, and other applicable levels of government). Land owners and users will be identified and

compensated prior to any disturbance to the land. The Project Negotiations Forum (PNF) (refer to Section 12.3)

established by the Company will be used during the planning and implementation of the land acquisition

programme.

Unanticipated impacts which lead to compensation claims relating to land and other assets will be managed

through the grievance process (refer to Section 13.3.3).

Detailed measures for compensation and livelihood restoration are provided in the LRP (Volume D). Following the

submission of the ESIA documents (including this ESMMP and the LRP) and obtainment of environmental permit,

the Company will conduct negotiations with Project affected persons and government authorities regarding

precise livelihood restoration measures.

In accordance with Senegalese legislation, international standards and Company policies, the key steps in the

livelihood restoration planning process are as follows:

Development of Mako Livelihoods Strategy, with consultation of affected people, based on preliminary

project design options (completed);

Development and refinement of the Livelihood Restoration and Resettlement Framework, based on

national and international standards (completed);

Optimization of project design and footprint to minimise impacts on livelihoods, with consultation of

affected people (completed);

Identification of residual impacts on livelihoods and affected groups (completed);

Development of the initial LRP as a component of the ESIA (completed);

Submission of ESIA with LRP to Government of Senegal, followed by public audiences (completed);

Approval of ESIA with LRP by Government of Senegal (not completed);

Financing of Project and decision to proceed (not completed);

Detailed negotiations with communities, finalisation of LRP and formal agreement (not completed);

Implementation of LRP and signing of formal individual agreements with affected people (not completed);

Formal granting of access to land (not completed); and

Continuation of livelihood restoration and livelihood improvement programmes (not completed).

12.2.3 Decommissioning and Closure Phase

To minimise impacts on land access during Decommissioning/Closure, the key mitigation measures are:

Handover the Main Access Road to local authorities for ongoing community use; and

Partial restoration of access within the PDA, with the exception of the Mine Pit.

To minimise impacts on artisanal mining, the following measures are required during the

Decommissioning/Closure:

Restore hydrological regime of the Badalla Creek and Kobokou Creek;

Page 140: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 125

Review the closure objectives for the PDA and the acceptability of allowing artisanal mining. This may be

facilitated through continuing consultation and coordination with the communities, local authorities and

miners.

During the Decommissioning/Closure Phase the rehabilitation and revegetation of some impacted areas will be

undertaken. Key measures for terrestrial resource use in this Phase include:

Planting and regeneration of useful species, in consultation with forest users; and

Species selection for all rehabilitation works should include species of economic or subsistence value to

local residents where possible.

Monitoring conducted in rehabilitated areas, in order to assess the success of restoration of forest areas for

wildlife and community use, as per the Rehabilitation and Conceptual Mine Closure Plan (Volume E).

12.2.4 Livelihood Improvement Programmes

Livelihood improvement refers to programmes or measures designed specifically to improve the assets, levels of

economic productivity, and/or standards of living of affected people to above pre-project levels. Subject to further

consultation with the Project affected communities, the Company has committed to supporting a range of

Livelihood Improvement Programmes covering agricultural, livestock and forest activities as detailed in the LRP

(Volume D). These Programmes will be primarily focused on people whose livelihoods are directly affected by the

Project. The Company will also target economically displaced people within the spirit and intent of IFC

Performance Standard 5.

12.2.5 Vulnerable Groups

Vulnerable groups are people who by virtue of gender, ethnicity, age, physical or mental disability, economic

disadvantage, or social status may be limited in their ability to claim or take advantage of development benefits.

A “vulnerable persons” assistance programme will be implemented as part of the LRP which will include specific

assistance measures for vulnerable households or groups that may be affected by Project land acquisition.

Specific aspects of the “vulnerable persons” programme will include:

Recruitment of part-time Vulnerable Persons Officer; and

Preparation and up-date of a formal register of vulnerable groups (“vulnerables watch list”) throughout the

life of the Project.

Other preventive measures and follow-up measures that will be considered include:

Ensuring that recruitment agencies meet national and relevant international standards, including the

following three principles in particular that are relevant to vulnerable groups (Toro Gold,2014a):

» The company is committed to the principles of equal opportunity and fair treatment and will not

discriminate in its employment decisions;

» The company will operate transparent and participatory approaches to employment; and

» The company will not employ forced labour, nor will it directly employ children.

Effective stakeholder engagement will continue via regular public consultation through existing structures

such as the Groupe de Contact to ensure the effectiveness of management and mitigation strategies; and

A Grievance Mechanism will be established to provide a means for responding to stakeholder concerns,

including vulnerable groups.

12.2.6 Gender

While the Project does not have a specific gender policy, gender considerations will be integrated into the general

management of the Project, and potential gender issues have been considered throughout the life of the Project.

Page 141: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 126

Measures to manage and mitigate Project impacts to women will be applicable throughout all Project Phases.

These measures will include:

Implement the Company’s ‘equal opportunity’ employment policy, which requires the Project to provide

equal opportunity to all applicants regardless of age, gender or ethnicity;

Ensure the mine site infrastructure and work environment are not a barrier to employment of women (e.g.

ensure that accommodation and ablutions facilities include separate facilities for men and women; ensure

that site uniforms meet safety standards, but are available and culturally appropriate for both men and

women) and adopt a zero tolerance policy to discrimination including threatening or sexist behaviour;

Implement gender sensitive livelihood restoration and livelihood improvement measures as part of the

Livelihood Restoration Plan (Volume D) including specific measures for vulnerable persons;

Implement a maternity leave policy as per Senegalese law. Ensure that female staff are aware of this policy;

Regularly monitor socio-economic conditions in Project-affected villages and particular changes to the

distribution of labour that adversely affect women ;

Provide continuous training and development of local employees;

Carry out community consultation sessions targeted at engaging women from the local communities;

Maintain female representation in the Project Community Relations Department and on the Groupe de

Contact/Consultation Committee and other relevant consultation groups; and

Code of Conduct for all Project staff and contractors, including curfew for Camp residents and restricted

access to villages.

12.3 Monitoring Measures

Table 12-1 presents the key monitoring measures related to land management and livelihood restoration for the

Mako Gold Project throughout all phases of development. These will be incorporated into the detailed monitoring

programmes prepared by the Company and its contractors.

Relevant guidelines and standards applicable to the Project are specified in Section 2.4 and the Registers of

Environmental and Social Management and Monitoring Commitments in Chapter 18 of this Plan.

Table 12-1 Register of Social Monitoring Measures – Land Management and Livelihood Restoration

Aspect / Impact Monitoring

Measure

Phase Method Parameters Frequency Location

Compensation

and livelihood

restoration

Establish a

programme to

monitor the

implementation

of the livelihood

restoration

programme

Prior to

Construction

Formal register of

Project affected

land, assets and

livelihood

Monitoring of key

indicators for

livelihood

restoration

Indicators shall

be developed in

consultation with

the community

and government

Ongoing

Project

affected

villages

Construction,

Operations

External

compliance

reviews and a

completion audit

will focus on the

assessment of

compliance with

the requirements

contained in the

Project audit and

compliance

Annually

Project

affected

villages

Page 142: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 127

Aspect / Impact Monitoring

Measure

Phase Method Parameters Frequency Location

LRP

Livelihood

Improvement

Programme

Establish a

programme to

monitor the

implementation

of the livelihood

improvement

programme

Prior to

Construction

Formal register of

Project affected

land, assets and

livelihood

Monitoring of key

indicators for

livelihood

improvement

Indicators shall

be developed in

consultation with

the community

and government Ongoing

Project

affected

villages

Page 143: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 128

13 COMMUNITY ENGAGEMENT

13.1 Objectives

The Company’s objectives for the Community Engagement programme for the Mako Gold Project will be to:

Ensure that Project affected communities and other stakeholders are well informed of the Project, its

potential environmental and social impacts and their mitigation measures;

Seek and document community input and actively engage in community consultation regarding project

activities, environmental performance and community initiatives; and

Implement mitigation measures to address community concerns; or if there are no feasible measures,

provide appropriate compensation to affected stakeholders.

13.2 Context

The Company is committed to continuing formal and informal consultation with stakeholders as the Mako Gold

Project progresses. The Company’s approach to stakeholder engagement has focused on the following core

values:

Proactive engagement to enable the early identification of potential issues and risks;

Generation of ideas and alternative solutions for early design considerations; and

Respect for local culture and established political, social and economic relations.

The OHS&E Manager will be directly responsible for ensuring the day-to-day implementation of the procedures

for interaction with community members and stakeholders. The OHS&E Manager will also ensure that the

Company has a presence at local community events to which the Company has been invited wherever appropriate.

Encouragement and support will be provided by the Company for a range of staff to attend these events. The

Community Relations Department will act as a conduit for local people to gain information about mining activities,

as well as to air any concerns or grievances.

As part of the induction programme, the Company employees and contractors will be provided with information

on cultural awareness and community sensitivity. Information may include (but is not limited to):

Local custom(s), beliefs, and traditions;

Any applicable laws unique to the area;

Languages and local dialects; and

Government structure and chains of command.

In accordance with international best industry practices, Company records communications and engagement.

13.3 Management and Mitigation Measures

13.3.1 Ongoing Public Disclosure and Consultation

The overall goal of stakeholder consultation for the Mako Gold Project is to improve decision-making and build

understanding to ensure the long-term viability of the Project and to enhance potential Project benefits. A

Stakeholder Engagement Plan (SEP, Volume C) has been prepared for the Project, detailing the methodology for

conducting stakeholder consultation and documenting the results of consultation activities. The Company’s

Community Relations Department will be responsible for updating and maintaining the SEP and providing regular

updates on progress of community projects.

Page 144: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 129

The Company has committed to continuing formal and informal consultation with stakeholders as the Project

progresses. A Grievance Mechanism will also be implemented (refer to Section 13.3.3 below). Community team

personnel will regularly (formally and informally) consult with and listen to individuals, community

representatives, government agencies, and non-profit organisations affected and/or interested in the Company’s

activities.

The Company will ensure that community consultations involve a cross-section of local residents (i.e. different

ethnicities, a range of ages, gender balance, etc.) to ensure that the opinions and concerns of all groups are

considered. The Company has also committed to undertaking regular household surveys in villages in the

immediate Project area to gain a greater understanding of the impacts and benefits occurring over time.

A number of groups have been established or are in the process of being established to facilitate consultation

during Project design and permitting, including existing structures such as with Municipal Councils and

Department Councils. These groups are detailed below.

Project Negotiation Forum to support the LRP

The Company will establish a Project Negotiations Forum (PNF), which will serve as a key, multi-stakeholder

decision-making forum for the planning and implementation of the land acquisition and livelihoods restoration

programme. The PNF includes representatives from the Company, Project affected communities, the Rural

Council and other Government representatives, as well as third party observers such as NGOs, community

organisations, spiritual leaders. Basic functions include (but are not limited to) providing strategic direction for the

land acquisition process, including preparing and implementing the LRP (Volume D). This team will be led by

professionals comprised of a mix of Company staff, licensed experts, as well as government technicians. Further

details on the PNF are outlined in the LRP (Volume D).

Local Consultation Committee (Groupe de Contacte)

The Company has established a Local Consultation Committee (Groupe de Contact Locale) comprising of local level

village and administrative representatives (i.e. Mayor of the Conseil Municipale de Tomboronkoto; Vice-Presidents;

Village Chiefs; and Women’s Group Representative and Youth Representatives from Project affected villages) to

assist with the dissemination of Project information, identification of potential issues and risks, to generate ideas

and alternative solutions on early design questions. Committee members are charged with the responsibility to

report back to the respective communities on the resolutions of the Committee.

Technical Groups

A number of ad hoc Technical Groups (Groupes Techniques) have been established to advise the Local Consultation

Committee on specific issues such as economy, artisanal mining, forest resources, etc. These comprise village

representatives from Project affected villages.

Group of Independent Experts

The Company has established a Group of Independent Experts to focus on the biodiversity in the Project

Development Area and surrounding areas as well as the Niokolo Koba National Park (PNNK). The group includes

specialists from the Université Cheikh Anta Diop, an IUCN representative and independent biodiversity specialists.

13.3.2 Community Awareness and Education Programme

Further awareness and education programmes for local communities will be conducted. The scope of these

programmes may include:

Public health, sanitation, and sexually transmitted diseases;

Safety exclusion zones;

Traffic awareness and safety (refer to Section 9.3);

Employment and skills development;

Livelihood, restoration and improvement; and

Economic participation (e.g. micro financing, financial management, etc.).

Page 145: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 130

Programmes will be adapted to meet ongoing needs and new risks, and will be prepared developed and

implemented with the participation of local authorities, NGOs, and community groups.

13.3.3 Grievance Management

During the implementation of Company activities, conflicts, complaints and grievances will undoubtedly arise and

will need to be resolved in a fair and transparent manner. The most important step in conflict resolution is conflict

avoidance, and a consultative and participatory nature in planning of activities affected the communities is used to

reduce the occurrence of disagreements and conflicting positions.

In instances where grievances do occur, it is important that they are resolved quickly before positions harden and

disagreements escalate. A grievance management system (Grievance Mechanism) receives and addresses

concerns raised by stakeholders in a transparent, constructive, timely, confidential (if desired), culturally

appropriate and accessible manner.

This grievance management system will comprise the four basic mechanisms.

First Order Mechanism - this will comprise an informal resolution process, in which a stakeholder brings

forward his/her concern for discussion with the Company, either directly or indirectly via their nominated

representatives (refer to Section 13.3.1). The Company expects that the vast majority of questions and

concerns will be heard and resolved within these informal interactions.

If this informal process does not resolve the issue satisfactorily, complainants will be encouraged to make

use of any of the other mechanisms presented below.

Second Order Mechanism - this will comprise the formal management of substantive, difficult and/or

written comments and concerns. The Company anticipates that most substantive grievances will be

successfully resolved by this mechanism. The procedure for this is summarised in Table 13-1 below. The

Company will inform local government authorities, village chiefs, and community representatives on the

use of the grievance procedure.

Table 13-1 Summary of the Company Grievance Procedure

Stages Activities Responsibilities Timeframe

Registration Complete the grievance registration

form.

Complainant, with the Company Community

Relations Department.

24 – 48 hours

Reporting Declare complaint / grievance to

Company management

Company Community Relations Department.

Validation Validate the complaint / grievance. OHS&E Manager.

Investigation Assess causes of grievance /

complaint and suggest solutions.

Company Community Relations Department

and the complainant if necessary.

14 days

Resolution Validation the action plan and

timeframe.

Implement the action plan.

Inform the complainant of the

progress and results of actions.

OHS&E Manager and Community Relations

Department.

If the OHS&E Manager cannot resolve the matter, or when more complex issues require higher-level

decision making, grievances will be forwarded on to the Third Order Mechanism.

Third Order Mechanism - this involves the presentation of grievances to a multi-stakeholder forum (i.e.

Local Consultation Committee) for discussion and resolution. The Company hopes that such forums will

serve as an important and trusted arbiter in complicated grievances. Deliberation and any decision taken

will be reflected in the minutes, and a written response provided to the complainant.

Page 146: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 131

Fourth Order Mechanism - this involves the formal judicial system. The Company recognizes that it is

unlikely to be able to satisfactorily address all grievances with the amicable mechanisms outlined above,

and that all parties have the right under Senegalese law to take their grievances into the judicial system at

any time. The Company will inform those who prefer litigation of their rights, entitlements and the

existence of any legal aid.

13.4 Monitoring Measures

Table 13-2 presents the key monitoring measures related to community engagement for the Mako Gold Project

throughout all phases of development. These will be incorporated into the detailed monitoring programmes

prepared by the Company and its contractors.

Relevant guidelines and standards applicable to the Project are specified in Section 2.4 and the Registers of

Environmental and Social Management and Monitoring Commitments in Chapter 18 of this Plan.

Table 13-2 Register of Social Monitoring Measures – Community Engagement

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Effectiveness

of the Project

Grievance

Mechanism

Review of

records

Informal

discussion

All

Project

phases

Review of

grievance register

and records

maintained by the

Company

Response times on claims Quarterly

Project

affected

villages

Number of claims elevated

to Third or Fourth Order

Mechanism

Quarterly

Satisfaction levels - gauged

via discussions with the

Local Consultation

Committee / Project

Negotiation Forum

As required

Information

disclosure

and

knowledge

Informal

discussion

All

Project

phases

Review of the

Company’s

stakeholder

engagement

activities to date

Community awareness and

understanding of Project

information, gauged after

consultations or through

discussions with the Local

Consultation Committee /

Project Negotiation Forum

Information disclosed as per

the Stakeholder

Engagement Plan

As required

and quarterly

Project

affected

villages

Implementati

on of

community

engagement

activities

Review of

records

All

Project

phases

Review of the

Company’s

stakeholder

engagement

activities to date

Key stakeholders consulted

as per the Stakeholder

Engagement Plan

Number of consultations

conducted

Records (i.e. attendance

sheets, photos, material

used, etc.) of local

community attendance

Quarterly and update each time information is produced or disseminated

Project

affected

villages

Page 147: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 132

14 COMMUNITY SAFETY AND HEALTH

14.1 Objectives

The Company’s objectives for community safety and health management for the Mako Gold Project are to:

Minimise potential health and safety risks for local communities due to the presence of the Project; and

Support the development of local health services as part of the Project's community development plan.

14.2 Context

The presence of the Project is likely to directly and indirectly result in improvement to local health facilities and

services in the area, such as improved water supplies and sanitation facilities, improved health care facilities and

easier access to such services (e.g. through road upgrade and maintenance). This is a significant potential benefit

of the Project.

The key health issues relevant to the Mako Gold Project are:

A potential increase in sexually transmitted infections (STIs) resulting from in-migration (and primarily in-

migration of young, single males for employment);

Local incidence of diseases, such as malaria, resulting from Project-induced in-migration and potentially

increased mosquito breeding areas due to Project development;

Potential indirect impacts on water quality due to Project-induced in-migration and informal settlements,

with subsequent impacts on health;

Increase in occurrence of ‘wealthy’ diseases, such as hypertension, high blood pressure and diabetes;

Potential psycho-social and health impacts from air quality and noise emissions;

Increased pressures on local food security due to Project-induced in-migration;

Community safety issues resulting from unauthorised access to Project facilities; and

Community safety and security issues resulting from in-migration.

14.2.1 Disease transmission and HIV/AIDS

The most common adult illnesses reported in surveyed villages was malaria, diarrhoea and the flu. Malaria was

also the most common illness affecting children and other reported illnesses included fever, dermatological

conditions, diarrhoea measles, stomach illness and dysentery. Malaria was also reported to be the primary cause

of death.

There will be a potential increase in sexually transmitted infections (STIs) resulting from both influx of Project

employees and in-migration (and primarily young, single males seeking employment). The risk of disease

introduction (e.g. STIs) will be greatest during Construction when short-term workers and in-migrants from other

regions of Senegal or other countries will arrive.

14.2.2 Water and Sanitation

As the surveyed villages rely on surface and groundwater resources for drinking, washing, cooking, recreation,

etc., the protection of water quality is understandably a key health issue for the Project. This is further discussed in

in Chapter 7 of the ESMMP.

Page 148: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 133

14.2.3 General Community Health and Safety

The key community safety impact would result from unauthorised access to Project facilities. There may also be

community safety and security issues related to Project-induced in-migration and influx of Project employees,

linked to potential lifestyle changes including increased drug and alcohol abuse, gambling, domestic violence and

anti-social behaviour. Transport safety issues are discussed in Section 9.

Other community safety concerns associated with the Project include fly rock, accidental spills, fires and

explosions, and accidents resulting from unauthorized access to Project areas. There are a number of safety risks

inherent at these sites, which could be particularly harmful to individuals unaware of these risks.

Air and noise may present a nuisance and reduced visibility on roads which may have a psycho-social impact (e.g.

leading to reduced quality of life and depression). Dust emissions may also increase the incidence of Acute

Respiratory Infections (ARIs), particularly asthmatic conditions. Social determinants of health which may be

affected by lifestyle changes resulting from the presence of the Project include drug and alcohol abuse, gambling,

domestic violence and anti-social behaviour associated with the rapid influx of labour (IFC Mining EHS Guidelines,

2007).

In-migration associated with the Project is also likely to place a burden on existing health facilities in proximity to

the Project.

Worker health and safety issues for the Operation are outside the scope of this document. However, the Company

has committed to developing and maintaining appropriate health and safety procedures for its staff and

contractors prior to pre-construction commencing, based on the Emergency Response Plan (to be prepared).

14.3 Management and Mitigation Measures

14.3.1 Pre-construction and Construction Phase

General management of community health and safety

Various measures will be implemented to minimise Project impacts on community health and safety during

Construction. These include:

The establishment of health and safety management systems for the community, covering aspects on

security, Project hazards, disease prevention (e.g. HIV and Malaria programmes), and safe sanitation and

hygienic practices;

A range of security controls will be developed in consultation with relevant actors in advance of Project

Construction. These controls will be routinely reviewed with regional authorities;

Provision of health care services for Company employees with an appropriately staffed on-site clinic and

medivac capabilities; The Company will implement a community education and awareness programme

regarding public safety in and around the PDA (particularly related to road safety);

Appropriate environmental emergency response procedures for potential spillage and accidents will be in

place;

A defined exclusion zone to restrict and control access within the PDA and ensure community safety for all

blasting activity to prevent fly rock injury. This zone will include the blast exclusion zone. The zone will be

monitored prior to blasting activity;

In partnership with local authorities, the Company will support community hygiene and sanitation

programmes in Project affected villages;

Mitigating the adverse impacts of the Project on access to community infrastructure and services (e.g.

water supply, hygiene and sanitation, health, security), particularly those related to Project induced in-

migration. The Company will monitor the impacts of in-migration in consultation with local authorities and

communities in Project-affected villages;

Page 149: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 134

Maintenance of a water quality monitoring programme including routine sampling of village drinking water

in Project-affected villages; and

Supporting community drinking water management programs in Project affected villages, in partnership

with local authorities.

Traffic Management and Road Accidents

The Company’s main objective for Project traffic management is to minimise the impact of mine traffic on local

villagers and the environment. The strategy for dealing with the road safety management associated with the

Project is discussed in Section 9.

Disease Transmission

The Company will facilitate and seek to provide assistance to local agencies to support training to local health

workers in implementing and providing education on sanitary practices for the community. An institutional

support programme to community hygiene committees in all Project affected villages will be established to

reinforce community sanitation and hygiene. This will be implemented by suitably qualified local partner under

supervision of the local health authority.

The potential for HIV / AIDS transmission will be minimised through strategies such as the development of

partnerships with Government HIV / AIDS programmes and NGOs / Aid agencies working in the area on HIV / AIDS

prevention and treatment.

The following specific measures will be implemented:

Implementation of a Code of Conduct for all Project staff and contractors, a camp curfew and restricted

access to villages to reduce the potential for transmission of STDs;

In partnership with local health authorities, support community HIV/AIDS awareness programmes in

Project affected villages;

In partnership with local health authorities, support community malaria prevention programmes in Project

affected villages.

Dust and Noise

General strategies to minimise community related impacts from dust and noise are provided in SOP04: Emission

and Dust Control and SOP05: Noise and Vibration (Appendix A).

During road construction, the Company will implement the following measures to minimise air quality and noise

impacts:

Prior notification of planned road construction and maintenance activities likely to cause nuisance noise and

dust (e.g. blasts) to potentially affected villagers;

Avoidance of road construction and maintenance works during night time hours where works are located

near roadside communities, to limit potential disruption;

Continue monitoring of noise and dust impacts within Project-affected villages to ensure that impacts are

at acceptable levels; and

Implementation of the Project Grievance Procedure to enable villagers to report any noise or dust related

complaints in relation to Project vehicles.

In-Migration

Strategies to minimise impacts of in-migration are discussed in Chapter 15.

Page 150: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 135

14.3.2 Operations Phase

Avoidance, mitigation and management measures for health during operations will be consistent with those

outlined for the pre-construction and construction phase, where applicable.

Community health and safety indicators will be developed in consultation with local authorities. These will be

monitored as part of the biennial socio-economic surveying for villages in the vicinity of the Project. Management

measures will be adapted accordingly.

14.3.3 Decommissioning and Closure Phase

The Company plans to construct an earth berm on Project roads within the PDA to prevent unauthorised access

and maintain community safety. For Project access roads that will be transferred to local governments or

communities, the Company will consult and negotiate with the relevant parties and stakeholders to ensure that:

Access to remaining mine facilities (e.g. TMF) that may pose a safety risk to the public are adequately

secured; and

Operation and maintenance requirements are clearly defined.

14.4 Monitoring Measures

Table 14-1 presents the key monitoring measures related to community health, food security and safety for the

Mako Gold Project throughout all phases of development. These will be incorporated into the detailed monitoring

programmes prepared by the Company and its contractors.

Relevant guidelines and standards applicable to the Project are specified in Section 2.4 and the Registers of

Environmental and Social Management and Monitoring Commitments in Chapter 18 of this Plan.

Table 14-1 Register of Social Monitoring Measures – Health and Safety

Aspect /

Impact

Monitoring

measure

Phase Method Parameters Frequency Location

Traffic

management

Refer to Chapter 9 (Roads and Transport).

Noise, dust

and vibration

nuisance

Dust and noise

inspection

investigation and

monitoring

All

Project

phases

Review of grievance

register maintained by

the Company

Community

complaints logged

via Grievance

mechanism

As required

Project

affected

villages

(refer to

monitoring

sites

shown in

Figure A1,

Appendix

C)

Monitoring of noise,

vibration and air quality

impacts

Noise limit and air

quality limit

exceedances at

nearby sensitive

receptors

Threshold limits

provided in Table 2-4

to Table 2-10

Introduction /

increased

transmission

of disease

(e.g. malaria,

STIs, etc.)

Survey

All

Project

phases

Monitoring of health in

the local community and

workforce

Health indicators (to

be developed in the

next phase)

Every two

years

Project

affected

villages

Increased

injuries and

fatalities

Monitoring

All

Project

phases

Grievance register

Training records (i.e.

attendance sheets,

Number of transport

related incidents /

grievance claims

Quarterly Project-

wide and

affected

Page 151: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 136

Aspect /

Impact

Monitoring

measure

Phase Method Parameters Frequency Location

photos, material used,

etc.)

Visual inspection and

audit records

Consultation record

sheet and database

Number of worker

training conducted

Number of

community safety

incidences or

livestock losses

associated with

restricted areas

Number of

community

consultations /

awareness sessions

conducted

villages

Food security

and nutrition Survey

All

Project

phases

Monitoring of nutrition in

the local community and

workforce

Nutritional indicators

in the local

community (e.g.

availability of food,

food supply options,

prevalence of

undernourishment,

agricultural / food

production etc.)

Every two

years

Project

affected

villages

Psychosocial

impacts

associated

with general

lifestyle and

quality of life

changes

Monitoring

All

Project

phases

Project Grievance

mechanism

Logged community

complaints Quarterly

Project

affected

villages

All

Project

phases

Socio-economic

monitoring/surveys

In-migration and

employment

statistics

Every two

years

All

Project

phases

Training and induction

records of Project staff /

contractors and the local

community

Number of

environmental and

social induction

programmes for the

workforce / cultural

awareness training

for the community

Records (i.e.

attendance sheets)

Quarterly

All

Project

phases

Socio-economic

monitoring/surveys

Socio-economic

conditions

Every two

years

Page 152: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 137

15 IN-MIGRATION

15.1 Objectives

The Mako Gold Project will generate employment and other economic opportunities that may lead to an increased

population in the socio-economic area surrounding the PDA, particularly during construction.

The Company is committed to local recruitment and the Company’s employment policy will assist in minimising

the influx of labour from outside the vicinity of the immediate Project region.

15.2 Context

Internal migration is common in Senegal. The primary reasons for migration within the country include economic

development, employment opportunities and family affairs, followed by moving due to a shortage of food,

shortage of land, or lack of water. In addition to permanent migration (i.e. moving to establish long-term

residency, establish crops, etc.), the area in the vicinity of the Project experiences some seasonal migration

primarily for artisanal mining. The dry season is peak time for seasonal migrations.

In-migration resulting from the employment and economic opportunities created by the Project is likely to be

greatest during Project construction. The extent of in-migration to each village will depend on the geographical

location and accessibility of each village. Villages such as Mako and the Niemenike cluster, which are located on

the RN7, are at the highest risk of potential impacts from Project-induced in-migration. If they experience a

population growth rate similar to the rate experienced by Sabodala village with the development of the nearby

Sabodala Mine, it is conceivable that the population could easily double within the life of the Project.

Migration rates in the vicinity of the PDA are currently moderate. Most of the Project-affected villages have

experienced some permanent migration, as well as a relatively large number of seasonal migrants. Most Project-

affected villages also reported a greater degree of in-migration compared to out-migration. Villages such as Mako

and the Niemenike cluster have had relatively high rates of recent migration and population growth (4% per

annum from 2004 to 2014) which is already putting some strain on local infrastructure and natural resources.

15.2.1 Pre-construction and Construction Phase

In the absence of management measures, in-migration into the Project area could potentially have the following

consequences (although note that there is already a certain level of seasonal migration, so many of the issues

below are likely to be already present to some degree):

Strain existing social services such as health, security and education facilities which are limited in the

Project-affected villages. This is a particular risk for Mako and the Niemenike cluster as they are already

experiencing some strain from existing migration;

Increased demand for (and reduced availability of) land, natural resources and agricultural produce by

migrant population. This is a particular risk for Mako and the Niemenike cluster as they are already

experiencing pressure on timber resources;

Increased demand for (and reduced availability of) water supply and pressure on water infrastructure. This is

a particular risk for Mako and the Niemenike cluster as they are already experiencing pressure on water

infrastructure;

Localised increase in cost of goods and services;

Reduced employment opportunities for original residents;

Increased risk of introduced diseases, especially those transmitted sexually. This is also likely to be a

particular risk for Mako as the largest village in close proximity to the Project;

Page 153: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 138

Increased solid waste generation in Project-affected villages;

Increased improper disposal of human waste and exacerbated unsanitary conditions and water quality

issues in Project-affected villages;

Impacts on priority species and habitats in the PNNK and potential for increased poaching;

Social disharmony and conflict between original residents and incoming migrants;

Changes to the social structures of local communities including an increase in sex workers; and

Gender imbalance, as the migrant population is likely to be predominantly male.

15.2.2 Operations Phase

Potential impacts of in-migration during the operations phase are likely to be similar to that of the pre-

construction and construction phase, however the magnitude of the impact may decrease with stabilisation of in-

migration levels.

15.2.3 Decommissioning and Closure Phase

During closure, a net out-migration may occur, as people leave to seek other employment opportunities.

15.3 Management and Mitigation Measures

Migration into the area will be controlled in a manner that does not compromise the development of the Project

by introducing new environmental and social issues.

The Company’s general approach to minimising and mitigating potential in-migration impacts will be to

incentivise in-migration to Kedougou, dis-incentivise in-migration to the local area, and increase the local capacity

to absorb in-migration in a manner that maximises the potential benefits to local communities.

A Local Economic Participation Plan (LEPP, Volume D), In-Migration Guidance Note (rePlan, 2015b) and Worker

Accommodation Guidance Note (rePlan, 2015a) have been prepared for the Project which together plan for

Project development to occur, where possible, in a way that allows Project benefits to accrue to local communities.

The LEPP includes measures that will assist in reducing the impacts of in-migration. Clear communication and

consistent application of these measures, and strict enforcement of hiring rules in particular, should serve to dis-

incentivise in-migration related to direct project employment.

In addition, the Company will establish a Local Enterprise Development Programme and a Local Procurement Policy

which will provide support for the growth of enterprises, including measures to maximise the opportunity for local

suppliers to participate in the supply chain for the Project. The preferred implementation approach is to work with

local partner organisations that have existing programmes and who have a mandate to support local enterprise

development. The priority for implementation will be to emphasise scaling up of existing activities rather than to

start new activities.

Page 154: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 139

15.3.1 Pre-construction and Construction Phase

The following policies and practices will be implemented by the Company to minimise the adverse impacts of

Project-induced in-migration in the vicinity of the PDA:

Work with local authorities to minimise the potential impacts on in-migration (e.g. security, education and

awareness campaigns against drug and alcohol abuse, supporting health services) to monitor demand and

resources;

Continual public disclosure and consultation with the local community during all stages of the Project;

Implement measures provided in the Local Economic Participation Plan (LEPP, Volume D), which prioritise

local employment, local procurement and local economic development. A “Local Economic Participation

Committee” with representatives from affected villages will be established in consultation with local

authorities and the community. Other measures include (but are not limited too):

» Implementation of a recruitment policy which prioritises local employment;

» Recruitment for unqualified positions to be restricted to residents in Tomboronkoto Commune only;

» Preferential access to skills upgrading courses for local and regional residents, based on Project skill

requirements;

» Provision of training as part of a Local Enterprise Development Programme to assist in developing local

skill levels and entrepreneurship that is not solely dependent upon the Project; and

» Local Procurement Plan: Prioritisation of local procurement and provision of assistance for businesses to

participate;

Increase the capacity of Tomboronkoto Commune, and Mako and Niemenike in particular, to plan for and

absorb in-migration in a manner that improves quality of life and maximises economic benefit. This may

include providing assistance to the Municipal Council to support the preparation of the Commune

Development Plan;

Work with local authorities and communities to restrict the development of new habitation areas within the

PDA and other areas of the mining concession where this could present risks to human safety and/or the

operational security of the Project;

Implement the measures in the In-Migration Guidance Note (rePlan, 2015b), which include:

» Use the pre-construction and construction phase as a training phase for local workers and businesses to

increase their ability to participate / bid for operations phase employment opportunities;

In partnership with local authorities, control illegal mining where this occurs within the proposed Mining

Concession;

Establish a social and environmental induction programme to educate outside contractors on the cultural,

social and environmental sensitivities of the Project location. Conversely, employees who are local

residents will receive cultural awareness training to encourage understanding of incoming workers;

Implement measures to incentivise land and natural resource use in areas that are not likely to impact on

the PNNK, threatened species or habitats; and

In partnership with relevant technical services and the Commune Council, improve village water

infrastructure and management systems to address the impact of Project-induced in-migration.

The following policies and practices will be implemented by the Company to minimise the adverse impacts of

influx of workers for the Project:

Implement the measures in the Worker Accommodation Guidance Note (rePlan, 2015c), which include:

» Incentivise the in-migration of Project staff to Kedougou where this has potential to result in adverse

impacts to Project-affected villages;

» Provide transportation from Kedougou and shorter shifts (e.g. 8 hours) to enable workers to live and

commute from Kedougou without suffering from fatigue;

Page 155: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 140

» Provision of short-term loans to workers recruited locally for the construction of new rooms or

separate buildings for rental to Project employees from outside Kedougou Region;

» Development of a homeownership programme to provide new, permanent housing for Project

employees from outside Kedougou Region; and

Working with national and regional government to encourage the distribution of Project-related government

revenues to local communities to improve physical infrastructure and services.

Community Development

The Company will also support other programmes that contribute to local economic development and mitigation

of in-migration, including providing support to the Tomboronkoto Council in rural and urban land use and

development planning, and implementing a Social Investment Programme. These include:

Continued community development investment focused on key areas (e.g. water resources, health and

education services);

Preparation of training programmes relevant to the Project’s closure to help people transition to alternative

employment as discussed in the LEP;

Support for the Tomboronkoto Council and work with the local community to develop formal land use and

urban development plans (e.g. the Commune Development Plan); and

Ensuring that revegetation and agricultural intensification activities increase the ability of local

communities to sustainably maintain access to natural resources and reduce stress on the nearby PNNK.

In-migration monitoring

The Company will undertake socio-economic surveying and review of census data for Project affected villages to

be conducted over the Project life to understand the extent of population growth and any related impacts,

including but not limited to the effect it has on water quality and availability.

15.3.2 Operations Phase

Operations mitigation measures for in-migration will be as per the pre-construction and construction phase as

outlined above, where applicable.

15.3.3 Decommissioning and Closure Phase

No additional management and mitigation measures are expected to be required during the decommissioning and

closure phase.

15.4 Monitoring Measures

The Company will develop Project-specific KPIs for employment of local and national workers and associated

training. Table 15-1 summarises the key monitoring measures that will apply for in-migration associated with the

Mako Gold Project during all phases of development. These will be incorporated into the detailed monitoring

programmes prepared by the Company and its contractors.

Relevant guidelines and standards applicable to the Project are specified in Section 2.4 and the Registers of

Environmental and Social Management and Monitoring Commitments in Chapter 18 of this Plan.

Table 15-1 Register of Social Monitoring Measures – In-Migration

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Page 156: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 141

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Socio-

economic

and

livelihood

changes in

the vicinity

of the

Project

Socio-economic

conditions (e.g.

demographics,

livelihoods,

health etc.)

All Project

phases Household surveys

Demographic

indicators

Population growth

and in-migration

Income and

expenditure

indicators, incidence

of poverty

Livelihoods and

employment

indicators

Housing and assets

Education

Health and nutrition

indicators

Every two

years

Villages in

the vicinity

of the PDA

Monitoring of

regional socio-

economic

conditions for

Kedougou

All Project

phases

Socio-economic

monitoring/surveys

Similar indicators to

the above obtained

through review of

publically available

reports or in

consultation with

local authorities

Annually Kedougou

Region

Economic

Developmen

t and

Employment

Monitoring of

effectiveness of

local recruitment

All Project

phases

Employment records

Training register/records

Local workforce

statistics (including

employment by

contractors)

Number of training

sessions

Quarterly Project-

wide

Monitoring of

effectiveness of

local

procurement

All Project

phases

Local supplier and

procurement

records/database

maintained by the

Company

Training register/records

Local goods and

services procured by

the Company

Local suppliers used

by the Company

Number of training

session for suppliers

Quarterly Project-

wide

Monitoring of

local economic

pilot

programmes

All Project

phases

Socio-economic

monitoring/surveys

Indicators will be

developed in

consultation with the

community and

government

Quarterly

Villages in

the vicinity

of the

Project

Community

Relations

Review of

records

All Project

phases

Grievance register

Consultation record

sheet and database

Logged grievances

and resolutions Quarterly

Project

affected

villages

Page 157: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 142

16 BIODIVERSITY MANAGEMENT

16.1 Objectives

The key objective related to biodiversity management for the Mako Gold Project will be to minimise Project

impacts on nearby protected areas (i.e. PNNK) and local terrestrial and aquatic flora and fauna (particularly local

and international conservation significant species). Where biodiversity impacts will be unavoidable, the Company

will implement an offset programme that meets with government, local community and other stakeholder

expectations, to ensure a net gain of biodiversity values is achieved upon closure.

16.2 Context

In summary, key biodiversity sensitivities within and near the Project Area that will be protected from potential

Project impacts include:

Niokolo-Koba National Park (Parc National du Niokolo-Koba, PNNK), a National Protected Area and World

Heritage site located approximately 1 km west of the PDA;

Communal Nature Reserve (Réserve Naturelle Communautaire, RNC) located near Niemenike (though not

considered to be part of the State network of protected areas in Senegal and it is a not a priority biodiversity

feature);

Local flora and fauna, particularly local populations of priority species (Critically Endangered or Endangered

species according to IUCN listing) recorded within and near the PDA, including:

» Priority fauna species, e.g. West African chimpanzee (Pan troglodytes spp verus, CR), African Wild Dog

(West Africa subpopulation), Western Giant Eland (subspecies), and Lion (West African subpopulation);

» Priority flora species - Lepidagathis capituliformis, Scleria chevalieri and Tephrosia berhautiana.

Habitats of high conservation value, including the Bowal and Gallery forests and other priority biodiversity

features (which include species which are not critical habitat qualifying features but where their

conservation is considered significant at the regional and National scales), e.g. African elephant (Loxodonta

africana – VU), Hooded vulture (Necrosyrtes monachus – EN), and White-backed vulture (Gyps africanus –

EN); and

Downstream aquatic habitat and biodiversity values of the Gambia River and tributaries, including the

restricted range fish species Barbus dialonensis (a priority species).

Significant biodiversity impacts have been summarised in the following subsections. The ESIA (Volume A) provides

a full list of the priority biodiversity species and features relevant to the Project, including a detailed discussion of

potential Project impacts and relevant management and mitigation measures for the Company to adopt.

16.2.1 Pre-construction and Construction Phase

The most significant impact on habitat and flora associated with the Project is expected to be during this phase

from land clearance and site preparation for Project components and establishment of Project road infrastructure

and upgrades, including:

Removal of vegetation and habitat for Project components (approximately 216.22 ha of natural vegetation

in total, mainly tree savannah and woody savannah bamboo mosaic);

Habitat fragmentation and degradation from vegetation removal;

Project related access to forested areas associated with construction of new access roads making these

areas more readily accessible for forest resource extraction (e.g. increased hunting, timber, NTFP collection)

(refer to ESIA, Volume A, Chapter 10);

Page 158: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 143

Displacement of local populations of priority species (e.g. West African chimpanzee) within the PDA; and

Introduced non-native and invasive species, including weeds and pests.

The Project will result in both temporary and permanent loss of vegetated areas. However, all natural vegetation

and habitat to be removed for the Project components have been previously disturbed by anthropogenic activities

(e.g. artisanal mining, burning, land cultivation, and over-exploration of forest resources), at varying levels.

No key priority habitat will be removed for Project components. There will be no direct impact on the vegetation

within the PNNK as none will be removed for the Project.

16.2.2 Operations Phase

Many impacts experienced during the previous phase will continue in varying degrees and intensities during

Project operations. Clearance activities will be scaled back, however noise, vibration, airblast and dust impacts will

likely intensify, particularly from blasting and excavation of the Mine Pit. Local fauna populations within the PNNK

adjacent to the Mine Pit may be displaced by noise, vibration and airblasts. It is anticipated that local fauna within

the PDA, including priority species, will disperse into surrounding areas (especially the PNNK) during construction,

and all priority species will avoid the PDA during blasting and other operational activities. As such, the potential

impact on behaviour and the stress response will most likely be minimal.

Another significant biodiversity impact will likely be the potential physical barrier posed by the Mine and ancillary

facilities (e.g. access roads) to local fauna movements, particularly for breeding exchange of female chimpanzees.

In addition, although the Project has been designed for ‘zero discharge operations’, there may be inadvertent

impacts on downstream water quality and aquatic biodiversity values. Project water contaminated with cyanide

or high levels of salinity can be particularly hazardous, and fatal to some species (at certain concentrations), e.g.

avifauna. The WSD and TMF may pose a physical and chemical hazard to fauna, such as drowning, or poisoning

from drinking saline water or cyanide contaminated tailings water from the TMF (particularly for avifauna).

Changed behaviour of local fauna may also occur from sustained night lighting within the PDA (e.g. the Process

Plant, which will operate 24 hours).

16.2.3 Decommissioning and Closure Phase

Most impacts experienced during the previous phases will cease during the decommissioning and closure phase.

The most likely impacts will be similar to site preparation impacts during the Pre-Construction and Construction

Phase, including:

Significant erosion of disturbed surfaces yet to be stabilised and surface runoff sediment transport, leading

to water quality issues in the local catchments;

Dust and exhaust emissions from earthworks to reinstate pre-existing landforms, revegetation of land, and

removal of paved areas and existing infrastructure; and

Noise emissions from combustion engines of diesel generators, trucks, dozers, and hydraulic excavators.

If unmitigated, the greatest potential source of impact would be to water quality. Potential contaminants in

discharges to the receiving environment, particularly from the TMF, include: cyanide, metals (particularly Cu and

Mn), AMD, nutrients, saline water and suspended sediment. In the event of a contaminated discharge, impacts on

flora and will be the same as those outlined in the case of an accidental release during the Operation Phase.

16.3 Management and Mitigation Measures

The Mako Gold Project will apply IFC Performance Standards 6 to its operations where they are more rigorous than

local regulation as an appropriate benchmark of international good practise for the Project. A Project-specific

Biodiversity Action Plan (BAP, Volume C) has been prepared that will outline detailed plans and procedures for the

protection and management of biodiversity (aquatic and terrestrial) issues for the Mako Gold Project. A CEMP will

be developed in line with this ESMMP prior to construction. Key biodiversity measures and strategies detailed in

Page 159: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 144

the BAP and Offset Strategy will be incorporated into relevant procedures, training, and instructions for the

workforce and contractors, as relevant to their roles and responsibilities.

During every stage of the Project, the Company will implement the mitigation hierarchy to avoid, mitigate,

manage, restore and offset impacts on biodiversity. The Company will adopt a net-gain approach, where impacts

to biodiversity and conservation values are compensated through environmental benefits (e.g. biodiversity

offsets).

16.3.1 Pre-construction and Construction Phase

The Company will implement relevant SOPs provided in Appendix A to manage potential impacts generated

during pre-construction and construction of the various Project components, including those specific for

biodiversity management.

Vegetation, flora and protected areas management

To minimise inadvertent impacts to the PNNK from mining activities, the Company will avoid land disturbance

within a 1 km buffer zone of the PNNK. The Company will adopt measures outlined in the BAP (Volume C) to avoid

or manage temporary and permanent impacts on flora, fauna and protected areas during pre-construction and

construction, including:

The footprint of the Project components have been minimised to limit vegetation clearance to the extent

practicable. The Company will adopt the relevant vegetation clearance measures specified in SOP09: Land

Clearance and Soil Stockpile (Appendix A), where appropriate;

Access to the PNNK and buffer zone by Project staff to be restricted and subject to approval from the DPN;

Ban Project staff, as a condition of employment, from hunting, buying or trading wildlife as well as

collecting timber and NTFPs to help conserve existing fauna and forest resources (e.g. food for wildlife);

Environmental education and awareness programmes for Project staff and contractors as relevant to their

roles and responsibilities (e.g. through staff inductions) to improve their understanding of conserving

threatened species and forest resources for the environment and local communities. This will also ensure

that the penalties and Project ban regarding hunting, wildlife trade and the collection of other forest

resources are widely known;

The requirements for land disturbance permits prior to any vegetation clearance, in accordance with SOP09

(Appendix A). Environmentally sensitive areas (e.g. critical habitat, PNNK boundary) will be clearly marked

as ‘No Go Areas’;

In areas to be cleared, identification and retention or relocation of restricted-range (Lepidagathis

capituliformis, Scleria chevalieri and Tephrosia berhautiana), threatened flora and important fauna resources

(e.g. baobab trees), where practicable. Seed collection and propagation of priority flora species identified in

the Project Area will be included in the inventory of plants used for Project revegetation activities;

Removal of identified Bowal (where this provides habitat to restricted-range flora species) and gallery forest

habitat (priority habitat for West African chimpanzee nesting sites) to be avoided where possible;

Invasive weed prevention protocol implemented as per SOP9 (particularly to prevent the spread of Mimosa

pigra), including washdown procedures and site access control (along designated ingress/egress routes) for

vehicles entering and exiting the PDA, limiting vehicle movements between areas where Mimosa pigra is

confirmed to occur and unaffected areas, and use of non-invasive local species for revegetation;

Progressive rehabilitation and revegetation undertaken as soon as possible throughout the life of the

Project to minimise the impact of land clearance as per the RCMCP (Volume E);

Bushfire controls implemented, including Project ban on open-burning of wastes, specific emergency

response procedures developed for managing bushfires, and establishment of fire breaks (where required);

Consult with local authorities to minimise the impact of in-migration on natural resource exploitation

(including hunting); and

Page 160: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 145

Periodic monitoring of habitat and key terrestrial and aquatic wildlife species to be conducted as part of the

BAP (Volume C) to assess whether any further mitigation or management measures are required.

In addition, Chapter 9 (Road and Transport) details specific measures for minimising potential impacts on wildlife

from Project related transportation, including emergency response systems for spills, and speed limits through

known sensitive areas (e.g. West African chimpanzee wildlife crossings).

Fauna management

The Company will adopt additional measures to mitigate fauna impacts, including:

Primary sources of water potentially contaminated with cyanide and other pollutants (e.g. waste

management facilities, Process Plant and TMF, hazardous chemicals and fuel storage areas) have been sited

within a single catchment away from major drainage lines with primary and secondary containment

facilities in place to prevent potential discharge into the receiving environment. These sites will have

fencing constructed to prevent access by fauna;

Security fencing provided around the site perimeter of the TMF to restrict livestock and local wildlife from

accessing this area;

Mandatory reporting system to record reportable incidents involving wildlife (and livestock), including

encounters of wildlife (i.e. injured and priority species) and observation of poaching, illegal wildlife trade or

logging. Relevant government authorities will be notified as necessary;

Adherence to the Injured Wildlife Protocol by staff and contractors if injured or dead wildlife is found or in

the event of an accident (e.g. fauna move away following vehicle collision), which includes the following

steps:

» Species identification;

» Procedures for the safe management of injured or dead wildlife including minimising human contact;

and

» Mandatory reporting of wildlife incidents that includes road accidents (e.g. collision with wildlife or

livestock) for all Project workers and contractors;

Operation of noisy machinery to be avoided at dusk, dawn and night;

Project staff to avoid initiating contact with fauna to minimise the risk of disease transfer and disturbance;

Project staff and contractors banned from hunting, buying or trading wildlife, fishing, collecting timber and

non-timber forest products and from entering the PNNK;

An ecologist will be on call during habitat clearance work to provide assistance / advice regarding any

biodiversity issues if required;

Priority species-specific monitoring and management (e.g. for West African chimpanzees) to be undertaken

as appropriate, as per the BAP (Volume C);

Implement relevant fauna management measures for night lighting detailed in SOP11: Lighting and Visual

Amenity Management, where necessary; and

Adherence to SOP02: Water Quality and Pollution Management for water quality and pollution

management throughout the lifespan of the Project to minimise the risk of adverse impacts to aquatic

fauna and habitats.

Project Induced In-migration

The Company will consult with local authorities to minimise the impacts of Project-induced in-migration on

chimpanzees and their habitats arising from hunting and the increased exploitation of timber and non-timber

products. The Company will also collaborate with PNNK area managers to ensure indirect impacts to the PNNK are

adequately mitigated.

Page 161: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 146

Biodiversity offset

To ensure ‘no net loss’ of regional and local biodiversity values, the Company has developed a Biodiversity Offset

Strategy to provide a compensatory mechanism to offset adverse impacts that cannot be avoided, mitigated

and/or managed. The Biodiversity Offset Strategy will be designed through a process of stakeholder engagement

and will focus on the conservation of priority species and habitats including the protection of the PNNK.

Refer to the BAP (Volume C) for further details of the strategy.

16.3.2 Operations Phase

The Company has designed for the Project to be a ‘zero discharge operations’ to avoid downstream water quality

impacts from environmental release of water potentially contaminated with pollutants such as cyanide, heavy

metals, nutrients and salinity. Additionally, concentrations of cyanide in tailings water will be regularly monitored

for consistency with relevant standards (i.e. ICMI Cyanide Code, 2014).

The management measures and strategies specified for the pre-construction and construction phase management

will continue to be applied during Project operations, where relevant. Additional biodiversity management

measures that will be applied during Project operations include:

Management of habitats and buffer zones adjacent to and within the PDA to minimise disturbance and

vegetation clearance (e.g. from poaching, exploitation of natural resources);

Establishment of a checkpoint at the entrance to the PDA to ensure no unauthorised entry;

Continual improvement of mine blast associated noise, vibration and airblast management measures to

minimise fauna impacts; and

Adaptive priority species-specific monitoring and management, as necessary.

16.3.3 Decommissioning and Closure Phase

Upon decommissioning and closure, the TMF will be rehabilitated and surface water from the facility (as well as

inputs from the WRD and Mine Pit overflow) will discharge from a constructed spillway into Badalla Creek

downstream of the facility, upstream from the PNNK.

In addition to the SOPs provided in Appendix A and the continued implementation of relevant measures listed

above, the Company will adopt the following vegetation mitigation measures as per the RCMCP (Volume E) in

accordance with the Forest Code and other legislative requirements:

Creation of natural filtering systems (e.g. mini-wetlands), where required;

Progressive revegetation and rehabilitation of all cleared/disturbed areas, unless required for community or

Government use;

Use of artificial filtering systems on discharge water;

Closure criteria for revegetation and vegetation offsets will be met; and

Monitoring conducted in rehabilitated areas, in order to assess the success of restoration of habitat.

16.4 Monitoring Measures

Table 16-1 summarises the preliminary monitoring measures that will apply for biodiversity management in

relation to the Mako Gold Project. The preliminary detailed biodiversity monitoring programme will further be

refined as more biodiversity management and offset information becomes available, and will be incorporated into

relevant documents for the Company and contractors to adhere to for the pre-construction, construction,

operation, and decommissioning and closure of the Project.

Refer to Biodiversity Action Plan (Volume C) for further details on the detailed biodiversity monitoring

programme, including specific monitoring sites for the Project. Relevant guidelines and standards applicable to

Page 162: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 147

the Project are specified in Section 2.4 and in the Registers of Environmental and Social Management and

Monitoring Commitments in Chapter 18 of this Plan.

Table 16-1 Register of Environmental Monitoring Measures– Biodiversity Management

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Terrestrial

habitat and

biodiversity

Terrestrial

habitat and

biodiversity

Camera

trapping

All

Project

phases

Review of data collected

from camera trapping

Changes in the location

of habitat use

Changes in frequency

of habitat use

Trigger for adaptive

management:

Decline in habitat use

Traps

checked

every two

months

Refer to

Biodiversit

y Action

Plan

(Volume C)

Targeted

chimpanzee

surveys

All

Project

phases

Review of data collected

from targeted

chimpanzee surveys

Changes in the number

of fresh, recent, old and

ancient nests

Changes in nesting

range

Changes in habitat

usage

Trigger for adaptive

management:

Significant decline in

the number of fresh /

recent nests

Significant declines in

maximum number of

nests per nesting site

Reduction in nesting

range

Census

undertaken

every two

years during

the wet and

dry seasons

Targeted

hippopotami

surveys

All

Project

phases Review of data collected

from targeted

hippopotami surveys

Changes in the total

number of hippopotami

Changes in the

maximum number of

hippopotami per group

Changes in seasonal

habitat use

Trigger for adaptive

management:

Significant reduction in

hippopotami numbers

Reduction in habitat

use between seasons

Census

undertaken

once a year

over a 3 days

period during

wet and dry

seasons

Vulture nest

surveys

All

Project

Review of data collected

from vulture nest surveys

Changes in the number

of active vulture nests

Changes in the number

of vulture nesting sites

Trigger for adaptive

Twice a year

during the

optimum

breading

season,

supplemente

Page 163: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 148

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

Terrestrial

habitat and

biodiversity

phases management:

Significant decline in

the number of active

nests

Decline in sites

d by camera

trapping

Priority flora

survey

All

Project

phases

Assessment of presence

/ likely absence of key

flora species

Records of

presence/absence of

key flora species

Beginning of

the wet

season when

grasses and

herbs are in

flower

Priority flora

monitoring

All

Project

phases Assessment of priority

flora monitoring

Dust levels

High level of dust on

individuals and signs of

plant stress

Changes in species

abundance

Trigger for adaptive

management:

Elevated dust levels

High coverage of dust

on priority flora and

bowal habitat

Monthly

checks during

construction

Quarterly

checks during

operations

Ongoing for

dust

monitoring

Invasive

species

reporting and

checks

Pre-

constru

ction,

Constru

ction,

Closure

Assessment of invasive

weed monitoring

New record of invasive

species i.e. Mimosa

Pigra

Trigger for adaptive

management:

Increased number of

infested sites

Bimonthly

during pre-

construction,

construction,

and closure

Quarterly

during

operations

Reportable

incidents

involving

wildlife (and

livestock),

including

encounters of

wildlife (i.e.

carcass,

injured and

priority

species) and

observation of

poaching,

illegal wildlife

All

Project

phases Mandatory wildlife

incident reporting system

for Project employees

and contractors

Relevant government

authorities will be notified

as necessary

Reportable information

includes:

- Species details, any

distinguishing features

(e.g. carcass found

near the TMF or road

side);

- Location / GPS data;

- Time and date;

- Weather conditions;

- Photograph, if

possible; and

- Any measures or

actions undertaken, if

applicable.

Trigger for adaptive

Ongoing

Page 164: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 149

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

trade or

logging.

management:

- Changes in the

number of deaths

- Confirmation of

disease outbreak

- Number of confirmed

poison cases

Monitoring of

vegetation

clearance

Pre-

Constru

ction,

Constru

ction

Routine checks to ensure

vegetation clearing is

confined to defined areas

of disturbance, vehicles

use designated access

routes, and any sensitive

environmental areas (i.e.

‘No Go Areas’) flora

specimens to be retained

are clearly marked (e.g.

flag/tape).

Land disturbance register

Extent of vegetation

cleared for the Project

During

vegetation

clearing

activities

Project-

wide

Aquatic

habitat and

biodiversity

Macro-

invertebrate

survey and

bio-indicator

water quality

assessment

All

Project

phases Aquatic fauna and habitat

monitoring as per

SOP02.18

Changes in water

quality identified by the

macro-invertebrate bio-

indicator assessment

Trigger for adaptive

management:

Significant decline in

macro-invertebrate

abundance and

diversity

Significant changes in

bio-indicator species

Reduction in the

biological health of the

Gambia River

Threshold limits

provided in Table 2-5 to

Table 2-7

Bi-yearly

during the dry

season over

a 5 day

period

Refer to

monitoring

sites

shown in

Figure A3

(Appendix

C) and

Biodiversit

y Action

Plan

(Volume C)

Drift net

survey

All

Project

phases

Aquatic fauna and habitat

monitoring as per

SOP02.18

Changes in the

diversity, abundance

and catch per unit effort

of fish

Changes in the

proportion captured

juvenile and adult fish

Trigger for adaptive

management:

Significant decline in

Bi-yearly

basis during

the dry and

wet seasons.

Each survey

conducted

over a 5-day

period

Page 165: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 150

Aspect /

Impact

Monitoring

Measure

Phase Method Parameters Frequency Location

the diversity,

abundance, CPUE of

fish

Significant decline in

adult fish

Impingement

checks

All

Project

phases

Review of aquatic

monitoring data collected

High quantity of biotic

impingement matter

Weekly for

one month

following pipe

installation,

subsequent

quarterly

checks

Rehabilitatio

n

Routine

monitoring of

rehabilitation

areas to

assess the

success of

restoration

measures

All

Project

phases

Land rehabilitation

register

Monitoring records of:

- Area

revegetated/rehabilitate

d;

- Survival rate of

planted seedlings by

species type and

replanting

requirements;

- Native versus non-

native plant

establishment; and

- Photographs.

Ongoing

Project-

wide (refer

to the

RMCP,

Volume D)

Water

quality

(ambient)

Routine

ambient water

quality

monitoring

Pre-

constru

ction,

Constru

ction

Visual checks for

sedimentation, oils and

grease

Project compliance Weekly

Discharge

points

(refer to

monitoring

sites

shown in

Figure A2,

Appendix

C)

All

Project

phases

Refer to SOP02.12

Field parameters and

laboratory testing as

per SOP02.12

Trigger for adaptive

management:

Water quality exceeds

applicable compliance

limit

Threshold limits

provided in Table 2-5 to

Table 2-7

Monthly

Upstream

and

downstrea

m of

Badalla

Creek and

Gambia

River (refer

to

monitoring

sites

shown in

Figure A2,

Appendix

C)

Page 166: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 151

17 ESTIMATED COSTS

The Company is committed to providing sufficient resources to ensure the successful implementation of the

environmental and social management and monitoring of the Mako Gold Project as identified in the ESMMP. The

Company will also ensure that, where applicable, contractors also include sufficient resources for the

environmental management of their activities.

The Company currently invests significant expenditure on environmental and social management and monitoring

for their Mako exploration activities. The development of the Mako Gold Project will lead to a significant increase

in the overall the Company environmental and social management operating budget.

A preliminary analysis of environmental and social management costs associated with the construction and

management of the Mako Gold Project has been undertaken.

Table 17-1 displays a conceptual Environmental and Social Management and Monitoring Budget. The proposed budget

includes capital cost, annual operating costs, and a closure cost (over five years). The closure budget will need to

be refined based on the result of closure investigations.

Page 167: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 152

Table 17-1 Conceptual budget for social and environmental management and monitoring for the Mako Gold Project during pre-construction, construction, operations, and decommissioning /

closure phases (FCFA ±20%) (converted from USD: 1USD = 587.706 FCFA, 9/9/2015)

Item Pre-

construction

Construction

Operations Decommissioning and Closure

Total

Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13

Staffing Costs

Human Resources (Environment and Social Dept.)

- 323,238,3

00 323,238,3

00 323,238,3

00 323,238,3

00 323,238,3

00 323,238,3

00 323,238,3

00 323,238,3

00 323,238,3

00 129,295,3

20 129,295,

320 129,295,

320 129,295

,320 129,295,320

3,555,621,300

Sub-total 0 323,238,3

00 323,238,3

00 323,238,3

00 323,238,3

00 323,238,3

00 323,238,3

00 323,238,3

00 323,238,3

00 323,238,3

00 129,295,3

20 129,295,

320 129,295,

320 129,295

,320 129,295,320

3,555,621,300

Capital Costs

Installation of groundwater monitoring bores

- 158,680,6

20 - - - - - - - - - - - - - 158,680,620

Establishment of environmental monitoring and laboratory equipment

- 88,155,90

0 - - - - - - - - - - - - - 88,155,900

Maintenance of environmental monitoring and laboratory equipment (10% capital)

- - 8,815,590 8,815,590 8,815,590 8,815,590 8,815,590 8,815,590 8,815,590 8,815,590 8,815,590 8,815,59

0 8,815,59

0 8,815,5

90 8,815,590

114,602,670

Sediment control infrastructure / materials

Not costed - to be included in mine design 0

TMF control measures for fauna (e.g. fencing)

Not costed - to be included in mine design 0

Sub-total 0 246,836,5

20 8,815,590 8,815,590 8,815,590 8,815,590 8,815,590 8,815,590 8,815,590 8,815,590 8,815,590

8,815,590

8,815,590

8,815,590

8,815,590

361,439,190

Page 168: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 153

Item Pre-

construction

Construction

Operations Decommissioning and Closure

Total

Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13

Environmental and Social Management Systems

Environmental and social monitoring protocols

23,508,240

11,754,120

11,754,120

- 2,938,530 - 2,938,530 - 2,938,530 - - - - - - 55,832,070

Preparation / Update of Monitoring Manual, CEMPs and Operations ESMMP

14,692,650

14,692,650

- - - - - - - - - - - - - 29,385,300

Regular updates of environmental and social management plans

- - 17,631,18

0 17,631,18

0 17,631,18

0 17,631,18

0 17,631,18

0 17,631,18

0 17,631,18

0 17,631,18

0

Refer Closure Costs

141,049,440

Internal audits / performance review

5,877,060

5,877,060 5,877,060 5,877,060 5,877,060 5,877,060 5,877,060 5,877,060 5,877,060 5,877,060 58,770,600

External audits 23,508,2

40 23,508,24

0 23,508,24

0 23,508,24

0

23,508,240

23,508,24

0 141,049,440

Annual Sustainability Report

- 5,877,060 5,877,060 5,877,060 5,877,060 5,877,060 5,877,060 5,877,060 5,877,060 5,877,060 - - - - - 52,893,540

Capacity building for local authorities, including Regional Environmental Monitoring Committee

- 17,631,18

0 17,631,18

0 17,631,18

0 17,631,18

0 17,631,18

0 17,631,18

0 17,631,18

0 17,631,18

0 17,631,18

0 17,631,18

0 17,631,1

80 17,631,1

80 17,631,

180 17,631,180

246,836,520

Sub-total 67,586,1

90 79,340,31

0 82,278,84

0 70,524,72

0 49,955,01

0 47,016,48

0 73,463,25

0 47,016,48

0 49,955,01

0 70,524,72

0 17,631,18

0 17,631,1

80 17,631,1

80 17,631,

180 17,631,180

725,816,910

Environmental Management and Mitigation

Page 169: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 154

Item Pre-

construction

Construction

Operations Decommissioning and Closure

Total

Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13

Hazardous Facility Registration (ICPE) and Emergency Response Plan (POI)

11,754,120

11,754,120

11,754,120

- - - - - - - - - - - - 35,262,360

Environmental monitoring, laboratory analysis and consumables

- 117,541,2

00 117,541,2

00 117,541,2

00 117,541,2

00 117,541,2

00 117,541,2

00 117,541,2

00 88,155,90

0 88,155,90

0 58,770,60

0 58,770,6

00 44,077,9

50 29,385,

300 29,385,300

1,219,489,950

Finalisation of Biodiversity Action Plan (BAP)

14,692,650

29,385,300

14,692,650

- - - - - - - - - - - - 58,770,600

Supplementary pre-construction baseline surveys

20,569,710

11,754,120

- - - - - - - - - - - - - 32,323,830

General Biodiversity Monitoring including targeted fauna surveys

8,815,590

8,815,590 17,631,18

0 8,815,590

17,631,180

8,815,590 17,631,18

0 8,815,590

17,631,180

8,815,590 17,631,18

0 8,815,59

0 17,631,1

80 8,815,5

90 17,631,180

193,942,980

Preparation and implementation of Cultural Heritage/Archaeology Management Plan

- 8,815,590 17,631,18

0 - 8,815,590 - 5,877,060 - 5,877,060 - - - - - - 47,016,480

Major Update of Rehabilitation and Closure

- - - - - - - - - 17,631,18

0 - - - - - 17,631,180

Page 170: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 155

Item Pre-

construction

Construction

Operations Decommissioning and Closure

Total

Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13

Plan Prior to Decommissioning

Preparation of Blasting Management Plan by blasting contractor

Not costed - to be included in mine design 0

Implementation of other aspects of ESMMP and BAP

Covered by staffing costs 0

Sub-total 55,832,0

70 188,065,9

20 179,250,3

30 126,356,7

90 143,987,9

70 126,356,7

90 141,049,4

40 126,356,7

90 111,664,1

40 114,602,6

70 76,401,78

0 67,586,1

90 61,709,1

30 38,200,

890 47,016,480

1,604,437,380

Biodiversity Offset Programme

Preparation of Biodiversity Offset Plan

29,385,300

29,385,300

29,385,300

- - - - - - - - - - - - 88,155,900

Biodiversity Offset Programme implementation

- 14,692,65

0 88,155,90

0 88,155,90

0 88,155,90

0 88,155,90

0 88,155,90

0 88,155,90

0 88,155,90

0 88,155,90

0 - - - - - 719,939,850

Biodiversity Offset Fund

- - 88,155,90

0 88,155,90

0 88,155,90

0 88,155,90

0 88,155,90

0 88,155,90

0 88,155,90

0 88,155,90

0 - - - - - 705,247,200

Biodiversity Offsets Monitoring (including detailed monitoring protocol development, satellite imagery analysis and ground-

17,631,180

11,754,120

11,754,120

11,754,120

11,754,120

11,754,120

11,754,120

11,754,120

11,754,120

11,754,120

11,754,120

11,754,120

11,754,120

11,754,120

11,754,120

182,188,860

Page 171: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 156

Item Pre-

construction

Construction

Operations Decommissioning and Closure

Total

Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13

truthing)

Supporting Biodiversity Conservation Actions

- - 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 - - - - - 235,082,400

Sub-total 47,016,4

80 55,832,07

0 246,836,5

20 217,451,2

20 217,451,2

20 217,451,2

20 217,451,2

20 217,451,2

20 217,451,2

20 217,451,2

20 11,754,12

0 11,754,1

20 11,754,1

20 11,754,

120 11,754,120

1,930,614,210

Social Management / Stakeholder Consultation Costs

Stakeholder and Government consultation / Community relations

- 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 Refer Closure Costs 264,467,700

Design and planning for Livelihood Restoration Program

29,385,300

44,077,950

29,385,300

- 14,692,65

0 - 5,877,060 - - - - - - - - 123,418,260

Livelihood Restoration Program Implementation (rePlan, 2015)

23,508,240

185,127,390

108,725,610

99,910,020

23,508,240

17,631,180

- - - - - - - - - 458,410,680

Livelihood Improvement Programs (rePlan, 2015)

- - - 105,787,0

80 82,278,84

0 82,278,84

0 70,524,72

0 70,524,72

0 - - - - - - - 411,394,200

Vulnerable Peoples Programs (rePlan, 2015)

- 14,692,65

0 14,692,65

0 - - - - - - - - - - - - 29,385,300

Page 172: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 157

Item Pre-

construction

Construction

Operations Decommissioning and Closure

Total

Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13

Community Infrastructure Mitigation Program (water, health and sanitation facilities)

29,385,300

58,770,600

58,770,600

29,385,300

29,385,300

29,385,300

14,692,650

14,692,650

14,692,650

14,692,650

Refer Closure Costs 293,853,000

Local Economic Participation Plan (including local content initiatives and capacity building)

29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 29,385,30

0 - - - - - 264,467,700

Preparation of Community Safety Plan

11,754,120

11,754,120

- - - - - - - - - - - - - 23,508,240

Social Monitoring

11,754,120

- 29,385,30

0 -

29,385,300

- 29,385,30

0 -

29,385,300

- Refer Closure Costs 129,295,320

Sub-total 105,787,

080 373,193,3

10 299,730,0

60 293,853,0

00 238,020,9

30 188,065,9

20 179,250,3

30 143,987,9

70 102,848,5

50 73,463,25

0 0 0 0 0 0

1,998,200,400

Environmental and Social Investment Fund

Environmental and Social Investment Fund

- 117,541,2

00 264,467,7

00 264,467,7

00 264,467,7

00 264,467,7

00 264,467,7

00 264,467,7

00 264,467,7

00 264,467,7

00 - - - - -

2,233,282,800

Sub-total - 117,541,2

00 264,467,7

00 264,467,7

00 264,467,7

00 264,467,7

00 264,467,7

00 264,467,7

00 264,467,7

00 264,467,7

00 - - - - -

2,233,282,800

Rehabilitation and Closure Costs

Physical Closure Costs

- - 39854608

4 39854608

4 39854608

4 39854608

4 39854608

4 39854608

4 39854608

4 39854608

4 75158427

7 1337257

27 1131731

58 103097

674 103097674

4,393,047,179

Closure Investigations and Methodology

- - 58035968 58035968 58035968 58035968 58035968 58035968 58035968 58035968 0 0 0 0 0 464,287,740

Socio- - - 45914531 45914531 45914531 45914531 45914531 45914531 45914531 45914531 0 0 0 0 0 367,316,250

Page 173: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 158

Item Pre-

construction

Construction

Operations Decommissioning and Closure

Total

Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13

economic Closure

Stakeholder Consultation

- - 11754120 - 11754120 - 11754120 - 11754120 - 11754120 0 1175412

0 0

11754120

82,278,840

Purchase/Hire Specialised Equipment

- - 29385300 29385300 29385300 29385300 29385300 29385300 29385300 29385300 0 0 5877060

0 0 0 293,853,000

Planning, Auditing and Reporting

- - 22038975 22038975 22038975 22038975 22038975 22038975 22038975 22038975 49073451 0 0 0 19688151

245,073,402

Staff and Contractor Demobilisation

- - - - - - - - - - 98734608 0 0 0 42314832

141,049,440

Post-Closure Monitoring

- - - - - - - - - - 11871661

2 1187166

12 1187166

12 118716

612 118716612

593,583,060

Administration and Personnel Costs

- - 47016480 47016480 47016480 47016480 47016480 47016480 47016480 47016480 17631180

0 4701648

0 4701648

0 470164

80 47016480

740,509,560

Sub-total 0 0 612,691,4

57 600,937,3

37 612,691,4

57 600,937,3

37 612,691,4

57 600,937,3

37 612,691,4

57 600,937,3

37 1,206,174

,868 299,458,

819 349,430,

970 268,830

,766 342,587,869

7,320,998,471

Grand Total 276,221,

820 1,384,047

,630 2,017,308

,797 1,905,644

,657 1,858,628

,177 1,776,349

,337 1,820,427

,287 1,732,271

,387 1,691,131

,967 1,673,500

,787 1,450,072

,858 534,541,

219 578,636,

310 474,527

,866 557,100,559

19,730,410,661

Page 174: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 159

18 REGISTERS OF ENVIRONMENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES

18.1 Summary of Environmental Management and Monitoring Measures

Table 18-1 Register of Environmental Management Systems Improvement Measures

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

Project Staff

Responsibilities

The Company will appoint suitably qualified and

experienced staff to implement the Project

ESMMP, including personnel responsible for

security, health and safety, environment and

community, emergency response, human

resources, and logistics.

Verification of implementation Project Director /

Operations Manager /

DEEC and CRSE

Not applicable.

Project Capacity

Building

The provisions for Project capacity building of

relevant external (i.e. regulatory government

authorities) and internal (i.e. for Project staff)

parties will be continually adapted to meet ongoing

needs, including for training, workshop,

competency upskilling, and induction provisions.

This will include capacity building and support for

the Regional Environmental Monitoring

Committee.

Verification of implementation OHS&E Manager / DEEC

and CRSE

Not applicable.

Project Capacity

Budget

The Company will continually review, update, and

fund the Project Environmental and Social

Management and Monitoring Budget.

Verification of implementation Project Director /

Operations Manager /

DEEC and CRSE

Not applicable.

Page 175: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 160

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

Environmental

awareness,

training and

induction

A community awareness program will be

undertaken regarding community safety issues

associated with blasting, road safety, hygiene and

sanitation, and disease prevention. The program

will be continually adapted to meet ongoing needs

and risks to potentially affected peoples.

Records (i.e. attendance sheets,

photos, material used, etc.) of

local community attendance

OHS&E Manager / DEEC

and CRSE

Not applicable.

An environmental induction will be conducted for

Project staff and contractors as appropriate for

their role and responsibilities. In addition to

increasing understanding of environmental issues

on site, this will also ensure that applicable

penalties and Project bans (e.g. drink driving,

trading wildlife products, etc.) are widely known.

Records (i.e. attendance sheets)

of Project staff and contractors

OHS&E Manager / DEEC

and CRSE

Not applicable.

Environmental training on specific work

procedures as specified in this ESMMP will be

provided for employees (including Contractors), as

appropriate for their role and responsibilities.

Records (e.g. attendance

sheets, formal training register)

of specific training course

attendance

OHS&E Manager / DEEC

and CRSE

Not applicable.

Emergency

Preparedness

And Response

Project specific Emergency Preparedness and

Response Plans will be developed prior to the

start of operations to include a POI in line with

Senegalese guidelines and a Cyanide Spill

Contingency Plan, and appropriate spill prevention

and response procedures in line with industry best

practice, IFC General EHS Guidelines, and the

ICMI Cyanide Code.

Verification of implementation Project Director /

Operations Manager /

DEEC and CRSE

Company Plans and Procedures

Project Risk Assessment (Etude de

Danger)

Emergency Preparedness and Response

Plans

Relevant Guidelines and Standards

Page 176: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 161

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

The Company will undertake a Project risk

assessment on an annual basis to review potential

emergency situations that may arise from the

Project in line with the methodology developed in

the Risk Assessment (Etude de Danger).

Records of risk workshops

Up-to-date Project risk register

Risk audits, job safety analysis,

etc.

OHS&E Manager / DEEC

and CRSE

Risk Assessment Guide (DEEC, 2007)

General EHS Guidelines (IFC, 2007)

Mining EHS Guidelines (IFC, 2007)

Cyanide Code (ICMI, 2014)

Monitoring Plans

and Programs

The Project Environmental and Social Monitoring

Manual will be updated in line with the various

monitoring programs set out in the ESMMP for the

different phases of the Project.

Verification of implementation OHS&E Manager / DEEC

and CRSE

Company Plans and Procedures

Environmental and Social Monitoring

Manual

A comprehensive environmental monitoring

program will be implemented in line with this

ESMMP to ensure any Project discharges to the

receiving environment will comply with applicable

guidelines and standards (e.g. for water quality, air

quality, and noise).

Monitoring databases,

inventories, results, records of

inspections/observations, etc.

(refer to Section 3.5.1 for further

details)

OHS&E Manager / DEEC

and CRSE

Relevant Guidelines and Standards

Refer to Table 2-3 of the ESMMP for

relevant environmental standards and

guidelines for the Project.

A comprehensive social monitoring program will

be implemented in line with this ESMMP.

Monitoring databases,

inventories, results, records of

inspections/observations, etc.

(refer to Section 3.5.1 for further

details)

OHS&E Manager / DEEC

and CRSE

Relevant Guidelines and Standards

Refer to Table 2-3 of the ESMMP for

relevant environmental standards and

guidelines for the Project.

Develop a detailed protocol for biodiversity

monitoring in accordance with this ESMMP and

the BAP.

Verification of implementation OHS&E Manager / DEEC

and CRSE

Company Plans and Procedures

BAP

Project reporting

Quarterly and annual reporting will be undertaken

for relevant regulatory authorities, as well as

reportable incidents and community grievances

reporting. Databases will be established and

maintained to support the Project reporting

Quarterly Reports and Annual

Sustainability Reports

Logged grievances

Reported incidents and near-

OHS&E Manager / DEEC

and CRSE

Global Reporting Initiative Sustainability

Reporting Guidelines

Page 177: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 162

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

commitments in place.

misses

Audit reports

Construction

Environmental

Management

Plan (CEMP)

A CEMP will be developed in line with this ESMMP

prior to construction.

Verification of implementation OHS&E Manager,

Contractors / DEEC and

CRSE

Company Plans and Procedures

CEMP, ESMMP

Contractor

Environmental

Management

Plans (EMPs)

Principal contractors for the Project will be

required to develop specific EMPs , which

incorporate measures detailed in this ESMMP and

as relevant to their work activities.

Verification of implementation OHS&E Manager,

Transport contractor,

Construction contractor,

Mining contractor,

Blasting contractor, Fuel

farm contractor, Power

station contractor / DEEC

and CRSE

Company Plans and Procedures

CEMP, ESMMP, SOPs

Blasting and

Flyrock

Management

Planning

A detailed Blast Management Plan will be

prepared that will specify blasting procedures,

training, auditing, PPE and other requirements.

OHS&E Manager, Blast

Contractor / DEEC and

CRSE

Company Plans and Procedures:

Blast Management Plan (to be

developed)

SOP08: Blast Management

SOP04: Emission and Dust Control

SOP05: Noise and Vibration

Management

International Standards and Guidelines:

Leading Practice Sustainable

Development Program for the Mining

Industry: Airborne Contaminants, Noise &

Page 178: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 163

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

Vibration (Australian Government, 2009)

Mining EHS Guidelines (IFC, 2007)

Waste

Management

Planning

The Company will prepare and implement a

detailed Waste Management Plan (inclusive of

hazardous wastes), and Waste Rock Management

Plan for the Project. The TMF Operating and

Monitoring Manual will be finalised prior to

Operations.

Verification of implementation OHS&E Manager / DEEC

and CRSE

Company Plans and Procedures

Waste Management Plan (to be

developed)

Waste Rock Management Plan (to be

developed)

TMF Operating and Monitoring Manual

(to be finalised)

National Standards:

Draft Standard on Management of Solid

Waste / Projet de Norme relative à la

Gestion des Déchets Solides (2005)

International Standards and Guidelines:

Mining EHS Guidelines (IFC, 2007)

General EHS Guidelines– Waste

Management (IFC, 2007)

Community

Safety Planning

A Community Safety Plan will be prepared and

implemented Verification of

implementation

Logged grievances

Noise limit and air quality

limit exceedances at

nearby sensitive

receptors

Health and nutritional

OHS&E Manager,

Contractors / DEEC and

CRSE

Company Plans and Procedures

Emergency Preparedness and Response

Plans (to be developed)

Blast Management Plan (to be

developed)

International Standards and Guidelines:

General EHS Guidelines (IFC, 2007)

Page 179: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 164

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

indicators in the local

community (e.g.

availability of food, food

supply options,

prevalence of

undernourishment,

agricultural / food

production etc.) and

workforce

Incident register

Mining EHS Guidelines (IFC, 2007)

IFC PS4 Community Health, Safety and

Security (2012)

IFC PS5 Land Acquisition and Involuntary

Resettlement (2012)

ICMI, International Cyanide Management

Code (2014)

Update of Plans

and Manuals

Review and update ESMMP prior to the

commencement of Construction, prior to the

commencement of Operations and every two

years during Project Operations to reflect changes

to Project activities, commitments, environmental

and social conditions, regulatory requirements,

and potential optimisation of best management

practices

Verification of implementation OHS&E Manager / DEEC

and CRSE

Company Plans and Procedures

ESMMP

Review and update the key

plans/manuals/programs prior to Operations and

then at least every 2 years thereafter, or when

there is a major change in the design or operation

of the Project. These will include:

Biodiversity Action Plan;

Stakeholder Engagement Plan;

Livelihood Restoration Plan;

Local Economic Participation Plan (LEPP);

Verification of implementation OHS&E Manager / DEEC

and CRSE

Not applicable.

Page 180: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 165

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

Community Safety Plan;

Waste Management Plan (inclusive of

hazardous wastes);

Waste Rock Management Plan;

TMF and WSD Operating and Monitoring

Manual;

Blast Management Plan;

Environmental and Social Monitoring

Manual; and

Emergency Preparedness and Response

Plans.

Rehabilitation

and Closure

Planning

Review and update Rehabilitation and Conceptual

Mine Closure Plan (RCMCP) at least every 3

years during Operations, or when there is a major

change in the design or operation of the Project.

Verification of implementation Operations Manager /

DEEC and CRSE

Company Plans and Procedures

RCMCP

Prepare a Final Rehabilitation and Mine Closure

Plan prior to Decommissioning.

Verification of implementation Operations Manager /

DEEC and CRSE

Company Plans and Procedures

RCMCP

Audits /

Inspections

Independent external audits of the ESMMP and its

implementation will be conducted once during the

construction phase and on an annual basis for the

first two years of operation. The frequency of

subsequent operational audits will be based on the

recommendations from the initial audits, and will

be at least every 3 years during operations.

As part of the audit of the ESMMP, an independent

external audit of the RCMCP will also be

Verification of

implementation

Audit reports

Project Director /

Operations Manager /

DEEC and CRSE

Company Plans and Procedures

ESMMP

RCMCP

Page 181: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 166

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

conducted as key operational and closure

milestones are reached.

The Environment Department will undertake a site

inspection of all Project facilities on a monthly

basis using a visual inspection form to record

observations onsite. KPIs will be developed to

enable environmental performance to be assessed

objectively and quantitatively across the operation.

Verification of

implementation

Site inspection reports

OHS&E Manager / DEEC

and CRSE

Company Plans and Procedures

Environmental Monitoring Manual

Social Monitoring Manual

TMF and WSD Operating and Monitoring

Manual

Page 182: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 167

18.2 Summary of Physical Management and Monitoring Measures

Table 18-2 Register of Physical Environment Management and Monitoring Measures

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

Project Traffic

and Transport

Safety

The Company will implement measures during the

construction, maintenance and operation of Project roads to

minimise the impact to other road users. These may include

the following:

Schedule for road works coordinated with relevant

agencies and stakeholders to minimise traffic

disruption for public and private road users;

Prior notification of planned road construction

activities likely to cause nuisance noise and dust

(e.g. blasts) to potentially affected villagers; and

Appropriate signage and traffic safety measures

(e.g. barriers) for road works will be undertaken in

consultation with local government and key

stakeholders.

The Company will implement measures to ensure traffic

safety, including:

All Project roads within the PDA will be signposted in

French to provide directions to traffic movements;

The use of private vehicles to be restricted once

past the Project entrance boundary;

Implementation of a ‘driver code of conduct’ for

Verification of implementation

Journey management plans

and in-vehicle monitoring

system for all Project vehicles

Records of driving training and

qualifications

Vehicle inspection checklists

Road safety and driver

compliance monitoring, e.g.

random breathalyser and

remote monitoring of driver

performance

Project vehicle fleet database

and maintenance program

Traffic incident reporting

system for the community and

Project workers: recording

date, time, location, persons

involved, and any actions

taken or required by the

OHS&E Manager,

Contractors /

DEEC and CRSE

1. Company Plans and

Procedures

2. CEMP

3. (Transport)

Environmental

Management Plan

4. Relevant Standards

and Guidelines:

5. Local and national

road standards

6. PS4 Community

Health, Safety and

Security (IFC, 2012)

7. General EHS

Guidelines – Traffic

Safety and Transport

of Hazardous

Materials (IFC, 2007)

8. International Cyanide

Management Code

(ICMI, 2012)

9. International Cyanide

Page 183: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 168

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

Project drivers and contractors;

Project vehicles to follow designated Project

transport routes within permitted driving hours;

Off-site vehicle movements (e.g. delivery of

supplies) to be limited to the day time, where

practicable;

Regular Project driver and contractor checks

performed for adherence to local traffic laws;

Vehicular speed limits as follows: Maximum of 50

km/h for Main Access Road, Haul roads and other

Project roads; National speed limit on the RN7; and

20 km/h through villages, residences or sensitive

areas (e.g. school);

Provision of training to vehicle drivers on safe

driving (e.g. collision avoidance), fatigue

management, and first aid training;

Project vehicles equipped with first aid equipment

and appropriate personal protection equipment

(PPE) (e.g. high visibility vest);

Vehicles transporting oversized loads to be

preceded by an escort ‘warning’ vehicle;

Transportation of dangerous goods and hazardous

materials will comply with measures specified in

SOP07: Hazardous Materials Management;

Zero tolerance on driving under the influence of drug

and alcohol for Project drivers. The Company will

contractor or the Company.

Management Code

Principles and

Standards of Practice

for cyanide handling,

storage and

transportation (ICMI,

2014)

10. United Nations,

Transport of

Dangerous Goods -

Model Regulations.

17th Revised Edition

(Volume 1) Geneva

2011

11. AS 1940 – The

Storage and Handling

of Flammable and

Combustible Liquids.

(Current 2004 ed.)

12. AS 2187 – Explosives

– Storage, Transport

and Use. (Current

1998 ed.).

Page 184: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 169

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

conduct regular compliance monitoring such as

random breathalyser and remote monitoring of

driver performance;

Project vehicles to meet road weight limits on the

designated routes, including for bridge crossings;

and

Safety inspections of Project vehicles will be

conducted on a regular basis (i.e. vehicle checklist

to complete).

A dust suppression program will be implemented involving

regular watering of unsealed road surfaces and trafficked

areas during the dry season or when excessive dust

generation is evident near sensitive receptors (e.g. villages /

settlements). Frequency of watering will be increased

during periods of high risk (e.g. dry and windy conditions).

Verification of implementation

Ambient dust monitoring for

dust deposition rates, PM10,

and PM2.5

Visual check for excessive

fugitive dust on unsealed

roads

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

CEMP

SOP04: Emissions and Dust

Control

National Standards:

Atmospheric Pollution Standard,

NS 05-062 / La Norme de rejets

NS 05-062 – pollution

atmosphérique (2004)

International Standards and

Guidelines:

Mining EHS Guidelines (IFC,

2007)

General EHS Guidelines – Air

Emissions and Air Quality (IFC,

2007)

Page 185: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 170

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

WHO Air Quality Guidelines –

Global Update (2005).

Routine maintenance of Project roads. Visual checks of road

condition

Project grievance mechanism

Incident register

OHS&E Manager /

DEEC and CRSE

Not applicable.

A vehicle and machinery maintenance program will be

established for the Project fleet to comply with relevant

standards and guidelines for transport safety, and vehicle

manufacturer’s instructions.

Project vehicle fleet database

and maintenance program

Vehicle inspection schedule

and checklists

OHS&E Manager /

DEEC and CRSE

National Standards:

Atmospheric Pollution Standard,

NS 05-062 / La Norme de rejets

NS 05-062 – pollution

atmosphérique (2004)

Environment Code (noise) (Code

de l’Environnement) (2001)

International Standards and

Guidelines;

Mining EHS Guidelines (IFC,

2007)

General EHS Guidelines (IFC,

2007)

WHO Air Quality Guidelines –

Global Update (2005)

UK Standards (vibration) BS

6472:2008, 4866:2010 and

7385-2:1993

International Cyanide

Management Code Principles

Page 186: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 171

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

and Standards of Practice for

cyanide handling, storage and

transportation (ICMI, 2014)

United Nations, Transport of

Dangerous Goods - Model

Regulations. 17th Revised

Edition (Volume 1) Geneva 2011

AS 1940 – The Storage and

Handling of Flammable and

Combustible Liquids. (Current

2004 ed.)

AS 2187 – Explosives – Storage,

Transport and Use. (Current

1998 ed.).

Waste Rock

Management

The WRD will be constructed with an overall slope

angle of 20 degrees for geotechnical stability and

operational safety, and incorporate features to

minimise the effect of leaching of contaminants;

The WRD will be progressively rehabilitated from

the bottom up using contoured batter slopes on the

outer face, native species planting for groundcover,

and erosion control blankets (e.g. Jute netting) and

fibre rolls to minimise water quality issues at the

base;

Seepage from the waste rock dump will be routinely

monitored and evaluated for water quality.

Verification of implementation

Seepage water quality data

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

SOP01: Erosion and Sediment

Control

SOP09: Land Clearance and

Soil Stockpiling

Waste Rock Management Plan

RCMCP

International Standards and

Guidelines

Mine site Water Management

Handbook (MCA, 1997)

Mining EHS Guidelines (IFC,

2007)

Page 187: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 172

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

Ore Stockpiling

Management

Seepage from the ore stockpile will be routinely monitored

and evaluated for water quality. Verification of implementation

Seepage water quality data

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

SOP01: Erosion and Sediment

Control

SOP09: Land Clearance and

Soil StockpilingRCMCP

International Standards and

Guidelines

Mine site Water Management

Handbook (MCA, 1997)

Mining EHS Guidelines (IFC,

2007)

General Mine

Safety

The following management and monitoring measures will be

implemented to ensure mine safety for workers and the

community:

Enforcement of a mine blast exclusion zone during

blasting;

Provision of 24 hour security guards and restricted

access safeguards (e.g. perimeter security fencing

and authorised personnel only) to provide a high

level of security for the explosives magazine and

Process Plant;

A safety berm and signage at key locations around

the Pit rim perimeter will be installed to prevent falls

into the Pit;

Zero incident record for blasts

Routine monitoring of flyrock

impacts (refer to SOP08.12)

Verification of security

practices

Verification of safety controls

and inspection records

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

Company Plans and Procedures

SOP08: Blasting Management

International Standards and

Guidelines

General EHS Guidelines (IFC,

2007

Mining EHS Guidelines (IFC,

2007

Page 188: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 173

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

The explosives magazine will comprise two separate

containments for the secure storage of (i) high

explosives and (ii) accessories (i.e. initiators). Each

containment will be surrounded by an earth

barricade. ;

Appropriate handling and storage of explosives

(refer to SOP07: Hazardous Materials Management)

and established procedures for initiating blasts (refer

to SOP08: Blasting Management, Appendix A) will

be followed by appropriately trained staff.

Fire Safety

Management

Fire prevention and response controls will be provided

onsite, including:

Fire water, hydrants and hose reels at strategic

locations (e.g. Power Station, flammable material

storage areas, offices, and camp) to ensure

complete coverage in areas where flammable

materials are present;

Bushfire prevention controls, including Project ban

on open-burning of wastes, establishment of fire

breaks near sensitive buildings (e.g. at explosive

magazine, fuel storage areas, Process Plant, Power

Station, accommodation camps);

Site-specific emergency procedures to respond to

fires, including fire evacuation plans posted at

strategic locations throughout each Project facility;

and

Training for Project personnel, as appropriate for

Fire safety inspection records

Checks of all fire suppression

equipment to ensure regular

maintenance has been

undertaken

Training records for fire-

fighting

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

International Standards and

Guidelines

General EHS Guidelines (IFC,

2007

Mining EHS Guidelines (IFC,

2007

Page 189: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 174

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

their role and responsibilities, for fire-fighting,

emergency response, and hydrocarbon

management.

Process Plant

Safety

Additional management and monitoring measures for

implementation at the Process Plant to ensure worker safety

include:

Provision of backup critical plant and equipment

(e.g. process water pumps, emergency diesel-

powered fire water pump) with proper safety controls

in place to ensure there is sufficient redundancy in

the plant system if there is a process failure or

maintenance work is required;

Built-in emergency warning system and plant

shutdown mechanisms (e.g. statutory interlocks

such as emergency stops and thermal protection to

be hardwired) to avoid the discharge of hazardous

materials to the environment;

Fire protection and control system for the Process

Plant and Power Station that will supply fire water at

the required pressure and flowrate in the event of an

emergency;

Adequate lightning and surge protection provided for

the Process Plant building structures and sensitive

equipment; and

Maintenance of the mechanical integrity and

operability of plant process systems (e.g. relief and

vent valves, shutdown systems, pumps,

Regular inspection for

potential leakage or seepage

of hazardous materials and

wastes

Inspection records

Zero incidents record for Plant

operation

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

International Standards and

Guidelines:

Mining EHS Guidelines (IFC,

2007)

General EHS Guidelines –

Hazardous Materials

Management and Transport of

Hazardous Materials (IFC, 2007)

United Nations, Transport of

Dangerous Goods - Model

Regulations. 17th Revised

Edition (Volume 1) Geneva 2011

AS 1940 – The Storage and

Handling of Flammable and

Combustible Liquids. (Current

2004 ed.)

International Cyanide

Management Code Principles

and Standards of Practice for

cyanide handling, storage and

transportation (ICMI, 2014)

AS 2187 – Explosives – Storage,

Transport and Use. (Current

1998 ed.).

Page 190: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 175

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

containment infrastructure, pressure tanks, etc.).

Dam Safety and

Integrity

The structural integrity of the TMF and WSD will be ensured

by implementing the following measures:

Dam infrastructure (including engineered

embankment and spillway) designed to

accommodate a 1 in 100 year rainfall event plus

contingency freeboard;

Provision of an impervious barrier and other design

measures to minimise loss of stored water by

seepage (e.g. installation of a cut off trench, low

permeability foundation sub-base material, etc.);

An emergency spillway will be provided at all times

in the event that rainfall exceeds the 1 in 100 year

storm event (i.e. greater than the dam design

criteria). Discharge under these conditions is

required in order to protect the integrity of the

embankments from overtopping;

Dam embankment constructed with at least a slope

of 2.5H:1V, with rock armouring (i.e. rip rap)

provided on the outer banks and spillway to prevent

potential scouring, erosion and embankment

instability;

Security fencing around the site perimeter of the

TMF to limit the public and livestock from accessing

the area;

Ongoing review of the site water balance and

inventory to avoid potential water overcapacity or

Independent audit reports of

the TMF dam structural

integrity

Regular inspections of dam

toe, emergency spillway,

embankment, tailings pipelines

(refer to SOP03.13 and

SOP03.14)

Monitoring of dam water levels

(i.e. TMF, WSD) for sufficient

freeboard and the groundwater

downstream

Monitoring of rainfall,

temperature, evaporation rates

(refer to SOP04.17) and site

water balance parameters

(refer to SOP03.10)

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

Company Plans and Procedures

TMF and WSD Operating and

Monitoring Manual

International Standards and

Guidelines:

ANCOLD and ICOLD standards

Page 191: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 176

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

shortages at the Project site;

A regular inspection and maintenance schedule of

TMF and WSD dam infrastructure (i.e. spillway,

embankment, pipelines, flanges, seals and pumps)

as detailed in the TMF and WSD Operational and

Monitoring Manual; and

Independent audits of the TMF and WSD conducted

by a suitably qualified geotechnical engineer on an

annual basis to ensure structural and operational

integrity of the dam facility is maintained.

The TMF and WSD Operating and Monitoring Manual will

be finalised prior to Operations.

Workforce

Sanitation and

Hygiene

Potable water will be treated to comply with WHO 2011

Drinking Water Standards and distributed for drinking, site

ablutions, safety showers and other potable water outlets.

All wastewater and raw sewage generated from kitchen,

bathrooms, and toilets will be treated to meet relevant

discharge standards via a site based modular sewage

treatment plant (STP).

Surplus activated sludge from the STP will most likely be

solar dried in a lined pond, and then buried in a lined landfill,

or co-disposed with process tailings. Treated effluent water

from camp sites (estimated at 50 – 100 m3/day) will be

disposed of via leach drains.

Verification of implementation

Potable water quality

monitoring

Discharge water quality

monitoring of wastewater for

parameters: Total and faecal

coliform, Total nitrogen, Total

Phosphorous, COD, and BOD

(refer to SOP2.14)

Waste inventory of major

waste streams generated

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

Company Plans and

Procedures:

SOP02: Water Quality Pollution

and Management

SOP06: Waste Management

SOP07: Hazardous Waste

Management

National Standards:

Draft Standard on Management

of Solid Waste / Projet de Norme

relative à la Gestion des

Déchets Solides

International Standards and

Page 192: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 177

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

Guidelines:

General EHS Guidelines (IFC,

2007)

Mining EHS Guidelines (IFC,

2007)

EU Ambient Water Quality

Guidelines

EU Council directive 9883/EC of

November 1998 on the quality of

water intended for human

consumption (EU, 1998).

WHO Guidelines for Drinking

Water Quality, fourth edition

(2011).

The Company will implement proper waste management

procedures for the collection, separation, and disposal of

Project waste. A preferred waste management hierarchy

will also be applied, with opportunities for waste

minimisation, reuse and recycling implemented where

practicable. Medical and sanitary waste will be disposed of

as per SOP07: Hazardous Waste Management.

Waste Inventory of major

waste streams generated by

workforce accommodation

Hazardous Waste Inventory

Inspection records

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

National Standards:

Draft Standard on Management

of Solid Waste / Projet de Norme

relative à la Gestion des

Déchets Solides

International Standards and

Guidelines:

General EHS Guidelines -Waste

Management (IFC, 2007)

Mining EHS Guidelines (IFC,

2007)

Water Quality

and Pollution Adopt relevant water quality and pollution management and

monitoring measures specified in SOP02: Water Quality and

Verification of implementation OHS&E Manager / Company Plans and

Page 193: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 178

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

Management Pollution Management.

DEEC and CRSE Procedures:

SOP02: Water Quality and

Pollution Management

Specific water quality management measures for

implementation at the Project site include:

Reuse and recycle process water to reduce the

requirement for raw water abstraction from the

Gambia River;

Use of erosion and sediment control measures as

detailed in SOP01: Erosion and Sediment Control;

Surface runoff diverted around the Project site;

All wastewater and sewage generated from

kitchens, bathrooms and toilets to be treated to meet

relevant discharge standards via a site-based

modular sewage treatment plant;

Adherence to proper handling and storage of

hazardous materials onsite in fully bunded,

weatherproof areas, including appropriate

emergency response and spill clean-up procedures

(refer to relevant measures specified in SOP07:

Hazardous Materials Management);

Maintenance of primary and secondary

containments for all hazardous material storage and

handling areas; and

Regular inspection for potential leakage or seepage

of contaminated water.

Verification of implementation

Visual check to ensure there

are no visible leakage or

seepage (refer to SOP02.19)

Inspection records

Incident records

Water quality monitoring

results

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

Company Plans and

Procedures:

SOP02: Water Quality and

Pollution Management

SOP01: Erosion and Sediment

Control

SOP07: Hazardous Materials

Management

International Standards and

Guidelines:

Mine site Water Management

Handbook (MCA, 1997)

Mining EHS Guidelines (IFC,

2007)

General EHS Guidelines –

Wastewater and Ambient Water

Quality (IFC, 2007)

Page 194: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 179

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

The following measures will be implemented to minimise

erosion and sedimentation to receiving waters from Project

road infrastructure:

Appropriate road specification standards selected to

minimise excessive earthworks with subsequent

requirements for large amounts of fill material;

Roads designed to include drainage systems that

channel water from the road surfaces to outlets with

erosion and sediment control facilities, including rip-

rap at inlets and outlets of culverts and channels

and sediment control basins constructed for larger

catchment areas;

Roads to be constructed during the dry season to

the extent possible. Erosion and sediment controls

for unsealed roads will be completed before the

onset of the wet season;

Drainage from upslope of road surfaces to be

diverted via roadside drainage channels to culverts

with velocity dissipaters and sediment control at

outlets;

Culverts installed at drainage crossings.

Permanent structures designed using an average

peak storm recurrence interval of 100 years, and

temporary structures designed using an average

recurrence interval of 2 years (24 hour storm

events);

Batter slope angles minimised to the extent feasible;

Verification of implementation

Routine erosion and sediment

transport monitoring (refer to SOP01:

Erosion and Sediment Control)

Water quality monitoring results

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

Company Plans and Procedures

CEMP, ESMMP

SOP01: Erosion and Sediment

Control

Relevant Guidelines

Mine site Water Management

Handbook (MCA, 1997)

Mining EHS Guidelines (IFC,

2007)

Page 195: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 180

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

and

Where feasible, vegetation will be left intact on road

verges and roadside batters to reduce surface flow

velocity and erosive potential. Road borders and

embankments will be progressively re-vegetated

where necessary for erosion control.

The TMF and tailings piping facilities will incorporate the

following water quality management measures:

A soil liner with permeability less than 1 x 10-8 m/s

will minimise the potential for seepage over the

extent of the basin area;

An HDPE geomembrane liner installed in the lower

reaches of the TMF basin and on the TMF

embankment upstream face. The liner will conform

to Nevada’s Water Controls for Mining Facilities

Standards (Nevada Administrative Code NAC

445A.438);

Monitoring of groundwater bores and surface water

sampling stations downstream of the TMF; and

Regular inspection and maintenance of the TMF and

associated pipelines (tailing and return water) in

accordance with the TMF Operation and Monitoring

Manual.

Verification of implementation

Inspection records

Incident records

Water quality monitoring

results

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

Company Plans and

Procedures:

SOP02: Water Quality and

Pollution Management

SOP03: Hydrology and Water

Management

TMF Operation and Monitoring

Manual

International Standards and

Guidelines

ANCOLD and ICOLD Standards

Mine site Water Management

Handbook (MCA, 1997)

Mining EHS Guidelines (IFC,

2007)

Nevada’s Water Controls for

Mining Facilities Standards

(Nevada Administrative Code:

NAC 445A.438)

Page 196: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 181

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

During Project Construction, routine water quality monitoring

will be conducted at discharge points to assess impacts.

Key parameters: Turbidity, TSS, DO,

temperature, electrical conductivity

(EC), and pH (refer to SOP02.9)

Visual checks for sedimentation, oils

and grease (refer to SOP2.10)

OHS&E Manager /

DEEC and CRSE

National Standards:

Inter-ministerial Decree No.

1555 Discharge Water

Guidelines / L’arrêté

interministériel No. 1555 de 15

mars 2002 portant application de

la norme NS 05-061 sur les

rejets des eaux usées (2002)

Waste Water Discharge

Standard, NS 05-061 / La norme

sur les rejets des eaux (NS 05-

061) (2001)

International Standards and

Guidelines:

General EHS Guidelines –

Wastewater and Ambient Water

Quality (IFC, 2007)

EU Ambient Water Quality

Guidelines

EU Council directive 9883/EC of

November 1998 on the quality of

water intended for human

consumption (EU, 1998)

WHO Guidelines for Drinking

Water Quality, fourth edition

(2011).

During Project operations, a routine water quality monitoring

program will be conducted of surface, ground and discharge

water This will include multi-element testing of samples

using ICP-MS to fully characterise water quality.

Surface water parameters (i.e. from

Pit sumps and Mine water):

Key parameters: Cyanide

(including free cyanide, weak

acid dissociable, and total),

salinity, total and dissolved

metals (full suite), and

nutrients, and AMD.

Field parameters (e.g. pH, EC,

ORP, DO, Temp., etc.) (refer to

SOP02.13 and SOP02.16)

Discharge parameters;

Salinity, Turbidity, TSS,

temperature, EC, ORP, pH

(refer to SOP02.14)

Visual checks for

sedimentation, oils and grease

(refer to SOP2.10)

Groundwater parameters :

Groundwater level

Key parameters: cyanide (free,

OHS&E Manager /

DEEC and CRSE

Page 197: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 182

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

weak acid dissociable, and

total), related breakdown

products of cyanide (e.g.

ammonia, nitrate, thiocyanate),

salinity, nutrients, and field

parameters (e.g. pH, EC, ORP,

DO, temp. etc.)

Acidity/alkalinity, sulfate, and

dissolved metals (to be

determined by waste rock

characterisation)

Hydrology and

Water

Management

Relevant hydrology and water management and monitoring

measures specified in SOP03: Hydrology and Water

Management will be adopted, where appropriate.

Verification of implementation

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

SOP03: Hydrology and Water

Management

Key measures of the Mine site water management system

for implementation include:

The mine will function as a ‘zero-discharge’

operation. Surface water from the Mine Pit, WRD,

Ore Stockpile and TMF will be contained by the TMF

embankment; and

Project abstraction from the Gambia River will not

exceed 3% of the instantaneous volumetric flow.

Abstraction will be limited to periods when the

Gambia River discharge exceeds 5 m3/sec.

Verification of implementation

Regular inspections of surface

water management features to

ensure their efficacy

Incident records

Hydrology records for the

Gambia River

Record of abstraction from

Gambia River

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

Company Plans nd Procedures:

SOP02: Water Quality and

Pollution Management

SOP03: Hydrology and Water

Management

International Standards and

Guidelines

Mine site Water Management

Handbook (MCA, 1997)

Mining EHS Guidelines (IFC,

2007)

Page 198: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 183

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

Erosion and

Sediment

Transport

Management

Relevant erosion and sediment control management and

monitoring measures specified in SOP01: Erosion and

Sediment Control will be adopted, where appropriate.

Verification of implementation

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

SOP01: Erosion and Sediment

Control

The following specific erosion and sediment management

measures will be implemented for mine facilities during the

pre-construction and construction phase of the Project:

The CEMP will include provision for erosion and

sediment control, including the measures specified

in SOP01;

Dam embankments to be constructed with a slope of

at least 2.5H:1V, with rock armouring (i.e. rip rap)

provided on the outer banks and spillway to prevent

potential scouring, erosion and embankment

instability; and

Soil stockpiles formed with as little compaction as

possible in mounds generally no more than 2 m high

(for topsoil) and 5 m high (for subsoil) to minimise

losses to erosion.

Verification of implementation

Routine erosion and sediment

transport monitoring (refer to

SOP01: Erosion and Sediment

Control)

Water quality monitoring

results

Project Director /

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

CEMP, ESMMP

SOP01: Erosion and Sediment

Control

RMCP

International Standards and

Guidelines

Mine site Water Management

Handbook (MCA, 1997)

Mining EHS Guidelines (IFC,

2007)

During the decommissioning and closure phase, specific

erosion and sedimentation management and mitigation

measures as specified in the RMCP include:

All exposed soil to be re-contoured and ripped

(during the dry season) and re-vegetated (at the

onset of the rainy season) to a landform consistent

with the surrounds upon mine closure to minimise

Verification of implementation

Routine erosion and sediment

transport monitoring (refer to

SOP01: Erosion and Sediment

Control)

Inspection records

Designers, OHS&E

Manager / DEEC

and CRSE

Company Plans and Procedures

SOP01: Erosion and Sediment

Control

RCMCP

International Standards and

Guidelines

Page 199: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 184

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

potential for erosion;

The TMF will be graded to a stable 1 in 100 slope

and the slopes engineered to encourage sheet flow

of run-off water and prevent excessive channelling

and erosion; and

Drainage will be redirected as necessary to

minimise erosion until vegetation is established.

Water in the sediment control structures will be

treated to achieve compliance with appropriate

discharge standards.

Water quality monitoring

results

Mine site Water Management

Handbook (MCA, 1997)

Mining EHS Guidelines (IFC,

2007)

Air Emissions

and Dust

Management

The Company will implement the following management

and mitigation measures to minimise impacts to air quality

from Mine Pit and WRD development:

Prepare an Occupational Health and Safety Plan

prior to Project Operations

Limitation of land clearing to the minimum required

area to reduce the potential for dust generation;

Topsoil stripping preferably conducted at times when

soil moisture can be expected to be optimal to

minimise dust formation; and

Progressive revegetation of disturbed areas.

Verification of implementation

Visual check for fugitive dust

Ambient monitoring of

particulates and dust

deposition

Land clearance and

revegetation records

OHS&E Manager /

DEEC and CRSE

Not applicable.

The Company will implement the following management

and mitigation measures to minimise impacts to air quality

from the Process Plant:

The lime silo will be fitted with a dust collector;

Water sprays and dust collection systems to be

Verification of implementation

Visual check for fugitive dust

Ambient monitoring of PM10,

and PM2.5, SO2, NOx, CO

and dust deposition rates via

Designers /

OHS&E Manager

/Operations

Manager / DEEC

and CRSE

National Standards:

Atmospheric Pollution Standard,

NS 05-062 / La Norme de rejets

NS 05-062 – pollution

atmosphérique (2004)

Page 200: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 185

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

installed for dust suppression in the crushing and

screening circuit and lime addition point, where

feasible;

As required, the Company will further consider

containing fugitive emissions within the Process

Plant to the extent practicable by either:

» Enclosing or covering all fugitive source

emissions such as the conveyors, hoppers, bins;

» Watering roads or gravel sheeting in ore-

handling areas to minimise windblown and traffic

generated dust; and

» Controlling a fugitive emission source from feed

ore handling by employing air extraction and

treatment through a baghouse or cyclone.

Routine monitoring of fugitive dust emissions at the

Process Plant.

dust gauge

Stack emission monitoring of

PM10, PM2.5, NOx, SO2, CO,

O3

International Standards and

Guidelines:

Mining EHS Guidelines (IFC,

2007)

General EHS Guidelines – Air

Emissions and Air Quality (IFC,

2007)

WHO Air Quality Guidelines –

Global Update (2005)

Specific measures for managing air quality and dust impacts

associated with transport for the Project will include:

A dust suppression program for the Project involving

regular watering of unsealed road surfaces, heavily

trafficked areas, and where excessive dust is

evident;

Project vehicle speed limits through villages of 20

km/h;

Low emission diesel engines and/or catalytic

Verification of implementation

Visual check for fugitive dust

Ambient monitoring of

particulates and dust

deposition

Grievance register

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

As above.

Page 201: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 186

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

convertors for Project heavy vehicles, trucks, and

excavators will be used, where possible;

Dusty material loads covered where transport is

required through settlements;

Unsealed roads heavily trafficked by Project

vehicles over a long period will be considered for

future application of gravel or paving; and

Regular maintenance of unsealed Project roads.

Adopt relevant air emissions and dust management and

monitoring measures specified in SOP04: Emission and

Dust Control, where appropriate.

Verification of implementation

OHS&E Manager,

Contractors /

DEEC and CRSE

Company Plans and Procedures

SOP04: Emission and Dust

Control

A detailed air quality monitoring regime will be implemented

and adapted for Project construction and operations which

will include ambient air quality monitoring and dust

deposition rates.

The Company will consult with local villages and will

address potential complaints regarding dust via the Project

Grievance Mechanism.

Visual check for fugitive dust

Ambient air quality station

monitoring for PM10, and

PM2.5, SO2, NOx, CO and

dust deposition rates via dust

gauge (refer to SOP04.16)

Grievance register

OHS&E Manager /

DEEC and CRSE

Same as above.

Noise and

Vibration

Management

The Company will implement specific noise and vibration

measures for Project facilities, including:

Integration of physical barriers (such as vegetation,

soil banks/berms and commercially-available

acoustic shields) with site components (e.g.

stockpiles and constructed buildings) to strategically

act as noise barriers for potential sensitive

Verification of implementation

Noise levels in dB(A) LAeq

(daytime and night-time period

(refer to SOP 05.12)

Grievance register

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

Company Plans and Procedures

SOP05: Noise and Vibration

Management

National Standards:

Environment Code (noise) /

Code de l’Environnement (2001)

Page 202: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 187

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

receptors;

Commercial acoustic shielding (typically insulator

material panels) around noise sources where

necessary and the adoption of high frequency

technology for fans, ducting and electrical systems;

Vibration-proofing and noise-reduction measures for

various noise sources within the Mine site, including

treatment measures for mine equipment such as

hydraulic excavators, crawler bull-dozers, loaders,

and jaw crushers;

Additional measures to minimise noise emitted by

the Process Plant operations may include:

» Use of barriers (e.g. near vibrating screen) and

other noise abatement technologies (e.g.

ventilation fan size or use of windscreens near

ventilation fan);

» Sound insulation of plant and machinery

engines, if required;

» Enclosure of high noise emitting areas such as

the crushing and grinding areas; and

» Provision of noise protection PPE for workers in

areas where plant equipment emits noise in

excess of 80 dB(A).

International Standards and

Guidelines

Leading Practice Sustainable

Development Program for the

Mining Industry: Airborne

Contaminants, Noise & Vibration

(Australian Government, 2009)

UK Standards (vibration) BS

6472:2008, 4866:2010 and

7385-2:1993

General EHS Guidelines – Noise

(IFC, 2007)

Mining EHS Guidelines (IFC,

2007)

The following air blast and vibration management measures

will be implemented for mine blasts:

Use of electronic detonation to significantly reduce

Verification of implementation

Routine monitoring of noise,

airblast, ground vibration, and

OHS&E Manager,

Blast Contractor /

DEEC and CRSE

Company Plans and Procedures

SOP08: Blast Management

SOP05: Noise and Vibration

Page 203: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 188

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

vibrations caused by the blast;

No explosive charge per blast hole to exceed the

estimated maximum charge weight per delay (i.e.

285 kg);

Only one charge detonated per delay and every

charge will be able to break and displace its burden

with reasonable ease;

Inter-row delays that long enough to give good

progressive relief of burden; and

Detonating cord trunklines to only be used to fire

pre-split blasts. Trunklines will have a core load of

only 5 g/m and will be covered by at least 250 mm of

sand or fine screenings; and

Inspection and review of any reported structure

damage after each blast, with immediate

investigation and follow-up control measures

implemented (as required).

flyrock impacts (refer to

SOP08.12)

Grievance register

Management

Relevant Guidelines

Leading Practice Sustainable

Development Program for the

Mining Industry: Airborne

Contaminants, Noise & Vibration

(Australian Government, 2009)

Mining EHS Guidelines (IFC,

2007)

Noise and vibration monitoring will be undertaken as

necessary for the Project during construction and

operations, including near noise sensitive receptors.

Noise levels in dB(A) LAeq

(daytime and night-time period

(refer to SOP 05.12)

Ground vibration levels

Grievance register

OHS&E Manager /

DEEC and CRSE

Same as above.

Relevant noise and vibration management and monitoring

measures specified in SOP05: Noise and Vibration

Management will be adopted, where appropriate.

Verification of implementation

OHS&E Manager,

Contractors /

DEEC and CRSE

Same as above.

Page 204: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 189

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

Blasting and

Flyrock

Management

A detailed Blast Management Plan will be prepared that will

further specify blasting procedures, training, auditing, PPE

and other requirements.

Detailed drill and blast procedures will be designed by

blasting specialists to ensure the safety of the mine

workforce and surrounding local population, the control of

flyrock, noise and vibration, in accordance with the following

measures:

A 500 m blast exclusion zone (minimum) enforced

for all blasting activities for the Project;

To ensure people are outside the blast exclusion

zone, the Company will deploy methods including:

sirens, amplified verbal warnings, the posting of

sentries, the closure of access roads, and pre-blast

surveys;

Blasting to be conducted at specified times during

the day (during daylight hours), with at least 24 hour

notice given to local villages;

Blast times and locations posted on boards in local

villages;

Visual monitoring of flyrock to confirm that the

exclusion zone is sufficient to protect sensitive

receptors (biological and social);

The Company will engage a blast contractor with

relevant expertise and experience; and

Training of Project staff on fly rock safety and

conduct a public education program regarding

Zero incident record for blasts

Communication notification

records

Grievance register

Project workforce induction

and training records

Routine monitoring of noise,

airblast, and ground vibration

impacts (refer to SOP08: Blast

Management)

Air quality discharge

monitoring (refer to SOP04:

Emission and Dust Control)

Noise emission monitoring

(refer to SOP05: Noise and

Vibration Management)

OHS&E Manager,

Blast Contractor /

DEEC and CRSE

Company Plans and

Procedures:

SOP08: Blast Management

SOP04: Emission and Dust

Control

SOP05: Noise and Vibration

Management

Blast Management Plan (to be

developed)

International Standards and

Guidelines:

Leading Practice Sustainable

Development Program for the

Mining Industry: Airborne

Contaminants, Noise & Vibration

(Australian Government, 2009)

Mining EHS Guidelines (IFC,

2007)

Page 205: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 190

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

community safety issues associated with blasting.

Borrow Areas

and Quarries

Best management practices will be adopted by the

Company and contractors for the development and

operation of borrow pits and quarries including:

Minimising the footprint disturbance area;

Limiting the number of rock and borrow pit cuts

required;

Minimising site erosion and sedimentation through

appropriate control measures (SOP01);

Restricting access to the public; and

Progressive rehabilitation of sites as they become

no longer needed.

Verification of implementation

Regular visual inspections of

the borrow pits and quarries

for safety, structural integrity

and authorised personnel

access

Grievance register

Routine monitoring of noise,

airblast, ground vibration, and

flyrock impacts

Visual checks for

sedimentation, oils and grease

Routine ambient and

discharge water quality

monitoring for field

parameters, laboratory testing,

and Turbidity, TSS, DO,

temperature, electrical

conductivity (EC), and pH

OHS&E Manager,

Contractors /

DEEC and CRSE

Company Plans and

Procedures:

CEMP

SOP09: Land Clearance and

Soil Stockpiling

International Standards and

Guidelines:

Mining EHS Guidelines (IFC,

2007)

Waste

Management

Putrescible waste such as food scraps and kitchen wastes

from site based accommodation camps will be disposed of

in a suitably designed and lined landfill within the PDA.

Other non-recyclable and non-hazardous solid waste will

Verification of implementation

OHS&E Manager /

DEEC and CRSE

Same as above.

Page 206: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 191

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

also be disposed of at the engineered landfill, while

recyclables will be recycled with an approved contractor,

where available.

Inert construction waste (i.e. concrete) will be co-disposed

with waste rock.

A detailed inventory of waste streams generated by the

Project will be maintained.

Verification of implementation

Inventory of Project waste streams

recording the following information:

Waste type;

Source;

Quantity; and

Management method.

OHS&E Manager /

DEEC and CRSE

Same as above.

Relevant waste management and monitoring measures

specified in SOP06: Waste Management will be adopted,

where appropriate.

Verification of implementation

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

SOP06: Waste Management

Hazardous

Materials and

Wastes

Management

The explosives magazine will comprise two separate

containments for the secure storage of (i) high explosives

and (ii) accessories (i.e. initiators). Each containment will be

surrounded by an earth barricade.

The magazine will be located a minimum of 800 m buffer

distance from human settlement, land use areas, and/or

built structures. (Distance subject to review during detailed

design when the quantities of explosive has been

confirmed).

Verification of implementation Designers / DEEC

and CRSE

International Standards and

Guidelines:

AS 2187 – Explosives – Storage,

Transport and Use. (Current

1998 ed.).

Page 207: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 192

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

Ammonium-nitrate fuel oil (ANFO) will be used as a low cost

and high stability blasting agent. ANFO will be mixed,

transported and loaded into blast holes using a specialised

truck.

The Company will implement the following specific

measures for hazardous materials stored and handled at

the Process Plant:

Hazardous wastes in the process circuit to be

reused to the extent practicable, including process

water, used carbon (which will be recovered and

reactivated) and spent electrolyte required for the

electrowinning process;

Primary containment (bunding) will be integrated for

all hazardous materials storage, handling and

transfer areas in the Process Plant (refer to below)

to ensure rainwater or spillage does not discharge

into the receiving environment. Secondary

containment has been designed for potential

discharges outside of primary bunding;

All pipe work and pumps within bunds or routed

above ground to allow the early identification of any

leaks;

Steel framed reagent storage shed constructed with

concrete floor, sumps and appropriate layout and

facilities to isolate, separate and handle hazardous

goods;

Plant areas subject to possible contamination from

chemical or slurry spills will have concrete slabs and

Verification of implementation

Spills and contaminated soil

inventory

Regular inspections for

hazardous materials leakage /

spillage

Incident register

Water quality monitoring

results

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

Company Plans and

Procedures:

SOP06: Waste Management

SOP07: Hazardous Materials

Management

Emergency Preparedness and

Response Plans (to be

developed)

National Standards:

Draft Standard on Management

of Solid Waste / Projet de Norme

relative à la Gestion des

Déchets Solides (2005)

Law No. 2001-01 of 15 January

2001 on the Environment Code

International Standards and

Guidelines:

Mining EHS Guidelines (IFC,

2007)

General EHS Guidelines –

Hazardous Materials

Management and Transport of

Hazardous Materials (IFC, 2007)

Page 208: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 193

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

bunds (with 110% holding capacity) installed;

Liquid hydrocarbon products (e.g. diesel) required

for site power generation at accommodation facilities

will be stored in appropriately bunded tanks (to meet

110% of stored volume capacity);

Bunded areas to be equipped with sump pumps to

recover any spilled material or rain falling on the

slabs, for reclaim to the process;

Site run-off and spillage exceeding the capacity of

the bunds that are potentially contaminated with

cyanide and reagents will report to a lined event

pond with a submersible pump for reclaim to the

process circuit (contaminated spillage will ultimately

report to the TMF), or discharge to the TMF. ;

The distance for the tailings / return pipelines to the

TMF has been minimised and the pipeline will follow

an alignment that runs down a continuous downhill

slope to the TMF with no ‘dead legs’ in the line

requiring drain valves and scour pits to minimise

potential for leakage;

Safety showers provided for workers accidentally

exposed to hazardous chemicals; and

Routine monitoring of water quality discharge from

the Process Plant will be conducted.

United Nations, Transport of

Dangerous Goods - Model

Regulations. 17th Revised

Edition (Volume 1) Geneva 2011

AS 1940 – The Storage and

Handling of Flammable and

Combustible Liquids. (Current

2004 ed.)

International Cyanide

Management Code Principles

and Standards of Practice for

cyanide handling, storage and

transportation (ICMI, 2014)

The Company will implement the following measures for

cyanide management at the Process Plant to be consistent

with the International Cyanide Management Code and

Verification of implementation

Incident register

Project Director /

Operations

Manager / OHS&E

Company Plans and Procedures

Emergency Preparedness and

Response Plans (to be

Page 209: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 194

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

Guidelines (Cyanide Code) (ICMI 2014):

Materials handling, containment and bunding in all

plant areas will be consistent with the Cyanide Code

(ICMI 2014) as well as well as Senegalese

legislative requirements, in particular Law No. 2001-

01 of 15 January 2001 on the Environment Code;

Cyanide storage, handling, destruction, and disposal

consistent with the Cyanide Code (ICMI 2014) and

be conducted in a manner that avoids potential

releases to receiving waters;

Cyanide will be purchased from a member of the

International Council of Chemical Associations

Responsible Care Program consistent with the

Cyanide Code (ICMI, 2014);

As a minimum, two people with rigorous cyanide

and emergency specific training will always be

present for cyanide unloading, storage and

automated mixing (to minimise human handling,

exposure and error);

Cyanide destruction methodology will ensure

residual cyanide from the CIL circuit in the Process

Plant will be less than 50 parts per million (ppm);

Preparation of a specific Cyanide Spill Contingency

Plan as part of the Project Emergency

Preparedness and Response Plans (to be

developed); and

Monthly water quality monitoring of tailings and

Regular inspections for

hazardous materials leakage /

spillage

Water quality monitoring of

tailings and supernatant water

for key parameters (refer to

SOP02.13)

Manager / DEEC

and CRSE

developed)

SOP07: Hazardous Materials

Management

National Standards:

Law No. 2001-01 of 15 January

2001 on the Environment Code

Inter-ministerial Decree No.

1555 Discharge Water

Guidelines / L’arrêté

interministériel No. 1555 de 15

mars 2002 portant application de

la norme NS 05-061 sur les

rejets des eaux usées (2002)

Waste Water Discharge

Standard, NS 05-061 / La norme

sur les rejets des eaux (NS 05-

061) (2001)

International Standards and

Guidelines:

International Cyanide

Management Code and

Guidelines (Cyanide Code)

(ICMI 2014)

Mining EHS Guidelines (IFC,

2007)

General EHS Guidelines –

Wastewater and Ambient Water

Quality (IFC, 2007)

Page 210: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 195

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

supernatant water for cyanide concentrations

(including breakdown products of cyanide).

EU Ambient Water Quality

Guidelines

A detailed inventory of hazardous wastes generated by the

Project will be maintained to include:

Waste type;

Source;

Quantity; and

Management method.

Verification of implementation

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

Waste Management Plan (to be

developed)

National Standards:

Draft Standard on Management

of Solid Waste / Projet de Norme

relative à la Gestion des

Déchets Solides (2005)

International Standards and

Guidelines:

Mining EHS Guidelines (IFC,

2007)

General EHS Guidelines– Waste

Management (IFC, 2007)

The following measures will be implemented to mitigate and

prevent potential land or water contamination from

accidental releases of hazardous chemicals into the

receiving environment:

Regular preventive inspections in areas where there

is potential for potential leakage or seepage of

hazardous materials and wastes (e.g. Process

Plant, storage areas, etc.);

The implementation of an incident register to include

spills and relevant spill management procedures to

effectively prevent and manage hazardous spills and

Visual check to ensure there

are no visible leakage or

seepage (refer to SOP07.28)

Incident register

Actions taken for immediate

remediation

Inspection records

Hazardous Waste Inventory

OHS&E Manager /

DEEC and CRSE

Same as above.

Page 211: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 196

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

leaks as necessary; and

Maintenance of a detailed Hazardous Waste

Inventory that accurately records and tracks the

location, destination and amounts of hazardous

wastes associated with the Project to ensure proper

management and disposal in accordance with best

practices.

Relevant hazardous materials and waste management and

monitoring measures specified in SOP07: Hazardous

Materials Management will be adopted, where appropriate.

Verification of implementation

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

SOP07: Hazardous Materials

Management

Transportation of

hazardous

wastes and

dangerous goods

Hazardous substances and dangerous goods will be

transported in accordance with relevant legislative

requirements and applicable standards and guidelines.

Explosives and other hazardous materials will be

transported by a suitably licensed and reputable carrier.

Prior to contract engagement, an audit of health and safety

documentation of transporters for hazardous materials and

dangerous goods to ensure they are adequate and

compliant with legislative requirements.

Cyanide transporters will be compliant with the Cyanide

Code (ICMI, 2014). The code-compliant transporters will be

required to prepare a detailed procedure for cyanide

transport to the Project site, and provide options where

necessary to minimise risks in consultation with community

and other stakeholders. The escort contractor must be a

signatory to the Cyanide Code (ICMI, 2014) for cyanide

transport.

Management of risks and emergency response to spills or

Verification of implementation

Compliance audit and review

of licensed and certified

suppliers / transporters’

documentation (refer to

SOP07.09)

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

CEMP

SOP07: Hazardous Materials

Management

International Standards and

Guidelines:

Mining EHS Guidelines (IFC,

2007)

General EHS Guidelines –

Hazardous Materials

Management and Transport of

Hazardous Materials (IFC, 2007)

United Nations, Transport of

Dangerous Goods - Model

Regulations. 17th Revised

Edition (Volume 1) Geneva 2011

Page 212: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 197

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

accidents during the transport of hazardous materials and

dangerous goods will be the responsibility of the licensed

carrier.

AS 1940 – The Storage and

Handling of Flammable and

Combustible Liquids. (Current

2004 ed.)

International Cyanide

Management Code Principles

and Standards of Practice for

cyanide handling, storage and

transportation (ICMI, 2014)

AS 2187 – Explosives – Storage,

Transport and Use. (Current

1998 ed.)

IFC PS4 Community Health,

Safety and Security (2012)

Key measures to adopt by the contractor for the

transportation of hazardous materials and dangerous goods

include:

A road safety and maintenance program for

transport vehicles that includes procedures for

vehicle and tire inspections, preventive

maintenance, drivers fatigue management and

permitted driving hours, tie-down of loads, and

actions to be taken if severe weather conditions are

encountered;

Careful consideration of transport distances and

routes;

Where appropriate, the Contractor will arrange for a

specialised escort ‘warning’ vehicle where transport

Verification of implementation

Compliance audit and review

of licensed and certified

suppliers / transporters’

documentation (refer to

SOP07.09)

Contractor training records

Hazardous materials and

dangerous goods inventory,

tracking and chain of custody

documentation

Incident register

OHS&E Manager,

Contractors /

DEEC and CRSE

Same as above.

Page 213: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 198

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

routes present safety or security concerns for the

transport of cyanide, explosives and other

dangerous goods or hazardous materials;

Project vehicles carrying dangerous goods and

hazardous materials will travel in off-peak times

when there is less traffic on roads to the extent

practicable. Procedures for regular communications

between transport vehicles and the transporter

contractor will be in place;

Drivers of dangerous goods and hazardous

materials will be adequately trained to handle local

road conditions and follow safety protocols;

The contractor will develop specific emergency

response and clean-up procedures for road

transport;

Drivers transporting dangerous goods and

hazardous materials will be adequately trained on

appropriate emergency response and clean-up

procedures to follow in the case of a spill;

of the contractor will provide appropriate PPE and

clean-up skill kits (including for cyanide specific PPE

and neutralising agents, where appropriate) for

drivers transporting hazardous materials and

dangerous goods, including gloves, plastic coveralls,

safety glasses and self-contained respirators, etc.;

and

Inventory controls and/or chain of custody

Inspection records

Page 214: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 199

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

documentation in place to identify the loss of any

hazardous material during transport.

Land and

Vegetation

Clearance

Management

The footprint of the Project has been minimised to limit

vegetation clearing to the extent practicable. The Company

will adopt relevant vegetation clearance measures specified

in SOP09: Land Clearance and Soil Stockpiling, where

appropriate.

Where appropriate, the procedure for land clearance will

include consultation with local villagers regarding current

land uses, and social and cultural assets in the area prior to

disturbance.

A register will be maintained of all land disturbed by Project

activities.

The extent of vegetation clearing will be continually

monitored to ensure unnecessary vegetation removal does

not occur (refer to SOP09.2).

Verification of implementation

Register of land clearance and

soil stockpiling

Ongoing monitoring of the

extent of vegetation clearing

for the Project

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

SOP09: Land Clearance and

Soil Stockpiling

International Standards and

Guidelines:

IFC PS6 Biodiversity

Conservation and Sustainable

Management of Living Natural

Resources (2012)

UNESCO Operational

Guidelines for the

Implementation of the World

Heritage Convention (2013)

Land and Soil

Resources

Management

Relevant land and soil resource measures specified in

SOP09: Land Clearance and Soil Stockpiling will be

adopted, where appropriate.

Verification of implementation

Soil stockpile inventory,

including location of temporary

and long-term stockpiles and

approximate volume of

material

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

SOP09: Land Clearance and

Soil Stockpiling

Archaeology and

Cultural Heritage

Management

The Company will implement the Chance Find

Procedure for the protection of physical cultural

resources in the PDA, as per SOP10: Cultural

Heritage Management.

Verification of implementation

Regular review of compliance

and implementation of

archaeological and cultural

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

Chance Find Procedure

SOP10: Cultural Heritage

Page 215: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 200

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

Project staff will be trained in the implementation of

SOP10, as relevant to their roles and

responsibilities.

A register will be maintained of all areas that have

been the subject of detailed archaeology and

cultural heritage studies. The register will include all

sites and artefacts identified in the Project area.

heritage management

measures

Periodic inspection of known

sites of cultural heritage or

archaeological significance

within or adjacent to a

construction worksite to

confirm no accidental

disturbance has occurred

Cultural heritage register

Grievance register

Training records

Management

Detailed archaeology and cultural heritage studies will be

conducted in advance of all land disturbance activities.

Infrastructure corridors will be the subject of an archaeology

and cultural heritage study in advance of Project

construction.

The Company will liaise with specialists regarding the

documentation and display of archaeology and cultural

heritage artefacts identified in the Project area.

Verification of implementation OHS&E Manager /

DEEC and CRSE

Same as above.

Lighting and

Visual Amenity

Management

The visual impacts of the Process Plant and ROM will be

minimised by implementing the following measures:

Strategic use of revegetation as visual screening

and noise buffer, where required;

Night lighting from the Process Plant and ROM to be

minimised to the extent possible for a safe working

environment, and site lighting will be directed to

Verification of implementation

Inspection records

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

Company Plans and Procedures

SOP11: Lighting and Visual

Amenity Management

Page 216: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 201

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

minimise spillage to external areas; and

Buildings, roofs and fencing will be painted in a

neutral non-reflective colour that blends with the

natural landscape and surrounds (e.g. dark green or

brown).

Relevant lighting and visual amenity measures specified in

SOP11: Lighting and Visual Amenity Management will be

adopted, where appropriate.

Verification of implementation

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

SOP11: Lighting and Visual

Amenity Management

Rehabilitation

and Mine

Closure

General environmental management measures that will be

implemented during the decommissioning and closure

phase of the Mako Gold Project will include:

Removal of access to facilities that present safety

risk (e.g. Mine Pit);

Removal of all equipment and vehicles from the site;

Removal and appropriate disposal of all chemicals,

fuels and oils from the PDA;

Buildings and structures demolished and the rubble

transported to an appropriate disposal area;

Buildings / facilities with significant residual value to

the Company may be sold for dismantling, relocation

and/or recycling;

Buried pipelines to be cleaned, sealed and left in-

situ;

Power lines and above ground pipelines removed to

an approved disposal area;

On-site and downstream water

quality (i.e. with respect to

baseline conditions and

applicable discharge

guidelines);

Land rehabilitation register:

revegetation success (e.g. %

coverage, species diversity, %

weeds)

Geotechnical and landform

stability

GPS locations of recorded

contaminated land sites

Inspection records

OHS&E Manager, /

Operations

Manager / DEEC

and CRSE

Company Plans and

Procedures:

RCMCP

BAP

Final RMCP (to be developed

prior to decommissioning)

SOP02: Water Quality and

Pollution Management

Page 217: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 202

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

Footings / foundations will be removed;

Stormwater management systems (i.e. drainage

channel and sediment pond below the TMF) will be

retained until they are no longer needed;

A contaminated land survey conducted to identify

any such areas and appropriate clean up measures

will be designed and implemented;

Compacted areas, including roads and building

footprints will be ripped and graded to blend into

surrounding contours and to ensure drainage

patterns are similar to pre-mining conditions;

Establishment of engineered erosion control

measures where needed;

All seeding and planting sourced from native stock

of local provenance; and

Fencing removed, unless retained for public and

livestock safety reasons.

The Company will implement the following specific

decommissioning and closure strategies and measures for

Project facilities:

Rehabilitation and revegetation of Pit margins and

temporary equipment access roads. A safety berm

will be constructed around the Pit void for public

safety. Targeted species may be planted on pit

benches, pending the suitability of the material to

support plant life;

Full suite of dissolved and total

metals, cyanide (total cyanide,

free cyanide, and WAD

cyanide), salinity, pH,

nutrients, etc. of the TMF

supernatant water

On-site and downstream water

quality (i.e. with respect to

baseline conditions and

OHS&E Manager /

DEEC and CRSE

Same as above.

Page 218: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 203

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

The WRD to be graded to contours that align with

adjacent topography and ripped to minimise batter

scour. Where possible, the WRD will be

progressively revegetated to establish a Wooded

Savannah vegetative community comprised of

native species of local provenance. Rock-lined

drains will be constructed, where required, to ensure

excess run-off is controlled and directed down to

sediment traps or to the TMF;

The TMF to be partially capped with waste rock in

order to prevent seepage; the top surface

engineered to prevent water pooling; slopes graded

to a stable 1 in 100 slope and engineered to

encourage sheet flow of run-off water and prevent

excessive channelling and erosion; and rehabilitated

with armoured drainage channels to ensure that

tailings material is securely stored (i.e. erosion

resistant);

At closure, the stormwater spillway on the eastern

abutment of the TMF will be converted into a

permanent discharge channel to allow surface water

to freely discharge from the surface of the

rehabilitated facility;

At the end of operations, the Processing Plant and

ROM pad will be cleared to ground level and

rehabilitated.All exposed soil will be re-contoured

and ripped and re-vegetated to a landform

consistent with the surrounds upon mine closure

applicable discharge

guidelines);

Land rehabilitation register:

revegetation success (e.g. %

coverage, species diversity, %

weeds)

Inspection records for

geotechnical and landform

stability

GPS locations of recorded

contaminated land sites

Page 219: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 204

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

(i.e. Bowal) to minimise potential for erosion;

A strategy for the disposal of processing reagents,

decontamination of equipment, removal of water

from pond surfaces, will be developed to a level

protective of human health and wildlife, and

installation of equipment necessary for long-term

protection of ground and surface water quality

during the Process Plant’s closure period.

Soil and groundwater testing will be undertaken to

determine whether contamination has occurred with

treatment/remediation implemented if required. The faces

of the ROM pad, the immediate surrounds of the Process

Plant and any exposed areas of soil within the Process

Plant site will be tested for contaminants and re-

vegetated as early as possible after deconstruction

(unless remediation for waste is required first). Any

concrete foundations or soil contaminated by metals,

hydrocarbons or other contaminants will be

decontaminated (volatilisation) and disposed of in a lined

landfill.

Treatment strategies to be further refined before

commissioning of operations;

The WSD embankment breached after mine closure

and the channel re-established so that the

watercourse will resume its natural flow regime post-

closure. The WSD footprint will be rehabilitated with

local non-invasive plant species;

Monitoring of aurface water quality at the

Page 220: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 205

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

downstream compliance points (Badalla Creek and

Gambia River) to ensure applicable discharge and

ambient water quality guidelines are met;

Analysis of the TMF supernatant water to determine

whether treatment is required before establishment

of a permanent discharge channel. Suitable

remedial measures, frequency of treatment, and

ongoing requirements will be determined, if post-

closure treatment is required;

Monitoring of planted / seeded vegetation for

successful establishment. These will be maintained

where necessary;

Monitoring of rehabilitated landforms for

maintenance requirements, particularly with respect

to erosion; and

Monitoring of biodiversity as per the Project BAP to

assess the effectiveness of mitigation measures for

rehabilitation. Monitoring will be undertaken in both

dry and wet seasons to allow comparisons to be

made between seasons over time and in key areas

such as chimpanzee nesting habitat.

For the decommissioning of Project road infrastructure, the

following management and mitigation measures will be

implemented to mitigate water quality and other

environmental impacts:

Road borders and embankments progressively re-

vegetated where necessary for erosion control;

Verification of implementation

On-site and downstream water

quality

Land rehabilitation register:

revegetation success (e.g. %

coverage, species diversity, %

OHS&E Manager /

DEEC and CRSE

Same as above.

Page 221: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 206

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation &

monitoring /

Enforcement

Relevant Documentation

C* O* D*

Road related structures removed where practicable,

including road signage, culverts, oil or grease traps

and hydrocarbons (if applicable);

Rehabilitate Project roads (unless they will be made

available for community use) by ripping road

surfaces, re-shaping to pre-construction contours,

and stabilising and revegetating with native plant

species of local provenance;

Road drainage redirected as necessary to minimise

erosion until vegetation is established; and

An earth berm constructed across the Main Access

Road to maintain community safety.

weeds)

Geotechnical and landform

stability

Inspection records

For Project infrastructure that will be transferred for future

use by local government or community, the Company will

consult and negotiate with the relevant parties and

stakeholders to ensure that:

Remaining mine facilities (e.g. TMF) that may pose

a safety risk to the public are adequately secured;

and

Maintenance requirements and associated costs are

clearly defined.

Verification of implementation OHS&E Manager /

DEEC and CRSE

Same as above.

Page 222: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 207

18.3 Summary of Biological Environment Management and Monitoring Measures

Table 18-3 Register of Biological Environment Management and Monitoring Measures

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation

& monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

Terrestrial and

Aquatic

Biodiversity

Management

The Company will implement the mitigation hierarchy to

avoid, minimise, restore and offset impacts on biodiversity.

The Company will adopt a no net loss approach, where

residual impacts to habitats and species will be offset.

Verification of implementation

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

BAP

SOP09: Land Clearance and Soil

Stockpiling

The Biodiversity Action Plan developed for the Project will

be implemented, providing detailed plans and procedures

for the protection and management of biodiversity (aquatic

and terrestrial) issues. Project personnel and contractors

will adhere to this Plan.

A Biodiversity Offset Strategy will also be implemented to

provide a compensatory mechanism to offset residual

impacts that cannot be avoided, mitigated and/or managed.

The Biodiversity Offset Strategy will be designed through a

process of stakeholder engagement and will focus on the

conservation of priority species and habitats including the

protection of the PNNK.

Key biodiversity measures and strategies detailed in the

BAP and Offset Strategy will be incorporated into relevant

procedures, training, and instructions for the workforce and

contractors, as relevant to their roles and responsibilities

Verification of implementation

Training records

OHS&E Manager,

Contractors /

DEEC and CRSE

Company Plans and Procedures

BAP (including Biodiversity Offset

Strategy)

SOP01: Erosion and Sediment Control

SOP09: Land Clearance and Soil

Stockpiling

International Standards and

Guidelines:

IFC PS 6: Biodiversity Conservation

and Sustainable Natural Resource

Management (2012)

IUCN Red list of Threatened Animals

and Plants (2013)

Good Practice Guidance for Mining

and Biodiversity (ICMM, 2006)

Standards on Biodiversity offsets

(BBOP, 2012)

Resolution VIII.9: 'Guidelines for

Page 223: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 208

incorporating biodiversity-related

issues into environmental impact

assessment legislation and/or

processes and in strategic

environmental assessment' adopted by

the Convention on Biological Diversity

(CBD), and the Ramsar Convention

The following biodiversity management measures will be

adopted to minimise potential impacts on flora, fauna and

protected areas:

To minimise inadvertent impacts to the PNNK from

mining activities, the Company will avoid land

disturbance within the 1 km buffer zone of the

PNNK;

Collaboration with the PNNK area managers to

ensure impacts on the integrity of the PNNK and

surrounding forested areas are adequately

mitigated;

The footprint for the various Project components

have been minimised to the extent practicable, and

a specific vegetation clearance procedure will be

implemented to avoid further disturbance to

surrounding areas. Land disturbance permits will be

required prior to any vegetation clearance, in

accordance with SOP09: Land Clearance and Soil

Stockpiling. Environmentally sensitive areas (e.g.

critical habitat, PNNK boundary) will be clearly

marked as ‘No Go Areas’;

Access to the PNNK and buffer zone by Project staff

to be restricted and subject to approval from the

DPN;

As a condition of employment, ban Project staff from

Verification of

implementation

Incident register

Detailed biodiversity

monitoring program

(refer to further details

below)

Training records

Consultation records

Land rehabilitation

register

OHS&E Manager /

DEEC and CRSE

Same as above plus:

SOP07: Hazardous Materials

Management

Page 224: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 209

hunting, buying or trading wildlife as well as

collecting timber and Non-timber Forest Products

(NTFPs) to help conserve existing fauna and forest

resources (e.g. food for wildlife);

In areas to be cleared, identification and retention or

relocation of restricted-range flora (Lepidagathis

capituliformis, Scleria chevalieri and Tephrosia

berhautiana), threatened flora and important fauna

resources (e.g. baobab trees), where practicable.

Seed collection and propagation of priority flora

species will be included in the inventory of plants

used for Project revegetation activities;

Removal of identified bowal habitat (where this

provides habitat to restricted-range flora species)

and gallery forest habitat (priority nesting habitat for

West African chimpanzee) will be avoided where

possible;

Use of water to minimise dust levels in areas of

biodiversity sensitivity. Control measures will be

employed to minimise erosion and the risk of

suspended sediments release drainage systems as

per SOP01: Erosion and Sediment Control;

Avoid impacts to habitats, priority flora and protected

area through spills of spills of hydrocarbon and

hazardous materials (e.g. paint, solvents etc.)

through adherence to SOP07: Hazardous Materials

Management;

Implementation of the invasive weed prevention

protocol to prevent the introduction and transfer of

invasive species (i.e. Mimosa pigra). This will

include the avoidance of affected areas by staff and

vehicles where possible; wash-down procedures of

Page 225: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 210

Project vehicles moving from the Gambia River and

other known affected areas; and use of non-

invasive local species for revegetation;

Progressive rehabilitation and revegetation

undertaken as soon as possible throughout the life

of the Project to minimise the impact of land

clearance as per the RCMCP (Volume E);

Implementation of bushfire controls, including

Project ban on open-burning of wastes, specific

emergency response procedures developed for

managing bushfires, and establishment of fire

breaks (where required);

Consultation with local authorities and communities

to minimise the impact of in-migration on natural

resource exploitation (including hunting);

Periodic monitoring of habitat and key terrestrial and

aquatic species will be conducted as part of the BAP

(Volume C) to assess the efficacy of the mitigation

measures and to inform any requirements for

adaptive management; and

Environmental education and awareness programs

will be conducted for Project staff and contractors as

relevant to their roles and responsibilities.

Supplementary flora studies of Bowal habitat in the vicinity

of the Project will be conducted

Verification of implementation

OHS&E Manager /

DEEC and CRSE

Same as above.

The Company will adopt additional measures to mitigate

fauna impacts, including:

Testing a variety of bird scaring techniques to

assess their effectiveness in deterring birds from

ingesting the surface water at the TMF. If the trials

are successful, bird scarers will be utilised on a

Verification of

implementation

Incident register

Detailed biodiversity

monitoring program

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

Same as above, plus:

SOP11: Lighting and Visual Amenity

Management

SOP02: Water Quality and Pollution

Management

Page 226: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 211

regular basis to prevent fauna poisoning from

drinking tailings water;

Security fencing around the site perimeter of the

TMF to restrict livestock and some species of local

wildlife from accessing these areas;

Injured Wildlife Protocol to be followed by staff and

contractors if injured or dead wildlife is found or in

the event of an incident (e.g. fauna move away

following vehicle collision), which includes the

following steps:

» Species identification;

» Procedures for the safe management of injured

and dead wildlife including the minimisation of

human contact;

» Mandatory reporting of wildlife incidents that

includes road accidents (e.g. collision with

wildlife or livestock) for all Project workers and

contractors.

Operation of noisy machinery will be avoided at

dusk, dawn and night wherever practicable, to avoid

disturbance to fauna;

Project staff to avoid initiating contact with fauna to

minimise the risk of disease transfer and

disturbance;

Vegetation clearance undertaken in a progressive

and sensitive manner to enable priority fauna to

move away from the area of works and to avoid

fauna from being isolated in fragmented pates of

habitat;

An ecologist will be on call during habitat clearance

(refer to further details

below)

SOP05: Noise and Vibration

Management

Page 227: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 212

work to provide assistance / advice regarding any

biodiversity issues if required;;

Priority species-specific monitoring and

management (e.g. for West African chimpanzees)

undertaken as appropriate, as per the BAP

monitoring requirements;

Implement relevant fauna management measures

for night lighting detailed in SOP11: Lighting and

Visual Amenity Management, where necessary; and

Adherence to SOP02: Water Quality and Pollution

Management for water quality and pollution

management throughout the lifespan of the Project

to minimise the risk of adverse impacts to aquatic

fauna and habitats.

Project roads have been aligned to minimise vegetation

clearance and habitat fragmentation, and avoid

environmentally sensitive areas. The Company will

implement key biodiversity management measures during

construction of Project roads, including:

Applying applicable elements of the BAP where

appropriate;

Avoid impacts to environmentally sensitive areas

wherever practicable as identified through the land

disturbance permitting system in place (refer to

SOP09: Land Clearance and Soil Stockpiling).

Sensitive areas will be marked as ‘No Go Zones’;

To minimise the risk of vehicle collision with fauna,

speed limits within the PDA will be reduced and

driving at night outside of the PDA will not be

permitted unless permission has been sought or in

the event of an emergency;

Verification of

implementation

Incident register

Detailed biodiversity

monitoring program

(refer to further details

below)

Land disturbance

register

Land rehabilitation

register

Project Director /

Operations

Manager / OHS&E

Manager / DEEC

and CRSE

Same as above.

Page 228: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 213

Avoiding impacts to waterways and riparian

vegetation during road construction to the extent

practicable;

Progressively rehabilitate temporarily disturbed

areas as soon as possible;

Restricting access to Project roads within the PDA

(where appropriate) to authorised people only; and

Adherence to the Injured Wildlife Protocol.

Specific biodiversity management measures that will be

applied during Project operations include:

Management of habitats adjacent to and within the

PDA to minimise disturbance to fauna, habitat loss

and degradation (e.g. from poaching, exploitation of

natural resources);

Establishment of a checkpoint at the entrance to the

PDA to ensure no unauthorised entry;

Continual improvement of mine blast associated

noise, vibration and airblast management measures

to minimise fauna impacts; and

Monitoring and adaptive management, as

necessary.

Verification of implementation

OHS&E Manager /

DEEC and CRSE

Same as above, plus:

SOP08: Blasting Management

The following mitigation measures will be adopted during

the decommissioning and closure phase:

All cleared/disturbed areas to beprogressively

revegetated and rehabilitated, unless required for

community or Government use;

Assess the feasibility of artificial filtering systems

(e.g. mini wetlands) for the treatment of discharge

Verification of

implementation

Rehabilitation and

closure success criteria

monitoring (as per

RCMCP)

Revegetation success

OHS&E Manager /

DEEC and CRSE

Company Plans and Procedures

RMCP

Page 229: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 214

water, and implement as appropriate;

Closure criteria for rehabilitation will be met; and

Monitoring in rehabilitated areas, in order to assess

the success of restoration of habitat.

Inspection records

A comprehensive biodiversity monitoring program for the

Project will be further refined and implemented, including

confirmation of specific monitoring sites, including:

See further details below.

OHS&E Manager /

DEEC and CRSE

Same as above.

Camera trapping and sightings

Changes in species

recorded;

Changes in frequency of

habitat use; and

Trigger for adaptive

management: decline in

habitat use.

Targeted chimpanzee surveys

Changes in the number

of fresh, recent, old and

ancient nests;

Changes in nesting

range;

Changes in habitat

usage;

Trigger for adaptive

management: significant

decline in the number of

fresh / recent nests,

significant declines in

maximum number of

nests per nesting site;

and reduction in nesting

range.

OHS&E Manager /

DEEC and CRSE

Same as above.

Page 230: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 215

Targeted hippopotami surveys

Changes in the total

number of hippopotami;

Changes in the

maximum number of

hippopotami per group;

Changes in seasonal

habitat use; and

Trigger for adaptive

management: significant

reduction in hippopotami

numbers, and reduction

in habitat use between

seasons.

OHS&E Manager /

DEEC and CRSE

Same as above.

Vulture nest surveys

Changes in the number

of active vulture nests;

Changes in the number

of vulture nesting sites;

and

Trigger for adaptive

management: significant

decline in the number of

active nests, and decline

in sites.

OHS&E Manager /

DEEC and CRSE

Same as above.

Priority flora survey and monitoring. Presence / likely

absence of priority flora

species based on field

investigations;

Dust levels;

High level of dust on

individuals and signs of

OHS&E Manager /

DEEC and CRSE

Same as above.

Page 231: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 216

plant stress e.g.

chlorosis;

Changes in species

abundances ;

Trigger for adaptive

management: elevated

dust levels, and high

coverage of dust on

priority flora and bowal

habitat.

Invasive species reporting and checks. New record of invasive

species i.e. Mimosa

Pigra;

Trigger for adaptive

management: increased

number of infested sites.

OHS&E Manager /

DEEC and CRSE

Same as above.

Report incidents involving wildlife (and livestock), including

encounters of wildlife (i.e. carcass, injured and priority

species) and observation of poaching, illegal wildlife trade or

logging.

Mandatory wildlife incident

reporting system for Project

employees and contractors.

Relevant government authorities

will be notified as necessary.

Trigger for adaptive

management: changes in

the number of deaths;

confirmation of disease

outbreak; number of

confirmed poison cases.

OHS&E Manager /

DEEC and CRSE

Same as above.

Monitoring of vegetation clearance. Routine checks to ensure

vegetation clearing is confined to

defined areas of disturbance,

OHS&E Manager /

DEEC and CRSE

Same as above.

Page 232: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 217

vehicles use designated access

routes, and any sensitive

environmental areas (i.e. ‘No Go

Areas’) to be retained are clearly

marked (e.g. flag/tape).

Land disturbance register

Macro-invertebrate survey and bio-indicator water quality

assessment. Changes in water quality

identified by the macro-

invertebrate bio-indicator

assessment.

Trigger for adaptive

management: significant

decline in macro-

invertebrate abundance

and diversity; significant

changes in bio-indicator

species; and reduction in

the biological health of

the Gambia River.

Aquatic fauna and habitat

monitoring as per SOP02.18.

OHS&E Manager /

DEEC and CRSE

Same as above.

Drift net survey; Changes in the diversity,

abundance and catch

per unit effort of fish;

Changes in the

proportion captured

juvenile and adult fish;

Trigger for adapted

management: significant

decline in the diversity,

abundance, CPUE of

OHS&E Manager /

DEEC and CRSE

Same as above.

Page 233: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 218

fish; significant decline in

adult fish.

Routine monitoring of rehabilitation areas to assess the

success of restoration measures. Monitoring records will include

the following:

Area

revegetated/rehabilitated

;

Survival rate of planted

seedlings by species

type and replanting

requirements;

Native versus non-native

plant establishment; and

Photographs.

OHS&E Manager /

DEEC and CRSE

Same as above.

Page 234: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 219

18.4 Summary of Social Management and Monitoring Measures

Table 18-4 Register of Social Management and Monitoring Measures

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation

& monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

Land

Management

and Livelihood

Restoration

The Company will avoid and/or minimise the economic

displacement due to Project land take. Mitigation measures will

be implemented such that no person will suffer a livelihood loss

due to the Project. The principles and approach that will be

adhered to are outlined in the Draft Livelihood Restoration Plan

(LRP).

Subject to consultation with Project affected people (PAP),

livelihood mitigation will be planned according to the following

hierarchy of preference:

Category 1 – Restoration of existing livelihood;

Category 2 – Intensification of existing livelihoods;

Category 3 – Introduction of alternative livelihoods.

Verification of implementation

Monitoring of the

implementation of livelihood

restoration program (indicators

will be developed in

consultation with the community

and government)

External compliance reviews

and a completion audit

focussing on the assessment of

compliance with the

requirements contained in the

LRP

OHS&E Manager /

DEEC and CRSE

Company Plans and

Procedures:

LRP

National Standards:

Senegal - Decree for

application 64-573 (GRS,

1964)

International Standards

and Guidelines:

IFC PS5 Land Acquisition

and Involuntary

Resettlement (2012)

IFC A Guide to Getting

Started in Local

Procurement (2011)

IFC Strategic Community

Investment (2010)

The Company will formally register privately owned and

community assets that are likely to be impacted by Project

development. This registration process will be done in

consultation with local communities and government authorities.

Formal register of Project affected land,

assets and livelihood

OHS&E Manager /

DEEC and CRSE

Same as above.

The Company will undertake detailed negotiations with Project Stakeholder engagement OHS&E Manager / Same as above.

Page 235: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 220

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation

& monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

affected people on the mitigation measures resulting from Project

land take. The outcome of these negotiations will include a

finalised LRP and collective and/or individual-level agreements.

database and consultation

meeting records

Collective and/or individual

agreements with Project

affected people

Final LRP

DEEC and CRSE

The Company will implement Livelihood Restoration and

Livelihood Improvement Programs as agreed with PAPs, aimed to

restore and improve the assets, levels of economic productivity,

and/or standards of living to pre-Project levels.

Livelihood mitigation measures will be maintained by the

Company for as long as necessary to fully restore the livelihood of

PAPs.

Verification of implementation

OHS&E Manager /

DEEC and CRSE

Same as above.

Vulnerable

Groups

A “vulnerable persons” assistance program will be implemented

as part of the LRP, which will include specific assistance

measures to vulnerable households or groups.

Specific aspects of the vulnerable persons’ assistance program

will include:

Recruitment of part-time Vulnerable Persons Officer; and

Preparation and up-date of a formal register of vulnerable

groups (“vulnerables watch list”) throughout the life of the

Project.

Verification of implementation

Formal register of vulnerable

groups (“vulnerables watch list”)

OHS&E Manager /

DEEC and CRSE

Same as above.

Employment

Opportunities

The Company will implement an overall Equal Opportunity

Employment Policy, which requires the Project to provide equal

opportunity to all applicants regardless of age, gender or ethnicity.

Workforce statistics (including

employment by contractors)

OHS&E Manager /

DEEC and CRSE

Company Plans and

Procedures:

LEPP and LRP

Page 236: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 221

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation

& monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

The Company will implement a Local Recruitment Policy that is

based on a preference for the most local candidate. The Local

Economic Participation Plan (LEPP) will be implemented to

support this recruitment approach.

International Standards

and Guidelines:

IFC PS5 Land Acquisition

and Involuntary

Resettlement (2012)

IFC: A Guide to Getting

Started in Local

Procurement (2011)

IFC Strategic Community

Investment (2010)

International Council on

Mining and Metals (ICMM)

Sustainable Development

Framework

Local

Procurement

The Company will implement a Local Procurement Policy to

maximise the opportunity for local suppliers to participate in the

supply chain for the Project.

Local goods and services

procured by the Project - refer

to procurement records

Maintenance of a Local Supplier

Database

Company Plans and

Procedures:

LEPP

International Standards

and Guidelines:

IFC: A Guide to Getting

Started in Local

Procurement (2011)

IFC Strategic Community

Investment (2010)

International Council on

Mining and Metals (ICMM)

Sustainable Development

Page 237: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 222

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation

& monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

Framework

Community /

Stakeholder

Engagement

Stakeholder consultation will be conducted for affected peoples,

and villagers.

The established Stakeholder Engagement Plan (SEP) for the

Project will be implemented and further refined.

Community consultation will involve a cross-section of local

residents (i.e. different ethnicities, a range of ages, gender

balance, etc.) to ensure that the opinions and concerns of all

groups are considered.

Disseminate understandable information in advance of

consultation and decision-making

Community awareness and

understanding of Project

information

Information disclosed as per the

SEP

Key stakeholders consulted as

per the SEP

Number of consultations

conducted

Grievance register

OHS&E Manager /

DEEC and CRSE

Company Plans and

Procedures:

SEP

International Standards

and Guidelines:

Stakeholder Engagement:

A Good Practice

Handbook for Companies

doing Business in

Emerging Markets. IFC

(2007)

Doing Better Business

through Effective Public

Consultation and

Disclosure. A Good

Practice Manual. IFC

(1998)

Handling and Resolving

Local Level Concerns and

Grievances. ICMM (2009)

Community Development

Toolkit. ICMM (2005).

Develop and maintain structured engagement mechanisms for

the dissemination of Project information responding to people’s

concerns, suggestions and grievances. This is expected to

include:

Verification of implementation

Consultation database

OHS&E Manager /

DEEC and CRSE

Same as above.

Page 238: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 223

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation

& monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

Project Negotiations Forum (PNF) to support the LRP;

Local Consultation Committee (Groupe de Contact); and

Other thematic working groups and focus group

discussions (as needed).

The Company will use a range of other engagement tools and

activities including:

Public Information Centre (PIC) to serve as a space for

trainings, meetings, workshops and to post notices;

Notice boarding, advertisements and press releases;

Community meetings in Project affected villages;

Meetings with existing structures such as the Municipal

Council.

Workshops to discuss technical issues with relevant

stakeholders;

Direct engagement with stakeholders where necessary.

Project

Grievances

The Project grievance management system will be implemented

to record and resolve community complaints in a transparent,

constructive and timely manner.

Reported grievances and

resolutions

Response times on claims via

the grievance register

Number of claims elevated to

Third or Fourth Order

Mechanism

Satisfaction levels - gauged

through discussions with the

OHS&E Manager /

DEEC and CRSE

Same as above.

Page 239: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 224

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation

& monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

Local Consultation Committee /

Project Negotiation Forum

Community

Health, Safety

and Security

The following general management measures will be

implemented to minimise Project impacts on community health

and safety:

Establishment of health and safety management systems

for the community, covering aspects on security, Project

hazards, disease prevention (e.g. HIV and Malaria

programs), and safe sanitation and hygienic practices;

A range of security controls will be developed in

consultation with relevant actors in advance of Project

Construction. These controls will be routinely reviewed

with regional authorities;

Implementation of a community education and awareness

program regarding public safety in and around the PDA

(particularly related to road safety);

An exclusion zone defined to restrict and control access

within the PDA and ensure community safety. This zone

will include the blast exclusion zone. The zone will be

monitored prior to blasting activity;

In partnership with local health authorities, support

community malaria prevention programs in Project

affected villages;

In partnership with local authorities, support community

hygiene and sanitation programs in Project affected

villages;

In partnership with local health authorities, support

Verification of implementation

Logged community complaints

and grievances through the

Project grievance management

process

Noise limit and air quality limit

exceedances at nearby

sensitive receptors

Health and nutritional indicators

in the local community (e.g.

availability of food, food supply

options, prevalence of

undernourishment, agricultural /

food production etc.) and

workforce

Increased injuries and fatalities,

including:

Number of transport related

incidents / grievance claims –

refer to grievance log

Number of community safety

incidences or livestock losses

associated with restricted

areas– refer to visual inspection

OHS&E Manager /

DEEC and CRSE

Company Plans and

Procedures

Emergency Preparedness

and Response Plans (to

be developed)

International Standards

and Guidelines:

General EHS Guidelines

(IFC, 2007)

Mining EHS Guidelines

(IFC, 2007)

IFC PS4 Community

Health, Safety and

Security (2012)

IFC PS5 Land Acquisition

and Involuntary

Resettlement (2012)

ICMI, International

Cyanide Management

Code (2014)

Page 240: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 225

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation

& monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

community HIV/AIDS awareness programs in Project

affected villages;

Mitigate the adverse impacts of the Project on access to

community infrastructure and services (e.g. water supply,

hygiene and sanitation, health, security), particularly those

related to Project induced in-migration. The Company will

monitor the impacts of in-migration in consultation with

local authorities and communities in Project affected

villages;

Maintain a surface and groundwater quality monitoring

program, including routine sampling of village drinking

water in Project affected villages;

In partnership with local authorities, support community

drinking water management programs in Project affected

villages.

and audit records

Number of community

consultations / awareness

sessions conducted – refer to

consultation record sheet and

database

Worker health

and safety

Establishment of health and safety management systems

for Project workers, covering aspects on security, Project

hazards, disease prevention (e.g. HIV and Malaria

programs), and safe sanitation and hygienic practices;

Provision of health care services for its employees with an

appropriately staffed on-site clinic and medivac

capabilities;

Health and nutritional indicators

in the workforce

Number of worker training

sessions conducted (refer to

training records)

OHS&E Manager /

DEEC and CRSE

In-Migration

Prior to construction and in consultation with local authorities, the

Company will re-assess the need for the development of an In-

Migration Management Strategy.

Verification of implementation

OHS&E Manager /

DEEC and CRSE

Not applicable.

Page 241: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 226

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation

& monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

The Company will mitigate the adverse impacts arising from

Project induced in-migration. The Company will monitor the

impacts of in-migration in consultation with local authorities and

communities in Project affected villages. Management measures

will include:

Working with local authorities to minimise the potential

impacts on in-migration (e.g. security, education and

awareness campaigns against drug and alcohol abuse,

supporting health services) and to monitor demand and

resources;

Provision of daily bus transportation for Project staff

between the Project site and Kedougou town to enable

workers to live and commute from Kedougou without

suffering from fatigue;

Implementation of a recruitment policy which prioritises

local employment;

Recruitment for unqualified positions to be restricted to

residents in Tomboronkoto Commune only;

Local and regional residents will have preferential access

to skills upgrading courses, based on Project skill

requirements;

Provision of training to assist in developing local skill

levels and entrepreneurship that is not solely dependent

upon the Project;

Access to the accommodation camps restricted to Project

staff and people with an authorised visitor pass. No staff

Verification of implementation

Household surveys recording the

following socio-economic indicators:

Demographic indicators;

Population growth and in-

migration;

Income and expenditure

indicators, incidence of poverty;

Livelihoods and employment

indicators;

Housing and assets;

Education; and

Health and nutrition indicators.

Monitoring of effectiveness of local

recruitment and procurement, including;

Local workforce statistics

(including employment by

contractors) - refer to

employment records;

Number of training sessions;

Local goods and services

procured by the Company (refer

to procurement records);

OHS&E Manager /

DEEC and CRSE

Company Plans and

Procedures:

In-Migration Guidance

Note

Worker Accommodation

Guidance Note

LEPP and SEP

Project recruitment policy

International Standards

and Guidelines:

Same as above.

Page 242: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 227

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation

& monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

will be allowed outside the camps between the hours of

seven pm till morning;

Socio-economic surveying and review of census data for

Project affected villages will be conducted over the Project

life to understand the extent of population growth and any

related impacts; and

Incentivise the in-migration of Project staff to Kedougou

where this has potential to result in adverse impacts to

Project affected villages;

Increase the capacity of Tomboronkoto Commune, and

Mako and Niemenike in particular, to plan for and absorb

in-migration in a manner that improves quality of life and

maximises economic benefit. This may include providing

assistance to the Municipal Council to support the

preparation of the Commune Development Plan ;

Work with local authorities and communities to restrict the

development of new habitation areas within the PDA and

other areas of the mining concession where this could

present risks to human safety and/or the operational

security of the Project.

Maintain a Local Supplier

Database;

Training session for suppliers

Monitoring of livelihoods, health and in-

migration indicators (indicators will be

developed in consultation with the

community and government)

Monitoring of local economic pilot

programs (indicators will be developed

in consultation with the community and

government)

Reported Project grievances and

resolutions

Community

Development

The Company will establish a social and environmental

investment fund to ensure that the Commune of Tomboronkoto,

and more broadly the State of Senegal, shares the benefits of the

Project. Investment will be aligned with government policy and

local development plans i.e. Commune and Departmental

development plans and PNNK management plan.

Verification of implementation

Achievement of development goals as

agreed with local authorities

OHS&E Manager /

DEEC and CRSE

Same as above.

Page 243: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 228

Aspect / Impact Phase Management Measure / Commitment Monitoring Indicators Responsible for

implementation

& monitoring /

Enforcement

Relevant Documentation

C

*

O* D*

Community

Awareness and

Education

Program

A community awareness and education program for local

communities will be conducted. The scope of these programs

may include:

Public health, sanitation, and sexually transmitted

diseases;

Safety exclusion zones;

Traffic awareness and safety;

Employment and skills development;

Livelihood restoration and improvement; and

Economic participation (e.g. micro financing, financial

management, etc.).

Programs will be adapted to meet ongoing needs and new risks,

and will be developed and implemented with the participation of

local authorities, NGOs, and community groups.

Number of social education and cultural

awareness training programs for the

community

OHS&E Manager /

DEEC and CRSE

Not applicable.

Project Staff and

Worker

Awareness

Social and cultural awareness programs for Project staff and

contractors (e.g. through staff inductions) will be implemented to

improve their understanding of various cultural and social

sensitivities.

Number of environmental and social

induction programs for the workforce

and contractors

OHS&E Manager,

Contractors /

DEEC and CRSE

Not applicable.

Page 244: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 229

19 REFERENCES

AMEC (2013). Tailing Management Facility Scoping Study, Mako Project, Senegal. Prepared for Toro Gold Limited, March 2013.

ANCOLD (2012). Guidelines on Tailings Dams. Source: http://www.ancold.org.au/?page_id=334, accessed

10/03/2015.

Coffey (2015). Toro Project Definitive Feasibility Study (June 2015).

Earth Systems, (2015). Mako Project, Senegal - Socio-Economic, Land and Water Use Study.

Earth Systems (2014). Final Mako Prefeasibility Study. Prepared for Mako Exploration Company.

EITI (2013). Senegal’s application for EITI candidature approved. Electronic source: http://eiti.org/news/senegal-application-eiti-candidature-approved. Accessed 22 November 2013.

European Union (EU) (2008). Directive 2008/105/EC of the European Parliament and of the Council of 16 December 2008 on Environmental Quality Standards in the Field of Water Policy, Amending and Subsequently Repealing Council Directives 82/176/EEC, 83/513/EEC, 84/156/EEC, 84/491/EEC, 86/280/EEC and Amending Directive 2000/60/EC of the European Parliament and of the Council. Sourced online at: http://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:L:2008:348:0084:0097:EN:PDF.

EU (2006). Directive 2006/44/EC of the European Parliament and of the Council of 6 September 2006 on the Quality of Fresh Waters Needing Protection or Improvement in Order to Support Fish Life. Sourced online at: http://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:L:2006:264:0020:0031:EN:pdf.

EU (1998). Council Directive 98/83/EC of 3 November 1998 on the quality of water intended for human consumption. Sourced online at: http://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:L:1998:330:0032:0054:EN:PDF.

Gouvernement de la République du Sénégal (GRS) (2002). Interministerial Decree No. 1555 Discharge Water Guidelines. Gouvernement de la République du Sénégal.

GRS (2001). Loi No 2001 – 01 du 15 Janvier 2001 portant Code de l’environnement. Available http://www.environnement.gouv.sn/IMG/pdf/code_env.pdf. Accessed 3 December 2013.

IFC (2012). International Performance Standards on Environmental and Social Sustainability and Guidance Notes, 2012. International Finance Corporation.

IFC (2009). Projects and People. A Handbook for Addressing Project-Induced In-Migration.

IFC (2008). IFC Environmental Health and Safety Guidelines for Thermal Power Plants, 2008.

IFC (2007a). Environmental Health and Safety (EHS) Guidelines - General, 2007.

IFC (2007b). Environmental Health and Safety (EHS) Guidelines – Mining, 2007.

IFC (1998). Good Practice Manual Doing Better Business through Effective Public Consultation and Disclosure.

International Cyanide Management Institute (ICMI) (2014). The International Cyanide Management Code For the

Manufacture, Transport, and Use of Cyanide in the Production of Gold" (Cyanide Code).

International Council on Mining & Minerals (ICMM) (2012). Voluntary Principles on Security and Human Rights.

Available http://www.icmm.com/library/voluntary-principles-on-security-and-human-rights. Accessed 8 August

2013.

International Commission on Large Dams (ICOLD) 1996. A Guide to Tailings Dams and Impoundments - Design,

Construction, Use and Rehabilitation.

International Standards Organisation (ISO) (2009). ISO31000 Risk Management; Principles and Guidelines.

International Standards Organisation (ISO) (2009). ISO31010 Risk Management; Risk Assessment Techniques.

Page 245: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 230

IUCN (2015). ‘The IUCN Red List of Threatened SpeciesTM’

. www.iucnredlist.org, International Union for Conservation of Nature.

Knight Piesold (2014). Review of Tailings Management and Water Management Options, Memorandum, 21 July 2014.

Knight Piesold (2015a). Tailings Management Facility Operating and Monitoring Manual.

Knight Piesold (2015b). Mako Gold Project – TSF and WSD Design Summary. Memorandum, 27 February 2015.

Knight Piesold (2015c). Pers. Comm., Mako Preliminary Water Balance Findings. Email communication from Steve McKean (Knight Piesold) to Russell White (Toro Gold), 4 March 2015.

Knight Piesold, (2015d). River Abstraction Preliminary Design. Memorandum, 20 March 2015.

Knight Piesold, (2015e). Mako Gold Project Water Balance Modelling Summary. Memorandum, 20 March 2015.

Knight Piesold (2015f). Tailings Management Facility - Site Selection Assessment.

MCA (1997). Minesite Water Management Handbook. Minerals Council of Austrialia.

Ministere de l’Environnement et de la Protection de la Nature (2007). ‘Etude de Danger – Guide Methodologique.’

NAC. Nevada Administrative Code Chapter 445a – Water Controls Mining Facilities. Source:

http://www.nmenv.state.nm.us/wqcc/documents/NMEDExhibit9.pdf, accessed 10/03/2015.

rePlan (2015a). Guidance Note: Worker Accommodation.

rePlan (2015b). Guidance Note: In-Migration.

SRK (2014a). Mako Prefeasibility Study Chapter 9: Processing Plant Design.

SRK (2014b). Mako Prefeasibility Study Chapter 10: Tailings Management Facility.

SRK (2014c). Mako Prefeasibility Study Chapter 7: Mining Engineering, Design and Production Scheduling.

SRK (2014d). Mako Prefeasibility Study Chapter 12: Water Management.

SRK (2015). Geochemical Characterisation and Management Report (unpublished).

Toro Gold (2013). ‘Toro Gold’. Source: http://www.torogold.com (Accessed 8 August 2013).

Toro Gold (2014). Environmental and Social Performance Framework.

Toro Gold (2015). Mako Gold Project Feasibility Study Monthly Report, January and May 2015.

UNESCO (2014a). World Heritage List. Source: http://whc.unesco.org/en/list/, accessed on 03/09/2014.

USEPA (2009). National Recommended water quality criteria; republication. United States Environmental Protection Agency, Federal Register Vol. 64, No. 277, 2009.

World Health Organization (WHO) (2011). Guidelines for drinking-water quality, 4th ed. Geneva, World Health Organization.

WHO (2005). Air Quality Guidelines for particulate matter, ozone, nitrogen dioxide and sulfur dioxide – Global Upate 2005, World Health Organization

Page 246: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 231

APPENDIX A

Standard Operating Procedures (SOPs)

Page 247: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 235

SOP01: Erosion and Sediment Control

I.D. No. Measures for erosion and sedimentation control and management Applicable

for

C* O* D

*

SITE EROSION AND SEDIMENT CONTROLS

SOP01.1 The Construction Environmental Management Plan (CEMP) will include provision for erosion and sediment control. Where appropriate, the plan will detail upstream and

downstream locations for structures, devices, and monitoring sites.

SOP01.2 Minimise erosion and sedimentation by employing the following measures, where appropriate:

Minimise vegetation clearance to the extent practicable;

Avoid ground disturbance works within 50 m of a river, stream or wetland unless necessary for in-stream works (e.g. water abstraction tower in Gambia River);

Schedule major earthworks and grading operations for early in the dry season. Avoid the wet / rainy season or periods of high intensity rainfall wherever possible;

Divert upstream surface runoff of a worksite away from exposed areas; and

Restrict vehicles to designated access tracks / roads and exclude vehicles from operating in areas not in use for construction or operation.

SOP01.3 Implement best practice erosion and sediment controls prior to any earthworks commencing, and maintain these in place until no longer required. Key measures include:

Identifying drainage lines and installing erosion and sediment control measures suitably designed for site conditions to accommodate for expected peak water flows

(e.g. designed for a one-in-two-year storm event for temporary structures, and 1 in 100 year 24 hour average return interval storm event for permanent structures),

where appropriate;

Containing surface runoff between worksites and adequately treating sediment-laden runoff prior to discharge to the receiving environment;

Install sediment control dams, drainage structures and additional sediment control facilities prior to the commencement of the wet season;

Employing intermediate controls to capture silt and coarser particles downstream of turbid water source, including check dams, sediment/silt traps, baffles, and

stormwater and sediment retention ponds;

Ripping the surface and re-contouring slopes and batters to maximise rainfall infiltration and decrease the velocity of water across the slope during rainfall events.

Where possible, drainage channels will typically have a uniform slope between 0.5% to 1%;

Page 248: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 236

I.D. No. Measures for erosion and sedimentation control and management Applicable

for

C* O* D

*

Installing dissipation structures or rock / concrete flow barriers at regular intervals for drainage channel slopes greater than 1%, to reduce water velocity (if

appropriate);

Employing scouring controls including vegetation, rip rap or other erosion resistant material to protect drainage lines, spillways and inlets/outlets from scouring;

Keeping to a minimum time exposed surfaces, and revegetating and/or stabilising exposed areas as soon as possible after works are completed;

Using cleared vegetation for erosion control and stabilisation of disturbed areas, where possible;

Disturbed land areas will be progressively rehabilitated when feasible, with priority rehabilitation and revegetation undertaken in high risk areas, such as steep slopes

and sites close to rivers and creeks; and

Embankments will be constructed with suitable materials to minimise the risk of failure due to erosion or excessive seepage rates and ensure geotechnical stability.

SOP01.4 For any in-stream construction work (e.g. for water abstraction from the Gambia River), ensure works are conducted during no or low water flow events (e.g. during dry

season), stream bank stabilisation is provided, and appropriate erosion and sediment control measures are implemented to protect streambeds from damage and minimise

sediment transport from construction.

SOP01.5 Incorporate additional water quality and stormwater management measures specified in SOP02: Water Quality and Pollution Management, and SOP03: Hydrology and

Water Management, where appropriate.

EROSION AND SEDIMENT MONITORING

SOP01.6 Implement routine maintenance and inspection schedule for erosion and sediment control devices to ensure they work properly and are effective. Key aspects will include:

Continually assess the suitability and effectiveness of erosion and sediment control measures and improve control measures if they are no longer effective, e.g.

clearing channels of sediment and replacement of bed scour protection; and

Routinely monitor for visual evidence of erosion and sedimentation (e.g. in areas where major earthworks is being conducted), particularly following intense rainfall

events.

* C = Pre-Construction/Construction; O = Operations; D = Decommissioning/Closure

Page 249: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 237

SOP02: Water Quality and Pollution Management

Surface and groundwater within the natural receiving environment may be contaminated from Mako Gold Project activities such as site preparation, open-cut mining and ore

processing, handling and disposal of hazardous materials, and workforce accommodation. Primary sources of contaminated water may include process and mine water, oily water

from vehicle workshops and washdown areas, raw sewage and wastewater from Accommodation Camps, and spillage/leakage of fuel or hazardous materials in storage and

handling areas.

As the Project will be a ‘zero-discharge’ operation, no releases to the receiving environment will occur. To ensure adequate management of contaminated water onsite and

compliance with applicable water quality discharge standards and guidelines, the Company will implement the management measures and procedures outlined in the table below

and ensure they are incorporated into a CEMP as appropriate.

I.D. No. Measures for water quality and pollution management Applicable

for

C* O

*

D

*

WATER QUALITY POLLUTION MANAGEMENT

SOP02.1 Where possible, clean water diversion structures will be provided outside the Mine Site perimeter and around active construction areas to intercept and divert upstream

clean water into sedimentation / retention ponds for release into the natural environment. Prior to release, ensure silt and coarser sediments have sufficient time to settle

to acceptable levels compliant with relevant discharge standards. Properly operate and maintain sedimentation / retention ponds to ensure they remain efficient.

SOP02.2 As the Project will be a ‘zero-discharge’ operation, all mine water from within the Mine Site boundary and from dewatering the Pit will be collected and diverted to

sedimentation / retention ponds, WSD or the TMF depending on the location and suitability of water, to allow for settling and reuse as process water or for dust

suppression (if water quality is suitable).

SOP02.3 Clearly communicate to all employees and contractors that any dumping or discharging of potentially contaminated water (e.g. oily water, raw sewage, untreated waste

water, mine water, etc.) into the receiving environment is strictly prohibited: through employee training, mandatory induction, specific contract requirements, and

procedures in place. Severe penalties will apply for any breaches and compliance monitoring and audits will be undertaken to ensure conformance with the ‘zero

discharge’ policy onsite.

SOP02.4 For any in-stream works carried out (e.g. for water abstraction from the Gambia River), the worksite will be operated as a closed system to the extent possible to avoid

pollution of surrounding surface water, and appropriate erosion and sediment control measures will be employed as per SOP04.4 to limit sedimentation impacts.

SOP02.5 Where possible, primary sources of hazardous material contaminated water will be identified (e.g. vehicle workshops, hazardous materials and fuel storage areas) and

equipped with appropriate facilities for the containment / controlled release of spills and stormwater, including bunding, sump collection, provision of grease and sediment

traps. Contaminated water from these areas will be transferred to the TMF via pipeline / channel. Refer to SOP07: Hazardous Materials Management for further details

Page 250: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 238

I.D. No. Measures for water quality and pollution management Applicable

for

C* O

*

D

*

on management procedures.

SOP02.6 The paving of surfaces for roads and other constructed areas will be scheduled to avoid wet weather, where possible, with appropriate sediment control devices provided

downstream of area to be paved.

SOP02.7 Refer to SOP06: Waste Management for implementing management procedures for solid and liquid waste, including for adequate treatment of raw sewage and

wastewater.

WATER QUALITY MONITORING

SOP02.8 Establish and maintain the detailed water quality monitoring programme for all phases of the Project based on the following applicable guidelines to ensure compliance:

Water Discharge and Monitoring

National Standards

Inter-ministerial Decree No. 1555 Discharge Water Guidelines / L’arrêté interministériel No. 1555 de 15 mars 2002 portant application de la norme NS 05-061

sur les rejets des eaux usées (2002)

Waste Water Discharge Standard, NS 05-061 / La norme sur les rejets des eaux (NS 05-061) (2001)

Draft Standard on Management of Solid Waste / Projet de Norme relative à la Gestion des Déchets Solides

International Standards:

IFC Mining EHS Guidelines (2007)

IFC General EHS Guidelines – Wastewater and Ambient Water Quality (2007)

EU Ambient Water Quality Guidelines

ICMI International Cyanide Management Code (2014).

Aquatic fauna / freshwaters

International Standards:

US National recommended water quality criteria (United States Environmental Protection Agency (USEPA), 2009)

EU Directive 2008/105/EC of the European Parliament and of the Council of 16 December 2008 on environmental quality standards in the field of water policy,

Page 251: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 239

I.D. No. Measures for water quality and pollution management Applicable

for

C* O

*

D

*

amending and subsequently repealing Council Directives 82/176/EEC, 83/513/EEC, 84/156/EEC, 84/491/EEC, 86/280/EEC and amending Directive 2000/60/EC

of the European Parliament and of the Council (EU, 2008)

EU Directive 2006/44/EC of the European Parliament and of the Council of 6 September 2006 on the quality of fresh waters needing protection or improvement

in order to support fish life (EU, 2006)

Drinking water

International Standards:

WHO Guidelines for Drinking Water Quality, fourth edition (2011)

EU Council directive 9883/EC of November 1998 on the quality of water intended for human consumption (EU, 1998).

SOP02.9 Weekly field water sampling at major construction area discharge points, active construction / mining areas, and soil stockpile areas for Turbidity, TSS, DO, temperature,

electrical conductivity (EC), and pH.

SOP02.10 Weekly visual checks for sedimentation, oils and grease at construction area discharge points.

SOP02.11 Routine monthly monitoring of treated effluent and wastewater from water treatment plants for total and faecal coliform, total nitrogen, total phosphorous, COD, and BOD

at the water treatment plants and/or discharge points.

SOP02.12 Monthly ambient water monitoring of field water parameters (pH, Redox potential (ORP), Dissolved Oxygen (DO), Electrical conductivity (EC), Total Dissolved Solids

(TDS), Turbidity and temperature) and laboratory testing for pH, EC, Total Dissolved Solids (TDS) and Total Suspended Solids (TSS), Cyanide (Weak Acid Dissociable

(WAD) CN and Free CN), Total alkalinity (or acidity), bicarbonate alkalinity, carbonate alkalinity and total hardness as CaCO3, Nutrients (ammonia as N, nitrate as N, total

Kjeldahl nitrogen and total phosphorous), Cations and anions (Cl, SO4, Ca, Mg, Na, K), total cations and total anions; and Total and dissolved metals (Ag, Al, As, Au, Ba,

Be, Cd, Co, Cr, Cu, Fe, Hg, Li, Mo, Mn, Ni, Pb, Sb, Se, Sn and Zn).

Monitoring locations are situated upstream and downstream of Badalla Creek and Gambia River, as described in the Surface Water and Groundwater Resources

Baseline Report (Volume C, Appendix 3).

SOP02.13 Monthly water quality monitoring of tailings, supernatant water, and seepage water at the TMF as well as of the mine water within the Pit (e.g. pit sumps) will be

undertaken. Sampling for laboratory testing of the following parameters will be undertaken to ensure cyanide concentrations are consistent with ICMI International

Cyanide Management Code (2014): cyanide (including free CN, WAD and total), salinity, total and dissolved metals (full suite), and nutrients. Field parameters (e.g. pH,

EC, ORP, DO, Temp. etc.) will also be sampled for using field probes.

The TMF will be monitored through the installation of geotechnical instruments including monitoring bores/ piezometers.

Page 252: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 240

I.D. No. Measures for water quality and pollution management Applicable

for

C* O

*

D

*

SOP02.14 The quantity and the concentrations of contaminants being discharged from the Project to the environment at Closure will be monitored for compliance. It is only when

the water quality is of adequate quality (in accordance with the relevant discharge and ambient (downstream) water quality criteria) that the water may be discharged

from site. Compliance sites (e.g. point of discharge at the Badalla Creek and Gambia River) and frequency will be confirmed in the next phase of the Project, as

described in the Surface Water and Groundwater Resources Baseline Report (Volume C, Appendix 3).

Parameters to be monitored will include pH, EC, ORP, acidity/alkalinity, sulfate, dissolved metals (to be determined by waste rock characterisation) and cyanide (i.e. free,

WAD, and total), related breakdown products of cyanide (e.g. ammonia, nitrate, thiocyanate), salinity, nutrients, pathogens and field parameters (e.g. pH, EC, ORP, DO,

temp. etc.). Multi-element testing using ICP-MS will be undertaken from time to time to fully characterise the discharge (refer to the Surface and Groundwater

Resources Baseline Report (Volume C, Appendix 3).

SOP02.15 Groundwater quality monitoring for the Project will include ongoing monitoring at the existing Company monitoring programme locations as described in the Surface and

Groundwater Resources Baseline Report (Volume C, Appendix 3).

During construction, a number of groundwater monitoring bores will be installed both up-gradient and down-gradient of the TMF, Mine Pit and WRD. Bores up-gradient

of the TMF and Mine Pit will be monitored monthly for water level, EC and pH, and quarterly for metals, major ions and ligands. Bores down-gradient will be monitored

according to the procedure described above for ‘Discharge Monitoring’ (refer to SOP02.14).

Once operations commence, this monitoring programme should be re-evaluated based upon previous results, existing operations, and environmental conditions.

SOP02.16 Prior to mine closure, surface and groundwater sampling of TMF water and down-gradient bores will be undertaken to ensure water quality is acceptable and meets

discharge standards. Sampling for laboratory testing of the following parameters will be undertaken to ensure cyanide concentrations are consistent with ICMI

International Cyanide Management Code (2014): cyanide (including free, WAD and total CN), salinity, total and dissolved metals (full suite) and nutrients. Field

parameters (e.g. pH, EC, ORP, DO, Temp. etc.) will also be measured using field probes.

SOP02.17 If a change in the geochemical risk classification of the tailings is observed, an AMD management plan will be prepared.

SOP02.18 The existing baseline aquatic fauna and habitat monitoring programme will be continued for areas upstream, within and downstream of the Project Development Area

using standard monitoring techniques (e.g. surveys and bio-indicator analysis, drift net surveys for fish), particularly for the restricted range fish species Barbus

dialonensis (a priority species).

The programme will use sample sites established in the baseline studies, as appropriate.

SOP02.19 All field sampling, handling, storage, and transport of samples will strictly be conducted in accordance with approved methodologies and procedures. All sample

laboratory testing will be conducted at an adequately licensed and accredited laboratory. Frequent re-calibration checks of field probes and instruments will be

undertaken to ensure they remain accurate.

Page 253: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 241

I.D. No. Measures for water quality and pollution management Applicable

for

C* O

*

D

*

SOP02.20 Regular visual checks and site inspections for potential leakage or seepage of contaminated water at primary source locations (e.g. Process Plant, TMF and associated

pipelines, fuel storage areas, etc.) for hazardous chemicals and hydrocarbons.

SOP02.21 Where appropriate, investigative water quality monitoring at key locations in response to applicable complaints received through the Project grievance management

system. Provide or adapt with additional mitigation if required.

* C = Pre-Construction/Construction; O = Operations; D = Decommissioning/Closure

Page 254: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 242

SOP03: Hydrology and Water Management

Water entering the Project site has the potential to become contaminated by hydrocarbons, chemicals (including hazardous chemicals), toxic pollutants (e.g. cyanide) and

sediments. To minimise the amount of water entering the Project Development Area and potentially becoming contaminated, the Company will implement a water management

strategy that is aligned with its ‘zero-discharge’ policy, and effectively manages site water according to international mining industry standards. The management measures and

procedures provided in the table below will be adopted and incorporated into the CEMP and other Project documents as appropriate.

I.D. No. Measures for hydrology and water management Applicable

for

C* O

*

D

*

WATER MANAGEMENT

SOP03.1 The amount of surface water runoff entering the Mine Site and active construction areas will be minimised by installing stormwater drainage systems with appropriate

erosion and sediment controls outside the boundary of the active Mine Site, to intercept and divert ‘clean water’ upstream for release into the natural environment, as

per SOP02.1.

SOP03.2 All water (including surface runoff) within the Mine Site will be captured in sedimentation / retention ponds and eventually discharged into the TMF or WSD facilities for

reuse as process water or dust suppression water (if water quality permits), where appropriate (as per SOP2.2).

SOP03.3 Surface water management infrastructure will be designed and installed as appropriate within and outside the Project Development Area to manage surface runoff and

mine water in a controlled and efficient manner (refer to SOP01: Erosion and Sediment Control and SOP02: Hydrology and Water Management, for details).

SOP03.4 Stormwater infrastructure/devices including cut-off / diversion drains, velocity dissipation devices and culverts will be used, where appropriate, to control water flow

velocities and avoid flows over bare slopes and disturbed surfaces. Devices will need to accommodate peak flows (e.g. at least 1:100 year average return interval storm

events)

SOP03.5 Water from dewatering the Pit and other potentially contaminated sites will be transferred via sumps to the TMF for reuse as process water.

SOP03.6 The use of passive water treatment methods will be maximised within the Project Development Area (e.g. sedimentation pond), where possible.

SOP03.7 Construction materials, equipment and chemicals will be stored away from flood prone waterways/drainage lines and inundation areas during the rainy season to avoid

accidental release to the natural environment.

SOP03.8 Upon completion of construction activities, disturbed surfaces will be graded where practicable to provide proper drainage.

SOP03.9 Provide employee training and awareness programmes on water management that focuses on water pollution prevention and water efficiency, recycling and reuse

strategies in place within the Project Development Area. Contractors will also be required to ensure water efficiency, recycling and reuse opportunities are maximised to

Page 255: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 243

I.D. No. Measures for hydrology and water management Applicable

for

C* O

*

D

*

the extent possible, and that they conform to water pollution prevention procedures.

SURFACE WATER MONITORING

SOP03.10 A site water balance and inventory will be prepared and continually maintained that monitors site water consumption (according to volume and water quality), as well as

water stored and managed onsite (including at the WSD and TMF), to avoid potential water shortages and/or overcapacity. Trigger levels will be established specifying

water volumes and parameter concentrations that, if exceeded, will require an appropriate management response. Historical climatic data collected onsite and

regionally will be considered for identifying new trends and continuous improvement.

SOP03.11 The Company has established a number of hydrology monitoring stations around the Mako Project area which are monitored on an ongoing basis. Installation of a

series of additional stream gauges on waterways upstream and downstream of the Project may be required depending on the preferred Project layout. Stream gauges

will be used to measure surface flow and stream height. Data will be collected routinely (e.g. daily or monthly) depending on the location. Implementation and

management will be the responsibility of the Company’s Environment Department.

SOP03.12 Surface water management structures and devices within and outside of the Project Development Area will be periodically checked to ensure their efficacy (and

improved or upgraded, if required).

SOP03.13 A regular inspection and maintenance schedule of dam infrastructure (e.g. TMF, WSD) to ensure adequate structural integrity and water levels for dam safety:

Daily visual inspections will be conducted of reservoir water levels for freeboard management to ensure sufficient freeboard for a 1 in 100 year rainfall event is

maintained to prevent overtopping of the dam wall and dam failure during periods of high or extended rainfall;

Periodic (e.g. daily or weekly) visual inspections will be undertaken of dam toe, emergency spillway and embankment, to inform any remedial works required.

The emergency spillway of the WSD will be inspected weekly during the dry season and on a daily basis during the wet season to ensure it is free of debris or

vegetation. The emergency spillway for the TMF will be inspected annually; and

Independent annual audits of the TMF and WSD will be conducted by a suitably qualified specialist to ensure structural integrity (e.g. for embankment

movement) is maintained.

Sediment and debris traps around the perimeter of the reservoir will also be maintained in order to reduce the amount of dirt in the reservoir.

SOP03.14 A regular inspection and maintenance schedule of water pipelines (e.g. raw water, process water, tailings), flanges, seals and pumps to ensure physical integrity and

condition. Pipeline channels will be kept free of vegetation and physical obstructions. The Company will engage with the community, and in particular herders, to

prevent pipe tapping of the pipe.

* C = Pre-Construction/Construction; O = Operations; D = Decommissioning/Closure

Page 256: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 244

SOP04: Emission and Dust Control

Project activities are expected to result in significant greenhouse gas (GHG) emissions as well as increased air pollutants of potential concern including fugitive dust or particulate

matter (PM10 and PM2.5), carbon monoxide (CO), carbon dioxide (CO2), oxides of nitrogen (NOx), sulphur dioxide (SO2), ozone (O3) and volatile organic compounds (VOCs). While

greenhouse gas emissions are known to be the primary contributor to global warming and climate change, the latter can create nuisance to local communities (particularly along

unsealed roads in the dry season) or impact public health, vegetation growth and agriculture.

The following SOP provides the minimum management measures to address dust, air quality and greenhouse gas impacts based on the IFC General EHS Guidelines 2007. These

will be incorporated into site procedures for the Project to be prepared prior to construction.

I.D. No. Measures for dust, air quality and greenhouse gas management Applicable

for

C* O

*

D

*

PREVENTION OF FUGITIVE DUST AND AIR POLLUTION

SOP04.1 Use dust controls (e.g. watering, gravel application) on unsealed access tracks and exposed surfaces heavily trafficked by machinery and vehicles (e.g. site entry/exit

points, loading and unloading areas, etc.) during the dry season or when excessive dust generation is evident. Increase frequency during periods of high risk (e.g. dry

and windy conditions). Dust suppression water will be taken from suitable recycled water sources (e.g. treated truck wash water and other mine wastewater), wherever

possible.

SOP04.2 Revegetate or cover any unused or exposed soils with mulching, woodchips, stone/gravel layering or grass matting (to quickly stabilise exposed soils).

SOP04.3 Implement the following dust management measures for soil stockpiling:

Rib and roughen smooth surfaces to reduce wind velocity;

Locate stockpiles in areas naturally sheltered from wind, if feasible;

Install temporary wind fences, if required;

Plant / revegetate long-term topsoil stockpiles (more than three months); and

Spray water on stockpiles if excessive dust generation is evident.

SOP04.4 Avoid undertaking primary dust generating activities during dry and windy conditions (e.g. loading, hauling and dumping of topsoil, blasts).

Page 257: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 245

I.D. No. Measures for dust, air quality and greenhouse gas management Applicable

for

C* O

*

D

*

SOP04.5 Ban open-burning of general wastes and vegetation. Unavoidable waste incineration (e.g. for cyanide and hydrocarbon wastes) will be undertaken in accordance with

the IFC General EHS Guidelines - Waste Management Facilities (2007).

SOP04.6 For temporary and permanent crushing and batching plant activities (e.g. concrete batching plant, Process Plant), employ suitable dust suppression control measures

(e.g. sprayers, dust collectors, unloading tubes) to ensure that dust emissions are not excessive.

SOP04.7 Employ additional measures provided in Chapter 9 (Roads and Transport) of the ESMMP for managing road and transport air quality emissions and SOP09: Land

Clearance and Soil Stockpiling to assist in managing dust emissions from land clearing and soil stockpiling.

BLASTING AND DRILLING MANAGEMENT

SOP04.8 Implement the following general dust and air quality management measures for blasting and drilling activities:

Lower dust aprons during drilling;

Equip drills with dust extraction cyclones or water injection systems;

Use water injection or dust suppression sprays prior to undertaking drilling or blasting when high levels of dust are being generated; and

Consider prevailing wind conditions (e.g. Harmattan winds) prior to blasting.

GREENHOUSE GAS MANAGEMENT

SOP04.9 Follow good international industry practices for minimising and offsetting Project related greenhouse gas emissions, particularly for major emission sources (e.g. Power

Station, Process Plant), including:

Adherence to energy, water and resource conservation and efficiency principles (e.g. fuel, reagents, grinding media, etc.) as per the IFC General EHS

Guidelines;

Use of best available technology to minimise emissions and energy consumption;

Selection of construction materials to minimise carbon footprint impact, where practicable (e.g. recycled steel, concrete with recycled fly ash and aggregate,

etc.);

Additional greenhouse gas emissions control procedures as described in Chapter 9 of the ESIA Study (Volume A), where practical; and

Minimisation of vegetation clearance and maximising abatement opportunities through vegetation offsets and carbon sequestration in the form of revegetation of

land during and after mining (as per the Rehabilitation and Conceptual Mine Closure Plan, Volume E).

Page 258: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 246

I.D. No. Measures for dust, air quality and greenhouse gas management Applicable

for

C* O

*

D

*

SOP04.10 Applying appropriate greenhouse gas management measures to all Project-related transport activities, including:

Minimising haul distance for material delivery and workforce transport to reduce fuel consumption;

Selecting fuel efficient vehicles and equipment; and

Avoid unnecessary idling, queueing, and overloading when operating vehicles or equipment.

SOP04.11 Integrate energy efficiency principles in building or facility design, including:

Optimised lighting system, e.g. skylight installations, solar powered or fluorescent lamps, timers on lights, etc;

Design to minimise air conditioning requirements and for building internal temperature to be maintained at optimum;

Energy efficient equipment in accordance with industry standards, including adoption of best industry practice technology for the processes involved, and most

efficient mining, blasting and crushing/grinding practices;

Alternative energy sources considered, e.g. co-generation plant, reciprocating engines, waste heat recovery, renewable energy sources such as biomass

gasification, solar power or the use of biofuels; and

Additional energy source and control procedures as described in Chapter 9 of the ESIA Study (Volume A), where practical.

SOP04.12 Ensure contractors comply with relevant measures for greenhouse gas management and energy conservation set out for the Mako Gold Project.

SOP04.13 Conduct awareness training on energy conservation and GHG reduction for Project employees and workforce.

SOP04.14 Establish greenhouse gas reduction and energy conservation targets for the Mako Gold Project for measuring improvement in the GHG intensity of mining operations in

accordance with good international industry practice.

AIR QUALITY AND GREENHOUSE GAS MONITORING

SOP04.15 Establish and maintain the detailed air quality programme for all phases of the Project based on the following applicable guidelines to ensure compliance:

National Standards:

Atmospheric Pollution Standard, NS 05-062 / La Norme de rejets NS 05-062 – pollution atmosphérique (2004)

International Standards:

Page 259: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 247

I.D. No. Measures for dust, air quality and greenhouse gas management Applicable

for

C* O

*

D

*

IFC Mining EHS Guidelines (2007)

IFC General EHS Guidelines – Air Emissions and Air Quality (2007)

WHO Air Quality Guidelines – Global Update (2005)

SOP04.16 Four dust monitoring points have been established by the Company in the vicinity of the PDA (refer Air Quality, Noise and Vibration Assessment, Volume A).

Maintain and update the air quality monitoring programme for the Project based on the IFC General EHS Guidelines for Air Quality to ensure compliance with relevant

national and international guidelines. Key air quality monitoring requirements include:

Daily visual checks for visible fugitive dust on all active Project roads, stockpiles, and material transfer points (e.g. at Process Plant);

Continued monitoring (on a biannual basis) of PM2.5 and PM10, SO2, NOx, CO and dust deposition rates at the four existing dust monitoring stations to evaluate

the performance and adequacy of management and mitigation measures (refer Air Quality, Noise and Vibration Assessment, Volume C). Dust monitoring of

both PM10 and PM2.5 will continue to be undertaken at these sites, with ten (10) days continuous monitoring undertaken at each site on a rotational basis.

Additional monthly monitoring of TSP at each site will also be required to allow comparison to IFC standards;

Where appropriate, investigative dust and air quality monitoring at key locations in response to applicable complaints received through the Project grievance

management system. Provide additional mitigation if required.

Additional dust monitoring sites may be required in villages located near the Main Access Road, at the new Accommodation Camp, and at a control site (refer to Air

Quality, Noise and Vibration Assessment, Volume A).

SOP04.17 Continued meteorological monitoring from the two Automatic Weather Stations (AWS) established in 2012 by the Company for the Mako Gold Project (refer

Meteorological Baseline Study, Volume C). The AWS automatically logs measurements of rainfall, wind speed and direction, temperature, and relative humidity. Data

will be downloaded on a monthly basis. Evaporation readings from an evaporation pan will also be recorded manually on a daily basis.

SOP04.18 As per IFC requirements, periodically update the Project GHG inventory developed for construction and operational GHG emissions during the calendar year period,

and assess performance against set GHG reduction and energy conservation targets. Incorporate additional GHG mitigation and abatement measures if required.

* C = Pre-Construction/Construction; O = Operations; D = Decommissioning/Closure

Page 260: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 248

SOP05: Noise and Vibration Management

The Mako Gold Project will involve heavy construction and earth moving plant and machinery, truck haulage, processing plant operations, and blasting practices. These Project

activities will generate increased noise and vibration (ground and airborne) impacts. General management measures are presented below to ensure that noise and vibration

impacts produced by the Project do not result in disturbance or nuisance to adjacent sensitive receptors (e.g. settlements, noise sensitive fauna), damage to nearby structures, or

exceed applicable noise and vibration criteria guidelines. They are based on the IFC General EHS Guidelines – Noise Management (2007), with the adoption of the following control

hierarchy for noise and vibration mitigation and management:

Elimination of the source;

Substitution with quieter equipment/process;

Engineering controls at the source;

Treatment of the propagation path; and

Installation of mitigation controls at the receiver.

More detailed site procedures specific to the Mako Gold Project will be developed prior to construction incorporating the below general management measures.

I.D. No. Measures for noise and vibration management Applicable for

C* O* D

*

ACTIVITY AND INFRASTRUCTURE SITING

SOP05.1 Locate major noise stationary sources (such as plant equipment and infrastructure including compressors, generators, concrete batching plant) away from potentially

sensitive receptors (biological and community) and take advantage of natural terrain and existing features (e.g. vegetation) to buffer the noise generated.

SOP05.2 Obtain approval by the Company’s OHS&E Manager for locating major noise/vibration sources (activities and infrastructure) near potentially sensitive receptors.

SOP05.3 Enforce exclusion zone of 500 m (to prohibit establishment of new settlements) near major Project components (e.g. Mine Pit, Process Plant, Power Station, etc.) to

limit noise and vibration impacts on potentially sensitive receptors.

NOISE AND VIBRATION MANAGEMENT

SOP05.4 Ensure all Mako Gold Project noise emissions comply with relevant noise and vibration guidelines for nearby residential dwellings, particularly the IFC General EHS

Guidelines – Noise Management (2007) (refer to SOP05.11 for further details):

Page 261: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 249

I.D. No. Measures for noise and vibration management Applicable for

C* O* D

*

75 dB(A) LAeq (daytime period) and 50 dB(A) LAeq (night-time period) during Project construction and closure; and

55 dB(A) LAeq (daytime 1 hour) and 45 dB(A) LAeq (night-time 1 hour) during Project operations.

SOP05.5 Adopt methods and technologies informed by detailed noise modelling to reduce noise impacts in the Project design, where possible.

SOP05.6 Implement the following noise and vibration management measures to all Project activities, where appropriate:

Maximise use of existing topography and features (e.g. vegetation) to shield noise sensitive receptors from major stationary sources;

Select quietest plant and equipment that can economically undertake the work;

Regularly maintain heavy machinery equipment and vehicle fleet in good working order and ensure they are within industry standards for noise and vibration

emissions;

Avoid conducting earthmoving, ground impacting, and demolition activities simultaneously near a sensitive receptor or structure to minimise the amount of

noise and vibration generated at any given time (if applicable);

If night-time work in residential areas is required, employ noise attenuation measures such as temporary noise enclosures or barriers to minimise noise

disturbance. Ensure affected residents are appropriately notified in advance of night-time works;

Use piling/drilling methods with the lowest noise and vibration impact, such as lowering drop heights or impact levels for piling hammers, and using piling

shrouds or temporary barriers or hoardings; and

Provide hearing protection to Project personnel working in noisy construction areas (i.e. where noise levels are expected to be greater than 80 dB(A)).

SOP05.7 Where required, incorporate noise reduction, sound insulation and absorption to different equipment and operations, including:

Impedance mufflers/silencers and vibration insulating on air compressors, blowers and fans;

Sound insulation covers, where applicable;

Sound insulation treatment for high noise equipment and primary noise-emitting buildings to improve acoustic performance (e.g. crushing area of the Process

Plant);

Suitable mufflers on engine exhausts and compressor components; and

Acoustic enclosures for equipment casing radiating noise.

Page 262: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 250

I.D. No. Measures for noise and vibration management Applicable for

C* O* D

*

SOP05.8 Employ additional measures provided in Chapter 9 (Roads and Transport) of the ESMMP for vehicular noise and vibration management, where applicable.

COMMUNITY COMMUNICATION PROTOCOL

SOP05.9 Ensure potentially affected nearby residents have been appropriately notified and consulted on scheduled Project activities prior to works commencing, following an

established communication protocol. Details will be communicated for:

Type of proposed activities (e.g. road construction, blasting, etc.)

Commencement and completion dates

Hours and likely timing of activities (including number of blasts, if applicable)

Any mitigation measures to be employed.

SOP05.10 Noisy construction activities near community sensitive receptors will be restricted to daytime hours only when ambient noise and levels are higher and less disruptive.

If a change is required to the approved hours or schedule, approval will be sought by the Contractor from the Company’s OHS&E Manager and affected local

residents notified in advance.

NOISE AND VIBRATION MONITORING

SOP05.11 Establish and maintain the detailed noise and vibration monitoring programme for all phases of the Project based on the following applicable guidelines to ensure

compliance:

National Standards:

Environment Code (noise) / Code de l’Environnement (2001)

International Standards:

British Standards (vibration) BS 6472:2008, 4866:2010 and 7385-2:1993 (1993, 2008, 2010)

IFC General EHS Guidelines – Noise (2007)

Mining EHS Guidelines (2007)

SOP05.12 Four noise monitoring points in the Mako Project area have been established by the Company (refer Air Quality, Noise and Vibration Assessment, Volume C).

Maintain and update the noise and vibration monitoring programme for the Project based on the IFC General EHS Guidelines (2007) for Noise to ensure compliance

with relevant national and international guidelines. Key noise and vibration monitoring requirements include:

Page 263: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 251

I.D. No. Measures for noise and vibration management Applicable for

C* O* D

*

Periodic (e.g. when there is a change of blast location) monitoring of noise, airblast, and ground vibration impacts within 500m of blast areas (during Project

pre-construction, construction and operations);

Bi-annual monitoring of noise levels in dB(A) LAeq (daytime and night-time period) at the Process Plant during Project Construction and Operations;

Noise logger monitoring (10 days continuous) will continue to be undertaken at the existing sites on a rotational basis for all phases of the Project to allow

comparison to IFC standards; and

Where appropriate, investigative noise and vibration monitoring in response to applicable complaints received through the Project grievance management

system. Provide additional mitigation if required (e.g. additional shielding, change timing of scheduled Project activities, substitute with quieter equipment,

etc.).

Additional noise monitoring sites may be required in villages located along the Main Access Road, at the new Accommodation Camp, and at a control site (refer to Air

Quality, Noise and Vibration Study, Volume A, Appendix 4).

SOP05.13 Maintain ongoing consultation and prior notification of potentially noisy works with affected settlements/villages to ensure noise and vibration associated impacts are

adequately addressed.

* C = Pre-Construction/Construction; O = Operations; D = Decommissioning/Closure

Page 264: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 252

SOP06: Waste Management

Proposed activities and personnel required for the Mako Gold Project will generate a number of general (non-mining) waste materials, including biodegradable (e.g. food scraps,

wood) waste, recyclable waste (e.g. plastics, scrap metal and timber, packaging) and residual landfill waste (e.g. construction concrete) as well as raw sewage and greywater.

General waste that is improperly stored or disposed of could have adverse effects on human health, habitat and biodiversity.

A preliminary summary of the general wastes to be generated by the Project and their method of disposal is presented below. This inventory will be updated in the next phase of

the Project as necessary.

General waste stream Nature of the general waste Estimated quantity Method of disposal in order of preference

LIQUID WASTE

Mine services area waste water Truck wash water <50 m3/day Used for dust suppression on haul roads

Sewage Treatment Plant (STP) treated water for

the accommodation camps

Treated water from camp STP 50-100 m3/d

Leach drains

Recycle/reuse

STP treated water plant for the mine services area Treated water from plant site STP 50-100 m3/d

Disposal to the plant tails hopper or TMF and recovered

for use as process water

SOLID WASTE

Putrescible waste Kitchen waste and food scraps 250 kg/day Burial in lined landfill

Office waste Paper , toner, etc. 250 kg/week Burial in lined landfill

Other domestic waste Bottles, cans, plastics <2 m3/day

Recycle

Balance to landfill

Construction waste Various categories 10 t/day

Sorted in accordance with types below and disposed of

in a similar manner

Scrap timber Packaging, scrap pallets, off cuts, etc. <2 m3/week

Recycle

Landfill

Page 265: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 253

General waste stream Nature of the general waste Estimated quantity Method of disposal in order of preference

Scrap metals Scrap equipment and parts, steel off cuts, etc. <2 m3/week

Recycle

Landfill

Non-toxic solid reagent packaging Polypropylene or similar bags <100 kg/week Landfill

Grinding media packaging 200 L steel drums 50/week Recycled

Vehicle workshop waste Used tyres Not available Reuse in mine site recapping if possible, or reuse in

retaining mine wall construction, or transfer to landfill as

a last resort.

General waste management for the Project will be undertaken in accordance with IFC General EHS Guidelines - Waste Management (2007) (refer to Chapter 1.6 Waste Management

of Guideline) and the following waste management hierarchy (in decreasing order of preference):

1. Minimise the production of waste

2. Maximise waste recycling and reuse

3. Treatment of waste

4. Ensure safe waste disposal.

A detailed inventory of hazardous wastes generated by the Project will be maintained to include:

Waste type;

Source;

Quantity; and

Management method.

Mine related wastes such as waste rock and tailings will be separately addressed in the Waste Rock Management Plan and Tailings Operating and Monitoring Manual respectively,

which will be developed in the next phase of the Project by the Company. Refer to SOP07: Hazardous Materials Management for relevant measures to specifically manage and

dispose of hazardous wastes.

Page 266: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 254

I.D. No. Measures for general waste management Applicable for

C* O

*

D

*

GENERAL WASTE MANAGEMENT AND PREVENTION OF LITTERING

SOP06.1 Employ site waste minimisation strategies, including

Optimising efficiency and resource use of all site production processes; and

Procuring supplies and consumables that have been produced from recycled materials or produce less waste in packaging and production

Educating staff and contractors on waste minimisation during inductions.

SOP06.2 Prohibit Project workforce from littering onsite.

SOP06.3 Install colour-coded bins with weatherproof lids and appropriate signage at designated locations around the Project site (e.g. workforce accommodation camp, Project

construction sites, and active operations sites) for collection and segregation of waste. Waste collection to occur frequently to avoid overflowing of bins.

SOP06.4 Train staff and contractors on waste management and specific procedures to follow.

SOP06.5 Educate staff, contractors and local community to actively clean-up litter and minimise the generation of litter.

SOLID WASTE MANAGEMENT, RECYCLING, AND REUSE

SOP06.6 Establish a waste management system and comprehensive waste inventory that identifies, tracks and quantifies major waste streams generated at the Project site.

The following information will be recorded:

Composition and waste type according to different waste streams

Quantity and storage location

Transport and disposal methods (e.g. safe disposal certificates)

Final destination, including amount of each waste type that has been recycled or reused.

SOP06.7 Collect and segregate solid waste into the following categories:

Biodegradable materials, e.g. cleared vegetation and food scraps;

Recyclable materials, e.g. scrap timber and metal, hard plastic, glass, paper and cardboard, batteries, and tyres; and

Non-hazardous residue waste, e.g. excess concrete, non-recyclable plastics, bricks, etc.

Page 267: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 255

I.D. No. Measures for general waste management Applicable for

C* O

*

D

*

SOP06.8 Manage general Project waste in accordance with IFC General EHS Guidelines – Waste Management (2007), including as follows:

Suitable waste management facilities for the Project include:

» Recycling facilities for the storage and collection of recyclable materials in separate weather-proof storage areas that can easily be cleaned, including

for glass, scrap metal, and scrap timber;

» Landfill facilities for disposal of non-recyclable and non-hazardous residue wastes. The landfill facility will be suitably designed and constructed with

lined cells developed progressively as required, and covered with soil on a weekly basis to prevent scavenging and windblown rubbish.

» Composting pits for the disposal of biodegradable waste, will be covered with soil on a weekly basis to avoid scavenging and windblown rubbish;

» Sewage treatment plants for the treatment of raw sewage and greywater (see below for further details).

Location of waste management facilities will be at least 50 m from any drainage lines, streams or rivers and within the TMF catchment, if possible;

Primary containment bunds will be provided containing at least 110% of the volume of non-hazardous wastes in storage areas; and

Perimeter security fencing will be provided, where appropriate, to deter wildlife and pest species, and ensure public safety (e.g. for land fill facilities and

sewage treatment plants).

SOP06.9 Identify opportunities for recycling and reusing Project wastes generated onsite to the extent practicable. Where possible, consider the following beneficial reuse

options:

Composted biodegradable materials for revegetation activities;

Treated effluent and wastewater for dust suppression; and

Inert construction waste (e.g. excavated subsoil, building rubble, concrete waste) for construction backfilling.

SOP06.10 Mark on maps of the Project site all waste management facilities (active and decommissioned), including GPS coordinates, area, volume, and type of waste stored in

each facility.

SOP06.11 Prohibit open-burning of general waste and vegetation for disposal.

SOP06.12 Identify reputable, licensed service providers for the recycling of recyclable wastes. Prior to engaging, review and audit contractor’s transport and disposal practices

and certification to ensure they are suitably qualified.

SEWAGE AND GREY WATER MANAGEMENT AND TREATMENT

Page 268: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 256

I.D. No. Measures for general waste management Applicable for

C* O

*

D

*

SOP06.13 Install ablution facilities and pit latrines (at isolated construction areas) for the Project workforce, and instruct workers to use the toilets provided.

SOP06.14 All raw sewage and wastewater will be treated by appropriate water treatment plants to meet relevant national and international water quality guidelines (refer to

SOP2.10). Dumping of untreated raw sewage and domestic wastewater into the receiving environment will be strictly prohibited. Installed storage facilities (e.g.

septic tanks) and water treatment plants will be sufficient to accommodate for the Project workforce, and conform to the industry standards for domestic water

treatment.

SOP06.15 Reuse treated water onsite (e.g. for dust spraying, process water, fire water tank, etc.), where possible.

GENERAL WASTE MONITORING

SOP06.16 Develop and maintain the detailed waste monitoring programme for the Project up-to-date based on the IFC General EHS Guidelines for Waste (2007) to ensure

compliance with relevant national and international guidelines. Key waste monitoring requirements include:

Conduct of annual waste audits to monitor emerging trends in waste generation over time. Relevant site waste management plans and procedures will be

updated for new waste streams and improved waste minimisation methods and recycling techniques, where applicable;

The Company to undertake regular inspections to monitor the success and compliance of waste management strategies onsite according to key performance

indicators (e.g. use of appropriate containers for waste, beneficial reuse or recycling, and waste reduction); and

Investigative monitoring for waste related complaints through the Project Grievance management system and implementation of remedial actions accordingly.

* C = Pre-Construction/Construction; O = Operations; D = Decommissioning/Closure

Page 269: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 257

SOP07: Hazardous Materials Management

Hazardous materials and dangerous goods may pose a hazard to human health or the environment if improperly handled due to its quantity, concentration, acute or chronic toxic

effects, carcinogenicity, flammability, explosiveness, radioactivity, or physical, chemical or infectious characteristics.

Hazardous materials that will be stored and handled onsite for the Mako Gold Project include cyanide and other process plant reagents; oils, solvents, and other hydrocarbons (e.g.

diesel); and herbicides. In addition, dangerous goods involving explosives will be stored and handled onsite for blasting during the construction and operational phases.

A number of hazardous wastes will be generated, including reagent bags (that are likely to contain some reagent residue), medical waste (e.g. sharps and bandages), waste oil and

lubricants, paints and solvents, hydrocarbon contaminated soil, and raw sewage sludge. A preliminary summary of the hazardous wastes expected to be generated by the Project

and their method of disposal is presented below. This inventory will be updated in the next phase of the Project as necessary.

Hazardous waste stream Nature of the hazardous waste Estimated quantity Method of disposal in order of preference

LIQUID WASTE

Truck wash sludge Hydrocarbon contaminated sludge from truck wash

sump <10 m3/week

Volatilise contaminants and burial in lined landfill

All water to be directed to Tailings Management Facility

(TMF)

Plant tailings Process plant tailings 225 t/h solids, 225 t/h process

water

Solids deposited in the TMF

50% of process water entrained in saturated tailings in TMF

Balance of process water recovered and returned to

process plant for re-use

Sewage treatment plant (STP) sludge Treatment plant sludge from all sewage treatment plants <50 kg/d Direct landfill burial in unlined pits

Waste oil Used as lubricating oil for vehicles and machinery 1,000 L/week Recycle

SOLID WASTE

Liquid reagent packaging 200 L plastic drums 20/week

Recycle

Landfill

Cyanide reagent packaging Wood and plywood bulk-boxes, bags <1,000 kg/week Burn and dispose of ashes in lined landfill

Page 270: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 258

Hazardous waste stream Nature of the hazardous waste Estimated quantity Method of disposal in order of preference

Oil-based waste Oil filters, waste oily rags

Not available

Removal of recyclable parts where possible, then

incineration.

Ash disposed in lined landfill

Contaminated soil Contaminated with chemicals and / or oil spills <1 m3/week average Volatilise contaminants and burial in lined landfill

Medical waste Clinic and first aid waste Not available Burn and dispose in landfill

The Company and its contractors will develop specific hazardous materials management procedures and sub-plans (i.e. Cyanide Spill Contingency Plan) as part of the Project Waste

Management Plan and Emergency Preparedness and Response Plans to be developed prior to construction commencing, which incorporate the below measures to ensure proper

compliance with the transportation, management, and disposal of hazardous chemicals and dangerous goods.

I.D. No. Measures for hazardous materials management Applicable for

C* O D*

HAZADOUS MATERIALS STORAGE AND CONTAINMENT (INCLUDING FOR HYDROCARBONS AND CYANIDE)

SOP07.1 Construct appropriately designed and marked hazardous material delivery, transfer and storage areas as follows:

Compliant with applicable building, fire safety and hazardous materials/dangerous goods code requirements;

Within the catchment of the TMF, where possible; or at least 100 m away from natural streams, wetlands, flood prone areas and sensitive areas;

Clear labelling of the type of hazardous materials handled or stored with relevant Material Safety Data Sheets (MSDS) displayed;

A primary containment system comprised of concrete slabs, bund (that can contain at least 110% of the volume of hazardous material stored onsite) and

sump to recover spilled material and rain from slabs (if applicable);

A secondary containment system where any spillage exceeding the capacity of bunds will report to a lined event pond;

All pipe work and pumps will be within bunds or routed above ground to allow the early identification of any leaks; and

Weatherproof shelters to prevent collection of rainfall within the bunded area.

SOP07.2 Install primary and secondary containment systems as per SOP07.1 in all areas where hazardous materials are stored, handled, transferred, or where there is

potential for contamination (e.g. Process Plant, Mine Services Area, Power Station).

Page 271: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 259

I.D. No. Measures for hazardous materials management Applicable for

C* O D*

HAZARDOUS MATERIALS MANAGEMENT AND DISPOSAL (INCLUDING FOR HYDROCARBONS AND CYANIDE)

SOP07.3 Be consistent with the following international standards and codes for hazardous materials and dangerous goods, where applicable:

International Cyanide Management Code Principles and Standards of Practice for cyanide handling, storage and transportation (ICMI, 2014);

IFC General EHS Guidelines 2007 (Chapter 1.5 Hazardous Materials Management and Chapter 3.5 Transport of Hazardous Materials);

United Nations, Transport of Dangerous Goods - Model Regulations. 17th Revised Edition (Volume 1) Geneva 2011;

AS 1940 – The Storage and Handling of Flammable and Combustible Liquids. (Current 2004 ed.); and

AS 2187 – Explosives – Storage, Transport and Use. (Current 1998 ed.).

SOP07.4 Establish a rigorous process that continually reviews risks, management priorities, and residual risks presented by hazardous materials onsite to reduce potential

risks to as low as reasonably practicable. Maintain a detailed inventory of hazardous materials used onsite, with the following details documented in a database:

Type and source of hazardous materials including wastes;

Quantity, location and physical state of stored materials;

Complete set of up-to-date MSDS from the supplier and manufacturer of products;

Method and date of storage, treatment or disposal; and

Waste tracking documentation including quantity, type, date dispatched / transported / received, and record of the originator, transporter and receiver.

SOP7.5 Provide and enforce use of appropriate personal protective clothing and equipment (i.e. gloves, plastic coveralls, safety glasses and self-contained respirators),

emergency information posters, and clean-up spill kits (including specialised kits for hydrocarbons, cyanide and other chemical spills) at strategic locations where

hazardous chemicals are handled.

SOP7.6 Develop work safety procedures, instructions and emergency response procedures (i.e. as part of the Project Emergency Preparedness and Response Plans to be

developed) on how to safely handle, store and dispose of hazardous materials (including for cyanide spills) as well as for adequate emergency communication

capability with potentially impacted communities, governments and nominated emergency response teams within a timely manner. Relevant safety procedures and

supporting material will be provided in the local language used onsite.

SOP7.7 Train workers responsible for hazardous materials handling, storage and use of hazardous materials as well as comprehensive emergency response training for

process operators. Employees with emergency spill clean-up training will be present during unloading and handling of hazardous materials. Key aspects covered in

training will include:

Page 272: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 260

I.D. No. Measures for hazardous materials management Applicable for

C* O D*

Identification and potential dangers and risks from hazardous materials and wastes;

Proper hazardous waste storage, handling and disposal procedures;

Safety and emergency response procedures; and

Use of warning signs, MSDS, PPE and clean up materials for spills.

SOP7.8 Secure and clearly label all designated hazardous materials and explosive storage areas and containers (including for collection and disposal) with the following

information displayed (in local language):

Words ‘Hazardous’ and name of material and its physical state (liquid or solid);

Hazard characteristics (e.g. ignitable, corrosive, toxic, reactive) and health danger (e.g. poison, burn, inhalation or eye/skin irritant);

MSDS; and

Date of storage and source.

SOP7.9 Identify suitably qualified and licensed transporters for dangerous goods and hazardous materials (e.g. ICMI 2014 Cyanide Code-compliant transporter).

Review/audit their internal health and safety documentation to ensure they are adequate prior to contract engagement.

SOP7.10 Use recommended herbicides (for weed control) and pesticides (for vector control) as pre-authorised by the Company Environment Department. Strictly follow usage

instructions and do not apply herbicides / pesticides during or just before rain events.

GENERAL HAZARDOUS WASTE MANAGEMENT (INCLUDING FOR HYDROCARBONS AND CYANIDE)

SOP7.11 Manage hazardous wastes using the following procedure, where appropriate:

Comply with applicable codes specified in SOP07.3 and SOP7.15 for the collection, handling and disposal of hazardous materials and wastes;

Collect hazardous wastes and store in appropriate waste management facilities constructed in accordance with SOP07.1;

Separate hazardous and non-hazardous waste streams, while considering the use of less hazardous substitutes for hazardous materials wherever possible.

Keep hazardous wastes separate to prevent potential for chemical reactions. Consider recycling useful hazardous wastes such as oil or water-based paint;

Prohibit disposal of hazardous wastes (e.g. solvents, used oils, paints, reagents, cracked batteries, acids) in general waste bins;

Hazardous chemicals in drums or bags stored on pallets;

Store cracked batteries in a non-leaking container even if the acid appears to have been drained out; and

Page 273: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 261

I.D. No. Measures for hazardous materials management Applicable for

C* O D*

Schedule periodic waste collection to prevent overflow of containers / facilities.

SOP7.12 Hazardous wastes such as reagent packaging that cannot be reused or recycled will be buried in a designated waste landfill lined with synthetic or compacted clay

basal liner to prevent contamination of surrounds. Hazardous waste requiring prior incineration (e.g. contaminated soil from chemical or oil spills, reagent packaging,

contaminated truck wash sludge) will be volatised in an appropriately designed burn-pit or incinerator.

SOP7.13 Ensure pests and native fauna cannot access hazardous waste items.

SOP7.14 Dispose of suitable sewage treatment plant sludge by direct landfill burial in unlined pits.

CYANIDE MANAGEMENT

SOP7.15 Be consistent with the ICMI Cyanide Management Code (Cyanide Code) Principles and Standards of Practice for cyanide handling, storage and transportation,

including independent third-party auditing of procedure conformance. ICMI Principles include (ICMI, 2014):

Production: Encourage responsible cyanide manufacturing by purchasing from manufacturers who operate in a safe and environmentally protective manner;

Transportation: Protect communities and the environment during cyanide transport;

Handling and Storage: Protect workers and the environment during cyanide handling and storage;

Operations: Manage cyanide process solutions and waste streams to protect health and the environment;

Decommissioning: Protect communities and the environment from cyanide through development and implementation of decommissioning plans for cyanide

facilities;

Worker Safety: Protect workers’ health and safety from exposure to cyanide;

Emergency Response: Protect communities and the environment through the development of emergency response strategies and capabilities;

Training: Train workers and emergency response personnel to manage cyanide in a sage and environmentally protective manner;

Dialogue: Engage in public consultation and disclosure.

SOP7.16 Specific training will be provided to plant operators and employees handling and transporting cyanide. In accordance with the ICMI 2014 Cyanide Code, the training

programme will include:

Improving the understanding of cyanide related hazards and health risks (including learning how to recognise and treat cyanide poisoning);

Use of operating manual, standard operating procedures, equipment, checklists, training documents, and tracking records in place to prevent or control

Page 274: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 262

I.D. No. Measures for hazardous materials management Applicable for

C* O D*

worker exposures and environmental releases during cyanide unloading, storage and mixing;

Emergency response procedures to respond to worker exposure or environmental release of cyanide, including decontamination and first aid procedures;

Refresher courses on a periodic basis and emergency drills to ensure effectiveness of procedures and training in place; and

Relevant staff and contractors will need to be trained and instructed to adhere to the specific Cyanide Spill Contingency Plan to be developed for the Project.

SOP7.17 Dispose of cyanide waste (e.g. packaging and containers) by incinerating in an appropriately engineered burn-pit/incinerator and disposing of potentially

contaminated ashes at an adequately designed landfill (refer to SOP7.12 for details on burying hazardous wastes).

HYDROCARBON MANAGEMENT

SOP7.18 Develop a specific hydrocarbon contaminated soils procedure detailing different methods for treatment and disposal based on scale and type of situation (e.g. small

spill, general spill, large spill).

SOP7.19 Implement the following procedure for areas used for hydrocarbon storage, refuelling, equipment laydown, and vehicle maintenance and washdown (e.g. Vehicle

Workshop, Fuel Depot, truck washdown area, grease and oil waste storage facility):

Perimeter bunding and interception drains to contain oily runoff. Containment facilities to include sediment and grease traps as a minimum;

Appropriate spill clean-up materials (e.g. Sorbex) for small hydrocarbon spills, and drop cloths and drain pains during vehicle maintenance to catch leaks or

spills;

All drainage in areas where fuel is stored or used will be routed through an oil interceptor before discharge to the TMF. Oily contaminated runoff water will be

collected at source and transferred to the TMF (via pipeline or channel). Discharge of oily contaminated water into the receiving environment without prior

treatment will be banned;

Grease and oily wastes (e.g. waste oils, lubricants, oil filters and oily rags) will be collected at source and immediately transferred to the grease and oil waste

storage facility. Waste oil, lubricants and oil filters will be recycled, where possible;

Truck washdown area will be paved with surface water diverted to a collection sump. Hydrocarbon contaminated sludge from the sump (<10 m3 per week)

will be volatilised and then buried in a lined landfill facility (as per SOP7.12). Treated wastewater (e.g. from oil / water separator at the sump) will be used for

dust suppression on haul roads;

Project vehicles/equipment will be checked regularly for any leaks (to be addressed immediately);

Project vehicles and equipment will be parked on sealed surfaces during non-operation, where possible;

Page 275: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 263

I.D. No. Measures for hazardous materials management Applicable for

C* O D*

Safety, fire and accidental spill procedures and ‘No Smoking’ signs will be posted clearly in strategic locations wherever fuel is handled or stored; and

Containment facilities will be checked on a regular basis to ensure their effectiveness.

SOP7.20 Ensure personnel are adequately trained in hydrocarbon storage, handling, spill prevention, and spill treatment measures with appropriate personal protective

equipment (PPE) provided. Stock adequate volume of hydrocarbons spill kits (e.g. Sorbex) in readily accessible locations where hydrocarbons are stored or handled.

EXPLOSIVES HANDLING AND STORAGE

SOP7.21 Store explosives in appropriately designed facility within an ‘explosives magazine storage area’. The facility must ensure the following measures are met:

Sufficiently located away from populated structures, frequently used areas and other utilities;

Designed, constructed and operated in accordance with AS 2187 – Explosives – Storage, Transport and Use. (Current 1998 ed.). As a minimum, the

magazine will be fully bunded/mounded and weatherproof, with appropriate earthing and lightning protection safety considerations provided;

Facility is fully secured with fencing, lock and 24 hour security, and access is restricted to authorised staff only;

Explosives inventory will be maintained and use of high explosives will be minimised (use of ANFO will be preferred);

Incompatible materials (e.g. detonators and dynamite) will be stored in separate facilities;

Adequate fire safety equipment, emergency management plan and procedures and employee training will be in place;

Regular stock takes and inspections will be conducted;

Fire break in place to prevent bushfires; and

Boxes containing explosives clearly labelled with an ‘explosive’ sign and appropriate posters (e.g. ‘No Smoking’) and MSDS will be provided.

SOP7.22 Maintain a log book at the facility to register movements of the explosives stored onsite (recording quantity, name of visitor/user and date).

CONCRETE WASTE MANAGEMENT

SOP7.23 Manage concrete waste in line with good industry practices to avoid potential discharge into the receiving environment by:

Providing appropriate concrete waste management facilities and training for employees and contractors;

Properly storing concrete and cement materials in adequate storage containers undercover;

Collecting and properly disposing of aggregate concrete wastes; and

Page 276: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 264

I.D. No. Measures for hazardous materials management Applicable for

C* O D*

Washing concrete-coated vehicles or equipment in designated washbay areas away from nearby waterways and wetlands, with primary and secondary

containment facilities installed to ensure contaminated wash water is captured and appropriately managed, e.g. transfer to a temporary pit or level bermed

area where the concrete can set and water can evaporate or be treated.

HAZARDOUS SPILL AND CONTAMINATED SOIL MANAGEMENT

SOP7.24 Personnel will be trained in the emergency preparedness and response protocols, and contractors to develop Emergency Preparedness and Response Plans that will

detail proper training requirements, storage and handling procedures, emergency spill clean-up requirements, etc.

SOP7.25 Ensure contracted dangerous goods and hazardous materials transporters are adequately prepared for emergency response and have detailed hazardous materials

transport plans (e.g. cyanide transport plan) and detailed risk assessment in place.

SOP7.26 In the event of a spill or leak of hazardous materials, the following procedure will be followed, as a minimum:

First person to notice the spill/leak will immediately notify nominated persons (i.e. the Company’s Environment Department) and authorities (depending on the

size, nature and scale of the spill/leak). Surrounding people will also be warned immediately (e.g. verbal notification, alarm, siren), particularly if there is a

health danger;

The spill/leak will immediately be contained, secured for restricted site access, and cleaned up by appropriately trained staff with PPE and spill clean-up kits;

Depending on the size of the spill, a sand berm or dike may be constructed to absorb the discharge if secondary containment should fail;

Avoid or minimise amount of water used to clean up spills on paved surfaces, and ensure contaminated water is captured and disposed of appropriately (refer

to above);

Properly dispose of materials used to clean-up spill/leak (e.g. contaminated soil from chemical or oil spills) in accordance with current national and

international regulations and SOP7.12 (which provides details on disposing of hazardous wastes); and

The Company’s Environment Department will be notified as soon as possible if the amount of discharge is sufficient to be reportable or if the discharge is

accidentally released into the receiving environment, for further spill response and management.

SOP7.27 Maintain a contaminated site register that tracks contaminated sites at the Project site, including accurate GPS coordinates of the location, type of contamination,

estimated volume, and any action taken to remediate. Prior to ground disturbance, check if any planned works will affect a contaminated site by reviewing relevant

historical records and databases.

HAZARDOUS MATERIALS AND DANGEROUS GOODS MONITORING

SOP7.28 Develop and maintain the detailed hazardous materials and dangerous goods monitoring programme for the Project up-to-date to ensure compliance with relevant

national and international guidelines. Key monitoring procedures include:

Page 277: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 265

I.D. No. Measures for hazardous materials management Applicable for

C* O D*

Regular (e.g. weekly) inspections of hazardous materials storage areas/containers/pipelines/flange seals to check their condition (for potential leakage or

seepage) and visually observe workforce compliance with established procedures to ensure preventive measures are effective and adequately employed;

The Company to undertake regular inspections to monitor the success and compliance of waste management strategies onsite according to key performance

indicators (e.g. use of appropriate containers for waste, beneficial reuse or recycling, and waste reduction);

Annual audits of hazardous materials and dangerous goods stored, handled and transported for the Project. Relevant site management plans and

procedures will be updated, where required;

Review of annual reportable incidents of accidental hazardous material spills and contaminated sites register to determine if additional preventive measures

for hazardous materials management are required;

Continuously measure usage rates per unit operation of cyanide, elution and detoxification reagents and diesel to reconcile with the records of amounts

delivered and stored onsite through delivery receipts and stock takes. Minimise the amounts of hazardous materials are stored, where possible; and

Investigative monitoring for related complaints through the Project grievance management system and implementation of remedial actions accordingly.

* C = Pre-Construction/Construction; O = Operations; D = Decommissioning/Closure

Page 278: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 266

SOP08: Blasting Management

Blasting of ore and rock for construction and mining activities will generate fly rock as well as significant noise and vibration (ground and airborne) emissions through the areas

surrounding the blast area. The blast contractor will prepare a Blast Management Plan prior to construction that is specific to the Project conditions and incorporates the below

management measures, where relevant. All blasting activities for the Mako Gold Project will be undertaken in accordance with the Blast Management Plan.

I.D. No. Measures for blast management Applicable for

C* O

*

D

*

BLAST MANAGEMENT

SOP08.1 Consider the following good industry practice measures in the blast design and procedure:

Only staff and contractors appropriately trained in handling and using explosives will be permitted to conduct blasts following rigorous training and review of

competency;

Ensure no explosive charge per blast hole exceeds the estimated maximum charge weight per delay;

Check that the charge is able to break and displace its burden with reasonable ease;

Verify that burden distances are not too small;

Ensure premature ejection of stemming columns does not occur;

Place inter-row delays long enough to give good progressive relief of burden. Consider using delayed/micro delayed electronic detonators, where practicable;

Detonate cord trunklines to fire pre-split blasts and ensure these trunklines have a core load of only 5 g/m ad are covered by at least 250 mm of sand or fine

screenings;

Ensure blast pattern designs and powder factors are sufficient to provide the required fragmentation while minimising the potential to cause damage to pit walls

and infrastructure.

SOP08.2 Blasts will be conducted no more than one blast during the daytime between 9 am and 5 pm, preferably in the afternoon at regular intervals to reduce startle factor.

Detonate only one charge per delay.

SOP08.3 Blasts will be conducted during favourable weather conditions, where practical (e.g. avoid periods of dry and windy conditions, Harmattan winds).

Page 279: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 267

I.D. No. Measures for blast management Applicable for

C* O

*

D

*

SOP08.4 Implement additional management measures relevant to blasting from the various SOPs and management plans developed for the Mako Gold Project, including dust,

noise and vibration control measures specified in SOP04: Emission and Dust Control and SOP05: Noise and Vibration Management.

BLAST HEALTH AND SAFETY

SOP08.5 Incorporate the following health and safety measures prior to any blasts conducted for the Project:

Blasting will be no closer than 500 m from an existing dwelling / structure without prior consultation and approval by a directly affected landowner;

Enforce a 500 m radius exclusion zone;

Secure site perimeter with security personnel (e.g. block access roads, exit/entry points, fencing and signage);

Use sirens or amplified verbal warnings to notify nearby people of the imminent blast; and

Survey the blast exclusion zone to ensure it has been cleared of unauthorised people or potential hazards (e.g. vehicles, hydrocarbon containers, etc.).

SOP08.6 Monitor flyrock visually to confirm that the exclusion zone is sufficient to protect sensitive receptors (i.e. biological and social). A record of any flyrock that travels more

than 200 m will be kept, with an investigation on how this occurred. Review any reported structural damage from blasting activities.

SOP08.7 Train Project staff on fly rock safety and conduct a public education programme regarding community safety issues associated with blasting.

SOP08.8 Drill and blast procedures will be designed by blasting specialists to ensure the safety of the mine workforce and surrounding local population, the control of flyrock,

noise and vibration. Procedures will be periodically re-assessed to confirm the effectiveness of blast management strategies.

COMMUNICATION FOR BLASTING

SOP08.9 Establish a blast schedule plan and communication protocol whereby nearby villagers and Project personnel receive sufficient prior notification. Notification will be

conducted via the following methods:

Ongoing village consultation and posters in villages with blasting dates / times or notification of blasting schedule at least 24 hours in advance of scheduled blast;

Appropriate signage in French located near the blast area; and

Use of a sounding horn to warn people in the area of impending blast (e.g. sounded 15 minutes and 5 minutes in advance of blast).

BLAST CONTRACTOR MANAGEMENT

SOP08.10 Select a blast contractor using the following criteria:

A licensed and competent blast contactor that has sound reputation and track record with respect to blast practices;

Page 280: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 268

I.D. No. Measures for blast management Applicable for

C* O

*

D

*

Proposed blasting practices are consistent with good industry standards;

Contractor’s staff are trained and competent; and

All relevant safety systems and procedures strictly followed.

SOP08.11 Employ blasting experts on a regular basis to audit and provide specialist advice on blasting issues.

BLAST MONITORING

SOP08.12 Maintain and update the blast monitoring programme for the Project to ensure compliance with relevant national and international guidelines. Key blast monitoring

requirements include:

Monitor blast results continually to make improvements and inform future blast designs (including extent of flyrock generated, and levels of airblast and vibration

caused) to achieve a ‘Zero incident record’ for blasts;

Visually inspect and monitor for flyrock to confirm that the exclusion zone adequately protects community and worker safety;

Routine monitoring of noise, airblast, ground vibration, and flyrock impacts within 500 m of the blast area on a periodic basis (e.g. when there is a change of blast

location) to determine extent of impact;

Visual observation checks for unauthorised people within the blast area prior to blasting; and

Regular audit of Quality Assurance and compliance processes based on blasting results and practices (by a blasting expert).

* C = Pre-Construction/Construction; O = Operations; D = Decommissioning/Closure

Page 281: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 269

SOP09: Land Clearance and Soil Stockpiling

Detailed site procedures and a CEMP will be developed by the Construction Contractor and the Company for the Mako Gold Project prior to pre-construction commencing, which

will detail the appropriate management and mitigation of Project impacts associated with land: including social aspects for Project compensation/restoration of temporary and

permanent land, assets and livelihood losses; and consultation with directly affected people and other relevant stakeholders. These procedures will incorporate the environmental

management and mitigation measures and strategies listed below for land clearance, soil resources and progressive rehabilitation management.

I.D. No. Measures for land clearance and stockpiling management Applicable

for

C

*

O

*

D

*

MINIMISATION OF SOIL AND VEGETATION DISTURBANCE

SOP09.1 Plan topsoil stripping, stockpiling and management prior to ground disturbance works commencing (preferably in dry periods) and avoid long periods of disturbed land

remaining unstable. Avoid conducting significant land clearance during the rainy season, where possible.

SOP09.2 Implement the following land clearance procedure for the Project (where appropriate):

Further consultation will be conducted through established consultation groups in advance with local villages/settlements regarding current land uses, and social

and cultural assets in the area to identify cultural, land and livelihood sensitivities; ;

The compensation process for any Project affected person will be in accordance with the Project Livelihood Restoration Plan (LRP) (Volume D);

Vegetation clearance will be conducted during the dry season and confined to the minimum area required for safe operations to reduce the potential for dust,

erosion and sediment transport. Where practicable, vegetation will be retained in steep areas and riparian corridors, or at least preserved in situ as long as

possible up until clearing is unavoidably required;

Temporary land disturbance (e.g. for construction laydown areas, site access, stockpiles) will be carried out in previously disturbed areas, where possible;

Prior to clearance, commercial forestry timber inventories will be determined by the Department of Water and Forests (Département des Eaux et Forêts) to

calculate the total loss of commercial timber and any applicable forestry taxes (note the Company will be exempt from paying forestry taxes under a current

Exploitation Permit);

Any commercially valuable timber will either be salvaged or compensated (where salvaging is not possible). This will be coordinated with the Department of Water

and Forests (Département des Eaux et Forêts) using local licensed logging contractors. Project affected communities will also be allowed to collect traditional

Page 282: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 270

I.D. No. Measures for land clearance and stockpiling management Applicable

for

C

*

O

*

D

*

forest resources (e.g. firewood, non-timber forest products), wherever possible;

Areas scheduled for land clearance will be clearly demarcated in advance and personnel informed that any activities outside the designated areas will be strictly

forbidden except for entry and exit along designated access routes;

Vegetation and topsoil removal will be minimised to the extent practicable by retaining trees and vegetation or clipping tree branches rather than complete removal

of trees (particularly along Project roads). If possible, retain roots in the ground to reduce erosion and to facilitate rapid revegetation;

An ecologist will be on call during habitat clearance work to provide assistance / advice regarding any biodiversity issues if required;

Progressive clearing of vegetation in a controlled manner (to allow mobile fauna to move away from clearance areas) giving priority to manual clearing near

sensitive vegetation, steep terrain, and along local waterways. Machinery and chemical clearance will be strictly supervised to ensure safe working conditions;

Progressively rehabilitate landforms from temporarily impacted areas that will not be required at a later stage, including buffer areas required for construction

equipment (e.g. road embankments, access for construction equipment, etc.);

Salvage stripped topsoil (topsoil removal to a depth of 10 cm) and subsoil, where feasible, in stockpiles for future reuse, and windrow cleared vegetation

stockpiles for later reuse in mulching / chipping or as an erosion control. Ensure stockpiles are managed to prevent spread of fire or collapse in accordance with

SOP09.7 and 9.8 below;

Soil seed bank in the topsoil will be preserved for future rehabilitation, to maintain local genetic diversity;

Stabilise any cleared areas in areas prone to erosion (e.g. steep terrain, near waterways or wetlands) as a priority by covering with wood chippings or grass

matting;

A land disturbance permit system will be established and any necessary land disturbance permits to be obtained in advance from the Company Environment

Department. The permit system will include the following key aspects:

» Proposed location and area of vegetation to be cleared;

» A site map indicating the boundaries of the area to be cleared, designated site access entry/exit routes, and clearly marked ‘No Go Areas’ for sensitive

residential, cultural and environmentally areas to avoid where feasible;

» Timing and duration of land clearance activities;

» Consideration of potential impacts associated with biodiversity, visual amenity, noise and dust nuisance, water quality, and future rehabilitation of the cleared

Page 283: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 271

I.D. No. Measures for land clearance and stockpiling management Applicable

for

C

*

O

*

D

*

areas;

» Consideration of potential impacts associated with cultural heritage, current land use, community and livelihood use of the cleared areas;

» Proposed means for planned mitigation (if applicable) and compensation requirements;

» Written approval or permit for forestry clearance issued by the relevant government authority;

» Proposed means for handling and reusing cleared vegetation and topsoil; and

» Authorised signatures of the Company’s nominated person of authority.

SOP09.3 Ensure acid sulphate soils (ASS) surveys are carried and an ASS management plan implemented in advance, where required.

SOP09.4 Provide employee training and awareness programmes for all Project staff and contractors (e.g. through staff inductions) focusing on improving their understanding of the

importance of threatened fauna and flora as well as forest resources for local communities. Communicate the Project ban (and associated penalties) that applies

regarding harvesting and collecting forest resources (including timber and non-timber forest products) and hunting, trading and buying of wildlife.

SOP09.5 Invasive weed spread will be minimised by implementing the following preventative controls:

Use of local non-invasive plant species for revegetation purposes; and

Compliance with the washdown procedures for vehicles and equipment entering worksites and site access control (refer to SOP07.18-20 and SOP09.9).

SOP09.6 Where appropriate, implement additional measures specified in SOP01: Erosion and Sediment Control, and the Project Biodiversity Action Plan (Volume C).

SOIL STOCKPILE MANAGEMENT

SOP09.7

Soil stockpiles will be constructed and managed following the below procedure, as appropriate:

Soil overburden will be stockpiled for use in later rehabilitation of mined-out areas;

Stockpiles will be located within designated soil stockpile areas where movement of vehicles and equipment are excluded and up-slope (at least 20 m away) from

local waterways and flood inundation areas;

Soil overburden will be stripped from all pit and waste rock dump areas during the dry season immediately prior to major earthworks, where feasible. Wherever

possible, overburden will be stripped and immediately placed on rehabilitation areas in the same area of the operation;

Where this proves impractical, topsoil and subsoil will be stockpiled separately;

Page 284: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 272

I.D. No. Measures for land clearance and stockpiling management Applicable

for

C

*

O

*

D

*

Soil overburden dumps will be formed with as little compaction as possible in mounds generally no more than 2 m high (for topsoil) and 5 m high (for subsoil) to

minimise losses to erosion. These stockpiles will be formed on flat ground, surrounded by low bunds and/or additional erosion and sediment control facilities that

will be constructed prior to the onset of the rainy season;

Slope ratios will be no more than 2:1 (horizontal/vertical);

Stockpiles will be stabilised with revegetation, grass matting or other appropriate controls if they are to remain bare for more than 3 months, particularly in the

rainy season;

Compaction of stockpiles will be avoided as this will hinder establishment of stabilising vegetation;

Location of soil stockpiles and batters will be geo-referenced and mapped in a GIS database with details on type of material and duration of stockpiling recorded;

Stockpiles to avoid visually unobtrusive locations, where possible; and

Diversion structures will be installed up-slope of stockpiles and sediment controls (e.g. silt fence) located downslope, to limit the generation of turbid water (refer to

SOP01: Erosion and Sediment Control for further details).

SOP09.8 Implement additional measures specified in SOP01: Erosion and Sediment Control, SOP2: Water Quality and Pollution Management, SOP04: Emission and Dust Control,

to minimise associated stockpile impacts, where appropriate.

SITE ACCESS CONTROL AND INVASIVE SPECIES PREVENTION

SOP09.9 A washdown procedure will be employed to prevent invasive weed spread (particularly for Mimosa pigra), and potential contamination of the receiving environment from

concrete coating and sediment tracking. The procedures will ensure that earthmoving equipment and vehicles will: 1) follow designated ingress/egress routes to control

site access; and 2) be thoroughly checked and cleaned in designated washdown bay areas before entering/leaving main worksites onto public roads and between areas

where Mimosa pigra is confirmed to occur and unaffected areas. Refer to SOP07; Hazardous Materials Management, for design and implementation details of the wash

bay areas.

SOP09.10 Clearly demarcate site access tracks/roads with flagging tape or signage where required, to minimise risk of rutting and erosion and unnecessary damage to road verge.

BORROW PITS AND QUARRIES

SOP09.11 Prioritise reuse of suitable construction waste (e.g. excavated subsoil, waste rock or inert construction rubble) available onsite as fill/gravel material, where possible. An

inventory of suitable materials (and testing undertaken) available onsite will be prepared and maintained.

SOP09.12 Where suitable sand, fill and gravel available onsite is not sufficient to meet Project demands, the Company and its contractors will source additional sand, gravel and fill

Page 285: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 273

I.D. No. Measures for land clearance and stockpiling management Applicable

for

C

*

O

*

D

*

material consistent with the following procedure:

Sand will be sourced from identified borrow areas situated within 5 km of the Project. If required, additional sand to supplement local sand available will be

sourced from a larger source located outside the Mining Concession;

Gravel (including aggregate and rip-rap material) will be sourced from the pre-existing quarry and gravel stockpile identified off the National Road 7, which was

used for the RN7 highway upgrade (preferred site);

Clay-rich material (engineering grade) required (e.g. for WSD and TMF embankment / dam construction / and maintenance and for the TMF HDPE liner) will be

sourced from local borrow areas within 2 km of construction activity;

Use of disturbed areas will be maximised for temporary laydown areas and key extraction areas;

The number of rock and borrow pit cuts will be minimised, where practicable;

Borrow pits and quarries will be slightly raised to promote site drainage, where possible;

Further testing of acid rock drainage (ARD) potential and construction material suitability will be conducted, as necessary;

Only mobile excavators will be permitted to extract fill and other soft materials;

Extraction will not exceed 6 m in depth or penetrate the underlying water table, whichever is the shallower;

Portable crushing plant operation and blasting will be conducted during daytime only, to avoid potential night-time disturbance;

Adequate drainage, erosion and sediment control devices will be installed to reduce sediment-laden runoff into the receiving environment (refer to SOP01, SOP02

and SOP03); and

Relevant environmental management measures detailed in SOP04 to SOP08, SOP10 and SOP11 will be implemented, as necessary.

SOP09.13 If required, identify new locations for borrow pits and quarries in accordance with the following site selection criteria:

As close to the Project and accessible to existing transport infrastructure as possible;

Avoidance of environmentally sensitive areas, known cultural heritage or archaeology sites, residential areas and productive agricultural land (cultivated or fallow),

where possible;

No closer than 500 m from an existing dwelling / structure unless a shorter distance is agreed through community consultation; and

Page 286: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 274

I.D. No. Measures for land clearance and stockpiling management Applicable

for

C

*

O

*

D

*

No closer than 50 m from a watercourse or wetland.

SOP09.14 For any blasting required, adhere to the Blast Management Plan that will be developed for the Project, in accordance with SOP08: Blasting Management.

SOP09.15 For discontinued use of borrow pits and quarries, progressively rehabilitate as soon as possible to final natural landform that takes into account pre-disturbance state,

public and wildlife safety, and community consultation outcomes (see below for further details).

POST-CLEARING MANAGEMENT AND MONITORING

SOP09.16 Disturbed areas will be progressively rehabilitated when feasible as soon as practicable after completion of works, with priority rehabilitation and revegetation undertaken

in high risk areas such as steep slopes and areas close to drainage lines and watercourses. Post-clearing management and monitoring from land clearance will be

undertaken as per the Rehabilitation and Conceptual Mine Closure Plan (Volume E), including:

Landscape disturbed area to reflect natural contours and restore suitable drainage paths;

Ensure re-planting uses indigenous and locally native species that are non-invasive;

Align with the rehabilitation requirements and strategies outlined in the Rehabilitation and Conceptual Mine Closure Plan (Volume E), Biodiversity Action Plan

(Volume C) and Livelihood Restoration Plan (Volume D) for the Project;

Monitor and maintain rehabilitated / revegetated areas to ensure effectiveness of planting and landscaping; and

Employ remedial measures (e.g. replanting dead or damaged trees or other vegetation types), as required.

SOP09.17 Regrowth vegetation will be regularly maintained (e.g. for fire breaks, operational safety purposes) using appropriate methods relative to the site’s environmental

sensitivity. Use of specific herbicides (for weed control) will need to be pre-authorised by the OHS&E Manager, and usage instructions strictly followed. Application of

herbicides will not be permitted during or just before rain events. Mechanical clearing or thinning will generally be preferred to the use of herbicides for vegetation

maintenance in sensitive locations because it is less likely to damage regenerating forest-edge vegetation and soil seed banks. No controlled burning will be allowed

activities for vegetation maintenance.

* C = Pre-Construction/Construction; O = Operations; D = Decommissioning/Closure

Page 287: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 275

SOP10: Cultural Heritage Management

Several cultural heritage surveys conducted for the Mako Gold Project (i.e. in Tambanoumouya) indicated there are no archaeological and culturally significant sites of local and

regional importance identified within the PDA. However, as there is still potential for Project activities to disturb cultural heritage values within the PDA during activities involving

ground disturbance or earthworks, the Company and its contractors will adhere to the below procedures and the CEMP accordingly. The cultural heritage management measures

provided below will be incorporated into relevant documents to ensure direct impacts on sites of international, national or regional cultural heritage significance are appropriately

managed.

I.D. No. Measures for cultural heritage management Applicable for

C* O

*

D

*

CULTURAL HERITAGEMENT MANAGEMENT

SOP10.1 Implement and maintain archaeological and cultural heritage register, management procedures, training, and instructions for employees and contractors in consultation

with a local cultural heritage expert and relevant government authorities.

SOP10.2 Educate and raise awareness of Project employees and contractors on the protection of local archaeological and cultural heritage values to employees and contractors

through mandatory inductions and training.

SOP10.3 Accurately map confirmed sites of cultural heritage or archaeological significance to prevent accidental disturbance and avoid to the extent possible direct disturbance to

these sites for site development and construction. Clearly mark known cultural heritage sites within and adjacent to disturbance areas as ‘No Go Areas’ to restrict

access by employees and contractors.

SOP10.4 Appropriately train all staff and contractors involved in any ground disturbance works on the latest version of the Chance Find Procedure for the Project provided in

Appendix B.

In the event of a find or suspected find of an artefact, human remains or site of cultural / archaeological significance, the Site Supervisor will strictly undertake the

following steps:

1. Immediately halt the ground disturbance works until further instructions from the Company’s Environment Department;

2. Implement the Chance Find Procedure as appropriate;

3. Notify relevant authorities of the find within 48 hours of the find and follow all instructions given by the authority, e.g. Ministry of Culture (Ministère de la Culture)

for human remains;

Page 288: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 276

I.D. No. Measures for cultural heritage management Applicable for

C* O

*

D

*

4. Conduct an investigation of the site in situ in collaboration with archaeologists and/or local specialists and prepare a Chance Find Report, if required;

5. Based on the outcome of the investigation, agree on the best course of action (e.g. if item should be removed or left in situ). Further investigation and

involvement of other government agencies (e.g. Directorate of Cultural Patrimony (Direction du Patrimoine Culturel) may be required, where necessary; and

6. Only allow ground disturbance works to recommence after the Company has been granted written approval by the relevant authority.

SOP10.5 For any unavoidable disturbance to an item or site of cultural / archaeological significance, consult in advance with relevant stakeholders (e.g. relatives of a burial site),

authorities (e.g. local government or Ministry of Culture and experts (e.g. archaeologists and/or local cultural heritage specialists) to inform, discuss and obtain approval

for any proposed management and/or mitigation measures.

The Company will provide appropriate relocation of the artefact or physical cultural resource to an agreed and safe location, or where an item cannot be relocated,

adequate compensation to affected parties in accordance with the Chance Find Procedure (Appendix C) and the Project’s compensation framework.

SOP10.6 Minimise risks of theft and vandalism to cultural sites and illegal trade of artefacts and other historic objects providing evidence of prehistoric human occupation in the

region, by providing adequate fencing and signage to restrict public access.

CULTURAL HERITAGE MONITORING

SOP10.7 Develop and maintain the detailed cultural heritage monitoring programme for the Project to ensure compliance with relevant national and international regulatory

requirements. Key cultural heritage monitoring procedures include:

Regularly monitor the implementation of archaeological and cultural heritage management measures for compliance, and adapt measures as necessary;

Periodically inspect known sites of cultural heritage or archaeological significance within or adjacent to a construction worksite to confirm no accidental

disturbance has occurred;

Continue to document all new archaeological or culturally significant sites and intangible heritage values within the Project Area in a GIS database; and

Investigate with monitoring and management measures as appropriate in response to cultural heritage related complaints through the Project grievance

management system.

* C = Construction; O = Operations; D = Decommissioning/Closure

Page 289: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 277

SOP11: Lighting and Visual Amenity Management

Potential visual amenity impacts from the Mako Gold Project may result from vegetation clearance, land disturbance, establishment of mine and ancillary infrastructure (e.g. access

roads), and night lighting from the 24-hour mine operations. Night lighting may affect local light-sensitive fauna and nearby communities, while landscape change has the

potential to impact surrounding tourism values (e.g. Niokolo Koba National Park). The level of visual and lighting impacts impact is expected to decrease considerably the further

away from villages and tourist sites.

The following table provides measures based on principles outlined in the IFC Mining EHS Guidelines (2007) to address visual amenity and lighting impacts, and will be incorporated

into detailed site procedures (e.g. CEMP) to be developed for the Project prior to pre-construction commencing.

I.D. No. Measures for lighting and visual amenity management Applicable for

C* O

*

D

*

VISUAL IMPACTS MANAGEMENT

SOP11.1 Take into account existing culturally or economically important viewpoints and visually sensitive locations (e.g. tourism areas, mosques, settlements) when planning the

locations of infrastructure and structures, where practicable.

SOP11.2 Commensurate to the landscape sensitivity, the following management procedures will be adopted to ensure infrastructure, access roads, storage areas and other

Project components are designed to minimise visual impact as much as practicable:

Minimise vegetation clearing to the extent practicable;

Use naturally occurring terrain features to conceal Project features, where possible;

Retain existing road and hillside vegetation as a screening buffer for the Project, where possible;

Clip or prune tree branches rather than removing trees (particularly along Project roads) and avoid clearing mature trees from areas that will only be disturbed

temporarily (e.g. laydown areas);

Consider placing Project components such as stockpiles, earth banks and access cuttings as visual barriers to sensitive receptors;

Ensure that construction sites are well maintained and kept tidy;

Progressively rehabilitate cleared areas and revegetate around major Project structures (e.g. Process Plant) to help it blend into the surroundings;

Actively pursue opportunities to reuse excavated material to minimise the length of time spoil is stored in the Project Area;

Page 290: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring Plan

FINAL 278

I.D. No. Measures for lighting and visual amenity management Applicable for

C* O

*

D

*

Utilise low-impact fencing such as wire mesh, rather than palisade or solid fence structures;

Use non-reflective surfaces for roofs, fences and building, and paint Project structures in muted colours in keeping with the local area and vegetation; and

Where relevant, incorporate visual amenity management and mitigation measures in tender documents and contracts with the Construction Contractor(s).

SOP11.3 Prior to construction, consider providing vegetation screening (e.g. significant tree or bamboo planting) around residential areas that are directly impacted by Project site

visibility, as identified through the community consultation process.

SOP11.4 Implement progressive rehabilitation as soon as practicable following disturbance and construction works. Revegetation will be consistent with surrounding landscape

character.

NIGHT LIGHT SPILLING MANAGEMENT

SOP11.5 Take into account locations of light-sensitive sensitive receptors (community and biodiversity) when designing measures to mitigate light spill, particularly for large

permanent facilities and buildings. Position night works lighting to minimise light spillage, e.g. directional lighting and/or shields to minimise spill into external areas.

SOP11.6 Keep site night lighting to the minimum necessary for safety and security. To minimise night-time light pollution and skyglow, consider using shielded lighting, lamps with

timers, or movement sensors to ensure lights are only lit when required.

SOP11.7 Avoid the need for night works in the vicinity of sensitive receptors (community and biodiversity) which are likely to be impacted, where possible.

SOP11.8 Limit light impacts from Project traffic by ensuring headlights are dipped after dark or using hoods, shields, or shorter lighting columns.

VISUAL AMENITY MANAGEMENT POST MINE CLOSURE

SOP11.9 To the extent feasible, land rehabilitation will be undertaken consistent with the surrounding landscape and aligned with the rehabilitation requirements and strategies

outlined in the Rehabilitation and Conceptual Mine Closure Plan (Volume E) developed for the Project.

VISUAL AMENITY MONITORING

SOP11.10 Investigate with monitoring and management measures as appropriate to respond to visual amenity related complaints through the Project grievance management

system.

* C = Pre-Construction/Construction; O = Operations; D = Decommissioning/Closure.

Page 291: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

APPENDIX B

Chance Find Procedure

Page 292: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

APPENDIX C

Monitoring Maps

Page 293: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

Figure A1 Air Quality and Noise Monitoring Sites Utilised for ESIA

Page 294: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL

Figure A2 Water Quality Monitoring Sites Utilised for ESIA

Page 295: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project Environmental and Social Management and Monitoring

Plan

FINAL

Figure A3 Aquatic Biodiversity Monitoring Sites Utilised for ESIA

Page 296: Mako Gold Project - Resolute Mining€¦ · 3.7.1 Assessment of Risk and Priority ... 151 18 REGISTERS OF ENVIRON MENTAL AND SOCIAL MANAGEMENT AND MONITORING MEASURES .....159 18.1

Mako Gold Project

Environmental and Social Management and Monitoring Plan

FINAL 284