Making Electricity Markets Work: The Ontario Industrial Perspective presented to CAMPUT Annual...
-
Upload
hilary-lyons -
Category
Documents
-
view
221 -
download
3
Transcript of Making Electricity Markets Work: The Ontario Industrial Perspective presented to CAMPUT Annual...
Making Electricity Markets Work:
The Ontario Industrial Perspective
presented to
CAMPUT Annual Conference 2005
Mike KuriychukChair, Board of Directors
Association of Major Power Consumers in Ontario (AMPCO)
May 3, 2005
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
2
Who is AMPCO?
The collective voice of large industrial electricity consumers Over 60 member companies with total load over 3000 MW
size range: 5 MW to over 250 MW each wide range of industrial sectors
Fundamental goal: to preserve and enhance industrial competitiveness through appropriate electricity policy in Ontario
Activities: provide policy advice to Ontario politicians on electricity issues provide technical and regulatory advice to the Ministries and
electricity organizations such as IESO, OEB, OPA, OPG, Hydro One provide a clearing house for technical and strategic information
among members
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
3
Outline
Attitude of large industry: market vs. regulatory solution
Ontario electricity history from an industrial viewpoint
Elements that create short-term risk in the hybrid market
What should be the ultimate end-state of the system What mechanism can be used to get there
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
4
What industry is seeking
The lowest practical delivered price of electricity, consistent with reliability, power quality, and environmental sustainability
The effects go beyond just an industrial consumer’s bottom line:
Electricity cost escalation in Ontario is adversely affecting profitability, as well as industrial competitiveness, economic diversity, employment, the balance of trade, and the provincial standard of living
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
5
Drivers towards a market solution
Experience with markets for manufactured products and production inputs
Preference for minimum intervention and the freedom to creatively solve problems
Belief in the economic efficiency of competition and choice
Skepticism in the ability of government and its agencies to solve problems
Distrust of political interventions Memory of excesses under the previous, regulated
Ontario system
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
6
Drivers towards a regulated solution
Realization that market dominance in generation has not been resolved and probably will not be, in the short term
Realization that electricity markets have some characteristics that preclude pure competition
Evidence from other jurisdictions that market solutions for generation capacity do not work
Evidence from other jurisdictions that open market regimes do not necessarily result in lower prices
Positive prior experience leveraging industrial capabilities in the regulated Ontario environment, for example, various interruptible rates
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
7
Outcome of this balance of opposing forces
Industry favours open market solutions as the preferred choice, but tempered by practical considerations:
Market solutions where possible, with minimum regulation where necessary
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
8
Electricity history in Ontario through industrial eyes (1)
Relentless cost escalation under former Ontario Hydro regime: went from second-lowest price jurisdiction in Canada to second highest over 15 years
Provincial utility had co-opted its shareholder and its regulator and was effectively out of control
With this history, the breakup of Ontario Hydro and creation of an open market was seen as a welcome change
But there were concerns over: opening the retail market – would unduly complicate the transition decision not to break up OPG into competing companies at the
outset – seen as a compromise and ultimately a problem opening market during a supply shortage – a timing issue
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
9
Electricity history in Ontario through industrial eyes (2)
The market opening process went very well planning, technology, and processes were almost flawless
Short-term price predictability was an operational issue pre-dispatch vs. dispatch prices items hidden in “uplift” (surcharges) Lack of generation transparency
But companies were learning to live with the situation: MPMA/BPPR provided an inherent hedge forward products were available, even though market was thin prices had moderated somewhat in the second year; more
supply was coming on stream from refurbished nukes many companies learned to mitigate risks of the new market
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
10
Electricity history in Ontario through industrial eyes (3)
Intent to further decontrol OPG (the basis of the MPMA) was abandoned, first informally by the PCs, then officially by the Liberals with the creation of the “hybrid” market
Cost overruns on OPG Nuclear are a continuing problem The issue of inadequate new supply needed to be
addressed due to the age of existing generation asset base However, too many decisions are now being driven by
ideology: “coal is bad; natural gas is the answer” “conservation/smart metering/windmills will save the day” insufficient cost/benefit scrutiny of programs, development
processes, renewables technologies
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
11
Risks in the present situation
Coal phase-out will come at the cost of significant price escalation: expect to see additional 20-30% price increase Classical rent-seeking behavior among prospective generators apparent lack of appreciation of the impact of fuel on the
margin --it’s not just an issue of percentage of generation cost escalation may make removal of fixed prices/revenue caps
politically difficult Some moves have been made to limit OPG rate of
return, but upward cost pressure in that organization still needs to be better controlled
Tendency within government and its agencies to adopt solutions with inadequate cost/benefit scrutiny
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
12
Risks in the present situation (cont)
Risk transfer from producers to consumers, through the Net Revenue Requirement with lack of transparency: NRR will be aggregated with other items in the Global Adjustment
Apparent execution issues with the generation RFPs: delays, lack of major players, local opposition some projects don’t fit criteria; additional processes will be needed
Realization in government that socioeconomic disruptions from electricity policy are occurring; uncertainty about what to do about it
Need to address longer term supply-side issues, e.g. next generation nuclear, clean coal, natural gas depletion
“Sovereign risk” (political/regulatory) in Ontario electricity industry is still high by international standards, inhibiting investment
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
13
Desired end-state: principles to follow
A balanced generation portfolio by technology, geography, plant size, ownership, useful life
Market liquidity on both the purchaser and seller side still room for more aggregation on the purchaser side long-term contracts need to play a larger role
Avoidance of risk transfer generation investment and operational risks need to stay with
the generator’s investors Stable policy environment
essential for sound investment planning on both the generator and large consumer sides
Balance of supply-side and demand-side solutions expanded role for industrial Demand Response
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
14
Attention to cost causality avoidance of cross-subsidies between producers and
consumers; between different classes of consumers, etc.
Transparency clear and unambiguous rules disclosure of reasoning for decisions reached opportunity for meaningful input derivation of cost components identified
Desired end-state: principles to follow (cont)
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
15
Some mechanisms to get there
Reconsider the off-coal decision why create additional crises?
Maintain and enhance the life of existing generation assets generally less expensive to maintain than replace will minimize NIMBY and BANANA
Adjust the generation procurement process to include opportunities that did not fit into the previous RFPs examples: industrial cogeneration, district heating establish an “evergreen” or open season process for projects maintain environmental standards and verify proponent
credibility on all proposals avoid arbitrary or ad-hoc solutions
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
16
Some mechanisms to get there (cont)
Monitor and control market power to avoid supra-normal profit levels
Maintain effective regulation of natural monopoly elements
Provide minimum levels of incentives for new generation
Assess the cost implications of fuel choices, technologies, and other concepts and ideas
Adopt the experience and best practices of others
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
17
Conclusions
Original intention to deregulate Ontario electricity market was the right move for its time
Some execution problems got us into the present “hybrid” state
Long-term goal should still be as much competition as possible, tempered by practicality
In the short term, cost escalation is still a major concern and must be controlled by addressing all components
Attention to fundamental principles will help us manage our way through this transition state
Presentation to CAMPUT 2005 ConferenceMay 3, 2005
18
Contact Information:
Mike Kuriychuk, Chairman, Association of Major Power Consumers in Ontario162 Cumberland Street, Suite 305Toronto, ON M5R 3N5
Web Site: www.ampco.org
Direct Line: (807) 475-2432
E-mail: [email protected]