Making Changes on the Construction Project

45
Making Changes and Resolving Disputes During The Construction Project Melissa Dewey Brumback Ragsdale Liggett PLLC [email protected] www.constructionlawnc.co m

description

Slideshow discussing AIA, EJCDC, and ConsensusDoc form construction contracts

Transcript of Making Changes on the Construction Project

Page 1: Making Changes on the Construction Project

Making Changes and Resolving Disputes During The Construction

Project   

Melissa Dewey BrumbackRagsdale Liggett [email protected]

www.constructionlawnc.com   

Page 2: Making Changes on the Construction Project

1.  Spells out rights & responsibilities2.  Protects from others' performance3.  Establishs procedure for changes4.  Courts will apply and enforce  

Importance of Contracts

Page 3: Making Changes on the Construction Project

Types of Contracts 

1.  Oral contract        ("handshake") 2.  Proposal or Estimate 3.  Written Contract    a.  Form contract    b.  Other contract  

Page 4: Making Changes on the Construction Project

Types of Change Contracts can address:

1.additional/reduced scope of work2.material spec changes3.defective plans/specs4.poor performance by others5.scheduling changes 6.sequence of work changes7.acceleration/suspension8.unexpected site conditions   

Page 5: Making Changes on the Construction Project

Changes Prior to Contract Execution

 

1.  The Form Contract 2.  Scope of Services

Page 6: Making Changes on the Construction Project

Form Contracts

•  American Institue of Architects (AIA)• Engineering Joint Contracts Doc. Comm. (EJCDC)• Consensus DOCS• Constr. Owners' Assoc. of America (COAA)• Assoc. General Contractors of America (AGC)• Design-Build Institute of America (DBIA)   

Page 7: Making Changes on the Construction Project

Form Contracts

1.Terms well defined2.Familiarity3.Court Decisions4.Not as flexible  

Page 8: Making Changes on the Construction Project

With Every Contract:

• changes of scope?            • notification requirements?• dispute resolution if can't agree?  

Page 9: Making Changes on the Construction Project

Scope of Services

  

• Well-defined• Spell out assumptions• Excluded Services   

Page 10: Making Changes on the Construction Project

Changes During Construction 

 

Page 11: Making Changes on the Construction Project

The Contract "Change" Clause

• Mechanism to deal with change on construction project

• Allows flexibility for site conditions & other unknowns

• In all standard form contracts• Should include in any other contracts

Page 12: Making Changes on the Construction Project

When terms are agreed to: AIA A201 at 7.2.1:    • Written change order signed by owner,

contractor & architect• Specifies money and time adjustments

Page 13: Making Changes on the Construction Project

When terms are agreed to: 

Consensus DOCS 200 at 8.1.2:  • Written change order signed by owner &

contractor only• Specifies money and time adjustments

Page 14: Making Changes on the Construction Project

When terms are agreed to: 

   EJCDC C-700 at 10.03:  • Written change order signed by owner

& contractor upon Engineer's recommendation• Specifies money and time adjustments• Also addresses changes where time/money are

in dispute

Page 15: Making Changes on the Construction Project

When terms cannot be agreed upon:

 AIA A201 at 7.3.3: Construction Change Directive (CCD) • mutual acceptance of lump sum• unit prices stated in contract• cost in "a manner agreed upon"

Page 16: Making Changes on the Construction Project

When terms cannot be agreed upon  (Partial Payment):

 AIA A201 at 7.3.9: • Architect makes interim determination for

monthly certification• Claims can be asserted later

Page 17: Making Changes on the Construction Project

When terms cannot be agreed upon:

 Consensus Docs 200 at 8.2.1 and 8.2.2:    Interim Directed Change Concensus Docs 200 at 8.3.3:  Owner pays 50% of Contractor's estimate pending final determination 

Page 18: Making Changes on the Construction Project

When terms cannot be agreed upon:

 EJCDC C-700 at 12.01.C.2: Directives dealt with in CO process • Payroll and labor: 15%• Payment to subs:  5%    

Page 19: Making Changes on the Construction Project

Authority to Issue Contract Changes:  

 Reserved for Owner Exception: minor changes   

Page 20: Making Changes on the Construction Project

What if there is no signed change order/directive?  May be out of luck  Federal project: definitely out of luck May qualify for equitable theories of relief (i.e., the court may save you from yourself)

   

Page 21: Making Changes on the Construction Project

Exceptions to Written Authorization Requirement: 

 

Implied Authority (principal-agent) Ratification (owner knowingly accepts) Oral Modification to Contract (not on Federal contracts)  

Do NOT rely upon!  

Page 22: Making Changes on the Construction Project

Types of Changes  

 

Page 23: Making Changes on the Construction Project

  Ordered Change v. Constructive Change       

 

Page 24: Making Changes on the Construction Project

Issues with Constructive Changes:  

Cannot be used where express provision applies to the extra work Compensation: based on value to owner, not costs to contractor Document costs to prove  

Page 25: Making Changes on the Construction Project

Requirements for Making CompensableContract  Changes  

 

Page 26: Making Changes on the Construction Project

Notification

  

In writing  (requirement may be waived) As soon as aware! 

Page 27: Making Changes on the Construction Project

Timlieness of Notice

 

14 days  (Consensus Docs)   21 days (AIA)   30 days (EJCDC)   

Page 28: Making Changes on the Construction Project

Documentation of Change

1.description of the changed work 2.number of days the work is extended 3.amount to be compensated 4.signature and date of owner, architect, and

contractor 5.back-up proposals, invoices, tickets, logs,

etc.

Page 29: Making Changes on the Construction Project

Liability Issues  

 

Page 30: Making Changes on the Construction Project

 

Waiver  

Page 31: Making Changes on the Construction Project

Standard of Care

In acceptance with standard of others employed in same profession-- "reasonableness" Indemnity Issues  

Page 32: Making Changes on the Construction Project

Oral Modifications

By conduct or practice Where owner aware and architect orders work  (estoppel)  Again:  Do NOT rely upon!

Page 33: Making Changes on the Construction Project

RESOLVING DISPUTES DURING THE CONSTRUCTION PROCESS  

 

Page 34: Making Changes on the Construction Project

Site Conditions  

• Constructive change 

• Mutual mistake• Cardinal change   

Page 35: Making Changes on the Construction Project

Site Conditions   

Removal of "changed condition" clause   

Page 36: Making Changes on the Construction Project

Disruption

   

Suspension of Work by Owner Discretionary Contract amount and time adjusted

Page 37: Making Changes on the Construction Project

Delay on the Project  

 

Page 38: Making Changes on the Construction Project

Excusable Delay

Not foreseeable   Not controlable ("act of God")   Time extension only 

Page 39: Making Changes on the Construction Project

Compensable Delay

Caused by Fault  Time extension & money Actual damages must be proven  "No damage for delay" provision limits recovery to time only

Page 40: Making Changes on the Construction Project

Compensable Delay:  Indirect Damages

Overhead, interest, profits, rents, equipment idle time, mobilization, increased material costs, etc. Reoverable if not speculative May be limited/waived by contract(Form contracts waive or limit) 

Page 41: Making Changes on the Construction Project

Concurrent Delay

Caused by Fault of more than one party Time extension & money only if allowed by contract Actual damages must be proven   

Page 42: Making Changes on the Construction Project

Delay by other Primes

All contractors owe duty to not delay/hinder any other party Includes design team No need for contractual privity on state multi-prime contracts

Page 43: Making Changes on the Construction Project

Acceleration

Expediting work Trade stacking

Page 44: Making Changes on the Construction Project

Avoiding contract provisions

1.Impossibility2.Mutual Mistake3.Duty to Disclose4.Breach of Warranty (Spearin doctrine) 

Page 45: Making Changes on the Construction Project

    Melissa Dewey Brumback Ragsdale Liggett PLLC Raleigh, North Carolina   919-881-2214 (direct) [email protected]   www.constructionlawnc.com