Project Progress Booklet
Issue 2 Page 1 of 21 01/04/2012
MAJOR WORKS & ENTERPRISE PROJECT PROGRESS BOOKLET
Waterway Unit North Wales and Borders
Canal Llangollen Canal
Functional Location(s) LA-035-002-L Hampton Bank
Notification Number(s) None
Project Title LA-035-002-L Hampton Embankment Stabilisation
Project Number P/09232
AR Number & Project
Expenditure Value
Def AR – N/A
Final AR – A/0007935 Value; £441k
Project Profile Major Works
Project Type MW – D&E Assets
Profit Centre NMHS1
Programme Board Business
Area
Embankments and Culverts
Intermediate/Major Repair Major
Enterprise Manager N/A
Engineering Manager Sally Boddy
Project Sponsor Mark Durham
Project Manager Richard Spencer
Funding Providers Major Works Budget
“Heads of” Review
(Enterprise Only)
N/A
Project Progress Booklet
Issue 2 Page 2 of 21 01/04/2012
Document control:
Revision: Issued by: Project stage: Date:
0.01 Working copy
1.00 Issue 1- EngM’s decision
1.01 Working copy
2.00 Mark Durham Issue 2 - EngM’s assessment
2.01 Project Manager Working Copy
3.00 Project Manager Definition AR
3.01 Project Manager Working Copy
4.00 Project Manager Final AR 24/03/14
5.00 Project Manager Post Project Appraisal
Project Progress Booklet
Issue 2 Page 3 of 21 01/04/2012
Contents
CHAPTER 1 - PROJECT APPRAISAL REPORT ............................................................................................................. 5
1.1 NATURE OF PROJECT.......................................................................................................................................... 5
1.2 DECISION BY ENGINEERING MANAGER .................................................................................................................. 7
CHAPTER 2 – ENGINEERING MANAGER’S ASSESSMENT ......................................................................................... 8
SOLUTION ANALYSIS .................................................................................................................................................. 8
2.1 FURTHER INVESTIGATION .................................................................................................................................... 8
2.2 MONITORING REGIME ....................................................................................................................................... 8
2.3 POTENTIAL MAJOR WORK – OPTIONEERING REPORT ............................................................................................... 8
2.3.1 Option 1 ................................................................................................................................................... 8
2.3.2 Option 2 .................................................................................................... Error! Bookmark not defined.
2.3.3 Option 2 .................................................................................................... Error! Bookmark not defined.
2.4 DECISION ......................................................................................................................................................... 8
2.5 CONSTRAINTS / REQUIREMENTS........................................................................................................................... 9
2.6 PROJECT STAKEHOLDERS ..................................................................................................................................... 9
2.7 RECOMMENDED DESIGN DELIVERY ....................................................................................................................... 9
2.8 WORKS DELIVERY STRATEGY ............................................................................................................................... 9
2.9 EXISTING INFORMATION AVAILABLE ..................................................................................................................... 10
2.10 ENGM FORECAST MAXIMUM LEVEL OF INVESTMENT FOR SELECTED OPTION ................................................................ 10
2.11 PROJECT CATEGORISATION ................................................................................................................................ 10
2.12 CDM............................................................................................................................................................ 10
2.13 RISKS & OPPORTUNITIES .................................................................................................................................. 10
2.14 VOLUNTEER/COMMUNITY INVOLVEMENT ............................................................................................................ 10
2.15 FUTURE MAINTENANCE REQUIREMENTS .............................................................................................................. 10
CHAPTER 3 – PROJECT DELIVERY (DEFINITION) .................................................................................................... 11
DEFINITION APPROPRIATION REQUEST (DAR) ........................................................................................................ 11
3.1 DAR BUDGET REQUEST ................................................................................................................................... 11
3.2 DECISION ....................................................................................................................................................... 11
CHAPTER 4 – PROJECT DELIVERY (IMPLEMENTATION) ......................................................................................... 12
FINAL APPROPRIATION REQUEST (FAR) ................................................................................................................... 12
4.1 PROJECT OUTPUTS/OBJECTIVES ......................................................................................................................... 12
4.2 CHANGE CONTROL .......................................................................................................................................... 12
4.3 CONSTRUCTION TARGET COST ........................................................................................................................... 12
4.4 KEY PERFORMANCE INDICATORS (KPI’S) .............................................................................................................. 13
4.5 MOBILISATION CONSIDERATIONS ........................................................................................................................ 13
4.5.1 Project Team .......................................................................................................................................... 13
4.5.2 Internal Communications ....................................................................................................................... 13
4.5.3 Customer/External Communications ..................................................................................................... 13
4.5.4 Safety ..................................................................................................................................................... 13
4.5.5 Environment & Water Management ..................................................................................................... 14
4.5.6 Heritage ................................................................................................................................................. 14
4.5.7 Consents ................................................................................................................................................. 14
Project Progress Booklet
Issue 2 Page 4 of 21 01/04/2012
4.5.8 Access Arrangements ............................................................................................................................. 14
4.5.9 Delivery Timetable ................................................................................................................................. 14
4.6 RISK MANAGEMENT ........................................................................................................................................ 15
4.7 FINANCIAL INFORMATION ................................................................................................................................. 15
4.7.1 SAP Final cost to completion – all years ................................................................................................. 16
4.7.2 Appropriation Request Value ................................................................................................................. 16
4.7.3 Cash Flow & Budget Request ................................................................................................................. 16
4.7.4 Legal review ........................................................................................................................................... 17
4.7.5 Supplementary Documents .................................................................................................................... 17
CHAPTER 5 – REVISED APPROPRIATION REQUEST ............................................................................................... 18
5.1 REASONS FOR REVISED AR ................................................................................................................................ 18
5.2 FINANCIAL INFORMATION ................................................................................................................................. 18
CHAPTER 6 – POST PROJECT APPRAISAL .............................................................................................................. 19
6.1 PROJECT MANAGER’S REPORT ........................................................................................................................... 19
6.2 REVIEW AGAINST THE BUSINESS CASE ................................................................................................................. 19
6.2.1 Benefits achieved to date & residual benefits expected ........................................................................ 20
6.2.2 Variation from the approved Business Case .......................................................................................... 20
6.3 REVIEW OF THE PROJECT OBJECTIVES .................................................................................................................. 20
6.4 REVIEW OF TEAM PERFORMANCE ....................................................................................................................... 20
6.5 LESSONS REPORT ............................................................................................................................................ 20
6.6 FOLLOW ON ACTIONS RECOMMENDATIONS (WITH DATES) ...................................................................................... 21
Project Progress Booklet
Issue 2 Page 5 of 21 01/04/2012
CHAPTER 1 - PROJECT APPRAISAL REPORT
1.1 Nature of Project
The Llangollen Canal, links Llangollen at the Western End and terminus of the canal, with the Shropshire Union at Hurleston Junction. As well as boat traffic the canal transports water to Hurleston Reservoir. This accounts for a significant part of the contribution to the reservoir and attracts a contribution of £1M per annum. Consequently a penalty is levied when the water supply is disrupted, for example, by a stoppage, unless the water supply is maintained through some other method. There are works already planned at Whixall Moss and Morris’ Embankments where the latter has badger infestation. This booklet refers to Hampton Bank Embankment, where recent activity from burrowing animals has weakened the structure and caused leaks to form. The result has been loss of fines through internal erosion and a significant depression consequently opening up on the crest.
Badger activity has been identified and continues to be monitored, this monitoring highlighted the current condition and concerns. Hampton Bank has breached previously (December 2004) , possibly as a consequence of badger burrowing, and has an anecdotal and documented history of breaches including a minor breach 2 years ago on the towpath side. Seapage zones have been identified near the toe and are monitored through AIP. A large void and depression was noted on 17th January 2014 on the crest of the canal and corresponding leakage was found on the face of the Embankment. This was noticed as a direct consequence of successful vegetation management and a full breach was avoided. The nature of the depression strongly suggests badger activity as being the cause and large voids contributing to an apparent sudden failure.
Project Progress Booklet
Issue 2 Page 6 of 21 01/04/2012
Structural piles are installed around the open bend as highlighted on the plan below. Continuation of the existing structural piling at this location is now proposed.
Hampton Bank Embankment has a history of badger activity, however the area currently active is that which is sheet piled. The redundant setts are at risk of collapse, the but the live sett is approximately 70m from the collapsed area described above and at least 15m from the piling works.
Project Progress Booklet
Issue 2 Page 7 of 21 01/04/2012
Location of Embankment
1.2 Decision by Engineering Manager
Based on the information provided, it is recommended that this project is progressed to
protect integrity of the Embankments.
The objectives are prioritised as follows;
1) Reduce risk of failure due to voids from badger presence
2) Minimise disruption to badgers
3) Maintain suitable habitat for badgers without presenting risk to structural integrity
Project Progress Booklet
Issue 2 Page 8 of 21 01/04/2012
CHAPTER 2 – ENGINEERING MANAGER’S ASSESSMENT
SOLUTION ANALYSIS
2.1 Further Investigation
Continue daily monitoring (waterway)
2.2 Monitoring Regime
Daily visiual inspection using notch boards as reference for leakage and observe
movement in Embankment.
2.3 Potential Major Work – Optioneering Report
2.3.1 Option 1
Description:
Undertake emergency works to protect embankment
Advantages/Disadvantages
Returns structural integrity to the embankment and protects against certain failure.
Water control and supply issues. Navigation will be affected.
Specific Risks:
Large investment required without planning. Ultimate cost will be manageable but cost
certainty is low.
Estimated Investment: £175k.
Potential unplanned costs £1.2M
This is a category 1 project as design and specification has been provided.
2.4 Decision
Progress piling as soon as possible.
PU9 piles to match existing. Exisitng are 5m long.
New piles to be 6m long with ongoing consideration following price estimates for longer
piles.
Proposed 100m linear length.
Project Progress Booklet
Issue 2 Page 9 of 21 01/04/2012
2.5 Constraints / Requirements
The following are the key issues/considerations:
Environmental: Badger Welfare.
Water Management: Major piling will require localised dewatering or careful
management and solutions.
Navigational Stoppage: See Water Management.
Provisional Construction Dates: As soon as possible.
A Register of Project Risks, if not already initiated, for the preferred option will be
initiated at the booklet review meeting.
2.6 Project Stakeholders
The following stakeholders should be contacted for further information/support/advice:-
Internal
Wendy Capelle – Waterway Manager
Mark Durham – Lead Engineerand Designer (will review design options and undertake
cost benefit analysis)
Stuart Moodie – Environment Contact
Glyn Stewart – Framework Ecologist
Andy Cawthorne – ESPI
Richard Spencer – Project Manager
External
Local farm owners. To be contacted and verified.
2.7 Recommended Design Delivery
CRT
2.8 Works Delivery Strategy
In consultation with the Project Management and Framework and Programme
Management team a delivery strategy is to be proposed for approval by the Head of
WEPD and Group Procurement Manager as appropriate (ref: Major Works roadmap flow
chart).
Major Works with Omnibus Contractor. See note above regarding contractor design.
Project Progress Booklet
Issue 2 Page 10 of 21 01/04/2012
2.9 Existing information available
PI– Andy Cawthorne on the Asset folder drive.
As built information from 2005 major works project 3417.
2.10 EngM forecast maximum level of investment for selected option
Based on an assessment of the outline scope of work an initial estimated level of
investment of £200k should be assumed for this project.
Engineering Manager’s Maximum Level of Investment (EMMLI) £000’s
Contract Costs 175
Internal Recharges 2.5/10% of contract costs(1) 17
Design/Professional Fees (incl Land Costs) internal
Internal Time 5% of contract costs(2) 8
Risk) -
Scope determination and value analysis allowance of £800k not
included.
Total EMMLI 200
2.11 Project Categorisation
This project should be considered as Category 1.
2.12 CDM
A CDM1.1 form has been initiated by the waterway engineering team. Contact Colin Lowndes.
2.13 Risks & Opportunities
Monitor effect on badgers during emergency phase of works. Employ silent piling techniques..
2.14 Volunteer/Community Involvement
None
2.15 Future Maintenance Requirements
Continued maintenance of the vegetation is essential and should be included as
a safety priority in the GWP for the waterway.
Continued surveillance of the badger activity will be important. At first AIP should
be sufficient, but the waterway and ecology team will need to be prepared to
extend beyond this if required.
Project Progress Booklet
Issue 2 Page 11 of 21 01/04/2012
CHAPTER 3 – PROJECT DELIVERY (DEFINITION)
DEFINITION APPROPRIATION REQUEST (DAR)
Based on the Engineering Manager’s assessment and the emergency nature of the project it was agreed that the project should be progressed direct to Final AR approval. An Emergency AR was approved to allow the construction works to commence (See Chapter 4).
3.1 DAR Budget Request – Not Required
Description of Investment £’000
Internal Recharge (Omnibus)(1)
Framework Contractor
Contractor Services (PSC design)
Internal Time(2)
Etc
Definition Appropriation Request Value (TOTAL)
Income from Third Parties
Net cost to British Waterways
(1) Include £7.5k for cat 1 project or £12.5k for cat 2 project
(2) This AR does not include for any costs associated with the Engineering, Environmental & Heritage Teams within the Technical Directorate. It also does not include any works undertaken through the Investigation Project; see [insert link] for the Investigation AR.
3.2 Decision
N/A
Project Progress Booklet
Issue 2 Page 12 of 21 01/04/2012
CHAPTER 4 – PROJECT DELIVERY (IMPLEMENTATION)
FINAL APPROPRIATION REQUEST (FAR)
At a value of £441k, this AR is submitted for approval by the Technical Director. The AR budget includes an income of £0k, resulting in a net cost to CRT of £441k. This is not in line with the Engineering Manager’s assessment of the maximum level of investment stated in section 2.10 of this project booklet - Section 4.2 below details the changes to the project which have altered the cost. A budget of £274k has already been allocated to the project to enable the contractor to mobilise as soon as possible. The Emergency AR can be found Here
4.1 Project Outputs/Objectives
Stabilise the embankment around the area where the bed of the canal
has fractured and the disused badger sett has collapsed – Length of
piling 100 linear metres
Continue with the installation of structural piles along the embankment
to complete as much as possible within the time constraints – Planned
additional length = 100m
4.2 Change Control
Length of piles have increased to ensure the structural piles toe in to made
ground. New piles vary from 7m to 8m to accommodate the slope in the field at
the toe of the embankment.
Amount of piling has doubled to 200 linear metres to make full use of the site
mobilisation and available closure period.
4.3 Construction Target Cost
There was no time to produce a Target Cost therefore the works are being undertaken
on a cost reimbursable contract. This AR has been produced based on the budget
estimate received from Kier. The budget cost estimate is £349k to install 200 linear
metres of structural piles.
The budget estimate table can be found Here
The budget cost to complete is 79% of the total project cost
Project Progress Booklet
Issue 2 Page 13 of 21 01/04/2012
4.4 Key Performance Indicators (KPI’s)
No specific Employer’s key success criteria for the scheme above are stipulated in the
WIP.
4.5 Mobilisation considerations
4.5.1 Project Team
The Project Delivery Team roles are as follows:
Mark Durham - Project Sponsor / Lead Engineer
Sally Boddy – Engineering Manager
Clive Mitchell – Project Team Manager
Richard Spencer - Project Manager/Clients Representative
David Heys - CDM Coordinator
David Clarkson - Principal Waterway Engineer
Glyn Stewart - Ecologist
Colin Lowndes- Waterway Engineer
Peter Dawson - Principal Contractor (representing Kier)
4.5.2 Internal Communications
The Principal Waterway Engineer David Clarkson, (Lead)Designer Mark Durham and CDM Co-ordinator David Heys have been consulted throughout the development of the scheme, and have all been invited to the site progress meetings. A monthly Progress Report is prepared for all projects to continually inform the waterway of the project status.
4.5.3 Customer/External Communications
A canal stoppage has been put in place from Wednesday 19th February 2014 until Friday
4th April 2014. The stoppage notice can be found Here
The following press release has been issued to regional media and trade press. Link
4.5.4 Safety
This project is a Level 3 (high risk) under BW Direction for Managing Health and Safety
in Construction Work and has been notified to the HSE under the CDM Regulations
2007.
The CDM roles of Clients Representative, (Lead) Designer, CDM Co-ordinator and
Principal Contractor are stated in section 4.4.1 above.
Project Progress Booklet
Issue 2 Page 14 of 21 01/04/2012
The Manager of Contractors under BW Directive Management of Contractors will be
carried out by Kevin Kirkland for Omnibus works.
CDM 1.1 Preconstruction Health and Safety Information can be found Here
CDM 2.3 Significant Residual Risks of design can be found Here
4.5.5 Environment & Water Management
A validated Environmental Appraisal and associated Action Report is located Here
The Action Report is part of the Works Information Package (WIP) issued to the
Contractor.
The significant issues to be managed on the project are:
The Waterway have a contract with UU to supply 45Ml/day of water to Hurleston
Reservoir - This must be maintained throughout the works.
There is a risk of the embankment breaching. The contractor is to install a
temporary clay dam to minimise water loss in the event of a breach.
There is significant badger activity on the embankment
4.5.6 Heritage
The structure is not listed
4.5.7 Consents
A badger disturbance licence is required as there is significant badger acitivity on the
embankment. The licence can be found Here
4.5.8 Access Arrangements
The embankment is on the offside and can only be accessed by waterborne plant. A site
compound is located in a CRT owned layby approximately 300m from the working area.
4.5.9 Delivery Timetable
A construction programme for this project is shown Here
The main construction phase of the project is planned from 19/02/14 to 04/04/14
The canal and towpath will be closed for the duration of the works.
Project Progress Booklet
Issue 2 Page 15 of 21 01/04/2012
4.6 Risk Management
A Register of Project Risks has been developed for this project and is located Here
The Project Manager Risk allowance for the project is £50k, which is 11% of the FAR
budget.
4.7 Financial Information
2013/14 2014/15 Total
£000's £000's £000's
Income
0 0 0
Total Income 0 0 0
Expenditure
CRT Project Management 5 2 7
Omnibus Staff Costs 20 15 35
Contractor Services (May Gurney) 250 99 349
Project budget 275 116 391
Project Manager Risk 0 50 50
Appropriation request value
441
Net Cost To CRT 275 166 441
An Emergency AR was circulated for approval to enable the contractor to
mobilise to site as soon as possible. The AR can be found Here and approval
can be found Here
Note: The works are an emergency therefore the project is being undertaken on a cost reimbursable contract through our Framework agreement with Kier - The final cost may change.
Project Progress Booklet
Issue 2 Page 16 of 21 01/04/2012
4.7.1 SAP Final cost to completion – all years
4.7.2 Appropriation Request Value
£,000
SAP FORECAST COST TO COMPLETION EXCLUDING RISK 391
CONTRACTOR RISK 10% OF PAR BUDGET/ REASONABLENESS CHECK
n/a (as have Target Cost)
PROJECT MANAGER BUDGET 391
PROJECT MANAGER RISK (WILL BE ON SEPARATE GL CODE)
50
APPROPRIATION APPROVAL 441
Final appropriation request approval will be in accordance with delegated authority schedule on gateway: Link
4.7.3 Cash Flow & Budget Request
Year Actual spent to date £’000 Budget required each year
£’000
2013/14 88 275
2014/15 0 116
Project Progress Booklet
Issue 2 Page 17 of 21 01/04/2012
4.7.4 Legal review
Not Applicable
4.7.5 Supplementary Documents
The following documents are included on the project website:
Risk Register
Environmental Appraisal
Works Information Package
Programme
Photographs
Project Progress Booklet
Issue 2 Page 18 of 21 01/04/2012
CHAPTER 5 – REVISED APPROPRIATION REQUEST
5.1 Reasons for Revised AR
As with section 1.1 the Project Manager (PM) describes the nature of the expected
cost overruns & CE’s and why the revised AR is required. This needs to include
where the additional funding is coming from, confirmation of this should be posted
onto the project website
5.2 Financial Information
Please use the financial information table on Sharepoint and copy here using paste
special Picture (Enhanced Metafile) Insert Link to table.
Authorised
AR
Additional
request
Revised AR
Total
£000's £000's £000's
Income
Harlow Council 302 75 377
Harlow Renaissance 50 0 50
Total Income 352 75 427
Expenditure
Design Fees (PSC) 13 0 13
Agency Staff 0 0 0
BW Project Management 13 0 13
Survey/Utility Search Fees 2 0 2
Compensation/Land Access Fees 4 0 4
Omnibus Staff Costs 32 0 32
Contractor Services (May Gurney) 290 114 404
Project Budget 354 114 468
Project Manager Risk 40 0 40
Appropriation request value 394 114 508
Net Cost To BW 42 39 81
Project Progress Booklet
Issue 2 Page 19 of 21 01/04/2012
CHAPTER 6 – POST PROJECT APPRAISAL
Type Project Timescale Financial factor Type of PPA
Low Short term within 3
mths
< £50k Box ticket in SAP – text
comment made if appropriate
Medium Under 12 mths <£250k Short form – maximum 2
pages in bullet point form
High Over 12 mths >£250k Long form – maximum 6
pages in bullet point form
The project timescale is a guide; the overriding factor will be the ‘actual’ cost of the project.
6.1 Project Manager’s Report
(Summarising the project’s performance and confirmation of satisfactory handover to operations and maintenance functions)
6.2 Review against the Business Case
(Summarising the validity of the project’s Business Case)
Please use the financial information table on Sharepoint and copy here using paste special
Picture (Enhanced Metafile) Insert Link to table.
Authorised
AR Actual Cost Variance
£000's £000's £000's
Income
Harlow Council 302 335 33
Harlow Renaissance 50 50 0
Total Income 352 385 33
Expenditure
Design Fees (PSC) 13 20 (7)
Agency Staff 0 0 0
BW Project Management 13 25 (12)
Survey/Utility Search Fees 2 2 0
Compensation/Land Access Fees 4 4 0
Omnibus Staff Costs 32 30 2
Contractor Services (May Gurney) 290 380 (90)
Project Budget 354 461 (107)
Project Manager Risk 40 0 40
Appropriation request value 394 461 (67)
Net Cost To BW 42 76 (34)
Project Progress Booklet
Issue 2 Page 20 of 21 01/04/2012
6.2.1 Benefits achieved to date & residual benefits expected
6.2.2 Variation from the approved Business Case
6.3 Review of the Project Objectives
(Review how the project performed against its planned targets and tolerances for time, cost, quality, scope, benefits and risk.
Consider Safety, Heritage and Environmental aspects.)
Project Objectives (use 4.1 above) Actual
Complete all works in the interest of
safety as identified by panel engineer
as per section 1.1.1 of this project
booklet.
All completed and panel engineer
report received confirming completion.
Fill in depressions in the crest to
prevent ponding
Done
Complete new grazing rights
arrangement with farmer to prevent
animals from accessing the dam
New Agreement signed with farmer on
00/00/00 and stock fencing erected to
prevent animals accessing the dam
With waterway programme in GWP
works and PPM maintenance
requirements
Of the GWP works all are completed
with the exception of x which is
programmed in by the BU in 2011 due
to budgetary constraints.
Target cost £ Delivered £
Project manager risk planned £x Project manager risk utilised £ywhich
represents z%
Delivery date Project completed 5 days ahead of
schedule
Customer complaints One external complaint relating to
communications of road closure
6.4 Review of Team Performance
(Provide recognition for good performance)
6.5 Lessons Report
Project Progress Booklet
Issue 2 Page 21 of 21 01/04/2012
(Review what went well, what went badly, and any recommendations for corporate or programme management consideration.
Link to the issues log where relevant)(list any key productivity rates)
6.6 Follow on Actions Recommendations (with dates)
(Refer follow on actions to Programme Board or Sponsor for advice on who should receive each recommended action. The
recommended actions are related to unfinished work, on-going issues and risks, and any other activities needed to take the
products to the next phase of their life)