Maintenance Management Assignment
-
Upload
viswanatha-sastry -
Category
Documents
-
view
161 -
download
9
description
Transcript of Maintenance Management Assignment
OM 315: MAINTENANCE MANAGEMENT
Page 1 of 50
Station: Visakhapatnam
Identity No. 10MB00199
Learner name D. SREENIVASA RAO
Mobile number 9032984120
Programme MBA
Group General
Paper name (Subject 315 - MAINTENANCE MANAGEMENT
Year/Semester III Year
Study Center CDL-GITAM, Visakhapatnam
OM 315: MAINTENANCE MANAGEMENT
Page 2 of 50
ASSIGNMENT – I
1. Explain in brief functions, objectives and types of maintenance.
Answer
MAINTENANCE OBJECTIVES:
The objectives of maintenance are to ensure the desired plant availability at
an optimum cost within the safety prescription. In other words, it may be mentioned that the objective of maintenance is to minimize the total cost of
unavailability and resources.
Whenever the plant is not available either due to breakdowns or due to planned stoppages, the following costs are incurred.
1. Loss of earnings due to stoppage of equipment 2. Loss of in service materials.
In addition the following costs are incurred on resources: Labor of overhead expenses
Materials in spares and consumables
Cost of storage of spares and facilities.
Hence, maintenance functions are so, organized as to minimize the total cost
of unavailability and resources.
MAINTENANCE FUNCTIONS
The above mentioned objectives are attained by taking certain action
illustrated below:
Action Purpose
Lubrication
Cleaning
Adjustments Return or slow down the process of deterioration or wear
Application of Protective coating
Examination of the state of the
components
Assess the extent of wear and
determine, on that basis, the action required to check a break-down and
the time when such action should be
taken
Analysis of history of behavior of the
machine and its components
Replacement of worn out component
Repair of cracks or other repairable damages
Restore the original operational capacity of the machine and prevent
further damage
Modification of design of the
components or location of the equipment
Affect improvements to reduce the
frequency of attention or to recduce cost of maintaining the equipment.
Capital replacement Replacement of the machine when
OM 315: MAINTENANCE MANAGEMENT
Page 3 of 50
the age of the existing machine
requirement of quality and quantity
of output and emergency of better
machines make it economical to dislodge the present and install a new
machine.
In these, the first four steps are taken with the sole purpose of reducing
friction, wear and effects of environment on the individual parts of a machine.
For example, lubrication reduces friction; cleaning prevents corrosion and
abrasion due to dust; adjustment of level or alignments or by tightening the loose bolts and nuts eliminates undue stresses; and preventive coatings
guard against rust and corrosion. These action increase the useful life of
parts and therefore, constitute an intrinsic part of Preventive Maintenance.
The next two steps, inspection of parts and analysis of history, are meant to
assess the condition of the part, the extent of wear, the action required to remedy the defect and the time when such action should be undertaken.
These activities are undertaken essentially to be able to plan the remedial
measures.
Inspection can be external for abnormal sound or temperature which does
not require a stoppage of the machine. It could even be internal, requiring a
machine to be stopped either purely for inspection or at the time of some other repair or during overhauling of the machine. Historical data on the
other hand, is a chronological record of repairs and replacements carried out
on a machine during its life in the company. Analysis of such a record helps
to estimate the life span of various components and establish the frequency of inspections, repairs, and replacements.
Replacement and repair of components can be undertaken on the basis of inspection reports, analysis of history or complaints of operating personnel.
Another important part of maintenance is the change in some characteristics
of the components which gives frequent trouble, to avoid re-occurrence of that trouble with that frequency. Such an action is taken on the basis of
history of the equipment and evaluation of costs involved. This step can be
defined as "Maintenance Prevention". Cost of maintenance of the machine
rises with the increase in its age. Moreover, passage of time also affects the operational efficiency of the machine. Requirements of quality and quantity of
production go through a change making an old machine more or less obsolete
in relationship to the new demands.
New and better machines emerge in the market. All these factors make it
necessary to replace the existing machines at some stage in their lives by new machines. Maintenance is vitally linked with such action. Analysis to
determine the economics in replacement of machines and their physical
installation, therefore, becomes a responsibility of the maintenance
personnel.
OM 315: MAINTENANCE MANAGEMENT
Page 4 of 50
MAINTENANCE TYPES
A. BREAKDOWN MAINTENANCE
Characteristics of Break-down Maintenance System:
No services except occasional lubrication unless failure occurs
No maintenance men on regular basis Maintenance done by sub-contractors
No organized efforts to find out reasons
No stock of spares No budget
No records
Initially it looks economical
Problems in case of Breakdown
Who is to do repair?
From where to get parts? How do we pay for them?
Who is to go to buy parts?
Results of Breakdown Maintenance System:
Increased Down Time
Increased costs & Pressures
B. ROUTINE MAINTENANCE
A procedure followed regularly i.e.,., A cyclic operation recurring
periodically.
Advantages
Simple to establish & follow Little or no clerical work
High degree of prevention by intercepting developing faults.
A more advanced stage of routine maintenance calls for 'service
instructions on a pre-printed schedule and checklists'.
Examples:
Check all compressors first on Mondays. Lubricate completely two machines daily.
Disadvantages Routine maintenance may not provide the service specified by the
manufacturer
We may ignore information regarding preceding breakdowns
Service required for a machine at different frequencies may be ignored
All similar machines may be serviced at same frequency
irrespective of working hours.
C. PLANNED MAINTENANCE
In this type of service, the emphasis is placed on the machines.
What does the manufacturer prescribe?
OM 315: MAINTENANCE MANAGEMENT
Page 5 of 50
Is the unit utilized for two, or three shifts per day?
Is it working under normal load?
Are the conditions as good as those envisaged by the manufacturer?
Do we allow for extra attention owing to corrosion-including
conditions?
Characteristics of Planned Maintenance
Instructions are more detailed than in routine maintenance
Calls for differently timed service for the same unit Schedule is drawn with dates
Need for establishing the work-load for the crew
Entails considerable planning effort, faithful implementation and
recording Initial list of planned maintenance will be in detail
Advantages of Planned Maintenance Will take into consideration the changes in conditions of use and
increased wear of parts
Inspections, replacement of parts and adjustments are included in the overall plan
Detailed instructions reduce the chance of missing any activity.
Unforeseen work is greatly reduced
Provides as much attention as the equipment requires - to the best judgment and ability of the planner
D. PREVENTIVE MAINTENANCE System which strives to reduce the likelihood of failures.
To achieve prevention of break-downs Planned service is carried out
with the explicit additional objective of detecting wear points and ensuring perfect functioning by replacing parts which could still be
used were it not for the assurance that is required.
Occasional use of statistical analysis/methods for determining life
expectancies of parts.
The system employs Measuring & Inspection Devices. This phase is
Predictive maintenance.
Preventive Maintenance System is more expensive due to more of
planning and replacement of parts before failing.
Preventive Maintenance increases reliability
Preventive Maintenance reduces total work-load
Preventive Maintenance reduces total down time Preventive Maintenance reduces unplanned work
Preventive Maintenance reduces total maintenance cost
Routine maintenance & Planned maintenance also include Preventive maintenance action.
Preventive maintenance could be grouped as under:
Fixed-time Maintenance Condition-based Maintenance
OM 315: MAINTENANCE MANAGEMENT
Page 6 of 50
Opportunity Maintenance engineering and management
E. Corrective Maintenance: Services carried out to restore an item to an acceptable working
condition. Services arising out of
Break-downs
Malfunctioning & Deteriorating conditions
Productive Maintenance An effort to set up the function on a planned and measured
production pattern. The output relates to the number of servicing
tasks completed, e.g., lubrication, inspection, overhaul, etc.
Originally used in USA.
Total Productive Maintenance (TPM)
Efforts with the total participation of employees. Used in Japan.
2. How do you prepare maintenance planning and scheduling? Explain with an example.
Answer
Planning in the context of maintenance means the process by which all
the elements required to perform a task are determined and prepared
prior to starting the job. Planning is a process of detailed analysis that determines and describes the work to be performed, the sequence of
associated tasks, methods to be used for their performance, and the
required resources – including skills, crew size, man hours, parts, special tools and equipment and an estimate of total cost. It also includes
identification of safety precautions, required permits, communication
requirement, and reference documents such as drawings and wiring
diagrams. It addresses essential preparation, execution and start-up efforts. Work estimates and activation of required procurements are parts
of the planning process.
Basic maintenance planning principles are as follows:
i. The planners are organized into a separate department from the craft
maintenance crews to facilitate specializing in planning techniques as well as focusing on future works.
ii. The planning department concentrates on future work (work that has
not been started) in order to provide the maintenance department at
least one week of work backlog that is planned, approved, and ready to execute. This backlog allows crews to work primarily on planned
work. Crew supervisors handle the current day‟s work and problems.
Any problems that arise after commencement of any job are resolved by the craft technicians or supervisors to the planning department.
After every job completion, feedback consists of any problems, plan
changes, or other helpful information so that future work plans and
schedules might be improved. The planners ensure that feedback information gets properly filed to aid future work.
OM 315: MAINTENANCE MANAGEMENT
Page 7 of 50
iii. The planning department maintains a simple, secure file system based
on equipment tag numbers. The file system enables planners to utilize
equipment data and information learned on previous work to prepare and improve work plans, especially on repetitive maintenance tasks.
The majority of maintenance tasks are repetitive over a sufficient
period of time. File cost information assists making repair or replace
decisions. Supervisors and plant engineers are trained to access these files to gather information they need with minimal planner assistance.
iv. Planners use personal experience and file information to develop work
plans to avoid anticipated work delays and quality or safety problems. As a minimum planners are experienced, top level technicians that are
trained in planning techniques.
v. The planning department recognizes the skill of the crafts. In general,
the planner‟s responsibility is „what‟ and the craft technician‟s responsibility is „how‟.
vi. Wrench time is the primary measure of workforce efficiently and of
planning and scheduling effectiveness. Wrench time is proportion of available-to-work time during which craft persons are not being kept
from productively working of a job site by delays such as waiting for
assignment clearance, parts, tools, instructors travel, coordination with other crafts of equipment information.
MAINTENANCE PLANNING AND SCHEDULING
Effective planning and scheduling contribute significantly to the following: Reduced maintenance cost.
Improved utilization of the maintenance workforce by reducing
delays and interruptions. Improved quality of maintenance work by adopting the best
methods and procedures and assigning the most qualified workers
for the job. Planning and Scheduling Objectives
Minimizing the idle time of maintenance workers.
Maximizing the efficient use of work time, material, and equipment.
Maintaining the operating equipment at a responsive level to the need of production in terms of delivery schedule and quality.
Classification of Maintenance Work According to Planning and Scheduling Purposes
Routine maintenance: are maintenance operations of a periodic
nature. They are planned and scheduled and in advance. They are covered by blanket orders.
Emergency or breakdown maintenance: interrupt maintenance
schedules in order to be performed. They are planned and scheduled as they happened.
Design modifications: are planned and scheduled and they depend on eliminating the cause of repeated breakdowns.
Scheduled overhaul and shutdowns of the plant: planned and
scheduled in advanced.
OM 315: MAINTENANCE MANAGEMENT
Page 8 of 50
Overhaul, general repairs, and replacement: planned and
scheduled in advanced.
Preventive maintenance: planned and scheduled in advanced.
An essential part of planning and scheduling is to forecast future work and
to balance the workload between these categories.
The maintenance management system should aim to have over 90% of
the maintenance work planned and scheduled.
Planning
Planning is the process by which the elements required to perform a task are determined in advance of the job start.
Planning It comprises all the functions related to the preparation of:
a. The work order
b. Bill of material c. Purchase requisition
d. Necessary drawings
e. Labor planning sheet including standard times
f. All data needed prior to scheduling and releasing the work order.
Good planning is a prerequisite for sound scheduling.
Planning Procedures
The planning process comprises all the functions related to the
preparation of the work order, bill of material, purchase requisition, necessary drawings, labor planning sheet, job standards, and all the data
needed prior to scheduling and releasing the work order. An effective
planning procedure should include the following steps:
i. Determine the job content (may require site visits)
ii. Develop a work plan. This gives the sequence of activities in the
job and establishing the best methods and procedures to accomplish the job.
iii. Establish crew size for the job.
iv. Plan and order parts and material. v. Check if special equipment and tools are needed and obtain them
vi. Assign workers with appropriate skills
vii. Review safety procedures
viii. Set priorities ix. Assign cost accounts
x. Complete the work order
xi. Review the backlog and develop plans for controlling it xii. Predict the maintenance load using an effective forecasting
technique.
Basic Levels of Planning Process (Depend on the Planning Horizon)
OM 315: MAINTENANCE MANAGEMENT
Page 9 of 50
Long-range planning: it covers a period of 3 to 5 years and sets
plans for future activities and long-range improvement.
Medium-range planning: it covers a period of 1 month to 1 year. Short-rang planning: it covers a period of 1 day to 1 week. It
focuses on the determination of all the elements required to
perform maintenance tasks in advance.
Long and Medium-Range Planning
Sets plans for future activities and long-range improvement. Needs to
utilize the following: Sound forecasting techniques to estimate the maintenance load.
Reliable job standards times to estimate staffing requirements.
Aggregate planning tools such as linear programming to determine
resource requirements.
Medium-Range Planning
Specify how the maintenance workers will operate. Provide details of major overhauls, construction jobs, preventive
maintenance plans, and plant shutdowns.
Balances the need for staffing over the period covered. Estimates required spare parts and material acquisition.
Short-Range Planning
It focuses on the determination of all the elements required to perform maintenance tasks in advance.
Scheduling Maintenance scheduling is the process by which jobs are matched with
resources and sequenced to be executed at certain points in time. Basic
maintenance scheduling principles are as follows:
i. Job plans providing number of persons required, lowest required
craft skill level, craft work hours per skill level and job duration
information and necessary for advance scheduling. ii. Weekly and daily schedules must be adhered to as closely as
possible. Proper priorities must be placed on new work orders to
prevent undue interruption of these schedules. iii. A scheduler develops a one week schedule for each crew based on
a craft hours available forecast that shows highest skills levels
available, job priorities, and information from job plans. iv. The one week schedule assigns work for every available work hour.
The schedule allows for emergencies and high priority, reactive jobs
by scheduling a sufficient amount of work hours on easily
interrupted tasks. Preference is given to completing higher priority work by under-utilizing available skill levels over completing lower
priority work.
v. The crew supervisor develops a daily schedule one day in advance using current job progress, the one week schedule and new high
priority, reactive jobs as a guide.
vi. Wrench time is the primary measure of work force efficiency and of
planning and scheduling effectiveness. Work that is planned before assignment reduces unnecessary delays during jobs and work that
OM 315: MAINTENANCE MANAGEMENT
Page 10 of 50
is scheduled reduces delays between jobs. Schedule compliance is
the measure of adherence to the one week schedule and its
effectiveness.
Is the process by which jobs are matched with resources and sequenced
to be executed at a certain points in time. Scheduling deals with the
specific time and phasing of planned jobs together with the orders to perform the work, monitoring the work, controlling it, and reporting on job
progress. Successful planning needs a feedback from scheduling.
Reliable Schedule Must Take Into Consideration
A job priority ranking reflecting the criticality of the job.
The availability of all materials needed for the work order in the
plant. The production master schedule and close coordination with
operation.
Realistic estimates and what is likely to happen rather than what scheduler desires.
Flexibility in the schedule.
Maintenance Schedule Can be Prepared at Three Levels (Depend on The
Time Horizon)
Long-range (master) schedule
Weekly schedule Daily schedule
Long-Range (master) Schedule Covering a period of 3 months to 1 year.
Based on existing maintenance work orders (blanket work order,
backlog, PM, anticipated EM). Balancing long-term demand for maintenance work with available
resources.
Spare parts and material could be identified and ordered in
advance. Subject to revision and updating to reflect changes in the plans and
maintenance work.
Weekly Schedule
Covering 1 week.
Generated from the master schedule. Takes into account current operations schedules and economic
considerations.
Allow 10% to 15% of the workforce to be available for emergency
work. The schedule prepared for the current week and the following one
in order to consider the available backlog.
The work orders scheduled in this week are sequenced based in priority.
CPM and integer programming techniques can be used to generate
a schedule.
OM 315: MAINTENANCE MANAGEMENT
Page 11 of 50
Daily Schedule
Covering 1 day.
Generated from weekly schedule. Prepared the day before.
Interrupted to perform EM.
Priorities are used to schedule the jobs.
Elements of Sound Scheduling
Requirements for effective scheduling:
Written work orders that are derived from a well-conceived planning process. (Work to be done, methods to be followed, crafts
needed, spare parts needed, and priority).
Time standards.
Information about craft availability for each shift. Stocks of spare parts and information on restocking.
Information on the availability of special equipment and tools
necessary for maintenance work. Access to the plant production schedule and knowledge about when
the facilities will be available for service without interrupting
production schedule. Well-define priorities for maintenance work.
Information about jobs already scheduled that are behind the
schedule (backlog).
Scheduling Procedures
Sort backlog work orders by crafts.
Arrange orders by priority. Compile a list of completed and carry over jobs.
Consider job duration, location, travel distance, and the possibility
of combining jobs in the same area. Schedule multi-craft jobs to start at the beginning of every shift.
Issue a daily schedule (not for shutdown maintenance).
Authorize a supervisor to make work assignments (dispatching).
Maintenance Job Priority System
Priorities are established to ensure that the most critical work is
scheduled first. It is developed under coordination with operations staff.
It should be dynamic.
It must be updated periodically to reflect changes in operation and maintenance strategies.
It typically includes three to ten levels of priority.
Scheduling Techniques The objective of the scheduling techniques is to construct a time chart
showing:
The start and finish for each job. The interdependencies among jobs.
The critical jobs that require special attention and effective
monitoring.
Scheduling Techniques
OM 315: MAINTENANCE MANAGEMENT
Page 12 of 50
Such techniques are:
Modified Gantt chart
CPM PERT
Integer and stochastic programming.
3. What is zero based budgets? Explain the sources of collecting maintenance costing and their applications.
Answer
There is tremendous pressure on maintenance managers to improve their
budget performance.
Traditional budget methods do not seem to be effective in the
maintenance arena because maintenance expenditures are made up of
1000's of seemingly unrelated events. Maintenance does not seem to be volume related (higher output equals higher maintenance).
The breakdowns and other maintenance activities are hard to predict and do not necessarily reflect what happened last year. To successfully budget
(and therefore predict) maintenance expenditures we must divide the
whole maintenance demand into its basic parts
A zero based budget breaks the overall demand for maintenance services
into its constituents, that is, assets or areas. Look at each asset (or group
of like assets) to determine the maintenance exposure. In addition to the unit or asset list, a zero based budget has allocations for certain areas
that are hard to define as individual assets such as the electrical
distribution system or the paved parking area and sidewalks.
Prior computerization of maintenance simplifies the construction of a zero
based budget. The computer can easily generate an asset and areas list.
Many systems allow you to create classes of equipment where like equipment is aggregated into one line.
If the system has been in use for more than a year you can attach the hours and material dollars for each asset and area. Some systems have a
reason for repair (see chapter on work orders). The reason for repair
would roughly correspond to the categories below. Most systems allow export of the files to a spread sheet for further manipulation.
All maintenance activity can be traced back to one of the eight demands
that follow. Shops that are craft dominated have a more complicated
problem. After the budget is completed they must go back to the individual demands and break-out the labor by craft.
The eight reasons for maintenance resources are:
1. PM- preventive maintenance hours/materials. Based on your
facility and equipment size, use, construction and the standard times of
the PM activities you can predict how much time and materials PM's will take. In a TPM shop some of the PM hours will come from operators. The
OM 315: MAINTENANCE MANAGEMENT
Page 13 of 50
simplest formula is to multiply the number of services by the time for
each service. Also look at the materials used for each service. Include
some time for the short repairs that the mechanic will get done during the PM. Since you have some flexibility in scheduling you can consider PM's as
a level demand throughout the year.
Specifically PM work includes all the inspection, adjustment, bolt tightening, oiling, cleaning, and readings that are initiated by task lists.
The task lists are initiated on a periodic (quarterly, annual) basis.
2. CM-corrective maintenance hours/materials. Also called
scheduled repairs or planned maintenance. As your PM inspectors inspect
each part of the facility and all equipment they write-up repairs
(deficiencies). These write-ups become your backlog of corrective maintenance (CM) for your maintenance schedule. The repairs are
considered scheduled repairs as long as they don't interrupt jobs in
process.
You can look at previous years to get an idea of the hours for this activity.
Since you have control of the schedule this demand can be considered level throughout the year. These scheduled repair hours are inserted by
equipment, by group of like equipment or by area.
There is a tremendous advantage to this type of work because you can plan the work and accumulate several jobs for a location or schedule them
together or assemble several jobs with the same materials or craft (fix all
the small roof problems at several locations) at the same time. I estimate that every hour spent planning these scheduled jobs you will save 5 hours
on the site.
3. UM- all types of user maintenance (hours/materials) is all requests
from users/customers from the routine broken pulley on a conveyor to a
$1,000,000 catastrophic breakdown. This includes UM-R (Routine work),
UM-P (Small projects), UM-B (breakdowns).
UM is the most common source of work in a breakdown driven
organization. Without inspection and inspectors the users find problems first. Users also are the first to find vandalism, breakdown and damage.
Responsive user complaint handling is essential if you are to be viewed as
effective. In fact, most users will judge you entirely on how you respond to their complaints (other benchmarks usually don't have as much impact
on their quality of life).
UM includes both breakdowns and routine service requests. UM includes servicing minor user requests for hanging pictures, moving furniture and
other personal service.
At the beginning of the year budget the same amount of hours for UM as
the previous year by asset or category. At the end of the year you can
back off emergency component of UM as the PM system starts to take
effect. For purposes of budgeting UM creates a level demand. In fact emergencies will tend to bunch. Many factories use outside contractors to
OM 315: MAINTENANCE MANAGEMENT
Page 14 of 50
level the demand for UM. In larger facilities this work will look more and
more level. See seasonal demands (SM) for a special case of UM demand.
4. SM- Seasonal Maintenance hours/materials. This includes all
special seasonal demands. Your entire grounds maintenance effort is
cer¬tainly driven by season. Review of roofing systems before summer
and winter or checking air conditioning before summer are seasonal demands.
Some businesses are seasonal. Cleaning the Candy Cane line before it starts up in July would be a seasonal demand. You can also use this
category to pick-up some percentage of the seasonally driven
emergencies or seasonally driven PM. Budget hours at the beginning of
each season by asset or group based on his¬tory.
5. RM- Replacement / Rehabilitation / Remodel Maintenance hours /
materials. In some organizations this category is capital improvement and is handled outside the normal maintenance budget.
RM also includes all maintenance improvements and efficiency improvements. At some point, units which have not been maintained for
a period of time or have reached the end of their useful life will have to be
rebuilt or replaced. The rebuilding effort should be added to your
maintenance budget as a capital replacement line item separate from any current maintenance activity. If your people are doing the modernization
to bring units up to PM standards then the hours will have to be budgeted.
Since you have control of the rebuild schedule you may be able to use
rebuilds as a crew balancing tool. A special case of RM is Management
decision. This work is generated by a manager when they decide to change something in, on or around a machine, other asset or the building.
The reasons for the decision might range from energy efficiency, improve
usage, legal problems or even a whim (I hate yellow presses, paint
them!).
Maintenance demands for the whole operation (not tracked by individual
but by location). After the base demand is cataloged by equipment or area of the plant look into some of the budget busters below. A well designed
budget can be ruined by excessive social demands generated by visiting
dignitaries or a large construction project's effect on the rest of your operation.
6. SD- Social Demands (sometimes known as hidden demands because
they don't always show up on work orders). This is also called PS for Personal Service. Your primary mission is maintenance of the equipment
and facility. You may be called upon for other duties in your organization.
These duties may include supplying clean-up people, running tours, preparation for visiting dignitaries, set up of special events (like running
sound cable), providing chauffeur services, picking-up or delivery of
papers or packages, organizing picnics or work on non-organization
equipment and facilities (charity work). Estimate your hours for these activities.
OM 315: MAINTENANCE MANAGEMENT
Page 15 of 50
7. ED- Expansion demands. Any expansion in the size of your facility,
size of your work force, additions to the scope of your control will add hours to your overall requirements. New buildings, assembly lines, major
changes to the plant require start-up time. New facilities disrupt current
activities as well as taking direct time. Adding satellite facilities will result
in additional lost time until systems are well in place. Estimate additional time if an expansion is contemplated.
8. CD- Catastrophic Demands. It seems that every location has characteristic catastrophes. Add time for one or two catastrophes. You
can review your records for the actual amount of time spent in a typical
catastrophe. This can include floods, hur¬ricanes, trucks taking out the
side of the buildings, fires, etc.
How to Set-up a maintenance budget
1. Start the process by compiling a list of all machinery, equipment that
you maintain. As much as possible arrange the list by department or cost
center. This will facilitate report printing at a later stage. If you have a CMMS, (Computerized Maintenance Management System), print an asset
or equipment list. This list might have as few as hundreds, thousands or
more entries depending of the size of your plant.
2. Add to this list areas of the plant and site that require maintenance
resources that don't lend themselves to the unit concept. Typical areas
include roofs, pavement, electrical distribution system, piping, doors/windows, etc.
3. Look at the list and see if there are any units that can logically be grouped together. A wire harness assembly plant might have 50 braiding
machines of similar usage and vintage. These could logically be
aggregated into one line. Putting similar units or areas together simplifies
the process and also makes predictions more accurate.
4. Collect any maintenance data available by unit or area for the last
several years if available. Your CMMS would facilitate this step. If the data is coming from the CMMS then see if it has an export capability. Some
systems will send data to spread sheet files without re-entry. Inquire if
your accounting or cost accounting group can shed any light on the costs to maintain certain areas, departments, assets or production lines.
5. We recommend this whole mass of information be designed in a
computer spread sheet Excel. Create a template to duplicate the form at the end of this section. The equipment, areas and groups of units/areas
are listed in the template. An alternate recommendation would be to enter
the data into a database manager. There are advantages to both approaches. Most budgets are usually run from spread sheets.
6. After the individual units and the general assets are listed add the
global lines (that apply to the whole site) social, expansion, catastrophes. Look into your history or estimate the impact of these areas. The three
OM 315: MAINTENANCE MANAGEMENT
Page 16 of 50
areas can be added as hours and materials or as percentages depending
on the need. If these areas have traditionally been non-work order items
now would be a good time to set-up the codes to put them on work orders. Once accounted for these costs can be studied year to year.
7. Once assets have been inserted into the template, this document
becomes the basis for your zero based budget. Back-up the filled in template. You have many hours in at this point so make your back-ups
now and keep them up to date! The other point is that this computerized
list might have other uses so a copy might be useful for another reason.
8. Review each unit, area or group and estimate your PM, CM, UM, RM,
SM costs and hours. A useable history of costs from accounting or from
the CMMS greatly simplifies this process.
9. Add in your estimates for SD- Social, ED-Expansion and CD-Catastrophe related demands against the department. These can be as
percentages of the above areas or as actual hours and material costs.
10. Your material costs are the sum of all material columns, your hours
are the sum of all hour columns. You would then apply the costs of your
labor, fringe benefits and maintenance overheads to determine your
budget.
When management wants reductions to your budget you have a new level
of discussion. All changes need to be justified in terms of higher or lower levels of service on individual assets or areas. Now when cuts are needed
you can talk about which assets will be allowed to deteriorate or which
departments will not be served as well.
Almost every business has deferred maintenance. You may see a problem
slowly developing and put off the work. You could be short of funds, be
planning a major rehabilitation, planning to sell the unit or property or lack the requisite skills. Some organizations run their whole operation with
excessive amounts of deferred maintenance Distribute your zero based
budget to the users, staff, and top management for comments.
If your current actual hours available are only a small percentage of your
budgeted demand then something will have to be done. Either deterioration is taking place or your customers are unsatisfied or both.
One solution is to use contractors to make up the short fall. Some
organizations are using this strategy to maintain maximum flexibility.
Using the budget to schedule the need for outsourcing
Some organizations use outsourcing strategies where they crew for 75% to 80% of demand and use outside vendors during peak periods. The
most effective way to predict the need for contract labor is to recast the
budget on a monthly basis. Using the hours per month you can see which
months will exceed your crew available hours.
OM 315: MAINTENANCE MANAGEMENT
Page 17 of 50
The process is similar to a staffing exercise. If your core crew has 1400
hours available a month the contractor would have to supply and labor
above 1400 hours. The budget will show which months it would be likely that contracting will be needed. Moving project work can be used to
minimize contractor needs in a given month.
4. Discuss in detail the spare parts inventory management.
Answer
The aim of spare parts inventory management is to make available to
maintenance, the right spare part, at the right place, at the right time, in
the right quantity, at the right price and at the lowest total cost to the
enterprise. Of these, the first four represent the service to the maintenance engineer and must be give first priority. The next part
means paying the least for a purchased item by locating and negotiating
with the suppliers for a reasonable price-provided the item meets the technical needs of maintenance. The last part of the aim minimizes the
total cost, consisting of the cost of administering the system and
procedures, the price paid for the parts and the cost of machine downtime incurred if the needed part was not available when required.
Types of spare parts
The three basic types of spare parts are:
PM spares
Those are replaced during preventive or opportunity maintenance.
Repair parts (breakdown spares)
Those are required to replace parts that fail during service and
Overhaul (shutdown) parts
Those required during planned overhaul or shutdown of the plant.
The quantity and the time of requirement cannot be predicted for the
repair parts. Only, the chance of their requirement can sometimes be
predicted. Statistical methods are needed for their inventory control.
Life cycle of spare parts
Spare parts go through the following six stages in their life cycle:
i. Design and specification (The right spare)
ii. Determination of initial requirement (The right quantity)
iii. Procurement (the right price) iv. Storage and preservation (minimum custodial and inventory
carrying cost)
v. Issue and replenishment (minimum downtime cost through inventory control)
vi. Disposal of damaged, surplus and obsolete spares (minimum
damage and maximum disposal value)
OM 315: MAINTENANCE MANAGEMENT
Page 18 of 50
Stage 1: Design and specification
Stringent specifications, high quality of manufacture and careful operation
/ maintenance of the machine reduce consumption and cost due to replacement of spares. Ideally, spare parts from the OEM (Original
Equipment Manufacturer) should be used. Spares have a huge range -
each one have several specifications, which are not available to the user.
Without actual fitting it is not possible to tell whether a part will fit or not. This is clearly not practicable as spares are stocked in advance of
requirement. It will be worth paying for a certificate or warranty for the
spare part from its supplier, at least for critical and expensive parts. Only large consumers such as railways, airlines, transport fleets, armed forces
etc. can assess the life of parts by destructive or accelerated life testing or
from the quality records of the manufacturer. One should never buy from
unauthorized dealers or unproved suppliers.
Stage 2: Determination of initial requirements
The machine supplier usually gives a “Recommend list of spares” to the user. This list should be scrutinized for additions that are basically profit-
oriented. The supplier should be asked to give consumption rate for
various spares. The supplier should be asked to give consumption rate for various spares. The maintenance engineer can then better assess the
spares to be stocked for a chosen initial period-say, for one to two years
based on his experience with similar items, number of machines installed,
age of machines, operating conditions, engineering factors and the inventory control system in operation. Casual selection of spare parts at
this stage will create a large inventory of nonmoving spares. In initial
stages only a few will need replenishment.
Spare parts planning begin with the selection of the machine. At this
stage weight must be given to the following:
Complete range of parts serviced by the manufacturer including
those from his sub-suppliers to be available, along with illustrated
catalogues for applicable models. Assurance of supply for the lifetime of the machine
Supply of manufacturing drawings as needed
Availability of observed/estimated consumption rates (not sales data) of spare parts.
Technical data/specifications for assessing failure rate
Warranty for quality and for life of supplied spares Guidance in identification, storage (for sensitive items) and
preservation.
Using this information and his own experience, the maintenance engineer assesses the initial requirement for a period that will cover on lead-time or
one-review period for spares for all types of maintenance, insurance items
and repair pool.
Stage 3: Procurement
For highly specialized equipment or for that likely to go out of production,
the user should assess their availability. There is not much room for competitive procurement of spares except at the time of buying the
OM 315: MAINTENANCE MANAGEMENT
Page 19 of 50
machine. Machines using standard replenishment parts should be
preferred. Non-standard parts are always expensive, and often difficult to
get.
Stage 4: Receipt, storage and Preservation
On receipt, the spare parts are checked for correctness of quantity and
quality before storing them. The principle here is a place for everything in its place. Spares are stocked machine-wise. Items common to more than
one machine are stocked together. The location of each spare is marked
on the bin card for the spare. These bin-cards are also the account cards, which indicate the receipt and issue (and stock balance) and particulars
(part number etc) of the spare. Mentioning details of interchangeable or
substitute spares are a great help in an emergency.
Security of spares in custody is the responsibility of the storekeeper.
Small and expensive spares can be easily pilfered. They are kept in a
locker. Spares are issued only to authorized maintenance personnel who needed them for their work. Physical stock of all items should be checked
with ledger balance annually and differences reconciled. Errors are
investigated to avoid recurrence.
Different preservatives and methods are needed for different spares.
Corrosion is the greatest enemy of all spares. Ball and roller bearings are
easily damaged by dust/humid and should be kept in original packing till needed. Heat sensitive electronic items like transistors should be kept in
cool places. Rubber and textile items should not be exposed to direct
sunlight or to come in contact with mineral oils.
Stage 5: Issue and replenishment
The replenishment of parts withdrawn from stock involves two basic questions, namely, How much to order? and When to order? The quantity
the time of replenishment has to be determined scientifically as they
profoundly affect the cost effectiveness of inventory management.
Stage 6: Disposal of damaged, surplus and obsolete spare parts
An organization expecting good resale value for its surplus spare parts
should ask itself, whether it would buy second hand spares from another unit at any price other than scrap value. One can never be sure as to how
long the parts had been in stock and what deterioration had set in during
storage. Such spares get some value only when they are sold along with the used machine itself. Further, it is not wise to dispose off spare parts
applicable to existing machines simply because they had not been used.
Only stock of insurance spares exceeding.
Cost control for spare parts: Role of maintenance
Cost due to and of spare parts occurs as (a) cost due to non-availability
when required for the machine, (b) consumption value (c) inventory carrying cost, and (d) capital cost of non-moving items. To minimize the
need for troublesome repair parts, operations must prevent failures, and
maintenance must ensure that maintenance is done on time is of high
quality. Maintenance must give top priority to eliminate failures requiring
OM 315: MAINTENANCE MANAGEMENT
Page 20 of 50
the high costs items that are also critical. Worn parts can often be rebuilt
at a fraction of the price of new parts.
Organizing for effective spare parts management
In large organizations there should be a spare parts cell consisting of a
representative each of maintenance, purchasing and stores. Apart from
initiating the indents, this cell should operate the MIS and continuously look for improvement in inventory control and const control introduce
computers for MIS, carry out various analyses and in general act as
internal consultants in the complex area of spare parts management. They should report to a senior level in expertise in this area. They should
report to the chief of materials. This places the responsibility of planning
and providing spare parts squarely where it belongs. In small
organizations, only those maintenance engineers who are trained in scientific inventory control of spare parts should be allowed to indent
spares parts. Their services should be utilized during a period updating of
the system as a whole.
5. Describe in detail safety and environmental issues in maintenance
management.
Answer
The modern concept of safety assurance tries to stress the importance of involvement of all the people, right from the top most owner of the
company to the lower most workers in these safety and environment
movement of the company. Terminologies like „total safety management‟, „Sustainable development‟ etc are the result of such modern thinking to
bring a holistic view into the subject.
The analysis of the causes of many safety and environmental accidents,
have invariably identified „improper maintenance‟ as one the major
reasons. While simple preventive maintenance activities like inspections,
timely replacements etc would be quite economical the neglect of the same has been the reason for enormous loss of revenue running to million
of rupees as a result of the accidents emanating from such causes, not to
speak of the invaluable loss of precious lives. Needless to emphasize, safety and environmental issues need to be made an integral part of the
maintenance management function, without which the basic-objective of
the maintenance function of assurance of plant availability is not complete.
The components of safety and environmental issues and their
relation to maintenance management There are various issues concerned with the safety and environmental
performance of an enterprise. Each of these issues has also linkage with
the operation and maintenance management functions. These are:
Corporate objectives and Goals
The top management of the organizations is expected to clearly specify
the corporate objectives and goals it would like to practice in terms of environment and safety assurance. Many a times, this is done through a
OM 315: MAINTENANCE MANAGEMENT
Page 21 of 50
widely publicized policy statement. The policy and objectives of the
operation and maintenance functions are expected to dovetail them into
the corporate safety and environmental objectives.
Documentation of process equipment
Another important requirement for the safety and environmental
assurance for the company is the meticulous documentation of the vital specifications of the process and equipment in terms of their compliance
to safety and environmental standards, statutory or otherwise. This
documentation can be either independently prepared or integrated into the operation and maintenance manuals of the plant processes or
equipment.
Risk management As it may not be possible to totally eliminate the risks to zero level,
specifically in case of large complex process plants it would be required to
scientifically analyze the risks involved and prepare plans to mitigate them. Risk management involves use of multi disciplinary knowledge and
participation to identify all possible hazards and also identify solutions to
keep their risks at acceptable levels. The contribution of operation and maintenance in risk management is to contribute to the analysis process
through inputs regarding various hazards of operation and maintenance
processes. For example, many of the accidents in chemical process plants
are due to typical maintenance operations like structure welding, catalyst change, overhauling etc. Hence the maintenance functions having
intrinsic knowledge of these processes needed to contribute in the process
of study of these risks.
Change management
In process plants, many of the environmental and safety failures arise from the failure to manage changes, both in the technology applications
or systems. The Flixborough accident happened due to the failure to
manage properly of a reactor. Hence process safety guidelines insist on
well laid out procedures for change management. As maintenance activities are the most prominent examples of unknown changes, due to
their unique nature each time, these requirements are mainly applicable
to the maintenance function.
Human factor
The untrained or improperly placed worker is likely to commit mistakes, which may lead to safety or environmental consequences. Apart from
this, there are other human factors like attitude, ergonomics, work culture
etc. which have great bearing on the safety and environmental
performance. Nurturing the human factors to enable achievement of best safety results is equally applicable to all plant functions, including
operational and maintenance.
Investigation of incidents
There is requirement, statutory or otherwise, to intensely investigating
incidents, so that underlying causes can be found out and corrective
actions for future improvements can be prescribed. The role of operation and maintenance personnel are important in such investigations, as they
OM 315: MAINTENANCE MANAGEMENT
Page 22 of 50
have to provide the correct sequence of activities before, during and after
the incident to the investigating team and also implement the suggestions
emanating from such investigations.
Safety and environmental audits
There is increasing tendency to integrate the safety and environment
audit requirements in the maintenance audits. The audits are mainly to identify whether the existing systems, techniques and procedures comply
with the stated and required standards and suggest improvements
wherever required. The maintenance executive is an important team member of the safety and environment audit team in many process
plants.
Maintenance techniques for safety and environmental improvements
The primary function of maintenance management is to ensure the
availability of the plant and equipment. However, intrinsic to this requirement is the necessity to also provide maximum reliability and
safety. Hence maintenance management needs to integrate their
techniques to simultaneously improve safety and environmental aspects of operation and maintenance of plant and equipment.
Classification of plant and equipment
It is normally required for the maintenance management function to classify the equipment into various categories so that resource allocation
can be facilitated according to their critically. A factorization method is
sometimes used to rank the equipment in term of their critically. Apart from the conventional broad factors of operational criticality, maintenance
intensiveness, quality of products, it is emphasized that safety and
environmental factor is also considered in such classification.
Preventive and predictive maintenance scheduling
Regular checklists and preventive maintenance schedules should include
important safety and environmental checkpoints. Nowadays preventive maintenance if often supported by instrument oriented measurements
called condition monitoring. Many of these monitoring instruments can be
used as dual purpose techniques, for example, measurement of thickness of reactor wall thickness using ultrasonic gauges not only predicts wear
and tear from maintenance replacement angle but also identifies potential
dangerous situations of excessive material deterioration, cracks etc. Similarly, thermograph can identify both insulation wear and thermal
breakdowns in high temperature reformers, furnaces etc.
Shutdown maintenance planning Long shutdowns for annual turnarounds and major overhaul are important
requirements of many process plants and heavier and complex
equipment. Due to the tight time schedule under which such shutdown maintenance are executed, there are many possibilities process of such
activities needs to meticulously include the steps required to ensure safety
and environmental standards.
OM 315: MAINTENANCE MANAGEMENT
Page 23 of 50
Communication between maintenance and other departments
Many safety and environmental hazards have emanated from improper
communication between maintenance and other departments, especially the operations department. Proper information systems like log book
entries, work order systems, work permit systems, lock out systems in
case of electrical hazards etc, are some of the requirements to ensure
communication, thus enabling safety.
Maintenance training
All maintenance personal working in plant facility should be trained in the basic understanding of the process and mechanical hazards. The training
should include mechanical skills, theory, on-the-job / apprentice training,
safe work practices training and specialized craft training. Maintenance
staff often forgets after a period thus the company often loses valuable work information. Several accidents have occurred due to such corporate
memory lapses. The techniques useful under such circumstances are:
Refresher training of all staff Use of incident investigation in training
Publicity campaigns on safety
Close supervision of new staff Continuous updation if maintenance instructions
Safety compliance audits
Counseling poorly performing staff
OM 315: MAINTENANCE MANAGEMENT
Page 24 of 50
ASSIGNMENT – II
6. What is the difference between maintenance technology and maintenance engineering? What steps are needed to introduce
and sustain HRD, specifically for maintenance in an organization?
Explain.
Answer
Maintenance engineering: A large variety of faults occur infrequently but they are spread over years
in the life of the machine there is rarely a second occurrence to learn from
experience in these cases the maintenance engineering.
Has to use his own judgment and deductive logics to meet the situation of
downtime caused this large range of infrequent failures. In these cases,
most of the downtime occurs due to the delay caused by hit and miss type of diagnosis. The supplier rarely covers in the training technology, the
problems due to aging that appear in the later life of a machine. Finally
the engineer has no guidance on improving on the design, operation ,preventive maintenance ,diagnosis and repair techniques/technology of
the existing design to make maintenance easier. This too is the task of
maintenance engineering. It should cover the following topics:
Maintainability design features.
Diagnostic and fault location; Fault –Tree
Analysis(FTA);symptom/fault correlation; Basic theory or reliability and maintainability
Weibull and other statistical analysis for assessing component and
machine life Developing new repair techniques and tools and processes
New repair materials
Spare parts forecasting-essentially a combined statistical and
engineering task.
Maintenance management
Management of maintenance relates to optimizing the resources of maintenance, namely, labor, accessories, workshop machines and tools
real time and spare parts. IT should include the following topics:
Assessing manpower for maintenance tasks i.e.; for installation preventive maintenance, inspections. Unscheduled and planned
repair and modifications.
Scheduling the above tasks with manpower and other resources
Obtaining the best results from own maintenance work force through good leadership, human relations, team building and
motivation
Forecasting the requirement and time for maintenance tools accessories and spare parts.
Using computers for the above, day-to-day work and long term
planning
Organizing own workshop facilities. Selecting and organizing maintenance work that is to be outsourced
OM 315: MAINTENANCE MANAGEMENT
Page 25 of 50
Operating company policies and procedures that are applicable to
all employees.
Role of Human Resource Development
How can an organization grow unless its most important instrument itself
grows? The term „growth applied to an individual in an organization means
developing his qualities to make him more useful to the organization. Behavioral scientists have discovered that the individual growth for self
also contributes to the growth of the organization. A constructive look at
the areas where the personal and organizational expectations or needs could match or be complimentary ,will help to bring out ways and means
to develop human being as a resource. Some expectations are common to
all while others vary to some extent with the job.
Here we deal with HRD for maintenance where specific needs for
maintenance have been considered. Maintenance can have several aims,
all of them converging on delivery of service in a cost effective manner. They are:
TO Maintain high level of equipment reliability and maintainability
as contributors to production /operations To maximize economy in equipment management for its entire life
To cultivate equipment related expertise and skills amongst
maintenance personnel
To create vigorous and enthusiastic work environment. To maximize overall equipment effectiveness through total
employee involvement.
Human side of maintenance:
More than anything else maintenance personnel need recognition of their
contribution–not just in terms of monetary benefits, but by treating them as equal partners in the organization. Their next expectation is for
priority.
For the resources that they need for doing a better job Low Morale amongst maintenance personnel is at least partly due to partisanship of
the on the part of management. Reversing this will greatly improve HRD
for maintenance.
Interdepartmental conflicts affecting HRD:
The most visible conflict between production/operations and maintenance is due to the former competing with the latter for getting their share of
machine time production for output and maintenance for preventive
maintenance. When mature thinking prevails this balance is well struck
mutually and productivity rises. Even more important is their attitudes become mutually supportive. when maintenance and production take
unenlightened views about their role there is an escalating conflict .
Hardening of attitudes over a period of time males for difficulties in HRD for maintenance Evidently a mutual respect for the personnel of these
departments would be created by the HRD. There are many reasons for
the above situation and solution .Among them the following main ones
need to be tackled:
OM 315: MAINTENANCE MANAGEMENT
Page 26 of 50
Ignorance/incompetence of a maintenance in their professional
areas namely maintenance technology, maintenance engineering
and maintenance management. Maintenance must learn to reduce repair effort by creative
application of maintainability principles .
Maintenance must first establish a strong self concept and identity.
Going all put to undertake the role with utmost dedication alone can achieve this.
Maintenance must learn to live with the fact that services are
forgotten after crisis is over. This gives them greater responsibility of convincing higher management and colleagues about their utility.
They must understand that their role is to support the user of the
machine.
Within the maintenance function there has to be a teamwork-mechanical ,electrical and instrument/electronic technicians have to
work in conjunction with each other
Teamwork must extend to sharing problems with related maintenance, disciplines, production /operations and stores.
Problem solving teams should be formed at the level of operators
and machines .they should attack joint problems under the guidance of the steering committee consisting of senior level
manages of both these departments.
Introducing HRD for maintenance THE starring point of HRD is the senior most maintenance engineer
/manager talking to his colleagues and subordinated to take the following
steps.: Identify the short and long term goals for maintenance; typically
reducing the downtime of selected machines to a lower level.;
reducing cost on spares ;increasing part rebuilding. For each goal undertakes a series of brainstorming sessions with
related persons at mixed levels on deterrents. That come in the
way of achieving that goal.
Prioritize these and select a few key deterrents and carryout further brainstorming to identify why these deterrents existed
After this stage the major problem areas will become clear as
perceived by the participants of the brainstorming session . This will fall into five main classes :
Knowledge skill ,attitudes, workload and the organization
These problems must now be solved step by step, again involving personnel at all levels. These steps (such as developing
excellence through various types of training, leadership , stress
management, teambuilding etc.
OM 315: MAINTENANCE MANAGEMENT
Page 27 of 50
7. Discuss in detail the replacement of unit machines and
components.
Answer
There are two kinds of replacement problems with regard to unit machines
and components. one related to determination of replacement interval for
unit machines or single component equipment whose operating cost increases with age and the other which deals with components wherein
there is no age related increase in operating cost, but which are subject to
sudden and catastrophic failures. The replacement problems with regard to unit machines and components therefore can be classified as
either deterministic in which the timing of equipment replacement which
in turn is dictated by the increasing trend of the of the operating and
maintenance cost and also the outcome of the replacement action are assumed to be known with certainty, or probabilistic in which timing and
outcome of the replacement action depend on chance, since it is generally
very difficult to predict with certainty when the failure of the component will occur.
Jardine calls these two classes of problems with regard to unit machines and components as short-term deterministic and short-term probabilistic
respectively to emphasize the fact that the interval between replacements
is comparatively short more likely to be measured in weeks or months
rather than in years as in the case of capital equipment. Thus incase of unit machines and components one need not take into account the effect
of inflation or interest on borrowed capital since even if the replacement
interval is a couple of years or so ,the effect of inflation can possibly be ignored for purpose of analysis and therefore discounting their present
worth equivalent annual cost.
Thus we find replacement problems concerning, which may be considered
to be single component equipment for the for the purpose of replacement
analysis as already stated , and components do not require engineering
economic analysis since time, value of money is comparatively insignificant and may be ignored. on the other hand these replacement
problems are amenable to quantitative procedures which are basically
optimization procedures and thus can be considered as applications of operations research.
Determination of optimal Replacement Interval for an equipment whose operating cost increases with use
To reduce the operating and maintenance cost a replacement can be
performed and after the replacement the trend of the operating cost is known since it is assumed that the replacement always the operating cost
to that of new equipment. Thus the operating cost trends following each
replacement are identical and the interval between replacements is constant and of length t.
Bi-annually major surveys are performed on equipment as per statutory
requirement .between two consecutive surveys, the operating cost of the equipment increases due to the deterioration of certain parts of the
OM 315: MAINTENANCE MANAGEMENT
Page 28 of 50
equipment. Some of these deteriorating parts can be replaced to bring
down the operating cost of the equipment .these replacements cost
money in terms of materials and wages that is cost of spares and cost of manpower and thus a balance has to be maintained between the money
spent on replacements and the savings obtained by reducing the
operating cost.
Let c(t) be the operating cost at unit time at time t after replacement
Let c(r) be the cost of replacement.
The replacement policy is to perform n equally spaced replacements at
intervals of tr between two consecutive surveys
The objective is to determine the optimal replacement interval which will minimize the operating and replacement costs between two consecutive
surveys. now if we denote the total cost C(tr)then
C(tr)= replacement cost between surveys + operating cost between
surveys.
Replacement cost between surveys=number of replacement between
surveys * cost of one replacement =nCr
And operating cost between surveys =number of intervals between surveys *operating cost of each interval between surveys.
= (n+1)[c(t)dt
Therefore c(tr)=nCr+(n+1)[c(t)dt
Determination of optimal replacement interval for a
component/equipment subject to sudden failures
Here we discuss the available models for determination of the optimal
replacement interval for such items of equipment and components. This problem of decision making under uncertainty since it is impossible to
predict with certainty when failure will occur or stated more generally
when the transition from one state to other will occur. This is a class of short-term probabilistic problem and for this class of problems we need to
invoke the assumptions stated before namely, the total cost of
replacement after the failure must be greater than before. There are only two states and conditions of the equipment/component, good or failed,
and that the condition or state is always known ,and finally the hazard
rate of equipment or component must be increasing ,that is the value of
the Weibull shaped parameter, beta, be greater than one.
There are two preventive replacement procedures which are adopted
namely the constant interval policy in which the preventive replacement of the equipment is carried out at fixed intervals and the problem is to
determine the optimal interval between replacements to minimize the
total expected cost per unit time and the age based policy where in
instead of fixed intervals one determines the optimal replacement age for
OM 315: MAINTENANCE MANAGEMENT
Page 29 of 50
the item. The first procedure is known as block replacement policy and
the second procedure is known as age replacement policy.
Block Replacement policy:
Failure is unexpected to any component of the equipment .we may
assume that failure replacement is more costly than preventive
replacement. This is true in most of the cases because a preventive replacements can be adequately planned and necessary arrangements
made for it to reduce both time and cost. and there is a possibility that a
failure may cost damage to the other components of the equipment making the total replacement cost much greater after the failure. In order
to reduce the number of failures and thereby reduce the total expected
cost of replacements, preventive replacements can be carried out at
specific intervals but for this one has to ensure that a proper balance is maintained between amount spent on preventive replacement and the
resulting benefit from preventive replacement namely expected reduction
in failure replacement and expected failure replacement cost. Thus we want to determine the optimum interval between preventive replacements
to minimize the total expected case of replacement per unit time. Given
that cp is the cost a preventive replacement, Cf the cost of failure replacement(Cf>Cp)and tp is the fixed interval between preventive
replacements , then the total expected cost per unit time for one cycle
C(tp)=Total expected cost in interval (0,tp) / length of the interval
But the total expected cost =cost of a preventive replacement in interval
(0,tp)+expected cost of failure replacement=Cp+Cr.H(tp)
Where H(tp)=expected no of failures in (0,tp)
So C(tp)= Cp+Cr.H(tp) / tp
Age replacement policy:
Determination of optimal preventive replacement age:
In this case we consider the above problem but instead of making preventive replacements at fixed intervals thus incurring the possibility of
carrying out a preventive replacement shortly after a failure replacement
.the time at which the preventive replacement is performed depends on the age of the equipment or component, which is the elapsed time from
the previous replacement. Thus the policy to perform preventive
replacements after the equipment has reached a specific age tp with failure replacements being performed whenever necessary.
The objective is determine the optimal age of replacement of the item to
minimize the total expected cost of replacement per unit time.
Let Cp=cost or preventive replacement
Cr=cost of failure replacement with Cr>Cp
And ft is the failure density function of the times of failure o the item. Now in this case there are two possible cycles of operation. Namely once where
OM 315: MAINTENANCE MANAGEMENT
Page 30 of 50
no failure occurs and the item reaches its planned replacement age, tp
and the other cycle which failure occurs before its planned replacement
necessitating a failure replacement.
Thus the total cost of replacement per unit time,
C(tp)= total expected replacement cost per cycle/expected length of the
cycle
Where total expected replacement cost per cycle
=cost preventive replacement*probability of a preventive cycle + cost of failure replacement *probability o a failure cycle
= Cp.R(tp)+Cr[1-R(tp)] and the expected length of the cycle is equal to
=length of preventive cycle * probability of preventive cycle
+expected length of the failure cycle =tp.R(tp)+M(tp)where M(tp) is the expected length of the failure cycle.
So = Cp.R(tp)+Cr[1-R(tp)] / tp.R(tp)+M(tp)
8. Explain the types of maintenance. Also describe the planning and
scheduling of a plant shutdown.
Answer
The dictionary defines maintenance as follows: “the work of keeping something in proper condition; upkeep.” This would imply that
maintenance should be actions taken to prevent a device or component
from failing or to repair normal equipment degradation experienced with the operation of the device to keep it in proper working order.
Unfortunately, data obtained in many studies over the past decade
indicates that most private and government facilities do not expend the necessary resources to maintain equipment in proper working order.
Rather, they wait for equipment failure to occur and then take whatever
actions are necessary to repair or replace the equipment. Nothing lasts
forever and all equipment has associated with it some predefined life expectancy or operational life. For example, equipment may be designed
to operate at full design load for 5,000 hours and may be designed to go
through 15,000 start and stop cycles.
The need for maintenance is predicated on actual or impending failure –
ideally, maintenance is performed to keep equipment and systems running efficiently for at least design life of the component(s). As such,
the practical operation of a component is time-based function. If one were
to graph the failure rate a component population versus time, it is likely
the graph would take the “bathtub” shape shown in Figure. In the figure the Y axis represents the failure rate and the X axis is time. From its
shape, the curve can be divided into three distinct: infant mortality, useful
life, and wear-out periods.
The initial infant mortality period of bathtub curve is characterized by high
failure rate followed by a period of decreasing failure. Many of the failures
associated with this region are linked to poor design, poor installation, or misapplication. The infant mortality period is followed by a nearly constant
OM 315: MAINTENANCE MANAGEMENT
Page 31 of 50
failure rate period known as useful life. There are many theories on why
components fail in this region, most acknowledge that poor O&M often
plays significant role. It is also generally agreed that exceptional maintenance practices encompassing preventive and predictive elements
can extend this period. The wear-out period is characterized by a rapid
increasing failure rate with time. In most cases this period encompasses
the normal distribution of design life failures.
The design life of most equipment requires periodic maintenance. Belts
need adjustment, alignment needs to be maintained, proper lubrication on
rotating equipment is required, and so on. In some cases, certain
components need replacement, (e.g., a wheel bearing on a motor vehicle) to ensure the main piece of equipment (in this case a car) last for its
design life. Anytime we fail to perform maintenance activities intended by
the equipment‟s designer, we shorten the operating life of the equipment. But what options do we have? Over the last 30 years, different
approaches to how maintenance can be performed to ensure equipment
reaches or exceeds its design life have been developed in the United States. In addition to waiting for a piece of equipment to fail (reactive
maintenance), we can utilize preventive maintenance, predictive maintenance, or reliability centered maintenance.
Reactive Maintenance Reactive maintenance is basically the “run it till it breaks” maintenance
mode. No actions or efforts are taken to maintain the equipment as the
designer originally intended to ensure design life is reached.
Studies as recent as the winter of 2000 indicate this is still the
predominant mode of maintenance in the United States. The referenced study breaks down the average maintenance program as follows:
>55% Reactive
31% Preventive 12% Predictive
2% Other
OM 315: MAINTENANCE MANAGEMENT
Page 32 of 50
Note that more than 55% of maintenance resources and activities of an
average facility are still reactive.
Advantages to reactive maintenance can be viewed as a double-edged
sword. If we are dealing with new equipment, we can expect minimal
incidents of failure. If our maintenance program is purely reactive, we will
not expend manpower dollars or incur capital cost until something breaks.
Since we do not see any associated maintenance cost, we could view this
period as saving money. The downside is reality. In reality, during the time we believe we are saving maintenance and capital cost, we are really
spending more dollars than we would have under a different maintenance
approach. We are spending more dollars associated with capital cost
because, while waiting for the equipment to break, we are shortening the life of the equipment resulting in more frequent replacement. We may
incur cost upon failure of the primary device associated with its failure
causing the failure of a secondary device. This is an increased cost we would not have experienced if our maintenance program was more
proactive. Our labor cost associated with repair will probably be higher
than normal because the failure will most likely require more extensive repairs than would have been required if the piece of equipment had not
been run to failure. Chances are the piece of equipment will fail during off
hours or close to the end of the normal workday. If it is a critical piece of
equipment that needs to be back on-line quickly, we will have to pay maintenance overtime cost.
Since we expect to run equipment to failure, we will require a large material inventory of repair parts. This is a cost we could minimize under
a different maintenance strategy.
Advantages
Low cost
Less staff
Disadvantages
Increased cost due to unplanned downtime of equipment.
Increased labor cost, especially if overtime is needed. Cost involved with repair or replacement of equipment.
Possible secondary equipment or process damage from equipment
failure. Inefficient use of staff resources.
Preventive Maintenance
Preventive maintenance can be defined as follows: Actions performed on a time- or machine-run-based schedule that detect, preclude, or mitigate
degradation of a component or system with the aim of sustaining or
extending its useful life through controlling degradation to an acceptable level.
The U.S. Navy pioneered preventive maintenance as a means to increase
the reliability of their vessels. By simply expending the necessary resources to conduct maintenance activities intended by the equipment
OM 315: MAINTENANCE MANAGEMENT
Page 33 of 50
designer, equipment life is extended and its reliability is increased. In
addition to an increase in reliability, dollars are saved over that of a
program just using reactive maintenance. Studies indicate that this savings can amount to as much as 12% to 18% on the average.
Depending on the facilities current maintenance practices, present
equipment reliability, and facility downtime, there is little doubt that many
facilities purely reliant on reactive maintenance could save much more than 18% by instituting a proper preventive maintenance program.
While preventive maintenance is not the optimum maintenance program, it does have several advantages over that of a purely reactive program.
By performing the preventive maintenance as the equipment designer
envisioned, we will extend the life of the equipment closer to design. This
translates into dollar savings. Preventive maintenance (lubrication, filter change, etc.) will generally run the equipment more efficiently resulting in
dollar savings. While we will not prevent equipment catastrophic failures,
we will decrease the number of failures. Minimizing failures translate into maintenance and capital cost savings.
Advantages Cost effective in many capital-intensive processes.
Flexibility allows for the adjustment of maintenance periodicity.
Increased component life cycle.
Energy savings. Reduced equipment or process failure.
Estimated 12% to 18% cost savings over reactive maintenance
program.
Disadvantages
Catastrophic failures still likely to occur. Labor intensive.
Includes performance of unneeded maintenance.
Potential for incidental damage to components in conducting
unneeded maintenance.
Predictive Maintenance
Predictive maintenance can be defined as follows: Measurements that detect the onset of system degradation (lower functional state), thereby
allowing causal stressors to be eliminated or controlled prior to any
significant deterioration in the component physical state. Results indicate current and future functional capability.
Basically, predictive maintenance differs from preventive maintenance by
basing maintenance need on the actual condition of the machine rather than on some preset schedule. You will recall that preventive maintenance
is time-based. Activities such as changing lubricant are based on time, like
calendar time or equipment run time. For example, most people change the oil in their vehicles every 3,000 to 5,000 miles traveled. This is
effectively basing the oil change needs on equipment run time. No
concern is given to the actual condition and performance capability of the
oil. It is changed because it is time. This methodology would be analogous to a preventive maintenance task. If, on the other hand, the operator of
OM 315: MAINTENANCE MANAGEMENT
Page 34 of 50
the car discounted the vehicle run time and had the oil analyzed at some
periodicity to determine its actual condition and lubrication properties,
he/she may be able to extend the oil change until the vehicle had traveled 10,000 miles. This is the fundamental difference between predictive
maintenance and preventive maintenance, whereby predictive
maintenance is used to define needed maintenance task based on
quantified material/equipment condition.
The advantages of predictive maintenance are many. A well-orchestrated
predictive maintenance program will all but eliminate catastrophic equipment failures. We will be able to schedule maintenance activities to
minimize or delete overtime cost. We will be able to minimize inventory
and order parts, as required, well ahead of time to support the
downstream maintenance needs. We can optimize the operation of the equipment, saving energy cost and increasing plant reliability. Past studies
have estimated that a properly functioning predictive maintenance
program can provide a savings of 8% to 12% over a program utilizing preventive maintenance alone. Depending on a facility‟s reliance on
reactive maintenance and material condition, it could easily recognize
savings opportunities exceeding 30% to 40%. In fact, independent surveys indicate the following industrial average savings resultant from
initiation of a functional predictive maintenance program:
Return on investment: 10 times Reduction in maintenance costs: 25% to 30%
Elimination of breakdowns: 70% to 75%
Reduction in downtime: 35% to 45% Increase in production: 20% to 25%.
On the down side, to initially start into the predictive maintenance world is not inexpensive. Much of the equipment requires cost in excess of
$50,000. Training of in-plant personnel to effectively utilize predictive
maintenance technologies will require considerable funding. Program
development will require an understanding of predictive maintenance and a firm commitment to make the program work by all facility organizations
and management.
Reliability Centered Maintenance
Reliability centered maintenance (RCM) magazine provides the following
definition of RCM: “a process used to determine the maintenance requirements of any physical asset in its operating context.”
Basically, RCM methodology deals with some key issues not dealt with by
other maintenance programs. It recognizes that all equipment in a facility is not of equal importance to either the process or facility safety. It
recognizes that equipment design and operation differs and that different
equipment will have a higher probability to undergo failures from different degradation mechanisms than others. It also approaches the structuring
of a maintenance program recognizing that a facility does not have
unlimited financial and personnel resources and that the use of both need
to be prioritized and optimized. In a nutshell, RCM is a systematic approach to evaluate a facility‟s equipment and resources to best mate
OM 315: MAINTENANCE MANAGEMENT
Page 35 of 50
the two and result in a high degree of facility reliability and cost-
effectiveness. RCM is highly reliant on predictive maintenance but also
recognizes that maintenance activities on equipment that is inexpensive and unimportant to facility reliability may best be left to a reactive
maintenance approach. The following maintenance program breakdowns
of continually top-performing facilities would echo the RCM approach to
utilize all available maintenance approaches with the predominant methodology being predictive.
<10% Reactive 25% to 35% Preventive
45% to 55% Predictive.
Because RCM is so heavily weighted in utilization of predictive maintenance technologies, its program advantages and disadvantages
mirror those of predictive maintenance. In addition to these advantages,
RCM will allow a facility to more closely match resources to needs while improving reliability and decreasing cost.
Advantages Can be the most efficient maintenance program.
Lower costs by eliminating unnecessary maintenance or overhauls.
Minimize frequency of overhauls.
Reduced probability of sudden equipment failures. Able to focus maintenance activities on critical components.
Increased component reliability.
Incorporates root cause analysis.
Disadvantages
Can have significant startup cost, training, equipment, etc. Savings potential not readily seen by management.
Planning and scheduling of a plant shutdown
Usually Periodic overhauls of plant and equipment constitute major plant
shutdowns, and these jobs pose planning problems, which are quite
different from those for the normal workload of the maintenance department. Plant shutdowns are essentially projects since they are non-
routine large and take significant amount of time and complex of a
multiplicity of interrelated activities which must be executed in a defined order for completing the entire task. All these activities have to be carried
out in a coordinate manner. Therefore plant shutdowns must be
recognized and managed as separate undertakings calling for different
methods of planning scheduling and monitoring of progress. Accordingly project planning methods are generally used for planning of
maintenance shutdowns. Major plant shutdowns may involve upwards of
few hundreds of activities and many tens of these activities may be simultaneous
Network planning method is used for planning these shutdowns. Moreover
for smaller shutdowns such network analysis may be manual with
extraction into a bar chart to facilitate control. For large projects network planning and associated scheduling and controls must be computerized.
OM 315: MAINTENANCE MANAGEMENT
Page 36 of 50
Establishment of a shutdown program
Planning of a plant shutdown consists of the following activities:
1. Preparation of the shutdown and startup procedures(listing of
operations in proper sequence together with cautions and special
instructions if any) 2. Preparation of a preliminary activity list and breaking it down under
trades and disciplines, such as mechanical, electrical piping
hydraulic pneumatic etc. 3. Preparation of the detailed activity list and estimation of activity
times and resource requirements.
4. Definition of precedence relationships and construction of the
activity network. 5. Network with the maintenance contractor and manpower contractor
as needed.
6. Negotiations with the maintenance contractor and manpower contractor as needed.
7. Carrying out preparatory work.
8. Assembling /collecting necessary tools and tackles and protective clothing as needed.
The monitoring and review of progress (control of the shutdown project )is
taken up once the actual shutdown commences.
For large shutdowns, planning takes a long time and must be started 8-10
weeks before the shutdown is due to start. Accordingly an essential prerequisite of a formal system of planning of individual shutdown is an is
an annual plan showing the timing of each of the major shutdowns , the
most important features of the 50-day planning programs are as follows:
1. A formal meeting of the management to decide and agree on the
extent of the shutdown (planned scope of work).
2. Availability of a good data retrieval system of estimating activity times and resource requirements/loadings for standard repetitive
activities.
3. Active association of personnel responsible for implementing the shutdown. The planning engineers must encourage these persons
to comment on the construction of the activity network /logic
diagrams for the particular areas of work. 4. Availability f computer service /computing facilities
5. Availability of adequate arrangements for issuing work orders and
for monitoring of progress.
6. Proper planning and control of preparatory work.
Monitoring of progress ,issue of necessary job instructions as and
whenever needed, review of activities and updating of the activity network are the basic activities which ensure the proper implementation of detailed
program.
OM 315: MAINTENANCE MANAGEMENT
Page 37 of 50
The monitoring of progress should be done on an hourly basis and
progress reports should be delivered to the central planning
office/maintenance planning bureau every two or four hours.
The progress report must contain the following information:
1. Estimated completion time for all „life‟ activities 2. Actual completion time of activities.
3. Review if pending activities
4. Excesses and shortfalls on resources and 5. Additional work arisen or expected to arise.
9. What is condition based maintenance? Discuss condition
monitoring techniques.
Answer
In a continuous growing global market Productivity is playing a key role to
stay competitive, for any manufacturing company. Productivity can be
achieved through availability and availability can be increased through adopting the efficient maintenance practices, by focusing on different
types of maintenance and strategies.
Condition based Maintenance or predictive maintenance, uses primarily non destructive testing techniques, visual inspection, and performance
data to assess machinery condition. It replaces arbitrarily timed
maintenance tasks with appropriate maintenance task at only when warranted by equipment condition. Condition-monitoring maintenance
task intervals must be properly understood and task intervals should be
determined based on the expected P-F interval. The P-F interval governs the frequency with which the predictive task must be done. Technological
advances are accepted and applied to CBM systems, which includes
improved knowledge of failure mechanisms, advancements in failure
forecasting techniques, advancements in monitoring and sensor devices, advancements in diagnostic and prognostic software, acceptance of
communication protocols, developments in maintenance software
applications and computer networking technologies.
The measurement precision and sensitivity of the CM technique being
used need to be understood because they affect the reaction time available to reduce or eliminate the consequences of the functional failure.
Condition monitoring maintenance tasks must be applicable and cost
effective. The aim of this paper is to give brief introduction of various CBM
techniques, selection of condition monitoring techniques and understanding of P-F interval, Advancement in CBM, Standardization of
CBM system, CBM approach on rail vehicles, advantages &disadvantages
of CBM.
Today, most maintenance actions are carried out by either the
predetermined preventive- or the corrective approach. The predetermined
preventive approach has fixed maintenance intervals in order to prevent components, sub-systems or systems to degrade. Corrective maintenance
OM 315: MAINTENANCE MANAGEMENT
Page 38 of 50
is performed after an obvious fault or breakdown has occurred. Both
approaches have shown to be costly in many applications due to lost
production, cost of keeping spare parts, quality deficiencies etc.
Basically, predictive maintenance or Condition Based Maintenance (CBM)
differs from preventive maintenance by basing maintenance need on the
actual condition of the machine rather than on some preset schedule. As the preventive maintenance is time-based and activities such as changing
lubricant are based on time, like calendar time or equipment run time. For
example, most people change the engine oil in their car/jeep at every 3,000 to 5,000 KMs vehicles traveled. No concern is given to the actual
condition and performance capability of the oil. This methodology would
be analogous to a preventive maintenance task. If on the other hand, the
operator of the car discounted the vehicle run time and had the oil analyzed at some periodicity to determine its actual condition and
lubrication properties, he/she may be able to extend the oil change until
the vehicle had traveled 10,000 KMs. This is the fundamental difference between predictive maintenance and preventive maintenance, whereby
predictive maintenance is used to define needed maintenance task based
on quantified material/equipment condition.
Condition Based Maintenance (CBM) or predictive maintenance is a
technology that strives to identify incipient faults before they become
critical which enables more accurate planning of the preventive maintenance. It may also be defined as Maintenance actions based on
actual condition obtained from in-situ, non-invasive tests, operating and
condition measurement. Or “CBM is a set of maintenance actions based on real-time or near-real time assessment of equipment condition which is
obtained from embedded sensors and/or external tests & measurements
taken by portable equipment.”
CBM or predictive maintenance is the means of improving productivity,
product quality and overall effectiveness of manufacturing and production
plants. CBM or Predictive maintenance is not vibration monitoring or thermal imaging or lubricating oil analysis or any of the other
nondestructive testing techniques, as predictive maintenance tools.
Rather, it is a philosophy or attitude that simply stated uses the actual operating condition of plant equipment and systems to optimize total plant
operation. A comprehensive predictive maintenance management
program utilizes a combination of the most cost-effective tools, i.e. thermal imaging, vibration monitoring, tribology, and other nondestructive
testing methods, to obtain the actual operating condition of critical plant
systems and based on this factual data all maintenance activities on an
as-needed basis are scheduled. Including CBM or predictive maintenance in a comprehensive maintenance management program will provide the
ability to optimize the availability of process machinery and greatly reduce
the cost of maintenance. It will also provide the means to improve product quality, productivity and profitability.
The maintenance organization in a company probably has one of the most
important functions, looking after assets and keeping track of equipment in order to secure productivity. A company with no or a poor maintenance
OM 315: MAINTENANCE MANAGEMENT
Page 39 of 50
organization will loose a lot of money due to lost production capacity, cost
of keeping spare parts, quality deficiencies, damages for absent or late
deliveries etc.
A relationship between failure rate versus change in maintenance
philosophy is showing decline trend as illustrated in figure below, also
representing the strengths and weaknesses of the different maintenance types.
The addition of a comprehensive predictive maintenance program can and
will provide factual data on the actual operating condition of critical
assets, including their efficiency, as well as the actual mechanical condition of each machine-train and the operating efficiency of each
process system. Instead of relying on industrial or in-plant average-life
statistics, i.e. mean-time-to failure, to schedule maintenance activities,
predictive maintenance uses direct monitoring of the mechanical condition, system efficiency and other indicators to determine the actual
mean-time-to-failure or loss of efficiency for each machine-train and
system in the plant. This data provides maintenance management the factual data needed for effective planning and scheduling maintenance
activities.
Methods advances and applications
Test & Inspection (TPM)
There are many sources of machinery health and production availability information available to an organization's maintenance and operations
staff. Two of the most commonly used sources of information are
scheduled inspection of machinery and condition monitoring.
OM 315: MAINTENANCE MANAGEMENT
Page 40 of 50
Inspection Routes can be split into 3 areas
Rounds
Where an operator or engineer completes a set circuit as a cursory status
check. Will often involve the making of notes or observations.
Adjustments
Often associated with the TPM philosophy, this type of route involves the
checking of settings, making the required changes, lubrication, cleaning etc.
Measurements
Gathering of plant panel data, oil levels, hours running, temperatures, overall vibration readings, quality tests.
All of the above can be achieved through the use of a clipboard, data entry grid and the use of a data entry clerk. Unfortunately paper based
Inspection data almost invariably ends up in a filing cabinet somewhere
and is only reviewed in the event of a problem or breakdown.
Methods of Inspection Data gathering
Paper Systems Log sheets, inspection instructions, production line test / fault books.
Electronic Clipboard Involves the gathering of data in an electronic format using a hand held
device and the downloading of this data into a software package.
Vibration Analysis
Vibration measurement systems fall into the following categories:
Single Value Methods Hand Held meters
SPM Units
Acoustic Emission Units Vibration Pens
4-20mA sensors
Time Frequency Methods
Hand Held Data-collectors
On line systems
Single Value Measurements
The variety of single value measurements is endless, from the ISO filtered levels mentioned in ISO 10816 [1] to the „magic numbers‟ offered by
some of the technology vendors; promising to solve all of your plant
condition problems within one simple solution. ISO 10816-3 is
summarised as a supporting appendix to this text.
OM 315: MAINTENANCE MANAGEMENT
Page 41 of 50
Please note single value methods are either „generic‟ or „specific‟. The
generic case is where a value will indicate the presence of „a problem‟ but
cannot categorise the problem into a specific fault (e.g. Unbalance, looseness, misalignment, cavitation etc.). The specific methods
concentrate on issues such as bearing faults and try to eliminate the
influence of „other‟ faults through the use of algorithms and electronic
design.
The following table outlines the more common types of measurement with
comments on applications and a brief technical description of the method.
Single Value Method Summary
Method Description Applications
ISO Filtered Velocity
2Hz – 1kHz filtered Velocity
Works as a general condition indicator.
SPM Carpet and Peak
related to the
demodulation of a sensor resonance
around 30kHz.
One of the better single value bearing
indicator methods. Some problems on
larger bearings and gear units.
Acoustic
Emission
Distress & dB,
demodulates a 100kHz carrier which is
sensitive to stress
waves.
Better general indicator than ISO
velocity, without the ISO comfort zone.
Vibration Meters
/ pens
Combine velocity,
bearing and
acceleration
techniques (sometimes include
thermal)
Look for ISO Velocity, envelope & high
frequency acceleration for best
performance.
4-20mA sensors Filtered data converted to DCS/PLC
compatible signal.
ISO velocity version available, envelope version still awaited.
Can be used to „home in‟ on specific
problems by special order.
Single value vibration methods have two major advantages and only one
real disadvantage; these are low cost, simple interpretation and lack of
accuracy respectively. The overall CM system implications of single value methods are discussed within the later sections of this text.
Single value data are easy to trend and interpret as shown by the inset
plot below.
Time Frequency Measurements
This type of measurement involves the detection and display of specific components of a time history sensor output. The use of specific frequency
components lends itself to the detection of faults down to a single
mechanical component (e.g. bearing, gear, impeller).
Once again, various methods, techniques and signal conditioning systems
are used to detect specific components of the raw time history data.
OM 315: MAINTENANCE MANAGEMENT
Page 42 of 50
Impacts are created as a rolling
element collides with a damaged
area.
These impacts show as transients
within the time domain. The Demodulator extracts these
transients.
Extracted impact frequencies are then displayed on an envelope
spectrum (shown opposite)
Displacement (Low Frequency)
Where the measurement of absolute movement is required, measured using LVDT‟s or eddy current probes. Particularly useful in detecting the
relative position of a rotor versus a structure and in the diagnosis of plain
bearing faults through the use of orbit plots.
Velocity (Mid Frequency)
The most commonly used method for fault identification, mainly due to
the scalar consistency of the method (i.e. 25mm/s is high almost irrespective of the machine type). Used to detect signs of mechanical
problems in the frequency range 20Hz – 2000Hz. Detection capabilities
cover the following fault conditions.
Unbalance, Misalignment, Looseness, Resonance, Cavitation, Blade problems, Turbulence
Acceleration (High Frequency) Amplitude Demodulation Methods used to extract impacts from the
standard acceleration spectra through the extraction of the amplitude-
modulated component and the display of the demodulated components within an auto-spectrum plot.
There are two main types of envelope measurement, namely:
Band Pass Filtered Enveloping Allows the time history associated with the excitation of a specific
frequency band pass through to the demodulator circuit. This method
avoids the possibility of phase cancellation and is better at isolating the transient activity.
High Pass Filtered Enveloping Sets a High Pass filter and allows all measured time data above the HP
filter pass to the demodulator, this method is regarded as less effective by
vibration practitioners.
General Acceleration
OM 315: MAINTENANCE MANAGEMENT
Page 43 of 50
Where rotating machine related frequency components are expected
above 2kHz, velocity measurement is not accurate due to sensor noise
levels. Acceleration time frequency analysis tends to be used for the detection of fault components from:
Any gear assembly (gearbox, timing gear, gear pump)
Where amplitude demodulation methods are not available (to
detect a „haystack‟ within the high frequency spectra) High speed screw assemblies.
Turbochargers
Blading problems on turbo-machinery High frequency resonances
Detection of gear and rub related transients
Thermal Techniques Thermal measurement systems fall into the following categories
Point/Zone Measurement
Dedicated temperature sensor Hand held
Point/Zone Measurement
These methods measure the temperature of a specific sensor touching the
structure or the emitted temperature from a radiating area. They come in hand held and fixed variants and are very convenient and robust.
Thermography Infrared detection systems provide a thermal picture of the target object,
both accurate and visually clear.
The following table outlines the more common types of measurement with
comments on applications and a brief technical description of the method.
Thermal Measurement Summary Table
Method Description Applications
Point temperature Usually a thermocouple or
RTD. Often „imbedded‟, can
be provided as an encapsulated sensor for
permanent fit.
Can be used on all
accessible surfaces.
Walk around versions take time to settle
and are less robust
than the pyrometer.
Area Pyrometer Measures the emitted IR radiation from a surface.
Often with a Laser sight or
area indicator.
Very good for walk around temperature
checks on machines
and panels.
Temperature Paint /
Stickers
Chemical indicators
calibrated to change colour
at a specific temperature.
Great for inspection
rounds.
Thermography Hand held still or video camera sensitive to emitted
IR.
The ultimate, high-resolution thermal
picture. Camera
costs £10k up,
OM 315: MAINTENANCE MANAGEMENT
Page 44 of 50
service £500 per
day.
Camera use and
interpretation does require „good‟
training.
Oil Analysis
The science of oil analysis falls into 4 main areas, which are listed below:
Fluid Physical Properties (Viscosity, appearance)
Fluid Chemical Properties (TBN, TAN, additives, contamination, % water)
Fluid Contamination (ISO Cleanliness, Ferrography, Spectroscopy,
dissolved gases[Transformer ]) Machine Health (wear metals associated with plant components)
Laboratory based oil analysis can provide the Fluid components, however the return of well informed machine health data from an oil analysis
service provider will require the following:
A real understanding of the machine and the associated
contamination risks. The ability to analyse oil data and relate that to the specific
machine using the lubricant.
Wear mode analysis through machine knowledge, particle shape, texture and composition
Some pitfalls
Beware the following types of oil analysis service provider: Free analysis with the supply of oil - The oil lab should be
independent as far as possible from the lubrication supply, free
service means there is a hidden charge and any margin calls will fall on the side of „replace the oil‟.
„Lights out‟ analysis facilities – These are production line facilities
that provide a production line output, they tend to automate the diagnosis and the Machine Health aspects are virtually useless.
Oil analysis labs that sub contract both the Fluid and the Machine
Health components of the analysis. This results in the provision of a
„Lights out‟ quality of analysis with an added mark up on price.
On site screening
If your reliance on optimal lubrication and hydraulic oil cleanliness is very high OR the volume of oil for analysis is prohibitively expensive OR the
option of lab based oil analysis is not there (shipping, nuclear, highly
contaminated). The use of on-site testing methods warrants consideration.
Visual appearance and smell
In the most extreme cases metal particles can be seen to glitter and water will come out of solution to provide a water layer. In these cases the full
laboratory analysis route is rather „late‟.
OM 315: MAINTENANCE MANAGEMENT
Page 45 of 50
Here are a few simple guides to the visual inspection of oil for water
content and odour relating to contaminants.
Water Contamination
As little as 1 % water can reduce the life of a Journal bearing by 90 %
The plot inset below shows how little water is required to make the oil appear cloudy. When one considers the dramatic effect of oil on
mechanical components such as rolling element and journal bearings, the
level of vigilance is clear.
A hot plate crackle test will also indicate the presence of water as a
contaminant.
Smell
A lot of caution should be exercised when smelling oil samples. Do not
place the bottle directly under your nose. Remember that there may be
toxic chemicals in the sample. Rather, wave your hand above the opening
to waft the scent toward your face. Sometimes it helps to heat the oil,
which increases the likelihood of detecting certain contaminants and
degradation by-products.
Typical Odours From:
Oxidation - sour or pungent odour, acrid (rotten egg) smell or something
similar to stale cheese
Thermal Failure - smell of burnt food
Bacteria - stench, road-kill smell
Running High Temperatures - no odour
Contaminants - solvents, refrigerants, degreasers, hydrogen sulphide,
gasoline, diesel, kerosene and process chemicals
Amino Acids - fish odour
OM 315: MAINTENANCE MANAGEMENT
Page 46 of 50
Nitro Compounds - almond-like scent
Esters (Synthetic Lubricants) and Ketones - perfume odour
Other On-site screening Alternatives
Viscosity Tests – Basic systems test at ambient temperature, the better systems offer temperature setting and measurement combined.
Chemical Tests –TAN, TBN etc. (can be bought as a lab kit from most oil analysis hardware providers)
ISO screening – A variety of methods are available, most are reliable and repeatable for oil screening
Combined analysers – These vary from a multi-function device that is
virtually automatic to those with an excess of operations to collate the complete set of analysis results. Always look for the average sample
processing time when considering a Combination Oil analyser (you may be
unpleasantly surprised). The better analysers will take Contamination level, ferrous index and viscosity from a single sample.
Transformer Oil Sampling The sampling and analysis of transformer oil is one of the „must do‟s‟ of
the Predictive Maintenance world. If nothing else the following 4 tests
must be included in any analysis:
Dielectric Strength (kV)
Dielectric strength is the ability of transformer oil to withstand electrical
stress without failure. Moisture, sediment and conducting particles tend to
reduce the dielectric strength of the oil.
Moisture Content (PPM)
Water in power equipment is attracted to areas of greater electrical stress
and this is where it is most dangerous. Moisture accelerates the
deterioration process of paper and oil, as well as badly maintained
breathers and oil leaks. The moisture detected in the oil, by doing a
moisture test, is directly related to the operating temperature of the
transformer windings where the continuous migration of moisture is
taking place as the temperature varies.
PCB Content
Polychlorinated Biphenyl is classified as a toxic material. No legislation has
been finalized to date, however, a risk analysis should be carried out to
identify and manage the product to prevent any contamination. COSHH
1994 and EPA 1990 provide guidelines for the reduction and handling of
PCB‟s.
On-line monitoring of CbM data
The complete coverage of this area is entirely beyond the scope of this
technical paper. On-line systems are available to measure all CbM related
OM 315: MAINTENANCE MANAGEMENT
Page 47 of 50
data where a sensor exists. The scope includes the following areas of
CbM:
Vibration in all of its guises Temperature
Oil Debris and optical particle count
Pressure Volume analysis on Diesel and Gas Engines
And will normally accept inputs from SCADA, DCS, 4-20mA sensors etc.
10.Discuss in detail importance, types and methodology of
maintenance audit.
Answer We are aware that maintenance function is a supporting activity to make
the planned availability of a plant and equipment possible. Since it is not
direct function connected to profits of organization like production finance and marketing, it is possible that the necessity of maintenance to be
properly managed is overlooked by top management at the same time
need to be at the optimum levels as either over maintenance or under maintenance ,both are likely to affect the costs incurred by the
organization .We have already seen that though the actual maintenance
cost may be only a small proportion like the tip of an iceberg the
consequential cost if improper maintenance could run to millions of rupees.
We have seen that maintenance management requires many features to be compiled by different levels of personnel in the organization.
Maintenance management requires attention from of management right
from the chief executive level to the bottom most worker level. These requirements and functions need to be standardized , monitored ,analyzed
and corrective actions prescribed from time to time. Hence the
importance of maintenance audit is very much emphasized.
Maintenance audit when properly and regularly conducted will have the
following benefits:
Helps in confirming, the function is performing towards the objectives that are set forth for it.
To compare the performance indices of the function with that of the
target as well as similar benchmarks for the industry sector or with the world class best benchmarks
To identify weak areas for performance improvement and
implementation strategies thereof.
To get certified towards proper system functioning from the auditing agency which may be requirement of a statutory and
standard agency
To apply and obtain popular awards like the total productive Maintenance (TPM)award etc.
Types of Audit:
There are various types of audit that are possible to be carried out in an organization. it would be useful to understand these terminologies so that
OM 315: MAINTENANCE MANAGEMENT
Page 48 of 50
one is able to understand and and appreciate their purpose and
requirements for different situations .These are briefly described below.:
Statutory Audit is the audit required by the law enacted by the
parliament or legislatures of a country. sometimes other statutory
or semi-statutory organizations like international labour
organization ,international standards organization etc also make specific provisions for
such statutory audits. On the other hand Voluntary audit is the
audit taken by an organization in its own interest.
Internal Audit is the audit taken by the internal department or
personnel of the company. Normally one department auditing the
functions of the other department.
External Audit is the audit conducted by an external agency
(neutral third party) either due to the wish of the company management to identify problems for improvement or mandated by
an enforcing agency like the government.
Preliminary Audit is normally conducted for a brief period of time
to identify major thrust problem areas in a function. The problem so
identified may be subjected to detailed examination and problem
solving at a later stage. On the other hand a Detailed Audit is carried out to study the complete features and requirements of a
specific function. normally the team members conduct such audit
for a considerable period
Management Audit is the audit carried out to check and identify
the suitableness of system and procedures of a management function .the audit carried out for an ISO-9000 certification is an
example of such an audit.
Technical Audit is the process of study of technical component of a plant with or without experimentation and instrument monitoring
to identify improvements in both hardware and software aspects.
For example environment audit of a factory involving measurement of pollution parameters is predominantly a technical audit.
All these types of audits have some amount of overlapping in their purposes and applicability. Example, a statutory audit can also be a result
o the voluntary requirement of the company. Or a external audit team
may co-opt an internal member to enhance the understanding of the
process being audited. All these type of audits have similar methodologies also.
Methodology of maintenance audit: Initial orientation: The auditing team has an initial meeting with the
representatives of the company‟s senior management and the regulating
agency, if any. In this meeting, the goals scope and coverage information
requirement, schedule of the meting, the techniques of the audit to be employed are presented in a summarized form. The initial meeting
OM 315: MAINTENANCE MANAGEMENT
Page 49 of 50
enables both the auditing and auditee groups to understand each others
concern well and lays the foundation for a detailed interaction at later
stages.
Preliminary preparation: During this step the auditors team studies
the management and technical information obtained in the initial
orientation and prepares a plan for addressing the major concern expressed by company management or the regulator .Accordingly the
most important areas of enquiry are identified and details audit visit plan
and schedule are prepared. It covers the areas of audit, identification of management personnel to be interviewed, facilities and work area to be
visited , data requirements etc.
Preliminary questionnaire survey: The auditors prepare a detailed questionnaire on the various issues of concern in maintenance
management and circulate in advance to the company management
personnel. The questionnaire contains a systematic identification of elements and series of questions to collect information about the same.
The questionnaire enables collection of documented information from a
large cross section of target personnel. The answers to the questionnaire are compiled and conclusion are arrived at as to the selected areas and
management personnel to be concentrated upon during the next steps.
Plan Visits: The auditing team undertakes a filed visit to the plant for collecting field information. During this visit interviews are held with
senior managers, supervisors and technicians etc to obtain a first hand
feeling of the management factors and concerns and feelings. During this visit additional information required in terms of work process, plant
performance parameters operations-maintenance interactions etc are also
collected.
In some special audits, plant visits are also taken up to a comparable third
party organization to make comparative analysis of the system and
technical parameters. At the end of the plant visits the auditing team would have the data essential to understand the companies maintenance
strategies, challenges and plans it also enables to fully understand the
present resources structure in terms of organization ,manpower, budget etc and its deployment.
Data analysis: During this step of the audit, the study team digests, summarizes and analyses all types of data and information gathered.
Profiles of maintenance management are developed and compared to the
companies past performance, and to the performance of the industry and
to similar companies. Many of the criteria used to evaluate effectiveness and efficiency can be measured quantitatively in terms of costs and
savings, man-hours percent adherence to schedule or budget energy
consumption, reliability, availability and so forth. However truly compared benchmarks may not be readily available. Accordingly the auditor must
consider the company‟s performance within the context of its unique
environment. Seasoned judgment both in tempering quantitative
evaluations and in measuring less tangible performance factors must be used.
OM 315: MAINTENANCE MANAGEMENT
Page 50 of 50
Development of Conclusions and Recommendations: Based on the
above evaluation the auditing team develops conclusions about the efficiency and effectiveness of the maintenance management system. The
factors that were observed to be examples of good management practices
are listed with supporting evidence and data and thus conclusions as to
the strengths of the system are identified .Similarly the possible sources of problems are also identified, documented and possible consequences, if
these problems are not tackled are also listed. Alternative strategies to
overcome the problem are identified and evaluated to indicate the most suitable option for problem solving.
Report Submission: The audit team prepared a comprehensive report
indicating the scope of the audit ,methodology adopted information gathered , analysis performed and recommendations arrived at as a result
of the audit Normally a draft report is submitted to ascertain the feedback
of the company management and the final report incorporating the suggestions and the feedback . The report submission is often
accompanied by a direct presentation to the management/regulatory
agency where the action plans for implementation of the suggestions and the requirement of the involvement of the auditors further can also be
discussed.