Main Beam / Drive Beam Phase alignment

15
Main Beam / Drive Beam Phase alignment B. Jeanneret CERN/BE CLIC Worshop , October 2009 1 CLIC_WSHOP_2009,BJ,WG5

description

Main Beam / Drive Beam Phase alignment. B. Jeanneret CERN/BE CLIC Worshop , October 2009. Tolerance on Phase and Gradient. Luminosity and understanding/adjustment of the Beam Delivery and of the Final Focus. D.Schulte & R.Tomas , PAC09. Overall cycle. - PowerPoint PPT Presentation

Transcript of Main Beam / Drive Beam Phase alignment

Page 1: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 1

Main Beam / Drive BeamPhase alignment

B. Jeanneret CERN/BECLIC Worshop , October 2009

Page 2: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 2

Tolerance on Phase and Gradient

• Luminosity and understanding/adjustment of the Beam Delivery and of the Final Focus

D.Schulte & R.Tomas, PAC09

Not much margin on these

Overall cycle DB intertrain (or sector to sector)

Page 3: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5

e+ injector, 2.4 GeV

e- injector2.4 GeV

CLIC 3 TeV

e+ main linace- main linac , 12 GHz, 100 MV/m, 20.85 km

BC2BC2

BC1

e+ DR365m

e- DR365m

booster linac, 9 GeV, 2 GHz or 4 GHz ?

decelerator, 24 sectors of 868 m

IP1

BDS2.75 km

BDS2.75 km

47.9 km

drive beam accelerator2.38 GeV, 1.0 GHz

combiner rings Circumferences delay loop 72.4 m

CR1 144.8 mCR2 434.3 m

CR1CR2

delayloop

326 klystrons33 MW, 139 ms

1 km

CR2delayloop

drive beam accelerator2.38 GeV, 1.0 GHz

326 klystrons33 MW, 139 ms

1 km

CR1

TAR=120m

TAR=120m

245m 245m

83ps

45fs

DB

MB

Page 4: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 4

Implications for different systems

• RF :– DB Linac : 1 GHz

Unless feed-back in between : δφ = 0.015o

• Timing system : – transmission stable over ~km down to 5μm

• Instrumentation :– Detection accuracy down to 15fs

• (Quasi-) Static path-length error in rings• Ground stability/vibrations in rings

Tolerance to rms : divide by 3 σz = 5 μm , σt = 15 fs

Not discussedtoday

Page 5: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 5

Phase control / RF

Page 6: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 6

Timing and feed-back strategy in the tunnel

• To relax on δφ : feed-forward & back before entering each DECEL

9 GeV MB as a fast clock

Timing line

TA

MB to IP

DB∆t to:injectors DB & MBDamp. RingsMB TADB TAs@50 Hz

BA

Phase from B, Energy jitter δE from A&B,Phase correction for δE

C

D

C&D, Phase error MB/DB , to synchronizethe injector linacs

Open issue: frequency band of δE correction

E

Notional, as for now

Page 7: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 7

Phase control - I

• measurement of the 9 GeV MB ( keep in memory for T = [0..23] × 6 μs] )• error in the 9 GeV MB from Injector and in the MB-TA• DB TA length stability ⇔ magnet stability to be specified• measurement of the DB• error of the feed-forward adjustement of the chicane• transmission error in the timing system• bandwidth limit for correction (30 MHz the filling of the MB_ACS) DOABLE ?• periodic dE/E structure complicating the measurement (slide 13)• Path-lengths variations to be worked-out in all rings (MB and DB)

Scheme : correct the phase with fast feed-forward in the final chicane and slow feed-back to the injectors

Ingredients

At 12 GHz

See talkA. Andersson

Page 8: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 8

Phase control – II : data L0

α

L0 = 8m α = 0.1 rad

Tolerance on α :-1/10 δztol

- 4 magnets

Use static magnets + variable deflectors for range δφr=10o

relax for DB linac

Chicane after TA

Range inside which correction applies

(Instead of 0.015o)

All this being re-worked(less demanding)F.Stulle, D. Schulte

Page 9: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 9

Fast timing network• Little (or no) expertise in the project as of today

• Presentations at this workshop : WG3 THURSDAY 11h00-12h30

– Long distance Optical Fibers with fs resolutionF. Oemer Ilday / Bilkent Univ. Ankara

– Overview of the Phase Measurement System at SLS/PSIVladimir Arsov / PSI

– Femtosecond optical synchronization system for FLASHMatthias Felber / DESY

Page 10: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5

e+ injector, 2.4 GeV

e- injector2.4 GeV

CLIC 3 TeV

e+ main linace- main linac , 12 GHz, 100 MV/m, 20.85 km

BC2BC2

BC1

e+ DR365m

e- DR365m

booster linac, 9 GeV, 2 GHz or 4 GHz ?

decelerator, 24 sectors of 868 m

IP1

BDS2.75 km

BDS2.75 km

47.9 km

drive beam accelerator2.38 GeV, 1.0 GHz

combiner rings Circumferences delay loop 72.4 m

CR1 144.8 mCR2 434.3 m

CR1CR2

delayloop

326 klystrons33 MW, 139 ms

1 km

CR2delayloop

drive beam accelerator2.38 GeV, 1.0 GHz

326 klystrons33 MW, 139 ms

1 km

CR1

TAR=120m

TAR=120m

245m 245m

Page 11: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 11

Fast timing network

MBTA

DRe-

Pre-DRe-

MBlinac

DRe+

IPEXP

TADBLinac

DLCR1,2

Source

MBLTL

Fbackbox

24 x

9Gev LTL

DECEL

Main Linac

2km

50m

1km

500m

?

5km

100m

1km

20km

50mAll this for σt = 15fs

Here to synchronize the two complexTolrance : σt = 7.5fs

Here relaxed, tol must be set for full capture and match to damping time

Page 12: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 12

Fast longitudinal measurement

Page 13: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 13

A complication : Incoherent synchrotron radiation

• X-ray @ 6 keV : L_absorption = 50 µm (Aluminium)

• Impact angle : ~ 0.2 rad• ∆T = 80 oK @ 50 Hz• Risk of rapid ageing

∆x = 10 µm

Overall dE/E of ISR varies betweenTrains travelling :- MIN : No DL, 1×CR1, 1×CR2- MAX : 1×DL, 3×CR1, 4×CR2- Max dE/E = 2 o/oo- Converts to dz after last chicane before DECEL- 1% longitudinal z-pitch modulation

TIME STRUCTURE

24 bunches x 121

Cure :- make the DL, CR1,CR2 longer accordingly- complicates the feed-forward φ–correction(see slide 20)

R56 = -0.33 m

Page 14: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 14

Detection of the bunch centroid

• Existing CTF3 data ?

10x tol 9x tol

2.5 x tol A gaussian bunch, with sσz = 1mmAnd tol σ(δz) = 0.005mm( σ(δt) = 15fs )

Page 15: Main  Beam  / Drive  Beam Phase  alignment

CLIC_WSHOP_2009,BJ,WG5 15

Summary

• Timing and feed-back in the femto-second range not trivial

• Much work in many areas

• Multi-group issue (RF,detectors,network?,beam)

• Long distance (km) & precise (10fs,5μm) new for us