Magdalena Discard Dump Conceptual Design rev001€¦ · conceptual design for the Magdalene coal...
Transcript of Magdalena Discard Dump Conceptual Design rev001€¦ · conceptual design for the Magdalene coal...
Est. 1987
63 Wessel Road Woodmead PO Box 2597 Rivonia 2128
South Africa Tel: +27 (0)11 803 5726 Fax: +27 (0)11 803 5745
Reg No: 2004/00765/07 DIRECTORS: AC Johnstone, W. Dressel, AWC Marais, SE Scawthon, AH Barbour (Non-exec) www.gcs-sa.biz
Johannesburg Durban
MAGDALENA COLLEIRY
COAL DISCARD DISPOSAL FACILITY
CONCEPTUAL DESIGN
Compiled for
Zinoju Investments (Pty) Ltd
W Dressel Pr Tech Eng
For GCS (Pty) Ltd
October 2006
Our Ref: SLA.06.190 rev001
Your Ref:
Magdalena Discard Disposal Facility – Conceptual Design i
GCS (Pty) Ltd October 2006 SLA.06.190
MAGDALENA COLLIERY
COAL DISCARD DISPOSAL FACILITY
CONCEPTUAL DESIGN
REPORT NO: SLA.06.190
Client: Zinoju Investments (Pty) Ltd
66 Karellandman Street Dundee 3000
DOCUMENT ISSUE STATUS
Report Issue Final
Reference Number SLA.06.190
Title Name Signature Date
Author Waldo Dressel
Oct 2006
Project Director Waldo Dressel
Oct 2006
Technical Reviewer Lynn Fitschen Oct 2006
This report is not to be used for contractual or engineering purposes unless the report is designated “FINAL”
Magdalena Discard Disposal Facility – Conceptual Design
GCS (Pty) Ltd October 2006 SLA.06.190
EXECUTIVE SUMMARY
GCS (Pty) Ltd was appointed by Slater Coal (Zinoju Investments (Pty) Ltd) to carry out a conceptual design for the Magdalene coal discard disposal facility approximately 22 km north- northwest of the town of Dundee in Northern Kwazulu Natal. The purpose of the report is to present the conceptual design for the coal discard facility.
The life of mine is planned for 10 yeas and discard will be generated at 16800 tonnes per month. A site selection process has been followed and a preferred coal discard disposal facility was selected. GCS (Pty) Ltd carried out a preliminary geotechnical investigation at the preferred site.
The discard disposal facility will accommodate the coal discard that will be generated during the life of mine and the facility will have a footprint area of approximately 20 ha and will reach a final height of 28m. The dump will be developed by means of an upstream construction method by tipping dry coal with trucks. The coal discard will be nominally compacted in layers.
The conceptual design includes the following components:
Surface water management infrastructure.
Temporary and final upstream storm water diversion for separation of clean and dirty water.
Under drainage system to minimise seepage to groundwater.
Pollution control measures.
The outer slopes of the discard facility will be constructed at an overall slope of 1:3 (v:h) and will be continuously covered with topsoil and vegetated.
Magdalena Discard Disposal Facility – Conceptual Design
GCS (Pty) Ltd October 2006 SLA.06.190
TABLE OF CONTENTS
1 INTRODUCTION ............................................................................................................. 1
2 PROJECT REQUIREMENTS .......................................................................................... 1
3 SITE LOCATION AND DESCRIPTION ........................................................................... 1
4 AVAILABLE INFORMATION ........................................................................................... 2
5 SURVEY.......................................................................................................................... 2
6 SITE SELECTION ........................................................................................................... 2
6.1 Introduction............................................................................................................... 2
6.2 Identification of Candidate Sites ............................................................................... 2
6.3 Site Locality .............................................................................................................. 3
6.4 Fatal Flaws And Critical Factors............................................................................... 3
6.5 Numerical Assessments ........................................................................................... 3
7 SAFETY CLASSIFICATION ............................................................................................ 4
8 GEOTECHNICAL INVESTIGATION................................................................................ 5
8.1 Site No. 1.................................................................................................................. 5
8.2 Site No. 2.................................................................................................................. 6
9 DEPOSITION MANAGEMENT PLAN ............................................................................. 6
9.1 Coarse Coal Discard ................................................................................................ 6
9.1.1 Capacity Analysis .............................................................................................. 6
9.1.2 Deposition Method ............................................................................................ 7
9.1.3 Access Control .................................................................................................. 7
9.1.4 Dump Construction............................................................................................ 7
9.2 Slurry Disposal ......................................................................................................... 7
9.3 Management............................................................................................................. 8
10 SLOPE STABILITY ANALYSIS.................................................................................... 8
10.1 Methodology ......................................................................................................... 8
10.2 Material Strength Parameters ............................................................................... 9
10.3 Phreatic Conditions............................................................................................... 9
10.4 Earthquake Conditions.......................................................................................... 9
10.5 Slope Stability Results .......................................................................................... 9
11 SURFACE WATER MANAGEMENT PLAN............................................................... 10
11.1 Surface Water Management Principles .............................................................. 10
Magdalena Discard Disposal Facility – Conceptual Design
GCS (Pty) Ltd October 2006 SLA.06.190
11.2 Freeboard ........................................................................................................... 10
11.3 Water Discharge Criteria..................................................................................... 10
11.4 Seepage Predictions........................................................................................... 10
11.5 Under Drainage System...................................................................................... 11
11.6 Storm Water Control ........................................................................................... 11
11.7 Water Balance .................................................................................................... 11
11.8 Return Water and Decant Systems .................................................................... 12
12 POLLUTION CONTROL MEASURES ....................................................................... 13
13 EROSION POTENTIAL AND PROTECTION ............................................................ 14
14 CONCEPTUAL REHABILITATION PLAN.................................................................. 15
14.1 Introduction ......................................................................................................... 15
14.2 Objectives ........................................................................................................... 15
14.3 Final Geometry ................................................................................................... 15
14.4 Final Surface Cover ............................................................................................ 15
14.5 Control of Water.................................................................................................. 16
14.6 Vegetation........................................................................................................... 16
15 CONCEPTUAL DRAWINGS...................................................................................... 16
16 CONCLUSIONS AND RECOMMENDATIONS.......................................................... 17
LIST OF TABLES Table 1: Fatal Flaw and Critical Factors ................................................................................. 3
Table 2: Ranking Matrix Results ............................................................................................. 3
Table 3: SABS (0286:1998) Safety Classification................................................................... 4
Table 4: Hazard Rating Results .............................................................................................. 4
Table 5: Summary of Capacity Analyses ................................................................................ 7
Table 6: Dump Construction with Coal Discard ...................................................................... 7
Table 7: Opencast................................................................................................................... 8
Table 8: Material Strength Parameters ................................................................................... 9
Table 9: Slope Stability Results .............................................................................................. 9
Table 10: Climatic Water Balance......................................................................................... 11
Table 11: Summary of Return Water System ....................................................................... 12
Table 12: Pollution Control Measures................................................................................... 13
Table 13: Factors Affecting the Erosion of Cover Systems .................................................. 14
Table 14: Conceptual Drawings............................................................................................ 16
Magdalena Discard Disposal Facility – Conceptual Design
GCS (Pty) Ltd October 2006 SLA.06.190
LIST OF APPENDICES
Appendix A Site Selection
Appendix B Geotechnical Investigations
Appendix C Capacity Analysis
Appendix D Slope Stability
Appendix E Conceptual Drawings
Appendix F Safety Classification
Magdalena Discard Disposal Facility – Conceptual Design 1
GCS (Pty) Ltd October 2006 SLA.06.190
1 INTRODUCTION
GCS (Pty) Ltd was appointed to carry out the necessary design activities and tasks, in accordance with the specified requirements, to present a conceptual design for the establishment of a coal discard disposal facility for the Magdalena Colliery.
The purpose of this report is to provide a conceptual design for the coal discard facility for a 10 year planned life of mine. The coal slurry will be backfilled into the opencast mine workings. The conceptual design for the coal discard disposal facility addresses the principles of the intended design, but do not include detail specifications. It includes all aspects of the design that will affect the successful operation and subsequent closure of the facility in an environmentally acceptable manner.
2 PROJECT REQUIREMENTS
The requirements of the coal discard disposal facility can be summarised as follows:
Table 1: Design Parameters
Design Life 10 years
Discard (dry tonnes) 16 800 t/month 2 016 000 t (total)
Discard Dry Density (t/m3) 1.4
Discard (m3) 12 000 m3/month 1 440 000 m3 (total)
Slurry tonnes 4 200 t/month 504 000 t (total)
Slurry Dry Density (t/m3) 1.05
3 SITE LOCATION AND DESCRIPTION
Magdalena Colliery is located approximately 22 km north- northwest of the town of Dundee and 63 km southwest of the town of Vryheid in Northern Kwazulu-Natal. Refer to Figure A, Appendix A.
This site consists of abandoned underground workings, current underground workings, rehabilitated opencast workings and un-rehabilitated opencast workings. The position of the current active Magdalena opencast strip is situated across the southwestern half of the site. The opencast mining at the south pit will be backfilled prior to discard disposal and will form a part of the discard disposal area.
Magdalena Discard Disposal Facility – Conceptual Design 2
GCS (Pty) Ltd October 2006 SLA.06.190
4 AVAILABLE INFORMATION
Prior to the investigation the following information was available:
Drawing, General Mine Surface Plan
Drawing, Magdalena Mining Plan, South Pit
Drawing, Mining Plan, Mining / Reserve Plan
5 SURVEY
The Client supplied all the survey information required for the conceptual design of the coal discard disposal facility. The survey was modeled with the Civil Designer and Microstation computer packages to create a three-dimensional model of the proposed site. This model was used for:
Water balance analysis.
Capacity analysis.
Site layout design.
Conceptual closure planning.
6 SITE SELECTION
6.1 Introduction
All possible alternative sites were considered before the preferred sites were identified. Sufficient candidate sites were identified to ensure the due consideration of potential alternatives. In identifying candidate sites, numerous economic, engineering, environmental and public acceptance criteria were considered. These criteria interrelate, as there are always economic implications when candidate sites are sub-optimal in terms of environmental and/or public acceptance characteristics. Also, the public will usually not accept an environmentally unsuitable residue disposal site.
6.2 Identification of Candidate Sites
Early considerations in site selection are to identify the size and general location of the required site. The further phases involved in the approach to site selection are as follows:
Elimination of all areas with associated fatal flaws, and taking note of all critical factors;
Identification of candidate sites based on the site selection criteria;
Ranking of the candidate sites; and
Carrying out a feasibility study on the best option(s).
Magdalena Discard Disposal Facility – Conceptual Design 3
GCS (Pty) Ltd October 2006 SLA.06.190
6.3 Site Locality
A total of three candidate sites have been identified (see Figure A, Appendix A).
Site 1: Located approximately 650m due south of the proposed plant area and is located on an area that will be disturbed by opencast mining.
Site 2: Located approximately 1400m south of the proposed plant area.
Site 3: Located approximately 950m due north of proposed plant area.
6.4 Fatal Flaws And Critical Factors
The fatal flaws and critical factors are summarised in Table 2 below:
Table 1: Fatal Flaw and Critical Factors
Site No. Fatal Flaw Critical Factor
1 None None
2 None None
3 None Close proximity to existing settlement
Geological structures traverse the site
6.5 Numerical Assessments
Each of the sites was assessed utilizing a ranking matrix (see Appendix A). The criteria of this matrix were appropriately weighted in order to reflect their relative importance. Scores were assigned for each criterion based on a qualitative assessment, and were added together to provide a total for each site. A maximum score for a particular aspect means that the site is suitable as far as that aspect is concerned.
The results of the ranking matrix are summarized in Table 3 below:
Table 2: Ranking Matrix Results
Site No.
Ranking (%)
1
86
2
77
3
75
Magdalena Discard Disposal Facility – Conceptual Design 4
GCS (Pty) Ltd October 2006 SLA.06.190
The above table indicates that:
All three sites will be suitable for coal discard disposal;
Site 1 is the preferred site for the establishment of a coal discard disposal facility; and
Site 2 ranks second.
7 SAFETY CLASSIFICATION
Great importance is attached to the qualitative safety classification associated with a particular residue disposal facility. This classification defines the potential consequences of a failure of the residue disposal facility.
The Code of Practice for Mine Residue (SABS 0286:1998) calls for a safety classification to differentiate between residue deposits of high, medium and low hazard rating on the basis of their potential to cause harm to life or property within the zone of influence. The classification should be based on the anticipated configuration of the residue disposal facility at the end of its design life, and on satisfying any one of the conditions set out in columns 1 to 4 of Table 4.
Table 3: SABS (0286:1998) Safety Classification
Number of residents in
zone of influence
Number of workers in
zone of influence1)
Value of third party property in zone of
influence2)
Depth to under-ground
mine workings3)
Classification
0 <10 0-R2m <200m Low Hazard
1-10 11-100 R2m – R20m 50 m – 200 m Medium
Hazard
>10 >100 >R20m <50m High Hazard
1) Not including workers employed solely for the purpose of operation of the deposit.
2) The value of third party property should be the replacement value in 1996 terms.
3) The potential for collapse of the residue deposit into the underground workings affectively extends the zone of
influence to below ground level.
The rating, base on the zone of influence, can be summarised as follows (Refer to Figure B, Appendix F):
Table 4: Hazard Rating Results
Item
Condition
Hazard Rating
Overall Rating
1 Number of residents in zone of influence Low
2 Number of workers in zone of influence Low
3 Value of third party property in zone of influence Low
4 Depth to under-ground mine workings Low
LOW
Magdalena Discard Disposal Facility – Conceptual Design 5
GCS (Pty) Ltd October 2006 SLA.06.190
8 GEOTECHNICAL INVESTIGATION
A preliminary geotechnical investigation was carried out by GCS, during September 2006, for the Magdalena coal discard disposal facility to gain an understanding of the sub-surface soil conditions underlying the proposed site.
Two sites were investigated. The first site was indicated on the Proposed Mining Layout Plan and defined within boundary EFGH. The second site was indicated by Mr Frank Talbot during the site visit, and is situated approximately 1km to the southeast of Site 1.
The founding conditions for the proposed discard disposal site is soft sandstone rock that lies directly over soft shale rock. Depth to bedrock is expected to vary between 1m and 5m. It is recommended that all the highly plastic material should be removed from the footprint of the discard disposal facility prior to deposition. Topsoil should also be preserved for progressive rehabilitation and final closure.
The shear parameters of the discard material collected from the existing discard dump respectively reflect internal angles of friction of 45o and cohesions of 7kN/m3. The maximum dry densities of the discard was 1469kg/m3, measured at 95% modified AASHTO.
The results of the geological and geotechnical investigations are presented in Appendix B.
8.1 Site No. 1
• This site is closer to the proposed washing plant than site no. 2.
• The site has an easterly gradient, and is vegetated by short grass and small thorn trees.
• A large portion of the western side of the site is covered by a wide drainage channel in which sandstone rock has been exposed, and has scattered loose dolerite boulders deposited over it.
• Some parts of this drainage channel are covered by soils and completely weathered very soft rock of up to 3.1m in thickness.
• On the southern side of this wide drainage channel, this rock is overlain by soils with a thickness of up to 1.6m.
• The soil profiles are silty clays and display expansive characteristics.
• The soils on the eastern side of the site are much deeper, reaching depths of up to 5.0m.
• A longwall excavation to the south of the site revealed a 1.0m thick completely weathered dolerite (residual soil with occasional boulders) sill at a variable depth (due to the westerly dip).
• The sandstone and shale rock are consistent and are expected to be suitable foundations for a discard dump.
• These rocks are also likely to form a barrier against the percolation of pollutants into the groundwater.
Magdalena Discard Disposal Facility – Conceptual Design 6
GCS (Pty) Ltd October 2006 SLA.06.190
• The clayey nature of the soils are also likely to form a barrier for the lateral movement of pollutants into surrounding areas.
• Excavation of the soils is likely to be soft excavation.
8.2 Site No. 2
• The site has a gentle easterly to north-easterly gradient, and is vegetated by short grass and small thorn trees.
• Large drainage channels draining in a north-easterly direction cross the site, and have eroded down to the bedrock.
• Soils were recorded to depths of between 3.0m and 4.3m.
• The soils are silty clays that display expansive characteristics.
• The soils are underlain by completely weathered soft sandstone rock with a thickness of 0.5m.
• The sandstone is underlain by completely weathered very soft shale.
• The sandstone and shale rock are closely bedded and dip in a westerly direction at approximately 150.
• The sandstone and shale rock are relatively consistent and are expected to be a suitable foundation for a discard dump.
• These rocks are also likely to form a barrier against the percolation of pollutants into the groundwater.
• The clayey nature of the soils are also likely to form a barrier for the lateral movement of pollutants into surrounding areas.
• Excavation of the soils is likely to be soft excavation.
9 DEPOSITION MANAGEMENT PLAN
The purpose of the deposition management plan is to present the principle on which the proposed facility will be operated.
9.1 Coarse Coal Discard
9.1.1 Capacity Analysis
The coal discard disposal facility was three-dimensionally modelled for an accurate determination of the relationship between the height; area and capacity using the computer program Civil Designer and Microstation. The detail was processed with Microsoft Excel to calculate the rates of rise for average production rates and eventually, the life of the facility. The stage capacity curve is attached in Appendix C and can be summarized as follows:
Magdalena Discard Disposal Facility – Conceptual Design 7
GCS (Pty) Ltd October 2006 SLA.06.190
Table 5: Summary of Capacity Analyses
Area (ha)
Deposition rate
(tpm)
Maximum height
(m)
Capacity
(million m3) Basin Final Top Surface
16 800 28 1.82 20 10
9.1.2 Deposition Method
In order to minimize the coal discard exposed to the atmosphere during disposal, the conceptual design allows for the dump to be developed from the lowest elevation via an “upstream” system of tipping by truck.
9.1.3 Access Control
The boundary fence for the disposal facility is indicated on the layout plans. The purpose of the fence, as required by law, is to keep livestock out and discourage people from gaining access.
Access roads to all major components of the discard facility are also shown on the layout plans.
9.1.4 Dump Construction
The Design Engineer will approve the foundation preparation for the starter walls, including the box cuts. The starter walls will be constructed of selected material from the return water dam basin and the coal discard dump basin. The starter wall will be nominally compacted in 200mm thick layers.
Future lifts will be constructed with coal discard. The coal discard material will be nominally compacted in horizontal layers. The proposed outer wall slope geometry can be summarised as follows:
Table 6: Dump Construction with Coal Discard
Slope Angel Benches
Intermediate (v:h)
Overall (v:h)
Width (m)
Vertical Intervals (m)
Max. Vertical Height
(m)
1:2 1:3 13.5 9 28
9.2 Slurry Disposal
Coal slurry will be disposed off in the opencast mining operations. The slurry will be deposited at a density of approximately 1.05 t/m3 and the supernatant water will be returned to the process plant for reuse. A total volume of approximately 500 000 m3 of slurry will be produced over the life of mine.
The following opencast areas will be available for slurry deposition (refer to Figure A, Appendix A):
Magdalena Discard Disposal Facility – Conceptual Design 8
GCS (Pty) Ltd October 2006 SLA.06.190
Table 7: Opencast
Opencast Description Volume Available (m3) Approximate Deposition Period (Years)
Existing void north of under ground
entrance (on farm Magdalena No. 7574) ±130 000 2.6
Proposed opencast extension to the
north (on farm Allen No 1 No. 15592) ±3 000 000 Adequate for life of mine
Existing opencast to the south (on farm
Magdalena No. 7574) To be determined Adequate for life of mine
Prior to closure of the slurry deposition areas the coal slurry will be allowed to settle sufficiently to allow the placement of topsoil and vegetation of the final landform.
9.3 Management
A system of management and monitoring will ensure that the residue disposal facility is operated safely and efficiently, in accordance with good environmental practice and in a manner compatible with the final closure requirements.
10 SLOPE STABILITY ANALYSIS
10.1 Methodology
The following section details the methodology for the slope stability analysis. The overall stability of the outer slopes has been assessed, using potential failure surfaces (Modified Bishop), in the limit equilibrium program WinStabl. This program allows the analysis of numerous potential failure surfaces, and the identification of the critical surface with the lowest factor of safety against failure.
Calculation of the factor of safety for a tailings embankment requires an analysis of the potential failure surfaces of the embankment. There are a number of common failure modes to which embankments may be vulnerable. These include slope failure from rotational slides, overtopping, foundation failure, erosion, piping, and liquefaction. Each failure may result in partial or complete embankment failure.
For the purpose of this stability assessment the rotational sliding and foundation block failure modes were considered. Rotational sliding, so named because the failure surface appears as a segment of a horizontal cylinder, may result in a slope failure ranging from local sloughing of tailings at random areas along the face of an embankment, to a massive circular arc slide extending over the entire structure.
Magdalena Discard Disposal Facility – Conceptual Design 9
GCS (Pty) Ltd October 2006 SLA.06.190
10.2 Material Strength Parameters
A literature survey was carried out to determine the material properties of both the coal tailings and the founding horizon for the discard disposal facility. The parameters used in the analyses are summarised in the table below:
Table 8: Material Strength Parameters
Material Type Moist Density (kN/m3) Cohesion (kPa)
Friction Angle (Degrees) Source of Data
Discard 16 20 40 Geotechnical testing
Soil 18 10 30 Geotechnical testing
Bedrock 22 100 45 Judgmental/estimate
10.3 Phreatic Conditions
A pore pressure co-efficient has been used to account for pore pressures within the voids of the discard.
10.4 Earthquake Conditions
The project area is in a region of low seismicity.
10.5 Slope Stability Results The slope stability results are summarised in the table below and the graphical sections are
attached in Appendix D.
Table 9: Slope Stability Results
ru
Scenario Coarse Coal Discard Foundation
Calculated Factor of Safety Allowable Factor of Safety
Circular Failure
A (fully drained) 0.1 0.0 2.17 1.3
B (partly drained) 0.2 0.1 1.91 1.3
C (near saturation) 0.3 0.2 1.66 1.3
Good international practice is based on an allowable factor of safety of 1.3.
Magdalena Discard Disposal Facility – Conceptual Design 10
GCS (Pty) Ltd October 2006 SLA.06.190
From the above table it can be seen that the overall stability for the discard disposal facility is
satisfactory for all conditions. The discard will be placed in a fairly dry state and compacted
in layers. The near saturation scenario was conducted to illustrate the worst case, however
these conditions are not expected during the operating life of the facility if good management
and monitoring measures are followed.
11 SURFACE WATER MANAGEMENT PLAN
The surface water management plan can be summarised as follows:
11.1 Surface Water Management Principles
The principles on which the surface water management plan is based, and which are implemented in the conceptual design are:
Separation of clean and dirty water.
Clean storm water run-off from the upstream catchments will be diverted around the dump.
Zero discharge of contaminated water to the environment.
Maximisation of seepage to the groundwater.
Minimum storage of water on the dump.
11.2 Freeboard
In South Africa, Government Notice No. 704, Regulation 6 requires that the minimum freeboard for a residue disposal facility and return water dam should be at least 0,8m above full supply level. It also states that a dirty water system must be designed and operated in such a manner that it is at all times capable of handling the 1:50 year flood event on top of its normal operating level without spilling.
11.3 Water Discharge Criteria
The disposal facility has been designed as a closed system, with no discharge of polluted water to the environment. In storm conditions, excess water will be temporarily stored on the benches and top surface from where it will evaporate.
The benches and top surface will accommodate the precipitate from a 1 in 50 year, 24-hour storm event. The return water dam will be utilised for storm events only and therefore not during normal operations.
11.4 Seepage Predictions
The coal discard will be nominally compacted in horizontal layers and it is anticipated that the dump will have a relatively low permeability. Seepage and leachate generation will originate from rainwater only and is expected to be minimal. A series of under drains will be installed to collect seepage water. The discard disposal facility will form part of the regional water monitoring program of the mine and will include groundwater levels and water quality.
Magdalena Discard Disposal Facility – Conceptual Design 11
GCS (Pty) Ltd October 2006 SLA.06.190
The clayey nature of the onsite solis and the bedrock will minimise seepage into the groundwater.
11.5 Under Drainage System
Under drains from selected waste rock or filter stone will be constructed to collect and direct rainwater seepage, that percale through the discard facility, from the base areas to collection/monitoring manholes. The water collection/quality monitoring manholes will be linked with a collector pipe and will have the provision to discharge water from a downstream collector sump and a return water dam.
11.6 Storm Water Control
The surface hydrology design includes surface drainage, storm water diversions and river diversions (where applicable), to meet the requirements of the Water Act. This includes the separation of unpolluted water from polluted water and the containment of polluted water on site in storage facilities.
A storm water diversion trench will be constructed upstream of the dump to prevent the ingress of storm water onto the dump. In the case of large storm events, resulting in flood conditions within the basin of the dump, temporary storm water cut-off berms have been provided to route the surplus water into the natural drainage systems.
The side slopes and benches will be paddocked, covered with a soil layer and vegetated as soon as possible. The top surface of the dump will be soil cladded and graded back towards the hill slopes at a grade of approximately 1: 200 to ensure the save storage of water.
Catchment paddocks will be constructed at the toe of the dump to collect and contain surface run-off and silt from the side slopes.
11.7 Water Balance
A climatic water balance [avg. rainfall (mm) – avg. soil evaporation (mm)] was done for the site to assist with the development of the water management plan.
The mean annual precipitation for the Dundee area is 791.5 mm. Mean wet season precipitation (October – April) is 702,9 mm, and mean dry season precipitation (May – September) is 88.4mm. Mean monthly precipitation is presented in the table below. The data was obtained from the weather Stations at Newcastle and Dundee and can be summarised as follows:
Table 10: Climatic Water Balance
Month Avg. Rainfall Dundee
1896 - 1999 (mm)
Avg. Evaporation Newcastle 1957 - 1987
(mm)
Avg. Soil Evaporation (0.7*A-Pan_mm)
Climatic Water Balance (mm)
Jan 145.6 186.5 130.55 +15.05
Feb 112.1 151.4 105.98 +6.12
Magdalena Discard Disposal Facility – Conceptual Design 12
GCS (Pty) Ltd October 2006 SLA.06.190
Table 10: Climatic Water Balance
Month Avg. Rainfall Dundee
1896 - 1999 (mm)
Avg. Evaporation Newcastle 1957 - 1987
(mm)
Avg. Soil Evaporation (0.7*A-Pan_mm)
Climatic Water Balance (mm)
Mar 76 143.6 100.52 -24.52
Apr 44.1 110.6 77.42 -33.32
May 14.8 89.9 62.93 -48.13
Jun 12.8 66.8 46.76 -33.96
Jul 5.6 80.9 56.63 -51.03
Aug 18.6 125.4 87.78 -69.18
Sept 36.6 159.7 111.79 -75.19
Oct 86.1 179.2 125.44 -39.34
Nov 108.8 177.5 124.25 -15.45
Dec 130.4 199 139.3 -8.9
Total 791.5 1670.5 1169.35 -377.85
The above table indicates that the site can be considered a water deficit area and that significant leachate would not be generated on account of the climate. It is expected that some limited leachate will be generated during the wet months especially during above normal rainfall years when precipitation could exceed evaporation.
11.8 Return Water and Decant Systems
The return water system includes a return water dam, pumps and return water pipeline to the proposed plant. The design can be summarized as follows:
Table 11: Summary of Return Water System
1:50 year, 24h storm event
(mm)
Exposed Coal Discard Surface
(ha)
Run-off factor
Storm Volume
(m3)
Return water dam capacity
(m3)
Return water pipeline length
(m)
125 10 0.8 12 500 14 000 760
The Design Engineer will approve the foundation preparation, including the box cut, for the return water dam. The homogenous embankment will be constructed of selected material from the return water dam basin and the dump basin. The embankment will be compacted in
Magdalena Discard Disposal Facility – Conceptual Design 13
GCS (Pty) Ltd October 2006 SLA.06.190
200mm thick layers to 100% Standard Proctor Density at optimum moisture content to +3% of the optimum moisture content.
The discard disposal facility will always have adequate freeboard to accommodate the 1:50 year, 24-hour storm event. The discard disposal facility is not equipped with a penstock decant system to remove stormwater. It is therefore recommended that a standby portable barge pump and pipeline be available to transfer storm water from the top surface of the discard disposal facility to the return water dam. This will ensure continuously disposal of discard during the wet season. The pump and pipeline should be designed to remove water from a 1:50 year, 24-hour storm event within a reasonable time (generally within 48 to 72 hours).
12 POLLUTION CONTROL MEASURES
A synergistic effect can be achieved by combining different controls together in one dump. Inclusion of the features in the table below is likely to give rise to the lowest pollution potential for the dump, taking not only the capital and operating costs into account, but also the contingent liability associated with potential water contamination.
Table 12: Pollution Control Measures
Control Type Description
Infiltration minimization
Topsoil removed from the footprint area will be stockpiled for future use as soil cover material.
The side slopes and berms of the coal discard dump will be covered with soil during the operational phase.
The soil cover will assist in reducing any contact of rainfall runoff with the coal discard. In addition, the side slopes and berms will be vegetated to minimize erosion. The vegetated soil cover will also deplete oxygen.
The top surface and benches of the dump will be graded back towards the hill slopes. This will reduce the total seepage flux and hence the contaminant load.
After decommissioning, the top surface of the coal discard dump will be shaped to suit drainage requirements and a soil cover provided. The cover will be vegetated to minimize the rate of erosion.
Clean water diversion
The design will include clean water diversion systems for surface water inflow from drainages within the natural catchment basins and precipitation runoff. The clean water systems will be designed so that it is not likely to spill into any dirty water system more than once in 50 years (Regulation 407 of the Water Act refers).
Appropriate erosion protection and energy dissipation measures will be included in the design (if necessary) for long-term closure requirements.
In the case of large storm events, resulting in flood conditions within the basin of the dump, temporary storm water cut-off berms will be provided to route the surplus water into the natural drainage systems.
Under drainage and re-
use of contaminated water
The design will include the implementation of an under drainage system to collect seepage for re-use as process water. This will require the conversion of the temporary storm water diversion systems into seepage collection drains.
The return water dam will be sized to accept seepage from the under drainage systems and will be designed so that it is not likely to spill into any clean water system more than once in 50 years (Regulation 407 of the Water Act refers).
The seepage rate from the under drains is expected to become negligible after decommissioning. Only small evaporation facilities will therefore be required, once Plant operations cease.
Magdalena Discard Disposal Facility – Conceptual Design 14
GCS (Pty) Ltd October 2006 SLA.06.190
Table 12: Pollution Control Measures
Control Type Description
Collection and treatment
of seepage
This tertiary control option is the least desirable from a business point of view and will only be planned for implementation as a last resort in the event that the recommended primary and secondary controls fail to meet the required standards.
Should the quality of runoff from the soil cladded side slopes prove unacceptable for discharge, it may be necessary to collect and/or treat the water in the catchment paddocks prior to discharge. The required treatment may comprise one or a combination of the following:
o Evaporation of surface runoff in the catchment paddocks o Settlement of suspended solids
13 EROSION POTENTIAL AND PROTECTION
The consequence of loss of material from the sides of discard disposal facilities is important from a water management perspective.
Firstly the water that comes in contact with the erodable coal discard, pick up solids and may carry it into the environment. Solids may find their way into water bodies where the elevated suspended solids may adversely affect aquatic ecosystems or where the deposition thereof could silt up water bodies and clog waterways.
To meet the requirements for closure, the residue deposit surface generally requires stabilization. Stabilization can range from direct re-vegetation of the surface, if possible, to multiple layered cover systems. Direct re-vegetation is an option where the available nutrients and climate make establishment of sustainable vegetation possible. This will prevent wind erosion but will generally do little to prevent infiltration of precipitation that will eventually seep from the deposit. If there are any contaminants such as heavy metals, the plants may take these up and make them accessible to grazing animals.
The factors listed in the table below are believed to be the most important in terms of erosion of layers of a dry cover system.
Table 13: Factors Affecting the Erosion of Cover Systems
Factor Comment
Slope angle Erosion rate increases with increased slope angle.
Slope length Erosion rate increases with increased slope length.
Material properties Materials with low cohesion, and small particle size (low mass) are more easily detached and entrained into water flow.
Rainfall intensity
Storm intensity defines the amount of runoff flow available for erosion - increased storm size will bring more erosion. It is not a linear relationship; a single large storm event has the ability to produce the majority of erosion experienced at a site over a long period of time.
Vegetation Vegetation increases the strength of the soil and reduces the energy of runoff by creating barriers to flow.
Base flow (antecedent moisture conditions)
Increased erosion occurs at seepage faces due to lower strength of the saturated material as compared to unsaturated material.
Magdalena Discard Disposal Facility – Conceptual Design 15
GCS (Pty) Ltd October 2006 SLA.06.190
14 CONCEPTUAL REHABILITATION PLAN
The conceptual rehabilitation plan can be summarised as follows:
14.1 Introduction
The detailed closure plan will be developed during the life of the mine. The purpose in preparing a conceptual closure plan is to ensure that the design, construction and operating procedures are compatible with the achievement of final closure and rehabilitation to accepted environmental standards and at a reasonable cost. It is anticipated that the conceptual plan will be updated periodically before the preparation of the detailed closure plan.
The rehabilitation programme will be prepared in accordance with the BATNEEC principle (best available technology not exceeding economic cost).
The minimum objectives for the closure and rehabilitation of a residue disposal facility must be to prevent air and water pollution in accordance with the requirements of the relevant regulations and with good international practice. The intended end use should take into consideration the prior land use and the location with respect to current and potential future socio-economic development.
14.2 Objectives
The objectives of the closure and rehabilitation measures will be:
To establish a self-sustaining solution with a minimum of on-going maintenance;
To minimise off-site impacts;
To create safe and stable landforms;
To return the site to beneficial land use; and,
To obtain a closure certificate.
In achieving these objectives, the measures must satisfy the regulations and conform to good international practice.
14.3 Final Geometry
The required final surface geometry will be achieved by the mechanical construction method during the life of the facility, particularly during the final years, and by subsequent limited earthworks. It is intended that the upper surface of the dump should be shaped to retain surface run-off and thus to prevent the erosion of the outer slopes and the discharge of polluted solids to the environment.
The outer slopes of the dump will be shaped and rehabilitated during the operational life of the facility.
14.4 Final Surface Cover
Topsoil removed from the dump base area will be stockpiled and used for capping the coal discard dump.
Magdalena Discard Disposal Facility – Conceptual Design 16
GCS (Pty) Ltd October 2006 SLA.06.190
A direct soil cover is considered the best compromise in terms of cost and performance and is most likely to satisfy closure requirements. This approach involves the placement of topsoil on the side slopes, step-ins and top surface (1,0m thick) at the coal discard dump. This approach allows storm water to run off the deposit quickly and avoid becoming polluted. Vegetation is to be established as soon as the soil cover is in place. Some vegetation will probably establish itself naturally.
14.5 Control of Water
The system of diversion canals to prevent storm water run-off from entering the site will remain in place.
Surface water falling on the top surface of the dump will be held on the dump. The top surface may be divided into separate paddocks, or the water may be allowed to drain in a controlled fashion to a pool. The decision will depend upon information gathered during the operating period. For the pool option, consideration will be given to the need for a buried HDPE liner over the potential pool area, to prevent seepage to the groundwater. An emergency spillway for decanting excess water from the top of the dump will also be considered.
The run-off on the surface of the dump will be further controlled by the creation of low bunds. The establishment of vegetation will reduce erosion but, where necessary, more permanent structures will be constructed with selected material.
14.6 Vegetation
Vegetation on the surface and outer slopes of the dump will reduce erosion and dust generation. It will be necessary to obtain the maximum benefit from the residual moisture in the soil and from the seasonal rainfall. Thus, efforts should be made to commence the establishment of vegetation during the operating life of the facility. It will certainly be possible to begin to establish vegetation on the outer slopes. It is anticipated that the mine will carry out experiments from the time of commissioning of the project. Information available from re-vegetation exercises in similar conditions will be gathered during the planning of the tests.
15 CONCEPTUAL DRAWINGS
The conceptual drawings are listed in the table below and are included in Appendix E.
Table 14: Conceptual Drawings
Drawing No. Date Description
SLA.06.190/1 October 2006 General Arrangement Pre-deposition Civil Works
SLA.06.190/2 October 2006 General Arrangement Final Layout
SLA.06.190/3 October 2006 Typical Sections and Details
SLA.06.190/4 October 2006 Typical Sections and Details
SLA.06.190/5 October 2006 Locality Plan
Magdalena Discard Disposal Facility – Conceptual Design 17
GCS (Pty) Ltd October 2006 SLA.06.190
16 CONCLUSIONS AND RECOMMENDATIONS
The following conclusions can be drawn from the conceptual design phase:
The disposal facility has been designed to minimise the impact of the contaminated water on the surrounding environment. The disposal facility is not expected to give rise to unacceptable levels of contamination of groundwater, surface runoff or air.
The proposed pollution control measures have been selected to minimise the operational and maintenance costs after decommissioning. Management input after decommissioning is expected to be limited to monitoring and maintenance of the cover and storm water control structures. Active control systems such as water treatment systems are not likely to be required after decommissioning.
It is recommended that:
The discard disposal facility should form part of a water quality management strategy and water balance for the entire mine complex.
A detailed design should be prepared for the pre-deposition civil works.
A code of practice and operating manual should be prepared to ensure that the facility is designed, operated and rehabilitated in a responsible manner.
Magdalena Discard Disposal Facility – Conceptual Design
GCS (Pty) Ltd October 2006 SLA.06.190
Appendix A
Site Selection
Magdalena Discard Disposal Facility – Conceptual Design
GCS (Pty) Ltd October 2006 SLA.06.190
Appendix B
Geotechnical Investigations
Est. 1987
Reg No: 2004/00765/07DIRECTORS: AC Johnstone, W. Dressel, AWC Marais, SE Scawthon, AH Barbour (Non-exec) www.gcs-sa.biz
Johannesburg Durban
Suite 11, Hillcrest Office Park 2 Old Main Road, Hillcrest PO Box 819, Gillitts, 3603
South Africa Tel: +27 (0)31 765 2088 Fax: +27 (0)31 765 8201
Our Ref: SLA.06.190 Your Ref:
PROPOSED MAGDALENA COLLIERY DISCARD FACILITY RESULTS OF GEOTECHNICAL INVESTIGATION
Compiled
by
GCS (Pty) Ltd
L B FITSCHEN Pr.Sci.Nat. Senior Engineering Geologist
for GCS (Pty) Ltd MARCH 2006
Proposed Discard Facility, Magdalena Colliery
GCS (Pty) Ltd October 2006 SLA.06.190
TABLE OF CONTENTS 1. TERMS OF REFERENCE .......................................................................................... 1 2. INFORMATION SUPPLIED AND CONSULTED........................................................ 1 3. FIELD INVESTIGATION............................................................................................. 1 4. SITE LOCATION AND DESCRIPTION ...................................................................... 2 4.1 Topography and Drainage........................................................................................ 2 4.2 Geology and Soils..................................................................................................... 3
4.2.1 Residual and Transported Soils................................................................... 3 4.2.2 Rock Types .................................................................................................... 4
5. LABORATORY TESTING .......................................................................................... 5 6. ENGINEERING GEOLOGICAL AND SOIL CONDITIONS AFFECTING
DEVELOPMENT......................................................................................................... 5 6.1 Materials Classification ............................................................................................ 5 6.2 Site Drainage ............................................................................................................. 7
6.2.1 Surface Drainage........................................................................................... 7 6.2.2 Permeability of Soils ..................................................................................... 7
6.3 Erosion Potential....................................................................................................... 7 6.4 Founding Conditions ................................................................................................ 8 6.5 Site Earthworks ......................................................................................................... 8 6.6 Slope Stability ........................................................................................................... 9 7. CONCLUSIONS AND RECOMMEDATIONS............................................................. 9 8. REFERENCES.......................................................................................................... 10
LIST OF TABLES TABLE 1: GPS CO-ORDINATES FOR SOIL PROFILE POSITIONS ................................... 2
TABLE 2: SUMMARY OF LABORATORY TESTING SCHEDULE....................................... 5
TABLE 3: LABORATORY TEST SUMMARY........................................................................ 6
TABLE 4: SUMMARY OF FOUNDATION LEVELS .............................................................. 8
LIST OF APPENDICES Appendix 1 SOIL PROFILE DESCRIPTIONS Appendix 2 LABORATORY TEST RESULTS
LIST OF FIGURES Figure 1 Site Plan
Proposed Discard Facility, Magdalena Colliery page - -
GCS (Pty) Ltd October 2006 SLA.06.190
1
1. TERMS OF REFERENCE
Zinoju Investments (Pty) Ltd appointed GCS (Pty) Ltd to conduct a geotechnical
investigation as a part of the EMP, for a coal discard facility at Magdalena Colliery, situated
near to Dundee in KwaZulu-Natal. Mined coal is presently being transported by road to
Dundee, where it is processed. It is the intention of Zinoju Investments to construct a
washing plant at the mine that will require a discard facility. Two possible sites were
investigated, the positions of which are given in Figure 1. The purpose of this report is to
review the results of the geotechnical investigation carried out during September 2006, and
to give conclusions and recommendations with regard to founding and earthworks on the
sites for the proposed discard facility.
Given below are the results of this review.
2. INFORMATION SUPPLIED AND CONSULTED
For the purpose of the review, the following information was supplied or consulted:
• The Geological Survey of South Africa 1: 250 000 scale geological series map, Sheet
2730 Vryheid 1988 Edition;
• The Topographical Map 2730 CC - Osizweni 1996 Edition at a scale of 1: 50 000;
• A plan entitled ‘Magdalena Colliery, Proposed Mining Layout Plan’ compiled by
GCS (Pty) Ltd at a scale of 1: 2 500, July 2006.
• Electronic copy of a plan entitled ‘Zinoju Investments, Conversion of an Old Order
Mining Right’ at a scale of 1: 10 000 supplied by Mr F W Talbot.
3. FIELD INVESTIGATION
The sites were visited on the 27th September 2006, during which an appraisal was made of
the general geology and geomorphology of the sites. Soil profiles that have been exposed in
eroded gullies and by mining operations were recorded according to the method outlined in
Jennings et al 1, and the profile descriptions are given in Appendix 1. Rock descriptions were
recorded according to the Core Logging Committee 2. The co-ordinate positions of these soil
profiles were recorded using a hand held Garmin GPS 5, and these are listed in Table 1,
below.
Disturbed soil samples were collected from selected soil horizons and submitted to Soilco in
Pietermaritzburg for analysis. The results of the laboratory tests were used to identify and
Proposed Discard Facility, Magdalena Colliery page - -
GCS (Pty) Ltd October 2006 SLA.06.190
2
classify the materials underlying the site, and are given in Appendix 2.
TABLE 1: GPS CO-ORDINATES FOR SOIL PROFILE POSITIONS
MAGDALENA DISCARD FACILITY WGS84 / SA Grid
Position Y Co-ordinate X Co-ordinate Soil Profile 1 31 Y0078593 X3096610 Soil Profile 2 31 Y0078539 X3096687 Soil Profile 3 31 Y0078856 X3096970 Soil Profile 4 31 Y0078884 X3096023 Soil Profile 5 31 Y0078878 X3096160 Soil Profile 6 31 Y0078903 X3096260 Soil Profile 7 31 Y0079187 X3096322
4. SITE LOCATIONS AND DESCRIPTION
The sites of the proposed Magdalena discard facility are located approximately 21km to the
north of Dundee. The site can be located by travelling north on the P272 road from Dundee
for approximately 24 km, and then left off this road for approximately 2km.
A large area of site 1 has sandstone rock exposed at the surface in a wide area of erosion
with scattered loose dolerite boulders that have been deposited over it. Some parts of the
exposed sandstone have very soft rock with residual soils overlying it that are vegetated by
grass and small trees. Site 1 is rectangular in shape and covers an area of approximately
34Ha. This site is situated over pre-existing underground workings. The position of the
Magdalena opencast strip is situated across the western half of site 1, of which a large
portion of the southern half is presently being excavated. After mining, this strip will be
backfilled and will form a part of the dump area.
Site 2 covers an area of approximately 44Ha, is triangular in shape and is vegetated by short
grass and small trees. Fairly wide and deep drainage channels that have eroded down to
bedrock traverse the site. A small, low discard dump and associated surface trenches from
previous mining operations lie in the south of the site.
4.1 Topography and Drainage
The surface topography of site 1 is very uneven as a result of erosion of wide drainage
channels and the deposition of large dolerite boulders. The natural ground of this site has
gradients that range between 1: 15 (4o) and 1: 20 (6o), and slopes in an easterly direction.
Surface runoff is therefore expected to flow across the site in an easterly direction, draining
Proposed Discard Facility, Magdalena Colliery page - -
GCS (Pty) Ltd October 2006 SLA.06.190
3
into nearby farm dams.
The surface topography of site 2 is relatively flat excepting where northward flowing drainage
channels have formed. The natural ground of this site generally has a gradient of 1: 30 (2o).
Surface runoff is expected to flow across the site in an easterly direction into the drainage
channels and nearby farm dams.
Surface runoff from site 1 will flow into farm dams situated further downstream than the
runoff from site 2. The potential for the spread of pollutants over a larger area is therefore
greater from site 2. Runoff from both sites will flow into the northward flowing
Bloubankspruit.
4.2 Geology and Soils
The soil and rock types at the two sites are similar, and these are discussed as one.
Both sedimentary and intrusive rocks underlie the sites. The sedimentary rocks are of the
Vryheid Formation, which forms a part of the Ecca Group, Karoo Sequence. The Vryheid
Formation consists of coal seams, grits, sandstone, shale, arkoses and mudrocks. These
sedimentary rocks have been intruded by much younger dolerite rock. Most intrusions of
dolerite rock into Karoo Sequence rocks are horizontal, sheet-like and concordant, but they
also occur as gently and evenly inclined discordant sheets to the host sediments. The
dolerite sill observed at the site, extends to under site 1, and is concordant with a near
horizontal orientation. Residual soils overly the bedrock and are in turn overlain by hillwash.
4.2.1 Residual and Transported Soils
The transported soils observed at the site consist of hillwash, and were observed in
Soil Profiles 1 to 7. These soils are slightly moist, dark tan brown, medium dense,
microshattered, silty clay with traces of fine and medium calcareous gravel that is
generally 0.4m in thickness at the surface.
The residual soils at the site consist of residual sandstone and residual dolerite soils.
Residual sandstone soils were recorded in Soil Profiles 1 to 6 and residual dolerite
soils were recorded in Soil Profile 7.
The residual sandstone soils can generally be described as follows:
Proposed Discard Facility, Magdalena Colliery page - -
GCS (Pty) Ltd October 2006 SLA.06.190
4
(a) Moist, dark brown, soft, slightly slickensided, silty clay with traces of fine and
medium calcareous gravel, with a thickness of between 0.2m and 1.0m generally
occurring from a depth of 0.4m;
(b) Moist, greyish brown, soft to firm, slightly slickensided, silty clay with traces of
fine and medium calcareous gravel with a thickness of between 0.5m and 1.8m
and generally occurring from a depth of between 0.5m and 1.4m;
(c) Moist, greenish brown mottled orange brown, firm, slickensided, silty clay with
traces of fine and medium calcareous gravel with a thickness of between 0.4m
and 2.3m and generally occurring from a depth of between 1.0m and 2.7m.
The residual dolerite soils were recorded in the opencast mine excavation and are
the remnants of a horizontal concordant dolerite sill. These soils can be described as
follows:
a) Slightly moist, reddish brown, firm, shattered silty clay with traces of coarse and
boulder dolerite gravel at a depth of 2.7m and with a thickness of 1.1m.
4.2.2 Sandstone Rock
The sandstone rock at the site was observed in Soil Profiles 1 to 6. This rock can
generally be described as light grey, completely weathered, thinly bedded, medium to
very coarse-grained soft rock. The thickness of this sandstone was found to be 0.5m
in Soil Profiles 1 to 3, but could not be determined in profiles 4 to 6, as it was not
completely exposed. The depth to the sandstone measured in the soil profiles ranges
between 1.4m and 5.0m. The dip of the sandstone measured at Soil Profile 1 is 15o
west, with a north-south strike. It is expected that a back actor will refuse on this rock
layer.
4.2.3 Shale Rock
The shale rock at the site was observed in Soil Profiles 1,2 and 7. The thickness of
the shale could not be determined due to the depth of exposures. This rock can
generally be described as follows:
a) Light purplish grey banded light orange brown, medium weathered, very thinly
bedded, very fine grained, soft rock and occurs at depths of 3.5m and 4.5m and
is at least 0.9m thick (in Soil Profiles 1 and 2);
Proposed Discard Facility, Magdalena Colliery page - -
GCS (Pty) Ltd October 2006 SLA.06.190
5
b) Brownish yellow, completely weathered, very thinly bedded, very fine grained,
soft rock and occurs at a depth of 2.7m and is at least 1.3m thick (in Soil Profile
7).
It is expected that the shale underlying the sandstone in Soil Profiles 1 and 2,
similarly underlies the sandstone described in Soil Profiles 3 to 6. It is likely that a
back actor will refuse on this shale layer.
5. LABORATORY TESTING
Disturbed soil samples were collected from selected soil horizons and submitted to Soilco in
Pietermaritzburg, for analysis. A summary of the samples collected and the testing schedule
are provided in Table 1. The detailed laboratory test results are given in Appendix 2.
TABLE 2: SUMMARY OF LABORATORY TESTING SCHEDULE
Soilco Laboratory Ref. No.
Soil Profile
No.
Depth Of
Sample (m)
Shear Box Test
Compaction Test
Grading Analysis
Atterberg Limits
Pinhole Test
P10813 SP 2 1.0 - 2.3 X X P10814 / 6488 SP 2 2.3 - 4.0 X X X
P10815 SP 5 0.5 – 1.0 X X P10816 SP 5 1.0 – 1.4 X X P10817 SP 7 1.6 – 2.7 X X
DISCARD - X X
6. ENGINEERING GEOLOGICAL AND SOIL CONDITIONS AFFECTING DEVELOPMENT
6.1 Materials Classification
A total of 7 disturbed soil samples were submitted for laboratory analysis. Tests conducted
on these samples include full grading and hydrometer and Atterberg Limits, and on one of
the samples a pinhole test to test for dispersivity. One sample consisting of coal discard was
collected from the discard facility at the coal processing plant in Dundee, and was tested for
compaction and shear parameters.
The results of the analysis are given in Appendix 2, and are summarised in Table 2 below:
Proposed Discard Facility, Magdalena Colliery page - -
GCS (Pty) Ltd October 2006 SLA.06.190
6
TABLE 3: LABORATORY TEST SUMMARY
Laboratory Number P10813 P10814 6488 P10815 P10816 P10817
Source SP2 SP2 SP5 SP5 SP7 DISCARD
Material Sandy Clay
Sandy Clay
Clayey Sand
Clayey Sand Silty Clay Coal
Discard
Laboratory and Field Data
Depth (m) 1.0 - 2.3 2.3 - 4.0 0.5 - 1.0 1.0 - 1.4 1.6 - 2.7 0 13.2 100 100 100 100 4.75 97 98 98 99 100 2,00 91 96 97 97 99
0,425 85 89 88 89 97 0,075 63 62 56 50 72 0.060 61 61 55 46 70 0,050 60 59 53 43 68 0.026 54 52 44 34 58 0,015 48 45 37 29 50 0.010 46 45 35 27 49 0.074 44 39 33 27 47 0,005 43 37 32 25 43
0.0036 41 36 28 25 41 0.002 39 34 25 21 39
0.0015 37 32 21 20 37 Coarse Sand (%) 7 7 9 8 2 Fine Sand(%) 37 38 43 52 31 Silt(%) 16 20 19 17 25
Soil Mortar
Clay(%) 40 35 29 23 42 Liquid Limit(%) 67 62 43 37 55 Plasticity Index(%) 38 36 25 21 32 Linear Shrinkage(%) 15 18 12 10 15
Atterberg Limits
Equivalent PI(%) 32.3 32.1 22.1 18.7 31.1 Grading Modulus 0.61 0.53 0.60 0.64 0.32 TRH 14 Class A-7-6(16) A-7-6(16) A-7-6(10) A-6(6) A-7-6(18) Potential Expansiveness Very High Very High Low Medium High
Internal Angle of Friction 45o Shear Parameters Cohesion 7
OMC % 8.7 Compaction Parameters MDD kg/m3 1469
Erosion None Pinhole Test Classification ND1
According to the Unified Classification System, the residual sandstone soils are classified as
sandy clays and clayey sands with clay contents varying between 23% and 40%. The
residual dolerite sill soils are classified as silty clays with clay content of 42%.
The samples tested from site 1 are highly plastic, display very high potential expansiveness
and can be classified as A-7-6 (16) in terms of the TRH14 classification. The samples tested
from site 2 are moderately plastic, display medium potential expansiveness and can be
classified as A-7-6 (10) and A-6 (6) in terms of the TRH14 classification. The sample tested
from the residual dolerite sill is highly plastic, displays a high potential expansiveness and
can be classified as A-7-6 (18) in terms of the TRH14 classification.
Proposed Discard Facility, Magdalena Colliery page - -
GCS (Pty) Ltd October 2006 SLA.06.190
7
The shear parameters of the sample collected from the existing discard facility, reflects an
internal angle of friction of 45o and cohesion of 7kN/m3. The maximum dry density of the
sample is 1469kg/m3, measured at 95% modified AASHTO.
The sample from Soil Profile 2 tested for dispersivity is non erosive and can be classified as
ND1 (non dispersive).
6.2 Site Drainage
The drainage of the sites is discussed below, with respect to the surface drainage and the
permeability of soils.
6.2.1 Surface Drainage
The surface runoff at the site is expected to flow in an easterly direction along
drainage channels that channel water to the Bloubankspruit. 6.2.2 Permeability of Rock and Soils
Water seepage was not observed at any of the positions where soil profiles were
recorded or in any of the mining excavations at the site, during the site visit.
The permeability of the soils at the site is expected to be low as a result of their high
clay contents. The grading analysis results indicate that when the materials at the
site are compacted they are likely to have moderately low permeability, restricting the
spread of pollutants from the site to surrounding areas.
The unfractured and continuous nature of the sandstone and shale at the site is likely
to form an impermeable barrier for water percolation.
6.3 Erosion Potential
Due to the relatively gentle topography of the sites, sheet erosion as a result of surface
water run-off in this area is not expected to be significantly high. The gradient of site 1 is
steeper, but erosion is expected to be minimal as most of the site consists of sandstone rock
exposed at the surface. Soils that are to be stockpiled for rehabilitation purposes are
susceptible to erosion, and the necessary soil conservation methods need to be adopted in
order to prevent this. The test results indicate that they are non-dispersive.
Proposed Discard Facility, Magdalena Colliery page - -
GCS (Pty) Ltd October 2006 SLA.06.190
8
6.4 Founding Conditions
The soft sandstone rock that lies directly over the soft shale rock at both sites is considered
to be a suitable foundation for the discard facility. The dip orientation of the sandstone rock
in relation to the gradient of the sites may result in the discard facility being founded on both
soft sandstone and soft shale rock. The depth to the soft sandstone/shale rock was
measured to be between 1.4m and 5.0m.
The expected foundation depths on the soft sandstone/shale rock are summarised in Table
4 below:
TABLE 4: SUMMARY OF FOUNDATION LEVELS Soil Profile Position Foundation Type
SP1 SP2 SP3 SP4 SP5 SP6 SP7
Soft Sandstone/Shale Rock Depth (m) 3.0 4.0 4.3 3.0 1.4 5.0 2.7
At site 1, where the footprint of the discard facility extends over a large portion of both the
backfilled opencast pit and soft sandstone/shale rock, differential settlement is likely to
occur. Site 1 will also be situated over underground workings from previous mining
operations, which may fail when loaded, affecting the construction of the discard facility as
well as creating the potential for pollutant flow to the groundwater.
The orientation of and the highly plastic and high potentially expansive nature of the dolerite
sill that extends under site 1, makes it unsuitable founding material and should be removed
prior to the deposition of discard. The very soft shale rock below the dolerite sill is likely to be
suitable founding material.
Prior to the preparation of the site for deposition of the discard, it is recommended that the
surface topsoil layer of hillwash be removed and stockpiled in such a way that it is preserved
for future rehabilitation purposes. Similarly, the underlying soils that are excavated should
also be stockpiled and preserved for rehabilitation purposes.
6.5 Site Earthworks
Excavation of the hillwash soils and residual soils at the site is not expected to present any
difficulties, and can generally be classed as soft excavation.
Should excavations be necessary in the soft sandstone rock, blasting may be required.
Proposed Discard Facility, Magdalena Colliery page - -
GCS (Pty) Ltd October 2006 SLA.06.190
9
6.6 Slope Stability
The slope of the natural ground surface at the two sites is very gentle, with a gradient of
between 1: 15 (4o) and 1: 20 (60) at site 1 and 1: 30 (20) at site 2, in an easterly direction.
Excavations to create level deposition platforms will expose deeper sidewalls in the west of
the site. The cut slopes should not exceed the angle of internal friction of 30° (1:1.73).
The placement of any discard should be preceded by the removal of all natural vegetation
and hillwash soils. The discard should be deposited in layers, each layer being properly
compacted to a minimum of 95% of Modified AASHTO maximum dry density of 1469kg/m3,
prior to the placement of the subsequent layer. The maximum batter slopes of the discard
dump should be 1: 1,73 (30°).
7. CONCLUSIONS AND RECOMMEDATIONS
A site investigation was carried out for the proposed Magdalena discard facility on the 27th
September 2006, during which exposed soil profiles were recorded. Two sites were
investigated that lie in close proximity to each other. The sites are underlain by hillwash and
residual sandstone soils. Soft sandstone and shale rock underlie these soils. These rocks
have been intruded by a concordant, horizontally orientated dolerite sill.
Disturbed samples of the residual sandstone and dolerite sill were collected and tested. The
soils at site 1 were found to be highly plastic and display a very high potential
expansiveness. The soils at the site 1 are classified as sandy clays. The soils at site 2 were
found to be moderately plastic and display a medium potential expansiveness. The soils at
the site 2 are classified as clayey sands. The dolerite soils were found to be highly plastic
and display a high potential expansiveness. The dolerite soils are classified as silty clays.
A disturbed sample was also collected from the existing discard dump at the washing plant
in Dundee order to determine the shear and compaction parameters.
Water seepage was not observed at any of the positions where soil profiles were recorded or
in any of the mining excavations at the site, during the site visit.
The permeability of the soils at the site is expected to be low as a result of their high clay
contents.
The unfractured and continuous nature of the sandstone and shale at the site is likely to form
an impermeable barrier for water percolation.
Proposed Discard Facility, Magdalena Colliery page - -
GCS (Pty) Ltd October 2006 SLA.06.190
10
The soft sandstone rock that lies directly over the soft shale rock at both sites is considered
to be a suitable foundation for the discard facility. The dip orientation of the sandstone rock
in relation to the gradient of the sites may result in the discard facility being founded on both
soft sandstone and soft shale rock.
At site 1, where the footprint of the discard facility extends over a large portion of both the
backfilled opencast pit and soft sandstone/shale rock, differential settlement is likely to
occur. Site 1 will also be situated over underground workings from previous mining
operations, which may fail when loaded, affecting the construction of the discard facility as
well as creating the potential for pollutant flow to the groundwater.
The orientation, highly plastic and high potentially expansive nature of the dolerite sill that
extends under site 1, is unsuitable founding material and should be removed prior to the
deposition of discard. The very soft shale rock below the dolerite sill is likely to be suitable
founding material.
Prior to the preparation of the site for deposition of the discard, it is recommended that the
surface topsoil layer of hillwash be removed and stockpiled in such a way that it is preserved
for future rehabilitation purposes. Similarly, the underlying soils that are excavated should
also be stockpiled and preserved for rehabilitation purposes. The residual sandstone soils at
the site are not dispersive, but are susceptible to erosion.
Excavation of the hillwash and residual soils can generally be classed as soft excavation.
Should excavations be necessary in the soft sandstone rock, blasting may be required.
The slope of the natural ground surface at the two sites is very gentle. Cut banks exposed by
excavations to platform level should not exceed a batter of 1: 1.73 (30o).
Discard should be placed in layers, and compacted to a minimum of 95% modified AASHTO
maximum dry density prior to placement of the subsequent layer. The maximum batter
slopes of the discard dump should be 1: 1,73 (30°).
8. REFERENCES
• Jennings, J.E., Brink, A.B.A., and Williams, A.A.B. (1973), Revised Guide to Soil
Profiling for Civil Engineering Purposes in Southern Africa, Trans. South African Inst.
Civil Eng., 15, 3 –12.
• Core Logging Committee of the South African Section of The Association of
Engineering Geologists (1976). A Guide to Core Logging for Rock Engineering.
Proposed Discard Facility, Magdalena Colliery page - -
GCS (Pty) Ltd October 2006 SLA.06.190
11
Proceedings of the Symposium on Exploration for Rock Engineering, Johannesburg,
November 1976.
L B FITSCHEN Pr.Sci.Nat.
Senior Engineering Geologist for GCS (Pty) Ltd
SEPTEMBER 2006
Proposed Discard Facility, Magdalena Colliery
GCS (Pty) Ltd October 2006 SLA.06.190
APPENDIX 1
SOIL PROFILE DESCRIPTIONS
LEGEND DESCRIPTION
0.4m
0.9m
1.5m
3.0m
3.5m
5.0m
Project No. SLA.06.1901) Soil Profile recorded from eroded drainage channel2) No water table was observed
Light grey, completely weathered, thinly bedded, medium to very coarse grained SOFT ROCK. Vryheid Sandstone Formation
Light purplish grey banded light orangy brown, medium weathered, very thinly bedded, very fine grained, SOFT ROCK. Vryheid Shale Formation
Slightly moist, dark tan brown, medium dense, microshattered, silty CLAY with traces of fine and medium calcareous GRAVEL. Hillwash.
Moist, dark brown, soft, slightly slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Moist, greyish brown, soft to firm, slightly slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Moist, greenish brown mottled orangy brown, firm, slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Magdalena Colliery Proposed Discard Facility
Geotechnical Investigation
1.0
1.5
4.0
3.0
2.0
Project:
DEPTH
SOIL PROFILE No. 1
0.0
0.5
3.5
2.5
4.5
5.0
5.5
LEGEND DESCRIPTION
0.4m
1.0m
2.3m
4.0m
4.5 4.5m
5.4m
Project No. SLA.06.1901) Soil Profile recorded from eroded drainage channel2) No water table was observed3) Disturbed sample taken for analysis from 1.0m to 2.3m and 2.3m to 4.0m
SOIL PROFILE No. 2
3.0
1.0
1.5
2.0
2.5
DEPTH 0.0
0.5
3.5
4.0
Project:
5.0
5.5
Slightly moist, dark tan brown, medium dense, microshattered, silty CLAY with traces of fine and medium calcareous GRAVEL. Hillwash.
Moist, dark brown, soft, slightly slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Moist, greyish brown, soft to firm, slightly slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Moist, greenish brown mottled orangy brown, firm, slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Light grey, completely weathered, thinly bedded, medium to very coarse grained SOFT ROCK. Vryheid Sandstone Formation
Light purplish grey banded light orangy brown, medium weathered, very thinly bedded, very fine grained, SOFT ROCK. Vryheid Shale Formation
Magdalena Colliery Proposed Discard Facility
Geotechnical Investigation
LEGEND DESCRIPTION
0.4m
0.9m
2.7m
4.3m
4.5
4.8m
Project No. SLA.06.1901) Soil Profile recorded from eroded drainage channel2) No water table was observed
TRIAL HOLE No. 3
Geotechnical Investigation
0.5
1.0
0.0
1.5
2.0
2.5
3.0
3.5
4.0
Project:
Magdalena Colliery Proposed Discard Facility
5.0
5.5
DEPTH
Slightly moist, dark tan brown, medium dense, microshattered, silty CLAY with traces of fine and medium calcareous GRAVEL. Hillwash.
Moist, dark brown, soft, slightly slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Moist, greyish brown, soft to firm, slightly slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Moist, greenish brown mottled orangy brown, firm, slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Light grey, completely weathered, thinly bedded, medium to very coarse grained SOFT ROCK. Vryheid Sandstone Formation
LEGEND DESCRIPTION
0.4m
0.8m
1.8m
3.0m
4.5
Project No. SLA.06.1901) Soil Profile recorded from eroded drainage channel
4.0
Investigation
SOIL PROFILE No. 4DEPTH
0.0
0.5
1.5
2.0
2.5
Project:
1.0
Magdalena Colliery Proposed Discard Facility
3.0
3.5
Light grey, completely weathered, thinly bedded, medium to very coarse grained SOFT ROCK. Vryheid Sandstone Formation
Geotechnical
5.0
5.5
Moist, greyish brown, soft to firm, slightly slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Moist, greenish brown mottled orangy brown, firm, slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Slightly moist, dark tan brown, medium dense, microshattered, silty CLAY with traces of fine and medium calcareous GRAVEL. Hillwash.
Moist, dark brown, soft, slightly slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
2) No water table was observed
LEGEND DESCRIPTION
0.5m
1.0m
1.4m
4.5
Project No. SLA.06.190
4.0
Geotechnical Investigation
SOIL PROFILE No. 5DEPTH
0.0
0.5
1.0
3.0
3.5
1.5
2.0
Moist, dark brown, soft, slightly slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Moist, greyish brown, soft to firm, slightly slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Moist, greenish brown mottled orangy brown, firm, slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Slightly moist, dark tan brown, medium dense, microshattered, silty CLAY with traces of fine and medium calcareous GRAVEL. Hillwash.
Light grey, completely weathered, thinly bedded, medium to very coarse grained SOFT ROCK. Vryheid Sandstone Formation
Project:
Magdalena Colliery Proposed Discard Facility
2.5
1) Soil Profile recorded from eroded drainage channel2) No water table was observed3) Disturbed sample taken for analysis from 0.5m to 1.0m and 1.0m to 1.4m
LEGEND DESCRIPTION
0.4m
1.4m
2.7m
4.5
5.0m
3.0
Geotechnical Investigation
SOIL PROFILE No. 6DEPTH
0.0
2.5
2.0
Project:
5.0
5.5
3.5
4.0
0.5
1.0
1.5
Magdalena Colliery Proposed Discard Facility
Slightly moist, dark tan brown, medium dense, microshattered, silty CLAY with traces of fine and medium calcareous GRAVEL. Hillwash.
Moist, greenish brown mottled orangy brown, firm, slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Light grey, completely weathered, thinly bedded, medium to very coarse grained SOFT ROCK. Vryheid Sandstone Formation
Moist, dark brown, soft, slightly slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Moist, greyish brown, soft to firm, slightly slickensided, silty CLAY with traces of fine and medium calcareous GRAVEL. Residual sandstone
Project No. SLA.06.1901) Soil Profile recorded from eroded drainage channel2) No water table was observed
LEGEND DESCRIPTION
0.3m
1.6m
2.7m
4.0m
Slightly moist, reddish brown, firm, shattered silty CLAY with traces of coarse and boulder dolerite gravel. Residual dolerite sill.
Brownish yellow, completely weathered, very fine grained, very thinly bedded, VERYSOFT ROCK shale. Vryheid shale formation.
Abundant, fine to coarse highly weathered shale GRAVEL in a matrix of slightly moist, brownish yellow, silty clay. Overall consistency is medium dense.
Slightly moist, dark tan brown, medium dense, microshattered, silty CLAY with traces of fine and medium calcareous GRAVEL. Hillwash.
DEPTH
3.0
2.0
2.5
0.0
Geotechnical Investigation
SOIL / ROCK PROFILE No. 7
1.5
3.5
4.0
0.5
1.0
Project:
Magdalena Colliery
4.5
5.0
5.5
Project No. SLA.06.1901) Profile recorded from side of opencast excavation2) No water table was observed
Proposed Discard Facility
Geotechnical Investigation
Proposed Discard Facility, Magdalena Colliery
GCS (Pty) Ltd October 2006 SLA.06.190
APPENDIX 2
LABORATORY TEST RESULTS
SOILCO MATERIALS INVESTIGATIONS (PTY) LTD CIVIL ENGINEERING MATERIALS TESTING LABORATORY Reg. No. : 1965/09585/07
Client : GCS (PTY0 LTD Job Card No. :Project : MAGDALENA COLLIERS Date Received :
Date Tested :Sample Delivered by : 0 Date Reported :
Sample Number : P10815 Field or Pit Number : TP 5
Position in field : 0.60 Depth ( mm ) : 500 - 1000
Sample Description : Light olive brown clayey sand
Equivalent PI : 22.1 Clay fraction of whole sample ( % < 2µ ) : 25
FINE MEDIUM COARSE FINE MEDIUM COARSE FINE MEDIUM COARSE
CLAY FRACTION SILT FRACTION SAND FRACTION GRAVEL FRACTION
The above test results are pertinent only to the samples received and tested at the laboratory. This report shall not be reproduced, except in full, without the prior consent of SOILCO MATERIALS INVESTIGATIONS (PTY) LTD.
11 HALSTED ROAD - 24 DAVLEN PARK - MKONDENI - P.O. BOX 846 - PIETERMARITZBURG - 3200TELEPHONE : ( 033 ) 386 9095 TELEFAX : ( 033 ) 386 1878 email : [email protected]
For Soilco:
POTENTIAL EXPANSIVENESS GRAPH
PARTICLE SIZE DISTRIBUTION CHART
0
2006-09-29
0
2006-10-11
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70
Equi
valen
t PI
Clay fraction of whole sample ( % < 2µ )
Very High
High
Medium
Low
0
10
20
30
40
50
60
70
80
90
100
0.0 0.0 0.0 0.1 1.0 10.0 100.0
% F
iner
Tha
n
Proposed Discard Facility, Magdalena Colliery
GCS (Pty) Ltd October 2006 SLA.06.190
FIGURE 1
SITE PLAN
1
SITE 1
SITE 2
DISCARD FACILITY SITES
SP1
SP2
SP3
SP4
SP5
SP6 SP7
Magdalena Discard Disposal Facility – Conceptual Design
GCS (Pty) Ltd October 2006 SLA.06.190
Appendix C
Capacity Analysis
1.40 t/m^3Deposition Vertical Elevation Area Area Volume Acc. Acc. Time Acc. Acc. Rate of
rate height volume tonnage time time rise(tpm) (m) (amsl) (m^2) (ha) (m^3) (m^3) (tonnes) (months) (months) (years) (m/y)
16 800 0 1256 6 315 0.0 0 0 0 0.0 0.0 0.00 0.0016 800 4 1260 26 126 2.6 64 883 64 883 90 836 5.4 5.4 0.45 5.5116 800 10 1266 59 961 6.0 258 260 323 143 452 400 21.5 26.9 2.24 2.4016 800 14 1270 70 109 7.0 260 140 583 283 816 596 21.7 48.6 4.05 2.0516 800 19 1275 88 700 8.9 397 024 980 306 1 372 429 33.1 81.7 6.81 1.6216 800 24 1280 92 764 9.3 453 662 1 433 969 2 007 556 37.8 119.5 9.96 1.5516 800 28 1284 100 914 10.1 387 357 1 821 325 2 549 855 32.3 151.8 12.65 1.43
DRY DENSITY:
CAPACITY ANALYSISMagdalena Coal Discard Disposal Facility
Magdalena Discard Disposal Facility – Conceptual Design
GCS (Pty) Ltd October 2006 SLA.06.190
Appendix D
Slope Stability
218.75
175.00
131.25
87.50
43.75
00 43.75 87.50 131.25 175.00 218.75 262.50 306.25 350.00
Scenario A - Fully Drained
2.172.192.202.212.232.272.292.292.302.30
Safety Factors
218.75
175.00
131.25
87.50
43.75
00 43.75 87.50 131.25 175.00 218.75 262.50 306.25 350.00
Scenario B - Partly Drained
1.911.931.941.941.962.002.012.022.022.03
Safety Factors
218.75
175.00
131.25
87.50
43.75
00 43.75 87.50 131.25 175.00 218.75 262.50 306.25 350.00
Scenario C - Near Saturation
1.661.671.681.681.691.741.741.741.751.75
Safety Factors
Magdalena Discard Disposal Facility – Conceptual Design
GCS (Pty) Ltd October 2006 SLA.06.190
Appendix E
Conceptual Drawings
OWNER: DATEBY
DRAWN
DESIGNEDCHECKED / REVIEW
SCALEDRAWING No. REVISION
DescriptionDate No. Initials
A
GPGP
WD
A0= AS SHOWN
001 GENERAL ARRANGEMENT
ZINOJU INVESTMENT
DISCARD COALFACILITY
(CONCEPTUAL DESIGN)
RETURN WATER DAMSECTIONS & DETAILS
SLA.06.190.004.DWG
A OCT 2006 GP CONCEPTUAL DESIGN ISSUED
Copyright reserved by GCS (Pty) Ltd.
63 Wessel Road WoodmeadPO Box 2597 Rivonia 2128 South AfricaTel: +27 (0) 11 803 5726Fax: +27 (0) 11 803 5745E-mail:[email protected]
REFERENCES
PROJECT:
DRAWING TITLE:
OCT 2006
REVISIONS
CLIENT:
DescriptionDrawing no.
(P T Y) L T D
W A T E R , E N V I R O N M E N T A L & E A R T H S C I E N C E C O N S U L T A N T S
1.5
1
OCT 2006
OCT 2006
(PTY) LTD.
002 PRI-CIVIL EARTH WORKS
003 COAL DISCARD DUMP SECTIONS & DETAILS
J
5000
1500 15000 1500
1000
1000
1000
1000 1000
900
600
SELECTED HOMOGENOUS MATERIALCOMPACTED TO 100% PROCTOR DENSITYAS APPROVED BY DESIGN ENGINEER
BOX-CUT DEPTH MIN.1m DEEP
NGL
RIP $ COMPACT BASE AREA
C WALL
2
1
200mm RIP & RAP
1251 EL.
NGL
NGL
200mm RIP & RAP
SCALE 1:200
SECTION B-B
1.51
1.51
C
1251 EL.
SPILLWAY
300mm THICK GROUTEDSTONE PITCHING
SCALE 1:50
SECTION J
J
004
004
004
SPILLWAY
PUMP STATION
RETURN WATER DAMOUTLET STRUCTURE
NOT TO SCALE
RETURN WATER DAM (PLAN VIEW)
C INTAKE
300mm MILD STEEL PIPE
M004
M004
FLOW
FLANGE 600/3
25 MPa CONCRETE
25 MPa CONCRETE
20 DIA. M.S. BARS1000mm LONG AT 150mm CENTRES
SCALE 1: 25
RETURN WATER DAM OUTLET STRUCTURE (PLAN VIEW)
C INTAKE
NGL
BEND TO SUIT 300 NB305C/F MILD STEEL PIPE
FLOW
300mm MILD STEEL PIPE
25 MPa CONCRETE
25 MPa CONCRETE
50mm THICK 15 MPaCONCRETE BLINDING
WELDMESH REF 617 STEEL REINFORCEMENT
MS LOST SHUTTER
510330 REDUCERWELDMESH REF 617 STEEL REINFORCEMENT
510 I.D. PRECAST PENSTOCK RING CAST IN FLUSH AND LEVEL
SCALE 1:25
SECTION M004
NOT TO SCALE
N.G.L.
1255
1245
1250
1260
1265
1270
1275
1280
1285
1290
1295
100 150 200 250 300 350 400 4500 50
OWNER: DATEBY
DRAWN
DESIGNEDCHECKED / REVIEW
SCALEDRAWING No. REVISION
DescriptionDate No. Initials
A
GPGP
WD
A0= 1:500/AS SHOWN
001 GENERAL ARRANGEMENT
ZINOJU INVESTMENT
DISCARD COALFACILITY
(CONCEPTUAL DESIGN)
COAL DISCARD DUMPSECTIONS & DETAILS
SLA.06.190.003.DWG
A OCT 2006 GP CONCEPTUAL DESIGN ISSUED
Copyright reserved by GCS (Pty) Ltd.
63 Wessel Road WoodmeadPO Box 2597 Rivonia 2128 South AfricaTel: +27 (0) 11 803 5726Fax: +27 (0) 11 803 5745E-mail:[email protected]
REFERENCES
PROJECT:
DRAWING TITLE:
OCT 2006
REVISIONS
CLIENT:
DescriptionDrawing no.
(P T Y) L T D
W A T E R , E N V I R O N M E N T A L & E A R T H S C I E N C E C O N S U L T A N T S
SCALE 1:25 (DIMENSIONS IN MM)
SEEPAGE COLLECTION DRAIN
COAL DISCARD MATERIAL
GEOFABRIC
NGL
1000
850
1000DRAIN COLLECTOR PIPE
WASH FILTER STONE
1.51.5
1 1
1000
NGL
1.5
1
1.5
1
1.5
1
1000
MIN. 80
0 (NTS)
NGL
SCALE 1:25 (DIMENSIONS IN MM)
STORM WATER CUT-OFF BERM
1.5
1
2
1
1000CATCHMENT AREA
1000
1:50 GRADIENT
1000
TOP SURFACE TO BE SHAPEDTO A MIN. 0F 1:200 GRADIENT
BERM WALL
CROSS WALL SPACEDAS PER DRAWING REF.OO1
GRASSING TO BE PLACEDCONTINUOUSLY AS SLOPESARE COMPLETED
2
1
SCALE 1:50 (DIMENSIONS IN MM)
DETAIL 1
NGL
ACCESS ROAD
DRAINAGE COLLECTORSUMP
CATCHMENT PADDOCK
TOE DRAIN
STARTER WALL
NGL
NGLTOP SURFACE MIN. 1:200 GRADIENT AS PER DRAWING REF.001
COAL DISCARD DUMP
STORMWATER DIVERSIONBERM
TOE DRAIN
STORMWATER DIVERSIONBERM
TOE DRAIN
PERMANENT STORMWATER DIVESIONBUNDWALL & ACCESS ROAD
TOE DRAIN
OCT 2006
OCT 2006
(PTY) LTD.
002 PRI-CIVIL EARTH WORKS
004 RETURN WATER DAM SECTIONS & DETAILS
DescriptionDate No. Initials
001 GENERAL ARRANGEMENT
(PTY) LTD.
GENERAL ARRANGEMENTPRE - DEPOSITION
CIVIL WORKS
DISCARD COALFACILITY
(CONCEPTUAL DESIGN)
A OCT 2006 GP CONCEPTUAL DESIGN ISSUED
Copyright reserved by GCS (Pty) Ltd.
REFERENCES
PROJECT:
DRAWING TITLE:
REVISIONS
CLIENT:
DescriptionDrawing no.
EXISTING DIAMOND MESH FENCE
X 309 6000
X 309 6200
X 309 6400
X 309 6600
X 309 6000
X 309 6200
X 309 6400
X 309 6600
Y 79
400
Y 79
200
Y 79
000
Y 78
800
Y 78
600
1240
1300
1295
1290
1285 1280
1275
1270
1265
1260
1255
1250
1245
1240
NEW ACCESS ROAD
15m PADDOCK WALL
DRAIN COLLECTOR PIPE
ACCESS TO EXISTINGHAUL ROAD
CONFINEMENT PADDOCK WALL
EXISTING DIAMOND MESH FENCE
STORMWATER CUT-OFF BERMREFER TO DETAIL 1
BARGE PUMP
HDPE OUTFALL LINE
1:20
0
PADDOCK CROSS WALL(TYPICAL)
NEW ACCESS ROADACCESS TO EXISTINGHAUL ROAD
RETURN WATER DAMOUTLET STRUCTURE
PUMP STATION
RETURN WATER TO PLANT
DRAIN OUTLET PIPE
ZINOJU INVESTMENT
003 DISCARD DUMP SECTIONS & DETAILS
004 RETURN WATER DAM SECTIONS & DETAILS
NORT
H
1:20
0
1:20
0
STARTER WALL
MH MH
MH
MH
MH
MH
MHMH
DRAIN OUTLETSUMP
TEMP. STORMWATER CUT-OFF BERMREFER TO DETAIL 1
TEMP. STORMWATER CUT-OFF BERMREFER TO DETAIL 1
OWNER: DATEBY
DRAWN
DESIGNEDCHECKED / REVIEW
SCALEDRAWING No. REVISION
DescriptionDate No. Initials
A
GPGP
WD
A1=1:1500
002 PRE-CIVIL WORKS
(PTY) LTD.
GENERAL ARRANGEMENTFINAL LAYOUT
DISCARD COALFACILITY
(CONCEPTUAL DESIGN)
SLA.06.190.001.DWG
A OCT 2006 GP CONCEPTUAL DESIGN ISSUED
Copyright reserved by GCS (Pty) Ltd.
REFERENCES
PROJECT:
DRAWING TITLE:
OCT 2006
REVISIONS
CLIENT:
DescriptionDrawing no.
(P T Y) L T D
W A T E R , E N V I R O N M E N T A L & E A R T H S C I E N C E C O N S U L T A N T S
63 Wessel Road WoodmeadPO Box 2597 Rivonia 2128 South AfricaTel: +27 (0) 11 803 5726Fax: +27 (0) 11 803 5745E-mail:[email protected]
A003
EXISTING DIAMOND MESH FENCE
X 309 6000
X 309 6200
X 309 6400
X 309 6600
X 309 6000
X 309 6200
X 309 6400
X 309 6600
Y 79
400
Y 79
200
Y 79
000
Y 78
800
Y 78
600
Y 79
400
Y 79
200
Y 79
000
Y 78
800
Y 78
600
1300
1295
1290
1285
1280
1275
1270
1265
1260
1255
1250 12
45
1240
1300
1295
1290
1285 1280
1275
1270
1265
1260
1255
1250
1245
1240
NEW ACCESS ROAD
15m PADDOCK WALL
DRAIN COLLECTOR PIPE
ACCESS TO EXISTINGHAUL ROAD
CONFINEMENT PADDOCK WALL
EXISTING DIAMOND MESH FENCE
STORMWATER CUT-OFF BERMREFER TO DETAIL 1
BARGE PUMP
HDPE OUTFALL LINE
1:200
1:200
1:200
BERM CROSS WALL(TYPICAL)
BERM WALL(TYPICAL)
PADDOCK CROSS WALL(TYPICAL)
NEW ACCESS ROADACCESS TO EXISTINGHAUL ROAD
RETURN WATER DAMOUTLET STRUCTURE
PUMP STATION
RETURN WATER TO PLANT
DRAIN OUTLET PIPE
A003
DETAIL 2003
OCT 2006
OCT 2006
ZINOJU INVESTMENT
003 DISCARD DUMP SECTIONS & DETAILS
004 RETURN WATER DAM SECTIONS & DETAILS
NORT
H
MH MH
MH
MH
MH
MH
MH
MHMH
COAL DISCARD DUMP
RETURN WATERDAM
B
004
B004
Magdalena Discard Disposal Facility – Conceptual Design
GCS (Pty) Ltd October 2006 SLA.06.190
Appendix F
Safety Classification
...\Appendix F - Figure B_Safety Classification(V8) 2D.dgn 2006/10/20 01:38:09 PM