Madrid, 11th September 2006
1st RCC Meeting
South Gas Regional Initiative
2
Part 1.
Introduction and organisational
issues
Part 2.
Technical issues Action plan and
definition of priorities.
Next steps
1. Opening
2. Gas Regional Initiative
3. Composition Roles and responsibilities for RCC, IG, SG, EC and Ministries
4. Rules of procedure
5. Draft action plan. Definition of priorities
6. National press releases
7. Next meetings
8. AOB
Part 1.
Introduction and organisational
issues
Part 2.
Technical issues
Action plan and definition of priorities.
Next steps
Presentation
3
Part 1.
Introduction and organisational
issues
Part 2.
Technical issues Action plan and
definition of priorities.
Next steps
Part 1.
Introduction and organisational issues
Presentation
4
1. Opening
Welcome.
Approval of the Agenda:Part 1. Introduction and organisational issues
I. Opening: approval of the agenda. (for approval)Welcome
Approval of the agenda
II. General Presentation of the S-GRI (for information)Presentation about the scope, proceedings and targets
III. Role and composition of different sub-groups: RCC, IG and SG. EC and Ministries role (for decision)
Composition of SG (Composition of IG already decided)
Roles and responsibilities of RCC, IG, SG, EC and Ministries (consider coherence with other RCC’s on this matter)
IV. Rules of procedure (consider coherence with other RCC’s) (for decision)
Decision making rules for RCC, IG and SG
Consultation process with IG and SG
Reporting to TF GMI
5
1. Opening
Approval of the Agenda (cont).:
Part 2. Technical issues: Action plan and definition of priorities. Next steps
V. Main topics to tackle. Draft action plan (for discussion and decision)
Identification of possible obstacles to the creation a Regional Market
Definition of priorities. Draft a consultation document for IG and SG
Tentative milestones and draft action plan.
VI. National Press releases (for decision)Publication on national level
Writing proposal
VII. Next meetings (for decision)Next RCC, IG and SG meetings
VIII. AOB
6
2. ERGEG Regional Initiative. General presentation2. ERGEG Regional Initiative. General presentationBackgroundBackground
• ERGEG published its gas roadmap for consultation in November 2005
• The roadmap sets out ERGEG‘s view on the key issues inhibiting the development of competitive gas markets
• ERGEG proposed a gas regional initiative to push forward market integration at a practical level
• 26 responses were received - non-confidential responses are published on ERGEG‘s website
• Support from all respondents for the gas regional initiative
• Lack of market integration identified by DG Competition & DG TREN as key issues
• Launch of the gas regional initiative in April alongside a gas roadmap conclusions paper
• Presented in the last Madrid Forum
7
• AIM: foster the creation of regional gas markets as a stepping stone towards a single competitive market
• FOCUS: trading at and between gas hubs and other issues impacting market integration
• e.g. transparency, network access
• SCOPE: address the shortcomings identified by DG COMP´s Energy Sector Inquiry Interim Report
• Market concentration, vertical foreclosure, lack of market integration, lack of transparency,price formation
• INVOLVEMENT: ensure that all key stakeholders are involved
2. ERGEG Regional Initiative. General presentation2. ERGEG Regional Initiative. General presentationMotivationMotivation
8
2. ERGEG Regional Initiative. General presentation2. ERGEG Regional Initiative. General presentationGoalsGoals
Practical output.
Identify existing obstacles and potential solutions, to increase:
Availability of transmission capacities. Harmonized TPA rules Market liquidity and competition in the region Security of supply
Develop and implement an action plan in the medium term
Coordinated developments with other Gas Regional Inititiatives
9
(*) Initially the North and North-West REMs will be run jointly, i.e. under the lead of DTe (The Netherlands). Once the first phase of the REMs has been completed it is intended that the North REM will revert to the leadership of BNetzA (Germany) and will be separated from the North West REM.
2. ERGEG Regional Initiative. General presentation2. ERGEG Regional Initiative. General presentationWhich are the RegionsWhich are the Regions
Region Countries Lead Regulator
North-
West
Netherlands, Belgium,
France, Great Britain,
Ireland
NorthGermany, Denmark,
Netherlands
SouthSpain, Portugal,
Southern FranceSpain
South-
South
East
Italy, Austria, Slovakia,
Hungary, Slovenia,
Greece, Poland, Czech
Republic
Italy & Austria
Netherlands
10
2. ERGEG Regional Initiative. General presentation2. ERGEG Regional Initiative. General presentationStructureStructure
Regional Co-ordination Committees
ERGEG established RCCs. Each RCC :- comprises regulators from the region;- has autonomy, & adopts its own decision making processIMPLEMENTATION GROUP (IG)
Includes TSOs, Market Operators (where appropriate)
This is the ‘do-er’ for each Regional Initiative
Chaired by RCC
STAKEHOLDER GROUP(SG)
Wide participation including market players
Chaired by RCC and used for consultation
MADRID FORUM
Overall forum for discussing progress in progressing regional initiatives and
pan-European consistency
MEMBER STATES
Input identifying and solving market integration issues – e.g. legislative proposals,
EU COMMISSION
11
www.ergeg.org/portal/page/portal/ERGEG_HOME/ERGEG_RI/Gas_Regional_Initiative
ERGEG website www.ergeg.org regional initiatives
2. ERGEG Regional Initiative. General presentation2. ERGEG Regional Initiative. General presentationIInformation, Access to documents, transparencynformation, Access to documents, transparency
12
Timing Action
April 2006 Finalise scope of gas REMs
May 2006 ERGEG presents establishment of gas REMs to the Madrid Forum
June 2006 1st meeting of RCC: Establish governance structure; Identify tentative priority actions based on roadmap paper and CEER/ERGEG workplan, DG COMP Sector Inquiry, EC Benchmarking report, stakeholders´ input; report to ERGEG
June/July 2006 RCCs to decide/establish/convene meetings of implementation Group and Stakeholder Group
Aug/Sept 2006
Sept/Oct 2006
Post Autumn 2006
RCC to develop forward Action plan in consultation with implementation and Stakeholder Group
RCC reports to ERGEG on Action Plan
ERGEG compiles report for 4 REMs and reports to Madrid Forum
RCC’s begin to implements Action Plan. Continued liaison with Implementation and stakeholders Groups
2. ERGEG Regional Initiative. General presentation2. ERGEG Regional Initiative. General presentationERGEG TimetableERGEG Timetable
13
• Regional Coordination Committee (RCC):
National Regulators + EC
• Implementation Group (IG): RCC + TSOs, SSOs and LNG Operators.
• Stakeholders Group (SG) (example Spain):
- National authorities: Ministry of Industry, Trade and Tourism
- National industry: TSOs and LNG op.: ENAGAS, Naturgas, BBG, SAGGAS…SSOs: ENAGASShippers: Gas Natural, Iberdrola, BP, U.Fenosa, Endesa…Distributors: Gas Natural, Naturgas, Endesa…Hub: N/ASuppliers: N/ATechnical Associations: Sedigas
- European associations (EUROGAS, EFET, etc)?
3. Composition, roles and responsibilities.3. Composition, roles and responsibilities.CompositionComposition
14
Regional Coordination Committee (RCC) Primary drive & motivation Establishment and lead of regional projects including way of work, decision
making, consulting stakeholders, convene Implementation Group/Stakeholder Group, involve Member State governments and EC
Reporting and monitoring of progress Prepare/commission discussion papers, gather information, distil/develop
conclusions/way forward, develop action plan ERGEG report to Madrid Forum
Member States Relevant powers often rest with Member State government new national
legislation may be needed political support is crucial
European Commission Key role in supporting each gas REM project and helping to deliver objectives Co-Chair (of which group?)
3. Composition, roles and responsibilities.3. Composition, roles and responsibilities.Roles and responsibilitiesRoles and responsibilities
15
Implementation Group (IG) Agreed proposals need to be implemented in a practical and efficient way Can be invited to put forward proposals for solutions, actions Regular dialogue with RCC – e.g. regular formal meetings
Stakeholders Group (SG) Stakeholders views and input crucial for progress Stakeholders will be involved in definition of detailed objectives and timetable regulators will ensure full transparency and consultation formal and informal dialogue
3. Composition, roles and responsibilities.3. Composition, roles and responsibilities.Roles and responsibilitiesRoles and responsibilities
16
4. Rules of procedure.4. Rules of procedure.Decision making rulesDecision making rules
Decision making rules (consider coherence with other RCC’s):
- Voting criteria: normally by consensus in RCC and IG. Only in special cases and if agreement cannot be reached voting by ERGEG weights (RCC) or EU weights (IG, by country). Dissenting positions officially recorded. No votes in the SG
- Consultation. A consultation document/s should be issued by RCC. Public hearing. Regulators chair the session and operators , stakeholders present their views on the proposed issues. Discussion may be solicited.
17
4. Rules of procedure.4. Rules of procedure.Consultation with other agents and reportingConsultation with other agents and reporting
How to consult IG and SG?• Consultation Paper circulated and published on ERGEG Website
• Bilateral Meetings
• Meetings with public hearings of stakeholders, discussion
Reporting to ERGEG TF GMI• By contact persons
Reporting to Madrid Forum• By chairmen
18
Part 2.
Technical issues Action plan and
definition of priorities.
Next steps
Part 2. Technical issues
Action plan and definition of priorities. Next steps
Presentation
19
5. Main topics to tackle. Draft action plan. Priorities5. Main topics to tackle. Draft action plan. PrioritiesIdentification of obstacles and definition of prioritiesIdentification of obstacles and definition of priorities
Main topics to tackle.
1. Implementation status of Gas Directive. Market opening and competition level
2. Interconnection capacity. Further developments
3. Transparency
4. Capacity allocation mechanisms. Secondary markets for capacity. congestion management procedures.
5. Balancing rules and penalties
6. Operators coordination
7. TPA tariffs regime.
8. Gas quality and interoperability
9. Secondary markets
10. Description of practical (or virtual) cases of transit among the three countries
20
5. Main topics to tackle. Draft action plan. Priorities5. Main topics to tackle. Draft action plan. PrioritiesIdentification of obstacles and definition of prioritiesIdentification of obstacles and definition of priorities
Main topics to tackle.
1. Implementation status of European legislation. Market opening and competition level
• Is there any article that hasn’t still been transposed into national laws?
• Market opening schedule.
• Level of real competition (switching levels, etc.)
• …
2. Interconnection capacity. Further developments
• Existing interconnections. Capacities, experience of use (problems?), possibility of Backhauls…
• New projects: capacities, starting dates, etc.
• …
21
5. Main topics to tackle. Draft action plan. Priorities5. Main topics to tackle. Draft action plan. PrioritiesIdentification of obstacles and definition of prioritiesIdentification of obstacles and definition of priorities
Main topics to tackle.
3. Transparency• Level of transparency in each country: directly, available on the website,
in English, under request, free of charge…• Implementation of Gas Regulation 1775/2005 concerning transparency• …
4. Capacity allocation mechanisms. Congestion management procedures.• CAM to transmission, regasification and storage capacities• Usit or lose it provisions?• Long/short term contracts• Interruptible capacity?• Congestion management procedures• …
22
5. Main topics to tackle. Draft action plan. Priorities5. Main topics to tackle. Draft action plan. PrioritiesIdentification of obstacles and definition of prioritiesIdentification of obstacles and definition of priorities
Main topics to tackle.
5. Balancing rules and penalties• Balancing period
• Tolerance levels
• …
6. Operators coordination• Fluent communication and coordination among operators?
• Existing Operational Business Agreements
7. TPA tariffs regime• TPA Tariff system
• Does domestic transport differ from transit tariffs?
• Flexibilities included in tariffs
• Compatibility of tariffs
• …
• …
23
5. Main topics to tackle. Draft action plan. Priorities5. Main topics to tackle. Draft action plan. PrioritiesIdentification of obstacles and definition of prioritiesIdentification of obstacles and definition of priorities
Main topics to tackle.
8. Gas quality and interoperability• Is there any interoperability problem between countries?• Coherent quality specifications (take into account EASEE-Gas CBP• …
9. Secondary markets• Liquid secondary markets for capacity?• Liquid secondary markets for gas?• …
10.Description of practical (or virtual) cases of transit among the three countries• Cases of transit between countries: France from/to Spain and France
from/to Portugal• Identify barriers, difficulties, problems to transit, derived from the study
of concrete and practical cases
24
5. Main topics to tackle. Draft action plan. Priorities5. Main topics to tackle. Draft action plan. PrioritiesTentative milestones and draft action planTentative milestones and draft action plan
• Action plan and milestones
• 12-15.09 Draft a short written report (2 pages) for the GMI TF meeting on 25.09
• 12-15.09 Complete the technical report to be submitted to the IG members, for discussion at the IG meeting on 21.09
• Complete…
25
6. National Press releases 6. National Press releases Publication on national level. Writing proposalPublication on national level. Writing proposal
PRESS RELEASE (See doc attached)
The Gas Regional Initiative for the “South Region”:
Portugal, Spain and South of France
- New Gas Regional Initiative launched by EU regulators
- Initiative supports European Commission’s policies on competition and security of supply
- Initiative designed to identify and remove barriers to competition in the initial four EU regions
- Gas Regional Initiatives (GRI) projects as stepping stones towards a single competitive market
-The GRI South
“ The European Regulators’ Group for Electricity and Gas (ERGEG) of Southern countries of the European Union launched on September 11th in Madrid. The new Gas Regional Initiative for South Europe (GRI-S), […]”
26
7. Next meetings7. Next meetings
- 21st September IG meeting
- 3rd October SG meeting
- …
27
8. And Other Business 8. And Other Business
…