Public Meeting 4Working Locally Preferred Alternative
and Station Design Input Meeting
Madison East-West Bus Rapid Transit (BRT) Planning Study
Madison College| September 26, 2019 | 6:00-8:00 PM
MADISON DEPARTMENT
OF TRANSPORTATION
![Page 2: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/2.jpg)
INTRODUCTIONS + AGENDA
![Page 3: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/3.jpg)
City Staff+ City of Madison
• Tom Lynch, Director of Transportation• David Trowbridge, Project Manager • Mike Cechvala, Planner
+ Metro Transit• Drew Beck, Planning Supervisor• Tim Sobota, Metro Planner
+ Madison Area Transportation Planning Board (MATPB)• Bill Schaefer, Transportation Planning Manager• Zia Brucaya, Transportation Planner
![Page 4: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/4.jpg)
Consultant Team
![Page 5: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/5.jpg)
1. Welcome, Presentation and Q+A (20 minutes)• Project overview and public engagement to date• Route options and working locally preferred
alternative• Next steps and schedule
2. Open House (90 minutes)• Station Design Information and Input
+ Please fill out the worksheet with your comments!
Tonight’s Agenda
![Page 6: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/6.jpg)
+ Ask clarifying questions as we go (explain a term or repeat a statement).
+ Save other questions for the Q&A – we may be planning to answer them!
+ Share your speaking time with others.
Ground Rules
![Page 7: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/7.jpg)
What is Bus Rapid Transit?BRT has:• Very high level service, similar to but one step down from light rail.
• Typically over 50 percent of the route will have dedicated bus lanes, giving buses an advantage in congestion.
• 10-15 minute service levels - 6 am to 12 midnight.
Cleveland’s Health Line BRT
Example of dedicated bus lanes
![Page 8: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/8.jpg)
+ Improved mobility
+ Future growth and development
+ Improved access to employment and education
+ Increased quality of life
+ More sustainable community
Benefits of BRT
![Page 9: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/9.jpg)
Goals, Key Steps, Public Engagement Process and Input To Date
PROJECT OVERVIEW
![Page 10: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/10.jpg)
Current Project Study Goals
+ Develop a plan for Madison’s first BRT route
+ Build community support
+ Identify local funding sources
+ Set the stage to apply for Federal funding
![Page 11: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/11.jpg)
Identify Locally Preferred Alternative(fall to winter)
Request Entry into Project Development)
Federal (FTA) Project Development
Receive Clearance from FTA
FUNDING
ENVIRONMENTAL
Start Federal (FTA) Project Development Process
Start Analysis
Request Eligibility Review from FTA
Apply for FTA Capital Funding
Receive Capital Funding from FTA
CONSTRUCTION
Begin Service
30% 60% 100%DESIGN
WeAre
Here
2019 2020 2021 2022 2023 2024
MADISON EAST-WEST BRT PLANNING STUDYProject Development Process
[
![Page 12: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/12.jpg)
Public Engagement to-Date
Public Meetings
Surveys
Small Group Meetings
Mobile Engagement
Stations
Social Media
Project Listserv
4Meetings
14Meetings
11.6KFollowers
5,078Responses 9
Meetings
243Sign-Ups
Working Locally Preferred Alternative
Public Meeting 4
Station Design Input
Session
Public Meeting 3
Locally Preferred
Alternatives
Public Meeting 2Preliminary Alternatives
Public Meeting 1Kickoff Open
House
![Page 13: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/13.jpg)
Public Engagement Outreach
Small Group Meetings -14Small Group Meetings - 14
Mobile Engagement Stations - 9Presentations (by request) - 4
Small Group Meeting
Mobile Engagement Station
Presentation (by request)
BRT Route
Public Meeting
Public Meetings - 4
Future North-South BRT Route
Lake Mendota
Lake Monona
Lake Wingra
![Page 14: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/14.jpg)
MADISON EAST-WEST BRTRoute Options and Working Locally
Preferred Alternative
![Page 15: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/15.jpg)
3 Alternatives Under Review
2 Alternatives Under Review
MADISON EAST-WEST BRT PLANNING STUDYWorking Locally Preferred Alternative Route
![Page 16: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/16.jpg)
Downtown Alternative 1
University
Johnson
Orc
hard
State
• Remove regional/commuter routes from State Street• Signal timing improvements, WB left arrow at Gorham• Reliable Y detour with Wisconsin Ave improvements
Capitol SquareNew bus lane
79% dedicated running way
Existing bus lanes
Off Square During Events
![Page 17: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/17.jpg)
University
Johnson
E Ca
mpu
s Mal
l
Orc
hard
Downtown Alternative 2
68% dedicated running way
New bus lane
Existing bus lane
New traffic signal
Requires ~110 Parking Spaces and Loading Zones
![Page 18: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/18.jpg)
University
Johnson
E Ca
mpu
s Mal
l
Orc
hard
Downtown Alternative 3
72% dedicated running way
New bus lane
Existing bus lane
Requires ~110 Parking Spaces and Loading Zones
Buses go both ways on BroomUsing new SB counterflow lane
![Page 19: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/19.jpg)
MADISON EAST-WEST BRT PLANNING STUDYLocation of Dedicated Lanes for Working LPA
Between 45% and 55% Dedicated Running Way
![Page 20: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/20.jpg)
MADISON EAST-WEST BRT PLANNING STUDYBRT Travel Time, Ridership, Capital Costs*
10,600
14,650
Travel Times (End-to-End)
Daily Ridership
Capital Costs
*All data reflects the Broom/Wilson downtown option**LPA = Locally Preferred Alternative, TSP = Transit Signal Priority, QJ = Queue Jump
13,60012,700 13,100
Via OdanaRoad
15,00010,000 11,000 12,20011,700
Via Mineral Point
Mineral Point / Odana Road
$111 M $121 M $172 M$123 M
$158 M$100M $180M$112 M$105 M $117 M
Via OdanaRoad
Via Mineral Point
68 minutes / 73 minutesMixed Traffic64 minutes / 68 minutes**Mixed Traffic and TSP + QJ
49 minutes / 50 minutes**Dedicated Lane and TSP55 minutes / 59 minutes**Working LPA
![Page 21: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/21.jpg)
MADISON EAST-WEST BRT PLANNING STUDYCapital Costs for Working LPAOdana and Broom/Wilson Options
Cost Categories Working LPA Cost ($2019 in millions)
Dedicated Lane Marker (Paint) $2
Stations and Shelters $24
Maintenance Facility $7
Roadway Improvements $19
Transit Signals and Intersection Improvements $22
Right-of-Way Acquisition $1
Electric Buses $30
Engineering, Environmental, and Construction Design $17
Contingencies $4Total $120-$130 million
Federal Contribution (up to) $100 million
Local (Non-Federal) Contribution $20-$30 million
![Page 22: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/22.jpg)
+ Fall 2019-Winter 2020: Apply for entry into federal funding process
+ 2020: Continued planning, community engagement and system design
Next Steps
![Page 23: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/23.jpg)
+ Stay to give input and learn about different station design options
Station Design Information & Input
![Page 24: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/24.jpg)
BRT Station Standard Elements
![Page 25: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/25.jpg)
Station Design PreferencesOverall Style• Modern• Traditional• Futuristic• Prairie
Modern DesignCebu City, Philippines. Design based on local basket weaving techniques, CAZA Architects.
Transitional Design Richmond, VA. Source: Kimley-Horn
Futuristic DesignHamburg, Germany. Source: Blunck+Morgen Architects
Modern Prairie DesignRochester, NY. Source: In.Site:Architecture
Materials• Wood• Metal• Glass• Brick
Traditional Design St. Paul, MN
![Page 26: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/26.jpg)
Station Design Preferences
Concrete seating, glass windscreen, solid ceiling
Glass and metal station, solid vs. translucent ceiling
Wood and metal, solid ceilingSource: IndyGo
![Page 27: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019 · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50](https://reader034.fdocuments.us/reader034/viewer/2022050520/5fa3c8a8b4c35656ed570a8e/html5/thumbnails/27.jpg)
+ www.madisonbrt.com+ @cityofmadison+ @mymetrobus+ Project Contacts:
• David Trowbridge, City Project Manager [email protected]
• Marcus Pearson, Public [email protected]
Thank You!