Public Meeting 4 Working Locally Preferred Alternative and Station Design Input Meeting Madison East-West Bus Rapid Transit (BRT) Planning Study Madison College| September 26, 2019 | 6:00-8:00 PM MADISON DEPARTMENT OF TRANSPORTATION

Transcript of Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high...

Page 1: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

Public Meeting 4Working Locally Preferred Alternative

and Station Design Input Meeting

Madison East-West Bus Rapid Transit (BRT) Planning Study

Madison College| September 26, 2019 | 6:00-8:00 PM

MADISON DEPARTMENT

OF TRANSPORTATION

Page 2: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

INTRODUCTIONS + AGENDA

Page 3: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

City Staff+ City of Madison

• Tom Lynch, Director of Transportation• David Trowbridge, Project Manager • Mike Cechvala, Planner

+ Metro Transit• Drew Beck, Planning Supervisor• Tim Sobota, Metro Planner

+ Madison Area Transportation Planning Board (MATPB)• Bill Schaefer, Transportation Planning Manager• Zia Brucaya, Transportation Planner

Page 4: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

Consultant Team

Page 5: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

1. Welcome, Presentation and Q+A (20 minutes)• Project overview and public engagement to date• Route options and working locally preferred

alternative• Next steps and schedule

2. Open House (90 minutes)• Station Design Information and Input

+ Please fill out the worksheet with your comments!

Tonight’s Agenda

Page 6: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

+ Ask clarifying questions as we go (explain a term or repeat a statement).

+ Save other questions for the Q&A – we may be planning to answer them!

+ Share your speaking time with others.

Ground Rules

Page 7: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

What is Bus Rapid Transit?BRT has:• Very high level service, similar to but one step down from light rail.

• Typically over 50 percent of the route will have dedicated bus lanes, giving buses an advantage in congestion.

• 10-15 minute service levels - 6 am to 12 midnight.

Cleveland’s Health Line BRT

Example of dedicated bus lanes

Page 8: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

+ Improved mobility

+ Future growth and development

+ Improved access to employment and education

+ Increased quality of life

+ More sustainable community

Benefits of BRT

Page 9: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

Goals, Key Steps, Public Engagement Process and Input To Date

PROJECT OVERVIEW

Page 10: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

Current Project Study Goals

+ Develop a plan for Madison’s first BRT route

+ Build community support

+ Identify local funding sources

+ Set the stage to apply for Federal funding

Page 11: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

Identify Locally Preferred Alternative(fall to winter)

Request Entry into Project Development)

Federal (FTA) Project Development

Receive Clearance from FTA

FUNDING

ENVIRONMENTAL

Start Federal (FTA) Project Development Process

Start Analysis

Request Eligibility Review from FTA

Apply for FTA Capital Funding

Receive Capital Funding from FTA

CONSTRUCTION

Begin Service

30% 60% 100%DESIGN

WeAre

Here

2019 2020 2021 2022 2023 2024

MADISON EAST-WEST BRT PLANNING STUDYProject Development Process

[

Page 12: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

Public Engagement to-Date

Public Meetings

Surveys

Small Group Meetings

Mobile Engagement

Stations

Social Media

Project Listserv

4Meetings

14Meetings

11.6KFollowers

5,078Responses 9

Meetings

243Sign-Ups

Working Locally Preferred Alternative

Public Meeting 4

Station Design Input

Session

Public Meeting 3

Locally Preferred

Alternatives

Public Meeting 2Preliminary Alternatives

Public Meeting 1Kickoff Open

House

Page 13: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

Public Engagement Outreach

Small Group Meetings -14Small Group Meetings - 14

Mobile Engagement Stations - 9Presentations (by request) - 4

Small Group Meeting

Mobile Engagement Station

Presentation (by request)

BRT Route

Public Meeting

Public Meetings - 4

Future North-South BRT Route

Lake Mendota

Lake Monona

Lake Wingra

Page 14: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

MADISON EAST-WEST BRTRoute Options and Working Locally

Preferred Alternative

Page 15: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

3 Alternatives Under Review

2 Alternatives Under Review

MADISON EAST-WEST BRT PLANNING STUDYWorking Locally Preferred Alternative Route

Page 16: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

Downtown Alternative 1

University

Johnson

Orc

hard

State

• Remove regional/commuter routes from State Street• Signal timing improvements, WB left arrow at Gorham• Reliable Y detour with Wisconsin Ave improvements

Capitol SquareNew bus lane

79% dedicated running way

Existing bus lanes

Off Square During Events

Page 17: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

University

Johnson

E Ca

mpu

s Mal

l

Orc

hard

Downtown Alternative 2

68% dedicated running way

New bus lane

Existing bus lane

New traffic signal

Requires ~110 Parking Spaces and Loading Zones

Page 18: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

University

Johnson

E Ca

mpu

s Mal

l

Orc

hard

Downtown Alternative 3

72% dedicated running way

New bus lane

Existing bus lane

Requires ~110 Parking Spaces and Loading Zones

Buses go both ways on BroomUsing new SB counterflow lane

Page 19: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

MADISON EAST-WEST BRT PLANNING STUDYLocation of Dedicated Lanes for Working LPA

Between 45% and 55% Dedicated Running Way

Page 20: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

MADISON EAST-WEST BRT PLANNING STUDYBRT Travel Time, Ridership, Capital Costs*

10,600

14,650

Travel Times (End-to-End)

Daily Ridership

Capital Costs

*All data reflects the Broom/Wilson downtown option**LPA = Locally Preferred Alternative, TSP = Transit Signal Priority, QJ = Queue Jump

13,60012,700 13,100

Via OdanaRoad

15,00010,000 11,000 12,20011,700

Via Mineral Point

Mineral Point / Odana Road

$111 M $121 M $172 M$123 M

$158 M$100M $180M$112 M$105 M $117 M

Via OdanaRoad

Via Mineral Point

68 minutes / 73 minutesMixed Traffic64 minutes / 68 minutes**Mixed Traffic and TSP + QJ

49 minutes / 50 minutes**Dedicated Lane and TSP55 minutes / 59 minutes**Working LPA

Page 21: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

MADISON EAST-WEST BRT PLANNING STUDYCapital Costs for Working LPAOdana and Broom/Wilson Options

Cost Categories Working LPA Cost ($2019 in millions)

Dedicated Lane Marker (Paint) $2

Stations and Shelters $24

Maintenance Facility $7

Roadway Improvements $19

Transit Signals and Intersection Improvements $22

Right-of-Way Acquisition $1

Electric Buses $30

Engineering, Environmental, and Construction Design $17

Contingencies $4Total $120-$130 million

Federal Contribution (up to) $100 million

Local (Non-Federal) Contribution $20-$30 million

Page 22: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

+ Fall 2019-Winter 2020: Apply for entry into federal funding process

+ 2020: Continued planning, community engagement and system design

Next Steps

Page 23: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

+ Stay to give input and learn about different station design options

Station Design Information & Input

Page 24: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

BRT Station Standard Elements

Page 25: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

Station Design PreferencesOverall Style• Modern• Traditional• Futuristic• Prairie

Modern DesignCebu City, Philippines. Design based on local basket weaving techniques, CAZA Architects.

Transitional Design Richmond, VA. Source: Kimley-Horn

Futuristic DesignHamburg, Germany. Source: Blunck+Morgen Architects

Modern Prairie DesignRochester, NY. Source: In.Site:Architecture

Materials• Wood• Metal• Glass• Brick

Traditional Design St. Paul, MN

Page 26: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

Station Design Preferences

Concrete seating, glass windscreen, solid ceiling

Glass and metal station, solid vs. translucent ceiling

Wood and metal, solid ceilingSource: IndyGo

Page 27: Madison East-West Bus Rapid Transit (BRT) Planning Study · 9/12/2019  · BRT has: • Very high level service, similar to but one step down from light rail. • Typically over 50

+ www.madisonbrt.com+ @cityofmadison+ @mymetrobus+ Project Contacts:

• David Trowbridge, City Project Manager [email protected]

• Marcus Pearson, Public [email protected]

Thank You!