Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the...

52
Maasvlakte Power Plant 3; Theory versus Practice Sevilla, 15 th April 2015 Ing. Aris Blankenspoor

Transcript of Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the...

Page 1: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Maasvlakte Power Plant 3;Theory versus PracticeSevilla, 15th April 2015

Ing. Aris Blankenspoor

Page 2: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Content

Short introduction to E.ON

Why a new power plant? Permit process !

MPP3 key data & Technology choice

Theory of good project management; Safety and Front End Loading at MPP3

The construction project

Lessons learned

Page 3: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Short introduction to E.ON

Page 4: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Some facts & figures (Annual Report 2014)

Europe: Focused and synergistic positioningOutside Europe: Targeted expansion

Sales 111 billion euro

Net income -/- 3.1 billion euro

Investments 4.6 billion euro

Sales electricity 735 TWh

Sales gas 1.161 TWh

Households 35 million

Employees 58.500

Page 5: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

SavingsSavingsNuclear Gas

Renewables High efficient coal with CCS

Leading E.ON developments

State of the art plants like

Irsching(60%).

Number of plants in

Germany from approx. 20 to 0.

Largest investor in Europe (3rd

worldwide).

Plant reduction by

80%.

Smart gridSmart grid

Connectingenergy

Connectingenergy

Page 6: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

E.ON to split into two publicly listed companies

Two highly competitive companies with distinct identities

NewCompany

Shaping markets

Empowering customers

Page 7: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Two leading companies for two energy worlds

New CompanyGeneration

Hydro

Wind/Solar/Other

E&P

Global Commodities

Germany

Other EU Countries

Russia

Turkey

Brazil

Renewables

RenewablesDistribution

CustomerSolutions

Renewables

Distribution

CustomerSolutions

Distinct opportunities, mindsets and capabilities

Page 8: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Why a new power plant?Permit Process!

Page 9: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Age Dutch power plants: replacement is necessary(Dutch government in energy report 2006)

Combined heat & power (gas fired) was heavily subsidized in 90’s

0

1000

2000

3000

4000

5000

6000

tot 1960 1960 -

1964

1965 -

1969

1970 -

1974

1975 -

1979

1980 -

1984

1985 -

1989

1990 -

1994

1995 -

1999

na 2000

in MWOverig

Olie

Nucleair

Kolen

Gas

Maasvlakte1987 coal

Other

Oil

Nuclear

Coal

Gas

Page 10: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

NL too muchdependenton gas

Wind

Hydro

Other

Derived gases

Uranium

Oil

Brown coal

Hard coal

Natural gas

Fuel mix in Europe (2006)

Page 11: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Emissions: the installations for flue gas cleaning

Coal mill

Coal

Boiler

Ash / slag Fly ash

Gypsum

Cleaned waste water

DeNOxinstallation

E-Filter

Chalk suspension

Flue gas desulpharisation

Chimney

Flue gas

Water treatment

Page 12: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Comparison of emission values (mg/m3)

Component IPPC /BREF DCMR Technique MPP 3

SO2 20-150 20-40 98% reductionMPP3: ok

max. 40

NOx 90-150 30-75 80-90 % reductionMPP3: ok

max. 65

Dust 5-20 1-3 5 or 6 fields filter MPP3: 6

max. 3

Page 13: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Energy-efficient = CO2-efficient

MPP3 has high efficiency (~ 47%). This leads to approx. 20% less CO2-emissions per KWh

MPP3 is CO2 capture ready

MPP3 is ready for heat supply to industries and residential areas in the region

Possibility for co-firing biomass is being researched and is part of the environmental permit

Page 14: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

ROAD Project – Full Chain CCS Demonstration

Capture: 250 MWe, 1.1 Mton/yrTransport: 25 km pipeline, 16”

max. capacity 5 Mton/yrStorage: depleted offshore gas

field (P18-A)Start of operation: 2016 …Capital investment: approx. M€ 400 (M€ 330 funded)Project Developer: Maasvlakte CCS Project C.V.

Page 15: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Reduction CO2 emission power plant

Old coal

-/- 20%Efficiency

Biomass

CCS demo

Heat supply

100%

50%

2010 2020

Gas

Full scaleCCS 2030

Page 16: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

PlanningSubmit Environmental Impact Assessment: December 2006

Submit environmental permits: June 2007

Environmental and building permits granted: April 2008

Start building activities: April 2008

Pouring concrete foundation: April 2009

First boiler column: January 2010

Boiler pressure test: October 2012

Commissioning:

In operation:

Last permit irrevocable (NPA)

Page 17: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

MPP3 key data

Page 18: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

MPP3 key data

Gross capacity 1,100 MWEfficiency ~ 47%Steam conditions 620°C

285 barStart construction April 2008In operation 2014 / 2015

E.ON is Owner, Engineer & Integrator

Workers on site > 2,500LTIFR 0TRIF 1,4Record safe days 1,337Safe hours > 9,500,000Worked hours ~ 14,700,000

Page 19: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry
Page 20: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Maasvlakte: a history of land and water

Maasvlakte 1 (1970)

E.ON

E.ON Maasvlakte is oneof the best optionsin Europe for a coalfired power plant

Maasvlakte 2 (2012)

Very large scale industrial area

Deep waterway: easy transport of coal and biomass

Sufficient cooling water

Infrastructure present

Building space available

Maasvlakte 2 = new co-siting opportunities

Page 21: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Technology choice

Page 22: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Technology Choice Pulverized coal = proven technology, safe, reliable,

economic, clean & innovative MPP3 has high efficiency (47% versus 38%) This leads to approx. 20-30% less CO2-emissions Complex technology, T-24 boiler material, steam

600°C, 285 bar, sea water cooling Once through boiler >> turn down ratio 83% Hot start to full load in 105 minutes Ramp up speed 50 MW/minute Electrical power (net): 1,069 MWel

ID size fan limits flue gas duct to 800 MWel

Generator limits capacity to about 1,155 MWel

MPP3 is CO2 capture ready MPP3 is ready for heat supply to industries and

residential areas in the region Possibility for co-firing biomass (up to 30%) Flue Gas Cleaning to comply with emission levels

far below BAT

SH1-outlet

SH2-inlet

SH2-outlet

SH3-inlet

HP-outlet

feedwater-inlet

RH1-inlet

RH2-inlet

RH1-outlet

SH1-inlet

RH2-outlet

Finned tubepreheater outlet

7CrMoVTiB10-10

Super304H

16Mo3

Super304H

16Mo3

Super304HHR3C

13CrMo4-5

X20 CrMoV 11-17CrMoVTiB10-10

Quelle: HPE

Page 23: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

T24 Recap and executed measures

Influencing the medium

• Optimised chemical cleaning

(pickling)

• Optimised water chemistry of

boiler water

• Optimised start-up procedure

Influencing stresses• Heat treatment at 450°C-520°C of

the complete boiler with external

burners

Material

condition

StressMedium

5

0

O2 content during start-up, Source: RWE

Time

O2

cont

ent i

n pp

b

Influencing material condition• Local heat treatment at

temperatures in the range of 600°C

in highly stressed areas

Source: VGB

Page 24: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

HR3C – Damage Mechanism (Connected to T24 treatment)

Root cause investigation revealed a systematic defect in the heat effected zone of the weldings of the tube material HR3C

Intercristalline corrosion of HR3C material was the reason for cracks in heat effected zones

HR3C material was sensitized by T24 related Stress Release Heat Treatment (SRHT) and triggered by chemicals in water phase

Triggering Chemicals entering during previous processes SRHT, flushing and chemical cleaning of the boiler

Page 25: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

High efficient turine; Actual operating clearances significantly smaller than intended

Assembly clearance

(Montagespiel)

Design clearance(calculated 2D by supplier as

intended)

Actual Operating Clearance(Ist Betriebsspiel)

(calculated 3D EON)

2

4

6

8

10

mm

Row15

Page 26: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

The theory of good project management;Safety and Front End Loading at MPP3

Page 27: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

“Efficiency and safety focus need not, and should not, compromise each other. This is a cultural and management issue. We owe a safe working environment to our employees and subcontractors - and not the least to their families, to our customers and to the communities we work for and among.”

Dr. Johannes Teyssen(CEO E.ON AG)

E.ON, dedicated to safety

Page 28: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

HSE Performance over time

Time

Inci

dent

rat

e

Technologyand standards

HSEManagementSystems

Improvedculture

• Engineering improvements• Hardware improvements• Safety emphasis• E&H Compliance

• Integrated HSE-MS• Reporting• Assurance• Competence• Risk Management

• Behaviour• Visible leadership /

personal accountability• Shared purpose & belief• Aligned performance

commitment & external view

• HSE delivers business value

Page 29: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

PATHOLOGICALwho cares as long as we’re not caught

REACTIVESafety is important, we do a lot every time we have an accident

CALCULATIVEwe have systems in place to manage all hazards

PROACTIVEwe work on the problems that we still find

GENERATIVEHSE is how we do business round here

Increasing Trust/Accountability

Culture Ladder

Increasinglyinformed

Page 30: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Culture Ladder

PATHOLOGICAL • The lawyers/regulator said it was OK• Of course we have accidents, it’s a dangerous business• Sack the idiot who had the accident

REACTIVE• We are serious, but why don’t they do what they’re told?• Endless discussions to re-classify accidents• You have to consider the condition under which we are working

GENERATIVE• Chronic unease• Safety seen as a profit centre• New ideas are welcomed

PROACTIVE• Resources are available to fix things before an accident• Management is open but still obsessed with statistics• Procedures are “owned” by the workforce

CALCULATIVE• We cracked it!• Lots and lots of audits• HSE advisers chasing statistics

Page 31: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Prof. Jop Groeneweg (Leiden University):

“An excellentprimary processmakes a safety departmentunnecessary.”

Page 32: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Aris Blankenspoor (E.ON):

“An excellent primary process

starts with Front End Loading.”

Page 33: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

FEL

time

influ

ence

& c

osts Influence

Design progressCosts / commitment

Front End Loading (FEL)

ImplementativeFEL

2. Cost of change is high value (% of overall commitment)

1. Cost of change is low value (% of overall commitment)

1

2

1

2

Page 34: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Optimize project result

34

Tota

l Inv

este

men

t cos

tsA

ccuracy

TimeConcept Basic DetailedFeasibility

+/-50% +40/-25% +15/-10%

Realisation Handover

Investment request

Estimated Total Final Costs

2 3 4 5 6

+10%+15%

+40%+50%

-50%-25% -15%

-10%

Page 35: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Focus on Safety Why:

Investment size and statistics Other projects 2 fatalities & >10 heavy injuries Target GPM MPP3 “zero” fatality & HI

How: Assume systems are available Shared purpose and believe Culture change / communication Example behavior and leadership 90% of incidents due to human error Control of primary process Control of quality and logistics No changes philosophy No rush jobs FEL / preparation is 90% of success Risk transition through project phases

Many construction employees on site (10.000) Over 2500 workers Safety culture and behavior contractors Size and weight of equipment Complicated logistic process (JIT) Failure of contractors to deliver standards in terms of

time, cost and quality Non-proven technology e.g. T-24 material, turbine Subcontractor management & pre selection VIP’s e.g. constructability reviews in design Delay in design documents

Result: Changes

Challenges from the practice

Page 36: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Culture is leading safety since 90% of the incidents are due to human error

FEL and good preparation of the construction process leads to zero change

Well developed process safety and risk transfer prevents operational and environmental incidents

Zero change leads to the highest safety performance AND to cost efficiency

Well prepared Front End Loading and Safety go hand in hand

However; challenges still lead to unexpected change.

Conclusion Safety and Front End Loading

Front End Loading must be a “leading indicator” forhigh safety performance and project cost efficiency.

Page 37: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

The construction project

Page 38: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry
Page 39: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry
Page 40: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry
Page 41: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

10,000 m2

7,500 tons of steel

650 piles (30 m, 1,5 m Ø)

Page 42: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

27,000 m3 of concrete

2.50 – 4 meters thick

Page 43: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry
Page 44: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry
Page 45: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry
Page 46: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry
Page 47: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry
Page 48: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry
Page 49: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

First coal in storage

Page 50: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

First coal fire: September 2013

Page 51: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Main Lessons Learned

Subject Explanation LessonPermit irrevocable With a valid permit the project

stays at risk. Irrevocable permit is required.

External stakeholder management and intensive alignment with authorities required.

Proven technology Time delay project mainly based on exotic materials T24 & HR3C and IP turbine

Use proven technology / do not perform as early adapter with highest technical parameters

E.ON specialists E.ON experts were in the leadto manage external OEM

Maintain a critical mass of owncompany specialists

Supplier reliability Critical suppliers do not perform as expected (quality)

Closer cooperation with strategic - key suppliers

Front End Loading Sub-optimal development of project in early phases leads to changes during execution

Projects to be developed more extensively before FID

Use front end loading approachSafety Safety results are lagging

indicators of the primary process

90% of success depends on preparation and no change.

Incidents happen for 90% due to human behavior

Page 52: Maasvlakte Power Plant 3; Theory versus Practice · T24 Recap and executed measures Influencing the medium • Optimised chemical cleaning (pickling) • Optimised water chemistry

Steering committee MPP3 26/03/2015 ETG52Steering committee MPP3 23/10/2013 ENT52

Thank you very muchfor your attention