    A PROJECT MANAGEMENT FRAMEWORK

    Dennis Trewin

    Australian Bureau of Statistics

  • 7/28/2019 m2 Framework

    2/15

    OUTLINE OF TALK

    Reasons for needing a Project Management

    Framework

    Illustration of ABS Project Management Framework

    Key Learningssuccesses and lessons learnt

  • 7/28/2019 m2 Framework

    3/15

    KEY MESSAGES

    You should have an agreed Project Management

    Framework to ensure consistent, effective

    management of project

    It doesnt have to be the ABS Framework

    Project Management software project is available

    (eg Microsoft Project)

  • 7/28/2019 m2 Framework

    4/15

    WHY DID THE ABS IMPLEMENT A PROJECT

    MANAGEMENT FRAMEWORK?

    Too many projects running over time and over

    budget

    Project scope creep

    Project management responsibility not clear

    Too much emphasis on outputs rather thanoutcomes

    Insufficient emphasis on risks

    Not a universal approach to project management

  • 7/28/2019 m2 Framework

    5/15

    KEY ELEMENTS OF THE PROJECT MANAGEMENT

    FRAMEWORK

    Project Planning Project Administration

    Management of Risk

    Management of Issues

    Management of Change

    Project Quality Project Governance

    Project Financial Management

    It is not rocket science!

  • 7/28/2019 m2 Framework

    6/15

    PROJECT PLANNING

    Sets out the business case

    Clearly defines project outcomes and links with

    project outputs

    Project initiation

  • 7/28/2019 m2 Framework

    7/15

    MANAGEMENT OF RISK

    Should identify significant risks

    Develop Risk Mitigation Strategies

    Decide whether to adopt Risk Management

    Strategy or take the risk

  • 7/28/2019 m2 Framework

    8/15

  • 7/28/2019 m2 Framework

    9/15

    MANAGEMENT OF CHANGE

    Must be planned for

    Not always welcomeidentify people affected

    by change and ensure that you have a plan to

    address their needs

  • 7/28/2019 m2 Framework

    10/15

    PROJECT QUALITY

    For each output, define how you are going to

    assess the output as fit for purpose

  • 7/28/2019 m2 Framework

    11/15

    PROJECT GOVERNANCE

    Establish milestones/project phases

    Define the roles and responsibility of all

    stakeholders

    Key roles

    - project manager- project owner (usually Chair of Project Board)

    Be prepared to make hard decisions that may

    curtail original project plans

  • 7/28/2019 m2 Framework

    12/15

    PROJECT FINANCIAL MANAGEMENT

    Need an itemised budget (project component x

    expenditure category)

    Track all expenditure on the project

    Analyse significant variations to plannedexpenditure

  • 7/28/2019 m2 Framework

    13/15

    FACILITIES AVAILABLE IN PROJECT MANAGEMENT

    FRAMEWORK

    Software Package (Lotus Notes)

    Templates (eg Issues Management, Risk Management)

    Guides

    Best practice examples

    Support arrangements

    Supported by classroom training and on-line training

    package

  • 7/28/2019 m2 Framework

    14/15

    SUCCESSES

    ABS has noted

    Better control of projects at all levels

    Increased identification and control of project risks

    More effective use of corporate finances

    Quality built into project outputsfit for purpose

    Improved information flows

    Earlier identification and resolution of problems

    Clearer project scope; reduced scope creep

  • 7/28/2019 m2 Framework

    15/15

    LESSONS

    Getting the scale of the project management inproportion to the size and impact of the project

    Better monitoring of milestones (and remedial

    action when milestones are not being met)

    Project Boards not micro-managing

    Killing off projects that wont deliver (or making

    major amendments)