M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012
description
Transcript of M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012
M1 Project (West Gate Freeway Section)Completion of cadastral and land tenure itemsMarch 2012
Presented by Glen Franklin
– Background of the M1 Project
– Stages of the project
– Completion of cadastral and land tenure items
• Scope the remaining items
• Staging and priorities
• Progress
• Expected completion
– Questions
M1 Project (West Gate Freeway Section)
Background video
M1 Project (West Gate Freeway Section)
The $1.39 billion ‘Monash-Citylink-West Gate’ M1 upgrade is the largest statefunded road project in Victoria’s history. Stretching 75km from Werribee to Narre Warren, it delivers a safe and efficient fourlane freeway that is Melbourne’s transport spine.
The project was split into four main pieces, and the 6.2km West Gate Freeway section through the CBD is relatively short in length. Yet it more than makes up for it in complexity, and an alliance of five groups delivered the project.
Background
To call this a brownfield site is a major understatement – the working parameters are tight and the existing roadways carry more than 160,000 vehicles every day.
New bridges, ramps, pillars and pavement contribute to a smoother and smarter traffic flow for the many motorists using this vital link.
Special legislation was created for the project. Schedule 5A was added to the Road Management Act 2004 that included:– Limits of the project– Acquisition of land– Surrender and Divesting of land
Background (cont.)
Redevelopment Project area - LEGL plans
Stages of the project
West Gate Freeway section
Stages of the projectDEVELOPMENT
& PLANNING
Ongoing MANAGEMENT
AS BUILT
PRE-CONSTRUCTION
DESIGN & CONSTRUCTION
Renovate Transportation Corridor
OpeningEverything finished ?????
Items that have been completed:– Aerial Photography– Control Survey Plan– Feature surveys– Laser Scanning of structures– Acquisition Survey Plans– Notice of Acquisition gazettals– Plans of Subdivision and creation of
easements– Governor in Council gazettals– etc
Completion of cadastral and land tenure items
Complete land status and ownership search was completed. Interesting items:– Stratum titles owned by Roads Corporation– Discontinuations vested in Roads Corporation (titles
still exist)– Discontinuations completed under Project
Development and Construction Management Act 1994
– Temporary Railway purposes reserves where a Crown Lease has been issued
– A title for 1m2
– Cancelled titles that should still exist– Multiple interests in land (and stratum)– Etc
Scope the remaining items
Summary of actions was created. For example:– Show existing West Gate Freeway declaration– Show the extent of the existing Crown Leases– Field survey to confirm the new structures were
located within the acquisition and proposed freeway declaration boundaries
– Plans of Subdivision– Plans for Creation of Easement– Defining the surplus land that is no longer required
for future road projects– Amending Crown leases to remove the acquired land– Show extent of temporary reserves to be revoked
Scope the remaining items (cont)
Staging and priorities
Stage Main Issue PrioritySouthern Link to Clarendon Street Surplus land &
Crown lease4
Clarendon Street to Whiteman Street Crown Leases 2Whiteman Street to Normanby Road VicTrack 3Normanby Road to Montague Street Convention
Centre1
Montague Street to Western Link Land Status 7Western Link to Todd Road Land Status 6Todd Road To Williamstown Road Land Status 5
Normanby Road to Montague Street
Progress – Convention Centre
Task StatusAs Built survey Completed
VicRoads Survey Plan CompletedGovernor in Council In progressDeclaration, Revocation & Discontinuation In progressTitle Plan In progressCrown Grant Conditions Final draftIssuing of titles To be commencedPlanning Scheme Amendment To be commencedMemorandum of Understanding Final draft
Normanby Road to Montague Street
– Pictures of the site
– Survey documents/plans produced
Progress – Convention Centre
Clarendon Street to Whiteman Street
Progress – Crown Leases
Task StatusAs Built survey Completed
VicRoads Survey Plan – Amendments Final draftDeclaration, Revocation & discontinuation To be commencedNew OP’s In progressSurrender of Crown Leases To be commencedIssuing of new Crown Leases To be commencedPlanning Scheme Amendment To be commenced
Clarendon Street to Whiteman Street
– Survey documents/plans produced
Progress – Crown Leases
Late 2012, depending upon the resources allocated
Expected completion