M. Circella, Technical and Planning issues, KM3NeT SC meeting, 29 July 2015 1 In this talk Preparation of mass construction (including DOM and DU integration) DU-2 Procurement of components Documents for STAC Review of the project

Transcript of M. Circella, Technical and Planning issues, KM3NeT SC meeting, 29 July 2015 1 In this talk...

M. Circella, Technical and Planning issues, KM3NeT SC meeting, 29 July 2015 1

In this talk

• Preparation of mass construction (including DOM and DU integration)

• DU-2

• Procurement of components

• Documents for STAC

• Review of the project

M. Circella, Technical and Planning issues, KM3NeT SC meeting, 29 July 2015 2

Preparation of mass construction

PMTs: 15,000 available – 7,500 being equipped (base installed, coating, test) in Naples – 7,500 shipped to Erlangen (test scenario to be defined)

DOM/DU integration sites:

4 DOM integration sites (Catania, Naples, Erlangen, Nikhef) preparing to mass production – target speed is 3-5 DOMs/week/site – each site committed to 120 DOMs

Strasbourg expected to join DOM integration later (people available, applying for funds)

3 DU integration sites in preparation: Nikhef, LNS and Naples

3 deployment preparation sites in preparation: CPPM, LNS and Naples

Important points:

Request for funds for 6 LOMs and 4 acoustic release frames ongoing in Italy (in order to sustain installation of batches of DUs)

Transportation (of components, DOMs and DUs) to be organized by all involved institutes until this is centrally supported (Common Fund)

M. Circella, Technical and Planning issues, KM3NeT SC meeting, 29 July 2015

DU-2 (general remarks)

3

Infrastructure in KM3NeT-It ready for connection (new CTF and JB installed)

PPM-DU left disconnected at end of operation (additional motivation to go for deployment of DU-1&2!)

Integration plan defined• DOMs built in Nikhef, Naples, Catania• Base module built in Bari• Integration of DOMs to VEOC started at Nikhef, completed in Naples• Integration of base module to VEOC and all following actions (tests, arrangement on LOM,

etc.) to be done in Naples

Schedule slipping (see later): first 3 DOMs mounted with VEOC, the rest awaiting for VEOC upgrade

Aiming for a deployment in fall (from second half of October until mid-November)

Review to be launched in early September

From now on: alternate-weekly meeting on DU-1 and DU-2 (next one will be on August 5)

DU-integration mailing list set up (I will distribute instructions for subscription soon after this meeting)

M. Circella, Technical and Planning issues, KM3NeT SC meeting, 29 July 2015

Preparation of DU-2

4

Availability of components:• DOMs – full set in production at NIKHEF + 3 to be built in Catania + 3 in Naples (progressing well, see Daan’s

report)• VEOC – available but needs modification to BEOC (see Edward’s report)• buoy - ordered• mechanical parts for buoy – to be produced• ropes and mechanical parts for DU – can be procured quickly• anchor – available, under finalization • base container – in preparation (in aluminum!) – see next slide• equipment for base container – available (except BCI, which has been ordered)

Availability of deployment tools:• LOM and acoustic release – available• acoustic release frame – not available • steel ropes for acoustic release and acoustic release controller – presumably available (to be confirmed)

Availability of integration and test tools:• LOM loader – available • welding machine – available• testing equipment – available• dark room – very simplified layout considered (DU arranged on transportation palette and shielded from light)• dark rom calibration tools – available• shore station/DAQ test station – in preparation• Field test equipment – to be defined (can it be the same as for DU-1?)

M. Circella, Technical and Planning issues, KM3NeT SC meeting, 29 July 2015

Base container of DU-2

5

Penetrator (dummy case) and mockup of endcap of BEOC used for tests of the screws

Internal frame

Front View Rear View

Flange equipped with all needed connectors and

(dummy) penetratorfor pressure test

Connector for jumper

Connector for hydrophone

Dummy penetrator and dummy BEOC endcap

Recent news: • Flange machined and equipped with connectors and (dmmy) penetrator for pressure test• Pressure test of sealed container ongoing (today!) • Cases of penetrators produced, now being equipped with feedthrough in USA

M. Circella, Technical and Planning issues, KM3NeT SC meeting, 29 July 2015

DU-2 (tentative) schedule

6

VEOC upgrade required for proceeding with integration

of DOMs with VEOC

Penetrator (feedthrough) to be

implemented by Pave Technology (to be

tested later by KM3NeT)

M. Circella, Technical and Planning issues, KM3NeT SC meeting, 29 July 2015 7

Procurement of components

Decided/ongoing:

• BCI (BPS-CLB Interface for base modules) – 35 (enough for full Phase-1)

• AHRS – 190 (enough for completing Phase-1)

• Power-boards – 350 (enough for completing Phase-1)

• VEOC – new round of pre-production for 5 cables

• DC/DC converters for the 5 VEOCs (estimated delivery: October) – should we start by building one VEOC ORCA-style with the existing DC/DC of Nikhef?

• SFP receivers for shore stations in KM3NeT-Fr and KM3NeT-It

• Note added during the meeting: SFPs and optical components for base modules of KM3NeT-Fr to be sorted out

Please inform me of ANY new order of components, possibly in advance if it requires more than 10 kEuro (they need to be accounted for in the table cost of the experiment)

M. Circella, Technical and Planning issues, KM3NeT SC meeting, 29 July 2015 8

Documents for STACThis is the list of documents requested from STAC earlier this year:

a) The work breakdown structure (WBS) (priority 1) b) The top level cost estimate (priority 2)c) The project schedule that shows a roll up of the major tasks (priority 1)d) A system block diagram with all the major at-sea and shore-side subsystems (priority 1 if easily available, priority 2 otherwise)e) The quality assurance documents and periodic reports (priority 1)f) The risk management documents

a) The reliability analysis, the risk register and the periodic reports are priority 1b) The FMECA, FTA are priority 2

g) Manufacturing documents and procedures (priority 2)h) Overall system test plan (priority 1) and procedures (priority 2)i) Results of any previous technical reviews and PRRs (priority 1)

This is what we provided or promised (in yellow fonts, together with further requests):

j) document provided k) no document provided – reference done to presentations at previous meetingsl) no document provided - milestones discussed at the meetingm) document with system block diagram promised for Septembern) NCR/DCR list provided, statistics of QAQC forms shown at meeting – their counter-request was to see how the recent

infrastructure problems (fault on node in KM3NeT-Fr, corrosion on JB of KM3NeT-It) are followed up in our QAQC systemo) sample of reliability studies document (CLB) provided – their counter-request was to see an executive summary of all these

studiesp) document on manufacturing and test procedures promised for Septemberq) qualification plan promised for Septemberr) reports on PRR of electronics and review of DU-1 provided, with the promise to send all new documents concerning review of

the project

M. Circella, Technical and Planning issues, KM3NeT SC meeting, 29 July 2015 9

Review of the projectFinalized:

• PMTs internal review – concluded June 2013• DAQ systemexternal review – meeting with reviewers: 7 August 2014 – report delivered• optical system external review – meeting with reviewers: 28 October 2014 – report delivered

Being finalized:

• electronics external review – meeting with reviewers: 9-10 September 2014 – reply to report from reviewers prepared

• DU-1 internal review – meeting with reviewers: 9 April 2015 – all actions being addressed

Started:

• VEOC (by Teledyne/ODI) Started in mid-June

In preparation:

• optical module integration (internal review) Target starting date: September

• DU-2 mechanics and deployment (internal review) Target starting date: September

• power system (external review) Target starting date: (late) summer a)

• calibration (external review) Target starting date: (late) summer a)

• string mechanics & deployment (external review) Target starting date: late summer – fallb)

Remarks:a) Including experience in construction of DU-1b) Including experience from installation of DU-1 and/or DU-2