M. Bonesini - MICE Inst Meeting 10-05-07
1
M. Bonesini INFN Milano
TOF installation plans
![Page 2: M. Bonesini - MICE Inst Meeting 10-05-071 M. Bonesini INFN Milano TOF installation plans.](https://reader036.fdocuments.us/reader036/viewer/2022083009/5697bf831a28abf838c866a2/html5/thumbnails/2.jpg)
M. Bonesini - MICE Inst Meeting 10-05-07
2
Hot issue: detector construction in house
material procurement: up to now no big delays
All PMTs ordered Scintillator ordered Electronics ordered ( status ofstretcher/splitter ?)
Counter assembly: mount & calibrate detectors with cosmics here delay may arise
3 months (April-June) to do this Detector plane assembly: you need to assemble X/Y planes in a rigid structure
1-2 months (July-August) to do this
From CM17
![Page 3: M. Bonesini - MICE Inst Meeting 10-05-071 M. Bonesini INFN Milano TOF installation plans.](https://reader036.fdocuments.us/reader036/viewer/2022083009/5697bf831a28abf838c866a2/html5/thumbnails/3.jpg)
M. Bonesini - MICE Inst Meeting 10-05-07
3
Detector construction
budget constraints (0 $ up to now) have began to show up (I expect by June/July) lightguides ordered/built 70%; but glueing in external firm has just started estimated delay ~ 1 month up to now August 15 RAL TOF0/1 delivery unrealistic (many orders still to be placed, …) seem more realistic a schedule // to KL: September/beg October 2007
![Page 4: M. Bonesini - MICE Inst Meeting 10-05-071 M. Bonesini INFN Milano TOF installation plans.](https://reader036.fdocuments.us/reader036/viewer/2022083009/5697bf831a28abf838c866a2/html5/thumbnails/4.jpg)
M. Bonesini - MICE Inst Meeting 10-05-07
4
Requests for delivery/installation
detailed map of MICE Hall to foresee installation, cables length etc (requested many times, never got) for setup: it will be done together with KL, we plan to have a joint mechanics/electronics team from Italy, but some general help may be useful (access to RAL mech workshop, availability of instruments: scopes, …)
![Page 5: M. Bonesini - MICE Inst Meeting 10-05-071 M. Bonesini INFN Milano TOF installation plans.](https://reader036.fdocuments.us/reader036/viewer/2022083009/5697bf831a28abf838c866a2/html5/thumbnails/5.jpg)
M. Bonesini - MICE Inst Meeting 10-05-07
5
Installation plan
June/July (?) full survey at RAL with mechanics engineer transport to RAL: heavy stuff (cables) shipped, detectors + electronics (50-100 Kg) transport by car date X delivery to RAL (full assembled TOF0/1 detectors or tested counters with PMTs to be arranged at RAL into TOF0/1 detectors) 2 weeks mechanics inst (detector planes+ support) + cabling for TOF0/1 with KL (TOF:Mi+PV 2 physicists, 1-2 mech. technicians, Sofia …) 1-2 weeks … TOF0/1 electronics debug (with beam or cosmics) (TOF: Mi+PV 1-2 physicists, 2 electronic technicians, Sofia …)
NOT FULLY WORKED OUT