Transcript of LWC-04 On Whimpey Creek
LWC-04LWC-04On Whimpey CreekOn Whimpey Creek
Horizontal Plastic Horizontal Plastic Belt POD ScreenBelt POD Screen
Process – Start to FinishProcess – Start to Finish
• Design ideas• Contact Hydrolox and purchase materials• Overcoming problems during fabrication• Input from engineer• Changes during fabrication• Finding a site for installation• Installation• Monitoring and evaluating screen operation
• Need for other types of POD screens
• Idea to build a horizontal plastic belt screen
• Fabrication crew talking about ideas and materials
• Jim Jones contacted Hydrolox and ordered plastic belt materials after discussions with their Engineers
• Harvey Goddard assigned to take lead on project
Monitoring and EvaluationMonitoring and Evaluation
• 2.47 cfs design flow
• Hydrolox Series 1800 mesh top with 37% open area
• 1.10 cfs measured flow
• Water level was to low to accurately evaluate both sweeping velocity and velocity through the screen