LULA GREEN ROAD UNION, SOUTH CAROLINA

6
LULA GREEN ROAD UNION, SOUTH CAROLINA Jerry A. Brannon, Sr. ,PE Union County Engineer

description

LULA GREEN ROAD UNION, SOUTH CAROLINA. Jerry A. Brannon, Sr. ,PE Union County Engineer. Project Description. Project Length – 2.8 Miles Dirt and stone – 2.5 Miles Asphalt - 0.3 Miles Ditches & shoulders - 5.6 Miles Crossline Pipe - 76 Feet 18 “ Rip Rap - As Needed - PowerPoint PPT Presentation

Transcript of LULA GREEN ROAD UNION, SOUTH CAROLINA

Page 1: LULA GREEN ROAD UNION, SOUTH CAROLINA

LULA GREEN ROADUNION, SOUTH CAROLINA

Jerry A. Brannon, Sr. ,PEUnion County Engineer

Page 2: LULA GREEN ROAD UNION, SOUTH CAROLINA
Page 3: LULA GREEN ROAD UNION, SOUTH CAROLINA
Page 4: LULA GREEN ROAD UNION, SOUTH CAROLINA

Project Description

Project Length – 2.8 MilesDirt and stone – 2.5 MilesAsphalt - 0.3 MilesDitches & shoulders - 5.6 MilesCrossline Pipe - 76 Feet 18 “Rip Rap - As NeededMacadam Stone - 2.5 MilesBituminous Surface - 2.5 Miles

Page 5: LULA GREEN ROAD UNION, SOUTH CAROLINA

Project Description

Re-grade 5.6 Miles of shoulders and ditchesRe-grade and reshape 2.3 miles of road bedSpread, shape and compact macadam stoneClean existing pipePlace new cross line pipesInstall erosion control

Page 6: LULA GREEN ROAD UNION, SOUTH CAROLINA

Project Description

Phase II – Install 18’ bituminous surface treatment

Total Project cost estimated at $125,000

Addition funds anticipated from CTC and Union County Forces providing most of labor