LTO Presentation - iaea.org · PDF fileIn October 2009, ... No technical obstacle in the area...
Transcript of LTO Presentation - iaea.org · PDF fileIn October 2009, ... No technical obstacle in the area...
LTO Presentation 24 October 2017 – Economic assessment of LTO, Lyon, France
G. Pironet
Introduction
Personal introduction
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 3
Guy Pironet, ENGIE Electrabel
Program Manager LTO Tihange 1 from March 2013 until March 2017
Deputy Site Manager Tihange NPP since April 2017
Agenda
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 4
1. Introduction
2. Regulatory Context
3. The LTO analysis project
4. Financial Feasibility and Business Case
5. Conclusion
6. Questions - Answers
Tihange 1 NPP
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 5
Owned by: Electrabel (50%), EDF (50%),
Commissioning date: 10/1975
Reactor type: 3 loops PWR
Power: 860 MWe uprated
to 962 Mwe
NSSS supplier:
— FRAMATOME/Westinghouse
— Fuel: 15x15 - 12 ft core - 157 FA
– 18 months cycle
Regulatory context
Belgian Regulatory context
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 7
Nuclear phase out law 2003: article 4 §1
Les centrales nucléaires destinées à la production industrielle d'électricité à
partir de la fission de combustibles nucléaires, sont désactivées quarante ans
après la date de leur mise en service industrielle et ne peuvent plus produire
d'électricité dès cet instant.
In Belgium, the nuclear phase out law limits the life time of nuclear
power plants to 40 years.
In October 2009, the Belgian Government announced its intention to make the
industrial operation of the nuclear powerplants of Tihange 1 and Doel 1-2 legally
possible up to 2025 (this means a life time extension to 50 years).
This period of 10 years of life time extension is considered as LTO-
period.
Introduction: Understanding the Belgian Context
FANC Framework – Belgian Authorities
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 8
Position issued by the FANC in October 2009
LTO to be evaluated in Safety Evaluation
Framework;
In line with industry practice;
Besides an evaluation of the preconditions +
CK&B for LTO, 2 Areas: Ageing (active and
passive SSC) and Design;
Ageing to be evaluated in accordance with
10CFR54 and IAEA SRS57.
Introduction: LTO - Some essentials
FANC Framework
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 9
Position issued by the FANC in October 2009
Introduction: LTO - Some essentials
End 2011:
File LTO Report V1
June 2012:
File LTO Report V2
ADU :Agreed Design Upgrade
2015 < 2020
Update Safety Evaluation Report
LTO File Define ADU*
Update Safety
Evaluation Report
Implement AMP
Implement Design
Upgrade Modifications
The LTO analysis project
Pre-Conditions – Competence Knowledge and Behaviour Results
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 11
The Tihange 1 NPP LTO Implementation Program: Tihange 1 NPP LTO Analysis results - Overview
Pre-Conditions
Competence,
Knowledge and
Behaviour
Analysis of existing Evaluations
Nuclear Safety Culture, including behaviour and attitudes
Competence development and management process
Knowledge Management, in particular knowledge, use and
integration of design basis during engineering of plant modifications
Plant programmes Management
system
Safety
analysis
TLAA
Licensing
basis
documents
Maintenance
Equipment
qualification
Surveillance
and monitoring
Chemistry
programs
In service
inspection
Modification
Management
Configuration
Management
Belgian methodology for AMPs in Ageing Management
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 12
IAEA NS-G-2.12 methodology
Belgian Approach for the use of AMPs in Ageing Management
The LTO analysis project: Methodology
LTO Ageing Analysis – Scoping Mechanical Systems
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 13
Systems in scope are:
Passive: Pressure boundary
Active: Pressure boundary + “Movement = YES”
The LTO analysis project: Methodology
CAE CAR/CAS CAU CCV CEB CEI CEN CEX CGN/CGH/CGC CHE
CIS CPE CRI CRP CSC CTP CVA CVD CVP EAN
EAS EDN EEE GBR GDS PGV RBR RPP RRA SUR
TEG TEL VBL VBU/VBW VBP VCT VEA VEE VGA VLE
Ageing - Mechanical Systems
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 14
Global Conclusion
No technical obstacle in the area of Mechanical Systems exists for Life Time
extension to 50 Years.
Specific points
— Specific corrective and preventive actions need to be taken:
• AME Passive: implement planned project CEI, CSC and CRP
• AME Active: implement RCM-results, combined with systematic trending
— Major uncertainties remained (financial contingency):
• TLAA: CCV Q01Pv Regenerative Heat Exchanger
• AME Passive: Replacement of CC/RW Heat Exchangers
Remark:
— Important in scope SSCs have been replaced during plant operation: steam
generators, reactor vessel head, replacement of RHR piping, …
The Tihange 1 NPP LTO Implementation Program: Tihange 1 NPP LTO Analysis results - Overview
Ageing Analysis – Scoping Mechanical Structures and Civil Works
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 15
1. Mechanical structures
— Primary containment structures & Joints
— Other non-category 1 structures within the scope of LTO
— Leaktight doors
— Pipe whip restraints and jet impingement shields
— E I&C panels, racks frames, cabinets and other enclosures
— Cable trays and supports
— ASME class 1 hangers, supports and snubbers
— Non-ASME class 1 hangers, supports and snubbers
2. Load Handling Systems
— Load Handling Systems and Nuclear Fuel Storage
3. Fire protection
— Fire Restistant Barriers
The LTO analysis project: Methodology
Ageing - Mechanical Structures and Civil Works
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 16
Global Conclusion
No technical obstacle in the area of Mechanical Structures and Civil works
exists for Life Time extension to 50 Years.
Specific points Mechanical Structures
The main specific issue is a systematic follow-up of non-ASME equipment:
— Baseline inspection and corrective actions, with specific attention to fire barriers
— Implementation of an ageing monitoring program of non-ASME equipment
The Tihange 1 NPP LTO Implementation Program: Tihange 1 NPP LTO Analysis results - Overview
Ageing Analysis – Scoping Mechanical Structures and Civil Works
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 17
4. Civil Works
— R – Reactor Building (internal structures, liner and double containment)
— N – Nuclear Auxilary Building
— E – Electrical Auxilary Building
— K – Water/Steam Building
— D – Emergency Diesels Building (1st level)
— P – Pump Station
— M – Turbine Hall
— J – Cooling Tower
— Circulating Water System
— Cable Galleries and Tunnels
— Raw Water and Liquid Radiological Waste
— Water Intake structure
— Ventilation Stack
— Emergency Cooling Water Wells
The LTO analysis project: Methodology
Ageing - Mechanical Structures and Civil Works
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 18
Global Conclusion
No technical obstacle in the area of Mechanical Structures and Civil works
exists for Life Time extension to 50 Years.
Specific points Civil Works
— Specific corrective and preventive actions need to be taken:
• Cooling tower: packing, internal structures and additional balances
• Additional measurements for “concrete” trending
— Major uncertainties remained (financial contingency):
• Seal between reactor building liner and base mat. Inspection during outage.
• Some uncertainties still remain and have to be lifted with additional inspections.
The Tihange 1 NPP LTO Implementation Program: Tihange 1 NPP LTO Analysis results - Overview
Ageing Analysis – Scoping E I&C (ref. NEI 95/10)
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 19
The LTO analysis project: Methodology
CG 73 Alarm Unit CG 91 Light Bulbs
CG 74 Analyzers CG 92 Loop Controllers
CG 75 Annunciators CG 93 Meters
CG 76 Batteries CG 94 Power Supplies
CG77 Cables and Connections CG 95 Radiation Monitors
CG 78 Chargers, Converters, Inverters CG 96 Recorders
CG 79 Circuit breakers CG 97 Regulators
CG 80 Communication Equipment CG 98 Relays
CG 81 Electrical heaters CG 99 Signal Conditioners
CG 82 Heat tracing CG 100 Solenoid Operators
CG 83 Electrical Controls and Panel Internal
Component Assemblies
CG 101 Solid-State Devices
CG 84 Elements, RTDs, Sensors,
Thermocouples, Transducers
CG 102 Switches
CG 85 Fuses and fuseholders CG 103 Switchgear, load centers, Motor control
centers
CG 86 Generator, Motors CG 104 Transformers
CG 87 High-voltage insulators CG 105 Transmitters
CG 88 Surge Arresters CG 128 Pressure reducer
CG 89 Indicators CG 129 Instrumentation tubing
CG 90 Isolators CG 131 Packages
Ageing Analysis – Scoping E I&C
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 20
The LTO analysis project: Methodology
Cable, supported by cable
trays = link to Structures &
CW
Cable to actuator = link with
Mechanical (via valve, damper, pump, …)
Electrical penetration =
link with Structures & CW
Power supply, RPS, … =
link to Structures & CW
Identified FL
Identified FL
Specific CG Specific and
Multiple CG
Specific and
Multiple CG
Specific CG
Specific and
Multiple CG
Specific and
Multiple CG
Specific CG Specific CG
Ageing - E I&C
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 21
Global Conclusion
No technical obstacle in the area of E I&C exists for Life Time extension to 50
Years.
Technical challenges:
— Obsolescence
— Ageing Management (preserving equipment qualification)
— Equipment Qualification requirement
Remark:
— Important SSCs have been replaced during plant operation: RPS, NIS, PIS, main
electrical boards
The Tihange 1 NPP LTO Implementation Program: Tihange 1 NPP LTO Analysis results - Overview
Ageing - E I&C
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 22
Global Conclusion
No technical obstacle in the area of E I&C exists for Life Time extension to 50
Years.
Specific points
In order to ensure safe Life Time Extension to 50 years, major investments were
needed. The most important were:
— Replacement or refurbishment of 1E Electrical motors , including valve actuators
— Replacement Fire Detection System
— Refurbishment of the I&C components of pneumatic and hydraulic actuators
— Replacement of electrical AC/DC power supply (380V-220V-115V)
— Conformity of incore thermocouples
— Refurbishment of electrical and instrumentation reactor building penetrations
(replacement of some feedthroughs)
The Tihange 1 NPP LTO Implementation Program: Tihange 1 NPP LTO Analysis results - Overview
Design Methodology
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 23
The LTO analysis project: Methodology
1,E-06
1,E-05
1,E-04
1,E-03
1,E-02
1970 1980 1990 2000 2010 2020 2030
Co
re D
amag
e F
req
uen
cy o
r C
DF
(
1 /
rea
cto
ryea
r )
Year
Long Term Operation - Agreed Design Upgrade
Core Damage Frequency (CDF) as a function of time
IAEA target for existing plants
IAEA target for future plants
Past
Future
Trend
First Periodic
Safety Review
Design
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 24
The identified concerns lead to proposed technical improvements.
The proposed improvements can be organized in 9 different areas, attending each a
specific safety concern.
The LTO analysis project: Tihange 1 NPP Results
Backup Safety Earthquake Fire
Flooding Operator Training Physical Separation
Qualification Severe Accident System
Backup Safety Earthquake Fire
Flooding Operator Training Physical Separation
Qualification Severe Accident System
1 3
2
4
Facts and Figures
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 25
LTO Analysis Project: 3 year project – peak: up to 130 people
For each plant, Tihange 1 NPP and Doel1/2 NPP, establishment of:
Ageing
— Object of Ageing Management Evaluations
• About 40 fluid systems
• 26 structure types
• 36 EI&C component types
Pre-Conditions & Competence Management
— 12 Self-Assessments
Design
— About 30 Agreed Design Upgrades
Total of 750 documents or about 12500 pages… for each plant…
Analysis fully in line with IAEA expectations
The LTO analysis project: Tihange 1 NPP Results
Financial Feasibility and
Business Case
Feasibility and Business Case
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 27
Analysis of the impact of the LTO Analysis
What are the related risks (nuclear safety, industrial safety, complexity, parts and
qualified staff availability, …)?
What is the financial impact of each commitment, what is the impact on HR?
What is the impact on plant availability and fleet availability?
Potential revenues and/or taxes
Solution
Major risks Matrix
Establishment of Budget & Commitment files;
Establishment of global planning (plant implementation and fleet optimization)
ALSO, integration of Non-Safety Related projects for PLEX
The LTO analysis project: Tihange 1 NPP Results
Feasibility and Business Case
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 28
The LTO analysis project: Tihange 1 NPP Results
Risk Analysis
CAPEX overrun
Longer outage
Additional Long Stop
Sourcing Delay
Market risk
Financial Analysis
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 29
Ageing Budget & Commitment files – 1 file per deliverable
Feasibility and Business Case
All files grouped for individual validation and global impact analysis
Deliverable
Overview
Origin
Exective summary
analysis
Risk analysis
CAPEX & manpower
OPEX & manpower
Feasibility and Business Case
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 30
PLEX analysis
— Analysis of Tihange 1 NPP project portfolio
• Replacement of N1E electrical motors
• Replacement of step-up transformers
• Replacement of main generator protection system
• Replacement of main turbines regulation system
— Analysis of existing “Ageing Summaries”
— Use of operating experience and tacit knowledge
Remark:
— Important out scope SSCs have also been replaced during plant operation: LPB main
turbines, heat exchangers, condensors, …
The LTO analysis project: Tihange 1 NPP Results
Significant milestones
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 31
The Tihange 1 NPP LTO Implementation Program: Tihange 1 NPP LTO Analysis
results - Overview
End 2011 File LTO Report V1
Mid 2012 File LTO Report V2
ADU :Agreed Design Upgrade
10/2015 • Préconditions
• CK&B
< 2020 Design
Implement Design
Upgrade Modifications LTO File Define ADU*
Update Safety
Evaluation Report
Implement AMP
Outage 2014
S1
Outage 2016
S2
Outage 2017
Design Part 1
Outage 2019
Design Part 2
Margin
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 32
Margin is determined as the difference between:
Conclusions
To keep in mind
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 34
1 Program grouping more than 100 projects
1 Team, an integrated organization EBL and TE.
3 Areas:
— Ageing Management
— Design Upgrade
— Processes
Planning:
— 30 September 2015: Processes up to date (Pre-Conditions and Competence/Knowledge
Management)
— Outage 2016: Ageing Management
— 2020: Design Upgrade
Investment: 600 M€ - Current best estimate on-track (progress ± 70%)
The Tihange 1 NPP LTO Implementation Program: Current Status
Questions and Anwers
24 October 2017 – Economic assessment of LTO, IAEA PLIM Conference, Lyon, France 36
Questions - Answers